Corrs Projects Update - Special Edition: ESG - environmental, social and governance

Page created by Lonnie Ruiz
 
CONTINUE READING
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Corrs Projects Update
Special Edition: ESG – environmental, social and governance
Q4 2021

corrs.com.au
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Q4 2021

     Welcome to the latest edition of
     Corrs Projects Update: Special
     Edition: ESG – environmental, social
     and governance
     Welcome to the latest edition of Corrs Projects Update.
     This publication provides a concise review of, and commercially focused commentary on,
     the latest major judicial and legislative developments affecting the Australian construction
     and infrastructure industry.
     In this special edition, we have a particular focus on ESG.
     The rise of ESG over the last 12 months has been driven by five major trends: the
     accelerating capital flows to ESG funds and businesses, the global drive to net zero, a move
     from voluntary principles and guidelines to mandatory regulation, shifting investor
     expectations and increasing shareholder activism, and a heightened customer and
     employee sensitivity to environmental and social issues.
     As capital and business opportunities are increasingly flowing to responsible businesses
     that are seen to hold themselves accountable by considering their environmental and social
     impacts, and governing with integrity and transparency, we continue to work with clients to
     build the best ESG risk frameworks across their operations and supply chains.
     This edition of the Corrs Project Update includes the usual case notes on important judicial
     decisions from across Australia, and also a focus to some of ESG issues as we explore:
     •    the dangers of greenwashing – as regulators shareholders and activists increasingly use
          litigation to hold companies to account;
     •    whether arbitration may provide the answer to ESG disputes in the future; and
     •    a practical guide to key climate change considerations for supply chains.
     We hope that you will find this publication both informative and thought provoking.

     Editors:
     Andrew McCormack                            Wayne Jocic
     Partner                                     Consultant

            Insights
            Corrs regularly publishes insight articles which consider issues affecting
            various sectors of the domestic and global economies. We have included
            at the end of this Update links to some of our recent articles on issues
            affecting the construction industry.
            The information contained in this publication is current as at December 2021.
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Q4 2021

     Contents

          ESG disputes: is arbitration the answer?		                                             6

          The dangers of greenwashing: it’s not easy being green		                               9

          A practical guide to key climate change considerations for supply chains		            11

          Termination for convenience: when and is it free? 		                                  12

          Commonwealth		14
          High Court News		                                                                     15

          New South Wales		                                                                     16
          Jabbcorp (NSW) Pty Ltd v Strathfield Golf Club [2021] NSWCA 154		                     17

          Queensland		19
          Cheshire Contractors Pty Ltd v Civil Mining & Construction Pty Ltd [2021] QCA 212		   20

          Tasmania		22
          Hansen Yuncken Pty Ltd v Parliament Square Hobart Landowner Pty Ltd [2021] TASFC 11   23

          Western Australia		                                                                   25
          Chevron (TAPL) Pty Ltd v Pilbara Iron Company (Services) Pty Ltd [2021] WASCA 193		   26
          Chevron Australia Pty Ltd v CBI Constructors Pty Ltd [2021] WASC 323		                28

          Other		30
          Triple Point Technology, Inc v PTT Public Company Ltd [2021] UKSC 29		                31

          Corrs Insights		                                                                      34

          Contacts		36

4
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Corrs Projects Update

                   5
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Q4 2021

     Feature article

     ESG disputes: is arbitration
     the answer?

                         To say that businesses are witnessing an
                         ‘ESG revolution’ is not hyperbole. Active
                         engagement with ESG issues is no
                         longer a choice; ESG impacts are
                         increasingly permeating public and
                         private decision making across all sectors
                         of the economy, as recent discussions
                         around the COP26 climate change
                         conference have shown. As outlined in
                         Corrs’ ESG Guide for General Counsel,

                            “The message from corporate
                            stakeholders is clear: companies must
                            rise to meet demands for ESG
                            accountability and transparency with
                            proper risk management, due diligence
                            and reporting, or risk shareholder and
                            employee activism, investor
                            divestment and exclusion.”

                         Those demands are producing new forms of risk (requiring
                         allocation) that businesses need to grapple with in their
                         operations and contractual relationships. In turn, these new
                         forms of risk are and will continue to give rise to disputes.
                         In that context, we ask: what role can arbitration play in
                         resolving ESG-related disputes?

6
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Corrs Projects Update

In this Insight, we explore this question from two                       dispute. For example, if the dispute is environmental or if it
perspectives. We first consider contractual disputes and the             involves new technology solutions, an arbitrator with
extent to which arbitration is suitable for resolving such               expertise in the technical issues can be appointed to hear
disputes on projects overlaid with ESG requirements.                     the dispute and bring their specialist knowledge to its
Second, we discuss the evolving ESG considerations that                  resolution. Moreover, arbitration can produce a final
businesses engaged in projects overseas should bear in                   resolution faster than the time it ordinarily takes to litigate a
mind to ensure that they are able to protect their interests             complex technical dispute in court.
through arbitration.                                                     With the commitments flowing from COP26 fresh in mind,
                                                                         many expect to see States’ climate policies attempt to
The role of commercial arbitration in                                    reshape the global energy industry. We may see an increase
                                                                         in disputes under ‘change in law’ clauses, as law and
resolving ESG-related contractual                                        regulation change to meet new climate policies. Given the
disputes                                                                 appreciation of different legal systems that comes with
                                                                         international arbitration practitioners, they are well suited to
Contracts are the ultimate risk allocation device. ESG risk              grappling with these disputes.
allocation too can be provided for by contract. Parties are
                                                                         Arbitration is also well suited to dealing with disputes that
increasingly asked to warrant that their activities will be
                                                                         give rise to high-tech and complex engineering issues on
responsible, that they will take steps to eliminate any
                                                                         major projects because it allows parties to agree on
modern slavery in their supply chains, and that they will
                                                                         procedures tailored to each individual dispute.
conduct their operations in line with emissions reduction
commitments. At the same time, some financiers are                       There are some risks involved in taking disputes involving
insisting on conditions precedent to finance requiring that              ESG clauses to arbitration. The strategic imperative behind
the financier be satisfied with the borrower’s ESG                       some ESG action is to attract attention or public scrutiny,
compliance.                                                              and plaintiffs see open court as a better way to achieve that
                                                                         end. This has in turn driven some large entities to introduce
Just as the uptake of ESG requirements in commercial
                                                                         arbitration clauses in their consumer contracts to preserve
transactions increases, so does the risk of dispute involving
                                                                         confidentiality. Recent US experience shows that this
those requirements. That risk is particularly pronounced
                                                                         approach runs the risk of plaintiff law firms ‘book building’
because of the tension between certainty and breadth in
                                                                         (that is, signing up individual claimants) and commencing
drafting ESG clauses.
                                                                         mass arbitrations, and it may also incite a public backlash
The concept of an ‘ESG risk’ is an umbrella term used to                 against what some see as a business using the
describe environmental, social or governance factors which               confidentiality of arbitration to hide its misdeeds.
may impact on (or present an opportunity for) the entity.1
                                                                         That backlash may be warranted where public policy
What falls inside or outside of the umbrella is not clearly
                                                                         concerns are in play but it is unlikely to detract from the
defined. As a result, any clause using the umbrella term is
                                                                         appeal of arbitration for resolving the majority of ESG
ripe for dispute.
                                                                         related disputes. The qualities of confidentiality, party
On the flip side, as clauses become more particular, the risk            autonomy and efficiency of arbitration mean that it will
that factors will be missed increases. One way drafters are              continue to be the forum of choice for many contracts that
managing this risk is to use a broad term and then give one              include ESG clauses. There will be an accordant rise in
party a contractual discretion. For example, one party may               expertise that arbitrators can bring to resolving ESG-related
need to satisfy the other ‘acting reasonably’ about its ESG              disputes and from which parties can draw when selecting
compliance. Risk lurks in these clauses too. A dissatisfied              arbitrators to hear their disputes.
party may challenge the exercise of the contractual
discretion, including by saying that, for example, the
decision maker had regard to irrelevant material.
If the parties fall into dispute on these issues, those
disputes can be dealt with through arbitration. Arbitration
provides a private and confidential way to resolve disputes.
Administered properly, it can be quicker and more efficient
than other methods of dispute resolution, including by
bringing proceedings in court. The parties can moreover
appoint arbitrators who are specialists in the issues in

