Ahmedabad Division Western Railway
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Division at a Glance …….. 1170 KM Single line 816 KM BG (381.87 KM Route Electrified) Double line 355.2 KM (X 2) Kilometres Under G.C. 281 KM Under doubling 2 316.6 KM
Station classification ….. Stations classification NSG1 01 NSG3 03 As per new NSG4 08 norms NSG5 09 NSG6 & HG 129 Total 150 A1 01 A 05 B 02 As per old D 11 norm E 81 3 F 50 Total 150
Ticketing facilities ….. Unreserved Ticketing System (UTS) -Stations 78 Cash operated Ticket Vending Machine (CoTVM) 12 Ticketing Locations served with computerized PRS on Western 17 facilities Railway 29-Jan-21 UTS-cum-PRS Stations Ahmedabad Division, Western Railway 35 PRS at Post Offices 02
Passenger Services Daily Weekly TOTAL Trains MAIL / EXPRESS 56 55.5 111.5 service PASSENGER 42 04 46 before DIESEL MULTIPLE UNIT 20 04 24 lock-down MEMU 20 00 20 TOTAL (BG) 138 63.5 201.5 Passenger Services Daily Weekly TOTAL Trains MAIL / EXPRESS 12 53 65 service PASSENGER nil nil nil after DIESEL MULTIPLE UNIT nil nil nil lock-down MEMU nil nil nil TOTAL (BG) 12 53 65 Following trains which were not running as regular train, are introduced as special/festival train: • 09083/84 – Ahmedabad-Muzzafarpur (Daily) • 09089/90 – Ahmedabad-Gorakhpur (Daily) • 09451/52 – Gandhidham–Bhagalpur (Weekly) Considering the requirement, following clone trains are introduced : • 09465/66 – Ahmedabad-Darbhanga (Weekly) Train Services ….. • 09447/48 – Ahmedabad-Patna (Weekly) Trains converted to LHB : • Train no.19165/19166 ADI-DBG-ADI • Train no. 19167/19168 ADI-BSB-ADI 29-Jan-21 Ahmedabad Division, Western Railway
Loading performance of Ahmedabad division ….. 90 80 70 60 LOADING IN MT 50 40 30 20 10 0 2020- 2017- 2018- 2019- 21 18 19 20 (upto Nov) W.Rly 76.68 83.48 77.06 50.52 ADI division 31.64 34.68 35.16 22.29 29-Jan-21 Ahmedabad Division, Western Railway % share 41% 42% 46% 44%
Developmental projects completed in recent past….. Gauge conversion Asarva – Himmatnagar section: Commissioned in Mar-2019. GC from Himmatnagar to Khedbrahma (54.83 km) is sanctioned and detailed Project Report has been submitted to the Railway Board for sanction. Mehsana-Vadnagar section: Commissioned in Sept’2019. Vadnagar-Varetha section: Commissioned in Oct’2020. Sabarmati – Kalol section :- GC commissioned in Oct 2019. New lines Patan-Bhildi section: Commissioned in Sept’2019. Doubling Diyodar-Jesali-Bhildi – Commissioned in October 2019- Jan 2020. Samkhiyali-lakadia section - Commissioned in March-20 Surbari – Katariya and Katariya – Samakhyali double line section is Commissioned in Oct’2018 Electrification Ahmedabad – Viramgam section: Commissioned in August 2019. Ahmedabad Palanpur section has been electrified in March 2018. Platform no. 9 at Ahmedabad is completed in January 2019. Coach maintenance pit-lines 2 pit-lines for 24 coach length commissioned at Sabarmati coaching depot in Jan’2019.
