User Guide Cost Center - HUAWEI TECHNOLOGIES CO., LTD - Issue Date - Huawei Cloud
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Copyright © Huawei Technologies Co., Ltd. 2021. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd. Trademarks and Permissions and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders. Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS" without warranties, guarantees or representations of any kind, either express or implied. The information in this document is subject to change without notice. Every effort has been made in the preparation of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute a warranty of any kind, express or implied. Huawei Technologies Co., Ltd. Address: Huawei Industrial Base Bantian, Longgang Shenzhen 518129 People's Republic of China Website: https://www.huawei.com Email: support@huawei.com Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. i
Cost Center User Guide Contents Contents 1 About Cost Center................................................................................................................... 1 1.1 Introduction............................................................................................................................................................................... 1 1.2 Data Scope.................................................................................................................................................................................2 1.3 Cost Type.................................................................................................................................................................................... 2 1.4 Data Precision........................................................................................................................................................................... 2 2 Enabling Cost Center.............................................................................................................. 4 3 Overview....................................................................................................................................5 4 Cost Analysis............................................................................................................................. 7 4.1 Viewing Cost Analysis............................................................................................................................................................ 7 4.2 Exporting Cost Details......................................................................................................................................................... 13 4.3 Rules for Recording Amortized Costs............................................................................................................................. 17 5 Budgets.................................................................................................................................... 20 5.1 Creating a Budget................................................................................................................................................................. 20 5.2 Viewing Your Budgets......................................................................................................................................................... 24 5.3 Editing a Budget.................................................................................................................................................................... 25 5.4 Copying a Budget..................................................................................................................................................................25 5.5 Deleting a Budget................................................................................................................................................................. 25 6 Reports..................................................................................................................................... 26 6.1 Analysis Reports.................................................................................................................................................................... 26 6.2 Budget Reports...................................................................................................................................................................... 29 7 Billing Mode........................................................................................................................... 31 7.1 Reserved Instances............................................................................................................................................................... 31 8 Cost Tags................................................................................................................................. 40 8.1 Overview.................................................................................................................................................................................. 40 8.2 Activating Cost Tags............................................................................................................................................................. 41 9 Export History........................................................................................................................ 42 10 Cost Management for Enterprises.................................................................................. 43 11 Permissions........................................................................................................................... 45 11.1 Introduction.......................................................................................................................................................................... 45 Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. ii
Cost Center User Guide Contents 11.2 Creating a User Group and Assigning Permissions.................................................................................................48 11.3 Creating a Custom Policy.................................................................................................................................................50 12 Quotas and Restrictions.................................................................................................... 51 Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. iii
