San Juan Generating Station Restructuring Agreements - Steve Cummins, Tim Glasco & Richard Virtue July 15, 2015

Page created by Freddie Lambert
 
CONTINUE READING
San Juan Generating Station Restructuring Agreements - Steve Cummins, Tim Glasco & Richard Virtue July 15, 2015
San Juan Generating Station
Restructuring Agreements
Steve Cummins,
Tim Glasco &
Richard Virtue
July 15, 2015
Agenda
1. San Juan Generating Station Project History
2. Restructuring the Ownership in the San Juan Generating Station (Background)
3. Restructuring Benefits to LAC Residents
4. Current Generation Resources Plan
5. Current Coal Supply through 2017
6. New Coal Supply
7. Restructuring Agreement
8. Mine Reclamation Agreement
9. Decommissioning Agreement
10. San Juan Project Participation Agreement Restructuring Amendment
    Conforming Changes
11. San Juan Project Participation Agreement
    Exit Date Amendment
12. Summary
13. Time Line to Close the Deal
14. Consequences of Failure
San Juan Generating Station
Project History
Investments in Power Generating Resources
1. County Council established the Citizens Review Committee (CRC) 1984
2. Tasked to assess Utilities Acquisition Projects
3. Committee made recommendations as follows:
    Approved by Utility Board and County Council
    Purchase of:
          7.2% of PNM’s San Juan Unit 4 coal-fired generating plant;
          PNM’s White Rock electric distribution system
          PNM’s White Rock gas distribution system - 1989
    Construction of:
          El Vado and Abiquiu hydroelectric plants providing renewable energy since 1990
San Juan Generating Station
Project History cont.
1985 - 86 issuance of utility revenue bonds $110 million
Funding over 30 years (paid off in 2015)
SJGS original cost - $46.3 million

San Juan Project Participation Agreement
      Term of agreement, 2022
      9 current owners (PNM, TEP,COF, LAC, UAMPS, TSGT, MSR, SCPPA, Anaheim)
      SJGS has 4 generating units
      LAC owns 7.2% interest in unit 4
Restructuring the Ownership in the San Juan
Generating Station (Background)
Restructuring the Ownership in the San Juan
Generating Station (Background)

  1. January 2011, the U.S. Environmental Protection Agency (“EPA”) issued a proposed Federal
     Implementation Plan (“FIP”) to reduce regional haze using BART.

  2. February 2013, PNM, EPA and the State of New Mexico executed a non-binding agreement
     (“EPA Term Sheet”) outlining an alternative to BART.

  3. The BART Alternative will require retirement of San Juan Unit 2 and Unit 3 by December 31,
     2017 and the installation of selective non-catalytic reduction (“SNCR”) technology on San
     Juan Unit 1 and Unit 4 by January 31, 2016.

  4. September 2013, the State of New Mexico approved the BART Alternative.
Restructuring the Ownership in the San Juan
      Generating Station (Background)cont.
5.   March 2014, PNM commences studies, analysis, assessments and design related to the installation
     of the BART Alternative on San Juan Units 1 & 4 in order to comply with the deadlines set forth
     in the EPA Term Sheet.
6.   The EPA issues final approval of the BART Alternative in the Fall of 2014.
7.   As a result of the BART Alternative, four of the SJGS owners decided it was in their interests to
     exit the plant early.
8.   With the shut down of two units and four participants desire to exit early, Restructuring of the
     plant participation agreement became necessary.
9.   The Participants have completed San Juan Restructuring negotiations.
Restructuring Benefits to LAC Residents

1. Most Economical Option
2. Aligns with current bond debt expiring in 2022
3. Environmental – reduced emissions from the SJGS by 50%
4. Aligns with our goal of being carbon neutral by 2040
5. Finalized a decommissioning Agreement among the 9 owners
6. SJGS is the County’s only controllable resource (hazard sharing, spin)
7. No rate increases resulting from restructuring
8. Potential for savings that can help us transition to future energy resources
Current Generation Resources Plan

