Generation Interconnection Facility Study Report For PJM Generation Interconnection Request Queue Position AB1-081 Anaconda – Heartease 115kV 56 MW Capacity / 80 MW Energy Revised March / 2018
Introduction This Facilities Study has been prepared in accordance with the PJM Open Access Transmission Tariff §207, as well as the Facilities Study Agreement between Harts Mill Solar, LLC, (Interconnection Customer (IC)) and PJM Interconnection, LLC (Transmission Provider (TP)). The Interconnected Transmission Owner (ITO) is Virginia Electric and Power Company (VEPCO). General The IC has proposed a solar generating facility located near Tarboro, NC in Edgecombe County. The installed facilities will have a total capability of 80 MW with 56 MW of this output being recognized by PJM as capacity. The proposed in-service date for this project is December 31, 2021. This study does not imply an ITO commitment to this in-service date. Point of Interconnection Queue AB1-081 will interconnect with the ITO transmission system via a new three breaker ring bus switching station that connects on the Anaconda – Heartease portion of the Anaconda – Hathaway 115kV line # 80. Cost Summary The AB1-081 project will be responsible for the following costs: Description Total Cost Attachment Facilities $ 505,291 Direct Connection Network Upgrades $4,721,367 Non Direct Connection Network Upgrades $1,849,641 Allocation for New System Upgrades $0 Contribution for Previously Identified Upgrades $0 Total Costs $7,076,299 © PJM Interconnection 2018. All rights reserved. 2 Queue AB1-081 Anaconda – Heartsease 115kV
A. Transmission Owner Facilities Study Summary 1. Description of Project Queue AA2-177 is a request to interconnect 80 MW (Capacity 56 MW) of energy from a new solar facility to be located near Tarboro NC in Edgecombe County. The proposed facility will interconnect with ITO’s Anaconda – Heartease 115kV line #80 via a new three breaker switching station (Harts Mill). The requested in-service date is December 21, 2021. Attachment Facility and Direct Connection Network upgrade construction is estimated to be 18-24 months. 2. Amendments to the System Impact Study data or System Impact Study Results None 3. Interconnection Customer’s Submitted Milestone Schedule Plan to break ground 3/01/2020 Turn over flat, graded site with one inch of gravel to ITO for new Harts Mill switching station 2/01/2019 Permits – state level Permit By Rule and county level Final Site Plan approval complete by 9/01/2019 Substantial site work completed 3/01/2019 Delivery of major electrical equipment 6/01/2019 Back Feed Power 12/02/2019 Commercial Operation 12/15/2019 4. Scope of Customer’s Work IC will build a solar generating facility in Edgecombe County, North Carolina. The generating facility (Harts Mill Solar) will be comprised of solar arrays. AB1-081 consists of 54 x 1.48 MW ABB Ultra-1500 inverters. The 27 x 34.5/0.690 kV generator step up (GSU) transformers with a rating of 3.0 MVA will connect the solar inverters to the 34.5 kV collector system. The generating facility will connect to the Point of Interconnection (POI) via a 115/34.5 kV wye grounded wye grounded main power transformer with a rating of 56/72/88 MVA. The AB1-081 POI will be at the new Harts Mill 115kV substation. 5. Description of Facilities Included in the Facilities Study The ITO will connect the proposed generator lead via Attachment Facilities to a new Harts Mill 115kV switching station adjacent to the 115kV transmission right of way on a property provided by the IC. Harts Mill switching station will be positioned in such a way that the new backbone will align with the perpendicular bisector at structure 80/114. The Hathaway – Tarboro 115kV #80 line will be cut and attached to the new backbone and risers will be dropped from both sides of the backbone to the bus sections directly underneath the backbone. The lines will consume two of the three positions in the ring bus. The third position will be for the 115-kV feed from IC’s collector station. The demarcation point between the switching station and the collector station will be the 4-hole pad on the ITO disconnect switch which is located on the first Attachment Facility structure outside of the Harts Mill switching station. The IC will bring its © PJM Interconnection 2018. All rights reserved. 3 Queue AB1-081 Anaconda – Heartsease 115kV
