Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20

Page created by Kathryn Norris
 
CONTINUE READING
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
Heathrow Aircraft De-icing
Plan (HADIP)
Winter Season 2019/20

Date:      23 October 2019

Version:   v01.00.00

Status:    PUBLIC
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
This version
authored by:

               Name:       Andy Knight

               Role:       Aircraft Operations Manager

Reviewed by:

               Name:       Mark Burgess

               Role:       Head of Airport Operations

Authorised for issue by:

               Name:       Kathryn Leahy

               Role:       Director of Operations
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
Revision Status & Approval Log

    Date          Status for Purpose                         Version      Author      Reviewer      Authoriser

    25 Oct 2019   V00.00.02 Draft for Internal Review        v00.00.02    A. Knight   M. Burgess      K. Leahy

    30 Oct 2019   v00.01.02 Draft for External Review        v00.01.00    A. Knight   M. Burgess      K. Leahy

    29 Nov 2019   v01.00.00 for External Publication         v01.00.00    A. Knight   M. Burgess      K. Leahy

Notes on Document Control

•      Users of the document are responsible for ensuring that they are working with the current version
•      An electronic copy is published for external use. It may be periodically updated to reflect changes to the
       airfield’s operation and to relevant procedures. It can be found on Heathrow’s public website at:
       https://www.heathrow.com/company/team-heathrow/airside/useful-publications/winter-operations
•      Paper or electronic copies may be used, however all copies not held or shared from within the Heathrow
       Aircraft Operations Unit SharePoint site are uncontrolled – therefore the document is uncontrolled when
       printed or emailed

HADIP Winter 2019-20 v01.00.00                                                                           Page | 3
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
Contents
List of Figures .............................................................................................................................. 5
List of Tables ............................................................................................................................... 6
List of Abbreviations & Glossary ................................................................................................... 6
1. Introduction, Scope & Objectives of the Plan.......................................................................... 9
2. Aircraft De-icing at Heathrow – The Basics ............................................................................ 9
   2.1. On-Stand De-icing ....................................................................................................... 11
   2.2. Off-Stand De-icing ....................................................................................................... 15
   2.3. AOP SNOW Module ON/OFF ........................................................................................ 17
3. AIRCRAFT DE-ICING PLAN................................................................................................... 18
   3.1. Winter Weather Forecasts ............................................................................................ 18
   3.2. Activation & Mobilisation ............................................................................................. 18
   3.3. Pre-Tactical Process ...................................................................................................... 21
   3.4. Tactical Process............................................................................................................ 26
   3.5. Closure of Event .......................................................................................................... 28
   3.6. Demand & Capacity Balancing (DCB) during Aircraft De-icing Events ............................. 28
   3.7. Airport Operations Plan (AOP) ...................................................................................... 29
   3.8. Remote De-icing Pads .................................................................................................. 35
4. Command Structure ........................................................................................................... 38
   4.1. Command & Control in Disruptive Events & Emergencies .............................................. 38
   4.2. Airside Command & Control during De-icing Operations .............................................. 39
   4.3. Communications ......................................................................................................... 39
5. Roles & Responsibilities ....................................................................................................... 42
   5.1. Heathrow – the Airport Operator ................................................................................. 42
   5.2. Aircraft Operator ......................................................................................................... 46
   5.3. Ground Handler .......................................................................................................... 47
   5.4. De-icing Service Provider .............................................................................................. 47
   5.5. NATS .......................................................................................................................... 48
   5.6. Airline Operators’ Committee ...................................................................................... 49
6. Training.............................................................................................................................. 49
7. Event Preparation ............................................................................................................... 49
   7.1. Scenarios & Resourcing ................................................................................................ 49
   7.2. DSP Media & Equipment .............................................................................................. 50
8. Reporting ........................................................................................................................... 52
   8.1. Before the Winter Season ............................................................................................ 52
   8.2. D-1 to 2nd Wave De-icing ............................................................................................. 52
   8.3. During 2nd Wave De-icing ............................................................................................. 52
   8.4. After De-icing .............................................................................................................. 53
9. Regulatory References & Further Reading ............................................................................ 53
   9.1. Overall ........................................................................................................................ 53
   9.2. Remote pads ............................................................................................................... 54
   9.3. Capacity Constraints .................................................................................................... 54
10. Appendix 1 – AOU De-icing Operations Preparation Process................................................. 55
11. Appendix 2 – JEDI Operation ............................................................................................... 56
   11.1.     Activation Request ................................................................................................... 56
   11.2.     Area Set Up ............................................................................................................. 56
   11.3.     Opening .................................................................................................................. 56
   11.4.     Operation ................................................................................................................ 57

HADIP Winter 2019-20 v01.00.00                                                                                                       Page | 4
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
11.5.  Operating Restrictions .............................................................................................. 57
  11.6.  De-Activation ........................................................................................................... 57
12. Appendix 3 – VADER Operation .......................................................................................... 58
  12.1.  Background ............................................................................................................. 58
  12.2.  Activation Request ................................................................................................... 58
  12.3.  Opening .................................................................................................................. 59
  12.4.  Operation ................................................................................................................ 59
  12.5.  Operating Restrictions .............................................................................................. 60
  12.6.  Emergency Procedures ............................................................................................. 61
  12.7.  De-Activation ........................................................................................................... 61
13. Appendix 4 – Capacity Constraints Interventions ................................................................. 61
14. Appendix 5 – De-icing Conditions based on Meteorological Conditions ................................ 62
15. Appendix 6 – AOP SNOW Module System Alerts ................................................................. 65
16. Appendix 7 – Forward Holding Tank Process........................................................................ 66
17. Appendix 8 – Fluid Delivery Process ..................................................................................... 66