1   In Corrs’ ESG Guide for General Counsel, we note that the concept of an ‘ESG risk’ is an umbrella term used to describe environmental,
    social or governance factors which may impact on (or present an opportunity for) the entity.

                                                                                                                                              7
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Q4 2021

     ESG considerations relevant to cross-                                    In one case involving an arbitration commenced by Spanish
                                                                              company Urbaser S.A. against Argentina, that arose out of
     border projects                                                          Argentina’s termination of a concession for water and
                                                                              sewerage services, Spain was allowed to pursue a
     Contractors involved in cross-border projects should be
                                                                              counterclaim against the claimant alleging that the
     mindful of how the increase in focus on ESG is changing
                                                                              claimant’s administration of the concession had breached
     their risk exposure when operating overseas, and how a
                                                                              international human rights obligations.2
     failure to comply with ESG requirements may come to
     affect their rights, in particular rights afforded under                 While the counterclaim was not ultimately successful, the
     international investment agreements.                                     case signals the willingness of tribunals to entertain
                                                                              ESG-related counterclaims.
     By way of context, many Australian companies with assets
     overseas benefit from legal protections available under                  Parties that fail in their ESG-related obligations can also face
     investment agreements between Australia and countries                    a reduction in damages to which they may otherwise be
     across Africa, South America, Europe and South-East Asia.                entitled – for example, if by failing to comply with social and
     These treaties protect individuals and companies from                    human rights obligations their ability to generate future
     certain kinds of government-mandated measures, typically                 income on a project is seen as too uncertain, or even if their
     in the form of changes in laws or regulatory action, that may            conduct is seen as having contributed to their losses.
     affect their assets - including contractual rights. Often these          In an arbitration between the Canadian mining company Bear
     treaties allow companies to commence arbitration                         Creek and Peru over a silver ore project that was unable to
     proceedings directly against the government of the state in              proceed to the exploration phase due to local community
     which the asset is located (i.e. the ‘Host State’) to seek               opposition, the tribunal awarded a significantly reduced
     damages for unlawful government action.                                  quantum of damages because the manifest failure to obtain a
     The ability to invoke investment treaty protections can be a             social license to operate (among other things) made it
     meaningful risk mitigation tool for Australian companies                 impossible to assess expected profitability of the project.
     undertaking commercial activities overseas. Indeed, there                Moreover, one of the arbitrators considered that the
     have been hundreds of arbitrations commenced by                          damages award should have been further reduced on
     individuals and corporations under various investment                    account of the claimant’s contributory fault, concluding that
     treaties worldwide and across a range of sectors – including             the community opposition to the project was the result of
     resources and construction – in circumstances where their                the claimant’s failure to engage in public consultations.3
     cross-border investments of capital and resources are
                                                                              Additionally, states increasingly see investment treaties as
     adversely affected by action taken by the Host State.
                                                                              policy tools that can contribute to their ability to meet
     These protections are increasingly being interpreted through             emissions reduction targets and promote responsible
     the ESG lens and newly-negotiated investment treaties are                business conduct. Some newly negotiated and model
     re-allocating the risk of foreign business operations that are           investment treaties already require investors to comply with
     not conducted responsibly. We note here a few ways in                    human rights due diligence obligations and conduct their
     which this shift manifests itself.                                       business responsibly. For example, the Morocco-Nigeria
     As an example, companies and individuals that otherwise                  Bilateral Investment Treaty (BIT) requires projects to be
     meet the requirements to be afforded protection under                    assessed for their environmental and social impacts and to
     investment treaties may lose the ability to rely on those                comply with international environment protection standards.
     protections if they fail to respect ESG requirements. One                The Netherlands Model BIT requires that individuals and
     reason for this is that there is either an explicit or an implicit       companies comply with the laws and regulations on human
     ‘legality requirement’ in investment treaties that conditions            rights in force in the country in which they invest, and the
     a party’s right to seek compensation on its compliance with              Indian Model BIT expressly contemplates a reduction in
     the Host State’s domestic legislation, which increasingly                damages payable where the foreign investor has caused
     mandates compliance with components of ESG.                              harm to the local community or environment.

     Further, on a number of recent occasions investment                      Australian companies operating overseas that rely on
     treaties have been interpreted to allow the Host State faced             investment treaty protections to de-risk their cross-border
     with a treaty claim by a foreign corporation to raise a                  operations and investments should follow these
     counterclaim and seek compensation for ESG-related harm                  developments closely. We expect that international treaties
     done by the corporation.                                                 will increasingly mandate that business is done responsibly
                                                                              before individuals and corporations can benefit from the
                                                                              protections they afford.

     2    Urbaser S.A. and Consorcio de Aguas Bilbao Bizkaia, Bilbao Biskaia Ur Partzuergoa v. The Argentine Republic, ICSID Case No. ARB/07/26.
     3    Bear Creek Mining Corporation v. Republic of Peru, ICSID Case No. ARB/14/2, Award of 30 November 2017, Partial Dissenting Opinion by
          Philippe Sands.

