PUBLIC COMMUNICATION PROGRAMME FOR THE FIRST NUCLEAR POWER PROJECT - Nguyen Viet Phuong - IAEA
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
MINISTRY OF SCIENCE AND TECHNOLOGY VIETNAM ATOMIC ENERGY AGENCY PUBLIC COMMUNICATION PROGRAMME FOR THE FIRST NUCLEAR POWER PROJECT Nguyen Viet Phuong Department of Nuclear Science & Technology Management Vienna, January 2012 1
MAIN CONTENTS I. Nuclear Power Programme of Vietnam II. Overview of Public Communication Programme III. Action Plan for Ninh Thuan NP Project IV. Response to Fukushima Accident V. Conclusion Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012 2
NP Development Projection Ky Xuan (Ha Tinh) Duc Thang (Quang Ngai) Duc Chanh (Quang Ngai) Hoai My (Binh Dinh) Xuan Phuong (Phu Yen) Binh Tien (Ninh Thuan) Vinh Hai (Ninh Thuan 2) Phuoc Dinh (Ninh Thuan 1) 3
Ninh Thuan Nuclear Power Project • Ninh Thuan NPP Project • Ninh Thuan 1: Phuoc Dinh – 2 x 1,000 MWe • Ninh Thuan 2: Vinh Hai – 2 x 1,000 MWe • COD: – Ninh Thuan 1: 2020-2021 – Ninh Thuan 2: 2021-2022 • Investment Owner: EVN • Technology: Advanced & proven (LWR) • Cooling: Sea water • Fuel: Imported 4
Milestones of the Project Milestone 1 • Ready to make knowledgeable commitment to a nuclear program (Completed in • 25th Nov. 2009: Pre-FS report of the Ninh Thuan NPP project was 11/2009) approved by the National Assembly • Ready to invite bids (Vietnam: ready Milestone 2 to sign the contract) • Construction of the 1st Unit will start (12/2012) in 2014. Milestone 3 • Ready to commission and operate the first unit of the Ninh Thuan NPP. (12/2020) 5
MAIN CONTENTS I. Nuclear Power Programme of Vietnam II. Overview of Public Communication Programme III. Action Plan for Ninh Thuan NP Project IV. Response to Fukushima Accident V. Conclusion Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012 6
Implementation Scheme Direction by Government Implementation by ministries of Sci. & Tech., Industry & Trade, Info. & Com., People’s Committee of Ninh Thuan Province Undertaken by MOST, EVN, local authorities of NP Project site & other stakeholders, in cooperation with foreign partners (JETRO, JAIF, ROSATOM, EDF,...) 7
Objectives of public communication • To build, maintain and develop a friendly and favourable relationship Short with local communities • To reach the consensus of the domestic and local community towards the investment policy and siting of Ninh Thuan NPP • To gain success in the site clearance, compensation and resettlement term during the project construction period • To increase the awareness and understanding of the local residents of the necessity and benefits of Ninh Thuan NPP, a nation-scale significant project, as well as the whole nuclear power development program Long • To enhance the public understanding of nuclear power • To gain the public acceptance of nuclear power development in Vietnam • To improve EVN’s image as a reliable project investor by social contributions in the project area, which will create a trust of the local residents towards the project owner term • To better the material as well as spiritual livings of local residents • To raise the public awareness of energy and environmental issues • To set up an effective communication system 8
Target groups of audiences Frequently watch TV, listen to radio, and read Officials in Governmental bodies, elective newspapers even in off peak hours; Quickly agencies (e.g. National Assembly), and communicate and make strong influence in Communist Party organizations, who will relatives, friends and neighbours, and of directly discuss, formulate, and approve the course their family (husbands and children) policies, plans of nuclear power development Housewife Decision group makers They are next generation who are in five or ten years will be decisive citizens and will Academics Especially for those who are School participate in the nuclear and working in energy industry and power development course of children energy related sectors the country professors Local communiti Media es journalists Crucial and long run target groups of public residents a special target group who is both the target information, including Veteran Association, of public information of nuclear power and Women Association, Youth Association, the producer of information religious dignitaries, Fatherland Front Committee, etc. Attention should be paid to ethnic minority people communities 9
Major theme General Public Local communities • Nuclear safety; • Major concerns of local • Rationale of nuclear power communities: introduction in Vietnam; • Project contributions to the host • Radioactive waste management; community: compensation • The economic competitiveness regime in the resettlement plan, of nuclear power employment opportunities, local socio-economic • Project implementation development, etc.; capabilities (HR); • Environmental impacts of the • Consideration of alternatives project; such as renewable energy or energy saving to defer the • Nuclear safety and emergency introduction time of nuclear preparedness plan; power. • Spent-fuel disposal and rad- waste management. 10