List of Figures
Figure 1: A-CDM Milestones ...................................................................................................... 10
Figure 2: Turn-round Target Milestones ...................................................................................... 11
Figure 3: On-Stand De-icing Activity & Pre-Departure Sequence .................................................. 12
Figure 4: On-Stand De-icing Activity with TSAT Delay .................................................................. 13
Figure 5: On-Stand De-icing Response to Ground Delay .............................................................. 13
Figure 6: On-Stand De-icing Activity with Network Delay ............................................................ 14
Figure 7: On-Stand De-icing Response to Network Delay ............................................................. 14
Figure 8: Remote De-icing Pad Locations .................................................................................... 15
Figure 9: Off-Stand De-icing Activity & Pre-Departure Sequence .................................................. 16
Figure 10: On-Stand De-icing Response to Network Delay ........................................................... 16
Figure 11: SNOW Module Icon in AOP........................................................................................ 17
Figure 12: Forecast & Activation Timeline ................................................................................... 19
Figure 13: Pre-Tactical Process Overview for D-4 ......................................................................... 22
Figure 14: Pre-Tactical Process Overview for D-3 ......................................................................... 23
Figure 15: Pre-Tactical Process Overview for D-2 ......................................................................... 24
Figure 16: Pre-Tactical Process Overview for D-1 ......................................................................... 25
Figure 17: SNOW Module set to ON in AOP................................................................................ 30
Figure 18: Assessing De-icing Conditions for AOP ....................................................................... 31
Figure 19: On Stand De-icing Process with AOP SNOW Module Enabled...................................... 33
Figure 20: On Stand De-icing Milestone Sequence ...................................................................... 33
Figure 21: De-icing Process with AOP SNOW Module Disabled .................................................... 34
Figure 22: Location & Layout of JEDI Remote De-icing Pads ......................................................... 36
Figure 23: Location & Layout of VADER Remote De-icing Pads .................................................... 37
Figure 24: Heathrow Emergency Command & Control Structure ................................................. 38
Figure 25: Aircraft De-Icing Stakeholders – Typical Organisational Structure ................................. 39
Figure 26: Online DSP Capability Declaration .............................................................................. 52
Figure 27: Example of Met Office OpenRunway® Forecast ........................................................... 52
Figure 28: Snow Data Tab in AOP .............................................................................................. 53
Figure 29: AOU De-icing Operations Preparation Process............................................................. 55
Figure 30: VADER De-icing Request Workflow ............................................................................ 60
Figure 31: Simplified Forward Tank Holding Process .................................................................... 66
Figure 32: Fluid Delivery Process ................................................................................................. 67

HADIP Winter 2019-20 v01.00.00                                                                                             Page | 5
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
List of Tables
Table 1: Met Office Winter Event Preparation ............................................................................. 20
Table 2: Process Overview for Scenario 1 – BAU De-icing from D-1 to End of Event...................... 26
Table 3: Process Overview for Scenario 2 – Snow Event from D-1 to End of Event ........................ 27
Table 4: Assessing Meteorological Conditions for AOP SNOW Module ........................................ 31
Table 5: HAL Aircraft De-Icing Management Team Contact Numbers .......................................... 42
Table 6: Key HADIP Stakeholders ................................................................................................ 42
Table 7: Key Stakeholder Roles & Responsibilities – Heathrow Airport .......................................... 46
Table 8: Key Stakeholder Roles & Responsibilities – Aircraft Operator........................................... 47
Table 9: Key Stakeholder Roles & Responsibilities – Ground Handler ............................................ 47
Table 10: Key Stakeholder Roles & Responsibilities – De-icing Service Provider ............................. 48
Table 11: Key Stakeholder Roles & Responsibilities – NATS .......................................................... 49
Table 12: Key Stakeholder Roles & Responsibilities – Airline Operators’ Committee ...................... 49
Table 13: Sample (Maximum) & Season Start DSP Capabilities ..................................................... 51
Table 14: De-icing Conditions based on MET Conditions ............................................................. 65
Table 15: AOP SNOW Module Performance Alerts ...................................................................... 66

List of Abbreviations & Glossary

 Acronym                         Definition
 A-CDM                           Airport Collaborative Decision Making
 ACL                             Airline Coordination Limited
 ACZT                            Actual Commencement of De-icing Time
 ADIT                            Actual De-icing Duration Time
 AEZT                            Actual End of De-icing Time
 AfCR                            Airfield Control Room
 AfDM                            Airfield Duty Manager
 AFR                             Arrivals Flow Rate
 AGLCS                           Aerodrome Ground Lighting Control System
 AIRT                            Airside Incident Response Team
 ANPT                            Airspace and Noise Performance Team
 AO                              Aircraft Operator
 AOC                             Airline Operators’ Committee
 AOM                             Airport Operations Manager
 AODM                            Aircraft Operations Duty Manager
 AOP                             Airport Operations Plan
 AOU                             Aircraft Operations Unit
 APOC                            Airport Operations Centre
 ARZT                            Actual Request for De-icing Time
 ASD                             Airside Safety Department
 ATC                             Air Traffic Control
 ATCO                            Air Traffic Control Officer
 ATM                             Air Traffic Management

HADIP Winter 2019-20 v01.00.00                                                                                           Page | 6
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
ATT                       Airside Tactical Team
 BA                        British Airways
 BAU                       Business as Usual
 CHMI                      Computer-Aided Slot Algorithm Human Machine Interface
 CRS                       Customer Relations & Service
 CTOT                      Calculated Take Off Time
 DCB                       Demand & Capacity Balancing Tool
 DfT                       United Kingdom Department for Transport
 DMO                       Dynamic Modelling of Operations
 DPI                       Departure Planning Information (Message)
 DSP                       De-icing Service Provider
 ECMT                      Executive Crisis Management Team
 ECZT                      Estimated Commencement of De-icing Time
 EDIT                      Estimated De-icing Duration Time
 EEZT                      Estimated End of De-icing Time
 ERZT                      Estimated Request for De-icing Time
 FCO                       United Kingdom Foreign and Commonwealth Office
 GH                        Ground Handler
 H24                       24 hours per day
 HADACAB                   Heathrow Airport Demand and Capacity Balancing Group
 HADIP                     Heathrow Aircraft De-icing Plan
 HAL                       Heathrow Airport Limited
 HOCC                      Heathrow Operational Conference Call
 HOEC                      NATS Heathrow Operational Efficiency Cell
 HOT                       De-icing Hold Over Time
 HSPA                      Heathrow Snow Plan Airside
 HSRF                      Heathrow Snow Response Forecast
 HTC                       NATS Heathrow Traffic Coordinator
 IATA                      International Air Transport Association
 IRT                       HAL Incident Response Team
 IT                        Information Technology
 MET                       Weather data (meteorology)
 NATS                      NATS Holdings
 NMOC                      EUROCONTROL Network Manager Operations Centre (Brussels)
 NOP                       Network Operations Plan
 OC                        AOU Operations Controller
 OLT                       HAL Operational Leadership Team
 PDR                       APOC Plan, Do, Review Conference Call
 PSC                       Performance Status Check
 RAG                       Red, Amber, Green
 SMS                       Short Message Service (text message)
 SOC                       AOU Senior Operations Controller
 SOM                       Senior Operational Meteorologist
 TC                        NATS London Terminal Control Centre, Swanwick

