TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland

Page created by Robert Bennett
 
CONTINUE READING
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
TII M17 M18 Gort to
Tuam PPP Scheme
DirectRoute Presentation | 12th September 2018
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Outline of Presentation

                                  Overview of the Project & PPP Structure
                                  Declan Carney, DR General Manager, Construction
                                  Stage
                                  Design and Construction Challenges
                                  Eamon Daly, Design Project Manager, Barry
                                  Transportation
                                  Emer O’Dea, Design Project Manager, Arup
                                  Operations and Maintenance Phase / Life-Cycle
                                  Niall Lyons, DR General Manager Operations
                                  Stage

                                  Q and A

M17 M18 Gort to Tuam PPP Scheme
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Overview of the Project &
                  PPP Structure
                  Declan Carney, DR General Manager, Construction Stage

M17 M18 Gort to Tuam PPP Scheme
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Overview of the Project

     4.2 km N17                   M17 26 km
                                                  N18 27km Oranmore –
     Tuam Bypass                  Galway –
                                                  Gort CPO 2006
     CPO 2005                     Tuam CPO 2007
M17 M18 Gort to Tuam PPP Scheme
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Overview of the Project
          IRELAND GDP FROM CONSTRUCTION - €m
          SOURCE: TRADINGECONOMICS.COM I CENTRAL STATISTICS OFFICE IRELAND

                                                            2005 – 2007      2008   June 2009-2014 - PPP Procurement   2014 -2016
                                                                                    (4 consortia)
                                                                             N18                                       Mobilisation,
                                                                                    • Stage 1 – Nov 2009               advance work &
                                                            3 Planning       D&B
                                                                                                                       design            2017 -
                                                            Approvals               • BAFOs – Aug 2010 and Aug
    1999 – 2006                                                                                                                          2042
                                                                                      2011
                                                                                                                          2015 – 2017
    •    Route Selection                                                                                                                 O&M
                                                                                    • Suspended 2012 – 2013
    •    Environmental Assessment                                                                                         Construction
                                                                                    • Contract Close – 30/04/14
    •    Preparation Planning Approvals

                                  PLANNING                                            PROCUREMENT                             D&B         O&M

M17 M18 Gort to Tuam PPP Scheme
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Overview of the Project

                                  Timetable               Target              Actual

                                  Permit To Use         30/11/2017         30/11/2017

                                  Completion            28/02/2018         19/12/2017

                                  Road opened early & in full to traffic on 27th September
                                                          2017

M17 M18 Gort to Tuam PPP Scheme
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Employer: Transport                              Sponsors Shareholding
                                                                                 Infrastructure Ireland (TII)                  Lagan Project Investments Ltd (10%)
                                                                                                                                PPP Road Holdings Ltd (10%) (Sisk)
                                                                                                                                         Strabag SE (10%)
                                                                                                                                                                                 Consultant Agreements
                                                                              NRA PPP Contract                                 Motorway West Ltd (10%) (Roadbridge)
                    Funders (EIB, Natixis, Societe                                                                           Road Infrastructure (Irl) Ltd (10%) (InfraRed)
                    Generale and Bank of Ireland)                                                                               Marguerite Road Ireland Sarl (50%)
                                                           Funding Agreements
                                                                                         PPP Co
                                                                                  DirectRoute (Tuam) Ltd
                                                                                                                                                  Shareholders agreement
                                                        Design & Build
                                                      Construction Contract
                                                                                                                 100%
                       Direct Agreement                                                                       Shareholding
                                                                                                                                DirectRoute (Tuam) Holdings Ltd

                           Construction Joint Venture
                           DirectRoute (Tuam) Construction Ltd                                                                   O&M Contract
                           Lagan Construction Group Ltd                                                                                                            Advisers to DirectRoute
                           Roadbridge                        25%                                                                                                  Financial: Societe Generale
                           John Sisk & Son (Holdings) Ltd    Each                                                                                                    Legal: A&L Goodbody
                           Strabag AG                                                                                                                             Insurance: AON & Glennon
                                                                                                                                                                    Tax & Accounting: BDO
                                                                                                                        PCGs (Jt and Sev)
                     D&C Works Agreement                                                                           Lagan Constr Group Hldgs Ltd
                                                                                                                            Sicon Ltd
                                                                                                                           Strabag SE
                                                                                                                           Roadbridge