8
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Corrs Projects Update

Feature article

The dangers of greenwashing:
it’s not easy being green

With widespread consensus on the need
to reach net zero by 2050, companies
have come under increasing pressure
from regulators, investors and consumers
to embed more robust environmental risk
management and disclosure practices
and to progressively ‘green’ their
business and supply chains.

Demands for stronger corporate action on climate change
are likely only to increase into the future. And, with
mounting evidence of the material financial risks posed by
climate change, the business case for going green could not
be clearer. It is no coincidence that the number of major
companies that have committed to reaching net zero has
more than trebled in the past year alone.
There are clear commercial benefits to ‘going green’, from
both a financial and reputational perspective. But such
moves are not without risk. Companies that exaggerate or
misrepresent their ‘green’ credentials expose themselves to
the risk of ‘greenwashing’ claims under the Australian
Consumer Law, the Australian Securities and Investments
Commission Act 2001 (Cth) and financial reporting rules.

                                                                                 9
Corrs Projects Update - Special Edition: ESG - environmental, social and governance
Q4 2021

     What is ‘greenwashing’?                                           in 2021, the Australasian Centre for Corporate Responsibility
                                                                       filed a greenwashing claim, under the Australian Consumer
     ‘Greenwashing’ is a term used to describe a wide range of         Law, against a major oil and gas company in Australia in
     actions which exaggerate or misrepresent a company’s              relation to its representations of producing clean energy and
     ‘green’ credentials.                                              pathway to reach net zero.
     The following types of company communications are                 Overseas, a number of proceedings have been brought
     particularly susceptible to claims of ‘greenwashing’:             against Exxon Mobil Corp (in Massachusetts and more
     •    Climate-related disclosures – financial and other            recently, in New York), Shell Oil Company, BP America Inc
          disclosures regarding exposure to climate risk;              and Chevron on the basis of misleading climate-related
     •    Broad corporate goals – representations in relation to       representations. More recently, in September this year,
          drivers such as:                                             shareholders launched a class action in the US against one
                                                                       of the world’s largest oat milk companies, Oatly, seeking
          –   alignment with Paris Agreement goals;
                                                                       damages said to result in part from misleading statements
          –   achievement of net zero or other emissions
                                                                       about sustainability. These include that the conversion from
              reductions targets by a specified date; and
                                                                       cow’s milk to Oatly results in 80% fewer carbon emissions,
     •    Green marketing – product and brand marketing which          79% less land usage, and 60% less energy use.
          makes representations about products or practices
          being environmentally friendly, sustainable or ethical.
                                                                       Risks
     If not carefully managed, such communications have the
     potential to become misleading or deceptive, or a breach of       As regulators, investors and consumers become more
     relevant reporting obligations under securities law.              environmentally sophisticated, such liability risks are only
                                                                       likely to grow.
     The rise of ‘greenwashing’ claims                                 ASIC has acknowledged that climate change is a systemic
                                                                       risk for the financial system and that it will play a role in
     Legal challenges to corporate ‘greenwashing’ are already afoot.   ensuring that what companies say about their plans to
     In December 2019, in response to action by the Australian         manage climate change matches what they do in practice.
     Competition and Consumer Commission, the Federal Court            More than ever, it is important for companies to assess
     ordered the highest penalty on record against Volkswagen          climate risks, how their business will manage those risks to
     ($125 million) for false representations about the                ensure compliance with all legal obligations and carefully
     compliance of 57,000 vehicles with Australian diesel              manage communications about those risk management
     emissions standards. On 12 November 2021, the High                plans and broader ‘green’ credentials.
     Court denied Volkswagen leave to appeal the penalty. Late

10
Corrs Projects Update

Feature article

A practical guide to key climate change
considerations for supply chains

Climate change has rapidly transformed supply chains and
project management. To address supply chain risk and build
resilience, organisations need to understand and consider
the key risks to supply chains and be proactive and
innovative in their approach going forward.
Whilst it remains unclear where this transformation will
ultimately lead, organisations need to consider that a
traditional approach to supply chain arrangements may not
be adequate into the future, particularly for arrangements
over the medium to long term. New approaches should be
explored, with careful consideration given to legal and
contractual, technical, financial, policy and risk issues.
Supply chains are also increasingly affected by changing
stakeholder requirements and expectations relating to
climate change and environmental factors. This is often
driven by customer, consumer and supplier concerns
                                                               Corrs has published A practical guide to key climate
relating to their own environment, social and governance
                                                               change considerations for supply chains to help
(ESG) objectives. Australia’s commitment to the Glasgow
                                                               organisations determine if a new approach to supply chain
Breakthroughs on near zero emission steel will increase
                                                               arrangements is needed. Key factors for consideration
this momentum.
                                                               include: the nature of the product supplied, the value at risk,
These new pressures being applied by climate change impact     and the time frames over which particular contracts operate.
key contractual matters in many different supply               If an organisation decides that no change is required, this
arrangements, including products and materials, and services   decision must be made consciously, rather than by default.
ranging from professional services, to design, construction,
                                                               As we move into a future where the legal approach to
operation and maintenance. These arrangements require the
                                                               supply chain arrangements remains unclear and it is
consideration from the perspective of both the suppliers,
                                                               essential for organisations to maintain open communication
contractors and sellers (Sellers), as well as principals,
                                                               between the legal and non legal areas of their business.
customers and clients (Purchasers).
                                                               Organisations will need to work collaboratively with contract
                                                               counter parties and the industry to develop solutions, as the
                                                               ability to think creatively, respond adroitly, acknowledge
                                                               mistakes and reflect on lessons learned will be important
                                                               for long term success.
                                                               You can access a copy of the Guide here.

                                                                                                                                 11
Q4 2021

     Feature article

     Termination for convenience:
     when and is it free?

                     Key takeaways                                                                    Keywords
                     Termination for convenience clauses have drawn significant media                 termination for convenience
                     attention given the Commonwealth’s decision to terminate the Future              clauses
                     Submarine Program contract with the Naval Group.
                     A poorly drafted termination for convenience clause has the
                     potential to be unenforceable. Potential traps include unfair contract
                     terms legislation, lack of consideration, good faith and the
                     calculation of compensation.

