Upcoming projects

 mars 2018

Bane NOR | Upcoming projects
Upcoming projects mars 2018 - Bane NOR
2    Bane NOR | Railway Tender Conference 2018 | The InterCity project                                                                      3

                                                                             Table of content   The InterCity project                      4
                                                                                                The Ringerike Line and E16 highway         6
                                                                                                Construction projects Vestfold Line
                                                                                                Drammen-Kobbervikdalen                      8
                                                                                                Nykirke-Barkåker                           10
                                                                                                Construction projects East
                                                                                                The Østfold Line
                                                                                                Sandbukta-Moss-Såstad                      12
                                                                                                Haug-Seut                                  14
                                                                                                The Dovre Line
                                                                                                Venjar-Eidsvoll-Langset                    16
                                                                                                Kleverud-Sørli-Åkersvika                   18
                                                                         2                      Construction projects West/Mid
                                                                                                The Bergen Line
                                                                                                Arna-Bergen                                20
                                                                                                Arna-Stanghelle                            22
                                                                                                The Oslo tunnel
                                                                                                Oslo S-Lysaker, Nationaltheatret-Bislett   24

Photo by Hilde Lillejord, Bane NOR
Upcoming projects mars 2018 - Bane NOR
4     Bane NOR | Upcoming projects | The InterCity Project                                                                                                                                                                                                                                                                                 5

                                                    Lillehammer

                                                                                                          The InterCity
                                                                                                          Project
                                                   Moelv
                                                                         Brumunddal

Planning status                                                             Hamar

InterCity                                                                        Stange

                                                                                      Tangen
    Municipal master plan

    Zoning plan

    Under construction
                                                                                                          Bane NOR is planning 270 km of new double-track between
    Completed                                                                                             Oslo-Lillehammer (Dovre line), Oslo-Halden (Østfold line),
                                                                                      Eidsvoll

                                                                                                          Oslo- Porsgrunn (Vestfold line) and Sandvika-Hønefoss
                                                                                                          (Ringerike line).
                                                                                Oslo Lufthavn
                             Hønefoss
                                                                                                                                                                                                    Photo by Hilde Lillejord, Bane NOR
                             Sundvollen

                                                                                Lillestrøm                The InterCity Project is a rail project      Norway is expecting a strong growth          Planning and constructing the remaining     Stabling                                      Upcoming contracts
                                                                                                          in South-Eastern Norway. The project         in population the coming years. With         infrastructure will take place in four      Bane NOR is also planning stabling (train     Stabling Drammen area. Stabling tracks
                                        Sandvika                    Oslo S
                                                       Lysaker
                                        Asker

                            Drammen
                                                                                                          involves building 270 km of new double-      shorter journeys and increased frequency     stages. These stages are described in the   parking) in these areas: Moss, Fredrikstad/   for 36 single train sets, each 110 meters,
                                                                     Ski
                                                                                                          tracks and 25 stations. The new tracks       InterCity will make it easier to live in     Norwegian National Transport Plan for       Sarpsborg, Drammen, Tønsberg and              and necessary service facilities.
                              Sande                                                                       will be dimensioned for speeds up to         one city and work in another. When the       the period 2018-2029 (NTP):                 Hamar. Building new stabling tracks
                             Holmestrand                                                                  250 km/h. The total investment cost is       marked for housing and labour expands,       • Hamar (Åkersvika), Fredrikstad (Seut)     is essential to reach the goals of the        Stabling Tønsberg area. Stabling tracks for
                                                                                                          estimated at NOK 150 billion.                the pressure on the capital Oslo will be        and Tønsberg in 2024                     InterCity project with more frequent train    14 single train sets, each 110 meters, and
                                                              Moss
                                        Horten                   Rygge
                                                                         Råde