                 Delivery Partner          Delivery Partner            Delivery Partner
                  South (Lagan)             Centre (Sisk)             North (Roadbridge)
                                  Design Agreements                                                                                                              O&M Sub-Contract
                                                                                                                      Interface Agreement

                                                                                                                                                            A-Way Lagan Infrastructure
                                                                                                                                                               Services Ltd (ALIS)
                         Design Team        Design Team       Design Team
                            South              Centre             North                     Collateral Agreement
                                                                                                 And step-in                 PCGs (Jt and Sev)
                                          Design JV (DJV)                                                             Lagan Constr Group Hldgs Ltd
                                                                                                                              Strabag SE
                                    Arup & Barry Transportation
M17 M18 Gort to Tuam PPP Scheme
                                                                                                                                                                                  Direct Agreement
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Delivery Structure                                               Authority:
                                                      Transport Infrastructure Ireland

                                                          PPP Contract

                                                                      PPP Co
                                                               DirectRoute (Tuam) Ltd

                                       Design & Build Construction
                                                Contract

                                                           Construction Joint Venture

                                                      DirectRoute (Tuam) Construction Ltd

                                     D&C Works Agreements

                                            Delivery Partner    Delivery Partner        Delivery Partner
                                             South: Lagan         Centre: Sisk          North: Roadbridge

                                  Design Agreements

                                                                 Design JV (DJV)

                                                           Arup / JB Barry Transportation

M17 M18 Gort to Tuam PPP Scheme
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Design & Construction Sections

                          JB Barry Transportation   Arup

M17 M18 Gort to Tuam PPP Scheme
TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
Refinancing
• Funding markets at Financial Close April 2014
  were generally closed to Ireland
• Improvement in funding market terms and
  liquidity in the two year period from financial
  close
• Recognised clear refinancing opportunity -
  highly unusual in the construction stage
• Refinancing Financial Close in May 2016
• Significant savings delivered to the Authority in
  line with the Project Agreement
• Change in identity of lenders
• Comparatively low transaction costs

M17 M18 Gort to Tuam PPP Scheme
Health & Safety

M17 M18 Gort to Tuam PPP Scheme
Safety Initiatives
•      Project Safety Forum

•      Bespoke training “black hat” for all supervisors

•      Common SOR system with trend analysis and
       information sharing.

•      Safety Incentive Scheme

•      H&S Newsletters

•      Stand downs/ Safety Days / Impact Speakers

•      Full Class 3 high vis PPE

•      10 minute “Safety Chats”

•      Worker surveys
    M17 M18 Gort to Tuam PPP Scheme
Design and Construction
                  Challenges
                  Eamon Daly, Design Project Manager, Barry Transportation
                  Emer O’Dea, Design Project Manager, Arup

M17 M18 Gort to Tuam PPP Scheme
Outline of Design and Construction Challenges

•   The Design Team
•   Design Challenges
•   Flooding and Drainage
•   Geotechnical Design
•   Pavement
•   Environmental Design and Mitigation
•   Key Structures and Junctions

M17 M18 Gort to Tuam PPP Scheme
Design Joint Venture

• Design Joint Venture consists of joint venture between Barry Transportation and Arup
• Tender Design was completed in 2010 and formed the Conceptual Design
• Barry Transportation were designers for the northern half of the scheme, Arup designers
  for the southern half of the scheme
• Detail Design commenced in May 2014 with the preparation of a Design Manual to
  standardise design approach across the Scheme
• Max Design Team at Peak: Design Office: 93 Site: 25

M17 M18 Gort to Tuam PPP Scheme
Scheme Information – Key Elements

• 53km of Standard Dual Carriageway Motorway
• 4km of Type 2 Dual Carriageway
• 4 grade Separated junctions including a major junction with the M6 Motorway
• Link Roads, Side Road Diversions and Access Roads
• 71 Principal Structures including road bridges, river bridges, rail bridges, footbridges,
  accommodation bridges and culverts,
• 33 other structures including retaining walls, gantry signs and VMS signs
• Fencing, Safety Barriers, drainage, communications, earthworks, signage, lining,
  landscaping, lighting, utilities, environmental and ancillary road works

