Town Halls - Proposed Golf Cart Path Project
     December 2017 & January 2018         1
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
Agenda
•   Committee Introduction
•   Current Golf Cart Paths
•   History of Golf Cart Paths
•   What We Have Heard & Where Are We
•   Project Detail & Cost
•   Bidding Process and Contractor Selection
•   Funding the Project
•   Summary
•   Next Steps

       Executive Summary                   2
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
Golf Cart Path Renovation Committee
          •   Keith Aspray
          •   Ted Barber
          •   Ted Bartlett
          •   George Beck
          •   Doug Douglas (DIOA Liaison)
          •   Bill Fox
          •   Brian Hollingsworth
          •   Dutchy Lewis
          •   Noel Mears
          •   David Muehl
          •   Lori Murdaugh
          •   Mike Sullivan

DIC Board Chartered – First Meeting March 8, 2017
          Executive Summary                         3
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
What is the Problem?

• 12 miles of asphalt golf cart paths which are an
  integral part of a key DIC member owned asset:
   – Used for managing golf cart traffic on the 2 golf courses
     (50% member participation)
   – Used for recreational purposes (sightseeing, walking,
     jogging, biking) during non-golfing hours
• The golf cart paths are failing at an accelerating rate
• Continued deterioration is detrimental to the golf
  courses and the community as a whole

        Renovate a Valuable DIC Member Asset
              Executive Summary                                  4
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
Goals of the Golf Cart Path Project
If the golf cart paths are renovated, the project must:
• Create a member friendly solution that is safe, value
    added and attractive
• Effectively route paths to remove unnecessary curves
    and under utilized paths
• Identify & install cost effective paths that are low
    maintenance
• Utilize a material that is durable and cost effective
    with long useful life

   7 Options Developed and Extensively Reviewed
             Executive Summary                        5
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
Current Golf Cart Paths

                          6
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
Golf Cart Paths: Failing & Safety Issue

                                          7
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
Golf Cart Paths: Failing & Poor Routing

                                          8
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
Golf Cart Paths: Failing & Drainage Issues

                                             9
Town Halls - Proposed Golf Cart Path Project December 2017 & January 2018 - Proposed Golf Cart Path Project December 2017 ...
History of Golf Cart Paths
• Original 12 miles of asphalt paths constructed in 1985 &
  1991
• Current paths are 32 & 26 years of age
• Golf Course Builders Association: Asphalt path life
  expectancy is 15 years
• 2011 & 2012 significant repairs made to paths to extend
  useful life during course renovations
   – Plan was to rebuild the paths during the golf course renovations,
     but loan requirements stopped the project
   – A 2nd effort in 2015 to renovate the paths was put on hold as the
     outdoor pool project was given top priority
• Paths have reached their useful engineered life and must
  be renovated – they are beyond repair

               Executive Summary                                    10
History of Golf Cart Paths

• Substantial repairs made in 2011 - $246,000
• Asphalt sealant applied in 2012 to extend life 5-7
  years - $48,000
• 2017 budget for patching/repairs is $10,000 and has
  been deferred
• Issues today: Pot holes, cracking, drainage, crumbled
  edging, smoothness and root damage
• Current repairs are a temporary solution with full
  renovation as the long term solution

             Executive Summary                        11
What We Have Heard and Where We Are

                                 12
What We Have Heard & Where We Are
• 7 materials options, pros & cons, costs reviewed with
  110+ Focus Group participants (May/June 2017)
   –   Do nothing (maintenance/patch mode)
   –   Partial concrete/asphalt with “scatter”
   –   Crushed shell/sand mixture/stone
   –   Partial concrete with crushed shell/sand mixture
   –   Polypavement, Flexipave, etc. (pervious materials)
   –   Asphalt (total replacement)
   –   Concrete (total replacement)
 • Emails from Members with options to consider

    32% of Focus Group Participants – Non Golfers
              Executive Summary                             13
What We Have Heard & Where We Are
 Estimated Cost Summary Presented @ Focus Groups
• Do nothing/patching - $300 k per year for 3- 5 years:
  Total $1.5 M
• Partial concrete & scatter $1.7 – $1.95 M
• Crushed shell/sand: $1.7 - $1.9 M
• Partial concrete with shell/sand: $2.1 – $2.3 M
• Polypavement, Flexipave: $2.5 - $3.3 M
• Asphalt – Total Replace: $2.2 – $2.8 M
• Concrete – Total Replace: $2.3 – $2.9 M
Focus Groups - 81% Favored Total Concrete – 12% Asphalt
             Executive Summary                            14
What We Have Heard & Where We Are