HADIP Winter 2019-20 v01.00.00                                                        Page | 7
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
TC                        Terminal Coordinator
 TOBT                      Target Off Block Time
 TRM                       Turn-round Manager (Flight Dispatcher)
 TSAT                      Target Start Up Approval Time
 VCR Supervisor            Visual Control Room (Tower) Supervisor
 WOM                       Winter Operations Manager

HADIP Winter 2019-20 v01.00.00                                      Page | 8
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
1. Introduction, Scope & Objectives of the Plan
The Heathrow Aircraft De-icing Plan (HADIP) is intended to provide all interested parties with an overview of
the airport’s approach to aircraft de-icing operations, endorsed by the Director of Operations for Heathrow
Airport Limited (HAL).

The plan is intended to minimise and mitigate the disruptive effects of frost, ice, snow or any adverse winter
weather event on the normal operation of aircraft flow by facilitating a consistent and coordinated response,
assisting the continual safe operation of the airfield even when conditions require reduced capacity.

In this document any reference to de-icing includes both the anti-icing and de-icing of aircraft. Airfield de-
icing is not within the scope of the HADIP. If wintry precipitation leads to the requirement for airfield
infrastructure including aprons, taxiways and runways to be anti-iced, de-iced or have snow cleared from
them, the Heathrow Snow Plan Airside (HSPA) is activated and dedicated resource is stood up to perform
these functions. The HSPA should be read in conjunction with the HADIP.

An important part of the plan for low temperature events that lead to icing conditions is how airlines, De-
icing Service Providers (DSPs), NATS and Heathrow maintain satisfactory aircraft flow rates when conditions
require aircraft to be de-iced. When demand for de-icing services becomes high across the airfield it quickly
becomes challenging to satisfy the scheduled runway throughput. The dynamic nature of de-icing service
provision means aircraft are at risk of repeatedly missing scheduled runway slots. Departure runway demand
can therefore reduce in a short period of time following the onset of snow or low temperatures, even when
sufficient runway capacity exists.

The HADIP optimises the deployment of resources taking into consideration the operational impact and
expected level of response by HAL to aircraft icing conditions including equipment, people, materials and
infrastructure. This document also provides a description of the activities undertaken by DSPs at Heathrow to
effectively deliver de-icing services to their airline customers and the communications required to support this
activity.

The deployment of de-icing operations resulting in the smooth delivery of aircraft in the correct sequence to
the departure runway can only be achieved through close communication with the key relevant stakeholders
who need to operate using accurate and timely information, allowing Heathrow to maintain a clear
assessment of its ability to complete the published flying schedule.

Heathrow provides several remote de-icing pad facilities on the airfield for selected, licenced DSPs to operate
in the delivery of off-stand aircraft de-icing. The operation of these pads and the procedure for their
activation and use is explained in this document.

The HADIP is reviewed annually and this version is effective for the period 27 October 2019 to 28 March
2020 (IATA Northern Winter Season 2019). It is issued in consultation with NATS, Aircraft Operators, Ground
Handlers and De-icing Service Providers.

Any enquiries concerning the Winter 2019/20 HADIP should be addressed to Andy Knight, Aircraft
Operations Manager on 020 8757 5229 or at andy.knight@heathrow.com

2. Aircraft De-icing at Heathrow – The Basics
Airport Collaborative Decision Making (A-CDM) is a pan-European concept which aims to improve the
efficiency and resilience of airport operations by optimising the use of resources and improving the
predictability of air traffic. Airport stakeholder partners (airport operators, aircraft operators, ground handlers
and ATC) and the EUROCONTROL Network Manager work transparently and collaboratively, exchanging
relevant accurate and timely data. There is a focus on aircraft turn-round and pre-departure processes at
airports.

HADIP Winter 2019-20 v01.00.00                                                                            Page | 9
Heathrow Aircraft De-icing Plan (HADIP) - Winter Season 2019/20
It allows the exchange of more accurate departure information, particularly target take-off times, with the
European ATFCM network, leading to better en-route and sectoral planning.

A-CDM is fully implemented at 27 airports across Europe, including Heathrow. The concept measures flight
trajectory performance, including the ground phase of the flight, through 16 primary data milestones that
are shown in Figure 1 below.

                                           Figure 1: A-CDM Milestones

Within the context of activities at airports and aircraft de-icing, the primary concern is with the turn-round
phase which starts when the aircraft arrives in blocks (Actual In-Block Time) and ends with the flight pushing
back for departure (AOBT, Actual Off-Block Time). After this the aircraft is still on the ground at the airport
but is now taxying for departure and eventually becoming airborne (ATOT, Actual Take-off Time).

Timestamps are recorded when these milestones ‘actually’ happen (AIBT, AOBT, ATOT), but before they
happen all airport stakeholders work to a plan that indicates when they want things to happen. Other
stakeholders who are involved in the turn-round process can use this information to plan their own (and
sometimes separate) activities. There are three primary target milestones readers should familiarise
themselves with, as shown in Figure 2 below.

HADIP Winter 2019-20 v01.00.00                                                                         Page | 10
Figure 2: Turn-round Target Milestones

De-icing activities must be accommodated during the turn-round phase and sequenced according to these
milestones, to ensure a smooth departure sequence to optimise runway throughput and therefore best use
of capacity. Put simply:

    •   TOBT is the time at which the aircraft operator or ground handler is expecting the aircraft doors to
        be closed, tug attached and ready to push back. When de-icing is in progress, this is the time at
        which de-icing activity may commence;
    •   TSAT is the time at which ATC is expecting to give a start clearance to flight crew, to release aircraft
        from the stand and taxy to the departure runway. When de-icing is in progress, TSAT reflects the
        time at which de-icing is expected to finish; and
    •   TTOT is the time at which ATC expects the flight to become airborne. If there is any en route delay
        then this is passed on to the flight as a restriction on the time at which the flight is permitted to take
        off, known as a CTOT.

