CNE Cernavoda Experience in developing and implementing an Integrated Management System - N. Florescu Department of Developing and Monitoring ...

 
CONTINUE READING
CNE Cernavoda Experience in developing and implementing an Integrated Management System - N. Florescu Department of Developing and Monitoring ...
CNE Cernavoda Experience in
developing and implementing an
Integrated Management System

           N. Florescu
           Department of Developing and
           Monitoring Management
           System
                                      1
CNE Cernavoda Experience in developing and implementing an Integrated Management System - N. Florescu Department of Developing and Monitoring ...
Content
   Introduction
   How we started (practical examples; difficulties
    encountered)
   Where we are (strategies to overcome those
    difficulties)
   What remained to be done (use lessons learned)
   Grading
   Conclusion

                                                       2
CNE Cernavoda Experience in developing and implementing an Integrated Management System - N. Florescu Department of Developing and Monitoring ...
SOCIETATEA NATIONALA NUCLEARELECTRICA (SNN) SA

                         SNN SA   2 units in operation

   CNE CERNAVODA UNITS            Nuclear Fuel Manufacturing
          1 and 2
                                         FCN PITESTI

                                                               3
                                                                   3
INTRODUCTION
   Construction of the Cernavoda units started early in 1980.
   5 CANDU units (work for the first reactor started in 1982, and
    each year a new unit was started). Cernavoda was considered
    the biggest site during Ceausescu regime.
   At the beginning of the 1990 the most advanced status was
    attained at units 1 and 2, the other 3 units were in a different
    stage of civil work. The work was stopped or drastically
    reduced.
   In 1992 there was restarted the work to Unit 1 and in 2002 to
    U2.
   U1 was finished in 1996 and unit 2 in 2007 by a consortium
    consisting from AECL, ANSALDO and Nuclearelectrica.
   U3 and U4 continued to wait decision for restarting the work.      4
How we start?

   Being a CANDU Design, for the project realization
    there was applied the requirements from Canadian
    QA Standards from series N286 and Z299.
   In 1982 there was issued specific
    legislation/regulation related to QA based on
    Canadian QA standards. The regulation was changed
    in 2003 when there was issued a new set of Quality
    Management Norms aligned to IAEA QA standards
    (13 QM Norms).
   In accordance with Romanian regulations, all
    documents describing QM System shall be approved
    by Romanian RB.
                                                         5
How we started?

   From the beginning, all the activities
    performed during construction and later
    during commissioning and operation were
    done in accordance with QM Systems rules.
   Procedures were prepared for each areas of
    activities such as Safety; QA; Technical;
    Administrative, Human Resources, Economic,
    etc.
                                                 6
How we started?

   The documents were issued under 4 levels:
    1.   QAM /QMM first level
    2.   RD’s – Governance level
    3.   SI’s – Administrative procedures
    4.   Working level procedures.
   As per Romanian norms all level 1 and 2 and
    part of the level 3 documents shall be
    approved by RB.
                                                  7
How we started?

   There were times when the approval by RB
    took more than 1 year.
   In 1999 Station Manager required QA
    Department to start a project for restructuring
    QA documentation and to reduce the number
    of documents which required approval by RB.
   This was the starting point for addressing a
    new idea related to integration.
                                                      8
How we started?

   Adherence of SNN to FORATOM gave the
    opportunity to access the information and
    started modernization of Cernavoda MS.
   Also, the creation of ROMATOM (SNN being at
    the base of foundation of the Romanian
    forum) gave the opportunity to SNN to force
    CNCAN to change the Romanian Norm and to
    align them to IAEA Standards.
                                                  9
How we started?
   In 2002, there was advanced the idea for
    adhering to the requirements of ISO14001.
   The idea was accepted by the Station
    Management.
   Quality management department plays the key
    role for integrating the ISO 14001 requirements
    in existing Quality Management System.
   A team was established in order to review and
    understand the standards requirements.
                                                  10
How we started?

   A gap analysis was performed by the team
    against the existing QMS requirements.
   The gap identified was incorporated in the
    existing management system documentation
    and in the Quality Management Manual.
   The auditors were trained in 2003 and
    qualified as internal auditors for environment.