     Background                                                               Should the other party be
     As the name suggests, exercising a termination for
                                                                              compensated where a right to
     convenience clause does not require the terminating party                terminate for convenience has been
     to prove any breach of obligation by the terminated party.
                                                                              exercised?
     These clauses are common in contracts, especially in large
     procurement projects involving governments.                              While parties are generally free to strike whatever bargain
                                                                              they choose, there are some limitations on the
     Despite the common nature of such clauses, there is limited
                                                                              enforceability of contracts in circumstances where a
     guidance as to whether the terminated party must be
                                                                              contract contains a right to terminate for convenience.
     compensated and the amount of compensation (if any) on a
     termination for convenience is also often unclear.
     A poorly drafted termination for convenience clause has the              Unfair contract terms
     potential to be unenforceable.
                                                                              Particular caution should be taken when negotiating an
     We take a look at the most recent commentary and judicial                exclusive right to terminate for convenience without
     considerations and set out some matters that are relevant                compensation being payable where the unfair contracts
     to the negotiation of a termination for convenience clauses.             regime applies.1

     1    The current regime applies to standard form contracts entered into or renewed on or after 12 November 2016, where:
          • it is for the supply of goods or services or the sale or grant of an interest in land;
          • at least one of the parties is a small business (employs less than 20 people, including casual employees employed on a regular and
             systematic basis); and
          • the upfront price payable under the contract is no more than $300 000 or $1 million if the contract is for more than 12 months.

12
Corrs Projects Update

                                                                     Good faith
                                                                     The law in Australia is unsettled as to whether a duty of
                                                                     good faith can be implied into a contract. Some contracts
                                                                     expressly include such an obligation.
                                                                     The duty of good faith can be relevant in the context of a
                                                                     termination for convenience.
                                                                     The NSW Supreme Court has taken the view that a breach
                                                                     of the duty of good faith would be unlikely to occur where
                                                                     an entitlement to terminate for convenience is accompanied
                                                                     by an obligation to pay fair (as agreed between the parties)
                                                                     compensation.5

In ACCC v Servcorp Ltd,2 one party could terminate for
convenience without paying compensation while the other
                                                                     Calculation of compensation
party had no such rights at all. This gave rise to a significant     If it is agreed that compensation is to be payable in the
imbalance in the parties’ rights and obligations and the clause      event of termination for convenience, the next question is
was deemed to be an unfair contract term and was void.               how that compensation is calculated.
Although the regime does not apply to all contracts,                 There are many possibilities, including compensating the
upcoming amendments will broaden the scope of the unfair             terminated party for one or more of the following:
contract term provisions and introduce civil penalties and
                                                                     •   works completed up to termination, including works that
further remedies.
                                                                         have not been invoiced for;
                                                                     •   demobilisation costs;
Consideration                                                        •   contribution to overheads and profit margin;

There is a difference between an agreement that provides             •   compensation for lost profit; and
an obligation to compensate for work done up until                   •   compensation for a forward commitment or liability to
termination, from an agreement that does not provide for                 third parties (including, for, example subcontractor
any compensation at all.                                                 break costs).

To ensure formation and enforceability of a contract,
obligations must be supported by ‘consideration’ (which              Conclusion
usually takes the form of an obligation to pay money and
provide products or services in return).                             Ultimately, the commercial viability of the agreement will
                                                                     likely depend on whether the parties are prepared to accept
Courts in the United Kingdom have taken the view that a
                                                                     the risk of potential termination without fault, and an
termination for convenience clause that does not provide
                                                                     entitlement to compensation may reduce the risk of loss.
compensation for losses (including loss of profit and
overheads) “risk[s] being treated as … unenforceable as              However it is a balancing act, as the compensation should
unconscionable.”3 However, the Australian Federal Court in           be proportionate to the potential benefits of being able to
Anderson Formrite Pty Ltd v Baulderstone Pty Ltd (No 7),4            terminate for convenience. Therefore, parties should
held that a $1 termination fee ensured the contract was              carefully consider the drafting of termination for
supported by consideration.                                          convenience clauses to ensure they reflect the commercial
                                                                     bargain and are enforceable. Clarity as to the losses to be
Consequently, inclusion of a termination payment
                                                                     covered through the compensation mechanism is critical.
obligation will help avoid a dispute as to whether an
agreement containing a termination for convenience                   Note: this article was first published on the Corrs website
clause is void for a lack of consideration. In some                  on 21 October 2021: https://www.corrs.com.au/insights/
circumstances, payment for work completed up to                      termination-for-convenience-when-and-is-it-free
termination may be sufficient consideration.

2   Australian Competition and Consumer Commission (ACCC) v Servcorp Ltd [2018] FCA 1044.
3   Abbey Developments Limited v PP Brickwork Ltd [2003] EWHC 1987 (TCC).
4   [2010] FCA 921.
5   Leighton Contractors Pty Ltd v Arogen Pty Ltd [2012] NSWSC 1370.

                                                                                                                                     13
Q4 2021

     Commonwealth

14
Corrs Projects Update

High Court News

               Key takeaways                                                                  Keywords
               In recent months, the High Court of Australia has declined to hear             special leave determinations
               appeals in two construction cases. One related to the ‘excluded
               amounts’ regime under Victoria’s security of payment legislation.
               The other concerned the prevention principle.

Background                                                             Our Insight on the Court of Appeal’s decision can be found
                                                                       here and the special leave transcript here.
Litigants do not have an automatic right of appeal to the High
Court of Australia. The High Court sifts cases to determine
                                                                       Bensons Property Group Pty Ltd v Key Infrastructure
whether to grant special leave to appeal. In recent times, most        Australia Pty Ltd
applications for special leave have been rejected on ‘the              In Bensons Property Group Pty Ltd v Key Infrastructure
papers’, without oral argument.                                        Australia Pty Ltd [2021] VSCA 69, the Victorian Court of Appeal
In the cases discussed below, a small bench of the High Court          held that:
heard oral argument to determine whether the matters should            •   the prevention principle is only enlivened where the alleged
proceed to a full hearing.                                                 act of prevention is a breach of an express or implied
                                                                           contractual term; and
Yuanda Vic Pty Ltd v Façade Designs International
                                                                       •   a party that seeks to rely on the prevention principle on the
Pty Ltd [2021] VSCA 44
                                                                           basis the other party has breached an implied duty to
The Victorian Court of Appeal held that courts could not give              cooperate must establish, on the balance of probabilities,
judgment where the relevant payment claim contained an                     that it would have been able to perform its obligations but
‘excluded amount’. This relied on a strict interpretation of               for the wrongdoing party’s uncooperative conduct.
section 16(4)(a)(i) of the Building and Construction Industry
                                                                       The High Court has not heard a case concerning the prevention
Security of Payment Act 2002 (Vic).
                                                                       principle. Arguably, this case provided a rare opportunity to
The High Court has previously decided security of payment              explore not only the operation but the juridical foundation of
cases on reference dates1 and on rights to judicial review of          the prevention principle.
adjudication determinations.2 The central issue in this case,
                                                                       Keane and Gleeson JJ disagreed, holding:
while important, was perhaps more parochial.
                                                                           “The appeal foreshadowed by this application for special
Keane, Gordon and Edelman JJ declined to grant special leave
                                                                           leave to appeal is not a suitable vehicle for consideration by
to appeal, reciting a familiar formulation:
                                                                           this Court of the prevention principle and, further, it does
    “The appeal foreshadowed by this application for special               not enjoy sufficient prospects of success to warrant the
    leave does not enjoy sufficient prospects of success to                grant of special leave to appeal. The application is
    warrant the grant of special leave to appeal. The application          dismissed with costs.”
    is dismissed with costs.”
                                                                       Further information on the Court of Appeal’s decision is
                                                                       provided in our podcast and in the special leave transcript.
1   Southern Han Breakfast Point Pty Ltd (in Liquidation) v Lewence Construction Pty Ltd [2016] HCA 52.
2   Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; Maxcon Constructions Pty Ltd v Vadasz [2018] HCA 5.
                                                                                                                                            15
Q4 2021