Developmental projects completed in recent past….. Date of Kms commissioning Double line Jasali-Dhanakwada-Diyodar on Palanpur-Samakhiali section 17.32 12.10.2020 Bhildi-Jasali section on Palanpur-Samakhiali section 11.10 30.01.2020 Samakhiali-Lakadiya stations (10.44 kms) on Palanpur- Samakhiali section 10.44 01.03.2020 Sadla-Bajana-Jatpipli) on Viramgam-Samakhiali section 18.223 06.08.2020 Lakadiya-Shivlakha-Chitrod-Kidiyanagar on Palanpur - Samakhiali section 25.02 17.09.2020 Gauge Conversion Mahesana-Vadnagar Gauge Conversion : CRS inspection conducted 34.43 21.6.2019 Sabarmati- Kalol section on Ahmedabad- Mahesana section (GC with RE ) 19.26 25.10.2019 Vadnagar-Varetha section on Mahesana-Taranga Hill section GC with RE work (CRS inspection conducted) 21.04 10.11.2020 New line Patan-Bhildi line 51.03 20.4.2019 3rd line New BG 3rd line (bi-directional on automatic signalling with 25 KV electrification ) between Kankariya and Vatva of Ahmedabad -Vadodara 5.03 9.11.2020 section Additional line Gandhidham Block cabin-Adipur byepass line commissioned 23.4.2019 Electrification Chandlodiya - Jakhwada (excl) section 92.94 TKM 30.06.2019 Jakhwada-Viramgam section : CRS inspection conducted 66.17 TKM 19.8.2019 Palanpur yard : CRS inspection conducted 11.3 TKM 19.8.2019 Sabarmati- Kalol section on Ahmedabad- Mahesana section (GC with RE commisssioned) 30TKM 25.10.2019 Mahesana-Viramgam section CRS inspection conducted 78.39 TKM 06.01.2020 Mahesana-Vadnagar RE work CRS inspection conducted 35.25 TKM 29.01.2020 Vadnagar-Varetha section on Mahesana-Taranga Hill section GC with RE work (CRS inspection conducted) 21.04 10.11.2020 Electric trip shed commissioned at Vatva 22.08.2019
Developmental projects- works in-progress ….. S.N Progress of ongoing works of Ahmedabad division TDC Doubling of Palanpur-Samakhiali section (247.73 kms) Doubling of Bhildi to Diyodar (25.97 kms) and Kidiyanagar to Samakhiali (33.59 kms) commissioned 1 Chandisar-Disa-Lorwada-Bhildi (32.16 kms) 31.12.2020 Radhanpur-Piplee-Varahi-Vaghpura : (25.12 kms) 31.03.2021 Rest of Palanpur-Samakhiali section (130 .89 kms) 31.03.2022
Developmental projects- works in-progress ….. S.N Infrastructure improvement works in progress TDC Doubling of Viramgam-Samakhiali section (182.23 kms) Doubling of Viramgam-Sukhpur section (88.75 kms) and Surbari to Samakhiali section (23.45 kms) commissioned. DHANALA-KHAKHRECHI : (17.59 kms) 28.2.2021 KHAKHRECHI-WADHARWA : ( 8.38 kms) 31.03.2021 2. WADHARWA - SURBARI (except TWO ROB's) (27.64 kms) 31.05.2021 The remaining section WADHARWA-MALIYA MIYANA and MALIYA MIYANA-INDIRANAGAR between ROB to ROB is targeted in FY 2021- 31.12.2021 2022
Developmental projects- works in-progress ….. S.N Infrastructure improvement works in progress TDC Gauge Conversion of Sabarmati -Mahesana section: (68.78 kms) Gauge Conversion of Sabarmati - Kalol (21 kms) commissioned. Kalol-Dangarwa section (16.33 kms) 31.12.2020 3 Dangarwa -Jagudan section (15.61 kms) 28.02.2021 31.10.2021 Jagudan-Mahesana section ( including Mahesana yard ) (9.87 kms)
Developmental projects- works in-progress ….. S.N Infrastructure improvement works in progress TDC 4 Mahesana- Palanpur Doubling work (65.10 kms) 31.03.2025 Electrification of Viramgam-Dhrangadhra section and 5 31.03.2021 Samakhiali-Adipur section: Work in progress
Developmental projects- works in-progress ….. S.N Traffic facility works in progress (Plan Head 16) TDC 1 Sabarmati : - Leftover facilities for operationalization of Coaching Terminal 31.03.2021 2 Provision of full length Shunting neck at Chirai 31.01.2021 CHHARODI - Extension of line no.1 Dead end towards ADI End by 3 31.12.2020 750m for handling Auto Car traffic 4 Ahmedabad - Extension of pit lines (4 Nos) & stabling lines (3 Nos) 31.03.2021 towards Maninagar for 24 coaches Vadodara end - Pit line no.1,2 completed. Work of line no. 3 and 4 is pending since more than one year . At present work is stopped due to want of permission from ASI (Shaking minarets) . There is an issue of temple located between the yard lines towards Sabarmati end. Hence, extension work of pitline towards Sabarmati is pending.
