LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis

Page created by Rhonda Allen
 
CONTINUE READING
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
LONG-TERM DEVELOPMENT PLAN—2016
    for Manitoba Hydro's Electrical Transmission System
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
Manitoba
Manitoba   Hydro’s
         Hydro’s    Existing
                  Existing   Generating
                           Generating   Stations
                                      Stations
  and
and   Transmission
    Transmission   System
                 System

    ii          LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
2           LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
Executive Summary
      Manitoba Hydro’s electrical transmission system, consists of a network of alternating current (ac)
      transmission lines and terminal stations plus high voltage direct current (HVDC) transmission lines and
      converter stations that collectively deliver the power from Manitoba Hydro’s generating stations to
      customers across the province and beyond provincial boundaries. This report describes the current
      long term development Plan for Manitoba Hydro’s electrical transmission system covering the period
      from 2016 to 2035.
      The Plan describes the proposed additions, enhancements, replacements, and refurbishments that
      are needed to ensure the transmission system continues to meet Manitoba Hydro’s mandate of
      serving the province with a reliable supply of electricity as well as meeting the regulated performance
      requirements of Manitoba Hydro and its interconnected utilities in Canada and the United States.
      A basic performance requirement is that the transmission system be able to continue to serve firm
      load during an outage of a system element such as a transmission line, transformer, circuit breaker,
      or other auxiliary device (also known as N-1 contingency planning). The transmission system must
      also be designed and operated such that an outage to one part of the network will not cascade
      or cause stress to other parts of the transmission system or interconnected utilities outside the
      province. Achieving these goals requires the timely implementation of additions, enhancements and
      replacements in order to avoid load shed, rotating blackouts or loss of export capacity.
      The bulk of Manitoba’s power is transmitted from remote generating stations in the north to
      customers in southern Manitoba over the Nelson River HVDC transmission system. The HVDC
      system is a critical component for meeting the electricity needs of the province. The two Nelson
      River HVDC transmission lines are located in the same corridor, and both HVDC southern
      converters are located at Dorsey which makes the current HVDC system vulnerable to a common
      outage. This plan includes overview of Bipole III project which increases the robustness of the
      HVDC system by providing an alternate transmission corridor and terminus.
      This Plan describes projects that span two main investment types and eight drivers of need for
      transmission capital investments. The two investment types are growth and sustainment, while the
      eight drivers are safety, load growth, reliability, transmission service, new generation, new customer
      connections, efficiency and aging infrastructure. The Plan also identifies which region of the province
      is being addressed by each capital investment. The map on the following page provides a visual for
      the more significant growth and sustainment projects to be implemented during the first ten years
      (fiscal years 2016/17 to 2025/26) of the current Capital Expenditure Forecast CEF16. A summary
      table follows, listing the approved and proposed capital investments covered by the Plan, grouped by
      region and investment type, with a mapping to the drivers that apply to each. A total of $6.15 billion of
      transmission-related project expenditures has been identified in the 20-year CEF16. The large majority
      of these expenditures are associated with growth, at $4.65 billion or 76%, while $1.50 billion or 24% are
      investments for sustainment.
      The long-term development plan is reviewed and adjusted annually to reflect revised load forecasts,
      updated system performance and asset condition assessments, and new requests for transmission
      service, bulk load connections and generation connections. Not all of the projects identified in this
      Plan will necessarily be built; while some are approved and either underway or ready for execution,
      others represent proposed investments that are in the early planning stage and hence are subject
      to change.
      The new station sites and transmission lines associated with the projects described in this Plan are
      shown for illustrative purposes only. Manitoba Hydro follows a Site Selection and Environmental
      Assessment Process, which includes public consultation on the preferred location of new stations
      and routing of new transmission lines, and obtaining the regulatory licenses necessary for
      construction of facilities.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                             iii
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
Transmission Business Unit - Heat Map for Major + Base Capital Under CEF16 (Fiscal years 2017-2026)

iv                         LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
Major Transmission System Projects and Drivers

                                                                                                                           Maintain or Improve Reliability

                                                                                                                                                             Provide Transmission Service

                                                                                                                                                                                                                                                                  Address Aging Infrastructure
                                                                                                                                                                                            Connect New Generation
                                                                                                 Serve Local Load Growth
                                                              Drivers of Need

                                                                                                                                                                                                                     Customer Connections

                                                                                                                                                                                                                                            Increase Efficiency
                                                                                Improve Safety

                                                                                                                                                                                                                                                                                                     ISD
                                         INTERCONNECTION PROJECTS
Manitoba-Minnesota Transmission Project                                                                                                                                                                                                                                                           2020 05
Manitoba-Saskatchewan Transmission Interface Project                                                                                                                                                                                                                                              2021 06
Keeyask Generation Outlet Transmission Facilities                                                                                                                                                                                                                                                 2021 08
                                                    INTER-REGIONAL
Sustainment
Bipole II Thyristor Valve Replacement                                                                                                                                                                                                                                                            2027 03(**)
Bipole I & II Major Refurbishment (*)                                                                                                                                                                                                                                                             2036 03
HVDC Transformer Sustainment Program                                                                                                                                                                                                                                                             2037 03(**)
Dorsey Synchronous Condenser Refurbishment (extended)                                                                                                                                                                                                                                            2031 03 (**)
Bipole I & II DC Disconnects                                                                                                                                                                                                                                                                      2029 03
HVDC Transformer Sustainment (extended)                                                                                                                                                                                                                                                          2030 03 (**)
Transmission Line Upgrades for Improved Clearance (NERC)                                                                                                                                                                                                                                         2023 03 (**)
Dorsey Synchronous Condenser Refurbishment                                                                                                                                                                                                                                                       2026 03(**)
Transmission Transformers Sustainment Capital Program                                                                                                                                                                                                                                            2032 09 (**)
Transmission Line Footing Sustainment Program                                                                                                                                                                                                                                                    2030 03 (**)
HVDC Smoothing Reactor Replacements                                                                                                                                                                                                                                                              2023 10 (**)
Station Battery Bank Replacement Program                                                                                                                                                                                                                                                          2022 03
Transmission Line Protection & Teleprotection Replacement                                                                                                                                                                                                                                        2018 05 (**)
Bipole I & II Space Dampers Project (Phase 2)                                                                                                                                                                                                                                                    2017 12 (**)
Transmission Line Wood Pole Sustainment Capital Program                                                                                                                                                                                                                                          2026 03 (**)
Mobile Radio System Modernization                                                                                                                                                                                                                                                                 2017 06
Bipole I & II Communications Upgrade                                                                                                                                                                                                                                                              2024 03
115 kV Protection Upgrades                                                                                                                                                                                                                                                                       2023 03 (**)
Telecommunications 48VDC Upgrades                                                                                                                                                                                                                                                                 2036 (**)
HVDC BP2 Valve Hall Wall Bushing Replace                                                                                                                                                                                                                                                         2024 10 (**)
PCB Bushing Elimination Program                                                                                                                                                                                                                                                                  2024 03 (**)
HVDC Gapped Arrester Replacement                                                                                                                                                                                                                                                                 2021 11 (**)
Transmission Breaker Sustainment Capital Program                                                                                                                                                                                                                                                 2033 03 (**)
HVDC Circuit Breaker Opp. Mechanical Replacement                                                                                                                                                                                                                                                 2019 03 (**)
13.2 kV Shunt Reactor Replacement Program                                                                                                                                                                                                                                                        2018 11 (**)
HVDC BP2 Refrigerant Condenser Replacement                                                                                                                                                                                                                                                       2025 11 (**)

 LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                                                                                                                                                                                                                        v
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
Maintain or Improve Reliability

                                                                                                                                                                Provide Transmission Service

                                                                                                                                                                                                                                                                     Address Aging Infrastructure
                                                                                                                                                                                               Connect New Generation
                                                                                                    Serve Local Load Growth
                                                                 Drivers of Need

                                                                                                                                                                                                                        Customer Connections

                                                                                                                                                                                                                                               Increase Efficiency
                                                                                   Improve Safety

                                                                                                                                                                                                                                                                                                        ISD
HVDC BP1 DCCT Transductor Replacement                                                                                                                                                                                                                                                               2028 10 (**)
HVDC System Transformer & Reactor Fire Protection                                                                                                                                                                                                                                                    2017 06
Bipole I & II DC Filter Protection                                                                                                                                                                                                                                                                   2025 03
Growth
Bipole III Reliability Project                                                                                                                                                                                                                                                                       2018 07
Southern AC System Breaker Replacements                                                                                                                                                                                                                                                             2017 06 (**)
Winnipeg Area Capacitor Bank Additions (Phase 1)                                                                                                                                                                                                                                                     2019 11
Winnipeg Area Capacitor Bank Additions (Phase 2)                                                                                                                                                                                                                                                     2026 10
                                                      REGIONAL
                                                   Northern Region
Sustainment
Diesel Generating Station Upgrades                                                                                                                                                                                                                                                                   2020 03
Mile 13 Station Salvage                                                                                                                                                                                                                                                                              2028 03
                                                   Western Region
Sustainment
Brandon Area Transmission Improvements                                                                                                                                                                                                                                                               2016 07
Growth
Southwestern Manitoba Capacity Enhancement                                                                                                                                                                                                                                                           2030 10
Winnipeg to Brandon System Improvements                                                                                                                                                                                                                                                              2025 04
Brandon-Victoria 115-66 kV Capacity Addition                                                                                                                                                                                                                                                         2022 10
Souris East Transformer Capacity Enhancement                                                                                                                                                                                                                                                         2019 10
Dauphin/Vermillion 230 kV Station Capacity Increase                                                                                                                                                                                                                                                  2022 10
                                                   Interlake Region
Growth
Ashern Bank Addition                                                                                                                                                                                                                                                                                 2023 09
Rosser Station 115-66 kV Transformer Addition                                                                                                                                                                                                                                                        2019 10
                                                    Eastern Region
Sustainment
Pointe du Bois Transmission Refurbishment/Redevelopment (Phase 1)                                                                                                                                                                                                                                    2016 12
Growth
Steinbach Area 230-66 kV Capacity Enhancement                                                                                                                                                                                                                                                       2020 10 (**)
Lake Winnipeg East System Improvements                                                                                                                                                                                                                                                               2017 09
Letellier - St. Vital 230 kV Transmission Line                                                                                                                                                                                                                                                       2020 07
Pointe du Bois Transmission Refurbishment/Redevelopment (Phase 2)                                                                                                                                                                                                                                    2024 04

 vi                              LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
Maintain or Improve Reliability

                                                                                                                                                                 Provide Transmission Service

                                                                                                                                                                                                                                                                      Address Aging Infrastructure
                                                                                                                                                                                                Connect New Generation
                                                                                                     Serve Local Load Growth
                                                                  Drivers of Need

                                                                                                                                                                                                                         Customer Connections

                                                                                                                                                                                                                                                Increase Efficiency
                                                                                    Improve Safety

                                                                                                                                                                                                                                                                                                         ISD
Whiteshell Area 115-33/66 kV Station                                                                                                                                                                                                                                                                  2028 10
Stanley Station 230-66 kV Transformer Additions                                                                                                                                                                                                                                                       2018 10
Portage Area 230-66 kV Capacity Upgrade                                                                                                                                                                                                                                                               2029 10
                                                  Winnipeg Region
Growth
Rockwood East 230-115 kV Station & Line Sectionalization                                                                                                                                                                                                                                             2016 02 (**)
SW Winnipeg 115 kV Transmission System Improvements                                                                                                                                                                                                                                                  2021 10 (**)
La Verendrye to St. Vital 230 kV Transmission Line and Breakers                                                                                                                                                                                                                                      2020 10 (**)
Northeast Winnipeg Capacity Enhancement                                                                                                                                                                                                                                                               2031 10
La Verendrye Station 230-66 kV Bank Addition                                                                                                                                                                                                                                                          2023 10