                                   Tønsberg
                                                                                   Sarpsborg                                                           reduced. InterCity also includes better      • Sarpsborg in 2026                         departures.                                   necessary service facilities.
         Skien                    Stokke
                                 Torp
                                                           Fredrikstad                                    The InterCity area consists of lines under   capacity for improving freight services.     • Porsgrunn in 2032
       Porsgrunn         Sandefjord                                                              Halden
                                                                                                          planning, lines under construction                                                        • Halden and Lillehammer in 2034            There will be changes from the NTP            Bane NOR will announce an adviser
                                   Larvik
                                                                                                          and lines that are completed. The total      If as many as possible are to benefit from                                               when the Norwegian Railway Directorate        contract for public planning and
                                                                                                          InterCity net will be completed with         this big investment, most stations must                                                  presents the specific action programme        technical planning for each project.
                                                                                                          double-tracks by the end of 2034.            be located centrally in the cities.                                                      for the railway sector in April. The action   Pre-qualification in the second or third
                                                                                                                                                                                                                                                programme will define the order in which      quarter of 2018.
                                                                                                                                                                                                                                                the projects are to be realized.
Upcoming projects mars 2018 - Bane NOR
6     Bane NOR | Upcoming projects | The Ringerike Line and E16 highway                                                                                                                                                                                                       7

                                                                                                                                                                                                                                     Major contracts

                                                  Ringerike Line and
                                                                                                                                                                                                                                     8 major contracts plus several contracts
    Ringerike Line and E16 highway                                                                                                                                                                                                   for preperatory and enabling works cov-
                                                                                                                                                                                                                                     ering all fields from designing and build-
                                                                                                                                                                                                                                     ing roads, tunnels and bridges to signal,

                                                  E16 highway
    Hønefoss
                                                                                                                                                                                                                                     system design for railway technique,
    Sundvollen                                                                                                                                                                                                                       telecom, contact line, high voltage, low
                                                                                                                                                                                                                                     voltage and railway tracks.
                                    Oslo S        Bane NOR and the Norwegian Public Roads Administration
               Sandvika
                          Lysaker
                                                  are working together to establish double-track railway and
                                                  four-lane highway between Sandvika and Hønefoss.                                                                                                                                   Planned schedule
                                                                                                                                            Railway and highway                       Tunnels and bridges                            • 2020 start Preparatory works
                                                                                                                                            • 40 km new double-track from Sandvika    • 23 km double-track railway tunnel with       • 2019/ 2020 Prequalification
                                                  The joint project’s main goal is to develop   the two cities make it one of the busiest     to Hønefoss designed for 250 km/h         parallel escape and service tunnel from        Main Contracts
                                                  and increase the commuter area around         connections in all of Europe.               • 15 km four-lane highway, designed for     Sandvika to Sundvollen                       • 2020/ 2021 Contract award first
                                                  the capital of Oslo, including Hønefoss                                                     110 km/h                                • 3 km double-track railway tunnel at Vik        Main Contracts
                                                  and Ringerike in the Norwegian InterCity      The works include big structures: several   • A new railway station at Sundvollen     • 770 m double-track railway bridge            • 2021/ 2022 Construction start first
Contact:                                          railway network.                              bridges and tunnels, including on of the    • Complete rebuild of existing railway      across Kroksund                                Main Contracts
Supplier relations Bjørn Einar Bjordal
                                                                                                longest railway tunnel in Northern            station at Hønefoss                     • 640 m four-lane highway bridge across
+47 913 59 331, bjobjo@banenor.no
                                                  When completed, the project will              Europe. The handling of soil and rock       • Three - or possibly four - highway        Kroksund
Communications manager Lisbet Botnen              increase road security and significantly      masses add up to 10 million m³, and the        intersections:                         • 2 x 3 km highway tunnels at Vik
+47 900 34 970, botnli@banenor.no                 improve the conditions and regularity for     project is planned partly in areas with       • Elstangen                             • Crossing the river and wetlands at
                                                  road travel. Another very important effect    challenging geotechnical conditions.          • Styggedalen                             Mælingen:
                                                  is the substantial reduction of travel time                                                 • Ve                                      Alt 1: Five bridges: 2 x 300 m + 3 x 900 m
More information:                                 by train between the two biggest cities of    The works on the main contract are            • Helgelandsmoen (possibly)               Alt 2: Three bridges: 3 x 1,800 m
www.banenor.no/ringeriksbanenE16                  Norway, Bergen and Oslo, getting it close     scheduled for start in 2021/2022.
                                                  to five hours. Today the air travel between   Estimated project finish 2028/2029.
Upcoming projects mars 2018 - Bane NOR
8       Bane NOR | Upcoming projects | The Vestfold Line                                                                                                                                                                                                                                  9