2.1.    On-Stand De-icing
At Heathrow, most de-icing activity takes place while the aircraft is still parked on the stand, before pushing
back for departure. Other milestones are timestamped around de-icing and are aligned with these planning
targets. For example, the estimated commencement of de-icing time should align with TOBT (ECZT).

The most important is the time at which the de-icing service provider (DSP) expects to finish de-icing (EEZT).
It is important because TSAT is adjusted to accommodate this activity and build the pre-departure sequence
accordingly. Therefore, DSPs should provide accurate data on their activities through AOP and update
dynamically when changes occur. This is shown in Figure 3 below.

HADIP Winter 2019-20 v01.00.00                                                                            Page | 11
Figure 3: On-Stand De-icing Activity & Pre-Departure Sequence

Flight crews should call Heathrow Delivery at TOBT as per the normal AOP process to confirm ready to de-ice.
 Note that de-icing may not start immediately. TSAT will be driven by the required de-icing time, as advised
by the De-icing Service Provider (DSP). Call Heathrow Delivery on completion of de-icing to request start and
                 push approval. If de-icing cannot be completed by TSAT, call ATC to advise.

Departing flights are planned to align with the Target Start-Up Approval Time (TSAT) to generate a smooth
and stable departure sequence. During aircraft de-icing operations TSAT is aligned with and driven by the
Estimated End of De-icing Time (EEZT), which is promulgated and updated in AOP by the DSP. This allows
airspace, airfield and weather conditions to be taken into account when planning timings, sequence and
numbers of aircraft to be de-iced.

Therefore, it is critical that the EEZT value is always kept as accurate and as up to date as possible to avoid
poor pre-departure sequencing, which in turn leads to increased start up delay and subsequent Hold Over
Time (HOT) risks.

Figure 3 shows de-icing in optimal conditions when there is no ground delay. However, delays to the
expected start approval time (i.e. TSAT delay) can be present for several reasons that may or may not be due
to de-icing itself, depending on the demand for the service and the DSP’s ability to cater for it. Provided the
DSP can satisfy its customers in a timely manner, TSAT delay can still be driven by other unrelated causes such
as airfield congestion, inefficient use of stand capacity and high demand on certain departure routes.

In these cases, the TSAT generator still looks at EEZT to generate the sequence, but it will also take more
penalising constraints into account such as those mentioned above which create further delay – TSAT will
‘move to the right’ accordingly. Compare Figure 3 with Figure 4 below – it shows that further ground delay
exists, so TSAT can now be expected at a later time than when de-icing was originally due to finish.

HADIP Winter 2019-20 v01.00.00                                                                            Page | 12
Figure 4: On-Stand De-icing Activity with TSAT Delay

Figure 5 below shows the correct response. No updates are required to TOBT (ready to de-ice) or especially
EEZT (completed de-icing) as this will drive further TSAT delay. The TSAT generator sees EEZT moving right
and it will itself move further right in response (due to the TSAT algorithm). This creates an endless loop
where no aircraft ever departs the stand. Instead, the DSP should plan to delay the actual commencement of
de-icing (ACZT) so that the actual end of de-icing (AEZT) will coincide with the new TSAT.

                               Figure 5: On-Stand De-icing Response to Ground Delay

There is more than one source of delay. TSAT delay refers to those delays suffered on the ground at
Heathrow or in the immediate airspace for departing aircraft. Another type of delay affecting Heathrow is
inherited from the wider European air traffic management network, which results in an en route airspace
restriction or congestion at the destination airport. In this case the air navigation service providers who are
involved in the flight’s trajectory will coordinate these restrictions to balance capacity and pass a departure
time back to Heathrow that must be observed.

This is known as a Calculated Take-Off Time (CTOT). When a CTOT is calculated to resolve an airspace
capacity restriction, it means the affected flight must become airborne within 15 minutes (minus 5, plus 10)
of the calculated time. When CTOTs are applied to departing flights at Heathrow, the TSAT generator will
now take this into account and generate a start-up sequence that aims to deliver an airborne time within that
window, see Figure 6 below.

HADIP Winter 2019-20 v01.00.00                                                                           Page | 13
Figure 6: On-Stand De-icing Activity with Network Delay

In this case it is acceptable to adjust estimated start and finish times for de-icing, as the TSAT generator will
respect the CTOT as the most penalising constraint and aim to release the flight from the stand at the correct
time for the CTOT window. It is worth noting that during winter weather with mass de-icing in effect across
the airfield, if CTOTs are numerous then this suggests widespread disruption across Europe – which may or
may not be related to degraded weather conditions. Either way, it is possible for airlines to see lengthy CTOT
(‘slot’) delays exceeding one or two hours.

To manage the airfield situation and achieve as orderly a flow as possible under these conditions, NATS
prefers a good buffer of approximately 60 minutes between the end of de-icing and the CTOT to manage
congestion more effectively. DSPs should therefore be aware of the possible knock-on impact to Holdover
Times (HOT) and look to complete de-icing activities as close to TSAT as possible.

                              Figure 7: On-Stand De-icing Response to Network Delay

In the example given above in Figure 7, the flight originally had a TOBT (ready to de-ice) at 10:00 but is now
faced with a three-hour slot delay (i.e. the CTOT is set at 13:00 by air traffic control). TSAT is now locked to
the CTOT to ensure the flight leaves the stand at the correct time to taxi to the runway and depart.

Therefore, EEZT could go forward by two hours and not affect the CTOT as TSAT is locked, avoiding the
earlier example for ground (TSAT) delay described in Figure 5. However, de-icing should still be completed
within 60 minutes of the CTOT to ensure the slot window of –5 to +10 minutes can be respected and the
aircraft becomes airborne at the correct time to avoid the en route restrictions.

HADIP Winter 2019-20 v01.00.00                                                                           Page | 14
2.2.    Off-Stand De-icing
While most de-icing activity stakes place on the stand, Heathrow has two sets of remote de-icing pads on the
airfield that allow aircraft to instead undertake de-icing on the way to the runway. The main benefit is
freeing up stand capacity for arriving flights, rather than keeping aircraft on-stand for longer while they de-
ice. In addition it alleviates Holdover Time issues to reduce the chance the aircraft will need to return to
stand to de-ice a second time, when extensive delays exist.