Implementation plan • Exhibitions/ Seminars/Workshops organized both in big cities and Exhibition Ninh Thuan • Domestic (to Da Lat Research Reactor) and abroad for target groups Facility tours of audience Public hearings • At least once a year Mass media • Information dissemination via news agency, VTV, VOV, press PR Centre • Nuclear PR Centre in Ninh Thuan & Hanoi Online promotion • Websites, online articles, interviews Education • Education & training programmes for schools & universities Support programme • Support programme for local communities 11
Major results of national activities (1) • 07 national nuclear exhibitions in the period of 2001-2010: – Nuclear exhibitions in Hanoi, Phu Yen, Ninh Thuan, Ho Chi Minh City – 04 Nuclear Power Expos in Hanoi (2004, 2006, 2008, 2010) – More than 38.000 turns of visitors, including members of National Assembly, senior officials of Government & local authority, school children, students,.... • Publishing of articles, books, leaflets, brochures on nuclear power • Regular organization of site visits for reporters from central and local media agencies • Interview, talk shows on nuclear power with the participation of authorized representatives of state management bodies, scientists, project owners, local authorities on VTV1, VTV2, VOV, Invest TV (VCTV), MOST Website, Vietnamnet, Government Web Portal,... • Organizations of seminars on nuclear power for broadcasts & press – The Workshop on “Situation of Nuclear Power Development in the world and Long-term Strategy on Nuclear Power Development in Vietnam” with participation of General Editors of Broadcast and Newspapers and PI key persons from all provinces in the North of Vietnam 12
MAIN CONTENTS I. Nuclear Power Programme of Vietnam II. Overview of Public Communication Programme III. Action Plan for Ninh Thuan NP Project IV. Response to Fukushima Accident V. Conclusion Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012 13
Ninh Thuan Province • Area: 3,358 km2 Population: 571,000 (2010) • Coastal line: 105 km Pop. den.: 170/km2 • GDP gross: – 2011: 10.6% – 2012-2015: >14% Kinh • GDP per capita: Cham – 2011: 800 USD (60% Ragley of domestic average) Others – 2015: ~ 1,400 USD (70% of domestic average) 14
Communication messages • Nuclear power as an engine for national economic development – Energy security – Reasonable answer to energy problems in the future – Solution to improve the national position in the international community • Benefits of nuclear power projects to the local communities – Material and non-material benefits – Local socio-economic development • Safety First policy in the pursuit of nuclear power project, including safety & environmental management of NPP • National knowledgeable commitments – Manpower preparation – Infrastructure development such as preparation of legal framework 15
Communication strategy - Focus on essential & sensitive target groups: Spiritual leaders, village patriarchs, seniors of Categorization of minority groups audience - Flexible content depending on level of understanding of audiences Flexibility of Diversification communication of -Different method for different communication for each category circumstances methods of audience - Greatly depends on capability of communicators 16
Type of activities Seminar Workshop Activities by Official visit local of top-level communicators officials Domestic & Field trip foreign for facility tours journalists Public Resettlement Local project Communica support tion Centre 17
Local support • Clear resettlement project with adequate infrastructure Vietnamese students sent of water, electricity and to Russia for nuc. eng. edu. business opportunities 80 70 • Infrastructure development 60 project (road, housing) for the 50 local communities 40 • Promotion of local 30 participation to the project 20 through increasing number of 10 Ninh Thuan students sent to 0 Russia for nuclear 2010 2011 engineering education Ninh Thuan 6 11 Other • Commitment by operator of 23 57 provinces profit sharing from the Project 18
Public Relation Centre (1) • Investor: EVN (as one of component projects of Ninh Thuan NPP approved by the Prime Minister) • Location: Phan Rang – Thap Cham City • Area: 3,000 m2 • Objectives: – A destination for local and foreign visitors for improving the awareness and understanding of nuclear power and Ninh Thuan NPP project – To bring the public closer to nuclear power with positive information 19