M17 M18 Gort to Tuam PPP Scheme
Key Design Challenges
• Three Contractors – Two Designers – Design
  Consistency
• Three Separate Design Supervision Teams with a
  head DSR overseeing all three
• The design of significant Peat areas within the
  Tuam Bypass and on the M17 south of Tuam
• Design of earthworks through areas of significant
  karst risk across all sections
• Drainage in areas of regionally sensitive aquifers
• Extensive seasonal flooding
• Environmental
• Structures
• Pavement
M17 M18 Gort to Tuam PPP Scheme
Flooding
    November
    2015

M17 M18 Gort to Tuam PPP Scheme
Flooding
    November
    2015

M17 M18 Gort to Tuam PPP Scheme
Mitigation against Flooding

• Drainage Blanket
• Road Design Levels
• Flood Relief Culverts

M17 M18 Gort to Tuam PPP Scheme
Road Drainage
Objectives

• The speedy removal of surface water from running carriageway areas

• The minimisation of the risks of pollution and flooding of receiving water bodies
  including measures to minimise the risk of accidental spillages causing pollution and to
  provide significant removal of suspended solids and other contaminants

• The removal of sub-surface water to protect pavements and associated earthworks.

M17 M18 Gort to Tuam PPP Scheme
Road Drainage - Pavement Drainage at transition areas
• Speedy removal of surface water –
  related to pavement gradient
• Potential flat spots at transition areas on
  sections of road with shallow gradients
• Solution - Rolling Crowns – Application
  of superelevation along a diagonal crown
  line across the carriageway
• Maintains minimum 2.5% carriageway
  gradient
• Sufficiently long to achieve satisfactory
  ride quality
• Particular care required with
  construction

M17 M18 Gort to Tuam PPP Scheme
Road Drainage

Types of Road Drainage Systems –
Sealed Drainage Areas
• Kerb Slot Drain / Carrier Pipe
• Kerb and Gully system with Carrier
  Pipe
• Combined Kerb Drainage Units –
  Envirokerb
• Median Drainage – Slot Drains /
  gullies
• Filter Drains also provided only to
  drain non contaminated run off and
  control groundwater levels

M17 M18 Gort to Tuam PPP Scheme
Road Drainage
Median Slot Drain

M17 M18 Gort to Tuam PPP Scheme
Road Drainage

Types of Drainage Systems – Non
- Sealed Drainage Areas
• Over the edge drainage
• Filter Drains

Sub Surface Drainage
• On embankments – extension
  of capping
• In Cuttings and Low
  embankments – Narrow Filter
  Drains

M17 M18 Gort to Tuam PPP Scheme
Road Drainage

Pollution Control
• Silt trap gullies
• Catchpits used throughout the
  scheme where possible
• By pass petrol / Oil interceptors
• Attenuation Ponds
• Infiltration ponds
• Pollution Control Forebays in all
  attenuation / Infiltration ponds

M17 M18 Gort to Tuam PPP Scheme
Road Drainage - Attenuation

Attenuation pond                    Infiltration Pond

  M17 M18 Gort to Tuam PPP Scheme
Road Drainage - Attenuation

Constructed Wetland and
Soakaway
• Infiltration System
• Excavation in Rock
• Proximity to SAC and Local
  Group Water Scheme
• Area of Seasonal Flooding

M17 M18 Gort to Tuam PPP Scheme
M17 Soft Ground
Treatment
•      Approx. 3km of soft ground
•      Vertical band drains at 1.0m
       spacing
•      Up to 7m of embankment
•      1.5 years duration
•      Constant monitoring of
       instrumentation. PWP,
       inclinometers, settlement
       plates, etc.