The de-icing pads to the west of the airfield are named ‘JEDI’, with a second set to the east named ‘VADER’.
More information on the pads is provided in Section 3.8, however the locations of the pads are shown in
Figure 8 below.

                                     Figure 8: Remote De-icing Pad Locations

HADIP Winter 2019-20 v01.00.00                                                                        Page | 15
In terms of their operation, de-icing activity on the remote pads must also be coordinated within the A-CDM
pre-departure sequence. The arrangement is different compared to on-stand de-icing.

TSAT is normally issued automatically at 30 minutes prior to TOBT. Once the de-icing location is set to ‘PAD’
in AOP by the De-icing Service Provider, no TSAT is displayed. That is, it disappears once the flight is
allocated to the pad. The flight crew call for start as normal at TOBT and the flight is released from the stand
by ATC to taxi to the pad. The order in which aircraft are released from stand and sent to the pad is
coordinated directly between the Pad Operator (known as the ‘ICEMAN’) who is located in the ‘Ice Tower’
and the VCR Supervisor in the control tower. The DSP sets the ECZT and EEZT values at the respective times
it expects the aircraft to enter and exit the pad (with engines running). Upon completion of de-icing the
aircraft proceeds to the runway for departure, see Figure 9 below.

                           Figure 9: Off-Stand De-icing Activity & Pre-Departure Sequence

Figure 9 considers operation of the remote pad in optimal conditions when no delay is experienced.
However, when delay exists, the situation becomes more complicated and coordination of affected flights
through the pad can be difficult. In the case of TSAT delay there is no problem, because once the flight is
allocated to the pad the TSAT is deleted anyway and coordination takes place directly between ICEMAN and
ATC. Figure 10 below considers what happens when a flight is impacted by a CTOT.

                             Figure 10: On-Stand De-icing Response to Network Delay

HADIP Winter 2019-20 v01.00.00                                                                         Page | 16
This is the same example as given above in Figure 7. The flight originally had a TOBT of 10:00 but now faces
a three-hour slot delay due to network restrictions (CTOT is set at 13:00). Before being assigned to the pad,
the TSAT will be generated at 30 minutes prior to TOBT (i.e. at 09:30), but this will disappear once the pad is
selected in AOP.

All relevant milestones must now be worked out backwards from the CTOT. As with on-stand de-icing when
CTOTs apply, NATS prefer a buffer of approximately 50-60 minutes between pushing back from stand and
the required take-off time, but an absolute minimum of 40 minutes for off-stand de-icing. This is to manage
airfield congestion.

The DSP must consider how long it will take to taxi from the stand to the pad, de-ice on the pad (EDIT), then
continue taxiing to the runway. This complete timespan is the Variable Taxi Time (VTT). Figure 10 shows this
as 10 minutes to taxi to JEDI, 20 minutes to de-ice on stand (EDIT), then 25 minutes to taxi to the runway
holding point; so VTT = 55 minutes.

Therefore, the airline or Ground Handler (in coordination with the DSP) must change the TOBT from 10:00 to
a new time of 12:05. This is because the Calculated Take-Off Time (CTOT) is 13:00 and the aircraft must
take off within the tolerance window (minus 5, plus 10). If the complete taxi phase plus de-icing activity on
the pad is 55 minutes, then it needs to leave the stand at 12:05. The TOBT now signals the time at which
the aircraft has its doors closed, tug attached and is ready to push back.

2.3.    AOP SNOW Module ON/OFF
During periods of light or sporadic de-icing across the airfield and the remote pads are not being used, it is
not always necessary to switch on the AOP Snow Module to allow de-icing to continue. The provision of de-
icing services can be coordinated directly between the airline, Ground Handler and DSP as and when
preferred between themselves. In this case, the Target Off-Block Time (TOBT) simply indicates de-icing
activity has been completed and the aircraft is ready to push. However, when the SNOW Module is switched
on, it means the aircraft is ready to be de-iced in accordance with the description given in the sections above.

AOP users can see when the SNOW Module is switched on by referring to the Airfield Status icon at the top
of the Home screen, see Figure 11 below.

                                      Figure 11: SNOW Module Icon in AOP

As some DSP solely use AOP for completely managing their de-icing operation, including the allocation of
requests and tracking of de-icing rigs, the SNOW Module may be switched on by arrangement directly with
the Aircraft Operations Unit at any time of the day. The Aircraft Operations Duty Manager (AODM) will
switch it on shortly after midnight in any case where the overnight air temperature is expected to fall to 3°C
or below.

For TSAT to take EEZT into consideration, the Adverse Weather Module in the control tower must be
switched on at the same time as the SNOW Module in AOP. This can be requested by the AODM, but the
DSP can also request it directly with the VCR Supervisor if the AODM is not present – which is why it is
turned on overnight when cold conditions are expected.

For more detailed information on the AOP SNOW Module and how de-icing activities are conducted with the
module switched on or off, please refer to Section 3.7.

HADIP Winter 2019-20 v01.00.00                                                                         Page | 17
It is important to note that during de-icing and snow operations, TOBT represents AIRCRAFT FULLY
                     READY TO BE DE-ICED, as opposed to aircraft ready to push.

3. AIRCRAFT DE-ICING PLAN
3.1.    Winter Weather Forecasts
Meteorological forecasts for the prediction of ice, snow and associated phenomena are provided by the
United Kingdom Met Office, from a working position located in the APOC at the Heathrow Compass Centre.
The Met Office desk is staffed H24 by a Senior Operational Meteorologist (SOM).

The SOM issues a variety of forecast products during the winter season which are described below; some are
issued throughout the year regardless of conditions. Each product has a bespoke distribution depending on
its operational application. Some of these products are available to internal HAL stakeholders only.

