Traffic
      Management                                CLIENT
         Plan

                                                PROJECT
                                                The demolition and associated works of identified
                                                structures within the Luton and Dunstable Hospital
                                                redevelopment enabling demolition works.
                                                FOR
                                                the planning and management of traffic envisaged for the
                                                project.
                                                AT
                                                Luton & Dunstable Hospital Development,
                                                Lewsey Road, Luton, LU4 0DZ
                                                CONTRACT NUMBER: C12259

                                                DOCUMENT REFERENCE: TMP/12259/MS-1

                                                VERSION: 1               DATE: 12 Feb 2021

ahead Office:              Arden House
                           Arden Road
                           Heartlands
                           Birmingham
                           B8 1DE

                    Tel:   0121 322 2225
                   Fax:    0121 322 2227              THE DEMOLITION AND DECOMMISSIONING EXPERTS
                Website:   www.dsmgroup.info
                 Email:    indo@dsmgroup.info
Traffic Management Plan - Planning Alerts | UK
TRAFFIC MANAGEMENT PLAN                                        www.dsmgroup.info
                                                               decommission / demolish /

Page intentionally left blank

                                Bedfordshire Hospital – C12259 - V1 Traffic
                                Management Plan - 12 February 2021 - Page 2 of 10
Traffic Management Plan - Planning Alerts | UK
TRAFFIC MANAGEMENT PLAN                                                                                 www.dsmgroup.info
                                                                                                        decommission / demolish /

1. DOCUMENT STATUS
document Version: 1

1. 1. DOCUMENT AUTHORISATION

                                  Author                                 Reviewed by
    Name        Matthew Sprayson CMIOSH,                    Stephen Young CMIOSH, MIIRSM,
                DIPRSA, C. Build E MCABE, MIDE,             AIEMA
                MIIRSM, MRSPH, AMCIEHF
  Position      Operations Director                         Health & Safety Manager

 Signature

Note; electronic versions of this document do not contain signatures

1. 2. DOCUMENT HISTORY

                         Revision        Page
    Review Date                                                       Comment / Amendments                                Initials
                         Number         Number
12 February 2021              1                       initial issue                                                          MS

DISCLAIMER
this document is produced as part of the DSM Safe System of Works and is intended to be used as a guide only for the health and
safety DSM’s site operatives, visitors, and adjacent occupiers of the site in question, so far as can be reasonably expected with the
actual knowledge and information available to DSM at the time of issue of this document. as such no reliance should be placed (and
DSM accepts no responsibility whatsoever for the consequences of such reliance) on this document by any person in any contractual
arrangement. this does not affect the statutory rights of any party contracting with DSM under general health & safety law.

                                                                      Bedfordshire Hospital – C12259 - V1 Traffic
                                                                      Management Plan - 12 February 2021 - Page 3 of 10
Traffic Management Plan - Planning Alerts | UK
TRAFFIC MANAGEMENT PLAN                                            www.dsmgroup.info
                                                                    decommission / demolish /

CONTENTS
 1. DOCUMENT STATUS                                                                      3
   1.1. DOCUMENT AUTHORISATION                                                           3
   1.2. DOCUMENT HISTORY                                                                 3

 2. INTRODUCTION                                                                         5

 3. SITE LOCATION                                                                        5

 4. ACCESS TO WORK AREA - PHASE 2 (MAIN WORKS)                                           6

 5. ROUTE TO SITE FROM NEAREST USED MOTORWAY (M40)                                       7

 6. SITE TRANSPORT RULES                                                                 8

 7. RULES FOR DRIVERS                                                                    9

 8. DELIVERY PROCEDURES                                                                  9

 9. REVIEWS                                                                              9

                                    Bedfordshire Hospital – C12259 - V1 Traffic
                                    Management Plan - 12 February 2021 - Page 4 of 10
Traffic Management Plan - Planning Alerts | UK
TRAFFIC MANAGEMENT PLAN                                                                       www.dsmgroup.info
                                                                                                decommission / demolish /

 2. INTRODUCTION
 As with the majority of sites the philosophy from the
 outset has to be planned around the peak traffic flows,
 local restrictions on parking and traffic routes.
 organisation and close coordination of our deliveries are
 essential for the smooth running of the site.
 The DSM Project/Site manager will be appointed ‘traffic
 Management Supervisor’ for the project who will be
 responsible for coordinating deliveries and managing the
 traffic flow to and from the site to minimise impact on
 the local area as required, this traffic plan will be
 amended as required by the project manager or health
 and safety department as the works progress / site works
 progress or the situation on site changes.

 SITE LOCATION

The site is located within the outskirts of Luton Centre, the
site comprises of a number of buildings that are to be
demolished, nonetheless the site is sited within a live
hospital, the main A road is the A505 and the existing road
infrastructure is suitable and sufficient to facilitate the
works.

                                                                Bedfordshire Hospital – C12259 - V1 Traffic
                                                                Management Plan - 12 February 2021 - Page 5 of 10
Traffic Management Plan - Planning Alerts | UK
Bedfordshire Hospital – C12259 - V1 Traffic
Management Plan - 12 February 2021 - Page 6 of 10
Traffic Management Plan - Planning Alerts | UK
TRAFFIC MANAGEMENT PLAN                                                                                                            www.dsmgroup.info
                                                                                                                                   decommission / demolish /

3. ACCESS TO WORK AREA - PHASE 2 (MAIN WORKS)

Access to the site will be via Lewsey Road and then Calnwood Road, we also note that the first section of Calnwood Road is a one way system which has
been indicated accordingly.