     New South Wales

16
Corrs Projects Update

Jabbcorp (NSW) Pty Ltd v Strathfield Golf Club
[2021] NSWCA 154

              Key takeaways                                                            Keywords
              Clauses dealing with excluded works must be carefully drafted for        excluded works
              certainty in determining what work falls outside the contract sum.

Background                                                       Decision
In late 2016, Strathfield Golf Club (Club) engaged Jabbcorp      In the Court of Appeal, Leeming JA gave the principal
(NSW) Pty Ltd (Jabbcorp) to design and construct a new           judgment, with which Basten JA agreed. Emmett AJA also
clubhouse, access road and associated works on land owned        agreed, providing supplementary reasons.
by the Club. A dispute arose about “drainage, pavement and       Their Honours concluded that the works in question were
other works near the greenkeeper’s shed” and “works on           outside the construction boundary of the ‘site’ (as that term
golf course and outside the construction boundary”.              was defined in the Contract) for the purposes of paragraph
Jabbcorp claimed that these works were ‘Excluded Works’          (u) under the definition of Excluded Works. When
as that term was defined in the parties’ contract and that       interpreting the ambit of the term Excluded Works, the
Jabbcorp was therefore entitled to an extra $700,000. The        Court followed the approach taken in XL Insurance Co SE v
Club argued the works were covered by the contract sum.          BNY Trust Company of Australia Ltd:

Relevant clauses of the contract                                     “… the starting point … must be the literal or
                                                                     grammatical meaning of the exclusion. It is then
The relevant construction contract provided that:
                                                                     necessary to consider the legal meaning of the
Clause 4: Contract sum means the sum set out in the                  exclusion, and then apply the legal meaning to the facts”.
Formal Instrument of the Agreement but excluding: …
                                                                 The Court also noted that the headings under Excluded
   (b) The cost of the Excluded Works and works associated       Works refer explicitly or implicitly to the possibility of doing
       with the Excluded Conditions …                            something extra. Jabbcorp relied on the word ’including’ in
Excluded Works: Notwithstanding any other clause means           paragraph (u) of the definition of Excluded Works to argue
the following works which do not form part of the Contract       that since the variations were both “on the golf course” and
Sum and if required to be carried out, will constitute a         “outside the construction boundary of the Site”, they should
variation under this Contract: …                                 be characterised as Excluded Works.

   (u) Any works required on the golf course and outside         The key requirement of the definition of Excluded Works
       the construction boundary of the Site, including if       was that the works must “not form part of the Contract
       those requirements are pursuant to the Development        Sum” and “if required to be carried out, will constitute a
       Consent …                                                 variation under this contract”.

The question to be answered was: did the relevant work fall      Leeming JA (with whom Basten JA and Emmett AJA
within the definition of Excluded Works, and is Jabbcorp         agreed) concluded that the works in question did not
entitled to a variation?                                         constitute Excluded Works, and therefore the Club’s
                                                                 interpretation was correct.

                                                                                                                                    17
Q4 2021

     Reasoning
     The Court followed the objective test set out in the High
     Court’s decision in Toll (FGCT) Pty Ltd v Alphapharm Pty
     Ltd, by determining how a reasonable person would
     understand the language in which the parties had
     expressed their agreement.
     First, the Excluded Works clause must be read as a whole.
     Many of the other Excluded Works paragraphs referenced
     Jabbcorp completing work over a specific measurement, or
     doing “something extra”, indicating that a clear variation was
     central to work being classified as Excluded Works. The
     Court found that Jabbcorp was attempting to take the
     words in paragraph (u) and extrapolate them to all 37
     paragraphs under Excluded Works, instead of reading the
     paragraphs as a whole and applying the broader
     interpretation to paragraph (u).
     Second, it was held that the works in question were always
     required to be done. Therefore, Jabbcorp’s construction was
     problematic, as it would impute the parties to have agreed
     that the works in question could constitute both ‘works
     undertaken for a fixed price’ under clause 2 of the contract
     and Excluded Works.
     Third, the disputed works specifically referenced work
     required by the Development Consent (relating to included
     works) pursuant to conditions which were not Excluded
     Conditions. Therefore, they could not be considered
     Excluded Works.
     Finally, Jabbcorp was not entitled to additional payment for
     these works, as a reasonable person would interpret the
     Contract Sum to mean “the maximum the Club would have
     to pay for Jabbcorp performing the works it had promised”.
     Their Honours dismissed the appeal with costs.
     https://www.caselaw.nsw.gov.au/
     decision/17ad1871762dfec34ca52f07

18
Corrs Projects Update

Queensland

                               19
Q4 2021

     Cheshire Contractors Pty Ltd v Civil Mining &
     Construction Pty Ltd
     [2021] QCA 212

                   Key takeaways                                                                Keywords
                   An arbitration agreement included in a contract need not exhaustively        arbitration agreements
                   spell out the defined legal relationship to which it applies. On ordinary
                   principles of contractual interpretation, the arbitration agreement will
                   be interpreted in its contractual context.
                   Needless to say, precision in the drafting of arbitration agreements
                   can help to avoid disputes.

     Background                                                          Issues
     This dispute arose out of a roadworks project in                    The central issue was whether there was an arbitration
     Queensland. The Queensland Department of Transport and              agreement in respect of a ‘defined legal relationship’?
     Main Roads engaged Civil Mining & Construction Pty Ltd              Section 7(1) of the Commercial Arbitration Act 2013 (Qld)
     (CMC). CMC in turn subcontracted some of the works to               defines arbitration agreements as:
     Cheshire Contractors Pty Ltd (Cheshire).
                                                                             “… an agreement by the parties to submit to arbitration
     The subcontract included a page-long dispute resolution                 all or certain disputes which have arisen or which may
     clause. Ultimately, ‘disputes or differences arising between            arise between them in respect of a defined legal
     the parties’ were referred to arbitration. Typically, such              relationship, whether contractual or not.”
     disputes or differences are qualified, for example as
                                                                         Cheshire argued that there was no arbitration agreement
     disputes or differences arising out of or in connection with
                                                                         because the relevant clause did not define the legal
     the contract or the project. Here, there was a bare reference
                                                                         relationship to which it applied. To be clear, Cheshire’s
     to ‘disputes or differences arising between the Parties’.
                                                                         position was that the definition of the legal relationship:
                                                                             “… requires - literally - a level of precision and specificity
                                                                             within the language of an otherwise compliant
                                                                             arbitration agreement that cannot be satisfied by mere
                                                                             implication or ‘vague allusion’.”
                                                                         This argument seemed to require interpretation of the
                                                                         dispute resolution clause in isolation, without considering
                                                                         the contract as a whole.

