EATM 28-01-20/SBA Meeting #1 report - Michael Lazzaroni, EN-EA-DC - CERN Indico
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Liens utiles • Compte-rendu et les précédents: \\cern.ch\dfs\Departments\EN\Groups\EA\Mee tings EA\SBA • Nouveau planning en ligne: https://oss- coordination.web.cern.ch/gantt/latest?baselines =false&dependencies=false&facilities=East%20 Area&forecast=false&potentialConstraints=fals e&scale=week&summary=false
AD – Input Francois AD-CONS: Green light for the extraction of BHW21 from HW tests schedule point of view. An ECR is under preparation. ELENA: All lines installed (except some SEM’s). Cabling started Experiments: ATRAP announced they will not restart in 2021. Reallocation of space between other experiments started.
North Area -Inputs from Sylvain TCC2: BDF T6 removal intervention weekly planning (EN-STI) • Monday 20th: transport robots and equipment, wheels installation + first robot tests (RP + HE + MRO + STI) • Tuesday 21st: robot tests (RP + MRO + STI) • Wednesday 22nd: robot tests (RP + MRO + STI) • Thursday 23rd: top shielding removal, target (80 mSv/h) installation on the support and remove draining screw (RP + HE + MRO + STI) • Friday 24th: unbolt all screws from the downstream flange and remove it (RP + HE + MRO + STI)
North Area - Inputs from Sylvain • PPE172 : • PPX 172 déplacé: Grillage a remettre en place • PPE132 : • PPX 132 a déplacer pour run ion, et blindage de la zone a modifier (layout a faire) • CEDAR-N installation vers January H2-132 (date exacte tbd) ; • PPE112: • Petite modification vacuum H4 (PPE112), deposer de BBS vieux et remplacer par vaccuum (pas urgent, mais a planifier) ; • TCC8: • Ouverture du double mur de séparation to be done (for beam line maintenance XTAX) • TT82-shielding: Relocalisation à prévoir pour un AUG ->EN-EL. Job ouvert pour fabrication – installation des cales pente et modification des chambres a vide. • Zone 118 et 128 (Alexander) : problème, avec faisceau électrons : investigation. ligne vide démontée. Chambres à vide désalignées(?) - M2: Muon_e sur M2 : a faire une estimation du temps d’installation / desinstallation du faisceau M2 depuis XCED 083 a QWL 122 (44m)
New SPS-PPS access control system in NA operational (BA80, 81, TCC8, ECN3) – Inputs Fabrice - All temporary and compensatory measures in place to access TCC8 and ECN3 during installation have been removed - Work to connect to EIS planned in 2020 (March for BA80 & test in April -> access perturbated in April). Planning to be rechecked soon with BE-ICS for BA81, TCC8 & ECN3. F. Gautheron
Lift renovated in bldg. 912 -> access TCC8 • Installation finished in December (20th!) • Door linings to be modified • An electronic card blown up during reception tests. Replaced one later. • Safety: Apave tests OK (Friday 17th) • Commissioning with AS company Monday 20th at the latest . F. Gautheron
NTOF • Inputs Sylvain: • Removal of target shielding progressing well (EN-HE) • Tests of mobile shielding at EHN1 this week (first door Jura side) • 19x 884 Steel blocks cleaning / painting to be done at b.157 by NUVIA
Please take note of the following changes of the gas stop in COMPASS and NA62: Please contact Bastien Rae or David Jaillet for more details
Thank you for your attention!