bus to the demarcation point. Metering equipment will be installed in the Harts Mill switching station. The grounding systems for both stations will be tied together. All substation permitting, site preparation and grading activity will be performed by IC. 6. Total Costs of Transmission Owner Facilities included in Facilities Study Direct Indirect Work Description Labor Material Labor Material Total Cost Attachment Facilities $280,186 $160,007 $48,671 $16,427 $505,291 Total Attachment Facilities Cost $260,186 $160,007 $48,671 $16,427 $505,291 Harts Mill 115 kV Switching Station (n5476) $2,039,855 $2,103,451 $356,564 $221,497 $4,721,367 Line #80 Transmission work (n5478) $430,792 $360,184 $128,710 $119,150 $1,038,836 Remote relay (n5477) $468,802 $217,871 $93,326 $30,806 $810,805 Total Network Upgrades $2,939,449 $2,681,506 $578,600 $371,453 $6,571,008 Total Project Costs $3,219,635 $2,841,513 $627,271 $387,880 $7,076,299 7. Summary of Milestone Schedules for Completion of Work Included in Facilities Study: Facilities are estimated to take 20 - 26 months to construct and this is based on the ability to obtain outages to construct and test the proposed facilities. Proposed Schedule Engineering 4 - 6 months Construction 16 - 20 months Engineering and construction timelines are based on the IC providing a graded and permitted site to the ITO at the time of executing ICSA. ITO requires the site to be fully graded and permitted site so they can start construction by October 2020. The estimated time to construct and build the proposed facilities is based on typical permitting timelines actual permitting requirements required by local zoning conditions may impact this schedule. © PJM Interconnection 2018. All rights reserved. 4 Queue AB1-081 Anaconda – Heartsease 115kV
B. Transmission Owner Facilities Study Results 1. Attachment Facilities The Attachment Facilities include that portion of the interconnecting switching station which is associated solely with the single feed to the generating facilities. The equipment associated with the Attachment Facilities includes the following: Purchase and install: 1. One (1), 115kV, 2000A Center Break Switch 2. Three (3), 115kV, Metering Accuracy CCVT’s 3. Three (3), 115kV, Metering Accuracy CT’s 4. Conductors, connectors, conduits, control cables, foundations, steel structures Purchase and install relay material: 1. One (1), 1109 – 28” Dual SEL-587Z Transmission Bus Panel 2. One (1), 4200 – Bus Differential C.T. M.U. Box 3. One (1), 1421 – Generation/NUG/PJM/IPP Metering Panel 4. One (1), 4524 – Revenue Metering C.T. M.U. Box 5. One (1), 4531 – Generator Interconnect CCVT Potential M.U. Box 6. One (1), 1611 – 28” SEL-451 PMU Panel w/SEL 735/735 7. Two (2), 4541 - Control Cable M.U. Box 2. Transmission Line – Upgrades PJM Network Upgrade #n5478 - Re-arrange Line #80 to loop into and out of the new three breaker Harts Mill 115 kV switching station at structure 80/114 on the Anaconda - Hathway 115kV line #80. The line connection will require the installation of (2) backbone structure. Two Static pole structures will also be installed for the protection of the substation equipment. ESTIMATE INCLUDES COST FOR THE FOLLOWING FACILITIES: 1. Two (2) 115kV Standard Backbone Structures 2. One (1) 115kV DC Engineered Monopole w/foundation 3. Install (1) 1-Phase FDE above Substation Wavetrap inside the fence at Anaconda Substation 4. Install (2) 1- phase FDE above Substation Wavetraps inside the fence at Tarboro Substation 5. Install approximately 0.33 miles of 7#7 ALW static wire. 6. Install approximately 0.07 miles of 3-Phased 1-636 ACSR (24/7) conductor. 7. Transfer (2) 3-phased conductors and (4) shield wire to new structure 3. New Substation/Switchyard Facilities PJM Network Upgrade #n5476 - Build a three breaker Harts Mill 115 kV switching station. The site is located along the ITO’s existing right of way for the Anaconda – Hathaway 115kV line #80. The work required is as follows: © PJM Interconnection 2018. All rights reserved. 5 Queue AB1-081 Anaconda – Heartsease 115kV