Cost Center User Guide 1 About Cost Center 1 About Cost Center 1.1 Introduction 1.2 Data Scope 1.3 Cost Type 1.4 Data Precision 1.1 Introduction Cost Center offers a suite of tools for free that help you track, analyze, and explore your HUAWEI CLOUD costs and usage. Currently, the tools include: ● Cost Analysis: presents cost in charts. You can view your HUAWEI CLOUD costs and usage of different billing cycles and dive deeper by service type, region, linked account, billing mode, and cost tag. ● Budgets: allows you to configure budgets and stay informed of how your cost and usage progress. ● Reports: allows you to learn about and explore your cost data, and save the analyses as reports so that you can share with the various member accounts under your master account. On the Analysis Reports page, you can use some commonly used analysis reports preconfigured by HUAWEI CLOUD. Also you can create budget reports on the Budget Reports page to track your budgeting on a regular basis. ● Billing Mode: provides you with your RI utilization, RI coverage, net savings, and potential savings on the Reserved Instances page. ● Cost Tags: helps you identify and manage your HUAWEI CLOUD resources by tag. You can activate the tags to track your HUAWEI CLOUD costs for cost analysis and budget management. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 1
Cost Center User Guide 1 About Cost Center 1.2 Data Scope NOTE The cost and usage data in Cost Center is only for your reference during the cost analysis and budget management. Cost Center prepares your cost and usage data for the last 18 months. ● If you are an individual HUAWEI CLOUD customer, Cost Center provides you with cost and usage data generated based on your resource usage. ● If you are an enterprise customer and are using the master account, you can access the following data in Cost Center: – Your own cost and usage data – Your member accounts' cost and usage data generated during association with your account for unified accounting management ● If you are using a member account associated with the master account for unified accounting management, Cost Center provides you only with the cost and usage data generated during the association period. If you are no longer associated with the master account and have become an individual customer, the cost and usage data generated during the association period will no longer be available to you. You will only be able to access the data generated during the disassociation period. ● If you are using a member account (non-unified accounting management), you can view your cost and usage data like an individual customer. Currently, Cost Center cannot be used to manage the costs of solution partners (including resellers) and reseller customers. 1.3 Cost Type The Cost Center provides you with two types of costs. ● Original cost: reflects the expenditures after discounts, excluding cash coupons. To view the expenditures after both discounts and cash coupons, see the net original cost. ● Amortized cost: reflects the amounts prepaid for yearly/monthly services and reserved instances, which are amortized on a daily basis. For example, if you purchased a one-year cloud service at $365 USD, the amortized cost per day is $1 USD. For detailed rules, see Rules for Amortized Costs. Cash coupons are not considered when the cost is amortized. To learn about the amortized cost after cash coupons, see the net amortized cost. 1.4 Data Precision ● Original costs and billed amounts are calculated to the 8th decimal place. ● Amortized costs are rounded off and have a slight precision difference. The costs for the following orders need to be amortized: Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 2
Cost Center User Guide 1 About Cost Center – Yearly/monthly subscriptions – Reserved instances – Monthly-settled CDN services (if you enabled) Data precision for the amortized costs: – The amortized costs of orders before July 1, 2021 are calculated to the 2nd decimal place. – The amortized costs of orders after July 1, 2021 are rounded off to the 8th decimal place. The amounts displayed on the Cost Center pages are rounded off to the 2nd decimal place. The amounts included in exported cost details are calculated to the 8th decimal place. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 3
Cost Center User Guide 2 Enabling Cost Center 2 Enabling Cost Center You need to enable Cost Center before using it. Important Notes After Cost Center is enabled, HUAWEI CLOUD will prepare your cost data from the last 18 months. The data is available for viewing in about 24 hours. By default, IAM users do not have the permission required to access Cost Center. See Permissions for details about how to obtain the permissions. Cost Center is enabled by default for the master account and for any member accounts associated for unified accounting management. If a previously associated account is disassociated but still wants to access Cost Center, they need to enable Cost Center. Procedure Step 1 Go to the Billing Center. Step 2 Choose Cost Center. Step 3 Click Enter Cost Center. Step 4 Read and ensure you understand the information in the displayed dialog box, select the check box, and click Enable to enable Cost Center. You can also click Learn more to learn about how to find the functions originally in Billing Center and the updates in Cost Center. ----End Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 4
Cost Center User Guide 3 Overview 3 Overview You can view a quick summary of your costs on this page. Current Month Costs You can view the total month-to-date original costs (excluding adjustments) and the MoM growth over the last month. You can click the MoM growth rate to access the Cost Analysis page to view details. Daily Costs You can view original costs (excluding adjustments) by day. You can click Cost Details to go to the Cost Analysis page and view your cost details. Current Month Trends You can view the top 5 cost trends (original costs of pay-per-use resources billed per usage and original costs of pay-per-use resources billed hourly) compared to the same period of the previous month by linked account, service type, and region. NOTE If there is no data in the same period of the current month, no trends will be displayed. ● Linked account: the cost trends of the top 5 linked accounts ● Service type: the cost trends of top 5 service types ● Region: the cost trends of the top 5 regions. You can click the trend information to access the Cost Analysis page to view details. Recently Accessed Reports You can view any reports you have recently accessed. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 5
Cost Center User Guide 3 Overview You can click the report name to view the analysis or click View all reports to go to the Reports page for details. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 6
Cost Center User Guide 4 Cost Analysis 4 Cost Analysis 4.1 Viewing Cost Analysis 4.2 Exporting Cost Details 4.3 Rules for Recording Amortized Costs 4.1 Viewing Cost Analysis On the Cost Analysis page, you can view the analyses of original costs, amortized costs, and the daily or monthly trends within a given time range. You can also select different dimensions or filters to dig deeper into the details. For the scope of data that you can analyze, see 1.2 Data Scope. Important Notes Cost data generated before June 2021 can only be viewed using the following dimensions and filters: ● Service Type ● Region ● Billing Mode ● Linked Account ● Business Entity ● Specification Code ● Usage Type ● Bill Type ● Cost Tag Specifying a Time Range You can view your cost data by day or month within a given time range. Granularity Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 7