    •   HSRF – the Heathrow Snow Response Forecast is issued whenever there is a 10% or greater risk of
        snow or sleet. It is issued 48 hours ahead, at 24, 18, 12 hours and then every 2 hours to onset. It
        may sometimes be reissued outside of these timeframes if there is a significant change in the
        forecast that may drive a change to HAL’s operational response.
    •   HSRF Closedown – the closedown is issued when the risk of snow has ceased and the actual
        amount of snowfall is recorded in this report alongside the original forecast for comparison. The
        distribution is the same for the HSRF.
    •   Temperature Curve – this is issued daily during the winter season to aid de-icing decision making,
        i.e. when to de-ice or anti-ice and what level of response is likely to be needed. This is also used by
        airlines and DSPs to pre-order the correct levels of de-icing fluids, and by landside teams to make
        decisions on whether to grit road surfaces, pavements and footways.
    •   HOCC Brief – the SOM attends the HOCC and provides participating stakeholders with an up-to-
        date status of current conditions and those to be expected in the coming hours. The forecast pack
        used in the HOCC is issued four times per day to match the HOCC schedule and at approximately
        0400L. The pack includes a weather risk assessment matrix for the next 24 hours indicating any
        phenomena that may impact the operation, using a simple RAG status. These briefings take place
        on every day of the year.
    •   OpenRunway® 5-Day Forecast – this forecast is generated daily and is usually produced by the
        night shift SOM, issued at or around 0400L. It is sent by email to a defined distribution list but it is
        also available via the Met Office’s online OpenRunway® portal at any time. Access requires a
        username and login but HAL freely provides access to all airport stakeholders who require it; contact
        Andy Knight, Aircraft Operations Manager on 020 8757 5229 for details.
    •   15-Day Forecast – this is also produced daily and sent to stakeholders at around 1100L. It consists
        of a simple risk matrix with a RAG status provided for each type of meteorological phenomena. It
        allows snow or ice events to be detected up to 15 days ahead. The likelihood of the event occurring
        gains greater granularity and confidence as it moves into the 5-Day forecast period.
    •   Frost Warning – issued when there is the risk of frost on ground, surfaces or in the air.

3.2.    Activation & Mobilisation
There are two levels of activation in response to predicted wintry conditions, in accordance with the scenarios
described below in Section 7.1:

HADIP Winter 2019-20 v01.00.00                                                                          Page | 18
1. Business as Usual – ad hoc de-icing, first wave de-icing, and further heavy frost requiring second
       wave de-icing; and
    2. Full snow team response – as per the HSPA in the event of significant snowfall impacting airport
       operations.

There have been instances in the past where prolonged periods of de-icing over several days were
immediately followed by a snow event, resulting in severe resource pressures for DSPs including staffing
levels and fatigue. There won’t always be a stark choice between the two scenarios above and it is important
that all parties maintain a good level of situational awareness and open information sharing to deal with such
occurrences.

The advanced 15-day weather forecast and the more focused forecast at 5 days out (D-5) identify the need
to respond to icing conditions or a snow event. Figure 12 below illustrates the timeline for the preparation of
required activities leading up to an event.

                                            Figure 12: Forecast & Activation Timeline

An initial decision on whether to trigger aircraft de-icing activities will be taken four days prior to an
anticipated de-icing or snow event, based on the 5-Day weather forecast provided by the Met Office, whose
online OpenRunway® portal is available to DSPs and all Heathrow stakeholders at any time. The Met Office
undertakes a variety of tasks to support the operation when wintry precipitation is expected as per Table 1
below.

 Phase                                             Actions

                                                   Winter weather forecast updated four times a day, three times daily
 D-5 prior to anticipated icing or snow
                                                   through the HOCC, chaired by the AODM

 D-4 to D-2 prior to anticipated icing or          Confirm snowfall or frost prediction & provide updates four times per
 snow                                              day (three times at HOCC)

HADIP Winter 2019-20 v01.00.00                                                                                     Page | 19
Phase                                        Actions

 24, 18, 12, and 9 hours prior to             Weather updates provided via HOCC & the Heathrow Snow Response
 anticipated icing or snow                    Forecast (HSRF)

                                              Confirm forecast, make yes or no-go decision based on predicted
 8 hours prior to anticipated icing or snow
                                              conditions and anticipated time of onset with AIRT Lead via HSRF

 4 hours prior to anticipated icing or snow   Send AIRT an update if and when significant changes occur to forecast

 During icing or snow                         Send AIRT an update only if significant changes occur

                                      Table 1: Met Office Winter Event Preparation

3.2.1. Activation Decision – Daily HOCCs
When the forecast predicts a snow event, the Winter Operations Manager will join the normal daily 0900L
HOCC conference call. HOCC participants will review the latest Heathrow Snow Response Forecast and
discuss HAL’s intended response to the event. Although HOCC calls usually attract a small number of airlines
during BAU conditions, participation tends to increase during expected winter operations and any operational
stakeholders are welcome to join the call – even in an unannounced, listen-only capacity – at any time using
the details provided earlier in Section 4.3.1.

3.2.2. DvC Activation
In the event of any short-term event (including weather) that may impact Heathrow’s ability to provide its
usual capacity levels, the Aircraft Operations Duty Manager (AODM) may instigate the Capacity Constraints
Level 2 ‘Demand versus Capacity’ (DvC) process and request that the relevant stakeholders attend the DvC
conference call, as per the UK Aeronautical Information Publication (AIP, see Appendix 4 – Capacity
Constraints Interventions).

As discussed earlier in Section 4.3.4, this call has two primary triggers:

    •    An Arrivals Flow Regulation (AFR) of 36 or less for a period of four hours or more; or
    •    An anticipated schedule slippage that indicates 10 scheduled flights or more operating into the Night
         Quota Period (i.e. these flights are deemed to be Night Jet Movements).

Both triggers are calculated using the Heathrow Service Plan (HSP) which is generated daily at D-1 by the
HOEC. The AODM uses it to assess the expected performance for the following day.

The aim of DvC is to allow airlines to pre-tactically cancel flights to provide a stable schedule for the following
day when disruption is expected, and to minimise the risk of Night Jet Movements. DvC member airlines are
the top 20 airlines in terms of traffic volume. They are invited to a conference call on the day prior to the
anticipated event where they receive a weather brief and a breakdown of the anticipated impact of the event
in terms of airport capacity. The AODM then puts forward a numerical proposal aimed at providing a stable
operation. A consensus agreement is sought and the fact that the call is generated does not automatically
mean that there will be a requirement for a schedule intervention. Airlines collaboratively agree to make
schedule reductions but it is not mandatory.