Purchase and install the following: 1. Approximately 300’ X 230’ site preparation and grading as required for installation of the switching station (by Sun Energy 1, LLC) not including any added land as required for SWM, etc 2. Approximately 1060 linear FT of 5/8” Chain Link, 12 FT tall, perimeter fence around the station along with the security cameras and integrators (Design 4 Standard). 3. Full substation ground grid as per engineering standards 4. Two (2) 115 kV Light Duty, Single Circuit Backbones 5. One (1) shield wire pole and two span of shield wires 6. Three (3), 115kV, 3000A, 40 kA, SF6 Circuit Breakers 7. Six (6), 115kV, 2000A Center Break Switches 8. Six (6), 115kV, CCVT's, relay accuracy 9. Two (2), 2000A, Vertically Mounted, Wave Traps along with two (2), Line Tuners 10. Nine (9), 90kV MO, 74kV MCOV Station Class Arresters 11. Four (4), 115kV, 100 KVA Power PT's for Station Service 12. Two (2), 115kV, 2000A, 2-Pole Center Break Switches (for PVT’s) 13. One (1), 24' x 40' Control Enclosure 14. One (1), 135VDC, 577Ah Batteries and 50A Charger 15. Oil Containment system for the 115kV PVT’s. 16. Cable Trough, concrete w/cover, 2’ 6’’ wide, approximately 250 FT, with a 20 FT road crossing section. 17. Steel structures as required including switch stands, bus supports, station service transformers, CCVT and wave trap supports 18. Foundations as required including control house, equipment and bus support stands 19. Conductors, connectors, conduits, control cables and grounding materials Purchase and install relay material: 1. Three (3), 1510 – 28” Dual SEL-351-7 Transmission Breaker w/ Reclosing Panel 2. Three (3), 4510 - SEL-2411 Breaker Annunciator 3. Two (2), 1320 – 28” Dual SEL-421-5 DCB Line Panel 4. Two (2), 4506 – 3 Phase CCVT Potential M.U. Box 5. One (1), 1603 – 28” SEL-451 Islanding Control Scheme Panel 6. Two (2), 4000 – Station Service Potential M.U. Box 7. Two (2), 4018 – 500A Station Service AC Distribution Panel 8. Two (2), 4007 – 225A Outdoor Transmission Yard AC NQOD 9. Two (2), 4019 – 225A Three Phase Throwover Switch 10. Two (2), 4016 – 600A PVT Disconnect Switch 11. One (1), 4153 – Wall Mount Station Battery Monitor 12. One (1), 5612 - SEL-3530 Data Concentrator Panel 13. One (1), 1255 – Station Annunciator Panel 14. One (1), 5021 – SEL-2411 RTU Panel 15. One (1), 5609 – Fiber Optic Management Panel 16. Three (3), 4526_A – Circuit Breaker Fiber Optic M.U. Box 17. One (1), 5202 – 26” APP 601 Digital Fault Recorder 18. One (1), 5603 – Station Network Panel 19. One (1), 5616 – Station Security Panel 20. One (1), Telephone Interface Box © PJM Interconnection 2018. All rights reserved. 6 Queue AB1-081 Anaconda – Heartsease 115kV
4. Upgrades to Substation / Switchyard Facilities PJM Network Upgrade #n5477 - Remote protection and communication work. ITO protection requirements to reliably interconnect the proposed generating facility with the transmission system determined that work is required at Anaconda, Hathaway, Tar River, and Tarboro 115kV substations. These costs include the following: Anaconda 115 kV Substation Project Summary Installation of a 800A Wave Trap on Line 55 at Anaconda Substation. Purchase and install: 1. Install one (1), 800A Vertically Mounted Wave Trap 2. Install any foundations, grounding, steel pipe stands, conductor and connectors as necessary Hathaway 115 kV Switching Station Project Summary Installation of a 2000A Wave Trap on Line 80 at Hathaway Substation. Purchase and install: 1. Install one (1), 2000A Vertically Mounted Wave Trap 2. Install one (1), Line Tuning Box 3. Install any foundations, grounding, steel pipe stands, conductor and connectors as necessary Purchase and install relay material: 1. One (1), 1604 – 28” Transmission Islanding Transfer Trip Panel 2. One (1), CS-51C Transfer Trip Set & tuning units 3. One (1), CS-28A Carrier Blocking Set Tar River 115 kV Substation Project Summary Installation of an 800A Wave Trap on the distribution transformer line tap from Line 55 at Tar River Substation. Purchase and install: 1. Install one (1), 800A Vertically Mounted Wave Trap 2. Install any foundations, grounding, steel pipe stands, conductor and connectors as necessary © PJM Interconnection 2018. All rights reserved. 7 Queue AB1-081 Anaconda – Heartsease 115kV