Cost Center User Guide 4 Cost Analysis ● Daily: View cost data by the day. ● Monthly: View cost data by the month. Period ● 7 days: the cost data for the last 7 days (excluding the current day) ● 14 days: the cost data for the last 14 days (excluding the current day) ● 30 days: the cost data for the last 30 days (excluding the current day) ● Month to date: the month-to-date cost data ● Last 3 months: the cost data for the last 3 months (excluding the current month) ● Last 6 months: the cost data for the last 6 months (excluding the current month) ● Last 12 months: the cost data for the last 12 months (excluding the current month) ● Year to date: the year-to-date cost data ● Custom: You can specify a specific time range for data query. Selecting Dimensions/Filters You can use different dimensions to identify the frequently used products, analyze cost distributions, or identify linked accounts with highest costs associated. You can also select filters to view desired datasets. If you select multiple filters, only results meeting all filtering criteria will be displayed. However, if you select multiple items for any given filter, results meeting any of the items selected will be displayed. You can use the following dimensions and filters for cost analysis: Dimensio Description n Service Category of a cloud service. Type Example: Elastic Cloud Servers Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 8
Cost Center User Guide 4 Cost Analysis Dimensio Description n Resource Category of the resource used for a cloud service. Type Example: Cloud servers Linked HUAWEI CLOUD account used to purchase and use resources. Account A customer using a master account can select the linked member accounts to view the cost data of their member accounts. Region Cloud service region that provides HUAWEI CLOUD service resources independently and serves a large geographical area. AZ A physically isolated zone where resources have their own independent power supply and internal networks. One region can have multiple AZs, and if one AZ becomes faulty, the other AZs in the same region can still provide services. AZs in the same region can access each other as they are on the same intranet. Enterprise The enterprise project selected when you purchase a cloud service. Project If no enterprise project is selected, default is displayed as the value for this field. If the enterprise project management is not supported for the cloud service, Not categorized is presented. Specificati A group of codes used to describe the specifications of a cloud on Code service. Example: s3.small.1.linux Billing Billing modes include Yearly/Monthly, Pay-per-Use, and Reserved Mode Instance. Usage The way a pay-per-use cloud service is billed. Type Example: Duration:Second (Virtual Private Cloud:VPN:Duration) Bill Type Type of a billing item. Example: expenditure-purchase and expenditure-hourly billing Business Business entity which a cloud service belongs to. Entity Example: HUAWEI CLOUD PayerAcco Account used to transact with HUAWEI CLOUD. unt Name ● Generally, resources are under this account. ● For a member account that is associated with a master account for unified accounting management, PayerAccount Name is the enterprise master account. The master account can switch the value of PayerAccount Name view the cost data of the member accounts that are not associated for unified accounting management. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 9
Cost Center User Guide 4 Cost Analysis Dimensio Description n Cost Tags Used to track costs of enterprise resources. To learn more about cost tags, see Activating Cost Tags. If you are a member account associated with the mast account for unified accounting management, you can only use the cost tags activated by the master account. Resource Unique ID of a cloud service resource. Advanced Settings Cost Center provides you with original cost analyses by default. You can configure advanced settings to view analyses of other costs if needed. Cost Type ● Original costs: reflect expenditures after discounts. The original cost is an estimate before the billing date. ● Net original costs: reflect original costs after cash coupons are applied. Before the billing date, it is equivalent to an estimated amount without any cash coupons applied. ● Amortized costs: reflect prepaid amounts amortized on a daily basis. For detailed rules, see Rules for Amortized Costs. The amortized cost is an estimate before the billing date. ● Net amortized costs: reflect amortized costs after cash coupons are applied. Before the billing date, it is equivalent to an estimated amount without any cash coupons applied. Showing Last Period Cost/PoP Rate ● Last period cost = Total cost of the current period – Total cost of the previous period ● PoP rate for total cost You can select Show last period cost/PoP rate to see the desired information. Showing List Price The list price is the sale price of a product without any discounts applied. If you select this option, the list price will be displayed only for analysis of original costs. Charts In Cost Center, you can display cost data in stacked charts, bar charts, and line charts. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 10
Cost Center User Guide 4 Cost Analysis NOTE A maximum of seven data records can be displayed in a chart. If you select 7 or more data records, the top 6 data records and Other are displayed by default. Other indicates the total number of the remaining data records combined. ● Stacked chart Figure 4-1 Stacked chart ● Bar chart Figure 4-2 Bar chart ● Line chart Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 11
Cost Center User Guide 4 Cost Analysis Figure 4-3 Line chart Viewing Cost Analysis Step 1 Log in to Cost Center. Step 2 Choose Cost Analysis. Step 3 Set search criteria to view desired cost data. ● When the cost type is Original costs or Net original costs, the data displayed on the page is nearly real-time. ● When the cost type is Amortized costs or Net amortized costs, the most recent data may take 24 to 48 hours to display. ● You can click Export and download the Cost Analysis - Overview file. ----End Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 12