Developmental projects- works in-progress ….. S.N Traffic facility works in progress(Plan Head 16) TDC 5 Chharodi - Provision of additional loop line with electrification. 31.12.2021 6 Kankariya Yard - Remodeling of Freight yard. 01.03.2022 7 Ahmedabad - Sanand section:- Provision of Automatic Signalling 31.03.2022
Passenger Amenity Work under progress 29-Jan-21 Ahmedabad Division, Western Railway
S / Work in progress Stations TDC N Redevelopment of Gandhinagar station alongwith construction of 300-rooms hotel on air-space of 1 GNC 28.02.2021 station building Renovation of CC aprons with drainages at platform Nos. 1,2,3,4,5,6,7 and new CC apron with drainages 2 ADI 16.02.2021 at platform No. 8 at Ahmedabad 3 Raising of platform No 1 & 2 at Chandlodiya Railway station. CLDY 31.01.2021 4 Replacement of ductable Split AC Unit with DX AC Unit at AC waiting hall at Ahmedabad Station. ADI 30.03.2021 5 Providing additional platform covering shed at Ahmedabad and Sabarmati Railway station. ADI & SBIB 28.02.2021 Improvement of watering arrangement by providing RCC over head tank (02 Nos) with bore well (01 No) 6 ADI 31.12.2020 at ADI Railway station. 7 Providing FOB (6.10m wide) in connection of Adarsh station at Ambli road Railway station. ABD 31.12.2020 8 Provision of FOB with one new Platform at Anjar Railway station.. AJE 31.12.2020 9 Redevelopment of Ahmedabad station. ADI 24.02.2021 1 Improvement to circulating area at Gandhidham, Viramgam, Patan & Samakhiali including new booking GIMB, VG, PTN & 31.05.2021 0 office at Samakhiali. SIOB 1 Replacement of Maninagar end foot over bridge at Ahmedabad Railway station. ADI 31.03.2021 1 SBT, KHD, SID, 1 Extension of Platform’s length with surface at Sabarmati (BG), Khodiyar, Siddhpur, Maliya Miyana, MALB, GIMB, 30.06.2021 2 Gandhidham, New Bhuj & Kalol stations (7 Stns-10 PF) BHUJ & KLL 29-Jan-21 Ahmedabad Division, Western Railway
Work sanctioned and on-going Stations TDC Providing FOB with one new platform at Bhandu station. BHU 31.03.2021 Providing additional FOB with approach cover shed with flooring at Palanpur station. PNU 30.06.2021 Ahmedabad-Palanpur Section - Raising of Rail level platform to High level upto BHU,DRW,JU 30.06.2021 350mt on home PF only with improvement to PF surface (5 stns - 8 PFs) L.KMLI.UM Extension of existing ML PF No -1 & PF NO 2-3 for full length with covering shed ABD 30.01.2021 Ambli Road Replacement of FOB at Maninagar station. MAN 18.03.2021 Setting up of quick watering arrangement on platform No. 1 & 2 at Mahesana MSH 31.03.2021 Railway station. Setting up of quick watering arrangement on platform No.1, 2 , 3 at ADI Railway ADI 31.03.2021 station. Setting up of quick watering arrangement on platform No. 1 at Bhildi Railway station. BLDI 31.03.2021 Kankariya(Goods shed)-Other Rail user's amenities at KKF Goods shed -Provision of KKF 30.04.2021 