TII M17 M18 Gort to Tuam PPP Scheme - DirectRoute Presentation | 12th September 2018 - Engineers Ireland
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Outline of Presentation Overview of the Project & PPP Structure Declan Carney, DR General Manager, Construction Stage Design and Construction Challenges Eamon Daly, Design Project Manager, Barry Transportation Emer O’Dea, Design Project Manager, Arup Operations and Maintenance Phase / Life-Cycle Niall Lyons, DR General Manager Operations Stage Q and A M17 M18 Gort to Tuam PPP Scheme
Overview of the Project & PPP Structure Declan Carney, DR General Manager, Construction Stage M17 M18 Gort to Tuam PPP Scheme
Overview of the Project 4.2 km N17 M17 26 km N18 27km Oranmore – Tuam Bypass Galway – Gort CPO 2006 CPO 2005 Tuam CPO 2007 M17 M18 Gort to Tuam PPP Scheme
Overview of the Project IRELAND GDP FROM CONSTRUCTION - €m SOURCE: TRADINGECONOMICS.COM I CENTRAL STATISTICS OFFICE IRELAND 2005 – 2007 2008 June 2009-2014 - PPP Procurement 2014 -2016 (4 consortia) N18 Mobilisation, • Stage 1 – Nov 2009 advance work & 3 Planning D&B design 2017 - Approvals • BAFOs – Aug 2010 and Aug 1999 – 2006 2042 2011 2015 – 2017 • Route Selection O&M • Suspended 2012 – 2013 • Environmental Assessment Construction • Contract Close – 30/04/14 • Preparation Planning Approvals PLANNING PROCUREMENT D&B O&M M17 M18 Gort to Tuam PPP Scheme
Overview of the Project Timetable Target Actual Permit To Use 30/11/2017 30/11/2017 Completion 28/02/2018 19/12/2017 Road opened early & in full to traffic on 27th September 2017 M17 M18 Gort to Tuam PPP Scheme
Employer: Transport Sponsors Shareholding Infrastructure Ireland (TII) Lagan Project Investments Ltd (10%) PPP Road Holdings Ltd (10%) (Sisk) Strabag SE (10%) Consultant Agreements NRA PPP Contract Motorway West Ltd (10%) (Roadbridge) Funders (EIB, Natixis, Societe Road Infrastructure (Irl) Ltd (10%) (InfraRed) Generale and Bank of Ireland) Marguerite Road Ireland Sarl (50%) Funding Agreements PPP Co DirectRoute (Tuam) Ltd Shareholders agreement Design & Build Construction Contract 100% Direct Agreement Shareholding DirectRoute (Tuam) Holdings Ltd Construction Joint Venture DirectRoute (Tuam) Construction Ltd O&M Contract Lagan Construction Group Ltd Advisers to DirectRoute Roadbridge 25% Financial: Societe Generale John Sisk & Son (Holdings) Ltd Each Legal: A&L Goodbody Strabag AG Insurance: AON & Glennon Tax & Accounting: BDO PCGs (Jt and Sev) D&C Works Agreement Lagan Constr Group Hldgs Ltd Sicon Ltd Strabag SE Roadbridge Delivery Partner Delivery Partner Delivery Partner South (Lagan) Centre (Sisk) North (Roadbridge) Design Agreements O&M Sub-Contract Interface Agreement A-Way Lagan Infrastructure Services Ltd (ALIS) Design Team Design Team Design Team South Centre North Collateral Agreement And step-in PCGs (Jt and Sev) Design JV (DJV) Lagan Constr Group Hldgs Ltd Strabag SE Arup & Barry Transportation M17 M18 Gort to Tuam PPP Scheme Direct Agreement
Delivery Structure Authority: Transport Infrastructure Ireland PPP Contract PPP Co DirectRoute (Tuam) Ltd Design & Build Construction Contract Construction Joint Venture DirectRoute (Tuam) Construction Ltd D&C Works Agreements Delivery Partner Delivery Partner Delivery Partner South: Lagan Centre: Sisk North: Roadbridge Design Agreements Design JV (DJV) Arup / JB Barry Transportation M17 M18 Gort to Tuam PPP Scheme
Refinancing • Funding markets at Financial Close April 2014 were generally closed to Ireland • Improvement in funding market terms and liquidity in the two year period from financial close • Recognised clear refinancing opportunity - highly unusual in the construction stage • Refinancing Financial Close in May 2016 • Significant savings delivered to the Authority in line with the Project Agreement • Change in identity of lenders • Comparatively low transaction costs M17 M18 Gort to Tuam PPP Scheme