Should a schedule intervention be required then a NOTAM is issued to support the requirement. Ad hoc slots
will be suspended and the divert status of the airfield will be switched to ‘unavailable’ (although emergencies
and home-based carriers are exempt). During the event the AODM is responsible for keeping the AOM and
the wider APOC team up to date with how the airfield and airlines are performing against the schedule. This
is actioned via the standard APOC ‘Plan, Do, Review’ (PDR) meetings and specific Airport Operations

HADIP Winter 2019-20 v01.00.00                                                                               Page | 20
Manager (AOM) reporting mechanisms. A full wash-up is actioned after every DvC event to determine any
areas for improvement and opportunities for enhancement.

3.2.3. HADACAB Activation
When weather is forecast of a type and nature that is likely to lead to deep and prolonged disruption, the
HADACAB process is typically triggered in response to such events requiring a capacity reduction of greater
than 10% and lasting more than 24 hours. This might also include the loss of infrastructure such as a
runway or terminal. The detailed process is documented in Local Rule 4 which is governed by the Heathrow
Coordination Committee and the process is owned by Heathrow Operations1. HADACAB is used sparingly
and only once in the last five years at the time of writing.

The AOM, AODM or relevant Heathrow stakeholders can recommend the activation of HADACAB at any
time according to the set criteria. This must be convened through the AOM, who will inform the HAL
Director of Operations.

    It should be noted that both DvC and HADACAB are only used when the potential for substantial
          disruption exists. During the winter season it is likely that if these measures are being
       implemented then the HSPA will have also been activated in response to a snow event that is
                               creating the need to use these interventions.

    In most cases it is expected that de-icing operations take place in Business as Usual conditions and
     the decision to switch AOP to the SNOW Module will be discussed on the regular HOCC involving
        BAU participants. If approaching icing operations are detected in the pre-tactical phase, the
                            process now follows as set out in the sections below.

3.3.        Pre-Tactical Process
All actions in the pre-tactical phase from D-4 to D-1 are the same for both de-icing scenarios, i.e. whether in
Business as Usual conditions or during a snow event. At D-1 the AIRT may be called out when a snow event
is declared and/or it is ascertained by the AODM that DSPs will be unable to provide sufficient capacity to
service the schedule leading to disruption. In both cases, the AIRT is stood up by the AOM based on the
AODM’s advice.

The entire process overview can be seen in a single A3 diagram in Figure 29 in Appendix 1 – AOU De-icing
Operations Preparation Process, however it is now examined in its components in the following sections.

3.3.1. Day–4
At D-4 the Met Office Senior Operational Meteorologist (SOM) based in the APOC will issue a weather
forecast that identifies a risk of icing conditions likely to trigger the need for de-icing operations. The
forecast may also indicate a risk of snow, which implies that de-icing operations will still take place and the
snow plan (HSPA) might additionally be activated to stand up snow clearance and incident response teams.
If no risk exists, the AODM will continue to monitor MET reports and re-assess the risk the next day at D-3.

If the risk is present then the AODM will contact De-icing Service Providers and request that they complete an
operational readiness status update using the online survey tool. From this the AODM can assess whether
any DSP is at risk of not being able to deliver de-icing services to its customers for the envisaged conditions.
If no risk exists, the process continues into D-3. If there is a risk, at this stage the Airside Incident Response
Team (AIRT) is simply updated with this information (see Figure 13).

1
    See: https://www.acl-uk.org/wp-content/uploads/2016/09/Airportinfolink_LHR_localrule4.pdf

HADIP Winter 2019-20 v01.00.00                                                                           Page | 21
Figure 13: Pre-Tactical Process Overview for D-4

3.3.2. Day–3
At D-3 the process repeats. The Met Office SOM will issue an updated forecast to identify the developing
risk of icing conditions and/or snow. If no risks exist the AODM will continue to monitor MET reports and re-
assess the risk at D-2.

If the risk is present then the AODM will re-establish contact with De-icing Service Providers and request that
they update their operational readiness status using the online survey tool. DSPs only need to respond if their
status has changed from the information given previously on D-4. From new responses the AODM will re-
assess whether any DSP is at risk of being able to deliver de-icing services as planned. If no risk exists the
process continues into D-2. If there is a risk, AIRT is informed accordingly (see Figure 14).

HADIP Winter 2019-20 v01.00.00                                                                        Page | 22
Figure 14: Pre-Tactical Process Overview for D-3

3.3.3. Day–2
At D-2 the SOM updates the forecast to confirm the ongoing risk of icing conditions or snow. If no risks exist
the AODM will continue to monitor MET reports and re-assess the de-icing risk at D-1. The AODM will also
provide the AIRT with an update on the risk.

If the risk is present then the AODM will contact the De-icing Service Providers once again, request that they
update their readiness status using the online tool; additionally in this case the AODM will contact the AOC
to advise that de-icing operations can be expected on D0. The AOC should in turn inform its members to
prepare for this accordingly.

The AODM will re-assess whether any DSP is at risk of being able to deliver as planned. If no risk exists the
process continues into D-1. If there is a risk, both the AOC and the AIRT are informed (Figure 15).

HADIP Winter 2019-20 v01.00.00                                                                         Page | 23
Figure 15: Pre-Tactical Process Overview for D-2

3.3.4. Day–1
On the day before expected icing conditions, the SOM will update the daily forecast as usual. The AODM will
calculate the level of required tactical interventions, if any, using the Capacity Constraints procedures for
Level 1 and 2. This is a precautionary measure to prepare for D0 and to determine if a DvC intervention is
needed. The AODM will review the likelihood of icing conditions and if the risk subsequently sufficiently
diminishes, the process ends until the next regular forecast identifies a new risk.

If the risk remains present then the AODM will contact De-icing Service Providers as on previous days and
request a further update. The DSP should then return any new information via the online survey tool and
consider the impact of the DvC intervention if it has indeed been promulgated by the AODM. If responses
indicate a risk to the de-icing operation, the AODM will determine the existing DSP capability and create a

HADIP Winter 2019-20 v01.00.00                                                                       Page | 24
proposal for mitigation to the AIRT. This is based on comparing rig availability and DCB predictions against
the pre-season plan and highlighting any bottlenecks or excess demand. If no risk is present the AIRT is
informed nonetheless. In either case the AIRT now actively takes information from AODMs and uses it to
determine an action plan for D0.