                                                                                                   Bedford Hospital – C12259 - V1 Traffic
                                                                                                   Management Plan - 12 February 2021 - Page 7 of 10
TRAFFIC MANAGEMENT PLAN                                                                   www.dsmgroup.info
                                                                                           decommission / demolish /

 4. ROUTE TO SITE FROM NEAREST USED MOTORWAY (M1)
The route from the existing motorway (M1 is shown below)

                                                           Bedford Hospital – C12259 - V1 Traffic
                                                           Management Plan - 12 February 2021 - Page 8 of 10
TRAFFIC MANAGEMENT PLAN                                                                        www.dsmgroup.info

 5. SITE TRANSPORT RULES
 The proposed works/site access will be as described
 above via Lewsey Road and then Calnwood Road, vehicle
 movements/deliveries will be assessed, and larger plant
 and machinery will be delivered outside of the peak
 traffic times for the area, we will also use reasonable
 endeavours to plan vehicle movements to ensure there is
 no disruption to the local traffic infrastructure and
 hospital deliveries.

We haves assessed the area as being normal amount of
public/pedestrian movement within these areas
expected for this type of location within close proximity
of the local Hospital.
                                                            The closes school is 1.69miles from site.
DSM Have further examined the locality of the site and
the following has been noted.

There are no schools within a mile of site, please see
below;

                                                             Bedford Hospital – C12259 - V1 Traffic
                                                             Management Plan - 12 February 2021 – Page 9 of 10
it is imperative that site activities do not impinge
 upon the adjacent roads and pavements. It is noted
 that schools and college pupils may still live within the
 area, i.e. near the Hospital, delivery of plant,                  7. DELIVERY PROCEDURES
 equipment and containers will be limited to the
 quieter times of the day avoiding rush hour and busy              PRIOR TO DELIVERY / COLLECTION
 pedestrian hours as far as is reasonably practicable.           The day prior to a scheduled delivery / collection,
                                                                   the person responsible for receiving the vehicle shall
                                                                   confirm with the (TMS) the particulars of the delivery
 DSM demolition will appoint a traffic marshal for specific        and any proposed changes or requirements. The
 responsibility for traffic control as required. The
                                                                   movement of skips on 8- whe e l lorries will be undertaken
 security/ gate man will provide all subcontractors,
                                                                   in off peak times 09:30-15:00 to minimise the disruption
 suppliers, and the authorities with one point of contact
 for any traffic issues, the traffic Management Supervisor         to local traffic where possible, all drivers will be made
 (TMS) will work closely with our project coordination             aware of the TRAFFIC MANAGEMENT PLAN and will have
 team and transport team.                                          a copy preferably within the cab of their vehicle.
 The (TMS) will carry a mobile phone and will have radio
 contact with key members of the team, he will have                DELIVERY / COLLECTION
 responsibility for ensuring the smooth running of the             The individual responsible for the delivery / collection
 deliveries and unloading activities of the specialist             (usually the TMS) is to be present on arrival and is
 suppliers and subcontractors.                                     responsible for arrival and departure, the deliver /
 All vehicles will leave site in forward gear.                     collection drivers’ ticket will clearly state:
                                                                         • the supplier from whom the delivery is being
 THE TRAFFIC MANAGEMENT SUPERVISOR HAS THE                                  made or the destination of waste.
 AUTHORITY TO REFUSE ACCESS TO ANY UNSCHEDULED
                                                                         • the individual on site who is responsible for
 VEHICLE, WHICH IN HIS OPINION CANNOT REASONABLY BE
                                                                            receiving the delivery where applicable.
 ACCOMMODATED WITHOUT UNDUE DISRUPTION TO
                                                                         • the scheduled time of arrival.
 OTHERS.
                                                                   IF ANY OF THE ABOVE IS NOT CLEARLY STATED THEN
 The vehicle movements will depend on the programmed               ACCESS MAY BE REFUSED.
 works, i.e., soft strip operations, demolition clearance etc
 we would envisage no more than 30 vehicle movements
 in any 1 day.                                                     8. REVIEWS
                                                                   These procedures will be subject to review and updating
                                                                   to ensure the maintenance of an effective traffic system,
  6. RULES FOR DRIVERS                                             all parties will be expected to comply with any necessary
    all drivers on site are required to comply with the            updates and changes of procedures.
    following site safety rules:
          • All drivers on site must wear safety helmets,
             safety footwear and high visibility vest, glasses
             and gloves when dismounting their vehicle.
          • When entering the access off Calnwood
             Street a speed limit of 10mph will be adhered
             too.
          • The instructions given by the designated
             traffic marshal must be followed.
all vehicle/plant lights, warning lights and other warning
devices must be fully functional.
          • the sheeting or netting of loads where
             applicable must be carried out before leaving
             the site.
          • Where ROPS protection is fitted safety
             belts must be worn.

 Bedford Hospital – C12259 - V1 Traffic
 Management Plan - 12 February 2021 – Page 10 of 10