cover shed at out ward platform and RCC road between TP-1 & TP-2. HMT, PTN, Providing Monumental flag at HMT, PTN, PNU, BHUJ, & MSH Railway stations. PNU, BHUJ, & 15.02.2021 MSH Chandlodiya (B panel)-Providing High level Passenger Platform at CLDY'B' Panel. CLDY 31.03.2021 Kandla Port - CC platform at line No. 9 at Kandla Goods shed. KDLP 15.02.2021 Ahmedabad area - CC surfacing of parking plots at Chandlodiya station, Maninagar CLDY, MAN & 28.02.2021 staton & Kalupur health unit. ADI 29-Jan-21 Ahmedabad Division, Western Railway
Passenger amenities completed recently….. Upgrading retiring room at Ahmedabad station Add a footer 18 Improvement in Non-AC waiting room at Ahmedabad station
Passenger amenities completed recently….. Provision of VIP longue at Ahmedabad station Improvement in A.C. system of waiting room at Ahmedabad station Add a footer 19
Passenger amenities completed recently….. Provision of Wi-Fi facility at 35 Stations Improvement to FOB on Maninagar end Add a footer 20
Passenger amenities completed recently….. Quick coach watering System provided for PF-4,5,6,7 (Ahmedabad) Work in progress at Mehsana, Bhildi and Ahmedabad (PF- 1,2,3) Add a footer 21 Concrete apron and covered drainage for Platform 8 at Ahmedabad station
High – Level PF along with FOB at Chandlodiya Development of Patan station as Adarsh station Passenger amenities completed recently….. Add a footer 22
Passenger amenities completed recently….. Train indicator board & Coach guidance system GIMB: Extension Add a footer of PF Shelter, 23 improvement to PF surface and Pathway
Passenger Information System at KLL, UJA, SID & SBT Passenger amenities completed recently….. Add a footer 24 Improvement to platform surface on platform no. 1 at ADI station
Passenger amenities completed recently….. Provision of High-Level platform at PF1 of SAU, CE & JKA stations Add a footer 25 Computer based reservation charting display system at 7 charting station (ADI, MSH, PNU, GIM, BHUJ, VG & SBIB)
Provision of Monumental flag at Ahmedabad & Gandhinagar station building Providing passenger lifts on PF No. 8/ 9 & 10/11 at Ahmedabad station Passenger amenities completed recently….. Add a footer 26
Automatic Coach Washing Plant provided at BHUJ coaching depot. Further work is under progress at Sabarmati and Gandhidham Passenger amenities completed recently….. Add a footer 27
RoB/RUB/sub-way completed recently….. In year 2020-21 …. Add a footer 28 3 ROBs and 5 RUBs commissioned
New sections inaugurated by Hon’ble MPs Shri Kirit Solanki, Shri Hasmukh Bhai Patel, Shri Dipsinh Rathod and Smt. Shardaben Patel Asarwa – Himmatnagar Mahesana - Vadanagar 29-Jan-21 Ahmedabad Division, Western Railway
29-Jan-21
Hon'ble MP Shri Vinod Chavda and MLA Dr. Nimaben Acharya inaugurated the ETP (Wastewater Treatment Plant) the plastic Bottle crushing machine at Bhuj Railway Station.