Time line 2015 to 2040
1. 2015 Prepare for 2022 – 2025 departure from the San Juan Project
2. 2025 Expiration of ECA in its current form
3. 2022 – 2025 Long term PPA to serve LAPP as necessary
4. Distributed Generation contribution to serve load (2015 approx. 400 kW)
5. Continue to stay apprised of industry changes with renewable energy
   resources dealing with the effects of intermittency
6. Investigate new base load resources
7. Implement FER committee recommendations approved by Utility Board
Current Coal Supply through 2017

1. Expires December 31, 2017
2. 2015 Price - $3.07/mmbtu
3. Take or pay minimum
4. 9 months of coal reserve for 4 unit operation
5. RSIP requires SNCR in operation by Jan 2016 and shut down of Units 2&3 by
   December 2017
6. BHP desire to exit coal mining in North America
New Coal Supply

 March 19, Coal bids received
 April 30, 2015 PNM and SJGS owners agree to terms of new coal supply
  agreement (CSA)
 PNM and Westmoreland are the signatories to CSA
 Decrease in Fuel Supply cost annually – Estimate $2.3 mil per year
     New fuel price ($2.20/mmbtu) is approximately a 29% reduction from current
      contract price
     Contract similar to current agreement (base coal min. tons (tier 1), incremental
      coal (tier 2)
     Term of agreement – Jan. 1, 2016 through June 30, 2022, aligns with SJPPA
     Option to extend beyond 2022 must be decided by participants in 2018
Restructuring Agreement
Summary
Exiting Participants
8/26/2014

The following four owners wish to exit the project on December 31, 2017 (Exit
Date) prior to 2022 which is the contract date for the San Juan Project
Participation Agreement (SJPPA):

MSR – Public Power Agency
SCPPA – Southern California Public Power Authority
City of Anaheim
TSGT - Tri-State Generation & Transmission
$$$ Cost To Exit Early

Demand Charge of $6.2 million paid by exciter's for the use of new capital
improvements on Unit 4 to be paid in equal shares from Jan 2015 through Dec. 2017:
 PNM       0.00%
 TEP       0.00%
 Farmington    55.6%
 LAC       22.2% x $6.2 million = $1,376,400.00
 UAMPS     22.2%

Restructuring Fee of $8.8 million will also be allocated using the percentages above
and paid on the effective date. Consideration for cost to restructure
 LAC       22.2% x $8.8 million = $1,953,600.00
Remaining Participants

PNM – Public Service Company of New Mexico “Utility”
PNMR-D – Public Service Company of New Mexico Resources and
Development (Power Merchant)
TEP – Tucson Electric Power
COF – City of Farmington
LAC – Los Alamos County
UAMPS – Utah Associated Municipal Power Systems
Compensation To Remaining
Participants for negotiating early exit

 Receive Demand Charge - LAC 22.2% x $6.2 million = $1,376,400.00 total
 Receive Restructuring Fee - LAC 22.2% x $8.8 million = $1,953,600.00 total
 LAC common O&M reduced from 4.309% to 3.123% from Jan. 1, 2018
  through June 30, 2022 (Value of reduced O&M over 5.5 years is estimated
  at approx. $3 million)

 Commitment is for LAPP not to be harmed financially from Restructuring
Project Liabilities

 Legacy Liabilities – remain the responsibility of the current owners by
  participant share
 LAC Decommissioning fund
 Reclamation trusts to be Funded by 2022
 Environmental Liabilities – all current SJGS participants retain their
  participant share unless it can be pointed to a particular incident post 2017
Mine Reclamation Agreement
Summary
Mine Reclamation Responsibilities

1.   Participants requirement to fund reclamation
      Section 23 of SJPPA reference to the UGCSA
2.   Reclamation of old surface mine and underground mine mouth and
     associated disturbances (vent shafts, access roads etc.)
      Coal Combustion Residuals (Ash) are used to fill the pit
      10 feet of earth fill above the ash, with 2 feet of top soil
      Permit requires 10 year monitoring post final reclamation
3.   Reclamation scenarios and the associated funding curves
      Cost of reclamation is highly dependent on quantity of Ash
Mine Reclamation Trust Funds