DSPs should also inform the AODM if they wish to open a remote pad to provide off-stand de-icing services.
In response, the AODM will instruct the DSP on the preferred mode of pad operation (location and aircraft
flow direction) and advise the Airside Safety Department (ASD) of the pad’s intended activation. At this point
the process ends and further, separate dedicated procedures are now followed to arrange the pad’s
activation, operation and deactivation (see Appendix 2 – JEDI Operation and Appendix 3 – VADER
Operation).

                                 Figure 16: Pre-Tactical Process Overview for D-1

HADIP Winter 2019-20 v01.00.00                                                                        Page | 25
The pre-tactical process remains the same regardless of the scenario. The only exception to this occurs when
a snow event is declared and the HSPA is activated – in effect the process is the same from D-4 to D-1 as in
Figure 16 above, the only difference is that on D-1 the AIRT is called out and is physically on site.

3.4.    Tactical Process
3.4.1. Process Overview: Scenario 1 – BAU De-icing from D-1 to End of Event
‘Business as Usual’ de-icing operations means that weather and other prevailing conditions are such that no
operational constraint affecting airport capacity exists other than the overall capability to de-ice aircraft and
sequence them to the departure runway. The weather is essentially benign other than the low ambient
temperatures being experienced which create the icing conditions.

Other than the requirement to monitor and manage overall aircraft throughput and traffic flow with
integrated de-icing activities, this represents a ‘normal’ operational day for the AODM who oversees this
process. Nonetheless the AODM undertakes the tactical actions as shown in Table 2 below, alongside APOC
partners from the Met Office and the AOU.

 Stakeholder                 -24 hours                       -12 hours                          -2 hours
                                                                                     Advise MET conditions against
 Met Office             Issue daily forecast
                                                                                                appendix
                                                                                         Switch AOP to Winter
                      Issue DSP status request         Review AODM coverage
                                                                                      Operations (SNOW Module)
                                                        Consider remote pad               Finalise remote pad
                         Assess DSP status
                                                           requirements                      requirements
 AODM
                                                                                     Request NATS switch CHMI to
                        Advise AOM & AOU
                                                                                        Adverse Weather mode
                      Complete PSC with DCB
                           information
 SOC                 Review AOU staffing levels      Review potential full house

                  Table 2: Process Overview for Scenario 1 – BAU De-icing from D-1 to End of Event

When aircraft are ready to commence de-icing operations, the Ground Handler and De-icing Service Provider
are jointly responsible for updating AOP with the following inputs:

    •   Request for De-icing;
    •   Estimated Commencement of De-icing Time (ECZT);
    •   Estimated De-icing Duration Time (EDIT);
    •   Estimated Ready for De-icing Time (ERZT) via TOBT update;
    •   Estimated End of De-icing Time (EEZT);
    •   Actual Commencement of De-icing Time (ACZT); and
    •   Actual End of De-Icing Time (AEZT).

During periods of high demand, remote de-icing pads may be used for off-stand service provision and to aid
airfield flow. British Airways will operate JEDI and all others use VADER, provided that in the latter case the
airline has a contractual relationship with the pad operator. For the winter 2019/20 season this is Aéro Mag.

HADIP Winter 2019-20 v01.00.00                                                                             Page | 26
Switching the allocation from ‘stand’ to ‘pad’ in AOP may only be performed by BA for JEDI. For VADER, the
AODM acts as the De-icing Coordinator in conjunction with Aéro Mag and selects aircraft in AOP to be de-
iced on the pad based on a set of acceptance criteria.

3.4.2. Process Overview: Scenario 2 – Snow Event from D-1 to End of Event
When a snow event is forecast and the HSPA is activated, aircraft will still typically require de-icing but now
the added complexity of snow clearance activity exists. Depending on the amount of snowfall, this can
quickly become the most constraining factor. The AODM will continue working to deliver the optimum level
of aircraft de-icing throughput under the conditions being experienced.

The AODM will ensure that all DSPs are aware of any planned or known runway closures to accommodate
anti-icing, de-icing and snow clearance activities. For example, when Runway 27L/09R is being swept no
crossings to or from Terminal 4 are permitted. This will drive a delay to the commencement of de-icing until
the runway is operational (usually 30 mins) to prevent returns to stand, media re-application, or Hold Over
Times from being affected.

                                                                          -10      -8        -6
    Stakeholder       -24 hours        -18 hours        -12 hours                                      -4 hours§2       -2 hours§
                                                                         hours    hours     hours

                                                                         Issue     Issue     Issue
    Met Office        Issue HSRF       Issue HSRF       Issue HSRF                                     Issue HSRF      Issue HSRF
                                                                         HSRF      HSRF      HSRF
                                        Move to      Consider remote                                     -4 hour
                       Issue DSP                                                                                      -2 hour snow
                                       24/7 roster     de-icing pad                                    operational
                    status requests                                                                                        call
                                        coverage      requirements                                      snow call
                      Assess DSP                                                                                     Switch AOP into
                        status                                                                                        SNOW Module
    AODM
                                                                                                                     Finalise remote
                    Advise AOM &
                                                                                                                       de-icing pad
                         AOU
                                                                                                                      requirements
                    Complete PSC                                                                                     Request CHMI
                      using DCB                                                                                       into Adverse
                     information                                                                                     Weather mode
                     Review AOU                      Review potential
    SOC
                    resource levels                   for ‘full house’

                    Confirm roster
    AIRT
                    and availability

                         Table 3: Process Overview for Scenario 2 – Snow Event from D-1 to End of Event

Just as in BAU conditions, when aircraft are ready to commence de-icing, the GH and DSP are responsible for
updating AOP with:

       •    Request for De-icing;
       •    Estimated Commencement of De-icing Time (ECZT);
       •    Estimated De-icing Duration Time (EDIT);
       •    Estimated Ready for De-icing Time (ERZT) via TOBT update;
       •    Estimated End of De-icing Time (EEZT);
       •    Actual Commencement of De-Icing Time (ACZT); and
       •    Actual End of De-Icing Time (AEZT).

2
    § Actions at -2 hours and -4 hours are coordinated with required actions in the HSPA for winter 2019/20

HADIP Winter 2019-20 v01.00.00                                                                                              Page | 27
You can also read