                                                      11
How we started?

   The application for certification was done when we
    considered that the requirements were appropriately
    implemented.
   We found a big problem with certification companies
    in making them understand the structure of the
    Management System developed based on the norms
    for nuclear field.
   In 2004 we migrated from QM System to IMS, this
    being accepted by RB.
   In parallel, all MS documentation were organized
    based on the process concept.                         12
How we started?

   For developing the process there was issued a
    model, appropriate to those used by BNFL.
   In 2004 we started to focus on integrating U2 so
    that the progress done on the process development
    was reduced.
   In 2005 proceeding similarly with ISO 14001 we
    started preparation with integrating requirements
    from OHSAS 18001. The OHSAS certification was
    obtained in 2007.

                                                        13
How we started?

   In 2009 CNE Cernavoda started the process of
    integrating the requirements of ISO 27001.
   A consultant was employed to prepare the
    organization for adherence to the new standard
    taken in consideration that several requirements
    addressed IT aspects. The certification for ISO
    27001 was obtained in 2010.

                                                       14
How we started?

   In accordance with Romanian norms an operation
    License is issued by RB for operating organization.
    The license is issued if the operating organization
    developed and implemented an Approved Quality
    Management System. The license, in accordance
    with law requirements, shall be renewed every two
    years. Hence, QMS is reviewed by operating
    organization every two years against last
    requirements of RB. In 2007 RB requested CNE
    Cernavoda IMS to integrate GSR3 requirements.
                                                          15
How we started?

   A gap analysis was conducted and the GAP was thus
    identified.
   All the Gaps identified were addressed through AT
    System.
   The main deficiency that was identified was that
    one related to processes definition and
    responsibilities for process so that in 2007 there was
    restarted the program for process development.
   A new proposal was issued by Quality Management
    Department and submitted to the management for
                                                             16
    approval.
How we started?

   New proposal was focused on managing the
    processes as per IAEA recommendation from GSR3
    and associated guides. We have redesigned the
    process and defined:
       Process Sponsor
       CNE Cernavoda Process Coordinator;
       Process Owner;
       Single Point of Contact
   The responsibilities for development were allocated
    to QM department.
                                                          17
How we started?

   Acceptance of the new proposal was difficult:
      Lobby was done at the level of the top

       management;
      Practical example was prepared by the team

       responsible with the development of the new
       approach;
      Benefits of transition to the new model was

       presented to top management.
   The resistance was not fully removed.
                                                     18
Where we are?
   All the processes are identified;
   CNE Process model was defined;
   The process owners were assigned;
   The diagram of majority of processes was issued
    (only diagrams for two process have not yet been
    defined). The process model was improved with
    the support of IAEA experts during assistance
    provided during Norway project.
   Over 80% of general procedures was prepared
    and over 60% issued;                               19
Where we are?

   The structure of the IMS was evaluated by
    an international team within Norway
    project and the recommendation for
    improve already addressed and
    implemented;
   A new revision of IMS Manual is ready to
    be submitted to RB for approval.

                                                20
CNE CERNAVODA PROCESSES CHART
                                                       - MODEL -

                                              MANAGEMENT PROCESSES

                       1) Process Management and Leadership;                  3) External Interfaces Control;
                       2) Management Systems Assessment;                      4) Maintaining Operation Licenses

                                                                              5) Manage and direct the business

                                                            KEY PROCESSES

  Operation and Monitoring                           Maintenance and Repair                             Configuration Changes
                                                     Work
  6) Operation Control and Monitoring;                                                                  14) Design Configuration Control
  7) Chemistry Control;                              10) Maintenance Programs;
  8) Radioactive Material Control;                   11) Planning;
  9) Reactivity Control;                             12) Maintenance Implementation;
                                                     13) SSCE Reliability Upholding;

                                                              SUPPORT PROCESSES

15) Human Resources and Organizational Development     19) Personnel Radiation Exposure Control;      25) Station Actions and Nonconformance Control;
16) Environmental Management;                          20) Emergency Response Preparation;
                                                                                                      26) Fire Protection;
17) Station Personnel Training Concept;                21) Documents and Records Control;
18) Physical Protection;                               22) Material Purchase and Management;          27) Informational System Control;
                                                       23) Financial Services;                        28) Projects Management.
                                                       24) Personnel Health and Safety Program;

                                                                                                                                                        21
What remained to be done?
   Issue all the process procedures as established in
    transition plan for IMS;
   Redefined SA process in order to migrate from SA
    process based on functional areas (as defined in
    WANO/INPO Guide) to SA focused on processes;
   Integrate the requirement of Internal Managerial
    Control with existing IMS including new process
    related to risk management.

