WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT

Page created by Peter Cooper
 
CONTINUE READING
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR GROUP LIMITED

 WILUNA WEST IRON ORE
       PROJECT
    C4 IRON ORE DEPOSIT
PART V LICENCE APPLICATION
  SUPPORTING DOCUMENT

                    M53/1087

  Proponent:        GWR Group Limited
  Address:          97 Outram Street, WEST PERTH 6005
  Postal Address:   PO Box 517, WEST PERTH 6872
  Contact:          Mick Wilson
                    Exploration Manager, GWR
                    Phone: (08) 9322 6666
                    E-mail: mickw@gwrgroup.com.au

                     March 2021
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited                                                                                    Part V Licence Supporting Document

                                                TABLE OF CONTENTS
                                                                                                                                  Page No
1.0        INTRODUCTION ..................................................................................................................... 4
     1.1          BACKGROUND ...............................................................................................................4
     1.2          OBJECTIVE .....................................................................................................................4
     1.3          LOCATION.......................................................................................................................4
     1.4          OWNERSHIP & LAND TENURE.....................................................................................4
2      ATTACHMENT 1A – PROOF OF OCCUPIER STATUS ............................................................ 7
3      ATTACHMENT 1B – ASIC COMPANY EXTRACT .................................................................... 9
4      ATTACHMENT 2 – MAP OF PRESCRIBED PREMISES ......................................................... 12
5      ATTACHMENT 3B – PROPOSED ACTIVITIES ....................................................................... 13
     5.1          OVERVIEW ................................................................................................................... 13
     5.2          PRESCRIBED PREMISES ........................................................................................... 16
     5.3          KEY INFRASTRUCTURE AND EQUIPMENT ............................................................. 16
     5.4          CRUSHING AND SCREENING PLANT ....................................................................... 16
     5.5          DIESEL & HYDROCARBON STORAGE ..................................................................... 18
6      ATTACHMENT 5 - OTHER APPROVALS AND CONSULTATION ......................................... 20
     6.1          OTHER STATUTORY APPROVALS ........................................................................... 20
     6.2          CONSULTATION .......................................................................................................... 20
7      ATTACHMENT 6A – EMISSIONS, DISCHARGES AND WASTE ........................................... 29
     7.1          POTENTIAL EMISSIONS ............................................................................................. 29
     7.2          RISK ASSESSMENT AND MANAGEMENT SUMMARY ............................................ 29
8      ATTACHMENT 7 – SITING AND EXISTING ENVIRONMENT ................................................. 33
     8.1          RECEPTORS ................................................................................................................ 33
     8.2          SPECIFIED ECOSYSTEMS ......................................................................................... 33
     8.3          CLIMATE ...................................................................................................................... 34
     8.4          REGIONAL SETTING ................................................................................................... 34
        8.4.1     IBRA Region.................................................................................................................. 34
        8.4.2     Soil-Landscape Zone .................................................................................................... 35
        8.4.3     Land Systems ................................................................................................................ 35
     8.5          GEOLOGY .................................................................................................................... 35
     8.6          SOILS ............................................................................................................................ 36
     8.7          SURFACE WATER ....................................................................................................... 36
     8.8          GROUNDWATER ......................................................................................................... 39
        8.8.1     Regional Hydrogeology ................................................................................................. 39
        8.8.2     Local hydrogeology ....................................................................................................... 40
        8.8.3     Groundwater Levels and Flow ...................................................................................... 40
        8.8.4     Mine dewatering and water requirements ..................................................................... 41
        8.8.5     Groundwater Quality ..................................................................................................... 41
     8.9          BIODIVERSITY ............................................................................................................. 43
        8.9.1     Communities ................................................................................................................. 43
        8.9.2     Vegetation ..................................................................................................................... 45
        8.9.3     Flora .............................................................................................................................. 49
        8.9.4     Fauna ............................................................................................................................ 49
        8.9.5     Short-Range Endemics (SRE) ...................................................................................... 49
        8.9.6     Subterranean Fauna ..................................................................................................... 50
9      ATTACHMENT 9 – PROPOSED FEE CALCULATION............................................................ 51
10     BIBLIOGRAPHY ........................................................................................................................ 52

FIGURES
Figure 1: Location of Wiluna West Project ........................................................................... 5

                                                                          ii
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited                                                                              Part V Licence Supporting Document

Figure 2: Project Tenements currently held by GWR........................................................... 6
Figure 3: Prescribed Premises map showing emission and discharge points .................... 12
Figure 4: Overall Project site layout................................................................................... 14
Figure 5: Site layout of crushing/screening plant area ....................................................... 15
Figure 6: Crusher Process Flowsheet ............................................................................... 18
Figure 7: C4 Catchments Map (from Rockwater 2020) ...................................................... 38
Figure 8: Surface Water Drainage Infrastructure Map (from Rockwater 2020b) ............... 39
Figure 9: Water levels in exploration holes (from Pennington Scott 2013) ......................... 41
Figure 10: Location of Wiluna West PEC .......................................................................... 44
Figure 11: Vegetation Ccommunities and Priority flora in the proposed prescribed premises
.......................................................................................................................................... 48