Health & Safety M17 M18 Gort to Tuam PPP Scheme
Safety Initiatives • Project Safety Forum • Bespoke training “black hat” for all supervisors • Common SOR system with trend analysis and information sharing. • Safety Incentive Scheme • H&S Newsletters • Stand downs/ Safety Days / Impact Speakers • Full Class 3 high vis PPE • 10 minute “Safety Chats” • Worker surveys M17 M18 Gort to Tuam PPP Scheme
Design and Construction Challenges Eamon Daly, Design Project Manager, Barry Transportation Emer O’Dea, Design Project Manager, Arup M17 M18 Gort to Tuam PPP Scheme
Outline of Design and Construction Challenges • The Design Team • Design Challenges • Flooding and Drainage • Geotechnical Design • Pavement • Environmental Design and Mitigation • Key Structures and Junctions M17 M18 Gort to Tuam PPP Scheme
Design Joint Venture • Design Joint Venture consists of joint venture between Barry Transportation and Arup • Tender Design was completed in 2010 and formed the Conceptual Design • Barry Transportation were designers for the northern half of the scheme, Arup designers for the southern half of the scheme • Detail Design commenced in May 2014 with the preparation of a Design Manual to standardise design approach across the Scheme • Max Design Team at Peak: Design Office: 93 Site: 25 M17 M18 Gort to Tuam PPP Scheme
Scheme Information – Key Elements • 53km of Standard Dual Carriageway Motorway • 4km of Type 2 Dual Carriageway • 4 grade Separated junctions including a major junction with the M6 Motorway • Link Roads, Side Road Diversions and Access Roads • 71 Principal Structures including road bridges, river bridges, rail bridges, footbridges, accommodation bridges and culverts, • 33 other structures including retaining walls, gantry signs and VMS signs • Fencing, Safety Barriers, drainage, communications, earthworks, signage, lining, landscaping, lighting, utilities, environmental and ancillary road works M17 M18 Gort to Tuam PPP Scheme
Key Design Challenges • Three Contractors – Two Designers – Design Consistency • Three Separate Design Supervision Teams with a head DSR overseeing all three • The design of significant Peat areas within the Tuam Bypass and on the M17 south of Tuam • Design of earthworks through areas of significant karst risk across all sections • Drainage in areas of regionally sensitive aquifers • Extensive seasonal flooding • Environmental • Structures • Pavement M17 M18 Gort to Tuam PPP Scheme
Flooding November 2015 M17 M18 Gort to Tuam PPP Scheme
Flooding November 2015 M17 M18 Gort to Tuam PPP Scheme
Mitigation against Flooding • Drainage Blanket • Road Design Levels • Flood Relief Culverts M17 M18 Gort to Tuam PPP Scheme
Road Drainage Objectives • The speedy removal of surface water from running carriageway areas • The minimisation of the risks of pollution and flooding of receiving water bodies including measures to minimise the risk of accidental spillages causing pollution and to provide significant removal of suspended solids and other contaminants • The removal of sub-surface water to protect pavements and associated earthworks. M17 M18 Gort to Tuam PPP Scheme
Road Drainage - Pavement Drainage at transition areas • Speedy removal of surface water – related to pavement gradient • Potential flat spots at transition areas on sections of road with shallow gradients • Solution - Rolling Crowns – Application of superelevation along a diagonal crown line across the carriageway • Maintains minimum 2.5% carriageway gradient • Sufficiently long to achieve satisfactory ride quality • Particular care required with construction M17 M18 Gort to Tuam PPP Scheme
Road Drainage Types of Road Drainage Systems – Sealed Drainage Areas • Kerb Slot Drain / Carrier Pipe • Kerb and Gully system with Carrier Pipe • Combined Kerb Drainage Units – Envirokerb • Median Drainage – Slot Drains / gullies • Filter Drains also provided only to drain non contaminated run off and control groundwater levels M17 M18 Gort to Tuam PPP Scheme