20
Corrs Projects Update

Decision
The Court of Appeal rejected Cheshire’s argument and
upheld the decision of the trial judge, Henry J. In the Court
of Appeal, Bowskill SJA gave judgment, with Morrison and
Mullins JJA agreeing. Her Honour’s 24-paragraph judgment
was unambiguous:
   “… there must be a defined legal relationship - in the
   sense of an identifiable legal relationship giving rise to
   legal remedies - but it strains the language of section
   7(1) to construe the words as requiring that the
   [arbitration] agreement itself must define that legal
   relationship.”
As is clear from this quote, Bowskill SJA supported authority
to the effect that the language in section 7(1) is directed to
excluding disputes in which no legal remedy is available. It
does not require express definition of the legal relationship.
Even if it were required, the legal relationship in question
could be discerned from the arbitration agreement, which
was contained in the dispute resolution clause in the
subcontract.
The Court of Appeal, and the trial judge, swiftly rejected
Cheshire’s central argument. Nonetheless, it might have
been possible to avoid the argument entirely if the
arbitration agreement had expressly specified the scope of
‘disputes or differences’ to which it applied.
https://www.queenslandjudgments.com.au/caselaw/
qca/2021/212/pdf

                                                                                   21
Q4 2021

     Tasmania

22
Corrs Projects Update

Hansen Yuncken Pty Ltd v Parliament Square
Hobart Landowner Pty Ltd
[2021] TASFC 11

              Key takeaways                                                              Keywords
              This case supports the view that a party may call on an unconditional      performance bonds
              performance bond even where the underlying contract - typically a
              construction contract - does not provide an express right to call on the
              performance bond. The question remains controversial.

Facts                                                              Defects bond
                                                                   The defects bond was dealt with separately in subclause
This dispute arose out of the Parliament Square                    6.6. Clause 6.4, which gave the Principal an express
development in Hobart. Parliament Square Hobart                    entitlement to call on the construction-phase bonds, did not
Landowner Pty Ltd (Principal) engaged Hansen Yuncken Pty           expressly cover the defects bond.
Ltd (Contractor) to build one stage of the works.
                                                                   At trial, the Contractor unsuccessfully sought an injunction
The contract required the Contractor to provide security. The      to restrain the Principal from calling on the defects bond.
arrangements were a little more complex than usual.
                                                                   Could the Principal call on the defects bond?
Construction-phase bonds
                                                                   Martin AJ gave judgment for the Full Court, with Wood
Before financial close, the Contractor was required to             and Geason JJ agreeing. The Court dismissed the
provide:                                                           Contractor’s appeal.
•   a performance bond from a bank (i.e. a ‘bank guarantee’)
    for 5% of the contract sum; and                                There was an express contractual right
•   a performance bond from an insurance company for               Martin AJ emphasised that the issue was ultimately an
    2.5% of the contract sum.                                      exercise in contractual interpretation. His Honour
                                                                   concluded that:
Clause 6.4 of the contract gave the Principal an express
entitlement to call on these performance bonds in four                 “Although clause 6 does not, in specific terms, apply the
situations, including where the Principal had a bona fide              provisions in clauses 6.4 and 6.5 to the operation of the
‘claim’ against the Contractor. The word ‘claim’ was defined           Defects Bond, no reason is apparent from the terms of
very broadly.                                                          the contract, or the commercial purposes of the contract
                                                                       and the guarantees, why the parties would have
When the Contractor reached practical completion of its
                                                                       intended to treat access to the Defects Bond in any
stage, the Principal was required to:
                                                                       manner different from access to the Performance Bond.
•   return the bond provided by the insurance company; and
                                                                       The contract as a whole, and in particular the exchange
•   exchange the performance bonds provided by the bank                process in clause 6, suggests otherwise.”
    for a defects bond for 2.5% of the contract sum.
                                                                   On this interpretation, the Principal had express rights to
                                                                   call on the defects bond in specific circumstances,
                                                                   including where it had a bona fide ‘claim’, which was
                                                                   defined very broadly.

                                                                                                                                   23
Q4 2021

     This aspect of the decision is a good reminder about                 This decision contradicted the commonly held view that a
     fundamental principles: the care needed when drafting                construction contract did not need to provide an express or
     security clauses, and the need to interpret a contract               implied right to call on performance bonds, since that right
     as a whole.                                                          rested in the bonds themselves (this view was manifest in
     Nonetheless, Martin AJ’s more significant comments                   the drafting of the owner-focused Property Council 1
     concern whether the Principal could have called on the               contract before Mossop M, which was silent on rights to
     defects bond without the support of clause 6.4.                      call on the performance bonds).
                                                                          It is regrettable that Mossop M’s judgment was not cited in
     Could the Principal call on the defects bond
                                                                          the present case.
     without an express contractual right?
                                                                          Despite this, Martin AJ’s position is clear:
     This question has been controversial since Mossop M’s
     judgment in Walton Construction Pty Ltd v Pines Living Pty              “In these circumstances, it is not appropriate as
     Ltd, where his Honour held:                                             contended by the plaintiff, to approach the issue by first
                                                                             asking where the right of recourse to the Defects Bond
          “… when dealing with an application for an injunction
                                                                             is identified in the contract, and then ask whether the
          directed to the beneficiary of the guarantee (as opposed
                                                                             first defendant has complied with any condition
          to the financial institution providing it) the starting point
                                                                             precedent to the right to recourse. The unconditional
          must be the terms of the contract between those
                                                                             right of access is found in the terms of the guarantees,
          parties that permit recourse to be had to the security. It
                                                                             and the correct approach is to identify any term in the
          is the terms of that contract which will define the scope
                                                                             contract (negative stipulation) which qualifies the right of
          of the entitlement to call upon the security and any
                                                                             recourse in particular circumstances.”
          constraints upon that entitlement.
                                                                          Whether this forms part of the binding reasoning in Martin
          “In a case where the contract does not expressly deal
                                                                          AJ’s judgment is probably debatable.
          with the circumstances in which the guarantee may be
          called upon, any capacity within the contract that would        Further disputes in the area seem certain.
          permit the defendant to have recourse to the security           http://www7.austlii.edu.au/cgi-bin/viewdoc/au/cases/tas/
          must, if it exists, be implied.”                                TASFC//2021/11.html

24
Corrs Projects Update

Western Australia

                                      25
Q4 2021

     Chevron (TAPL) Pty Ltd v Pilbara Iron Company
     (Services) Pty Ltd
     [2021] WASCA 193

                     Key takeaways                                                                  Keywords
                     In price review clauses or the like, courts will not presume that notice       time is of the essence; time bars
                     requirements are inessential.
                     While the interpretation of notice requirements always turns on the
                     precise language, courts will generally enforce contractual
                     requirements and will bar rights if notices or claims are late.

