MINISTRY OF SCIENCE AND TECHNOLOGY
         VIETNAM ATOMIC ENERGY AGENCY

  PUBLIC COMMUNICATION PROGRAMME
FOR THE FIRST NUCLEAR POWER PROJECT

                 Nguyen Viet Phuong
   Department of Nuclear Science & Technology Management

                  Vienna, January 2012

                                                           1
MAIN CONTENTS

                 I. Nuclear Power Programme of Vietnam

         II. Overview of Public Communication Programme

                III. Action Plan for Ninh Thuan NP Project

                    IV. Response to Fukushima Accident

                                        V. Conclusion

Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012
                                                                                                  2
NP Development Projection

                            Ky Xuan (Ha
                            Tinh)

                                            Duc Thang
                                            (Quang Ngai)
                                            Duc Chanh
                                            (Quang Ngai)
                                               Hoai My
                                               (Binh Dinh)
                                                 Xuan Phuong
                                                 (Phu Yen)
                                                 Binh Tien
                                                 (Ninh Thuan)
                                                 Vinh Hai
                                                 (Ninh Thuan 2)
                                          Phuoc Dinh
                                          (Ninh Thuan 1)

                                                                  3
Ninh Thuan Nuclear Power Project
                      • Ninh Thuan NPP Project
                       • Ninh Thuan 1: Phuoc Dinh
                          – 2 x 1,000 MWe
                       • Ninh Thuan 2: Vinh Hai
                          – 2 x 1,000 MWe
                       • COD:
                          – Ninh Thuan 1: 2020-2021
                          – Ninh Thuan 2: 2021-2022
                       • Investment Owner: EVN
                       • Technology: Advanced &
                         proven (LWR)
                       • Cooling: Sea water
                       • Fuel: Imported

                                                      4
Milestones of the Project

     Milestone 1    • Ready to make knowledgeable
                      commitment to a nuclear program
    (Completed in   • 25th Nov. 2009: Pre-FS report of the
                      Ninh Thuan NPP project was
      11/2009)        approved by the National Assembly

                    • Ready to invite bids (Vietnam: ready
     Milestone 2      to sign the contract)
                    • Construction of the 1st Unit will start
      (12/2012)       in 2014.

     Milestone 3    • Ready to commission and operate
                      the first unit of the Ninh Thuan NPP.
      (12/2020)

                                                                5
MAIN CONTENTS

                 I. Nuclear Power Programme of Vietnam

         II. Overview of Public Communication Programme

                III. Action Plan for Ninh Thuan NP Project

                    IV. Response to Fukushima Accident

                                        V. Conclusion

Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012
                                                                                                  6
Implementation Scheme

                    Direction by
                    Government
              Implementation by ministries of
               Sci. & Tech., Industry & Trade,
             Info. & Com., People’s Committee
                   of Ninh Thuan Province

            Undertaken by MOST, EVN, local
         authorities of NP Project site & other
       stakeholders, in cooperation with foreign
        partners (JETRO, JAIF, ROSATOM, EDF,...)

                                                   7
Objectives of public communication

               • To build, maintain and develop a friendly and favourable relationship

  Short          with local communities
               • To reach the consensus of the domestic and local community towards
                 the investment policy and siting of Ninh Thuan NPP
               • To gain success in the site clearance, compensation and resettlement

  term
                 during the project construction period
               • To increase the awareness and understanding of the local residents of
                 the necessity and benefits of Ninh Thuan NPP, a nation-scale significant
                 project, as well as the whole nuclear power development program

   Long
               • To enhance the public understanding of nuclear power
               • To gain the public acceptance of nuclear power development in Vietnam
               • To improve EVN’s image as a reliable project investor by social
                 contributions in the project area, which will create a trust of the local
                 residents towards the project owner

   term        • To better the material as well as spiritual livings of local residents
               • To raise the public awareness of energy and environmental issues
               • To set up an effective communication system