                                                                                                                                                                                                                                                 The scope of work includes the tracks

                                                              Drammen-
                                                                                                                                                                                                                                                 between Drammen and Gulskogen stati-
        Vestfold Line                                Oslo S
                                                                                                                                                                                                                                                 ons, rebuilding of both stations and general
                                Sandvika
                                           Lysaker                                                                                                                                                                                               technical railway works for the whole
                                Asker
                                                                                                                                                                                                                                                 project. Extensive groundwork and substru-
                     Drammen

                        Sande
                                                              Kobbervikdalen                                                                                                                                                                     cture works, and multidisciplinary technical
                                                                                                                                                                                                                                                 railways works will be carried out in several
                                                                                                                                                                                                                                                 demanding phases.
                      Holmestrand                             Bane NOR is planning the construction of 10 km of
                                                                                                                                                                                                                                                 Notification is planned for May 2019, and
                                Horten                        double-track from Drammen to Kobbervikdalen and                                                                                                                                    the contract is expected to be signed in
                             Tønsberg
                                                              from Drammen and Gulskogen, as part of the ongoing                                                                                                                                 May 2020
        Skien                Stokke                           modernization of the Vestfold Line.                                                      The railway station in Drammen city will be rebuilt with new plattforms and tracks.
     Porsgrunn
                            Torp
                    Sandefjord
                                                                                                                                                                                                                                                   Other contracts
                                                              The project is complex, with extensive        Drammen station and Gulskogen station      constructed using a standard drill and           In addition to the soil and concrete       The project includes several smaller
                             Larvik
                                                              groundwork and substructure works,            will both be rebuilt, with new platforms   blast method.                                    tunnels, the scope of work includes        contracts. These contracts include impor-
Vestfold line                                                 multidisciplinary technical railways works,   and tracks.                                                                                 a branch line towards Nybyen, open         tant preparatory works, such as:
                                                              and a number of demanding constructi-                                                    Notification is planned for September            construction pits, and the rock tunnel     UDK 28 – Preparatory technical railway
                                                              on phases. Large parts of the works are       The construction works are split into      2018, and the contract is expected to be         entrance.                                  works. The contract is expected to be sig-
                                                              to be done in densely populated areas,        three main contracts:                      signed in August 2019.                                                                      ned in March 2019.
                                                              especially the contracts UDK 02 and UDK                                                                                                   Notification is planned for June 2018, and UDK 33 – Preparatory groundwork and sub-
    Contact:                                                  03.                                           UDK 01 - Rock tunnel and open              UDK 02 – Concrete tunnel and soil tun-           the contract is expected to be signed in structure works. The contract is expected to
    Project Manager Hanne A. Stormo                                                                         stretches in Skoger. EPC contrakt.         nel. EPC contract.                               June 2019.                                 be signed in March 2019.
    +47 913 25 084, stohan@banenor.no                         The project includes 10 km of double-         Procurement procedure: Negotiated.         Procurement procedure: competitive
                                                              track from Drammen to Kobbervikdalen          The scope of work includes the 6 km        dialogue. To be able to learn more about         UDK 03 – Drammen-Gulskogen and           All calls for tender will be announced
    Head of Contract Eirik Harding Hansen                     and from Drammen to Gulskogen, a 6 km         rock tunnel, the tunnel approach and                                                                                                 through Bane NORs procurement system,
                                                                                                                                                       soil tunnels, this procedure is considered       general technical railway works
    +47 932 49 943, hansei@banenor.no                         rock tunnel, an 850 m concrete tunnel         the open stretches connecting to the       necessary to facilitate the early involve-       Implementation contract.                 using TED and/or the TransQ pre-qualifica-
                                                              (cut and cover), a 270 m soil tunnel, and a   existing Kobbervikdalen track. Bane NOR    ment of and interaction with the                 Procurement procedure: Negotiated.       tion system.
    More information:
    www.banenor.no/drammen-kobbervikdalen                     branch line towards Nybyen.                   has decided that the tunnel should be      contractor.
Upcoming projects mars 2018 - Bane NOR
10       Bane NOR | Upcoming projects | The Vestfold Line                                                                                                                                                                                                                                       11

