Monthly construction update - Domain Precinct April 2021 - Metro Tunnel

Page created by Jason Mueller
 
CONTINUE READING
Monthly construction update - Domain Precinct April 2021 - Metro Tunnel
Monthly construction update
Domain Precinct
April 2021

Major construction is continuing in Domain at the site of the future Anzac
Station. This update provides an outline of current and upcoming works
in your area.

In an exciting milestone, TBM Millie has now                 When are we working?
completed her 1.8 kilometre tunnelling drive from
Anzac Station to Town Hall Station. TBM Alice
continues to make great progress as well and is                             Normal construction hours
now in her deepest section of tunnel, having now
travelled beneath Citylink.                                                 7am to 6pm, Monday to Friday
                                                                            7am to 1pm, Saturdays.
At the future site of Anzac Station, works are
progressing on both sides of the acoustic
shed, and beneath St Kilda Road. The Shrine of                              Out of hours
Remembrance station entrance and the train/
tram interchange continue to take shape.                                    Some works are required to
                                                                            take place out of normal
In the station box, the first stage of sacrificial tunnel                   construction hours.
demolition and excavation is complete, with crews
now returning their attention to constructing the
concourse level slab. Underneath the acoustic shed,
in the northern part of the station box, the team is                        24 hours
currently working to construct columns from base                            24 hour works are sometimes
to concourse level.                                                         required during peak
                                                                            construction activities.
Construction snapshot
Construction works are continuing within the
Domain precinct during April and will include:
— Tunnelling and TBM retrieval
                                                               Health and safety
— Tunnelling support site – excavated soil removal
                                                               Works on the Metro Tunnel Project are
— Station box construction                                     progressing with strict COVIDsafe Plans
                                                               in place. The health and safety of our
— Anzac Station entrance – Shrine of
                                                               workforce and community remains our top
  Remembrance
                                                               priority. For more information and advice
— Anzac Station entrance – tram interchange.                   about the coronavirus (COVID-19), please
                                                               visit http://coronavirus.vic.gov.au.
Further information on these works can be
found overleaf or at metrotunnel.vic.gov.au

                              Construction partner:

                                              Design &
                                              Construction
Monthly construction update - Domain Precinct April 2021 - Metro Tunnel
Works in your area                                      — The large crane on surface may be required until
                                                          10pm on some nights to feed steel down to the
                                                          teams working on the concourse
Tunnelling and TBM retrieval
                                                        — These works are expected to generate low to
Beneath St Kilda Road and Queen
                                                          medium levels of noise underneath the roof slab
Victoria Gardens
Ongoing until mid-2021                                 — Once the base slab has been poured, the team
                                                          will work to remove the falsework deck that
— TBM Millie completed her 1.8km journey from the         supported the concrete pour. This will be lifted
  Anzac Station site to the Town Hall Station site in     out from the void in south box
  late March, while TBM Alice has now completed
                                                        — Towards the end of the month, excavation and
  one kilometre, having passed the halfway mark
                                                          demolition of the sacrificial tunnel will restart
  to her tunnelling drive
                                                          once the concourse falsework has been removed
— Now that TBM Millie has finished tunnelling,
                                                        — Large longreach excavators will be delivered to
  crews will begin to dismantle the system of pipes
                                                          site to carry out these works
  that fed excavated material from the TBM back
  to the tunnelling support site                        — Excavation will continue beneath the roof slab
                                                          24/7, with this section of work being deeper into
— The pipes will be removed from site by trucks
                                                          the shaft than stage one
  through the acoustic shed
                                                        — On surface level, activity will include excavators
— Pipe removal will mostly occur within the tunnels
                                                          loading out soil. This loadout on surface will be
  and the acoustic shed and will generate low
                                                          required until 10pm
  levels of noise
                                                        — In the northern end of the station box (under the
— This month work will also begin on dismantling
                                                          acoustic shed) work will continue to construct
  the TBMs within the tunnels and pulling the
                                                          columns from the base level to the concourse
  gantry pieces back to the Anzac Station site to
                                                          level. This will involve installing falsework,
  be removed
                                                          formwork and completing concrete pours
— Once the Shrine of Remembrance station
                                                        — Additionally, construction of the concourse slab
  entrance is backfilled to ground level, this area
                                                          will commence in this area. Following the same
  will be used to store TBM pieces
                                                          methodology as in the southern part of the
— Track the progress of all TBMs on the Metro             station box, a falsework deck will be installed
  Tunnel Project website here: metrotunnel.vic.           before steelfixing is completed in preparation for
  gov.au (indicative only). For specific information      large concrete pours
  regarding the location of a TBM please get in
                                                        — Some steelfixing work may be required overnight
  touch with the project team on 1800 105 105.
                                                          contained within the north box and acoustic
                                                          shed area
Tunnelling support site
                                                        — To ensure structural integrity, concrete pours
Edmund Herring Oval and northern
                                                          must be continuous and therefore may need to
station box site
                                                          continue outside of normal construction hours.
Until late 2021
                                                        Anzac Station entrance –
— The TBM support site at Edmund Herring Oval
  continues to operate 24/7 to support tunnelling       Shrine of Remembrance
  operations until early May when TBM Alice             North east of construction site
  completes the drive to Town Hall Station              April
— Trucks removing excavated soil from the site
  will continue to use the primary route of Dallas      — The roof slab of this Anzac Station entrance
  Brooks Drive, Birdwood Avenue and Linlithgow            is now complete, with the two concrete pours
  Avenue (see map). With TBM Alice at work, soil          required to construct the roof completed in March
  removal is continuing overnight.                      — Since completion the team has been
                                                          waterproofing the slab to prevent water ingress
Station box construction
                                                        — This month, the team complete the backfill
Southern and northern station box site                    around the suspended roof slab, reinstating the
April ongoing                                            ground to the original surface level
                                                        — This backfilling work will require some pile
— Work to construct the concourse slab continues
                                                          breakback to cut the piles to the correct height.
  within the station box
                                                          This will generate periods of high level noise
— In the southern end of the station box, steelfixing
                                                        — Once the backfilling is complete, and the area
  work will be completed for the next concrete
                                                          is reinstated, it will be handed over to the
  slab to be poured
                                                          tunnelling team who will use the space for TBM
                                                          part storage during retrieval.
Monthly construction update - Domain Precinct April 2021 - Metro Tunnel
t
        sS
    orca                                                                                      Bi rd
   D                                                                                                  woo
                                                   Shrine of                                                dA