                                                                                             8
Target groups of audiences
Frequently watch TV, listen to radio, and read                              Officials in Governmental bodies, elective
newspapers even in off peak hours; Quickly                                  agencies (e.g. National Assembly), and
communicate and make strong influence in                                    Communist Party organizations, who will
relatives, friends and neighbours, and of                                   directly discuss, formulate, and approve the
course their family (husbands and children)                                 policies, plans of nuclear power development

                                                 Housewife     Decision
                                                   group       makers

They are next generation who
are in five or ten years will be
decisive citizens and will                                            Academics            Especially for those who are
                                            School
participate in the nuclear                                               and               working in energy industry and
power development course of                children                                        energy related sectors
the country
                                                                      professors

                                                   Local
                                                 communiti      Media
                                                    es        journalists
Crucial and long run target groups of public      residents                 a special target group who is both the target
information, including Veteran Association,                                 of public information of nuclear power and
Women Association, Youth Association,                                       the producer of information
religious dignitaries, Fatherland Front
Committee, etc. Attention should be paid to
ethnic minority people communities

                                                                                                                        9
Major theme

         General Public                   Local communities

• Nuclear safety;                 • Major concerns of local
• Rationale of nuclear power        communities:
  introduction in Vietnam;        • Project contributions to the host
• Radioactive waste management;     community: compensation
• The economic competitiveness      regime in the resettlement plan,
  of nuclear power                  employment opportunities,
                                    local socio-economic
• Project implementation
                                    development, etc.;
  capabilities (HR);
                                  • Environmental impacts of the
• Consideration of alternatives
                                    project;
  such as renewable energy or
  energy saving to defer the      • Nuclear safety and emergency
  introduction time of nuclear      preparedness plan;
  power.                          • Spent-fuel disposal and rad-
                                    waste management.

                                                                        10
Implementation plan
                    • Exhibitions/ Seminars/Workshops organized both in big cities and
    Exhibition        Ninh Thuan

                    • Domestic (to Da Lat Research Reactor) and abroad for target groups
   Facility tours     of audience

  Public hearings   • At least once a year

   Mass media       • Information dissemination via news agency, VTV, VOV, press

    PR Centre       • Nuclear PR Centre in Ninh Thuan & Hanoi

 Online promotion   • Websites, online articles, interviews

    Education       • Education & training programmes for schools & universities

Support programme   • Support programme for local communities

                                                                                           11
Major results of national activities (1)
•   07 national nuclear exhibitions in the period of 2001-2010:
     – Nuclear exhibitions in Hanoi, Phu Yen, Ninh Thuan, Ho Chi Minh City
     – 04 Nuclear Power Expos in Hanoi (2004, 2006, 2008, 2010)
     – More than 38.000 turns of visitors, including members of National Assembly,
        senior officials of Government & local authority, school children, students,....
•   Publishing of articles, books, leaflets, brochures on nuclear power
•   Regular organization of site visits for reporters from central and local media
    agencies
•   Interview, talk shows on nuclear power with the participation of authorized
    representatives of state management bodies, scientists, project owners, local
    authorities on VTV1, VTV2, VOV, Invest TV (VCTV), MOST Website,
    Vietnamnet, Government Web Portal,...
•   Organizations of seminars on nuclear power for broadcasts & press
     – The Workshop on “Situation of Nuclear Power Development in the world and
        Long-term Strategy on Nuclear Power Development in Vietnam” with
        participation of General Editors of Broadcast and Newspapers and PI key
        persons from all provinces in the North of Vietnam

                                                                                           12
MAIN CONTENTS

                 I. Nuclear Power Programme of Vietnam

         II. Overview of Public Communication Programme

                III. Action Plan for Ninh Thuan NP Project

                    IV. Response to Fukushima Accident

                                        V. Conclusion

Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012
                                                                                                  13
Ninh Thuan Province

• Area: 3,358 km2
                           Population: 571,000 (2010)
• Coastal line: 105 km        Pop. den.: 170/km2
• GDP gross:
  – 2011: 10.6%
  – 2012-2015: >14%
                                                  Kinh
• GDP per capita:                                 Cham
  – 2011: 800 USD (60%                            Ragley
    of domestic average)                          Others
  – 2015: ~ 1,400 USD
    (70% of domestic
    average)