         Vestfold Line
                                 Sandvika

                                 Asker
                                            Lysaker
                                                      Oslo S
                                                               Nykirke-
                      Drammen

                         Sande
                                                               Barkåker
                       Holmestrand                             Bane NOR is planning to build 14 km double-track from
                                 Horten                        Nykirke to Barkåker, and a new station at Skoppum outside
                                 Skoppum

                              Tønsberg
                                                               Horten, as a part of the ongoing upgrade of the Vestfold
         Skien                Stokke
                             Torp
                                                               Line.
     Porsgrunn       Sandefjord                                                                                                                         The new railway station in Skoppum outside the city of Horten. Illustration: Vianova/Aas-Jacobsen
                                                               The new line consist of two bridges, four    Bane NOR is planning to divide the work
                              Larvik
                                                               tunnels totaling 5,3 kilometres, and a new   into two large EPC (engineering, procure-
Vestfold line                                                  modern station west of Skoppum.              ment, construction) contracts for this
                                                                                                            project, one civil works contract and one   Facts and numbers                                New station at Skoppum                             Planned schedule
                                                               The new station is planned with an ample     railway system contract.                    • 14 km double-track designed for                • Partly located on a bridge crossing              • Autumn 2018, pre-qualification for civil
                                                               parking lot for both cars and bikes.                                                       250 km/h                                         rv. 19                                             work contracts, and one railway system
                                                                                                            The contracts for the preparatory works     • Gråmunkentunnelen 1,2 km (rock)                • Connection to existing road network                contract
    Contact:                                                   There will be a good connection to the       is planned to be signed before summer       • Kopstadunnelen 900m (concrete)                   for all road user groups                         • Spring 2019, tender conference
    Project Manager Anders Dahl Johansen                       existing road network for all road user      2018, with start up this autumn.            • Skottåstunnelen 2,3 km (rock) and              • 3 tracks to platform                             • Late 2019, main construction work
    +47 922 94 698, johand@banenor.no                          groups. Changeover to alternative trans-                                                   700m (concrete)                                • Service track for machines and equip-            • End of 2024, new infrastructure in
                                                               portation modes has been facilitated for                                                 • Solerød bridge over Fv. 665                      ment                                               operation
    Head of Contract Per Gunnar Johansen                       with both bus and taxi stops close to the                                                • A bridge crossing Rv. 19                       • Passing track for local trains and trains
    +47 934 83 145, johper@banenor.no                                                                                                                   • New station at Skoppum                           in deviation
                                                               main entrance.
                                                                                                                                                                                                         • Parking for cars and bikes
    More information:
                                                                                                                                                                                                         • Bus stop, taxi stop and kiss & ride
    www.banenor.no/nykirke-barkaker
Upcoming projects mars 2018 - Bane NOR
12   Bane NOR |Upcoming projects | The Østfold Line                                                                                                                                                                                                                 13

                    Oslo S     Østfold Line
                                                    Sandbukta-
                    Ski

                                                    Moss-Såstad
                                                    The Sandbukta-Moss-Såstad (SMS) project is part of the
             Moss
                Rygge
                                                    Intercity development. This section includes a 10 km, new
                        Råde