Cost Center User Guide 4 Cost Analysis 4.2 Exporting Cost Details Important Notes In the Cost Center, you can only export monthly amortized costs. To view your original cost, log in to the Billing Center and choose Billing > Bills. If you are using the master account to export cost details, the exported file will include the costs of your member accounts during the association period (for unified accounting management). Procedure Step 1 Log in to Cost Center. Step 2 Choose Cost Analysis. Step 3 Click export records. Step 4 Select the cost type and specify the period, and click OK. ----End Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 13
Cost Center User Guide 4 Cost Analysis Fields Table 4-1 Fields regarding cost details Field Description Month The month costs are amortized over. See Rules for Amortized Costs for details. Enterprise The enterprise project selected when you purchase a cloud Project service. If no enterprise project is selected, default is displayed as the value for this field. If the enterprise project management is not supported for the cloud service, Not categorized is presented. Enterprise The ID of the specified enterprise project. If no enterprise project Project ID is selected during purchases, 0 is displayed as the value of this field. Linked HUAWEI CLOUD account used to purchase and use resources. Account PayerAccou Account used to transact with HUAWEI CLOUD. nt Name Service Type Code of the cloud service type. Code Example: hws.service.type.vpc Service Type Cloud service type. Example: VPC Resource Code for the category of the resource used for a cloud service. Type Code Example: hws.resource.type.ip Resource Category of the resource used for a cloud service. Type Example: EIP Product ID ID of a product. Billing Billing mode of the product. When the order type is Mode unsubscription, this field has no value. ● Yearly/Monthly ● Pay-per-use ● Reserved instance Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 14
Cost Center User Guide 4 Cost Analysis Field Description Bill Type Type of a billing item. ● Expenditure-purchase: fees for purchased yearly/monthly products ● Expenditure-renewal: fees for yearly/monthly subscriptions that you manually renew ● Expenditure-use: fees for pay-per-use products ● Expenditure-auto-renewal: fees for yearly/monthly subscriptions that are automatically renewed ● Expenditure-hourly billing: fees for reserved instances that are billed hourly ● Expenditure-unsubscription service charge: handling fees charged for unsubscriptions ● Expenditure-month-end deduction for support plan: fees charged for the support plan at the end of a month ● Expenditure-change: fees for changing the specifications of yearly/monthly products ● Expenditure-tax: taxes for yearly/monthly subscriptions and pay-per-use products ● Expenditure-difference amount: fees that HCDP customers need to pay if their expenditures do not reach the minimum guaranteed amount. Difference amount = Minimum guaranteed amount – Expenditure amount ● Refund-unsubscription: fees for a yearly/monthly subscription that is unsubscribed from or for which the specification is downgraded ● Refund-unsubscription tax: taxes refunded when a yearly/ monthly subscription is unsubscribed from or for which the specification is downgraded ● Adjustment-compensation: fees compensated by HUAWEI CLOUD ● Adjustment-deduction: fees paid when HUAWEI CLOUD makes an account adjustment. For example, when HUAWEI CLOUD adjusts a specification downgrade order, the original refund amount is paid first. ● Adjustment-compensation tax: taxes for HUAWEI CLOUD compensations ● Adjustment-deduction tax: taxes for HUAWEI CLOUD account adjustments Order No. Unique identifier of a yearly/monthly or a reserved instance order. Start Time Time when billing for a specified cloud service starts. End Time Time when billing for a specified cloud service ends. Billing Cycle Billing cycle in which original costs for resources are generated. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 15
Cost Center User Guide 4 Cost Analysis Field Description Resource ID Unique ID of a cloud service resource. Resource User-defined name of a cloud service resource. Name Specificatio A group of codes used to describe the specifications of a cloud n Code service. Example: s3.small.1.linux Specificatio Resources specifications. ns Region Code of a region. Code Region Cloud service region that provides HUAWEI CLOUD service resources independently and serves a large geographical area. AZ A physically isolated zone where resources have their own independent power supply and internal networks. One region can have multiple AZs, and if one AZ becomes faulty, the other AZs in the same region can still provide services. AZs in the same region can access each other as they are on the same intranet. Usage Type Code of a usage type. Code Example: Duration Usage Type The way a pay-per-use cloud service is billed. Example: Duration:Second (Stream computing:Stream computing:Duration) Usage The amount a cloud service was used within the amortization period, measured by such items as duration, capacity, count, or traffic. Usage Unit The unit used to measure the product usage. Package The usage of a resource included in a package within the Usage amortization period. If this usage does not exceed the package quota, no extra charges are incurred. Usage in The usage of a resource included in a reserved instance within the Reserved amortization period. If this usage does not exceed the package Instances quota, no extra charges are incurred. Original The original cost of a resource. This is equivalent to the amount Cost due in the bill. Current The amount amortized to the current month. Month Amortized Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 16
Cost Center User Guide 4 Cost Analysis Field Description Amortized The amount of cash coupons amortized to the current month. Cash Coupon Cost Tag The name of a cost tag for a resource within the amortization period. If there are multiple cost tags for a given resource, then multiple values will be displayed. Example: Department 4.3 Rules for Recording Amortized Costs This section describes the rules for recording amortized costs and net amortized costs. Pay-per-Use Resources NOTE For pay-per-use resources settled on a monthly basis (for example, CDN billed by 95th percentile bandwidth), the amortized cost is recorded from when the bills are settled. This explains why there may be a peak in the middle of a month. The amortized costs of pay-per-use resources are calculated based on the resource usage. ● If the time when a pay-per-use resource started being used (the first time expenditures were incurred) and the transaction time (when the amount due was paid) were in the same billing cycle, the amortized cost of the resource is recorded for the day when it started being used. Example: Suppose you used a pay-per-use resource from June 10, 2021 23:00:00 to June 10, 2021 23:59:59, the transaction time was June 11, 2021 00:53:30, and the amount due was $2 USD. Cost amortization: As the time when expenditures were incurred (June 10, 2021 23:00:00) and the transaction time (June 11, 2021 00:53:30) were in the same billing cycle, the amount due ($2 USD) is recorded as the amortized cost for June 10, 2021. ● If the time when a pay-per-use resource started being used (the first time expenditures were incurred) and the transaction time (when the amount due was paid) were not in the same billing cycle, the amortized cost of the resource is recorded for the transaction day. Example: Suppose you used a pay-per-use resource from June 30, 2021 23:00:00 to June 30, 2021 23:59:59, the transaction time was July 1, 2021 00:53:30, and the amount due was $2 USD. Cost amortization: As the time when expenditures were incurred (June 30, 2021 23:00:00) and the transaction time (July 1, 2021 00:53:30) were not in the same billing cycle, the amount due ($2 USD) is recorded as the amortized cost for July 1, 2021. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 17