    M17 M18 Gort to Tuam PPP Scheme
M17 Soft
     Ground
     Treatment

M17 M18 Gort to Tuam PPP Scheme
M17 Soft Ground
     Treatment
     •    600mm lifts
     •    3-4 month hold
          periods
     •    PWP monitoring
     •    1500mm of
          settlement predicted
     •    1500mm of
          settlement achieved

M17 M18 Gort to Tuam PPP Scheme
M17 Rock excavation

• Approximately 1.8M m3
  of rock excavation
• 2m rock bench at top
• Majority blasted and
  then excavated by
  machine to achieve the
  slope angle
• Excavated to a 1:0.5
  slope
• https://www.youtube.c
  om/watch?v=7GNnT-
  oO8_k

M17 M18 Gort to Tuam PPP Scheme
Karst risk assessment and standard detail development
 Desktop Study                                    Site Walkover
 GSI Geology map and karst landforms via ArcGIS   New features identified

M17 M18 Gort to Tuam PPP Scheme
Karst risk assessment and standard detail development
                                                            • 1km Sections
                                                              Assessed

                                                            • Risk Assessment
              Length (m)          % of alignment   Risk       based on
              9+530               43               High       overburden cover,
                                                              rock type, density
              11+510              52               Medium
                                                              of karst and
              1+160               5                Low        proximity to the
                                                              scheme

M17 M18 Gort to Tuam PPP Scheme
Karst risk assessment and standard detail development

M17 M18 Gort to Tuam PPP Scheme
Karst risk assessment and standard detail development
                                                            • Geotextile
                                                              Requirement
                                                              reduced to
OB89 – Karst Uncovered

M17 M18 Gort to Tuam PPP Scheme
Karst shown in
  geophysics
  at west
  and central pier
  during
  construction

M17 M18 Gort to Tuam PPP Scheme
Option 1 – Leave OB89 in place and remediate karst
                                        Central pier
                                                                         Phase 1 rotary percussive and
                                                                      geophysics 3 to 4m above formation
                                                                                  COMPLETE

                                                                         Phase 2 Ground investigation –
                                                                       geophysics at actual formation and
                                                                       rotary percussive probes on grid to
                                                                           estimate extent of feature

                                                                     Phase 3 Create safe working platform
                                                                    and carry out shell and auger boreholes
                                                                    to determine soil parameters and rotary
                                                                    coring 3m into rock for rock parameters

                                                                              Clear out feature
                                                                               and determine
                                                                                   extent

                                     Backfill feature
                                  beneath pavement to
                                          SED

                                                           Scenario A                                        Scenario B
                                                     If void beneath structure
                                                 foundation is small, backfill with                If feature is large and in filled
                                                 inverted filter and design slab to               with overburden and rock is at            Scenario C
                                                            span feature                          depth, design skin friction piles
                                                                                                                                        If feature is large and
                                                                                                                                       rock is present, design
                                                                                                                                          rock socketed piles

M17 M18 Gort to Tuam PPP Scheme
Scenarios B and C – Piled Solutions

                                                             ????             ????

                         Either piles bearing in soil and                            Base of central pier at
                            on rock or 3m into rock –                                  18.6 m OD malin
                             dependent on depth of          Type, depth, permanent casing
                        competent rock from boreholes       and number TBC post design

M17 M18 Gort to Tuam PPP Scheme
Proposed alternative
                                                               locations and additional
                                                               ground investigation
     OB89:
     How did we
     fix this on
     Site?                        New location chosen
                                  approximately 20m north of
                                  the original

M17 M18 Gort to Tuam PPP Scheme
M17 Ballinphuil Overbridge

 •     Large Void 12m x
       8m
 •     Clay filled =
       inactive
 •     8 conduit karst
       features above
       the void – 600mm
       wide
 •     Smooth edges,
       flowing water =
       active
M17 M18 Gort to Tuam PPP Scheme
                                  Map all available information
Ballinphuil: How did we
fix this on Site?
•       Design already issued for
        construction - 5mm
        settlement limit at central pier

•       Inactive void – infilled with
        Class 6N2 and blinded with
        concrete

•       Active conduits – backfilled
        with 0.5m no fines concrete

•       Backfill with concrete to
        underside of pier
M17 M18 Gort to Tuam PPP Scheme
Tuam Bypass
                                  Ballygaddy Overbridge

                                  Explorations Carried Out
                                  •   4 Rotary Cores
                                  •   1 CP Hole
                                  •   5 trial pits
                                  •   6 Geophysical resistivity
                                      profiles
                                  •   Ground conductivity survey
                                  •   Karst Features Protocol
                                      Followed

M17 M18 Gort to Tuam PPP Scheme
Tuam Bypass - Ballygaddy Overbridge

  • Large Active Linear
    Karst Feature
  • Saturated sand
    filled void
  • 3.5m width
  • Over 20m in length
  • Depth to solid rock,
    13m

M17 M18 Gort to Tuam PPP Scheme
Ballygaddy Overbridge
Linear Karst Feature-
Geophysics

• Resistivity Profiles and
  Ground Penetrating Radar
  to verify location

• Additional drilling to
  determine ground
  condition for foundation

M17 M18 Gort to Tuam PPP Scheme
Ballygaddy
   Overbridge –
   How did we fix this
   on site?