  1.   Current Trust established in 2012 per current UG-CSA
        2038 closure scenario to be fully funded by 2017
        estimated cost $38 million in 2012 dollars
        LAC trust fund $478,000 YE 2014
  2.   Participants desire is to fund 2022 closure by 2017
        estimated cost $133 million in 2012 dollars
        LAC has this scenario budgeted in the 2016 budget
  3.   Funding Curves developed by PACE Wiley for multiple closure scenarios
  4.   Funding curves to be reviewed by modified as necessary by new miner
Mine Reclamation Agreement
Overview
1.   Term – 180 days after Bond Release
      10 year monitoring period begins after final reclamation is completed
2.   Recognition of Obligations
      Pre 2017 Exit date disturbances
      Post Exit date disturbances
3.   Funding of Reclamation Trusts
      beneficiary, Investment Policies, Annual True-ups, defaults etc.
4.   Adjustments to Reclamation Curves as necessary
Mine Reclamation Agreement
Overview Cont.
1.   Reclamation Investment Committee
      review funding levels
      allowable investments
2.   Reclamation Oversight Committee
      Oversee reclamation work, cost reviews, surveys
3.   Reclamation Trust Funds Operating Agent
      PNM to monitor operations of the San Juan Coal Co.
      review budgets and invoices
      reclamation progress etc.
SJGS Decommissioning Agreement
Summary
SJGS Decommissioning

Initial Decommissioning Work $1.2 million (Exhibit D)
Interim Decommissioning Work
 Period between Exit Date(Dec. 31, 2017) & retirement of units 1 & 4
    Any necessary decommission work will be treated as O&M if below threshold of $
$500,000 and paid by the remaining participants
    Decommissioning Work above threshold will either be required by law or determined
to be a prudent cost avoidance and paid by all nine participants
SJGS Decommissioning Cont.

Use of equipment located on Units 2 & 3 for continued operation on units 1 & 4 without
compensation to exiting participants
 Unit 3 and Unit 4 have the same capacity

However any salvage value obtained will be distributed to all nine parties
 Ex. Sale of turbine generator set
Final Decommissioning Plan

After final shut down of units 1 and unit 4 an updated decommissioning plan will be
performed to identify the cost associated with following scenarios:
1.   What’s required by law, Asset Retirement Obligations (ARO)
2.   Brownfield
3.   Green Field
Decommissioning Committee will vote on desired plan – Need unanimous vote to select
any plan other than the minimum required by law
Decommissioning Trust Fund

1.   Initial funding level $30 million to meet expected ARO
2.   All nine participants must fund by 2022
3.   LAC currently has $4.2 Million in a restricted fund designated for decommissioning of
     SJGS
Decommissioning Trust Fund cont.

1.   Brown field scenario estimated in 2012 at $150 million – LAC share $3 million
2.   Reassessment of target amount in 2022 and every five years thereafter
3.   Excess funds released 2 years after decommissioning work is completed
4.   Obligations are several and not joint
San Juan Project Participation Agreement

Restructuring Amendment
Conforming Changes

Amendment incorporates relevant provisions of the Restructuring Agreement
San Juan Project Participation Agreement
Exit Date Amendment
Purpose of Exit Amendment

Amendment reflects the exit from the project of the Exiting Participants and to
set forth the terms of the SJPPA under which the remaining participants will
continue their participation in the project
 Operations of Units 1 & 4
 Exiting Participants (MSR, SCPPA, Anaheim, TSGT)
 Retirement of Unit 2 and Unit 3
 Effective Date on the Exit Date Dec. 31, 2017
 Remaining Participants(PNM, PNMR-D, TEP, COF, LAC, UAMPS)
Administration
San Juan Project Participation Agreement
Exit Date Amendment

Coordination Committee Voting
 Projects greater than $5 million or Coal related decisions require More than
  82% majority of common participant shares and a Minimum of 66 2/3 %
  majority of the number of the individual participants
Extension of Termination Date for Large
Capital Improvement section 40A
San Juan Project Participation Agreement
Exit Date Amendment