Road Drainage Median Slot Drain M17 M18 Gort to Tuam PPP Scheme
Road Drainage Types of Drainage Systems – Non - Sealed Drainage Areas • Over the edge drainage • Filter Drains Sub Surface Drainage • On embankments – extension of capping • In Cuttings and Low embankments – Narrow Filter Drains M17 M18 Gort to Tuam PPP Scheme
Road Drainage Pollution Control • Silt trap gullies • Catchpits used throughout the scheme where possible • By pass petrol / Oil interceptors • Attenuation Ponds • Infiltration ponds • Pollution Control Forebays in all attenuation / Infiltration ponds M17 M18 Gort to Tuam PPP Scheme
Road Drainage - Attenuation Attenuation pond Infiltration Pond M17 M18 Gort to Tuam PPP Scheme
Road Drainage - Attenuation Constructed Wetland and Soakaway • Infiltration System • Excavation in Rock • Proximity to SAC and Local Group Water Scheme • Area of Seasonal Flooding M17 M18 Gort to Tuam PPP Scheme
M17 Soft Ground Treatment • Approx. 3km of soft ground • Vertical band drains at 1.0m spacing • Up to 7m of embankment • 1.5 years duration • Constant monitoring of instrumentation. PWP, inclinometers, settlement plates, etc. M17 M18 Gort to Tuam PPP Scheme
M17 Soft Ground Treatment M17 M18 Gort to Tuam PPP Scheme
M17 Soft Ground Treatment • 600mm lifts • 3-4 month hold periods • PWP monitoring • 1500mm of settlement predicted • 1500mm of settlement achieved M17 M18 Gort to Tuam PPP Scheme
M17 Rock excavation • Approximately 1.8M m3 of rock excavation • 2m rock bench at top • Majority blasted and then excavated by machine to achieve the slope angle • Excavated to a 1:0.5 slope • https://www.youtube.c om/watch?v=7GNnT- oO8_k M17 M18 Gort to Tuam PPP Scheme
Karst risk assessment and standard detail development Desktop Study Site Walkover GSI Geology map and karst landforms via ArcGIS New features identified M17 M18 Gort to Tuam PPP Scheme
Karst risk assessment and standard detail development • 1km Sections Assessed • Risk Assessment Length (m) % of alignment Risk based on 9+530 43 High overburden cover, rock type, density 11+510 52 Medium of karst and 1+160 5 Low proximity to the scheme M17 M18 Gort to Tuam PPP Scheme
Karst risk assessment and standard detail development M17 M18 Gort to Tuam PPP Scheme
Karst risk assessment and standard detail development • Geotextile Requirement reduced to
OB89 – Karst Uncovered M17 M18 Gort to Tuam PPP Scheme
Karst shown in geophysics at west and central pier during construction M17 M18 Gort to Tuam PPP Scheme
Option 1 – Leave OB89 in place and remediate karst Central pier Phase 1 rotary percussive and geophysics 3 to 4m above formation COMPLETE Phase 2 Ground investigation – geophysics at actual formation and rotary percussive probes on grid to estimate extent of feature Phase 3 Create safe working platform and carry out shell and auger boreholes to determine soil parameters and rotary coring 3m into rock for rock parameters Clear out feature and determine extent Backfill feature beneath pavement to SED Scenario A Scenario B If void beneath structure foundation is small, backfill with If feature is large and in filled inverted filter and design slab to with overburden and rock is at Scenario C span feature depth, design skin friction piles If feature is large and rock is present, design rock socketed piles M17 M18 Gort to Tuam PPP Scheme
Scenarios B and C – Piled Solutions ???? ???? Either piles bearing in soil and Base of central pier at on rock or 3m into rock – 18.6 m OD malin dependent on depth of Type, depth, permanent casing competent rock from boreholes and number TBC post design M17 M18 Gort to Tuam PPP Scheme