                                                           14
Communication messages
• Nuclear power as an engine for national economic development
   – Energy security
   – Reasonable answer to energy problems in the future
   – Solution to improve the national position in the international
     community
• Benefits of nuclear power projects to the local communities
   – Material and non-material benefits
   – Local socio-economic development
• Safety First policy in the pursuit of nuclear power project, including
  safety & environmental management of NPP
• National knowledgeable commitments
   – Manpower preparation
   – Infrastructure development such as preparation of legal
     framework

                                                                           15
Communication strategy
                                                       - Focus on essential &
                                                       sensitive target groups:
                                                       Spiritual leaders, village
                                                       patriarchs, seniors of
                                   Categorization of   minority groups
                                       audience

- Flexible content
depending on level of
understanding of
audiences
                          Flexibility of        Diversification
                        communication                 of            -Different method
                          for different        communication        for each category
                         circumstances             methods          of audience
                                                                    - Greatly depends
                                                                    on capability of
                                                                    communicators

                                                                                    16
Type of activities
                                        Seminar
                                        Workshop

              Activities by                                  Official visit
                  local                                      of top-level
             communicators                                     officials

        Domestic &                                                   Field trip
          foreign                                                       for
        facility tours                                              journalists

                                                                                 Public
                         Resettlement               Local
                            project                                           Communica
                                                   support
                                                                              tion Centre

                                                                                            17
Local support
• Clear resettlement project
  with adequate infrastructure       Vietnamese students sent
  of water, electricity and         to Russia for nuc. eng. edu.
  business opportunities                  80
                                          70
• Infrastructure development
                                          60
  project (road, housing) for the
                                          50
  local communities
                                          40
• Promotion of local                      30
  participation to the project            20
  through increasing number of            10
  Ninh Thuan students sent to              0
  Russia for nuclear                             2010      2011
  engineering education             Ninh Thuan    6         11
                                      Other
• Commitment by operator of                       23        57
                                    provinces
  profit sharing from the Project

                                                                   18
Public Relation Centre (1)
• Investor: EVN (as one of
  component projects of Ninh
  Thuan NPP approved by the
  Prime Minister)
• Location: Phan Rang – Thap
  Cham City
• Area: 3,000 m2
• Objectives:
   – A destination for local and
     foreign visitors for improving the
     awareness and understanding of
     nuclear power and Ninh Thuan
     NPP project
   – To bring the public closer to
     nuclear power with positive
     information

                                          19
Public Relation Centre (2)

Functions                         Structures
• Exhibitions of energy, power    • Exhibition hall (three-storied
  generation and nuclear power       building)
• NPP introduction history in     • 3D projection room
  Vietnam                         • Meeting room
• Introduction of EVN; chain of   • Library
  electricity supply from         • Data archive area
  generation, transmission to
  distribution                    • Exhibition room of Ninh Thuan’s
                                     specialities
• Overview of NPP reactors, NPP
  operation schemes               • Entertainment area
• Introduction of nuclear fuel
  cycle, nuclear safety and
  radiation protection
• Emergency preparedness
  response

                                                                      20
Activities in number (1)
• 05 provincial-level seminar/workshop (2003, 2008, 2009, 2011 – in
  cooperation with ROSATOM):
   – Theme: Nuclear power, Ninh Thuan NPP, benefit of Ninh Thuan
      from the Project
   – Audience: 300-400/event, including official of local authorities,
      minority group leaders (spiritual leader, senior bonzes), religion
      leaders (Catholics, Protestant)
• 60 small-scale workshops targeted at various local people groups
   – Audience: ~ 7000 (in total), including official of local authorities,
      representatives of social organizations (youth, woman, veteran),
      soldiers from local military units, school children,...
• 02 three-day training courses (2009, 2010) to train local
  communicators on nuclear power for 30 participants from local region
• 11 domestic facility tours to Da Lat Research Reactor & 06 foreign
  facility tours (to Japan, France, China, the US) for local leaders and
  residents with >260 local participants
                                                                             21
Activities in number (2)
• Various official visits to the project sites of high-ranking officials
  such as the Prime Minister, Deputy Prime Minister, Minister of Planning
  and Investment, Minister of Industry, Chairman of the National
  Assembly’s Science, Technology and Environment Committee, etc.
• Organization of 06 field trips to NPP site for journalists
• Other local supports:
   – Giving presents (notebooks, school bags) for good and poor pupils,
     and bookcases for local elementary and secondary schools
   – Financial contribution & participation by EVN to local charity &
     community activities, including local traditional cultural festivals,
     especially those of local ethnic minority people
   – Support for local competition to disseminate legal information
     regarding nuclear power