Tarboro 115 kV Substation Project Summary Installation of Wave Traps on Line 55 Terminal at Tarboro Substation. Due to space constraints at the site, three individual wave traps will need to be installed to accommodate the new carrier as required by SPE (what is SPE?) – one Wave Trap at the existing 115kV Capacitor Bank and Transformer #3 Low Side junction, one Wave Trap at the Transformer #4 Low Side and Town of Tarboro DP junction and one at the Distribution Transformer High Side tap. It will be necessary to relocate the existing A Phase Line 55 CCVT to the new Transformer #3/115kV Capacitor Bank junction Wave Trap installation. Purchase and install: 1. Install two (2), 2000A Vertically Mounted Wave Traps 2. Install one (1), 800A Vertically Mounted Wave Trap 3. Install one (1), Line Tuning Box 4. Install any foundations, grounding, conduit, control cable, steel pipe stands, conductor and connectors as necessary Purchase and install relay material: 1. One (1), 4506 – 3 Phase CCVT Potential M.U. Box 2. One (1), 1604 – 28” Transmission Islanding Transfer Trip Panel 3. One (1), CS-51C Transfer Trip Set & tuning units 4. One (1), CS-28A Carrier Blocking Set Direct Indirect Work Description Labor Material Labor Material Total Cost Anaconda $78,612 $14,622 $14,987 $1,994 $110,215 Hathaway $111,326 $75,379 $23,233 $10,779 $220,717 Tar River $75,291 $12,249 $15,392 $1,826 $104,758 Tarboro $203,573 $115,621 $39,714 $16,207 $375,115 Total Remote Relay Upgrades $468,802 $217,871 $93,326 $30,806 $810,805 5. Metering & Communications PJM Requirements The IC will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for IC’s generating Resource. See PJM Manuals M- 01 and M-14D, and PJM Tariff Sections 24.1 and 24.2. Meteorological Data Reporting Requirement The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including: Temperature (degrees Fahrenheit) © PJM Interconnection 2018. All rights reserved. 8 Queue AB1-081 Anaconda – Heartsease 115kV
Atmospheric pressure (hectopascals) Irradiance Forced outage data ITO Requirements Metering and SCADA/Communication equipment must meet the requirements outlined in section 3.1.6 Metering and Telecommunications of ITO’s Facility Interconnection Connection Requirement NERC Standard FAC-001 which is publically available at www.dom.com. At the IC’s expense, the ITO will supply and own at the Point of Interconnection bi-directional revenue metering equipment that will provide the following data: a. Hourly compensated MWh received from the Customer Facility to the ITO; b. Hourly compensated MVARh received from the Customer Facility to the ITO; c. Hourly compensated MWh delivered from the ITO to the Customer Facility; and d. Hourly compensated MVARh delivered from the ITO to the Customer Facility. The IC will supply and own metering equipment that will provide Instantaneous net MW and MVar per unit values in accordance with PJM Manuals M-01 and M-14D, and Sections 8.1 through 8.5 of Appendix 2 to the ISA; The IC will access revenue meter via wireless transceivers or fiber cabling to meter with RS-485 or Ethernet communication port for dial-up reads. IC must provide revenue and real time data to PJM from Interconnection Customer Market Operations Center per “PJM Telemetry Data Exchange Summary” document available at PJM.com. 6. Environmental, Real Estate and Permitting Issues The IC would be responsible for the following expectations in the area of Environmental, Real Estate and Permitting: Suitable Access Road from Substation to a North Carolina Maintained Roadway. Any additional land needed for Storm Water Management, Landscaping, and Wetlands/Wetlands Mitigation. Conditional Use Permit for Substation. Any other Land/Permitting requirements required by the Substation. ITO Real Estate Needs: The substation layout is complete and ITO requires a 300’x 230’ piece of property (title in fee) to build the substation. The property includes the piece of property between the substation and collector station for the strain bus. o ITO requires ownership transfer of the substation site before they start construction. Target for the deed by October 2020. o The size of the station assumes ITO will not need a separate storm water management system for the substation. If the county rules differently then the ITO will need to revisit the land requirements. ITO will need a letter similar to the zoning letter from the county stating that if the solar farm is retired and / or decommissioned the substation will remain. © PJM Interconnection 2018. All rights reserved. 9 Queue AB1-081 Anaconda – Heartsease 115kV
Attachment 1. Site Plan © PJM Interconnection 2018. All rights reserved. 10 Queue AB1-081 Anaconda – Heartsease 115kV
Attachment 2. Single Line © PJM Interconnection 2018. All rights reserved. 11 Queue AB1-081 Anaconda – Heartsease 115kV