Classified as Internal FINANCIAL FORECAST BOARD MEETING David Sidwell, Assietou Diouf 30 July 2020, Virtual Meeting www.gavi.org
Classified as Internal Forecasting…the journey October AFC July AFC ▪ Annual forecasts update • Covid19 impact • Replenishment ▪ Board decisions on Covax Facility July & & Covax AMC December December 2019 Board September ▪ Board decisions 2020 Board on additional Board investments Focus on near term 2020-2021 We are here 2 2021-2025 Board Meeting 30 July 2020
Classified as Internal Main Assumptions Vaccines Medium Severity Scenario Outcome of the HSS Replenishment 6-month acute pandemic period 12-24 months recovery with COVID 19 resurgence in some countries Board 2016-2020 2021-2025 Medium economic downturn and Decisions on social stability with some exceptions Gavi’s Gavi-supported countries US$ 1.375 US$ 1.2 response to substantially affected for 1-3 years billion billion support countries WHO Bottom-up review of each country’s Delays in near-term anticipated disbursements Pulse countries in RI survey outputs 3 Board meeting 30 July 2020
Classified as Internal Impact of COVID-19 pandemic on Gavi’s core mission BREAK-DOWN BY ANTIGEN OF DELAYED INTRODUCTIONS AND CAMPAIGNS DUE TO COVID-19 68 15 39 delayed due 100% = 39 7 8 24 to COVID-19 3YF 1 Campaign 43 Men A 18 3 IMPACT Measles 12 ON 2020 IPV TARGETS 6 6 4 5 9 1 Intro. 25 1 5 7 Typhoi 4 d 4 4 7 3 4 6 6 3 Total Moved Delayed Risk of Delayed Not Completed target to 2021 delay (not Covid affected so far Rota related) MR HPV Of the 39 identified: 30 were in the Dec-19 Board forecast (77%), 23 have approvals (58%) and 15 have been disbursed (38%). Of the 24 Delayed, 19 currently with re-schedule intro dates are within 2020 Data as of 22/06/2020 Source: Gavi Vaccine Launch Database, also available on Country Dashboard; CP COVID Tracker, 22 June 2020 Board meeting 30 July 2020
Classified as Internal Gavi’s immediate response to supporting countries …at a glance Countries Partners Pillar 1: HSS Re-Programming UNICEF Pre Financing Immediate Support • PPE for Country Response • Freight Pillar 2: Supplemental Approaches PEF – TCA and SFA As presented to Maintain, Restore & including: the Board in May Strengthen • PIRI’s Immunisation • Catch up campaigns & June 2020 Services ▪ 2020 Co-Financing Waivers Pillar 3: Responding to Fiscal ▪ 2021 freezing of Eligibility Impact ▪ Prevention of Backsliding in former Gavi eligible 5 countries
Classified as Internal Short Term impact : 2020-2021 Expenditures (in US$ million) Refer Annex 2 2020 150 20 -188 78 15 6 -75 40 -75 2,119 8 -50 -9 2,040 $79m Original Charter PPE Adv. Supplemnt. TCA SFA Co-financing Post Updated Programmatic Delayed Updated Secretariat New forecast Freight Adv. - UNICEF Delivery waiver transition PCV-AMC disruption new intros & cashflow Forecast - UNICEF Actv. (Vax) support assumptions campaigns assumptions 2021 10 10 -20 51 30 -140 1,858 52 -40 1,803 -8 Original Suppl. HSS TCA SFA Freezing Programmatic Delayed Updated VIS Updated New forecast Delivery transition disruption new intro & assumptions Cashflow Forecast Actv. (Vax) phase campaigns assumptions 6 Pillar (a): Immediate Pillar (c): Resp. Updates to Forecast Assumptions Pillar (b): Maintain & Restore Response to Fiscal Impact on Immun. Svcs
Classified as Internal Qualifying Resources Re-forecast (in US$ millions) 2016-2020 • Update of Direct Contributions 281 0 -188 40 -253 • C&I Reserve: updated to reflect 67 changed estimates in expenditure 9,520 9,467 • Removal of allowance for further -$53m contributions (now incl. in direct Original Direct IFFIm - PCV-AMC Inv. Income C&I Reserve Allowance New contributions) forecast Contribs incl. CEPI Proceeds / Other for Further Forecast Contrib 2021-2025 • Figures updated for 4 June 2020 Vaccine Summit 7,837 734 0 0 -58 -7,451 • C&I Reserve: updated to reflect changed estimates in expenditure +$1.06bn 10,540 9,478 • Removal of allowance for further contributions (now incl. in direct Original Direct IFFIm - Inv. Income C&I Reserve Allowance New contributions) forecast Contribs excl. CEPI / Other for Further Forecast Contrib 7 *includes reduction for PCV-AMC (-$187.5m)
Classified as Internal Net Available for Resources Expenditure Future Investment is -0.6% US$ 368m 2016-2020 -0.1% 9,520 9,467 9,110 9,099 303 253 343 65 65 4 300 367 513 496 530 342 665 988 1,020 665 7,469 7,750 7,544 7,515 Dec-19 Board July Re- Dec-19 Board July Re- forecast forecast Direct Contributions Investment Income Programmatic CEPI IFFIm - incl CEPI Available from C&I Partnership Current decisions - July Board 8 AMC Proceeds Allowance for DC Secretariat
Classified as Internal Net Available for Future Resources Expenditure Investment is 2021-2025 +11.2% US$ 1.18 bn 10,540 -0.9% 9,478 125 332 9,444 9,364 413 3 413 2,209 557 557 1,299 1,362 ▪ US$1.18 billion remain available for future investments 7,451 ▪ Revised forecast to 7,874 be presented to the 7,175 7,029 AFC in September 125 390 1,475 37 Dec-19 Board July Re- Dec-19 Board July Re- forecast forecast Direct Contributions Available from C&I Partnership Current Decision - July Board 9 IFFIm Allowance for DC Secretariat Investment Income Programmatic Prov Strategic Inv
Classified as Internal Net Potential Available shows that enough resources are available for future investments $ 368m $ 1.18bn $ 413m $ 1.590bn 2016-2020 2021-2025 September Board Available for future Subject to further updates on Strategic forecasts and donor’s Investments considerations Excludes Covax AMC Contributions & Commitments 10 Board meeting 30 July 2020
Classified as Internal Covax Facility & Covax AMC Set up costs Additional Support required to dedicated to Covax operationalize the COVAX Systems in place to Facility & track and monitor COVAX AMC Resources & ▪ Legal fees expenditures ▪ Consultancy ▪ Surge capacity allocated to the Facility & Covax AMC $ 8.4m FOR DECISION PreFinancing 11 Board meeting 30 July 2020
Classified as Internal Decision 1: Financial Forecast The Gavi Alliance Board: Noted that the Audit and Finance Committee has reviewed the financial implications of the recommendation as set out in Figures 1 of Doc 03 b (Financial Update) to the 23 July 2020 meeting of the Audit and Finance Committee and concluded that the recommendation could be approved by the Gavi Alliance Board in accordance with the Programme Funding Policy 12