                                                                             22
Major results (3)

                                                           Local competition on nuclear power, 1/2011

Especially, Ninh Thuan is chosen for the construction of
the first two NPPs in the country, with the total
investment of r. 16 bil. USD and the most advanced
and safe technology in the world. This is an essential
opportunity for Ninh Thuan to have a breakthrough in
rapid and sustainable development.                             Atomstroyexport Workshop, 12/2011
- Prime Minister Nguyen Tan Dung, Ninh Thuan 2011
                                                                                                   23
Results and Issues
Results                               Issues
• Active support from majority of     • Low frequency, lack of continuity
  local communities to the Project,     and long-term plan for activities
  some even urge to accelerate          (now mainly focus on short
  the Project                           events like seminar, visit,..)
• Official agreement to the Project   • Insufficient content for
  from the People’s Committees          communication (lack of suitability
  (local authority) of all three        with level of understanding of
  levels: Phuoc Dinh & Vinh Hai         local people)
  communes (sites for 2 first         • Insufficient understanding
  NPPs); Ninh Phuoc (now Thuan          between investor, organizers of
  Nam) & Ninh Hai districts; Ninh       activities and press, results in
  Thuan Province                        conflict & biased information by
• Continuous public understanding       newspapers, website,…
  and support , even after            • Lack of coordinator for activities
  Fukushima Accident                  • Negative effects of Fukushima
                                                                         24
MAIN CONTENTS

                 I. Nuclear Power Programme of Vietnam

         II. Overview of Public Communication Programme

                III. Action Plan for Ninh Thuan NP Project

                    IV. Response to Fukushima Accident

                                        V. Conclusion

Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012
                                                                                                  25
Immediate response
15/3/2011: Press conference on the
incident hosted by MOST
16/3/2011: Establishment of Working
Group on Analysis & Distribution of
Information on the Fukushima Accident by
MOST
3-4/2011: Timely monitoring of radiation
level in Hanoi, Da Lat, Ninh Thuan, Lang
Son, Ho Chi Minh City
16/3-28/4/2011: Distribution of Daily
Report by the Working Group on the
Fukushima Accident & Result of domestic
measure of radioactivity & radiation level
3/2011: Radiation screening for
Vietnamese citizen came back from the
affected zone (Sendai) & examination of
imported goods & foods of Japanese origin

                                             26
Daily Report on Fukushima by MOST

•   Number of reports: 38 (16/3-28/4)   •   Assessment:
•   Frequency: Daily (by 6 PM                – Provide press and public with
    everyday)                                  reliable and well-sourced
•   Content                                    information
     – Update on situation of                – Stabilize the public opinion about
       Fukushima & radioactive                 the accident
       discharge from Fukushima              – Reassure public about the safety
       (analyzed information from              for human and environment
       JAIF, NISA, IAEA, CTBTO, US           – Inform press and public
       NRC, IRSN, WNN)                         knowledgeable and clear
     – Result of daily measurement by          information about nuclear safety
       MOST (VINATOM, VARANS) of               & technology
       environmental background              – Raise the public awareness
       radiation level & radiation             about the first priority of safety in
       monitoring                              nuclear industry
     – Confirmation of safety for            – Maintain the public support for
       human and environment                   the nuclear power programme