   • Void infilled with Class
     6C material

   • Slab spanning feature

   • Supporting overlying
     structure

M17 M18 Gort to Tuam PPP Scheme
Pavement Design
Mainline - Analytically designed Flexible
Composite Pavement
Non-Project Road – Standard Method

• Why analytical design?
• Common on many PPP Projects
• Based on customising design to locally
  available materials and construction
  methods
• Maximise whole life value
• Additional testing in situ
• No negative construction tolerances
M17 M18 Gort to Tuam PPP Scheme
Why Flexible Composite Pavement?
• Site won Aggregate – very significant limestone rock ideal for aggregate
    • Sustainable use of Material
    • Cost Efficiency

• Flexible Composite design in soft ground?
• Assumed foundation CBR of 15% proved through testing
• Primary settlement fully achieved and significant secondary settlement achieved through
  maintaining surcharge beyond required design period
• Use of geosynthetics as reinforcement to pavement layers eg Kilmore Roundabout
• Reduced crack induced spacings to 2m.

• All of this reduced the potential for settlement or reflective cracking
M17 M18 Gort to Tuam PPP Scheme
Comparison of Analytical and Standard Pavement Construction
                      Mainline – 56msa and CBR >15%
                   Layer          Clause   Material        Grade of       Analytical   Standard
                                                           Binder         Thickness    Thickness
                   Surface        942      SMA 10 surf                    30           30
                   Course                  PMB 65/105-
                                           60 des
                   Binder Course 929       AC 20 dense     40/60          55           55
                                           bin des
                   Upper Base     929      AC 32 dense     40/60          75           95
                                           base des
                                                      Thickness of Asphalt 160         180
                   Lower Base     822      CBGM B                         180          180
                                           C12/15
                   Sub-base       808      Type B                         100          300
                   Capping        613      6F1 or 6F2                     -            150
                                                      Total Thickness (mm) 440         610
M17 M18 Gort to Tuam PPP Scheme
Environmental Challenges                                   cSAC – Candidate Special Area of
                                                           Conservation,
                                                           pNHA – Potential National Heritage Area,
                                                           SPA – Special Protection Area,

• Scheme encroaches into the catchment area of a
                                                           SNR – Statutory Nature Reserve

  number of SACs their associated river networks
       • Lough Corrib SAC
              • Abbert River
              • Grange River
       • Coole – Garryland Complex (SAC, pNHA, SPA, SNR)
       • Kiltiernan Turlough (SAC, pNHA)
       • Rahasane SAC
              • Dunkellin River
• Scheme is also adjacent to Nationally rare plants
  – Mudwort, Dropwort, Alder, Buckthorn, Lady’s
  Tresses, Orchid and Wood Bitter Vetch

M17 M18 Gort to Tuam PPP Scheme
Environmental Challenges
 Whooper Swan                             Pine Martin                         Bewicks
                                                                              Swan

The habitats of
protected
species that are
located within
the scheme
                                  Otter                 Lesser Horsehoe Bat
M17 M18 Gort to Tuam PPP Scheme
Environmental Mitigation

M17 M18 Gort to Tuam PPP Scheme
Environmental Mitigation –Bats
• EIS - “Guidelines for the Treatment of
  Bats during the Construction of National
  Road Schemes” – DMRB
• Bat Conservation Ireland - Consultation
• Early Landscaping Works
• Bat Hop-Over Points - consisting of
  diamond shaped areas with existing or
  semi mature tree vegetation either side
  of the road – 2.5-3.5m in height at 5-7m
  centres
• Stone Cladding and Bat Boxes provided
  on River Bridges catering for all bat
  species
M17 M18 Gort to Tuam PPP Scheme
Environmental Mitigation – Lesser Horseshoe Bats
• Lesser Horseshoe Bats
       • International Importance
       • Dramatic declines in population in Ireland
         and extinction in parts of Europe
• Coole Green Bat Bridge
       •   Only bridge of its kind in Ireland
       •   Twin Arch Structure
       •   Hedgerow vegetation to guide bats
       •   Feeding grounds either side and a roosting
           site in Kiltartan Cave