                               Sarpsborg
                                                    double-track railway and is situated on the Østfold Line.
          Fredrikstad
                                                                                                                                     The new railway station in Moss city.
                                           Halden   The 10 km SMS-section covers three     The Carlberg tunnel is a 2,350 m long     Facts and numbers                           • Easy access for pedestrian and bikes    •SMS 7 Local noise measures, Contract
                                                    open stretches and two tunnels,        tunnel from Kleberget to Carlberg,        • 10,3 km double-track                                                                award 2018
                                                    including 630 m substructure for       including a 200m long concrete            • The Moss tunnel: 2,3 km (rock) and        Main contracts for SMS:                   •SMS 8 Settlement measurement, Con-
                                                    double-track railways on the open      culvert.                                    420 m (concrete)                          •SMS 2A EPC substructure, Contract        tract signed
                                                    line at Sandbukta.                                                               • The Carlberg tunnel: 2,15 km (rock) and   award 2019 (ongoing tendering)            •SMS 9 Building survey, Contract award
                                                                                           A 3,850 m substructure for double-           200 m (concrete)                         •SMS 2B Railway system, tracks and ca-    2018
                                                    The Moss tunnel is a 2,720 m long      track railway on the open line. It will   • A new station in Moss                     tenary, Contract award 2021
Contact:                                            tunnel from Sandbukta to Moss          connect to the existing double track                                                  •SMS 2C Railway system high power and     Planned schedule
Project Manager Jarle Midjås Rasmussen              center, including a 420 m long con-    at Såstad in Rygge.                       Moss Station - a new meeting place          telecom, Contract award 2021              • 2017 Preparatory construction
+47 916 73 402, raja@banenor.no                     crete culvert.                                                                   • 4 tracks to platform south of the Moss    •SMS 3 Framework agreement Thales,          ongoing
                                                                                                                                       tunnel                                    Class B signaling system, Call-off 2022   • Fall 2019 Construction start
Head of Contract Kjell Gunnar Braaten                                                                                                • A connecting track towards Moss           •SMS 5 Preparatory works, Contract        • End of 2024 New infrastructure in
                                                    The new Moss station includes an 800
+47 946 55 044 , kgb@banenor.no
                                                    m long station area.                                                               harbor                                    signed                                      operation
More information:                                                                                                                    • An indoor waiting area and bike hotel     •SMS 6 EPC Demolition of buildings,       • 2025 Estimated project finish
www.banenor.no/moss                                                                                                                  • Easy access to public transportation      Contract award 2018 (ongoing tendering)
Upcoming projects mars 2018 - Bane NOR
14   Bane NOR | Upcoming projects | The Østfold Line                                                                                                                                                                                   15

                     Oslo S     Østfold Line
                                                     Haug-
                     Ski

                                                     Seut
                                                     The Haug-Seut (HS) project is part of the InterCity develop-
              Moss
                 Rygge
                                                     ment. The section is about 16,8 km long and situated be-
                         Råde

                                Sarpsborg
                                                     tween the cities of Moss and Fredrikstad on the Østfold Line,
           Fredrikstad
                                                     the main route to Europe.
                                            Halden   Today’s single-track is a bottleneck and   • A new public railway station located         Progression and main contracts:                Planned schedule
                                                     the upgrade of this section will double       in Råde. The station will be universally    Progression and main contracts: Bane           • 2020 – Preparatory works at
                                                     the scheduled departures from                 designed with elevators and ramps           NOR is currently working on the local            Fredrikstad station
                                                     Fredrikstad and also improve the freight      for easy access, platform lengths of 350    development plan for the section that          • 2021 – Preparatory works on existing
                                                     capacity.                                     m, parking capacity for 400 cars, bicycle   will later be treated by the municipalities,     single-track railway and nearby
                                                                                                   parking and more                            followed by the parliament approval.             conflicting areas
                                                     Facts about the project:                   • 5 tunnels with a combined length of                                                         • 2021 – Invitations to tender on the
Contact:                                             • 16,8 km new double-track railway            approximately 1,250m                        Ahead of the opening of the new dou-             EPC-contracts followed by the award
Project Manager Adler Enoksen                          designed for speeds up to 250 km/h       • Most of the section is situated in a rural   ble-track, some preparatory works are          • 2022 – Main works initiated
+47 949 71 793 enoadl@banenor.no                     • 4 bridges with various lengths from         and unspoiled area                          planned at Fredrikstad station and the         • 2024 – Tendering and awards various
                                                       230m to 600m and a                       • The route passes through terrain alter       nearby areas of the existing single-track        railway and signalling works
Head of Contract Marit Johanne Svingen                                                                                                         railway.
                                                       combined length of approximately            nating between good patches of be
+47 411 23 195 , svimar@banenor.no
                                                       1,900m                                      drock and sections that contains soft
More information:                                                                                  soil and demanding ground conditions
www.banenor.no/haug-seut
Upcoming projects mars 2018 - Bane NOR
16   Bane NOR | Upcoming projects | The Dovre Line                                                                                                                                                                                                                      17

               Lillehammer
                             Dovre Line
                                                     Venjar-
                                                     Eidsvoll-Langset
              Moelv
                             Brumunddal