Proposed alternative locations and additional ground investigation OB89: How did we fix this on Site? New location chosen approximately 20m north of the original M17 M18 Gort to Tuam PPP Scheme
M17 Ballinphuil Overbridge • Large Void 12m x 8m • Clay filled = inactive • 8 conduit karst features above the void – 600mm wide • Smooth edges, flowing water = active M17 M18 Gort to Tuam PPP Scheme Map all available information
Ballinphuil: How did we fix this on Site? • Design already issued for construction - 5mm settlement limit at central pier • Inactive void – infilled with Class 6N2 and blinded with concrete • Active conduits – backfilled with 0.5m no fines concrete • Backfill with concrete to underside of pier M17 M18 Gort to Tuam PPP Scheme
Tuam Bypass Ballygaddy Overbridge Explorations Carried Out • 4 Rotary Cores • 1 CP Hole • 5 trial pits • 6 Geophysical resistivity profiles • Ground conductivity survey • Karst Features Protocol Followed M17 M18 Gort to Tuam PPP Scheme
Tuam Bypass - Ballygaddy Overbridge • Large Active Linear Karst Feature • Saturated sand filled void • 3.5m width • Over 20m in length • Depth to solid rock, 13m M17 M18 Gort to Tuam PPP Scheme
Ballygaddy Overbridge Linear Karst Feature- Geophysics • Resistivity Profiles and Ground Penetrating Radar to verify location • Additional drilling to determine ground condition for foundation M17 M18 Gort to Tuam PPP Scheme
Ballygaddy Overbridge – How did we fix this on site? • Void infilled with Class 6C material • Slab spanning feature • Supporting overlying structure M17 M18 Gort to Tuam PPP Scheme
Pavement Design Mainline - Analytically designed Flexible Composite Pavement Non-Project Road – Standard Method • Why analytical design? • Common on many PPP Projects • Based on customising design to locally available materials and construction methods • Maximise whole life value • Additional testing in situ • No negative construction tolerances M17 M18 Gort to Tuam PPP Scheme
Why Flexible Composite Pavement? • Site won Aggregate – very significant limestone rock ideal for aggregate • Sustainable use of Material • Cost Efficiency • Flexible Composite design in soft ground? • Assumed foundation CBR of 15% proved through testing • Primary settlement fully achieved and significant secondary settlement achieved through maintaining surcharge beyond required design period • Use of geosynthetics as reinforcement to pavement layers eg Kilmore Roundabout • Reduced crack induced spacings to 2m. • All of this reduced the potential for settlement or reflective cracking M17 M18 Gort to Tuam PPP Scheme
Comparison of Analytical and Standard Pavement Construction Mainline – 56msa and CBR >15% Layer Clause Material Grade of Analytical Standard Binder Thickness Thickness Surface 942 SMA 10 surf 30 30 Course PMB 65/105- 60 des Binder Course 929 AC 20 dense 40/60 55 55 bin des Upper Base 929 AC 32 dense 40/60 75 95 base des Thickness of Asphalt 160 180 Lower Base 822 CBGM B 180 180 C12/15 Sub-base 808 Type B 100 300 Capping 613 6F1 or 6F2 - 150 Total Thickness (mm) 440 610 M17 M18 Gort to Tuam PPP Scheme
Environmental Challenges cSAC – Candidate Special Area of Conservation, pNHA – Potential National Heritage Area, SPA – Special Protection Area, • Scheme encroaches into the catchment area of a SNR – Statutory Nature Reserve number of SACs their associated river networks • Lough Corrib SAC • Abbert River • Grange River • Coole – Garryland Complex (SAC, pNHA, SPA, SNR) • Kiltiernan Turlough (SAC, pNHA) • Rahasane SAC • Dunkellin River • Scheme is also adjacent to Nationally rare plants – Mudwort, Dropwort, Alder, Buckthorn, Lady’s Tresses, Orchid and Wood Bitter Vetch M17 M18 Gort to Tuam PPP Scheme
Environmental Challenges Whooper Swan Pine Martin Bewicks Swan The habitats of protected species that are located within the scheme Otter Lesser Horsehoe Bat M17 M18 Gort to Tuam PPP Scheme
Environmental Mitigation M17 M18 Gort to Tuam PPP Scheme