     (*) Projects indicated in red are currently in the Early Planning Stage and subject to change.
     (**) Multiple years
     Table does not include projects under $10 million.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                                                                                                                                                                                                                            vii
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
Contents
       Manitoba Hydro’s Existing Generating Stations and Transmission System.................................... ii
       Executive Summary......................................................................................................................................... iii
       Major Transmission System Projects and Drivers.................................................................................. v
       1. Introduction.................................................................................................................................................. 1
       2. Drivers and Process for Transmission Capital Investments............................................................. 3
           2.1 Drivers.................................................................................................................................................................................................3
                       2.1.1 Improve Safety............................................................................................................................................................3
                       2.1.2 Serve Local Load Growth...................................................................................................................................3
                       2.1.3 Maintain and Improve Reliability....................................................................................................................4
                       2.1.4 Provide Transmission Service...........................................................................................................................4
                       2.1.5 Connect New Generation..................................................................................................................................4
                       2.1.6 Customer Connections........................................................................................................................................5
                       2.1.7 Increase Efficiency....................................................................................................................................................5
                       2.1.8 Address Aging Infrastructure............................................................................................................................5
           2.2 Planning Process..........................................................................................................................................................................6
       3. Transmission System Projects................................................................................................................. 9
           3.1 Interconnections Projects.....................................................................................................................................................9
                       3.1.1 Manitoba - Minnesota Transmission Project (MMTP)....................................................................9
                       3.1.2 Manitoba-Saskatchewan Transmission Interface Project (MH-SPC)..................................11
                       3.1.3 Keeyask Generation Outlet Transmission Facilities.........................................................................13
           3.2 Inter-Regional Projects..........................................................................................................................................................15
                       3.2.1 Growth..............................................................................................................................................................................17
                       3.2.1.1 Bipole III Reliability Project............................................................................................................................17
                       3.2.1.2 Winnipeg Area Capacitor Bank Additions..........................................................................................19
                       3.2.2 Sustainment..................................................................................................................................................................19
                       3.2.2.1 Transmission Line Upgrades for Improved Clearance................................................................19
                       3.2.2.2 Bipole I & II Spacer Damper Replacement..........................................................................................20
                       3.2.2.3 Bipole II Thyristor Valve Replacement...................................................................................................20
                       3.2.2.4 HVDC Transformer Replacement Program.......................................................................................20
                       3.2.2.5 Dorsey Synchronous Condenser Refurbishment.........................................................................21
                       3.2.2.6 Circuit Breaker Replacements.....................................................................................................................21

viii                                                 LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
3.3 Regional Issues/Solutions......................................................................................................................................................22
                    3.3.1 Regional Load Growth...........................................................................................................................................22
                    Summer Load Growth Projections............................................................................................................................24
                    Winter Load Growth Projections...............................................................................................................................25
         3.3.2 Northern Region.....................................................................................................................................................................26
                    3.3.2.1 Diesel Plant Upgrades.......................................................................................................................................27
                    3.3.2.2 Mile 13 Station Salvage...................................................................................................................................27
         3.3.3 Western Region.......................................................................................................................................................................28
                    3.3.3.2 Souris East Capacity Enhancement........................................................................................................31
                    3.3.3.3 Brandon-Victoria 115 kV Breaker Replacement..........................................................................31
                    3.3.3.4 Reston Station New 230 kV Ring Breaker........................................................................................31
                    3.3.3.5 Virden West Capacitor Bank Installation.............................................................................................31
                    3.3.3.6 Dauphin/Vermilion 230 kV Capacity Increase................................................................................31
                    3.3.3.7 Brandon-Victoria Station Capacity Increase....................................................................................32
                    3.3.3.8 Southwestern Manitoba Capacity Enhancement.........................................................................32
         3.3.4 Interlake Region.......................................................................................................................................................................33
                    3.3.4.1 Ashern Bank Addition........................................................................................................................................34
                    3.3.4.2 Rosser Station 115–66 kV Transformer Addition .....................................................................34
         3.3.5 Eastern Region.........................................................................................................................................................................35
                    3.3.5.1 Steinbach Area Capacity Enhancement...............................................................................................36
                    3.3.5.2 Stanley Station 230-66 kV Station Expansion..............................................................................37
                    3.3.5.3 Pointe du Bois Transmission Refurbishment/Redevelopment.............................................38
                    3.3.5.4 Lake Winnipeg East System Improvements.....................................................................................39
                    3.3.5.6 Letellier - St. Vital 230 kV Transmission Line..................................................................................41
                    3.3.5.7 Whiteshell Station Bank 1 Replacement.............................................................................................42
                    3.3.5.8 Whiteshell Area 115–33/66 kV Station............................................................................................42
         3.3.6 Winnipeg Region.....................................................................................................................................................................43
                    3.3.6.1 Improvements of 115 kV Southwest Winnipeg Transmission System.........................45
                    3.3.6.2 La Verendrye to St. Vital 230 kV Transmission Line...................................................................47
                    3.3.6.3 La Verendrye 3rd Bank Addition...............................................................................................................48

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                                                                                                                        ix
LONG-TERM DEVELOPMENT PLAN-2016 - for Manitoba Hydro's Electrical Transmission System - OATi Oasis
4. Future Capital Requirements for Transmission.................................................................................. 49
        4.1 Future Transmission Interconnections.........................................................................................................................49
        4.2 Access to Electricity Markets - Transmission Service.......................................................................................49
        4.3 Future Generation Interconnection..............................................................................................................................50
        4.4 Wind Generation Interconnection.................................................................................................................................51
        4.5 Northern Exploratory Study...............................................................................................................................................53
        4.6 Major Customer Interconnection and Load Addition.......................................................................................53
        4.7 Addressing Aging Infrastructure.......................................................................................................................................53
        4.8 Northern Damping (Low Frequency Oscillations)..............................................................................................54
        4.9 Future Transmission Corridors..........................................................................................................................................55
        4.10 Resource Adequacy................................................................................................................................................................56
    Appendix 1......................................................................................................................................................... 57
    Appendix 2 — Glossary................................................................................................................................. 63