M17 M18 Gort to Tuam PPP Scheme
Structures - Coole Green Bat Bridge
• Twin Arch Pre-Cast Concrete Buried Structure
• 1:2 sloping elevations topsoiled and landscaped

M17 M18 Gort to Tuam PPP Scheme
Structures - Ballygaddy Overbridge
Concept Design
- Cambered Steel Beams
- Long span variable depth beam bridge
  Plan on Highway Alignment              Elevation on Concept Design

                                             Crest Curve –
                                             330m Radius

M17 M18 Gort to Tuam PPP Scheme
Detailed Design
•    Innovative precast concrete pretensioned super-Y beams
•    40m Span, 16m wide, 16deg Skew
•    Varying depth beams – parabolic top profile
•    Level beam soffit

    M17 M18 Gort to Tuam PPP Scheme
Rathmorrissy Junction
• 3 Level Motorway to             M6 to
  Motorway Interchange            Galway

• Largest junction in Ireland
• Circulatory Carriageway –
  1km – longest in Ireland
• Design Optimisation
• Roundabout - Oblong Shape
      • Reduced Earthworks
        Heights
      • Reduction of radii on
        structures
                                           M6 to
• Steepened Slopes                         Dublin

• Reduction of over
  100,000m3 achieved
M17 M18 Gort to Tuam PPP Scheme
Rathmorrissy Junction
• 5 Bridge Structures
  Required
• 3 Underbridges carrying
  the M18 mainline over the
  circulatory carriageway
• Single Spans over the
  existing M6 – no works in
  median
• Overbridges over the live
  M6 motorway installed at
  night
       • Eastbound – rolling
         closures
       • Westbound – closure and
         local diversions
M17 M18 Gort to Tuam PPP Scheme
Operations and Maintenance
                  Phase / Life-Cycle
                  Niall Lyons, DR General Manager Operations Stage

M17 M18 Gort to Tuam PPP Scheme
O&M Requirements
     • 25yr O&M Contract for the Project
       Road, Project Road being smaller in
       extent than the road constructed
     • Availability based contract
     • No tolling of the road
     • O&M requirements set out in
       Schedule 7 – very prescriptive
       maintenance and inspection
       requirements
     • Operations to be carried out in
       accordance with TII Publications and
       the Traffic Signs Manual

M17 M18 Gort to Tuam PPP Scheme
O&M Phase Set Up
    • Long term O&M Contractor (A-way Lagan
      Infrastructure Services aka ALIS)
    • PPP Co responsible for lifecycle works
    • Extensive plant & equipment required to
      provide O&M services
    • Centrally located depot
    • Long-term local employment
        • All employees are local.
        • Local specialist subcontractors –
          pavement testing, plant hire

M17 M18 Gort to Tuam PPP Scheme
Winter Maintenance
     • Precautionary treatment where ice, frost
       or snow conditions are forecast to occur
     • 3 winter maintenance routes, all to be
       completed within 2hrs
     • Duty Officer and winter maintenance
       team on call 24/7
     • Use of pre-wet system
     • Plant & Equipment
         • 4no. Prewet gritting trucks with snow
           ploughs
         • Brine batching plant
         • 1000 tonne salt store
         • Vaisala ice forecast software
         • Weather Station

M17 M18 Gort to Tuam PPP Scheme
Winter Maintenance – Storm
     Emma
     • Storm Emma – 26th February to 4th March
     • Storm Emma in numbers;
         • 34no. Prewet treatments
         • 27no. Dry treatments
         • 350 tonnes salt used
         • Procured additional gritter and loading
             shovel
         • Hotel rooms booked for staff
         • Gritting and ploughing non stop for 3
             days
     • All lanes kept open
     • Particular issues
         • Getting to motorway
         • No traffic to help activate the salt