                                Hamar

                                    Stange

                                          Tangen

                                                     Upcoming project on the Gardermoen and Dovre Line in
                                                     Eidsvoll municipality, north of Oslo, and part of the InterCity
                                          Eidsvoll
                                                     double-track development.
                                  Oslo Lufthavn

                                                     The project consists of extension from                                                   Minnevika Bridge, 860 meters long and will be the longest railway bridge in Norway, until Tangenvika Bridge is finished
                                                     one to two railway tracks over a 9 km        Adjustments of track system at
                 Oslo S
                                  Lillestrøm
                                                     stretch from Venjar to Eidsvoll north, and   Eidsvoll station, and modification of the
                                                     extension of the existing railway track      existing signal system on the stretch       Planned schedule:                                 Eidsvoll-Langset:
Contact:                                             (filling in to Vorma) including a new 4 km   Venjar to Eidsvoll (Siemens).               2016: Local development plan submittet            2018: Prequalification process started
Project Manager Rønnaug Resset                       double-track railway from Eidsvoll north     New power supply infrastructure and         2017: Preparatory work started                         Construction contract
+47 450 02 287, resron@banenor.no                    to Langset.                                  new signal system (Thales) from Eidsvoll    2017: First budget approval in Parliament         2019: Contract award and
                                                                                                  to Langset.                                                                                        commencement of work
Head of Contract Marita Ræstad             The project also consists of four smaller                                                          Venjar-Eidsvoll:                                  2023: New infrastructure in operation
+47 482 67 474, rasmar@banenor.no          railway bridges, and the second longest                Construction contract consist of            2017: Prequalification process started,           2024: Estimated project finish
                                           railway bridge in Norway (Minnevika                    substructure, track structure, overhead           Construction contract
Communications Manager Hilde Marie Braaten
                                           bridge, 836m), and one soft-soil tunnel                contact system, power supply and tele.      2018: Contract award and
+47 977 00 383, brahil@banenor.no
                                           at Eidsvoll to be built in parallel with the           Estimated contract value Venjar-Eidsvoll,         commencement of work
More information:                          existing one.                                          1-2 billion NOK, and Eidsvoll-Langset,      2022: New Infrastructure in operation
www.banenor.no/eidsvoll                                                                           1-1,8 billion NOK.                          2023: Estimated project finish
Upcoming projects mars 2018 - Bane NOR
18   Bane NOR | Upcoming projects | The Dovre Line                                                                                                                                                                                                                     19

              Lillehammer
                              Dovre Line
                                                    Kleverud-
                                                    Sørli-Åkersvika
             Moelv
                            Brumunddal

                               Hamar

                                   Stange

                                         Tangen

                                                    A part of the InterCity double-track railway development on
                                                    the Dovre Line in Stange municipality, north of Oslo.
                                         Eidsvoll

                                 Oslo Lufthavn

                                              Kleverud- Sørli                              Planned schedule Kleverud-Sørli:
                                              The new line consist of 15,8 km              2016: Local development plan approved         Tangenvika Bridge (1070 m) will be the longest railway bridge in Norway when it`s finished.
                                 Lillestrøm
                Oslo S
                                              double-track railway, designed for 250       2018 (Q4): Approved contract strategy         Sørli-Åkersvika                                                                      The new railway station in Stange city
                                              km/h (200 km/h with Thales). Included in     2019 (Second half ): Start prequalification   The new line consist of 14 km double-track,
Contact:
                                              the project is the                           of first main contract                        designed for 250 km/h (200 km/h with Thales).
Project Manager Geir Kvillum
+47 930 19 550, kvigei@banenor.no             construction of the longest railway brid-    2019: Start preparatory works                 A new station at Stange is included in the project, as well as Åker-
                                              ge in Norway, Tangenvika bridge              2020: Planned government funding              svika Wetlands, Ramsar-area.
Project Manager (construction) Gunnar Sletten (1070m), and one rock tunnel,                2020: First main contract award
+47 951 81 301, slegun@banenor.no             Hestnes tunnel 3,1 km.                       2026: New infrastructure in operation         Planned schedule Sørli-Åkersvika:
                                              The project also consists of a new station                                                 2018 (Q4): Approved contract strategy
Head of Contract Gro-Ane Haarklou Westbye at Tangen.
                                                                                                                                         End 2019: Local development plan approved
+47 908 55 482, wesgro@banenor.no
                                                                                                                                         2019: Start preparatory works
More information:                                                                                                                        2020 (Second half ): Start prequalification of first main contract
www.banenor.no/stange                                                                                                                    2021: Planned government funding
www.banenor.no/sorli-akersvika                                                                                                           2021: First main Contract award
                                                                                                                                         2026: New infrastructure in operation
20       Bane NOR | Upcoming projects | The Bergen Line                                                                                                                                                                                                                                                    21