x                                            LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
1. Introduction
      The Long Term Development Plan - for Manitoba Hydro’s Electrical Transmission System - 2016
      addresses future transmission system developments.
      This 2016 plan reflects planned projects that have been approved in the 2016 Manitoba Hydro
      Capital Expenditure Forecast (CEF16).
      Manitoba Hydro is a provincial Crown Corporation providing electricity to 567,634 customers
      throughout Manitoba and natural gas service to 276,858 customers in various communities
      throughout southern Manitoba (Manitoba Hydro-Electric Board 65th Annual Report). Manitoba
      Hydro also has formal electricity export sale agreements with a number of electric utilities and
      marketers in the Midwestern U.S., Ontario, and Saskatchewan.
      Nearly all electricity generated is from clean renewable water power. On average, about 33.1
      billion kilowatt-hours of electricity are generated annually. Seventy-five percent is produced by five
      hydroelectric generating stations on the Nelson River; the remainder is generated at ten hydroelectric
      stations on the Winnipeg, Saskatchewan, Burntwood and Laurie rivers; two thermal stations; two
      independently owned wind farms and four diesel sites. The electricity is transmitted over nearly
      100,000 kilometres of transmission and distribution lines.
      Manitoba Hydro has 5,690 MW of generation connected to its network. In addition, 116 MW of wind
      generation at St. Leon and 138 MW of wind generation at St. Joseph are available to Manitoba Hydro
      under power purchase agreements. Roughly 3.7% of Manitoba’s annual energy generation is supplied
      by wind turbines.
      In 2015/16, the corporation supplied a provincial gross total peak of 4,479 MW (weather adjusted
      4,634 MW). The provincial peak load is growing at an average rate of about 1.4% per year (energy
      1.4% per year) over the next 10 years.
      The length of transmission lines connected to Manitoba Hydro’s transmission network include the
      following:
           •   1840 km of 500 kV transmission (HVDC)
           •   210 km of 500 kV transmission (AC)
           •   5000 km of 230 kV transmission (AC)
           •   1400 km of 138 kV transmission (AC)
           •   2900 km of 115 kV transmission (AC)
      Manitoba Hydro plans additions and enhancements to its transmission and distribution systems to
      ensure that the systems will continue to operate acceptably in the future, as the requirements change.
      Manitoba Hydro expects its transmission system to meet performance requirements set out in the
      following:
           •   North American Electric Reliability Corporation (NERC) Reliability Standards
           •   Manitoba Hydro’s own Transmission System Interconnection Requirements (TSIR), which
               defines standards for system adequacy, reliability, and security.

      These standards and criteria are used to develop system addition and enhancement plans. Numerous
      transmission system developments comprise this plan.

      Each of the developments discussed has one or more drivers of need, which are described in detail in
      Chapter 2. This chapter also includes the planning process followed to develop and prioritize projects.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                         1
Transmission regional issues and solutions are introduced in Chapter 3. Project developments are
    also highlighted in this chapter with brief descriptions, expected in-service dates, and estimated cost
    estimates.

    Currently, there are no independent generator developments in the queue. For the sake of
    completeness, the major proposed utility transmission and generation developments, although not
    finalized, are also briefly reviewed in Chapter 4. Section 4.7 of this plan provides insight into a long-
    term (10 years) strategy to replace aging transformers, circuit breakers and wood pole transmission
    structures.

    Manitoba Hydro’s existing transmission facilities are outlined in Appendix 1. Abbreviations and some
    utility terms are listed in Appendix 2.

    This document is the current Long Term Development Plan for Manitoba Hydro’s electrical
    transmission system. Subsequent development plans will be issued annually to reflect changing
    circumstances such as changes in customer demand, the need for reliability enhancements, request
    for transmission service, or the addition of new generator connections, addressing aging infrastructure
    or regulatory requirements.

    The Long Term Development Plan will be posted on Manitoba Hydro Open Access Same Time
    Information System (OASIS) website, which can be found on the Manitoba Hydro web page (http://
    www.hydro.mb.ca), then by clicking on Transmission Tariffs for Energy Supplies and Power Producers,
    under Your Business tab, and then selecting either the Transmission Tariff Link or Interconnection
    Tariff Link to get to the Manitoba Hydro OASIS page (http://www.oasis.oati.com/MHEB/index.html).
    The Long Term Transmission Plan is located under the System Information tab.

      From Generating Stations to
      Customers
      The major transmission system is a network             Voltage Ranges:
      of high voltage transmission lines used to
      move electrical power over long distances,                  •   Generating Stations: 4 kV to 15 kV
      from generating stations to terminal stations.
                                                                  •   HVDC ± 463.5 kV, ± 500 kV
      At terminal stations, electrical power is
                                                                  •   Northern Transmission: 138 kV,
      transformed down to mid-range voltages and
                                                                      230 kV
      sent over a network of distribution system
      lines to groups of distribution stations.                   •   Southern Transmission: 115 kV,
                                                                      230 kV, 500 kV
      At each distribution station power is
      transformed to lower voltages and distributed               •   Distribution: 4 kV to 66 kV
      over the distribution system feeder lines
      (either overhead pole lines or underground             Note: 1 kV is 1,000 volts
      cables) to distribution transformers. Each
      distribution transformer transforms the
      voltage to lower user voltages, to directly
      feed a customer or a cluster of customers.

2                          LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
2. Drivers and Process for Transmission Capital
Investments
      Manitoba Hydro’s transmission planning process identifies plans to connect new generating resources
      and new customers and assesses the adequacy of the existing and planned transmission network to
      provide a reliable and economic supply of electricity to Manitoba customers and external customers.
      Conceptual plans are developed, based on generation and load forecasts over a 10-20 year period, to
      ensure that the Manitoba load and contractual firm exports can be served.
      Manitoba Hydro plans transmission facilities in compliance with all applicable local, regional and
      international reliability standards and requirements. Planning studies and assessments follow
      established methodologies and must meet standards and criteria established by Manitoba Hydro and
      other regulating entities such as the Midwest Reliability Organization (MRO) and NERC.

2.1 Drivers
      There are eight drivers of need in determining additions, enhancements, repairs and replacements
      required to the transmission and HVDC systems.
           1.   Improve safety
           2.   Serve local load growth
           3.   Maintain or improve reliability
           4.   Provide transmission service
           5.   Connect new generation
           6.   Customer connections
           7.   Increase efficiency
           8.   Address aging infrastructure
      Each of the projects highlighted in this plan reflects one or more of these drivers, but not necessarily
      all eight of the drivers.