TABLES
Table 1: Tenements part of the C4 Project Prescribed Premises ........................................ 4
Table 2: Summary of the C4 Project (Stage 1) .................................................................. 13
Table 3: Key Equipment and Infrastructure to be installed................................................. 16
Table 4: Crushing Plant design and operation requirements ............................................ 17
Table 5: Statutory approvals required for the C4 Project ................................................... 20
Table 6: Stakeholder consultation undertaken................................................................... 22
Table 7: Risk assessment and management summary for the crushing and screening plant
.......................................................................................................................................... 30
Table 8: Risk Criteria......................................................................................................... 32
Table 9: Receptors and distance from activity boundary ................................................... 33
Table 10: Specified Ecosystems and Designated Areas.................................................... 33
Table 11: Soil units in the Project area .............................................................................. 36
Table 12: Results of groundwater analysis ........................................................................ 43
Table 13: Vegetation units within the proposed prescribed premises ................................ 45

                                                                     iii
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited                                                  Part V Licence Supporting Document

      1.0        INTRODUCTION
      1.1        BACKGROUND
      GWR Group Limited (GWR) own the Wiluna West Project which comprises eight iron ore deposits
      over the two Banded Iron Formation (BIF) ridges (Ridges B and C as classified by GWR). Gold
      deposits are known to occur in the swales between the BIF ridges and there are numerous Gold
      Deposits that have been identified (13 in resource category).
      Due to known occurrences of both minerals within the tenement package and depending on which
      commodity was being put forward the Project has been referred to as both the Wiluna West Gold
      Project (WWGP) and the Wiluna West Iron Ore Project (WWIOP).
      There is a large iron ore resource (130Mt @ 60% Fe) with an associated reserve of 69.2Mt @
      60.3% Fe and there has been extensive work completed over the last 10 years in developing the
      WWIOP with various studies performed with two distinct options:
      •     Stage 1 – 1 -2 Mtpa operation looking at high grade deposits with low set up costs, utilizing a
            mobile crushing and screening plant and road transport to either establish rail platforms or direct
            to the Geraldton or Esperance ports.
      •     Stage 2 – 5-7 Mtpa operation looking at 10 Year mine Life and full reserve extraction, fixed
            infrastructure on site but very dependent on major upgrade of rail and port facilities (Oakajee).

      GWR has approval for:

      •     a 10 Mtpa development involving mining of the Bowerbird, C3 and C4 iron ore deposits (Reg
            ID 55179); and
      •     a 1.5Mtpa development of the C4 deposits high grade iron ore (referred to as Stage 1) which
            includes a 18.6 km haul road, a crushing /screening plant and associated infrastructure (Reg
            ID 86015)
      •     the construction of a crushing/screening plant (W6444/2020/1).
      Construction works of the crushing/screening were completed in December 2020 with
      commissioning being completed in January 2021. GWR intend on operating the crushing/screening
      plant under a Part V operating licence.
      1.2        OBJECTIVE
      As part of the C4 (Stage 1) iron ore deposit development, GWR intends to operate the following
      prescribed premises:
      •     Category 5 - Processing or beneficiation of metallic or non-metallic ore (Modular crushing and
            screening plant)

      This document has been prepared to support the Licence application. Subject to approval, the
      expected commencement date is scheduled for Q1 2021.

      1.3        LOCATION
      The Project is located approximately 700 kilometres northeast of Perth and 40 kilometres
      southwest of Wiluna in the north-eastern Goldfields of Western Australia (Figure 1).

      1.4        OWNERSHIP & LAND TENURE
      The Project is located within M53/1087 which is 100% owned by GWR Group Limited (Table 1,
      Figure 2).

                       Table 1: Tenements part of the C4 Project Prescribed Premises

                                                       4
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited                                      Part V Licence Supporting Document

       TENEMENT     OWNER               DATE GRANTED        EXPIRY DATE            AREA
       M53/1087     GWR Group Limited   23/09/2010          22/09/2031             6343.37 ha

                            Figure 1: Location of Wiluna West Project

                                             5
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited                                 Part V Licence Supporting Document

                    Figure 2: Project Tenements currently held by GWR

                                         6
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited                                              Part V Licence Supporting Document

2       ATTACHMENT 1A – PROOF OF OCCUPIER STATUS
Details of the Mining Lease (M53/1087) to which this application relates, providing proof of
the occupier status, are provided on the following page.