Capital Project Cost > $50 million require unanimous approval (section 18.4.5)
 Participants to negotiate in good faith equitable option for all parties or
  possible conveyance of ownership interest
Extension of Termination Date and Coal
Supply Agreement, section 40B
San Juan Project Participation Agreement
Exit Date Amendment

1.   No later than June 30, Operating Agent shall have negotiated prices for
     coal supply beginning July 1, 2022
2.   Participants shall provide notification to extend agreement beyond July 1,
     2022 by July 1, 2018
      Negotiate Sale of ownership interest
      Binding Agreement on sale of ownership interest must be executed by
       November 15, 2018
      If no Purchase Contract, Non-Extenders shall negotiate with Extenders to convey
       right, title, and interest in the San Juan Project to other participants to assure the
       continued successful and proper operation and maintenance of the project
Budgets & Operating Expenses
          San Juan Project Participation Agreement
          Exit Date Amendment

Equipment and Facilities Common to all units (section 22.1.7)
 LAC common O&M reduced from 4.309% to 3.123% from Jan. 1, 2018 through June
  30, 2022
 Value of reduced O&M over 5.5 years is estimated at approx. $3 million
In Summary
Summary of Restructuring Agreements
         “Package Deal”
1. Agreements contingent upon one another to complete the deal
2. Participant Agreements
    Restructuring
    Mine Reclamation
    Decommissioning
    Exit Date Amendment to the SJPPA
    Amended and Restated SJPPA
   3.   Operating Agent Agreements (PNM)
    Coal Sales (CSA)
    Coal Combustion Residuals Disposal (CCRDA)
    Mine Reclamation & Trust Fund (MRTFA)
Summarizing of benefits
   1. LAC is made whole financially from the restructuring
   2. Preserve our option to exit the project in 2022 or option to extend
   3. Formalized the Decommissioning obligations among the existing
      participants
   4. Environmental – reduced emissions from the SJGS by 50%
   5. Aligns with our goal of being carbon neutral by 2040
   6. SJGS is the County’s only controllable resource (hazard sharing, spin)
   7. No rate increases resulting from restructuring
   8. Potential for savings that can help us transition to future energy resources
Summary of liabilities

  The current 9 owners of the San Juan Generating Station retain all of their
  liabilities except as modified by the restructuring agreements are as follows:
   SJPPA Term 2022 – modified for the exiting participants
   Environmental – Exiting participants not liable if environmental issue can be
    shown to have occurred post 2017 (Exit Date)
   Reclamation - Exiting participants not liable for new disturbances
    associated with mining operations post 2017 (minor disturbances if any)
   Decommissioning – Exiting participants retain their decommissioning
    liabilities based on a sliding scale using MW-years (LAC increases by 0.2% if
    we exit in 2022 at which time it will begin to decrease until the plant is shut
    down.
Summary of Economics

1.   LAC Receives Demand Charge                              $1,376,400
2.   LAC Receives Restructuring Fee                          $1,953,600
3.   LAC Decrease in Fuel Supply cost for term of contract   $14,950,000
4.   LAC Increase in common O&M for term of contract         ($2,300,000)
Total dollar value                                           $15,980,000
Time Line to close deal

1. PNM’s NMPRC Filing for Certificate of Public Convenience and Necessity
   (CCN)
2. 9 Participants Governing Body’s Approvals prior to August 1st
3. FERC filing of Amended SJPPA (August 2015)
4. CSA effective date Jan 1, 2016, dependent on Mine Purchase Closing
Consequences of Failure

1. Decommissioning Principles unresolved
2. Mine Reclamation trusts under funded
3. Current Coal contract expires in 2017
4. Current SJPPA term through June 30, 2022
5. New coal supply deal fails
6. Unit 1 and Unit 4 completed installation of SNCR’s (Totaling $130 Million of
   new capital investment). The only two units able to operate through term
   of SJPPA would have no coal supply
7. Potential for Extensive Litigation
THE END

Questions
You can also read