      2.1.1 Improve Safety
      Safety is Manitoba Hydro’s first priority and most important goal. One of the important components of
      Manitoba Hydro’s vision is to be recognized as a leading utility in North America with respect to safety.
      Manitoba Hydro is committed to protecting the public and its employees from personal injury by
      maintaining and operating the transmission system in a safe manner. This commitment involves
      modifying existing circuit protection schemes, implementing new protection schemes, and periodically
      replacing or upgrading aging infrastructure to meet changing conditions. Circuit protection schemes
      are installed to minimize the probability of equipment failure and personal injury. Transmission lines are
      upgraded to ensure adequate clearance between the energized conductors and ground level.

      2.1.2 Serve Local Load Growth
      Forecasted provincial load growth is used to determine the need for transmission system additions
      and enhancements. Expected provincial load growth is detailed in a corporate “2016 Electric Load
      Forecast”. Developed annually, the Electric Load Forecast predicts provincial electric load growth
      for the next 20 years in various load sectors, including residential, general service, area and roadway
      lighting, construction power, and station service. Electric load forecast predictions are based on
      historical billing data and the current economic and energy price outlook and planned corporate
      demand side management targets.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                               3
2.1.3 Maintain and Improve Reliability
    To fulfill its vision to be recognized as a leading utility in North America with respect to reliability,
    Manitoba Hydro endeavors to continue to serve firm load for an outage of a transmission system
    element such as transmission line, transformer, circuit breaker, or any other auxiliary device. If
    a system element fails to function to its design specification for any reason, the network can be
    re-configured so that affected area can be served from an alternate supply in most of cases. The
    transmission system is designed such that outages in one part of the network should not cascade or
    spread to neighboring areas of the transmission system causing stress on other system elements.
    Achieving these goals often requires transmission system additions, replacements and enhancements.
    If these improvements are not completed in a timely manner, service to firm load customers would be
    greatly compromised.
    Manitoba Hydro regularly conducts system simulation studies to assess the performance of the
    existing and future projected systems against reliability standards and to determine what transmission
    system improvements are required to maintain system reliability.
    Manitoba Hydro expects its transmission system to meet the provincially legislated performance
    requirements of the North American Electric Reliability Corporation (NERC) standards, and its own
    Transmission System Interconnection Requirements.

    2.1.4 Provide Transmission Service
    Transmission system improvements may be required to provide or maintain transmission service
    under Manitoba Hydro’s Open Access Transmission Tariff (OATT). In addition Manitoba Hydro receives
    numerous requests for seasonal firm service and short term non-firm service, all of which are posted
    on the Manitoba Hydro website. (see section 4.2)

    Export Sales: Manitoba Hydro currently has long term firm export sales agreements with utilities in
    Minnesota, Wisconsin and Saskatchewan.

    Import Purchases: Manitoba Hydro plans its generation resources based on hydraulic generation
    availability during the lowest river flows on record. The hydraulic generation is augmented by Manitoba
    Hydro thermal generation and imports.

    Manitoba Hydro secures imported power during the winter season. The Corporation’s predominantly
    hydraulic generation system usually produces surplus energy during the summer season, when river
    flows are generally normal or above normal. Peak Manitoba loads occur in winter.

    Import purchase agreements are also used to provide energy during periods of sustained drought.

    2.1.5 Connect New Generation
    Generation within the province may be connected to the Manitoba Hydro transmission or
    distribution system, in accordance with the terms and conditions of the Manitoba Hydro’s Open
    Access Interconnection Tariff (OAIT), posted on the Manitoba Hydro website (see section 4.2).

    Manitoba Hydro conducts system studies to determine what enhancements or additions to the
    network will be required to connect new generation. Major generation can be connected to the
    transmission system with minor transmission additions only if the generation is close to major load
    centres or if the generation results in reversed or reduced flow on the existing transmission network.

4                          LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
2.1.6 Customer Connections
      New major customer loads requiring up to 5000 kW of power can generally be supplied by the
      distribution system, whereas new major loads requiring more than 5000 kW of power will likely
      need to be supplied by the high voltage distribution system or network transmission system.
      Technical requirements for connecting generators and loads to the high voltage distribution
      or network transmission systems are defined in Manitoba Hydro’s “Transmission System
      Interconnection Requirements”, also available on Manitoba Hydro’s website which can be found on
      the Manitoba Hydro web page (http://www.hydro.mb.ca), then by clicking on Transmission Tariffs
      for Energy Supplies and Power Producers, under Your Business tab, then selecting either the
      Transmission Tariff link or Interconnection Tariff link to get to the Manitoba Hydro OASIS page
      (http://oasis.midwestiso.org/oasis/mheb).

      2.1.7 Increase Efficiency
      The responsibility of the Transmission is to provide a reliable and safe transmission system for the
      delivery of electricity to domestic and out-of-province customers at the lowest possible cost. In order
      to achieve this objective, Manitoba Hydro conducts system simulation studies to determine feasible
      transmission system improvements for efficient energy transmission and reduced power losses. Bipole
      III will provide increased efficiency by means of reducing HVDC transmission losses in Manitoba’s three
      HVDC bipoles. Transmission voltage upgrades have also been implemented to reduce losses.