Cost Center User Guide 4 Cost Analysis Yearly/Monthly Subscriptions or Reserved Instances As of August 01, 2020 00:00:00 GMT+08:00, the costs of new subscriptions are amortized based on the following rules: ● Daily amortized cost = Order amount/Number of days in the order effective term (expiration time – effective time) ● If the resources in an order are not enabled, the costs of such resources are not amortized. ● If the order effective time and order expiration time are on the same day, the cost of the order is not amortized but is recorded for that day, instead. ● If a subscription is renewed but the order effective time has elapsed, the historical costs will still be amortized over the time the order was effective. ● Daily amortized cost for unsubscribed or downgraded orders = Refund amount/Number of days in the order effective term (expiration time – effective time) The costs incurred during the elapsed days are recorded as amortized costs for the day when the orders were unsubscribed from or downgraded. The remaining costs are amortized over the upcoming days. For example, if you subscribe to a 30-day product for $60 USD and request a full-amount refund on the third day of the subscription month, then the cost amortized over the first three days ($-2 USD each day and $-6 USD in total) is recorded as amortized cost for the day when the order was refunded, and $-2 USD is recorded as amortized cost for each of the remaining days from the 4th day to the 30th day. Order 1st 2nd 3rd 4th 5th 6th ... 30th Line Day Day Day Day Day Day Day New 2 2 2 2 2 2 ... 2 subscr iption s Full- - - -6 -2 -2 -2 ... -2 amou nt refun ded items Enterprise Projects and Tags for Amortized Costs Yearly/Monthly Subscriptions ● Enterprise project: By default, the enterprise project selected for the order is used for the amortized costs of your yearly/monthly resources. ● Tags: Starting from June 1, 2021, the resource tags used when the amortized costs are calculated are applied to the daily amortized costs of your yearly/ monthly resources. Tags for costs amortized before June 1, 2021 do not change even if the tags for their resources change. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 18
Cost Center User Guide 4 Cost Analysis Pay-per-Use Resources The enterprise project and cost tags used when pay-per-use resources are settled are used for your amortized costs. Example If you placed a yearly/monthly order (valid from December 11, 2020 to January 10, 2021) and paid $300 USD, and then unsubscribe from the order on December 21, 2020 and pay a handling fee of $5 USD, the daily amortized cost will be $10 USD. You will see two amortized cost records for December, 2020. ● One for the total cost of $200 USD to be amortized over the period from December 11, 2020 to December 31, 2020. ● The other for the sum of the refund and the handling fee ($-95 USD in total). (On the unsubscription day of December 21, 2020, the refund of $100 USD is recorded. The refund is not recorded as the amortized cost but the handling fee of $5 USD is recorded as the amortized cost.) Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 19
Cost Center User Guide 5 Budgets 5 Budgets 5.1 Creating a Budget 5.2 Viewing Your Budgets 5.3 Editing a Budget 5.4 Copying a Budget 5.5 Deleting a Budget 5.1 Creating a Budget You can set budget thresholds and configure alerts to track your daily, monthly, and quarterly costs and your resource usage. If your actual costs exceed the configured budget threshold, you will receive a notification. Important Notes Alerts are not supported for the current month for certain cloud services, such as CDN billed by 95th percentile bandwidth, because their usages for the current month will not be billed until the following month. You can create up to 1,000 budgets. Each recipient can receive a maximum of 100 notifications a day. The budget monitoring data is updated hourly, so your actual costs and usage may have already exceeded the budget when you receive a notification. Creating a Cost Budget You can use the following procedure to create a budget that is based on your costs: NOTE Currently, you can only track your original costs. Step 1 Log in to Cost Center. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 20
Cost Center User Guide 5 Budgets Step 2 Choose Budgets. Step 3 Click Create Budget. Step 4 Select Cost budget, and click Next. Step 5 Configure the budget details and define the budget scope, and click Next. Table 5-1 Parameters for creating a cost budget (1) Parameter Description Budget The budget name must be unique. Name Reset Period The reset period for a budget can be Daily, Monthly or Quarterly. ● Daily: Budget evaluation begins at 00:00 GMT+08:00 on the start date and will be reset to zero at 00:00 GMT+08:00 on each day moving forward. ● Monthly: Budget evaluation begins at 00:00 GMT+08:00 on the 1st day of the start month and will be reset to zero at 00:00 GMT+08:00 on the 1st day of each month moving forward. ● Quarterly: Budget evaluation begins at 00:00 GMT+08:00 on the 1st day of the start quarter and will be reset to zero at 00:00 GMT+08:00 on the 1st day of each quarter moving forward. Budget Recurring: You set a start date on which the recurring budgets Duration will begin renewing. Expiring: You set a time range, outside which expiring budgets will not renew. Allocation If your reset period is Daily, you can only enter a fixed amount. If your reset period is Monthly or Quarterly, you can set a fixed budgeted amount or enter the total amount that you want to use every month or quarter. Budgeted If Allocation is Fixed, you just set a fixed value. (USD) If Allocation is Monthly or Quarterly, set budgeted amounts one by one. If the budgeted amount is not set for a period, the amount most recently entered will be applied. For example, if the budgeted amount of May 2021 is not set, the system will inherit the budgeted amount from April 2021. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 21