Parcel Office Inaugurated on 12/12/2020 by Hon’ble MP Shri Hasmukh Bhai Patel 29-Jan-21 Ahmedabad Division, Western Railway
Various passenger amenities such as Ladies Waiting Room, Toilet Blocks, Refreshment Room Four Lifts and Two Escalators inaugurated at Mahesana on 12/12/2020 by Hon’ble MP Smt. Shardaben A Patel 29-Jan-21
29-Jan-21 Inauguration of New FOB at Himatnagar Station by Hon’ble MP Shri Dipsinh S. Rathod on 12/12/2020. Ahmedabad Division, Western Railway
Inauguration of High-Level PF No.1 at Kukma Station. Extended PF No.1 along with cover shed and 01 lift at Gandhidham Station by Hon’ble MP Shri Vinod L. Chavda on 12/12/2020
Inauguration of New Reservation and Booking office at Palanpur Station by Hon’ble MP Shri Parbatbhai S .Patel date 12/12/2020 29-Jan-21 Ahmedabad Division, Western Railway
Inauguration of New FOB at Viramgam Station by Hon’ble MP Dr.Mahendrabhai Munjapara date 11/12/2020 29-Jan-21 Ahmedabad Division, Western Railway
29-Jan-21 Bhumi Poojan of New Booking Office & Waiting hall at Patan Station by Hon’ble MP Shri Bharatsinhji S. Dabhi on 12/12/2020 Ahmedabad Division, Western Railway
29-Jan-21 Bhumi Poojan for Escalator at Ahmedabad Station by Hon’ble MP Dr. Kiritbhai P.Solanki on 12/12/2020 Ahmedabad Division, Western Railway
Status of Lifts and Escalators over Ahmedabad Division Lifts Escalator Stations Commissioned Sanctioned Commissioned Sanctioned Ahmedabad 9 - 4 9 Mahesana 4 - 4 - Gandhidham 2 - 2 2 Bhuj 2 - 1 1 Palanpur 0 3 2 - Sabarmati - 3 - - Maninagar - 2 - - Samakhiali - 2 - - Total 17 10 13 12 29-Jan-21 Ahmedabad Division, Western Railway
Efforts to prevent Covid-19 29-Jan-21 Ahmedabad Division, Western Railway
ADI Evacuation of Passengers from Ahmedabad Station after Lockdown 1.0 - Large number of passengers were stranded at Ahmedabad Station, due to non-availability of local transport (including buses). - Arrangement for free transportation of passengers in coordination with AMC, round the clock. - This 24 hour operation was closely monitored until the last passenger moved out of the station premises safely. Ahmedabad Division, Western Railway
ADI Feeding needy and poor - Due to loss of livelihood amid lockdown, Coolies, contract labour, homeless, slum dwellers, etc. were failing to make ends meet across the Ahmedabad division. To help them: - DRM Benevolent fund was set up and contributions were invited from officers and staff across the division. - About 3200 specialized dry ration kits were also distributed, sufficient for a family of four for 2 weeks, for distribution among the coolies, casual labour, slum dwellers, etc. - Distribution was done duly co-ordinating with appropriate state govt authorities for locating the needy. Without caring about the risk of getting infected, the distribution team consisting of departmental staff reached to the needy areas. - Total 2.75 Lakh food packets distributed. Out of this 1.7 Lakh were from DRM benevolent fund. Ahmedabad Division, Western Railway
Seamless Shramik Movement • 27 rakes were formed in the division • All“Sharmik special” trains escorted by RPF personnel. • 3.81 Lakh Labourers facilitated reaching their home • ₹ 24.87 Cr.: Revenue • 3 Shramik Specials terminated at BHUJ, Gandhidham and Palanpur stations bringing 3921 labourers back to their native 29-Jan-21 Ahmedabad Division, Western Railway
Meals & PDW in Shramik State: 212 Trains, 3.09 Lakh meals and 3.73 lakh PDW. NGO: 45 Trains, 0.67 Lakh meals and 1.12 lakh PDW. 29-Jan-21 Ahmedabad Division, Western Railway
Good Samaritan by Staff • Shri Balwant J Rathod Dy. Chief Ticketing Inspector, Mahesana distributed innumerable food packets to needy and the poor. • Ticket Checking Staff Shri Gopal - Mahesana & Shri Bharat Gohil - Viramgam distributed Slippers to needy passengers. 29-Jan-21 Ahmedabad Division, Western Railway
Specially designed Box Counter for Ticket Checking Staff • Magnifying glass • Covered from 3 sides • Counter communication system for all PRS/UTS offices and special counters 29-Jan-21 Ahmedabad Division, Western Railway
