Wicklow County Council Bray Head Special Amenity Area Order Management Plan 2017 2021

Page created by Jeanne Bryant
 
CONTINUE READING
Wicklow County Council Bray Head Special Amenity Area Order Management Plan 2017 2021
Wicklow County Council
Bray Head Special Amenity Area Order
Management Plan 2017 ‐ 2021
Wicklow County Council Bray Head Special Amenity Area Order Management Plan 2017 2021
Aerial Overview of Bray Head

                        1|P a g e
Wicklow County Council Bray Head Special Amenity Area Order Management Plan 2017 2021
Introduction & Background
The Special Amenity Area Order (SAAO), confirmed by An Bord
Pleanala in 2008, is designed to preserve and enhance the amenity
value of the lands at Bray Head, Co.Wicklow; the area covers
approximately 335 Hectares (827 Acres) and is considered to be one of
outstanding natural beauty.

The making of the Order provided an additional level of protection to the lands and enabled
the Local Authority to set-out policy objectives to help ensure the preservation of the
character of the area. It also served to de-exempt some forms of development that would
otherwise be deemed as ‘exempt development’ under the Planning Regulations.

In confirming the Order an Bord Pleanala required the Local authority to include the following
objective:

        “The planning authorities shall jointly set up a management committee to
        manage the Special Amenity Area Order area, which shall be
        representative of the local authorities concerned, local community
        interests,   including   landowners    and   relevant    environmental    and
        conservation interests at the discretion of the local authorities. The
        committee shall be responsible for producing a five-year management plan
        for the area for monitoring environmental quality in the area and for
        monitoring implementation of the plan.”

The SAAO Management Committee established on foot of this requirement includes
representatives from the Council, local landowners, local community groups, residents of the
area, and the National Parks and Wildlife Service.

This document has been drafted by the Committee and represents the management plan for
the SAAO for the 5 year period 2017 – 2021. The Management Committee is responsible for
overseeing its implementation. The Plan will be reviewed annually having regard to progress
and future events that may impact on the priority of works.

SAAO Management Committee
Feb 2016

                                                                                          2|P a g e
No.                                Action                                       Partners                 Resources        Timeline            KPI♦

1     Map existing paths & trails. Ensure information is recorded in       WCC.                      €-                   2017          Production of
      WCC G.I.S system                                                                                                                  records

2     Audit trails, assess condition & develop works plan to bring them    WCC                       €                    2017          Report
      up to standard.
                                                                           Landowners                Extent of works
                                                                                                     required yet to be
                                                                           Irish Sports
                                                                                                     determined
                                                                           Council/National Trails
                                                                           Office

3     Agree trail names                                                    All stakeholders          €-                   2017          Trails named

4     Seek accreditation of trails with National Trails Office. Have the   WCC                       €-                   2017 - 2018   Successful
      routes included in WCC insurance policy.                                                                                          inclusion of routes
                                                                           Landowners
                                                                                                                                        on Council
                                                                                                                                        insurance policy.
                                                                           Irish Sports
                                                                           Council/National Trails
                                                                           Office

                                                                                                                                                  3|P a g e
5   Carry out a needs assessment regarding signage. Develop a            All stakeholders   €                   2018      Installation of
    signage plan that covers waymarking of trails, map boards at trail                                                    signage
                                                                                            Subject to tender
    heads, the SAAO & SAC. This should include all associated
    public information signage, both directional & educational, and
    identify boundaries of both public and private lands♣

6   Ensure regular checking of signage for damage/graffiti. Repair or    WCC                € 7,000 SAAO        Ongoing   Timely repair of
    replace as needed.                                                                      Annual Budget                 signage

7   Develop a plan for the ongoing maintenance of trails, cutting of     All stakeholders   €7,000 SAAO         2018      Condition of trails
    vegetation & surfacing repair                                                           Annual Budget*

8   Produce a list of appropriate plant species, including trees that    WCC                €-                  2018      Preferred planting
    may be planted within the SAAO area having regard to the SAC                                                          list
                                                                         National Parks &
    habitat. Develop a planting schedule that appropriately
                                                                         Wildlife Service
    addresses fire damaged areas and provides for future amenity
    woodland.

9   Develop a Fire Management Plan – include mapping fire                All stakeholders   €7,000 SAAO         2018      Improved fire
    hazards, fire brigade access, fire breaks, public fire awareness                        Annual Budget                 control measures/
                                                                         National Parks &
    (information signs)                                                                                                   risk reduction
                                                                         Wildlife Service

                                                                         Fire Service

                                                                                                                                    4|P a g e
10   Develop proposals to address littering within the SAAO area.            All stakeholders       €-              2019      Reduction in litter
     Raise public awareness. Determine appropriate locations for
     bins.

11   Investigate potential for wheelchair accessibility. Assess existing     All stakeholders       €7,000 SAAO     2019      Improvements in
     trails and consider the possibility of developing suitable route on                            Annual Budget             accessibility of
                                                                             Wheelchair users/IWA
     the Par 3 Golf Club Lands.                                                                                               these lands.

12   Develop a plan for the former Par 3 Golf Club lands. To be              All stakeholders       €-              2020      Production of Plan
     consistent with the zoning objective of the lands and the
     requirements of the Special Amenity Area Order.

13   Control of Invasive Species. Carry-out annual inspection for            WCC                    €7,000 SAAO     Ongoing   Eradication of
     invasive species (e.g. Rhododendron, Japanese Knotweed &                                       Annual Budget             invasive species
                                                                             Landowners
     Giant Hogweed) Issue reminders to Landowners. Where found
     arrange for removal and treatment.

14   Develop a strategy for the management & protection of lands             All stakeholders       €-              2020      Production of
     within the SAAO Area that are common to the SAC. This shall                                                              strategy/guidance
                                                                             National Parks &
     identify relevant sustainability indicators, risk factors and include                                                    document
                                                                             Wildlife Service
     measures to be put in place to monitor, assess and evaluate
     these to ensure a high quality environment.

                                                                                                                                        5|P a g e
15    Develop proposals for the improvement of Naylor’s Cove to       All stakeholders           €                    2021          Increased public
      increase its attractiveness and natural amenity value.                                                                        use of Naylors
                                                                                                 Extent of works
                                                                                                                                    Cove
                                                                                                 required yet to be
                                                                                                 determined

16    Produce an accessible & easily understood guidance document     WCC                        €-                   2020 - 2021   Guidance
      covering Planning & Development in the SAAO Area.                                                                             reference
                                                                                                                                    produced.

17    Commission a report on the stone walls within the SAAO area,    All stakeholders           €7,000 SAAO          2021          Production of
      map their location, survey their condition & include                                       Annual Budget*                     report
                                                                      Suitably qualified third
      recommendations for their repair and ongoing maintenance.
                                                                      party

     ♦KPI ‐ Key Performance Indicator
     *May require additional funding, to be determined at the time.
     ♣
       May be done in conjunction with Cliff Walk signage

                                                                                                                                                6|P a g e