• 3 funding options developed and presented
   – A: $5/month dues increase (10 years);
     balance from allocated reserve funds
   – B: One-Time $600 assessment; balance
      from allocated reserved funds
   – C: $300/year dues increase (10 years);
      remaining balance from reserves
   65% Favored Option A   22% Favored Option B
           Executive Summary                     15
Other Factors Considered
• 30 clubs in the area were surveyed and 78% have
  concrete/asphalt paths
• 4 clubs visited with various materials used for paths
      Callawassie - Asphalt
      Berkeley Hall - Concrete
      Long Cove – Overlay Asphalt
      Colleton River – Concrete with shell/sand mix
• Superintendents were questioned regarding best
  material for maintenance and longevity – concrete
  preferred
 Direction Chosen – Bid Total Asphalt and Concrete
                   Replacement
            Executive   Summary                           16
Request for Proposals and Bidding Process
                                                      REQUEST FOR PROPOSAL (RFP)
• Request for Proposals                                    DATAW ISLAND CLUB
                                                      CART PATH RENOVATION PROJECT
  (RFP’s) were developed
  for the formal bidding
  process
• Concrete and asphalt                                                     DATAW ISLAND CLUB
                                                                             100 CLUB DRIVE

  were bid                                                               DATAW ISLAND , SC 29920

• 4 National Golf Course                                                                    8/1/2017

  Renovation and Cart Path    TABLE OF CONTENTS
  companies bid the project   1.   SUMMARY AND BACKGROUND ............................................................................................. 2

• Bids were submitted
                              2.   PROPOSAL GUIDELINES......................................................................................................... 2
                              3.   PROJECT PURPOSE AND DESCRIPTION ................................................................................... 3
  October 1                   4.
                              5.
                                   PROJECT SCOPE..................................................................................................................... 4
                                   REQUEST FOR PROPOSAL AND PROJECT TIMELINE................................................................ 5
• Negotiated with 2 lead      6.   BUDGET ................................................................................................................................ 5
                              7.   BIDDER QUALIFICATIONS ..................................................................................................... 6
  bidders – reduced project   8.   PROPOSAL EVALUATION CRITERIA ....................................................................................... 6
  cost
             Executive Summary                                                                                                                                                 17
Tree Strategy
• Golf Course design guidelines – tree removal within 5
  feet of path
• Project guidelines – remove only hazardous or
  encroaching – all potential trees not removed
• Certified Arborist reviewed all trees for disease and
  hazards (stress cracks, leaning, trip hazard, utility
  encroachment)
• Goal is to protect the future path work from long term
  root damage
• Ongoing root pruning will be required due to limited tree
  removal

 Staff, Path Committee, County and Certified Arborist
                 Engaged
             Executive    in Process
                         Summary                     18
Tree Strategy
• Tree Survey: 146 Trees significantly impacting cart
  paths:
   – No Live Oaks to be impacted
   – Pines: 95 trees causing major path issues
      • 44 hazardous/51 healthy
   – Laurel/Water Oaks: 44 causing major path issues
      • 38 hazardous/6 near end of life
   – Balance: 7 other types (Sweet Gum)
   – Limited tree removal – future damage is possible
      • Aggressive root pruning to mitigate future problems

 146 Trees for Potential Removal – Review Continues
              Executive Summary                               19
Tree Examples

Executive Summary   20
Project Execution and Timeline

•   Project start date: August 6, 2018
•   Completion date: December 31, 2018
•   Process begins with old path incorporation
•   Grading and drainage improvements
•   New concrete paths formed and installed
•   Sod installed as each hole is complete
•   3-5 holes closed to play to accommodate work
•   Any tree work to begin prior to construction

            Executive Summary                  21
Bid Results and Project Cost

  Executive Summary            22
Bid Results
Contractor          Landscapes    Environmental Southeastern Bennett
Pricing-Items       Unlimited     Solutions                  Paving
Mobilization        $220,000      $10,000       $30,000        $7,875
Cart Path Work      $1,689,877    $2,295,506    $2,240,554     $3,239,958
Sod                 $342,000      $67,162       $107,000       $335,916
Drainage            $76,005       $64,176       Not included   Not included
Root Pruning        $37,500       $15,400       Not included   Not included
Testing             included      $35,000       Not included   Not included
Total-Concrete      $2,365,382    $2,487,244    $2,377,554     $3,556,748
Landscapes
Diseased Trees Unlimited
                $133,415 Bid is Not$133,415
                         $133,415    to Exceed   (NTE)
                                             $133,415

County Mitigation   $41,020       $41,020       $41,020        $41,020

Fill Dirt           $57,600       $57,600       $57,600        $57,600
Contingency         $150,000      $150,000      $150,000       $150,000
Total-Concrete      $2,747,417    $2,869,279    $2,760,589     $3,938,783
Total-Asphalt       $2,823,150    $3,916,818    Not Bid        $3,461,830

DIC Board Recommends Project with Landscapes
       Unlimited as Preferred Contractor                                      23
Landscapes Unlimited

• Golf course construction and renovation
• Lincoln, Nebraska based: 41 Years in business
• Completed over 1800 golf course projects with a value
  of $2.5 billion
• Constructed 250 new golf courses which included path
  systems
• “The Cart Path Company” – subcontractor for concrete
  path system
• Recent local projects: The Landings - Skidaway Island,
  GA; The Oaks – Osprey, FL; Quail West – Bonita
  Springs, FL; The Atlanta Athletic Club – Johns Creek, GA
             Executive Summary                           24
Landscapes Unlimited Projects