Thermal Screening enabled at Ahmedabad Station • Non-contact hands free thermal scanner provided at Ahmedabad station. • These scanners equipped with infrared cameras with facility for measuring temperature of multiple people at once. • The non-interfering process provokes less fear and negative emotions among staff and reduces psychological impact. 29-Jan-21 Ahmedabad Division, Western Railway
1st time over Indian Railways, Baggage Sanitation and Wrapping service. 29-Jan-21 Ahmedabad Division, Western Railway
Mask and Sanitizer Vending Machine at Ahmedabad Station, 1st over Western Railway 29-Jan-21 Ahmedabad Division, Western Railway
Rail Divyang Saarthi The application has been designed to digitize the procedure for fresh application, re-issuance, lost/damaged card application, verification, and issuance of Unique Identity cards for Divyangjan by the Divisional railways under CC-18 of 2015. This is helping in fighting Covid-19 as it has reduced the Divyangjans’ visit to the Divisional office from numerous to only one. 51
Freight Segment 29-Jan-21 Ahmedabad Division, Western Railway
2020-21 9.84 Record loading of 9.84 Crore litres milk through Milk Special Trains from Palanpur of Ahmedabad division to Hind Terminal, which is highest over Indian Railways. 129 milk special trains were run to ensure the supply of milk. Revenue of ₹17.05 cr. generated. 29-Jan-21 Ahmedabad Division, Western Railway
1st Parcel Rake for Bangladesh Loaded with General Goods from Kankariya on 08th Aug’20. • 10 no of rakes Loaded • ₹3.42 Cr. revenue generated 29-Jan-21 Ahmedabad Division, Western Railway
Parcel Traffic Loading other than regular Train service • 122 Piecemeal VPs • 54 VP rakes • 2 GS Rakes • 129 RMT rakes • 56 Piecemeal GS Total Parcel Revenue ₹46.98 Crore 29-Jan-21 Ahmedabad Division, Western Railway
Transportation of Medicines & Medical Goods: • Medicines : 1070 Tonne • Medical Goods: 1480 Tonne • Fruit & Vegetables : 549 Tonne • Fish & Crab : 2254 Tonne • Total Revenue: ₹2.38 Crore 29-Jan-21 Ahmedabad Division, Western Railway
Goods Shed infrastructure improvement Work Gandhidham: Approach Road and Platform Pre Post
Goods Shed infrastructure improvement Work Kankariya: RCC road between Sorting 2 & 6 Pre Post
Goods Shed infrastructure improvement Work Halvad: Repair – Approach road, Temporary repaired by Quarry Dust & Patch Repair work of PF surface Pre Post
Goods Shed infrastructure improvement Work Halvad: Repair – Approach road, Temporary repaired by Quarry Dust & Patch Repair work of PF surface Pre Post
• CWCJ at Jakhwada • MHPL at Sananad Commissioned • SCLS at Sukhpur • Ahir Salt at Shirva • Total Shipping at Bhankoda • Gokul Refoils & Solvent Ltd. Sidhpur • Synergy Warehousing Sanand Pipeline • Aarya Ocenic Pvt Ltd Maliya Miyana • PFT by CONCOR at Khodiyar
• • Novel • Freight • Initiatives • • •
Issues affecting progress of important projects ….. ● Provision of third line between Vatva-Ahmedabad so as to ease the congestion at Ahmedabad (Kalupur) is held up due to existence of a Mazaar in the alignment. Alternate arrangement for entry/exit to this mazaar is developed by Railway. However, Trustees of Dargah filed a suit in Waqf Tribunal , gandhinagar and status quo has been ordered. The issue needs to be resolved. ● Ahmedabad Coaching Complex: Work of proposed extension of pit line towards Sabarmati end, so as to examine 24 coach trains, has been has been held up due to existence of Shiv temple in the alignment . Railway offered alternate location adjacent to the existing temple and assured of shifting of temple at Railways cost. However, the trustees of the temple are not conceding with the agreement. The issue needs to be resolved. The mandir needs to be shifted to an alternate location, so as to complete the work . ● Ahmedabad Coaching Complex: Work of proposed extension of pit line towards Vadodara end, so as to examine 24 coach train,s, has been held up due to existence of shaking minarets adjacent to the alignment. Railways has been asked to stop the construction work by Archaeological Survey of India (ASI) due to close proximity to the shaking minarets. The train movements in this portion will be with a speed of 8 KMPH only and hence will not affect the strength of this archaeological structure. The issue needs to be resolved.
Thank You Ahmedabad Division, Western Railway