      2.1.8 Address Aging Infrastructure
      Replacement or repair of aging infrastructure is often required to attain a reliable transmission system.
      Refurbishment of aging transmission lines, the reconstruction of high voltage transmission circuits and
      the replacement of circuit breakers that have reached their end-of-life are examples. Re-construction
      of Scotland Station, Pointe du Bois line upgrades, and replacement of St. James station, are further
      examples. Manitoba Hydro’s Transmission business unit has also started a condition assessment
      program for its major assets and, based on initial results, has established sustainment programs for its
      transformer, circuit breaker and transmission line wood pole structure assets as part of its capital plan
      to fund proactive replacements and refurbishments.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                          5
2.2 Planning Process
    Planning of the Manitoba Hydro transmission system is performed by the System Planning
    Department. The primary objective of the planning process is to ensure the transmission system
    can economically meet the current and future energy needs of the province in compliance with all
    applicable local, regional and international reliability standards and requirements. The North American
    Electric Reliability Corporation (NERC)1 Planning Standards require that a transmission system
    performs in a reliable manner not only under normal system operating conditions but also following
    a range of system disturbances using year 1 and year 5 models for the present and near-term
    assessment and year 10 model for long-term assessment. As a member of the Midwest Reliability
    Organization (MRO)2 , Manitoba Hydro complies with the NERC Transmission Planning Standards by
    completing an annual Transmission System Performance Assessment and submitting to the MRO a
    study report and documentation of any planned transmission system upgrades. Manitoba Hydro also
    coordinates planning activities with other neigbouring utilities and jurisdictions.
    Planning begins with concepts that are developed in response to the annual long term provincial
    load forecast, the annual Transmission System Performance Assessment, requests for generation
    interconnections, transmission usage requests, and bulk load connection requests. These concepts
    are studied and refined into alternatives in consultation with various stakeholders, and the
    alternative that represents the best overall value to the customer is chosen for implementation as a
    capital investment project.
    Public consultation and regulatory approvals are required to implement the selected plan if it involves
    development of a new station site, a new transmission corridor, and/or a new international or inter-
    provincial connection. Manitoba Hydro follows a Site Selection and Environmental Assessment process
    which includes public consultations to select locations for stations and routes from transmission lines
    and obtain the regulatory licenses necessary for construction of new facilities. Manitoba Hydro also
    conducts Environmental Impact Assessment and develops a comprehensive Environment Protection
    Plan for each facility proposed.
    The newly identified capital investments are added to the list of active and future capital investments, and
    this portfolio of projects is prioritized over the ten-year forecast window. The goal of the prioritization
    process is to optimize the scheduling of capital investments to achieve the best net value possible with
    the resources available. The factors that are considered during prioritization are as follows:
          a)    a project’s matrix score under the Capital Budget Ranking Tool,
          b)    a project’s risk profile determined via the System Reliability Risk Model (i.e., the ∆EUE),
          c)    a project’s readiness to execute,
          d)    the options available to mitigate the risks associated with deferral of an investment.
    Each of these is explained in the following paragraphs:
        a) The Capital Budget Ranking Tool was developed in 2006 as a means of ranking the relative
             importance of Transmission’s capital investments using common criteria that are linked to
             business unit goals. The tool provides a matrix framework for scoring projects based on the
             degree to which they contribute to the goals of safety, service and reliability, transfer capacity,
             a positive financial impact, and/or a positive environmental impact. The more goals to which

    1 The North American Electric Reliability Corporation is a not-for-profit international regulatory authority whose mission is to assure the
    reliability of the bulk power system in North America.

    2 Midwest Reliability Organization (MRO) is a non-profit organization dedicated to ensuring the reliability and security of the bulk power
    system in the north central region of North America, including parts of both the United States and Canada. MRO is one of eight regional
    entities in North America operating under authority from regulators in the United States through a delegation agreement with the North
    American Electric Reliability Corporation and in Canada through arrangements with provincial regulators. The primary purpose of MRO is to
    ensure compliance with reliability standards and perform regional assessments of the grid’s ability to meet the demands for electricity.

6                                  LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
a project may be linked, and the greater degree to which a project is likely to contribute to
               a goal, the higher the score it will achieve. Projects with high matrix scores should receive
               funding allocations ahead of those with lower scores.
           b) The System Reliability Risk Model is a sophisticated tool developed in 2015 by System
              Planning with the aim of quantifying the risk associated with a capital project or group of
              projects in terms of potential impacts to the reliability of the transmission system. The
              tool models the operation of the transmission system with and without the additional or
              replacement assets for a given project or group of projects, and compares the expected
              unserved energy (EUE) for various potential failures on the related system network. The
              model factors in the system topology, load data, equipment reliability data, and network-
              specific conditions (e.g., tapped lines, special protection schemes, common-mode outages,
              etc), and averages the results over a five-year window. The difference between the EUE
              without the new assets and the EUE with the new assets is referred to as the delta EUE (or
              ∆EUE). The ∆EUE represents the risk to the reliable operation of the system that would be
              mitigated with the implementation of the project. Projects with high ∆EUEs should receive
              funding allocations ahead of those with lower ∆EUEs.
           c) A project’s readiness to execute is based on such elements as the availability of labour
              resources, the status of licensing and property requirements, and the status of material
              delivery and construction contracts. A project may have a high matrix score and/or a large
              ∆EUE but yet may still have a later in-service date under CEF16 than it did under CEF15,
              due to one or more of these elements causing a delay to the schedule. In such cases the
              change to the project’s in-service date is recorded as a delay rather than a deferral, since it
              is an outcome of project logistics rather than a decision by management. Knowledge about
              these delays will play a part in determining whether a project’s funding needs to be protected
              in the near-term portfolio plans or may be released to some other project.
           d) The options available to mitigate the risks associated with a project deferral has to do with
              the number of ways and ease with which operators can make real-time adjustments to the
              system in order to avoid dropping load or causing voltage issues. In some cases the options
              are very limited, are complex to implement, or would introduce problems elsewhere on the
              system, such that they would be the option of last resort. A project that addresses a problem
              area that has little to no operating flexibility should receive funding ahead of those that may
              be mitigated more easily.
      Once all approvals and corporate funding are in place, detailed engineering, material procurement,
      construction and commissioning will take place. The project implementation phase for new facilities
      can take several months to several years, depending on the scope and complexity of the project.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                            7
Transmission Planning Process
             Provincial     Transmission     Asset
               Load     System Performance Condition
             Forecast       Assessment    Assessments

    Transmission       Bulk Load       Generation
       Service        Connection       Connection
      Request           Request         Request

                         IDENTIFY
                    REQUIREMENTS FOR
                    CAPITAL INVESTMENT

                          PROJECT
                        DEFINITION
                        & APPROVAL

                         PORTFOLIO
                        PORTFOLIO
                       PRIORITISATION
                       OPTIMISATION
                   MITIGATION IF DEFERRED

                      20 YEAR
           CAPITAL EXPENDITURE FORECAST

                    Transmission Planning Process

8     LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
3. Transmission System Projects
      The following projects reported in the 2015 plan have been completed:
           •   Neepawa 230/66 kV Station.
           •   Rockwood East 230/115 kV Station
           •   Keeyask Construction Power
      The following transmission system developments presented in this chapter, approved in Manitoba
      Hydro’s Capital Expenditure Forecast, are required to keep the transmission system operating reliably.
      While these represent the bulk of projects, numerous smaller enhancement projects are also included
      in the Capital Plan.