                                                                                   27
Preliminary effect of Fukushima
• Nuclear safety to human & environment becomes priority of
  people’s concerns
• Significant improvement of public understanding about
  nuclear technology and nuclear safety
• Several opposite opinions against nuclear power and the NP
  Project appeared on the Internet through blogs, forum &
  interview
• Some concerns about the project from local communities in
  Ninh Thuan
• Questions from Members of National Assembly to the
  Government on nuclear safety and location of NPP project in
  Vietnam
• Needs of a better siting & technology assessment for the NP
  Project

                                                                28
Actions by the Government
•   Response from Government in General Session of National Assembly:
      – Emphasize the priority of nuclear safety
      – Ninh Thuan NPP will use advanced & proven technology
      – Siting activities take into account earthquake, tsunami & other factors to
         the safety of NPP
      – Recalled about the preparation activities for the NPP Project
      – Government will report to the National Assembly about the preparation
         of Ninh Thuan NPP Project
•   Reconfirmation of nuclear power programme by high-ranking official
      – 8/2011: Deputy Prime Minister Hoang Trung Hai noted that NPP
         development program still needed to be implemented, and FS needed
         to be finished to evaluate the safety of the project before making
         decision
•   Active cooperation with with Japan, Russia in siting assessment, FS report,
    human resources training, etc for Ninh Thuan NPP Project
•   Cooperation with IAEA, vendor countries & other to develop the nuclear
    infrastructure for the NPP Project

                                                                                     29
MAIN CONTENTS

                 I. Nuclear Power Programme of Vietnam

         II. Overview of Public Communication Programme

                III. Action Plan for Ninh Thuan NP Project

                    IV. Response to Fukushima Accident

                                        V. Conclusion

Nguyen Viet Phuong, Public Communication Programme for the 1st NP Project, Vienna, January 2012
                                                                                                  30
Challenges & Solutions (1)
Challenges                           Solutions
• Lack of a clear nuclear power      • Development and enforcement
  public information policy            of a national PI policy
• Lack of an organized,              • Establishment and realization of
  systematic, long-term nuclear        a national long term and
  power public information             systematic organized public
  programme                            information campaign
• Lack of human resources for        • Human resource training and
  public communication, including      development in the PI area
  training programme for             • Promotion of international
  communicators                        cooperation for public
• Insufficient financial resources     communication
• Lack of active participation of    • Close coordination among
  local authorities and                various relevant organizations
  communities                          (MOIT, MOST, MOIC, local
                                       authorities,...)
                                                                          31
Challenges & Solutions (2)
Challenges                          Solutions
• Unfavourable information caused   • Best preparation for the first
  by recent nuclear accidents in      nuclear power project
  Japan.                            • Systematic study of anti-nuclear
• Academic oppositions from some      opinions & countermeasures
  well-known experts through        • Continuous distribution of
  interview & internet                reliable and well-sourced
• Uncertainty of public opinion       information through interview,
  under influence of mass media       articles, documentary,...
• Over-critical view & negative-    • Close communication with press
  report tendency of mass media     • Most important: Acceleration of
  towards nuclear power               resettlement project &
                                      infrastructure development
                                      project in Ninh Thuan

                                                                         32
Lessons learned
• To secure a successful public information program, the
  following factors are critical:
• Strong commitment of the top leaders of the country towards
  nuclear power;
• Strong support and close cooperation from local authorities;
• Positive support of the mass media;
• Dissemination of transparent information: open all information;
  supply objective and true information; and ready to honestly
  answer all questions relating to nuclear power;
• Creation of confidence is important, but maintenance of such
  thing is vital;
• Thoughtful attitude and goodwill of the project owner towards
  all aspects of the locality.

                                                                    33
Thank you for your attention!
                    Nguyen Viet Phuong
     Department of Nuclear Science & Technology Management
                 Vietnam Atomic Energy Agency
        113 Tran Duy Hung Str., Cau Giay, Hanoi, Vietnam
        nvphuong@most.gov.vn; ngvietphuong@gmail.com

With contributions of: Dr. Hoang Anh Tuan (VAEA), Mr. Pham Quang
Trung (VAEA), Ms. Nguyen Thi Van Ly (EVN NPB), Dr. Tran Van Luyen
(EVN NPB)

                                                                    34
You can also read