Cost Center User Guide 5 Budgets Parameter Description Budget You can define a budget scope as required. Specifically, you can Scope set filters such as Service Type, Enterprise Project, Region on (optional) the left, and the cost data for the last 12 months will be displayed on the right. In the Advanced Settings area, set Cost Type. You can choose to summarize cost data based on the original cost or the net original cost. If you are using a master account and want to create a budget for your member accounts, select these member accounts from Linked Account. Step 6 Set alert thresholds and recipients, and click Next. Table 5-2 Parameters for creating a cost budget (2) Parameter Description Thresholds If the actual costs reach a certain amount or a certain percentage of a budgeted amount, an alert will be reported. A maximum of five thresholds can be set for each budget. ● Amount (USD): If the actual costs reach a certain amount, an alert will be reported. ● (%) of budgeted amount: If the actual costs reach a certain percentage of a budgeted amount, an alert will be reported. Recipients Information of contacts who will receive the alerts. You can add up to 10 recipients for each alert. To add or modify recipient information, go to the Recipient Management page in the Message Center. Step 7 Confirm your budget settings and click Save. ----End Creating a Usage Budget You can use the following procedure to create a budget that is based on your usage: Step 1 Log in to Cost Center. Step 2 Choose Budgets. Step 3 Click Create Budget. Step 4 Select Usage budget and click Next. Step 5 Configure the budget details and define the budget scope, and click Next. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 22
Cost Center User Guide 5 Budgets Table 5-3 Parameters for creating a usage budget (1) Parameter Description Budget The budget name must be unique. Name Usage Type The way a pay-per-use cloud service is billed. Choose the specific service usage measurements that you want the budget to monitor. Reset Period The reset period for a budget can be Daily, Monthly or Quarterly. ● Daily: Budget evaluation begins at 00:00 GMT+08:00 on the start date and will be reset to zero at 00:00 GMT+08:00 on each day moving forward. ● Monthly: Budget evaluation begins at 00:00 GMT+08:00 on the 1st day of the start month and will be reset to zero at 00:00 GMT+08:00 on the 1st day of each month moving forward. ● Quarterly: Budget evaluation begins at 00:00 GMT+08:00 on the 1st day of the start quarter and will be reset to zero at 00:00 GMT+08:00 on the 1st day of each quarter moving forward. Budget Recurring: You set a start date on which the recurring budgets Duration will begin renewing. Expiring: You set a time range, outside which expiring budgets will not renew. Allocation If your reset period is Daily, you can only enter a fixed amount. If your reset period is Monthly or Quarterly, you can set a fixed budgeted amount or enter the total amount that you want to use every month or quarter. Budgeted If Allocation is Fixed, you just set a fixed value. (USD) If Allocation is Monthly or Quarterly, set budgeted amounts one by one. Usage Scope You can define a budget scope as required. Specifically, you can (optional) set filters such as Linked Account, Region, and PayerAccount Name on the left, and the usage data from the last 12 months will be displayed on the right. If you are using a master account and want to create a budget for your member accounts, select these member accounts from Linked Account. Step 6 Set alert thresholds and recipients, and click Next. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 23
Cost Center User Guide 5 Budgets Table 5-4 Parameters for creating a usage budget (2) Parameter Description Thresholds If the actual usage reaches a certain amount or a certain percentage of a budgeted amount, an alert will be reported. A maximum of five thresholds can be set for each budget. ● Usage (Byte): If the actual usage reaches a certain amount, an alert will be reported. ● (%) of budgeted usage: If the actual usage reaches a certain percentage of a budgeted amount, an alert will be reported. Recipients Information of contacts who will receive the alerts. You can add up to 10 recipients for each alert. To add or modify recipient information, go to the Recipient Management page in the Message Center. Step 7 Confirm your budget settings and click Save. ----End Alerts ● When the actual cost or usage reaches the configured threshold, the system will notify the recipients by email or SMS. ● The recipients will receive the alerts within one hour. Each recipient can receive a maximum of 100 budget alerts a day. Plan your budget appropriately. ● Within a budget monitoring period, the alert notification is sent only once even if more than one configured thresholds are reached. Assume that you set the budgeted amount to $100 USD, and alert thresholds to 60%, 70%, and 80%. If the actual cost is $85 USD (85% of the budgeted amount), the system will send only one alert, informing recipients that the current cost exceeds 80% of the budgeted amount. ● An alert is sent only once for each threshold in a reset period. Assume that you set the reset period to Monthly, budgeted amount to $100 USD, and threshold to 80%. If the actual cost of the current month reaches $80 USD (80% of the budgeted amount), the system will report an alert. If the threshold of the current month is changed to 90%, the system will check costs based on the new threshold. If the actual cost of the current month reaches $90 USD (90% of the budgeted amount), the system will send an alert again. 5.2 Viewing Your Budgets Step 1 Log in to the Cost Center. Step 2 Choose Budgets. Step 3 View the list of your budgets. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 24
Cost Center User Guide 5 Budgets Actual/Budgeted: Displays the percentage of your actual costs or usage to the total budgeted amount. Step 4 Click a budget name to view the budget details. ----End 5.3 Editing a Budget If you want to edit the information of a created budget, such as the budget duration and time range, perform the following operations: Step 1 Log in to the Cost Center. Step 2 Choose Budgets. Step 3 Select a budget and click Edit in the Operation column to edit the budget. ----End 5.4 Copying a Budget If you want to quickly create a budget, perform the following operations: Step 1 Log in to the Cost Center. Step 2 Choose Budgets. Step 3 Select a budget and click Copy in the Operation column. Step 4 Modify the copied budget. Step 5 Click Save. ----End 5.5 Deleting a Budget Step 1 Log in to the Cost Center. Step 2 Choose Budgets. Step 3 Select a budget and click Delete in the Operation column to delete the budget. ----End Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 25