Environmental Mitigation –Bats • EIS - “Guidelines for the Treatment of Bats during the Construction of National Road Schemes” – DMRB • Bat Conservation Ireland - Consultation • Early Landscaping Works • Bat Hop-Over Points - consisting of diamond shaped areas with existing or semi mature tree vegetation either side of the road – 2.5-3.5m in height at 5-7m centres • Stone Cladding and Bat Boxes provided on River Bridges catering for all bat species M17 M18 Gort to Tuam PPP Scheme
Environmental Mitigation – Lesser Horseshoe Bats • Lesser Horseshoe Bats • International Importance • Dramatic declines in population in Ireland and extinction in parts of Europe • Coole Green Bat Bridge • Only bridge of its kind in Ireland • Twin Arch Structure • Hedgerow vegetation to guide bats • Feeding grounds either side and a roosting site in Kiltartan Cave M17 M18 Gort to Tuam PPP Scheme
Structures - Coole Green Bat Bridge • Twin Arch Pre-Cast Concrete Buried Structure • 1:2 sloping elevations topsoiled and landscaped M17 M18 Gort to Tuam PPP Scheme
Structures - Ballygaddy Overbridge Concept Design - Cambered Steel Beams - Long span variable depth beam bridge Plan on Highway Alignment Elevation on Concept Design Crest Curve – 330m Radius M17 M18 Gort to Tuam PPP Scheme
Detailed Design • Innovative precast concrete pretensioned super-Y beams • 40m Span, 16m wide, 16deg Skew • Varying depth beams – parabolic top profile • Level beam soffit M17 M18 Gort to Tuam PPP Scheme
Rathmorrissy Junction • 3 Level Motorway to M6 to Motorway Interchange Galway • Largest junction in Ireland • Circulatory Carriageway – 1km – longest in Ireland • Design Optimisation • Roundabout - Oblong Shape • Reduced Earthworks Heights • Reduction of radii on structures M6 to • Steepened Slopes Dublin • Reduction of over 100,000m3 achieved M17 M18 Gort to Tuam PPP Scheme
Rathmorrissy Junction • 5 Bridge Structures Required • 3 Underbridges carrying the M18 mainline over the circulatory carriageway • Single Spans over the existing M6 – no works in median • Overbridges over the live M6 motorway installed at night • Eastbound – rolling closures • Westbound – closure and local diversions M17 M18 Gort to Tuam PPP Scheme
Operations and Maintenance Phase / Life-Cycle Niall Lyons, DR General Manager Operations Stage M17 M18 Gort to Tuam PPP Scheme
O&M Requirements • 25yr O&M Contract for the Project Road, Project Road being smaller in extent than the road constructed • Availability based contract • No tolling of the road • O&M requirements set out in Schedule 7 – very prescriptive maintenance and inspection requirements • Operations to be carried out in accordance with TII Publications and the Traffic Signs Manual M17 M18 Gort to Tuam PPP Scheme
O&M Phase Set Up • Long term O&M Contractor (A-way Lagan Infrastructure Services aka ALIS) • PPP Co responsible for lifecycle works • Extensive plant & equipment required to provide O&M services • Centrally located depot • Long-term local employment • All employees are local. • Local specialist subcontractors – pavement testing, plant hire M17 M18 Gort to Tuam PPP Scheme
Winter Maintenance • Precautionary treatment where ice, frost or snow conditions are forecast to occur • 3 winter maintenance routes, all to be completed within 2hrs • Duty Officer and winter maintenance team on call 24/7 • Use of pre-wet system • Plant & Equipment • 4no. Prewet gritting trucks with snow ploughs • Brine batching plant • 1000 tonne salt store • Vaisala ice forecast software • Weather Station M17 M18 Gort to Tuam PPP Scheme
Winter Maintenance – Storm Emma • Storm Emma – 26th February to 4th March • Storm Emma in numbers; • 34no. Prewet treatments • 27no. Dry treatments • 350 tonnes salt used • Procured additional gritter and loading shovel • Hotel rooms booked for staff • Gritting and ploughing non stop for 3 days • All lanes kept open • Particular issues • Getting to motorway • No traffic to help activate the salt M17 M18 Gort to Tuam PPP Scheme