M17 M18 Gort to Tuam PPP Scheme
Asset Management -
  RMMS
  • Steanne Solutions Geoworks 7 RMMS used for all asset
    management excl Structures and major capital structural
    maintenance of pavements
  • All inventory on Project Road recorded via As Built survey and
    inputted into RMMS
  • Requirements of RMMS
      • Store and manage inventory data
      • Take details of Safety and Detailed Inspections and turn
         them into a program of work
      • Produce schedules of inspections and required cyclical
         activities
      • Be able to produce lists of outstanding Defects grouped
         together by date, category, activity or Defect
      • Have facility to audit performance
      • Have an archiving feature to maintain records
  • All defects are categorised – Category 1 , Category 2 High,
    Medium and Low, Category 3
  • All defects have a required initial response time and permanent
    repair time
M17 M18 Gort to Tuam PPP Scheme
Structures Maintenance
     • 75 no. Structures on Project Road (32
       over bridges, 14 under bridges, 15
       gantries, 4 river bridges, 10 others)
     • PPP Co uses the Authority’s Bridge
       Management System – Eirspan
     • Inspections include weekly Overseer
       inspections, annual routine
       inspections, principal inspections
       every 6 yrs and special inspections as
       required
     • Routine inspection identifies
       maintenance requirements for the
       year. Work orders are raised through
       Eirspan

M17 M18 Gort to Tuam PPP Scheme
Emergency Response
       • Ensure emergency response team
         availability for 24hrs a day everyday,
         to facilitate any necessary Lane
         Closures
       • Attendance within maximum 1 hour
         and 1.5hours out of normal hours
       • Must have plant and equipment
         available at all times including
       • Liaise closely with the Emergency
         Services and adjacent maintenance
         contractors (MMaRC B JV, N6
         Operations and Galway County
         Council)

M17 M18 Gort to Tuam PPP Scheme
Accidents
• The collision rate per km on the old N17
  and N18 was 0.29 in 2014.
                                                         Cause of Road Traffic Accidents
• The collision rate per km for the first 338    18      18      18                18

  days on the M17M18 motorway is 0.16            16

• Equal spread of accidents due to;              14

                                                 12
    • Driver Error – drivers typically state     10
      that they made an error i.e. pressed       8
      accelerator instead of brake, pulled out   6                       5

      in front of another vehicle etc            4
                                                                                            2

    • Hail – driving too fast during wintery     2

      conditions                                 0
                                                      DRIVER   HAIL   MOTORIST   UNKNOWN   VEHICLE
    • Unknown – typically unreported                  ERROR             LOST
                                                                      CONTROL
                                                                                            FAULT

      barrier or signage damage, or driver                             OF MV

      could not explain reason for accident
M17 M18 Gort to Tuam PPP Scheme
Pavement Testing - SCRIM

     • SCRIM testing carried out annually to
       Lane 1 and all slip roads
     • Lane 2 tested every second year
     • Contract sets out minimum SCRIM
       Coefficient values based on the road
       type
         • Investigatory Levels
         • Minimum Performance Levels
         • Handback Levels

M17 M18 Gort to Tuam PPP Scheme
Pavement Testing- Road
     Surface Profiler
     • Road Surface Profiler (RSP) used to
       measure
        • International Roughness Index(IRI)
        • Mean Profile Depth (MPD)
        • Rut Depth
     • Measured same frequency as SCRIM
     • Minimum performance and
       investigatory levels set out in the
       contract and in the TII standards
     • Structural capacity of the pavement is
       measured using Falling Weight
       Deflectometer every 4 years
M17 M18 Gort to Tuam PPP Scheme
Lifecycle/Handback Requirements
      • The Authority effectively gets a new motorway
        back at the end of the concession period
      • Lifecycle model determining the maintenance and
        renewal requirements
      • A number of key assets will require replacement
        prior to handback including
           • Pavement – extensive minimum performance
             levels must be achieved in addition to a
             residual life of 10 years
           • Fencing
           • Safety Barriers
           • Signage
           • Lighting
           • ERT etc

 M17 M18 Gort to Tuam PPP Scheme
Q&A

M17 M18 Gort to Tuam PPP Scheme
You can also read