Cost Center User Guide 6 Reports 6 Reports 6.1 Analysis Reports 6.2 Budget Reports 6.1 Analysis Reports On the Cost Analysis page, you can save the analyses that you have created by configuring specific filters or other requirements, as reports. When you view a saved report later on, the system displays the same type of report, but updated with the most recent data. Preconfigured Reports There are seven analysis reports that have been preconfigured by HUAWEI CLOUD for your quick analysis. Preconfigured reports cannot be deleted. They can only be copied and added. Table 6-1 Reports on costs and usage Report Name Description Monthly Costs Types of services with high original costs over the last six by Service Type months Monthly Costs Linked accounts with high original costs over the last six by Linked months Account Daily Costs Daily original costs over the last three months Monthly Monthly amortized costs over the last 6 months Amortized Costs Pay-Per-Use ECS Monthly original costs and usage of a pay-per-use ECS Monthly Costs and Usage Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 26
Cost Center User Guide 6 Reports Table 6-2 Reserved Instance Reports Report Name Description ECS RI Coverage Combined coverage across all of your reserved instances (RIs), and how much of your RI usage is covered by reservations ECS RI Combined usage across all of your RIs, and how much you Utilization saved by using RIs Creating a Cost and Usage Report Method 1: Step 1 Log in to Cost Center. Step 2 Choose Reports > Analysis Reports. Step 3 Click Create Analysis Report. Step 4 Select Cost and usage and click Create Report. Step 5 Configure filters on the Cost Analysis page and click Save Report. NOTE ● For details about the filters, see Viewing Cost Analysis. ● Click in the upper left corner of the page to edit the report name. ----End Method 2: Step 1 Log in to Cost Center. Step 2 Choose Cost Analysis. Step 3 Configure filters on the Cost Analysis page. For details about the filters, see Viewing Cost Analysis. Step 4 Save the report. ● Click Save Report to save the report. The report is named after the current date in the YYMMDD format by default, for example, 210520. You can click the Edit button in the upper left corner to modify the report name. ● Click Save As, specify a name for the report, and click OK. ----End Creating an RI Utilization Report Method 1: Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 27
Cost Center User Guide 6 Reports Step 1 Log in to Cost Center. Step 2 Choose Reports > Analysis Reports. Step 3 Click Create Analysis Report. Step 4 Select RI utilization and click Create Report. Step 5 Set filters on the Reserved Instances > RI Utilization page and click Save As. NOTE For details about the filters, see RI Utilization. ----End Method 2: Step 1 Log in to Cost Center. Step 2 Choose Billing Mode > Reserved Instances > RI Utilization. Step 3 Set filters on the RI Utilization page. For details about the filters, see RI Utilization. Step 4 Save the report. ----End Creating an RI Coverage Report. Method 1: Step 1 Log in to Cost Center. Step 2 Choose Reports > Analysis Reports. Step 3 Click Create Analysis Report. Step 4 Select RI coverage and click Create Report. Step 5 Set filters on the Reserved Instance > RI Coverage page, and click Save As. NOTE For details about the filters, see RI Coverage. ----End Method 2: Step 1 Log in to Cost Center. Step 2 Choose Billing Mode > Reserved Instances > RI Coverage. Step 3 Set filters on the RI Coverage page. For details about the filters, see RI Coverage. Step 4 Save the report. ----End Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 28
Cost Center User Guide 6 Reports Copying a Report Step 1 Log in to Cost Center. Step 2 Choose Reports > Analysis Reports. Step 3 Select a report and click Copy in the Operation column. Step 4 Specify a name for the report, and click OK. Step 5 Configure filters on the Cost Analysis page and click Save As. ----End Viewing a Report Step 1 Log in to Cost Center. Step 2 Choose Reports > Analysis Reports. Step 3 Click the name of a report to go to the Cost Analysis page and view the report details. NOTE ● The most recent cost data is displayed based on the filters configured in the report. ● You can also modify and save the filters. ----End Deleting a Report Step 1 Log in to Cost Center. Step 2 Choose Reports > Analysis Reports. Step 3 Select a report and click Delete in the Operation column. NOTE Preconfigured reports cannot be deleted. Step 4 Click Yes in the displayed dialog box. ----End 6.2 Budget Reports You can create reports for your budgets, and HUAWEI CLOUD will send you the budget reports on a specified day. Important Notes Budget reports are delivered at approximately 02:00 (GMT+08:00) on the specified day. Expired budgets are not included in the reports sent to you. A maximum of 50 budget reports are allowed for an account. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 29
Cost Center User Guide 6 Reports Creating a Budget Report Step 1 Log in to the Cost Center. Step 2 Choose Reports > Budget Reports. Step 3 Click Create Budget Report in the upper right corner of the page. Step 4 Set the report name, select budgets to be included, and click Next. Step 5 Set the report frequency, select the report recipients, and click Next. NOTE A maximum of 50 contacts can be selected for each alert. If you want to add or modify recipient information, go to the Recipient Management page in the Message Center. Step 6 Confirm your budget report information and click Save. ----End Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 30
Cost Center User Guide 7 Billing Mode 7 Billing Mode 7.1 Reserved Instances 7.1 Reserved Instances You can view the usage of the reserved instances (RIs) you have purchased. The amounts shown on the Billing Mode > Reserved Instances page of Cost Center are only estimates. You can view the exact amounts in the bills generated on the third day of the following month. NOTE If the master account and member accounts of an enterprise share RIs, the RI utilization and RI coverage before and after the bill is generated may be different. This is normal. RI Utilization You can learn about the RI usage, including the amounts saved and amortized after using RIs, and monitor the comprehensive utilization rate of your RIs. RI utilization = Number of used RI hours/Number of purchased RI hours x 100% Step 1 Log in to Cost Center. Step 2 Choose Billing Mode > Reserved Instances. Step 3 Click RI Utilization. Step 4 Set search criteria to view the RI utilization. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 31