                                             7
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited       Part V Licence Supporting Document

                    8
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited                                         Part V Licence Supporting Document

3 ATTACHMENT 1B – ASIC COMPANY EXTRACT
A current company information extract for GWR Group Limited and company details from the ASIC
website is provided below.

                                              9
WILUNA WEST IRON ORE PROJECT - C4 IRON ORE DEPOSIT PART V LICENCE APPLICATION SUPPORTING DOCUMENT
GWR Group Limited        Part V Licence Supporting Document

                    10
GWR Group Limited        Part V Licence Supporting Document

                    11
GWR Group Limited                                      Part V Licence Supporting Document

4 ATTACHMENT 2 – MAP OF PRESCRIBED PREMISES

       Figure 3: Prescribed Premises map showing emission and discharge points

                                         12
GWR Group Limited                                                   Part V Licence Supporting Document

5       ATTACHMENT 3B – PROPOSED ACTIVITIES
5.1     OVERVIEW
A summary of the C4 (Stage 1) Project is provided in Table 2 with an overall site layout provided
as Figure 4 and layout for the crushing/screening plant provided in Figure 5.
The initial first year production is anticipated to be 1 Mtpa with the potential to expand production
to 1.5Mtpa with the progression of a cutback at C4 and possibly adjacent deposits at a later
date.
                           Table 2: Summary of the C4 Project (Stage 1)
Element                              Description
C4 (Stage 1) Project Ore             976,000 t @ 62% Fe

Mine Life                            12 Months (19 months including construction, operation and
                                     rehabilitation)

Mining method                        Open pit

Total waste rock                     891,898 t

Depth of pit                         ~ 40m

Depth of water table                 ~ 50m (40-60m Range in C4 Area)

Area of disturbance including        101.7 ha
access (Stage 1)
Water Supply for operations          Water bores (C4PB01 & BBPB01)

Processing                           Modular crushing and screening plant (1-1.5 Mtpa capacity)

Power generation                     Portable diesel-powered generators on site

Accommodation                        Rosslyn Hill Camp (off-site)

Construction commencement            Q4 2020

                                                   13
GWR Group Limited          Part V Licence Supporting Document

                    Figure 4: Overall Project site layout

                                       14
GWR Group Limited                                           Part V Licence Supporting Document

                    Figure 5: Site layout of crushing/screening plant area

                                             15
GWR Group Limited                                                   Part V Licence Supporting Document

5.2       PRESCRIBED PREMISES
As part of the C4 development, GWR intends to operate the following prescribed premises:
      •    Mobile crushing and screening plant (Category 5) – 1.5 Mtpa (maximum).

The prescribed premises boundary and discharge points are shown in Figure 3.

5.3       KEY INFRASTRUCTURE AND EQUIPMENT
The key infrastructure and equipment is summarised in Table 3, with further detail specific to
the plant provided in the following sections.
GWR has constructed a stormwater catchment trench at the western end of the
crusher/stockpile area which slopes down towards. This will prevent potentially contaminated
stormwater from the plant/ROM area flowing into the surrounds.
After a rain event the stormwater will be pumped out and transported to the turkey’s nest.
GWR will ensure a pump with sufficient pumping capacity is maintained to ensure the trench
does not overflow.
                    Table 3: Key Equipment and Infrastructure to be installed

 Category       Equipment and Infrastructure to be installed

 5              Crushing/Screening Plant
                A mobile crushing and screening plant to provide two-stage crushing and screening
                and a combination of diesel/electric powered modular mounted crushers, screens
                and portable conveyors.

5.4       CRUSHING AND SCREENING PLANT
The plant will process the ore at rate of just under 1Mtpa (dry tonnes) (maximum 1.5 Mtpa).
Ore will be hauled to the ROM via a 1 km two-way haul-road from the open pit by the mining
fleet and stockpiles as directed.
All ore will be transported from the pit to various ROM stockpiles which may demarcate
different ROM grades and ore characteristics (e.g. high grade/low grade). The ROM will be
under the control of the ROM loader operator and traffic management will ensure positive
communication prior to entry. Ore will be processed through a mobile crushing and screening
circuit to produce two distinct ore products, Coarse Ore (Lump) and Fines stockpiles, with a
process flowsheet shown in Figure 6. Based on information available for stage 1 the crushing
and screening process is deemed fit for purpose.
The product will be stacked in separate stockpiles (Lump and Fines) and selectively removed
offsite via road trains to Geraldton.
The ROM stockpiles will have a total capacity of approximately 150,000 tonnes of ore and are
anticipated to be relatively dry. Dust suppression at the ROM will be achieved via the
installation of water sprays and the mobile water truck with expect moisture of between 5-8%
to minimise dust generation. Additional stockpile capacity of 50,000 tonnes will be in the DSO
products stockpiles to the west of the plant. Water sprays will be installed around the product
area to minimise dust generation.
Ore processing will consist of crushing and screening of the ore through a modular constructed
two-stage crushing and screening plant to produce lump and fines using an electric powered
modular mounted crushers, screens and portable conveyors. The plant will produce two
products: a lump product which is between 31.5mm and 6.3 mm product and a fine product (-
6.3 mm).