                        Stanghelle
                                     Bergen Line     Arna-
                                                     Bergen
                         Vaksdal

              Arna

Bergen

         Godsterminal
                                                     Bane NOR is constructing a double-track railway between
                                                     Arna and the centre of Bergen. The main part of the section
                                                     passes through a tunnel under Mount Ulriken where Bane
                                                     NOR is building a new, parallel tunnel - New Ulriken tunnel.                             One of the 16 cross passages between the new and the original Ulriken tunnel (to the right). Left: New Ulriken tunnel. Photo by Ingvild Eikeland, Bane NOR

                                                     Construction of the tunnel started in      Upgrading Ulriken tunnel -                   Scope of work:                                         • Maintenance/adjustment of existing                    Bane NOR is reviewing the scope and the
                                                     November 2014, and the double track        Contract UUT23                               • Tunnelling: Breakthrough for two                       drainage system, emergency lighting                   progress plan of the project. Tendering of
                                                     will be completed in 2024.                 The original Ulriken tunnel opened in          diagonal tunnels between existing and                  and cable ducts                                       contracts is estimated to 2020.
                                                                                                1964. The cross sections in the tunnel are     new tunnel in Arna                                   • Planned tendering is 2020 and start-up
                                                     Construction Arna-Bergen consists of two   25-30m2. The water and frost proofing in     • Back-ripping (enlargement of profile)                  spring 2021.                                          Bergen-Fløen
                                                     projects; Arna-Fløen and Nygårdstangen-    the tunnel consists of patches of              for fans in the tunnel ceiling in Fløen                                                                      • New double-track from Fløen to
                                                     Bergen-Fløen.                              uncovered PE-foam.                           • Dismantling of existing PE-foam                      Project Nygårdstangen-Bergen-Fløen                        Bergen railway station
Contact:                                                                                                                                     • Back-ripping for new water and frost                 The distance from Fløen to Bergen                       • Optimalisation of track layout
Project Director Hans-Egil Larsen                    The main contracts in project Arna-Fløen   When the new Ulriken tunnel opens in           proofing at different locations through-             railway station and the freight terminal at             • New electronic interlocking system
+47 474 76 616, larsha@banenor.no                    are: New Ulriken tunnel, Arna station, a   December 2020, the original tunnel will        out the tunnel                                       Nygårdstangen is 1.3 km. The project has
                                                     railway-technical contract and upgrading   be temporarily closed to be upgraded.        • Replacement of existing PE-foam,                     a high complexity due to limited space in               Nygårdstangen/Bergen freight terminal
Head of Contract Stian Ekornaas
+47 945 01 346, ekosti@banenor.no
                                                     of the existing Ulriken tunnel.                                                           fireproofing with shotcrete                          the city centre, and coordination with                  • Reconstruction and upgrading/
                                                                                                                                             • Supplementary work in cross passages                 other projects in the same area.                          optimalisation of the freight area
More information:                                                                                                                              (blasting/road heading/cable ducts)                                                                          • Building new track
www.banenor.no/arna-bergen                                                                                                                   • Installation of bolts for signs and fans                                                                     • New freight buildings
22       Bane NOR | Upcoming projects | The Bergen Line                                                                                       23

                        Stanghelle
                                     Bergen Line     Arna-
                                                     Stanghelle
                         Vaksdal