                                                     22
What remained to be done?
   Reevaluate the internal oversight function in
    order to increase the role of oversight;
   Increase the efficiency of IMS by more involving
    at the management level in sustaining the
    implementation of the IMS requirements.

                                                       23
Grading

   It is requirement of the Romanian Norms related to Quality
    Management System (NMC-02) to have classified the SSC in 4
    safety class (as per IAEA standard):
   “The licensee shall establish a list of SSC and clasify them
    on a scale from 1 to 4 based on imprtance to safety and
    radiological risk.
   The classification procedure and list of SSC shall be submitted
    to RB for approval;
   The list shall be submitted to participants for use”

                                                                  24
Grading

   Also Norm establish that participants or contractors shall
    prepare specific procedures related to gradual application of
    the QMS based on Safety Classification of the SSC received
    from the licensee, and shall submitted the to RB for approval.
   Note: This requirements was never implemented .
      CNE Cernavoda has been prepared procedure related to

       establishing Safety class of SSC and list of SSC with their
       classification in 2006, but the procedures was not yet
       approved. CNE Cernavoda use initial design classification
       list based on Canadian concept.

                                                                 25
Grading

   CNE Cernavoda has a procedure for establishing Quality Level
    of items and Services for procurement purpose based on NMC
    13
       5 different level (class 1 to 4 and Best Commercial)
       For class 1 to 4 is required selection process and qualification of
        suppliers based on different level of evaluation.
       For BC is required only ISO certificate.
   Related to other operational activities we have declaration in
    the IMSM that the requirements will be applied gradual based
    on importance of the activities for Safety.

                                                                              26
Grading

   Each procedures describing processes or activities contain
    information related to gradual application e.g.:
   Abnormal condition Report (RCA):
       RCA-Root cause
       RCA-important with investigation
       RCA – important with evaluation
       RCA – minor with evaluation
       RCA – minor with record for training.

                                                                 27
Grading

   Improvement action report close-up approval:
       Station Manager – if is recommendation from RB, or other improvement
        programs.
       Senior Superintendents if is from Observation Program, Human
        Performance or other departmental evaluation.
       Process Owner if is an improvement for process which not involve
        resources or major change in process.
   Document approval:
       Station Manager for RD/SIs;
       Department managers for IDPs,
   Etc.

                                                                          28
Conclusion
   SNN CNE Cernavoda even started the
    implementation of an IMS over 7 years
    ago, has not yet finalized the process of
    transition.
       Small groups initially involved in developing
        transition process;
       The project objectives were not well defined
        from the beginning, and a low support was
        received from management;
                                                        29
Conclusion
   The project was delayed by the effort done
    to integrate operation of the U2 with U1.
    Success of integration is demonstrated by
    results of operation of the U2.
   It is essential to be sustained by the top
    management;
   An aggressive communication into
    organization is essential for the success of
    the project.                                 30
RESULTS
 CAPACITY FACTOR (%)

 100

   90

   80

   70

   60

   50

   40

   30

   20

   10

    0
                                                                                                                    since
          1997   1998   1999   2000   2001   2002   2003   2004   2005   2006   2007   2008   2009   2010    2011     in
                                                                                                                    serv.

 FPI U1 87.27 86.19 84.51      88.3   88.25 89.37 79.52 89.71     90.08 91.37 97.62    84.8 100.10 91.53     99.67 89.94
                                                                                                                      31
 FPI U2                                                                         93.23 96.92   90.6   97.24   91.07 93.94
Questions?

             32
You can also read