                                            Fiddlesticks Country Club Fort Myers, FL

      TheCounty
Broadmoor WalkerClub
                Course Clemson,
                     Colorado   SC CO
                              Springs,         The Reserve at Lake Keowee Sunset, SC

    Sea Dallas
        Pines Country
                      Executive Summary
                       Club Dallas,
               TX National  Hilton Head,
                                    TX SC        Sandy Lane Resort St. James, AL
                                                                                       25
Project Funding

Executive Summary   26
Definitions
Settlement funds
• When Alcoa (developer) turned assets over to Dataw
  Island Club members, the exit settlement awarded
  to the DIC was close to $5 million dollars. Approx. $4
  million in cash plus the sales center building.
Use of Settlement Funds
• When Alcoa departed, the Club was operating at an
  annual loss of close to $500,000. The Club uses the
  Alcoa settlement funds to subsidize dues and cover
  the operating loss. These funds are only used to
  offset operating shortfalls and are not used for
  capital projects or renovations.

                                                        27
Definitions
DIC Reserve Funds
• $13,500 of the $17,500 initiation fee and a portion
  of Base membership dues are allocated to the DIC
  reserve fund. These funds are used for Capital
  improvements and the long term renovation and
  renewal of DIC assets. On average we spend
  $750,000 per year on capital improvements to DIC
  assets. The 2017 year end reserve balance is
  projected to be $2,362,000.

                                                        28
Definitions
One Island Concept
• All resident members as of June 2001 are club members.
• Club members own all of the assets of the Club
• All sports amenity facilities and assets are owned by the
  members even if not participating in a sports package
• DIC Bylaws state all assessments are borne equally by all
  club resident members.
• Long term maintenance and upgrading of club facilities
  adds value to real estate on the island and provides a
  competitive advantage
• Country Club members cannot be assessed since the
  memberships are callable and they do not own the assets

                                                              29
How Do We Fund the Project?
Concept

• Provide viable financing options for completion of
  cart path renovation/replacement project

• Use a portion of current & future reserve
  contributions to service a loan. Reallocates what we
  currently put into Reserves from Base dues

Minimize the financial impact to members

                                                       30
How Do We Fund the Project?

Actions to date

• In 2014 we began allocating a larger portion of Base
  dues to Reserves for future capital projects.

• New membership plan & long range budget originally
  projected approx. $20/month of base dues allocated
  to Reserves, however, the allocation was increased to
  $34/mo in 2016 and $36/mo in 2017.

                                                         31
How Do We Fund the Project?

Basic Data

Assumes Cart Part Project Cost of:        $2,750,000

Borrow @4-5% for 10 years                 $2,000,000
Use from Current Reserves                 $ 750,000
Total Funding                             $2,750,000

15 Year Amortization / 10 year estimated payoff
      - Loan paid off by year-end 2027
                                                       32
How Do We Fund the Project
$5/month member assessment
• 2018 Base Dues allocation to reserves increased to
  $40/month/member
   – $20/month to Reserves based on original projections
   – $20/month to loan repayment
• Continue to increase Base Dues @ the Taskforce
  recommended rate of 5% until DIC operates at
  breakeven
• $5/month/member additional base dues assessment
  ($60/year) which goes directly to loan repayment
                                                           33
How Do We Fund the Project

Monthly Base Dues        2017    2018
Base Dues                $317    $333
$5/mo Assessment         $ 0     $ 5
Total Base Dues          $317    $338

• $5/month assessment continues for 10 years
• $60/year = $600 over 10 years

                                               34
How Do We Fund the Project

Bottom Line Impact
• Negligible as the Base dues to Operations does not
  change from the original plan

• Reserve Balance by year end 2027 is projected to be
  approx. $3.5 to $4 M when Cart Path loan is paid off

• Other Capital Projects not impacted and we are still
  maintaining a reserve balance above the original 10
  year plan

                                                         35
Summary

          36
Summary
• DIC Board and Committee Recommending Project
  Approval
  – Replace current paths with concrete (cost effectiveness)
  – Project start date of August 6, 2018
  – ~5 month project completion with rolling hole closures
  – Investment protection: drainage improvements & limited
    tree removal
  – Budgeted cost of $2.75 M; Project is in Price Range
    Expected
  – Funding:
      • Bank loan of $2 M at 4-5% for 10 years
      • Balance of project cost from Reserves
      • Dues increases of $5/month/member for 10 years ($60/year)

           Replacement of a Valuable Asset                     37
What’s Next?
• Committee will work with LU to further value engineer the
  project (costs and benefits)
• Tree canopy review continues requiring county’s feedback
  (balance asset protection and island’s beauty)
• Final review with DIC Board in January 2018
• Ballots to be mailed to DIC Members in January 2018
   – Annual DIC Meeting February 2018
   – For project to proceed requires >50% approval from
     voting members

 The DIC Board supports this project and recommends that
                   members Vote Yes

   Thank Executive
         You for Your Summary
                      Support and Attention               38
Questions

Questions: cartpathproject@islc.net

                                      39