     Background                                                                   “The Buyer or the Sellers may initiate a Price Review by
                                                                                  issuing, in the case of the Buyer, to the Sellers and the
     The full facts of this case are complex. These are the critical              Sellers’ Representative and in the case of the Sellers, to
     details: the appellants (Sellers) agreed to sell gas to the first            the Buyer, a notice which complies with Clause 14.4
     respondent (Buyer) for a number of years. The gas supply                     (Price Review Notice) not more than 120 days nor less
     contract allowed either party to initiate a review of the gas                than 90 days prior to a Price Review Date.”
     price. To do this, a party needed to give notice 90-120 days
     before a price review date.
                                                                            Decision
     In 2020, the Buyer gave a notice before the price review
     date but three weeks after notice was required.                        Quinlan CJ, Murphy and Beech JJA gave a joint judgment of
                                                                            more than 300 paragraphs. Their Honours treated the time
     Was timely notice essential?                                           requirement as essential, meaning that the Buyer could not
     The central question was whether the notice was ineffective            initiate a gas price review as its notice was late.
     because it was given late. In the Court of Appeal and at trial,        Their Honours carefully analysed clause 14 in light of the
     this was framed as whether the parties objectively intended            entire contract. Naturally, any dispute about the meaning of
     the time stipulation to be essential. This question is usually         an express term turns on the language in which it is
     associated with whether “time is of the essence” in the                expressed. Despite this, two aspects of the judgment are
     sense that late performance might allow the aggrieved party            likely to be useful in future cases.
     to terminate the contract. That was not the issue in this
     case. Rather, the issue is directly equivalent to time bars,           No presumption timely notice was not essential
     which the Western Australian Court of Appeal has previously            First, the Buyer had argued that there is a general principle
     enforced strictly.1                                                    that time stipulations in “machinery-type provisions for
     The price review clause, even in redacted form, stretches to           determining price adjustments are not construed as
     eight pages. The most important aspect is subclause 14.3,              essential unless there was an express provision or
     headed ‘Initiation of Price Review’ which provides that:               necessary implication to that effect”.

     1    See CMA Assets Pty Ltd v John Holland Pty Ltd [No 6] [2015] WASC 217.

26
Corrs Projects Update

The Court of Appeal’s rejection was strident: “In our view,
neither authority nor principle sustains any such general
principle or presumption.” Their Honours reached this
conclusion after detailed analysis of the principal Australian
and English cases.

Contractual interpretation arguments favouring
treating timely notice as essential
The second significant aspect of the judgment is the
Court’s textual analysis of the contract. Their Honours
relied on six reasons to conclude that the timely notice
was essential. In generalised form, these factors provide a
helpful summary for parties regarding when time bars will
be enforceable, and they were:
•   the language and structure of the clause support treating
    the timely notice as essential;
•   nothing in the language or structure points away from
    timely notice being essential;
•   treating timely notice as inessential would give the
    temporal aspect of the clause no work to do;
•   reating timely notice as essential would be harmonious
    with other aspects of the clause;
•   treating timely notice as inessential would result in
    incoherence when read with other clauses; and
•   a clause that allows a party to initiate a price review
    cannot be seen as merely mechanical.

Conclusion
The Court treated the time requirements for notices under
clause 14.3 as essential. As a result, a late notice was
ineffective. This is consistent with the courts’ literal
approach to time bars.
Finally, it is worth noting that different drafting might have
avoided or simplified the dispute. The timing requirement
might expressly have been described as essential.
Alternatively, it might have been framed as a condition
precedent. Including the words ‘only if’ may also have
sufficed.
https://ecourts.justice.wa.gov.au/eCourtsPortal/Decisions/Vi
ewDecision?returnUrl=%2feCourtsPortal%2fDecisions%2f
Filter%2fSC%2fRecentDecisions&id=e244f149-ef0e-45b7-
b0d8-0d31b0c66d56

                                                                                   27
Q4 2021

     Chevron Australia Pty Ltd v CBI Constructors Pty Ltd
     [2021] WASC 323

                   Key takeaways                                                               Keywords
                   While Australian courts might typically seek to uphold arbitral awards,     setting aside interim arbitral
                   courts do have discretion to set them aside. One situation in which         award; functus officio
                   this may occur is where the arbitral tribunal has already discharged its
                   mandate. Through the legal doctrine of ‘functus officio’, an arbitral
                   order may be set aside in that situation on the basis that the tribunal
                   lacked jurisdiction.
                   This has tactical implications for decisions about the structure of
                   arbitral proceedings.

     Facts                                                               Prior to the second hearing on quantum issues, however,
                                                                         CKJV amended its quantum case by submitting tabulated
     In 2011, Chevron Australia Pty Ltd (Chevron) engaged CBI            information explaining the basis on which it sought
     Constructors Pty Ltd and Kens Pty Ltd (CKJV) to provide             reimbursement. CKJV’s amended case was an attempt to
     ‘Craft Labour and Staff’ to carry out work on Chevron’s             recast its case on liability under the banner of quantum.
     Gorgon oil and gas project.                                         Chevron objected to CKJV’s new case and applied to have
     A dispute arose over the meaning of provisions of the               the plea struck out.
     Contract requiring Chevron to reimburse CKJV. Chevron               Chevron contended that there was no longer any valid
     argued that it had overpaid CKJV, while CKJV argued it was          submission by the parties to allow the Tribunal to hear
     owed more money.                                                    further liability issues. In the second hearing, the Tribunal
     In February 2017, arbitration commenced, with a three-              rejected Chevron’s functus officio argument by a two-to-one
     person tribunal. In March 2018, CKJV sought to split the            majority. Therefore, the Tribunal proceeded to determine the
     arbitration into two separate hearings: the first dealing with      merits of CKJV’s arguments on particular staff costs rather
     liability, and the second with quantum and quantification.          than considering the contention as a preliminary objection.
     Chevron objected, but the Tribunal approved the split.              In this context, the Tribunal issued a Second Interim Award
                                                                         in CKJV’s favour in respect of the staff costs issue.
     In the first hearing, CKJV contended that a variation of the
     Contract in August 2016 had changed the earlier terms so            Chevron sought to have the question of the arbitral tribunal’s
     that it would be reimbursed for labour costs on the basis of        jurisdiction determined by the court, under section 16(9) of
     ‘rates’ rather than ‘actual costs’. The Tribunal delivered an       the Commercial Arbitration Act 2012 (WA) (CAA). It also
     interim award (the First Interim Award) resolving this issue        sought relief under section 34(2)(a)(iii) of the CAA to have the
     in Chevron’s favour.                                                second interim award dated 4 September 2020 set aside.

