MTEP20 Reliability Study
                  Overview
     3rd South Subregional Planning Meeting
                               August 25, 2020

1
MTEP20 Reliability Study Overview - 3rd South Subregional Planning Meeting August 25, 2020 - Midcontinent ...
Purpose &            Purpose: Provide an overview of MTEP20
Key                  reliability projects recommended for BOD
Takeaways            approval
              Key Takeaways:
                  • 513 new projects, at a cost of $4.01 billion, will be
                    recommended for MTEP20 Appendix A
                         •   46 new projects are proposed in the South region, at a cost of
                             $0.53 billion

                         •   Zero Expedited Project Review (EPR) requests received in the
                             South region

                  • In December, MISO staff will present the recommended
                    MTEP20 Appendix A projects, as well as the report, for BOD
                    approval

2           Project information as of August 3, 2020
MTEP20 Reliability Study Overview - 3rd South Subregional Planning Meeting August 25, 2020 - Midcontinent ...
Historical MTEP investment (millions) shows slight growth

                                                                                                   $3,996                $4,008

                                                                            $3,469

                                $2,695                $2,683
          $2,589

        A in MTEP15         A in MTEP16           A in MTEP17           A in MTEP18           A in MTEP19           A in MTEP20

3
                                              Project information as of August 3, 2020
          Statistics do not reflect all economic projects, GIPs, or TDSPs currently under evaluation in separate planning processes
MTEP20 Reliability Study Overview - 3rd South Subregional Planning Meeting August 25, 2020 - Midcontinent ...
MTEP20 Top 10 Projects1 (by cost)

           2. New LaSalle Area 138kV Statcom                                             6. Upgrade Greentown 765kV Substation

                                                                                      3. New Robinson 138kV Statcom
          1. New Massac Substation
          4. Rebuild Grand Tower - Carbondale
          5. Rebuild Albion South - Norris City
          9. New Jordan Substation - Convert                                8. Choudrant 230kV Station
          West Frankfort 230kV to 345kV

                   7. Millbend 138kV Station

                                                                    10. Castle 230kV Station

4                           1. Blanket Asset Renewal Projects excluded from ranking
                                    Project information as of August 3, 2020
Majority of MTEP20 projects go into service within four years
 and are primarily transmission line and substation work
                                                                                                                                                Transmission
              26.3%                                                                                                                               Line New
                       25.3%                                                                                                                         11%
                                  24.0%

                                                                                                             Substation
                                                                                                               45%                         Transmission
                                                                                                                                           Line Upgrade
                                                                                                                                               37%
       9.2%                                   9.0%

                                                         4.3%

1.2%
                                                                    0.4%       0.2%       0.2%              Transformer          Voltage Device
                                                                                                                4%                     2%
2019   2020   2021      2022       2023       2024       2025       2026       2027       2029                        Facility type

  5
                                                   Project information as of August 3, 2020
               Statistics do not reflect all economic projects, GIPs, or TDSPs currently under evaluation in separate planning processes
In MTEP 2020 – 513 new projects will be recommended for
approval
                                                                                         BRP 8

                                                                                                                                       Other        BRP 33
                                                                                             GIP                                        38
    Other Local Needs                                                                        49
            9                                                                                          West
                                                                                 Other 90
                                                                                                                                                 GIP 15
      Load Growth                                                                                                              East
          53
                                                    MISO Total                                                                                 BRP 25
                                                                                                                                                          GIP 14
                                                                                                                       Central
        Age and                                               BRP
        Condition
          137                                                  75                                                                    Other
                                                                                                                                      195
                                                Other                 GIP                              BRP 9
                                                                                            Other
                                                 345                  93                     22
                                                                                                        GIP       South
                                                                                                        15
     Local Reliability
           146

6
                                                         Project information as of August 3, 2020
                     Statistics do not reflect all economic projects, GIPs, or TDSPs currently under evaluation in separate planning processes
In MTEP 2020 – An estimated cost of $4.01 billion will be
recommended for approval                                                                 BRP $42M
                                                                                                                                       Other       BRP
                                                                                               GIP                                    $193M       $198M
    Other Local Needs                                                                         $230M
          $45 M                                                                                                                             GIP
                                                                                    Other              West                                $126M
                                                                                    $665M
      Load Growth                                                                                                              East
        $480 M
                                                    MISO Total
                                                                                                                                                  BRP
        Age and                                                BRP                                                     Central                   $372M     GIP
       Condition                                                                                                                                          $87M
       $1,079 M                                               $684M                                                                  Other
                                                                                                     BRP                            $1,562M
                                                                    GIP                              $72M
                                                                   $538M                                 GIP
                                                                                                        $96M
                                               Other                                           Other             South
                                              $2,786M                                         $367M