Public Relation Centre (2) Functions Structures • Exhibitions of energy, power • Exhibition hall (three-storied generation and nuclear power building) • NPP introduction history in • 3D projection room Vietnam • Meeting room • Introduction of EVN; chain of • Library electricity supply from • Data archive area generation, transmission to distribution • Exhibition room of Ninh Thuan’s specialities • Overview of NPP reactors, NPP operation schemes • Entertainment area • Introduction of nuclear fuel cycle, nuclear safety and radiation protection • Emergency preparedness response 20
Activities in number (1) • 05 provincial-level seminar/workshop (2003, 2008, 2009, 2011 – in cooperation with ROSATOM): – Theme: Nuclear power, Ninh Thuan NPP, benefit of Ninh Thuan from the Project – Audience: 300-400/event, including official of local authorities, minority group leaders (spiritual leader, senior bonzes), religion leaders (Catholics, Protestant) • 60 small-scale workshops targeted at various local people groups – Audience: ~ 7000 (in total), including official of local authorities, representatives of social organizations (youth, woman, veteran), soldiers from local military units, school children,... • 02 three-day training courses (2009, 2010) to train local communicators on nuclear power for 30 participants from local region • 11 domestic facility tours to Da Lat Research Reactor & 06 foreign facility tours (to Japan, France, China, the US) for local leaders and residents with >260 local participants 21
Activities in number (2) • Various official visits to the project sites of high-ranking officials such as the Prime Minister, Deputy Prime Minister, Minister of Planning and Investment, Minister of Industry, Chairman of the National Assembly’s Science, Technology and Environment Committee, etc. • Organization of 06 field trips to NPP site for journalists • Other local supports: – Giving presents (notebooks, school bags) for good and poor pupils, and bookcases for local elementary and secondary schools – Financial contribution & participation by EVN to local charity & community activities, including local traditional cultural festivals, especially those of local ethnic minority people – Support for local competition to disseminate legal information regarding nuclear power 22
Major results (3) Local competition on nuclear power, 1/2011 Especially, Ninh Thuan is chosen for the construction of the first two NPPs in the country, with the total investment of r. 16 bil. USD and the most advanced and safe technology in the world. This is an essential opportunity for Ninh Thuan to have a breakthrough in rapid and sustainable development. Atomstroyexport Workshop, 12/2011 - Prime Minister Nguyen Tan Dung, Ninh Thuan 2011 23
Results and Issues Results Issues • Active support from majority of • Low frequency, lack of continuity local communities to the Project, and long-term plan for activities some even urge to accelerate (now mainly focus on short the Project events like seminar, visit,..) • Official agreement to the Project • Insufficient content for from the People’s Committees communication (lack of suitability (local authority) of all three with level of understanding of levels: Phuoc Dinh & Vinh Hai local people) communes (sites for 2 first • Insufficient understanding NPPs); Ninh Phuoc (now Thuan between investor, organizers of Nam) & Ninh Hai districts; Ninh activities and press, results in Thuan Province conflict & biased information by • Continuous public understanding newspapers, website,… and support , even after • Lack of coordinator for activities Fukushima Accident • Negative effects of Fukushima 24
MAIN CONTENTS I. Nuclear Power Programme of Vietnam II. Overview of Public Communication Programme III. Action Plan for Ninh Thuan NP Project IV. Response to Fukushima Accident V. Conclusion Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012 25
Immediate response 15/3/2011: Press conference on the incident hosted by MOST 16/3/2011: Establishment of Working Group on Analysis & Distribution of Information on the Fukushima Accident by MOST 3-4/2011: Timely monitoring of radiation level in Hanoi, Da Lat, Ninh Thuan, Lang Son, Ho Chi Minh City 16/3-28/4/2011: Distribution of Daily Report by the Working Group on the Fukushima Accident & Result of domestic measure of radioactivity & radiation level 3/2011: Radiation screening for Vietnamese citizen came back from the affected zone (Sendai) & examination of imported goods & foods of Japanese origin 26