              Arna

Bergen

         Godsterminal
                                                     This is a joint project collaboration with the Norwegian
                                                     Public Roads Administration in the lead. The main purpose
                                                     of the project is to build a safer and faster railway and road
                                                     between Arna and Stanghelle.
                                                     Large parts of the section will be parallel   Planned schedule:
                                                     railway and road tunnels with shared          The local development plan will be
                                                     cross-passages for evacuation between         completed in the spring of 2020 and will
                                                     the tunnels.                                  most likely be approved by the planning
                                                                                                   authorities by end of 2020.
                                                     The railway part will have 2 tunnels, one
                                                     of 18,7 km and the other 8,0 km.              Start-up is planned in 2022 (road) and
Contact:                                             Two new railway stations will be built.       2024 (railway).
Project Director Hans-Egil Larsen
+47 474 76 616, larsha@banenor.no                    The road part includes 3 tunnels of
                                                     9-10 km.
Head of Contract Stian Ekornaas
+47 945 01 346, ekosti@banenor.no

More information:
www.banenor.no/arna-bergen
24          Bane NOR | Upcoming projects | The Oslotunnel                                                                                                                                                                                                                                             25

                                                                                                 Oslo S-Lysaker and
                                         Lillehammer

                                        Moelv
                                                                Brumunddal

                                                                                                 Nationaltheatret-Bislett
                                                                   Hamar

                                                                        Stange

                                                                             Tangen

                                                                             Eidsvoll
                                                                                                 Todays double-track between Oslo S–Lysaker has been a
                                                                       Oslo Lufthavn
                                                                                                 bottleneck since 2007. New double-track railway Oslo S–
                  Hønefoss

                  Sundvollen
                                                                                                 Lysaker and Nationaltheatret–Bislett is together with the new
                                                                       Lillestrøm
                                                                                                 metro and tram a part of the key infrastructure projects in the
                             Sandvika

                           Asker
                                                Lysaker
                                                            Oslo S
                                                                                                 Concept Study Oslo Hub.
                Drammen                                     Ski

                   Sande                                                                                                                                           Realization of these projects meets          This project consists of new double           It has not yet been concluded on
                 Holmestrand                                                                                                                                       demands for transport capacity towards       track in tunnel from Oslo S through the       which line will be recommended for
                                                                                                                                                                   2030 and 2060 in the Oslo area.              city centre to Nationaltheatret (approx.      construction between Nationaltheatret
                                                      Moss
                             Horten                      Rygge
                                                                Råde

                        Tønsberg
                                                                          Sarpsborg                                                                                                                             1,8 km), extension of Nationaltheatret        and Lysaker. Two different options is
  Skien                 Stokke
                        Torp
                                                  Fredrikstad
                                                                                                                                                                   New double-track railway enables             station with four new tracks, new double-     considered:
               Sandefjord
                                                                                                                                                                   separation of local and regional train       track in tunnel for local trains from         • New double-track in tunnel (alt. 3 with
Porsgrunn                                                                               Halden

                        Larvik

                                                                                                                                                                   traffic and higher frequency for both        Nationaltheatret to Bislett (approx. length      approx. length of 6,5 km) or
                                                                                                                                                                   local, regional and freight traffic. This    of 1,5 km) with new station at Bislett, new   • Alongside existing line (alt. 7 with
Contact:
Project Manager, Nina Tveiten                                                                                                                                      project has high priority in the Norwegian   double-track between Nationaltheatret            approx. length of 6 km).
+47 916 75 783 nt@banenor.no                                                                                                                                       National Transport Plan 2018-2029.           and Lysaker and extension of Lysaker
                                                                                                                                                                                                                station with to new tracks on the bridge.
                                                                                                 Photo by Øystein Grue, Jernbanedirektoratet
26   Bane NOR | Upcoming projects

Suppliers Relations and
Market Contact
For more overall information about our projects or the
tendering process in Infrastructure Construction Division,
please contact:

                    Morten Sigvardsen
                    Supplier Relations and Market Manager for
                    Infrastructure Construction Division
                    +47 901 18 565
                    E-mail: morten.sigvardsen@banenor.no

                                                                Holmestrand station, photo by: Anne Mette Storvik, Bane NOR
Adress: Bane NOR SF, Postboks 4350, NO-2308 HAMAR, Norway
Visitor address: Bane NOR Utbygging, Biskop Gunnerus’ gate 14, NO-0185 OSLO, Norway