       Reliability
       $1,185 M

7
                                                         Project information as of August 3, 2020
                     Statistics do not reflect all economic projects, GIPs, or TDSPs currently under evaluation in separate planning processes
Proposed investment for the South Region for MTEP20 is
less than that of MTEP19
                                              MTEP19                    MTEP20
                                         Approved Appendix A       Proposed Appendix A
                                             Project Count - 71        Project Count - 46

                                                   BRP             Other              GIP

8
                                          Project information as of August 3, 2020
      Statistics do not reflect all economic projects, GIPs, or TDSPs currently under evaluation in separate planning processes
Questions?
Appendix
MTEP20 Top 10 Projects1 Details
                                                                                                                          Submitting         Estimated
     Rank   PrjId      Project Name                                                                            Type
                                                                                                                          Company            Cost ($M)
                                                                                                            Local        Ameren Services
      1     11925 New Massac Substation - Convert Joppa 230 kV substation to 345 kV substation                                                 112.4
                                                                                                           Reliability   Company
                                                                                                                         Ameren Services
      2     18249 New LaSalle Area 138 kV Statcom (100 MVAR)                                                   BRP                             91.4
                                                                                                                         Company
                                                                                                                         Ameren Services
      3     18250 New Robinson 138 kV Statcom (70 Mvar)                                                        BRP                              78
                                                                                                                         Company
                                                                                                           Age and       Ameren Services
      4     17910 Rebuild Grand Tower-Carbondale NW 138 kV line                                                                                75.6
                                                                                                           Condition     Company
                                                                                                           Age and       Ameren Services
      5     13797 Rebuild Albion South-Norris City North 138 kV to double circuit                                                               74
                                                                                                           Condition     Company
                                                                                                           Age and       American Electric
      6     17684 Upgrade Greentown 765 kV substation                                                                                           70
                                                                                                           Condition     Power

      7     18248 Millbend 138 kV: New Distribution Station                                              Load Growth     Entergy Texas         65.4

      8     13925 Choudrant: New distribution substation                                                 Load Growth     Entergy Louisiana     56.2

                     New Jordan Substation - Convert West Frankfort 230 kV substation to 345 kV             Local        Ameren Services
      9     11926                                                                                                                              56.1
                     substation                                                                            Reliability   Company

      10    15648 Castle 230 kV: New Distribution Station                                                Load Growth     Entergy Texas         50.51

                                                     1. Blanket Asset Renewal Projects excluded from ranking
11                                                           Project information as of August 3, 2020
MTEP20 Utilizing ShareFile
•        MISO’s secure FTP is under transition to MISO
         ShareFile service to post non-public information for
         MTEP studies
         https://misoenergy.sharefile.com/Authentication/Login

•        New users can request access through MISO website
         https://www.misoenergy.org/access-request/access-request-form/

•        Similar folder structure with FTP and subfolders
         named in a commonly way
         •      MTEP20/Input_Files
         •      MTEP20/Dynamics
         •      MTEP20/Steady_State_Analysis
                •     …Results
                •     …Models
         •      Many other resources used in analysis
    12                                                                    MTEP20 folder in MISO ShareFile view
MISO South top 10 Targeted Appendix A projects represents
66% of the total MTEP20 cost of $534 million for the region

13
Overview of MTEP Types
                                  • Transmission projects required to meet reliability standards
 Baseline Reliability Projects
                        (BRP)       of NERC or applicable Regional Reliability Organizations in
                                    the Transmission Provider Region.

        Transmission Delivery
      Service Projects (TDSP)     • Required to satisfy a Transmission Service request.

 Generation Interconnection       • Upgrades that ensure the reliability of the system when new
              Projects (GIP)        generators interconnect.

                                  • Provide reductions in market congestion.
      Market Efficiency Project
                        (MEP)     • Developed to produce a benefit-to-cost ratio of 1.25 or
                                    greater.

                                  • Provide regional public policy economic and/or reliability
     Multi-Value Project (MVP)
                                    benefits.