Cost Center User Guide 7 Billing Mode ① Period: monthly, daily, or hourly. You can query data from the last 18 months. ● Monthly: You can view the utilization data from the last 3, 6, or 12 months. Also you can manually search for data within a specific period (18 months at most). ● Daily: You can view utilization data from the last 7 days, 14 days, 30 days, 3 months, or the month-to-date data. ● Hourly: You can view the utilization data from 00:00 to 24:00. ② displays the utilization data within the queried period. Table 7-1 Description of parameters related to RI utilization Parameter Description Example Pay-per- Pay-per-use costs Example: You purchase an RI with a Use Cost equivalent to the RI duration of 100 hours. The price of a pay- Equivalent hours you have per-use resource with the same used, calculated specifications is $4 USD per hour. This pay- based on the list per-use resource has matched the RI for 6 price. hours. Scenario 1: No upfront fee is charged for RI Cost Cost of used RIs the RI, and the hourly rate is $1.5 USD. amortized by hour. In this case: RI cost = Upfront costs for purchased ● Pay-per-use cost equivalent = 4 x 6 = RIs amortized by $24 USD hour + Cost charged ● RI cost = 1.5 x 6 = $9 USD amortized by hour ● Total net savings = 24 – 9 = $15 USD ● Total potential savings = 4 x 100 – 1.5 x 100 = $250 USD Scenario 2: A partial upfront fee of $40 USD is charged for each RI, and the hourly rate is $1 USD. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 32
Cost Center User Guide 7 Billing Mode Parameter Description Example Total Net Total saved amount In this case: Savings for used RIs ● Pay-per-use cost equivalent = 4 x 6 = compared with pay- $24 USD per-use resources. ● RI cost = 40/100 x 6 + 1 x 6 = $8.4 USD Total net savings = ● Total net savings = 24 – 8.4 = $15.6 USD Pay-per-use cost equivalent – RI cost ● Total potential savings = 4 x 100 – (1 x 100 + 40) = $260 USD Total Potential savings Scenario 3: An upfront fee of $100 USD is Potential that may be charged for each RI. Savings realized if RIs are all In this case: used up. ● Pay-per-use cost equivalent = 4 x 6 = Total potential $24 USD savings = Pay-per- use cost equivalent ● RI cost = 100/100 x 6 = $6 USD for purchased RI ● Total net savings = 24 – 6 = $18 USD hours – RI cost ● Total potential savings = 4 x 100 – 100 = $300 USD ③ displays the utilization trend for the queried period. Example: If you purchase a 100-hour RI and the matched pay-per-use resource has been used for 6 hours, the RI utilization is 6% (6/100 x 100%). ④ Filters: Set the filter to include or exclude what data to display. Table 7-2 Description of filters related to RI utilization Parameter Description Service Type Displays specified service types to get RI utilization. Specification Displays specified specifications to get RI utilization. Code Linked Displays data for enterprise master/member accounts associated Account with the account to get RI utilization. Region Displays data for a specified region (such as CN South- Guangzhou) to get RI utilization. Availability Displays data for a specified AZ to get RI utilization. Zone Operating Displays RI utilization based on the operating system used. System Scope Specifies whether the RI can be used in a given AZ or a region. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 33
Cost Center User Guide 7 Billing Mode Parameter Description Business Displays RI utilization based on the business entity the cloud Entity services belong to. Example: The business entity of direct customers is HUAWEI CLOUD. The business entity of a partner's customers is the same as that of the partner. ⑤ Utilization Objective: If Display utilization objective in the chart is selected, the utilization objective will be displayed in an orange solid line in the chart, based on which you can determine whether the objective has been reached. If the option is deselected, the utilization objective will not be displayed in the chart. Step 5 Click Export to export the RI utilization data in the chart or table. NOTE ● You can click in the upper right corner of the RI utilization list to customize what data is displayed. ● You can select the check box on the left of the RI utilization list to view the utilization of a specified RI. If it is not selected, the average utilization of all RIs is displayed by default. ● When you export the RI data, if there is currently no data, 0% is displayed. Table 7-3 Description of parameters in the exported chart Parameter Description Date Date when an RI is used. ● Query by month: billing cycle when an RI is used ● Query by day: date when an RI is used. ● Query by hour: time when an RI is used. Example: If the value is 2020-06-06 15:00:00, it indicates the RI usage data from 2020-06-06 14:00:00 to 2020-06-06 15:00:00. Utilization Utilization of an RI. Table 7-4 Description of parameters in the exported table Par Parameter Description am ete r Typ e RI Account Name of the account that purchases the RI pro Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 34
Cost Center User Guide 7 Billing Mode Par Parameter Description am ete r Typ e per Order ID Unique order ID of an RI ties Reserved Name and unique ID of an RI Instance Name/ID Start Time Date when the RI takes effect, that is, the time when the RI starts being used End Time Date when the RI becomes invalid, that is, the time after which the RI will no longer be used Scope Specifies whether the RI can be used in a given AZ or a region Region Region where an RI operates. Availability Availability zone where an RI operates Zone Payment Billing mode of an RI, including No upfront, Partial Option upfront, or All upfront RI Type Specifies the RI type. The default value is Standard. Specification Product specifications of an RI Code Number of Number of reserved instances RIs Operating Operating system of the RI. System RI RI Utilization Percentage of used RIs to purchased RIs. stat RI utilization = Number of used RI hours/Number of istic purchased RI hours x 100% s RI Hours How many hours the RI is purchased for within the Purchased specified time range RI Hours How many hours the RI has been used within the specified Used time range RI Hours How many hours the RI has not been used within the Unused specified time range Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 35
Cost Center User Guide 7 Billing Mode Par Parameter Description am ete r Typ e RI Cost Sum of upfront cost for purchased RIs amortized by the hour and costs amortized by the hour. RI cost = Upfront cost for RIs amortized by hour + Hourly cost Pay-per-Use Pay-per-use costs equivalent to the RI hours you have Cost used, calculated based on the list price Net Savings Total saved amount for used RIs compared with pay-per- use resources. Net savings = Pay-per-use cost equivalent – RI cost Potential Potential savings that may be realized if RIs are all used Savings up ----End RI Coverage RI coverage lets you know what percentage of pay-per-use resources are covered by your purchased RIs so that you can evaluate whether you have purchased enough RIs. Coverage = RI covered hours/Total resource running hours x 100% Step 1 Log in to Cost Center. Step 2 Choose Billing Mode > Reserved Instances. Step 3 Click RI Coverage. Step 4 Set search criteria to view the RI coverage. Issue 01 (2021-10-29) Copyright © Huawei Technologies Co., Ltd. 36
You can also read