                         St Kilda Rd
                                                                                                               ve
                                                 Remembrance

                                                                                                                    l l a s B r o o k s Dr
 We
  lls S

                                                                                                                Da
                     t
        t

                  kS
            Par
                                                                Domain
                                                                            Rd

                                                                                                                                             Domain
                                                                                                                                                         Rd
                                                                                      Melbourne
                                                                                   Grammar School
                                            Ln
                                        n
                                       we

                                                                                    St

                                                                       es                             Legend
                                       Bo

                                                                  Cr                                                                             Bromb
                                                                                                                                                         y St
                                                                                      Ki

                                                              n                                                 Work zone
                                                           we
                                                                                       lda

                                                      Bo                                                        Void
                                                                                         Rd

                                                                                                                Northern station box
                                                                            Que

                                                                                                                Southern station box
                                            Ki
                                                                             ens

                                                 ng                                                             Station entrance construction
                                                      sW                                                        Tram interchange works
                                                                              Ln

                                                           ay
                                                                                                                                                                 t

                                                                                                                Tunnel boring support site
                                                                                                                                                         Adams S
                                                                                                                                             t
                                                                                                                                    Arnold S

                                                                                                                Acoustic shed
                                                                                                                Pedestrian access
                                                                                                                Cyclist access
                                                                                                                Traffic access
                                                                                                                Truck entry route (primary)
                                                                                                                Truck egress route (primary)

Indicative only

Anzac Station entrance –                                                         — To ensure structural integrity, concrete pours
tram interchange                                                                   must be continuous and therefore may need to
                                                                                   continue outside of normal construction hours
Between acoustic shed and St Kilda Road
April ongoing                                                                   — The team will also conduct waterproofing works
                                                                                   in the area to prevent water ingress
— This month, work will continue to construct                                    — Steelfixing and waterproofing works typically
  the base slab of the tram interchange                                            generate low to medium levels of noise.
  station entrance
— Steelfixing will continue in preparation for
  a large concrete pour in mid-April
Look ahead for 2021
                                              April           May                   June                  July

   Tunnelling

   TBM retrieval and tunnelling support
   site demobilisation

   Station box
   Concourse level construction

   Shrine entrance
   Roof construction and backfill

   Tram interchange entrance
   Base slab construction

   Tram interchange entrance
   Internal walls and roof construction

   Station box excavation to base level
   - southern end

   Station box base slab construction
   - southern end

   Traffic and transport impacts                          Business support
   — There will be ongoing 24/7 truck activity            While the new Anzac Station will be a significant
     in the Domain precinct until mid-2021                boost for the local area, construction activities
     associated with the delivery of pre-cast             can impact local businesses. In response to this,
     concrete tunnel segments and excavated               our Business Support Team assists businesses
     soil removal from the tunnelling support site        through the disruption and any permanent
     (see map).                                           changes that will take place.
                                                          Please see the offer in this notification from
                                                          Spence & Larder located at 403A St Kilda Rd,
                                                          Melbourne VIC 3004. We look forward
                                                          to promoting more local businesses as the
                                                          project progresses.

More information
To find out more about the Metro Tunnel Project:
   metrotunnel.vic.gov.au
   1800 105 105 (24 hours a day, 7 days a week)      It should be noted that this information is current at the time of
                                                      printing, however due to unforeseen circumstances, changes
Rail Projects Victoria                                may occur. Please visit railprojects.vic.gov.au for
                                                                                                                           CYP-WN00444

PO Box 4509, Melbourne, VIC 3001                      the latest updates.
spenceandlarder.com.au

   We have a large range of options to choose from including sandwiches,
         salads, hot meals, pies, sausage rolls, sweets & desserts
                   as well as smoothies and fresh juices.

      Everything we serve you is made in-house with fresh ingredients
       from our local suppliers… Oh, and coffee… really great coffee!

                               Catering now available
       Please contact via email orders@spenceandlarder.com.au or call on 9867 3790.

     403A St Kilda Rd, Melbourne VIC 3004       We look forward to seeing you!
                     @spence_and_larder         6am-4pm Monday - Friday
                         spenceandlarder        8am-3pm Saturday
                                                                                      CYP-BS00216
You can also read