            Market Participant    • Network upgrades fully funded by one or more market
             Funded Projects        participants but owned and operated by an incumbent
                     (MPFP)         Transmission Owner.
                                                                                                   1.   Reliability
                                                                                                   2.   Age and Condition
                                  • A project not meeting any of these classifications is          3.   Load Growth
                Other Projects
                                    designated as ‘Other’.                                         4.   Other Local Needs

14                                             More detailed is in Appendix                                           14
Overview of Tariff-defined project types
•    “Baseline Reliability Projects are Network Upgrades identified in the base case as required to ensure that the Transmission System
     is in compliance with applicable national Electric Reliability Organization (“ERO”) reliability standards and reliability standards
     adopted by Regional Reliability Organizations and applicable within the Transmission Provider Region.”
•    “Generation Interconnection Projects are New Transmission Access Projects that are associated with interconnection of new, or
     increase in generating capacity of existing, generation.”
•    “Market Participant funded projects (MPFPs) are defined as Network Upgrades fully funded by one or more market participants but
     owned and operated by an incumbent Transmission Owner.”
•    Other projects do not meet the criteria to be considered as Baseline Reliability Projects, New Transmission Access Projects, Market
     Efficiency Projects, or Multi-Value Projects. Other projects may include projects to satisfy Transmission Owner and/or state and local
     planning criteria other than NERC or regional reliability standards, interconnect new Loads, relocate transmission facilities, address
     aging transmission infrastructure, replace problematic transmission plant, improve operational performance or address other
     operational issues, address service reliability issues with end-use consumers, improve aesthetics including but not limited to
     undergrounding overhead transmission facilities, address localized economic issues, and address other miscellaneous localized
     needs.
•    Market Efficiency Projects (MEPs) meet Attachment FF requirements for reduction in market congestion and are eligible for
     regional cost allocation. Projects qualify as MEPs based on cost and voltage thresholds and are developed to produce a benefit-to-
     cost ratio of 1.25 or greater
•    Multi-Value Projects (MVPs) meet Attachment FF requirements to provide regional public policy, economic and/or reliability benefits.
     Costs are shared with loads and export transactions in proportion to metered MWh consumption or export schedules
•    Transmission Delivery Service Project (TDSP) projects are required to satisfy a transmission service request. The costs are
     generally assigned to the requestor.

    15
MTEP20 Reliability Planning Stakeholder Meeting Schedules
                                                                   2020
   Jan           Feb            Mar           Apr       May          Jun           Jul          Aug              Sept         Oct            Nov          Dec

                                                           2nd SPM,                        3rd SPM,
   1st SPM
                                                        Michigan TSTF                   Michigan TSTF                                                  MTEP20
Present TO/MP                                                                                                                                           BOD
                                                       Present results of               Recommendation
  submitted                                                                                                                                           Approvals
                                                       MISO independent                   of MTEP20
   Projects
                                                        TPL assessment                      Projects                                                    Dec
     Jan
                                                           May/Jun                            Aug

                                                                  Meeting Locations
SPMs                                                MCPS TSTF                 Michigan TSTFs*                     Other TSTFs
Central: SPM1: MISO-Carmel, SPM2 & 3: TBD           WebEx Only                Two TSTFs: Occur two weeks prior    Based on proximity to study needs
East: SPM1: Regional TOs Offices, SPM2 & 3: TBD                               to SPM2 and SPM3
South: SPM1: MISO-Little Rock, SPM2 & 3: TBD                                  TSTF1: WebEx;
West: SPM1: MISO-Eagan, SPM2 & 3: TBD                                         TSTF2: TBD

    16                                              * Michigan TSTFs will address only reliability issues
MTEP20 Reliability Planning Processes are closely
      coordinated on issues and solutions
                 2019                                                                      2020
Jun        Jul   Aug     Sept    Oct     Nov   Dec       Jan       Feb      Mar      Apr     May   Jun    Jul     Aug   Sept    Oct   Nov   Dec

                             TO/MP        Exchange of              MISO Independent TPL
 Information Exchange       proposed      TO planning            assessment to identify issues        MISO reviews
TO models and Planning        project      information                                               alternatives and
        Criteria            submittals    between TO            Review TO projects and identify
                                                                                                     completes gap
                                for            and                          gaps
Stakeholder Comments                                                                                     analysis
                             MTEP20       Stakeholders         Stakeholders provide alternatives
      Jun – Sept                                                                                        Jun - July
                            Sept 15th      Sept - Dec                    Jan - May                                                  Project
                                                                                                                               Recommendation
                                                                                                                               for BOD Approval
                                                                                                                                   Sept - Dec

                                                                  Issues and Solution Development Coordination

      17