Daily Report on Fukushima by MOST • Number of reports: 38 (16/3-28/4) • Assessment: • Frequency: Daily (by 6 PM – Provide press and public with everyday) reliable and well-sourced • Content information – Update on situation of – Stabilize the public opinion about Fukushima & radioactive the accident discharge from Fukushima – Reassure public about the safety (analyzed information from for human and environment JAIF, NISA, IAEA, CTBTO, US – Inform press and public NRC, IRSN, WNN) knowledgeable and clear – Result of daily measurement by information about nuclear safety MOST (VINATOM, VARANS) of & technology environmental background – Raise the public awareness radiation level & radiation about the first priority of safety in monitoring nuclear industry – Confirmation of safety for – Maintain the public support for human and environment the nuclear power programme 27
Preliminary effect of Fukushima • Nuclear safety to human & environment becomes priority of people’s concerns • Significant improvement of public understanding about nuclear technology and nuclear safety • Several opposite opinions against nuclear power and the NP Project appeared on the Internet through blogs, forum & interview • Some concerns about the project from local communities in Ninh Thuan • Questions from Members of National Assembly to the Government on nuclear safety and location of NPP project in Vietnam • Needs of a better siting & technology assessment for the NP Project 28
Actions by the Government • Response from Government in General Session of National Assembly: – Emphasize the priority of nuclear safety – Ninh Thuan NPP will use advanced & proven technology – Siting activities take into account earthquake, tsunami & other factors to the safety of NPP – Recalled about the preparation activities for the NPP Project – Government will report to the National Assembly about the preparation of Ninh Thuan NPP Project • Reconfirmation of nuclear power programme by high-ranking official – 8/2011: Deputy Prime Minister Hoang Trung Hai noted that NPP development program still needed to be implemented, and FS needed to be finished to evaluate the safety of the project before making decision • Active cooperation with with Japan, Russia in siting assessment, FS report, human resources training, etc for Ninh Thuan NPP Project • Cooperation with IAEA, vendor countries & other to develop the nuclear infrastructure for the NPP Project 29
MAIN CONTENTS I. Nuclear Power Programme of Vietnam II. Overview of Public Communication Programme III. Action Plan for Ninh Thuan NP Project IV. Response to Fukushima Accident V. Conclusion Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012 30
Challenges & Solutions (1) Challenges Solutions • Lack of a clear nuclear power • Development and enforcement public information policy of a national PI policy • Lack of an organized, • Establishment and realization of systematic, long-term nuclear a national long term and power public information systematic organized public programme information campaign • Lack of human resources for • Human resource training and public communication, including development in the PI area training programme for • Promotion of international communicators cooperation for public • Insufficient financial resources communication • Lack of active participation of • Close coordination among local authorities and various relevant organizations communities (MOIT, MOST, MOIC, local authorities,...) 31
Challenges & Solutions (2) Challenges Solutions • Unfavourable information caused • Best preparation for the first by recent nuclear accidents in nuclear power project Japan. • Systematic study of anti-nuclear • Academic oppositions from some opinions & countermeasures well-known experts through • Continuous distribution of interview & internet reliable and well-sourced • Uncertainty of public opinion information through interview, under influence of mass media articles, documentary,... • Over-critical view & negative- • Close communication with press report tendency of mass media • Most important: Acceleration of towards nuclear power resettlement project & infrastructure development project in Ninh Thuan 32
Lessons learned • To secure a successful public information program, the following factors are critical: • Strong commitment of the top leaders of the country towards nuclear power; • Strong support and close cooperation from local authorities; • Positive support of the mass media; • Dissemination of transparent information: open all information; supply objective and true information; and ready to honestly answer all questions relating to nuclear power; • Creation of confidence is important, but maintenance of such thing is vital; • Thoughtful attitude and goodwill of the project owner towards all aspects of the locality. 33
Thank you for your attention! Nguyen Viet Phuong Department of Nuclear Science & Technology Management Vietnam Atomic Energy Agency 113 Tran Duy Hung Str., Cau Giay, Hanoi, Vietnam nvphuong@most.gov.vn; ngvietphuong@gmail.com With contributions of: Dr. Hoang Anh Tuan (VAEA), Mr. Pham Quang Trung (VAEA), Ms. Nguyen Thi Van Ly (EVN NPB), Dr. Tran Van Luyen (EVN NPB) 34