      The project diagrams included with the project descriptions in this chapter are conceptual diagrams. As
      such, these diagrams do not illustrate transmission facility siting or routing. Manitoba Hydro follows a
      Site Selection and Environmental Assessment process to select locations for new stations and routes
      for new transmission lines as discussed in Chapter 4.

3.1 Interconnections Projects
      3.1.1 Manitoba - Minnesota Transmission Project (MMTP)
      Studies have been completed with the Midcontinent Independent System Operator (MISO)
      to determine the necessary transmission facilities needed to increase the firm Canada to U.S.
      transmission export and import capability. Facilities study concluded that new facilities will increase the
      MH-US export capability by 883 MW and the MH-US import capability by 698 MW.

      MMTP project has the following components:
           1. Development of a 500 kV AC Transmission Tie Line from Dorsey-U.S. border (approximately
              215 km in length). The 500 kV AC transmission link to connect Dorsey Station to the U.S.
              border will be located within the south loop corridor that currently is located to the south of
              Winnipeg.
           2. Addition of a second 500/230 kV transformer bank at Riel Station.
           3. Addition of a phase shifting transformer at Glenboro 230 kV Station on Glenboro – Rugby
              (U.S.) 230 kV Line (G82R). This device is being added to mitigate loop flow issues on the
              Manitoba to U.S. interface.
      MMTP connects to the Great Northern Transmission line (GNTL) project at the U.S. border. GNTL is
      being constructed by Minnesota Power and consists of a 500 kV line between the border and Iron
      Range (A new substation northwest of Duluth, Minnesota), a 500/230 kV transformer bank at Iron
      Range as well as a series compensation station near Warroad, Minnesota. The final preferred route of
      MMTP is shown in the figure below [https://www.hydro.mb.ca/projects/mb_mn_transmission/]. This
      project is being constructed under the OATT.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                             9
The project is planned to be in-service by May 2020 and is expected to cost approximately $450
       The project is planned to be in-service by May 2020 and the Manitoba portion of the project is
      million.
        expected to cost approximately $450 million.

     LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                  21

10                               LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
500kV
                Dorsey
                                                                         Riel                         345kV
                                                                                                      230kV
                                                                                                 NEW FACILITIES
                   G82R
                                                                                    MANITOBA

                                                                                     MINNESOTA
                Glenboro Phase Shifter 300             M602F              60%
                MVA +/- 80 degrees

                                                                         New Tie
                                                                                               Transfer Level:
                                                                         570 kms               883 MW South
                                                                          D604I                698 MW North

                                              Forbes                            Ironrange
                                                               1200MVA

                                             Chisago
                                                                                            Arrowhead

                                                                                                  Stone Lake
                                                               King

                                               Eau Claire                Arpin                              Gardiner Park

      3.1.2 Manitoba-Saskatchewan Transmission Interface Project (MH-SPC)
      Facility Studies are currently being finalized which will determine the necessary transmission facilities
      needed to facilitate a 100 MW increase in Power exports from Manitoba to Saskatchewan.
      MH-SPC Interface project has the following components:
           1. Addition of a new 91 km, 230 kV transmission line between Birtle South 230 kV (Manitoba)
              and Tantallon 230 kV (Saskatchewan) stations. MH portion of the new line is approximately
              61 km (67%) at an estimated cost of $47.3 million.
           2. Birtle South 230 kV Station (Manitoba) modifications/additions, including facility additions
              associated with the termination of the 230 kV new transmission line and the replacement of
              the 230 kV line B69R current transformer (CT) at an estimated cost of $7.7 million.
           3. Upgrade of the MH section of the 230 kV line P52E to 100°C design rating including wave-
              trap and riser replacement at The Pas-Ralls Island 230 kV Station (Manitoba) at an estimated
              cost of $3.0 million.
      The total cost for the required Network Upgrades in Manitoba is estimated to be approximately
      $58.0 million dollars. It should be noted that this project also requires the conversion and
      utilization of existing Brandon Unit #5 as a synchronous condenser. The in service date of the
      project is June 2021.
      This project is being evaluated under the Manitoba Hydro Open Access Transmission Tariff. It
      becomes an official Manitoba Hydro Transmission project once a facility construction agreement
      has been signed under the tariff, which is expected to happen in 2017.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                                         11
Manitoba-Saskatchewan Interconnection Lines

12   LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
3.1.3 Keeyask Generation Outlet Transmission Facilities
      The new 695 MW Keeyask Generating Station (net 630 MW) consists of 7 units. The new outlet
      transmission facilities (named Keeyask Transmission Project) are needed to integrate the Keeyask
      generating station to the Manitoba Hydro grid at Radisson Converter station.
      A new Keeyask Switching Station will be established to terminate seven new 138 kV lines including
      four unit lines (approximately 3 km each) to receive the power from Keeyask Generating Station, and
      three 138 kV transmission lines (approximately 38 km each) to convey the power to Manitoba Hydro’s
      existing Radisson Converter Station.
      A construction power station has been completed and fed primarily from a 138 kV transmission
      line with an approximate length of 22 km tapped from existing line KN36. One of the Radisson-
      Keeyask lines will be constructed earlier than the other two, in order to serve as a back-up source of
      construction power. Station upgrades at the Radisson station will also be required including a new bay
      to terminate new 138 kV lines and upgrades of 31 breakers. In addition to connecting new generation
      to the system, the new facilities will improve the reliability of the overall transmission system.
      Keeyask transmission is being constructed pursuant to the terms of the Open Access Interconnection
      Tariff (OAIT), and construction has started after the Keeyask Hydropower Limited Partnership signed
      an Interconnection and Operating Agreement (IOA) in May 2015. All of the transmission facilities will
      be completed by August 2021 with an estimated cost of $247 million.