28
Corrs Projects Update

Decision                                                              Consequently, Martin J held that an application to set aside
                                                                      an arbitral award based on questions about authority or
Issue one: application to have the court determine                    jurisdiction arising from allegations that the Tribunal is
the tribunal’s jurisdiction                                           functus officio does engage section 34(2)(a)(iii) of the CAA,
                                                                      which contemplates issues “beyond the scope of the
The first issue determined by the Court was whether it
                                                                      submission to arbitration”.
should decide the arbitral tribunal’s jurisdiction.
                                                                      Further, in assessing the second sub-issue, his Honour held
Under section 16(9) of the CAA, a party, after receiving
                                                                      that it “must always be for the court itself to render its own
notice of a ruling by an arbitral tribunal as a preliminary
                                                                      objective determination on the issue.” Arbitrators “cannot by
question, may request that the Court decide the matter. This
                                                                      their own decision … create or extend the authority
issue was decided swiftly as the Tribunal had not rendered a
                                                                      conferred upon them”.
ruling against Chevron’s functus officio objection as a
preliminary question.                                                 It was thus open to Chevron to seek to have the Court
                                                                      examine afresh its arguments that the Tribunal was
Instead, it had proceeded to resolve the objection, along
                                                                      functus officio.
with further issues on the merits, under the second interim
award. Consequently, the limited avenue of recourse to a              Issue three: was the tribunal functus officio?
court under section 16(9) of the CAA was not available.               By majority, the Tribunal rejected Chevron’s functus officio
Thus, the application was dismissed.                                  objections. Martin J disagreed with this assessment.
Issue two: application to have the second interim                     His Honour held that by application of the functus officio
award set aside                                                       doctrine, the Tribunal’s jurisdiction to resolve liability (heard
                                                                      in the first hearing) had ended and therefore the tribunal
One question is whether the court may intervene in setting
                                                                      was functus officio as regards matters dealt with in the
aside arbitral awards under section 34(2)(a)(iii) where the
                                                                      Second Interim Award.
Tribunal has discharged its duties (that is, it is functus officio)
but has proceeded to resolve further issues on their merits.
In determining this, two sub-issues emerge. First is whether          Conclusion
the functus officio condition arises under section 34(2)(a)(iii),
and then whether the Court itself makes this assessment.              Martin J set aside the Second Interim Award.

On the first sub-issue, Kenneth Martin J relied on the                Australian courts will seek to uphold arbitral awards.
reasoning in CRW Joint Operation v Pt Perusahaan Gas. In              However, courts’ pro-enforcement attitude is not
that case, the Court of Appeal of Singapore held that                 determinative and courts will intervene if a tribunal has
‘authority’ is “a significant and influential authority towards       acted outside its jurisdiction.
supporting the potential for a s 34(2)(a)(iii) engagement             http://www.austlii.edu.au/cgi-bin/viewdoc/au/cases/wa/
under functus officio encountered circumstances.”1                    WASC//2021/323.html

1   [2011] SGCA 33 at [30]–[33].

                                                                                                                                          29
Q4 2021

     Other

30
Corrs Projects Update

Triple Point Technology, Inc v PTT Public
Company Ltd
[2021] UKSC 29

                Key takeaways                                                                     Keywords
                Even where a liquidated damages clause is poorly drafted, high                    liquidated damages
                authority supports a commercial approach to its interpretation.
                Typically, that will mean that liquidated damages will be available to
                the point that the work is completed or the contract has been
                terminated.

Facts                                                                     Court of Appeal: liquidated damages
PTT engaged Triple Point to develop a new software
                                                                          unavailable
system for commodities trading. Under the contract,
                                                                          In the Court of Appeal, Sir Rupert Jackson (with Floyd and
payment became due when Triple Point reached
                                                                          Lewison LJJ agreeing) held that PTT was not entitled to
milestones. When Triple Point fell significantly behind in the
                                                                          liquidated damages. After analysing the case law, Sir
work, PTT stopped making payments. Triple Point
                                                                          Rupert concluded:
eventually stopped work midway to the next milestone and
brought a claim for outstanding payments. PTT counter-                        “[t]he phrase in article 5.3 ‘up to the date PTT accepts
claimed liquidated damages for delay, as well as general                      such work’ means ‘up to the date when PTT accepts
damages for repudiation of the contract. Article 5.3 of the                   completed work from Triple Point’. In my view Article 5.3
contract provided:                                                            in this case, like clause 24 in Glanzstoff, has no
                                                                              application in a situation where the contractor never
    “If CONTRACTOR fails to deliver work within the time
                                                                              hands over completed work to the employer”.1
    specified and the delay has not been introduced by PTT,
    CONTRACTOR shall be liable to pay … at the rate of                    In a Corrs Insight on the Court of Appeal decision we
    0.1% (zero point one percent) of undelivered work per                 observed that many Australian standard form contracts take
    day of delay from the due date for delivery up to the                 a different drafting approach. For example, AS4000–1997
    date PTT accepts such work.”                                          and AS 4300–1995 expressly provide that liquidated
                                                                          damages are available for the period between:
Critically, the contract was terminated before the relevant
                                                                          •   the date for practical completion; and
work was completed or accepted. The central issue was
whether PTT was entitled to liquidated damages for the                    •   the sooner of the date of practical completion or the
period between the due date for delivery and the date of                      date of termination.
termination (other issues arose from the construction of a                The outcome could differ given small changes in the
limitation of liability clause that carved out liability arising from     drafting, or unusual facts. In short, the Court of Appeal
negligence, but that topic is beyond the scope of this note).             decision raised the stakes for contract drafters.

1   Triple Point Technology, Inc v PTT Public Company Ltd [2019] EWCA Civ 230 at [112]. The Glanzstoff decision, on which Sir Rupert heavily
    relied, is British Glanzstoff Manufacturing Co Ltd v General Accident, Fire and Life Assurance Co Ltd (1912) SC 591 (Glanzstoff).

                                                                                                                                               31
You can also read