Asset Management - RMMS • Steanne Solutions Geoworks 7 RMMS used for all asset management excl Structures and major capital structural maintenance of pavements • All inventory on Project Road recorded via As Built survey and inputted into RMMS • Requirements of RMMS • Store and manage inventory data • Take details of Safety and Detailed Inspections and turn them into a program of work • Produce schedules of inspections and required cyclical activities • Be able to produce lists of outstanding Defects grouped together by date, category, activity or Defect • Have facility to audit performance • Have an archiving feature to maintain records • All defects are categorised – Category 1 , Category 2 High, Medium and Low, Category 3 • All defects have a required initial response time and permanent repair time M17 M18 Gort to Tuam PPP Scheme
Structures Maintenance • 75 no. Structures on Project Road (32 over bridges, 14 under bridges, 15 gantries, 4 river bridges, 10 others) • PPP Co uses the Authority’s Bridge Management System – Eirspan • Inspections include weekly Overseer inspections, annual routine inspections, principal inspections every 6 yrs and special inspections as required • Routine inspection identifies maintenance requirements for the year. Work orders are raised through Eirspan M17 M18 Gort to Tuam PPP Scheme
Emergency Response • Ensure emergency response team availability for 24hrs a day everyday, to facilitate any necessary Lane Closures • Attendance within maximum 1 hour and 1.5hours out of normal hours • Must have plant and equipment available at all times including • Liaise closely with the Emergency Services and adjacent maintenance contractors (MMaRC B JV, N6 Operations and Galway County Council) M17 M18 Gort to Tuam PPP Scheme
Accidents • The collision rate per km on the old N17 and N18 was 0.29 in 2014. Cause of Road Traffic Accidents • The collision rate per km for the first 338 18 18 18 18 days on the M17M18 motorway is 0.16 16 • Equal spread of accidents due to; 14 12 • Driver Error – drivers typically state 10 that they made an error i.e. pressed 8 accelerator instead of brake, pulled out 6 5 in front of another vehicle etc 4 2 • Hail – driving too fast during wintery 2 conditions 0 DRIVER HAIL MOTORIST UNKNOWN VEHICLE • Unknown – typically unreported ERROR LOST CONTROL FAULT barrier or signage damage, or driver OF MV could not explain reason for accident M17 M18 Gort to Tuam PPP Scheme
Pavement Testing - SCRIM • SCRIM testing carried out annually to Lane 1 and all slip roads • Lane 2 tested every second year • Contract sets out minimum SCRIM Coefficient values based on the road type • Investigatory Levels • Minimum Performance Levels • Handback Levels M17 M18 Gort to Tuam PPP Scheme
Pavement Testing- Road Surface Profiler • Road Surface Profiler (RSP) used to measure • International Roughness Index(IRI) • Mean Profile Depth (MPD) • Rut Depth • Measured same frequency as SCRIM • Minimum performance and investigatory levels set out in the contract and in the TII standards • Structural capacity of the pavement is measured using Falling Weight Deflectometer every 4 years M17 M18 Gort to Tuam PPP Scheme
Lifecycle/Handback Requirements • The Authority effectively gets a new motorway back at the end of the concession period • Lifecycle model determining the maintenance and renewal requirements • A number of key assets will require replacement prior to handback including • Pavement – extensive minimum performance levels must be achieved in addition to a residual life of 10 years • Fencing • Safety Barriers • Signage • Lighting • ERT etc M17 M18 Gort to Tuam PPP Scheme
Q&A M17 M18 Gort to Tuam PPP Scheme
You can also read