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                       13
Simplified single line diagram of Keeyask Generation Outlet Transmission

                                                                                                    KEEWATI-
                                                                                                     NOHK
                                                                                                     230 kV

                LEGEND
     PROPOSED
     EXISTING

            Simplified conceptual diagram of Keeyask Generation Connection to Northern Collector System

14                              LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
3.2 Inter-Regional Projects

                                             Inter-Regional Projects

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System   15
Inter-Regional Projects
                                  Project Name                                          I.S.D.              Estimated
                                                                                                          Cost (millions)
 Sustainment Related Projects
 1    Bipole II Thyristor Valve Replacements                                      2027/03 (multi)              $236
 2    Bipole I & II Major Refurbishment                                           2036/03 (multi)              $198
 *    HVDC Transformer Sustainment Program                                        2037/03 (multi)              $189
 3    Dorsey Synchronous Condenser Refurbishment (extended)                    Annual/March (multi)             $99
 4    Bipole I & II DC Disconnects                                                2029/03 (multi)               $89
 *    HVDC Transformer Sustainment (extended)                                     2036/03 (multi)               $88
 *    Transmission Line Upgrades for Improved Clearance (NERC)                        2023/03                   $75
 5    Dorsey Synchronous Condenser Refurbishment                                  2026/03 (multi)               $74
 *    Transmission Transformers Sustainment Capital Program                       2032/09 (multi)               $64
 *    Transmission Line Footing Sustainment Program                               2030/03 (multi)               $50
 *    HVDC Smoothing Reactor Replacements                                         2023/10 (multi)               $47
 *    Station Battery Bank Replacement Program                                    2022/03 (multi)               $46
 *    Transmission Line Protection & Teleprotection Replacement                   2018/05 (multi)               $26
 6    Bipole I & II Spacer Dampers Project (Phase 2)                              2017/12 (multi)               $24
 *    Transmission Line Wood Pole Sustainment Capital Program                     2026/03 (multi)               $24
 *    Mobile Radio System Modernization                                               2017/06                   $24
 7    Bipole I & II Communications Upgrade                                            2024/03                   $21
 *    115 kV Protection Upgrades                                                  2023/03 (multi)               $20
 *    Telecommunications 48VDC Upgrades                                           2036/03 (multi)               $19
 8    HVDC BP2 Valve Hall Wall Bushing Replace                                    2024/10 (multi)               $19
 *    PCB Bushing Elimination Program                                             2024/03 (multi)               $19
 *    HVDC Gapped Arrester Replacement                                            2021/11 (multi)               $16
 *    Transmission Breaker Sustainment Capital Program                            2033/03 (multi)               $14
 *    HVDC Circuit Breaker Opp. Mechanical Replacement                            2019/03 (multi)               $14
 *    13.2 kV Shunt Reactor Replacement Program                                   2018/11 (multi)               $14
 9    HVDC BP2 Refrigerant Condenser Replacement                                  2025/11 (multi)               $13
 10   HVDC BP1 DCCT Transductor Replacement                                       2028/10 (multi)               $12
 *    HVDC System Transformer & Reactor Fire Protection                               2017/06                   $11
 11   Bipole I & II DC Filter Protection                                              2025/03                   $10
 Growth Related Projects
 12   Bipole III Reliability Project                                                  2018/07                 $5,042
       • Bipole III - Converter Stations                                          2018/07 (multi)                   $2,781
       • Bipole III - Transmission Line                                           2018/07 (multi)                   $1,958
       • Bipole III - Collector Lines                                             2018/07 (multi)                     $247
       •    Bipole III - Community Development Initiative (CDI)                   2018/07 (multi)                      $57
 *    Southern AC System Breaker Replacements                                     2017/06 (multi)               $14
 13   Winnipeg Area Capacitor Bank Additions (Phase 1)                                2019/11                   $11
 14   Winnipeg Area Capacitor Bank Additions (Phase 2)                                2026/10                   $10

      Items marked with * encompass multi-areas and are not indicated on map.
      NOTE: Table does not include projects under $10 million. Projects indicated in red are currently in the Early Planning
      Stage and subject to change.

16                               LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System
3.2.1 Growth
      3.2.1.1 Bipole III Reliability Project
                                                                           Enhancement of the reliability and
                                                                           security of the existing Nelson
                                                                           River HVDC transmission system
                                                                           has been under investigation for
                                                                           some time. The existing Bipole I &
                                                                           II transmission lines carry 70
                                                                           percent of Manitoba Hydro's
                                                                           generating capacity and are
                                                                           located on a common corridor,
                                                                           895 km in length.
                                                                           The southern converters of Bipole
                                                                           I and II are both terminated at
                                                                           the Dorsey Converter Station.
                                                                           The Bipole I & II corridor and the
                                                                           Dorsey Station are vulnerable to
                                                                           low probability, but severe events
                                                                           such as fire, wind bursts, tornadoes
                                                                           and ice storms; that could cause
                                                                           extended outages creating
                                                                           severe hardship to Manitoba
                                                                           Hydro customers and Manitoba.
                                                                           One such event occurred on
                                                                           September 6, 1996 when straight
                                                                           line winds associated with a micro-
                                                                           burst resulted in the collapse of
                                                                           19 HVDC transmission towers
                                                                           immediately north of the Dorsey
                                                                           Converter Station taking both the
                                                                           Bipole I and II out of service.
                                                                           Manitoba Hydro has evaluated
                                                                           various alternatives for enhancing
                                                                           the reliability of the HVDC
                                                                           transmission, namely the addition
                                                                           of gas turbines in southern
                                                                           Manitoba, the purchase of U.S.
                                                                           generation via a new 500 kV
                                                                           import line and a 2000 MW Bipole
                                                                           III HVDC system. Manitoba Hydro
                                                                           selected the Bipole III HVDC
                                                                           system as the preferred reliability
                                                                           enhancement project.
      The 2000 MW Bipole III HVDC system currently includes:
           •   a ±500 kV 2000 MW HVDC overhead transmission line (west of Lake Winnipegois and Lake
               Manitoba), about 1384 km long, from new Keewatinohk Converter Station to Riel Converter
               Station
           •   a 2000 MW converter station in the north (new Keewatinohk Converter Station);
           •   One 52 km 230 kV transmission line from Long Spruce to Keewatinohk and associated
               upgrades at Long Spruce Station

LONG-TERM DEVELOPMENT PLAN—2016 for Manitoba Hydro's Electrical Transmission System                         17
You can also read