                                                  16
GWR Group Limited                                                   Part V Licence Supporting Document

The ore will be fed into the hopper of the primary crusher using a front-end loader. The crushed
material from the primary crusher will then fed directly to a screen, set for a 32mm split size.
The undersize material will report to the secondary screen while the oversize material will
report to the secondary crusher. The undersize material from the secondary screens will report
to the fine’s product stockpile and the oversize material will report to the lump product
stockpiles.
Key design features of the plant design include plant operation is based on a single 12-hour
shift, 7 days per week roster. There is ample capacity in the circuit to increase production to a
24-hour, 7 day a week basis.
The ROM pad will cover an area (100m x 200m) with a 6 m high steel retaining wall located at
the northern end of the ROM pad. This will allow the ore bin apron feeder module to abut
against a 40 m long, 15 m wide ramp inclined at 10% grade to be feed by frontend loader.
Two stacker conveyors will transfer ore from the crushing and screening plant onto the Fines
and Lump stockpiles in one direction. The stacker conveyors will operate a 600mm wide belt
which will be equipped with dust suppression sprays.
Front end loaders will be fitted with bucket load cells to control loading operations for main
road compliance. An additional weigh bridge is located at the Rosslyn office area for secondary
and spot checks (outside of the Project area).
Table 5 summarises the crushing/screening plant design and operation requirements.

                 Table 4: Crushing Plant design and operation requirements

Infrastructure       Requirements

Design and construction

Crushing/Screening   •   Primary Crusher and ROM pad
Plant                •   Secondary crusher trailer and 10m hopper/feeder
                     •   Screening trailer and 10m hopper feeder
                     •   Temporary lump stacker
                     •   Temporary fine stacker

Commissioning and Time-limited operations
Crushing/Screening   •   Water will be added to the process to achieve approximately 5% moisture
                         content to minimise dust generation.
Plant
                     •   Dust suppression sprinklers and sprays will be installed at the ROM feed
                         hopper and transfer points to control levels of fugitive dust and will be
                         operational.
                     •   Water trucks will be available and used around the plant and on the ROM
                         and roads as required to minimise fugitive dust emissions.
Product stockpile    •   Dust suppression sprinkler and sprays to control levels of fugitive dust.
                     •   Maximum moisture levels of the final product will be controlled to maintain
                         operational efficiency from road haulage vehicles and adjusted for seasonal
                         conditions

                                                  17
GWR Group Limited                                              Part V Licence Supporting Document

                           Figure 6: Crusher Process Flowsheet

5.5     DIESEL & HYDROCARBON STORAGE
All hydrocarbons and chemicals will be located within bunded areas or on drip trays to contain
any potential spills. Bulk fuel storage will be within a self-contained, double-skinned storage
tank. They will be two Diesel Storage facilities onsite, one located near the power pack for the
Crushing and Screening facilities and the second for the mobile equipment for mining.

                                              18
GWR Group Limited                                              Part V Licence Supporting Document

Waste oil will be stored in a tank and removed from site for recycling by a licensed collection
service. Oil filters and hydrocarbon-contaminated rags will be collected in approved
receptacles and removed from site to an appropriate facility at Rosslyn Hill.
Two self-bunded diesel storage facilities are to be installed at the C4 site. One of the diesel
storage facilities will be located adjacent to the power-pack for the crushing and screen plant.
The other 110kl storage tank will be location near the go-bay to facilitate the mining fleet and
miscellaneous mine vehicles requirements.
Self-bunded day tanks will be installed to provide fuel to stand-alone diesel generators (e.g.
producing water bores) at their respective locations where required.
All chemical and reagents classed as dangerous goods will be stored in accordance with the
requirements of the Dangerous Goods Safety Act 2004 and the Dangerous Goods Safety
(Storage and Handling of Non-explosives) Regulations 2007. Spill kits will be made available
for use to contain hydrocarbon spills.

                                              19
GWR Group Limited                                                     Part V Licence Supporting Document

6       ATTACHMENT 5 - OTHER APPROVALS AND CONSULTATION
6.1     OTHER STATUTORY APPROVALS
Table 5 summarises the statutory approvals required for the C4 Project.

                    Table 5: Statutory approvals required for the C4 Project
 Relevant Legislation                   Environmental        Relevant approval requirement
                                        Factor
                                        regulated/affected
 APPROVALS
 Environment Protection and             Biodiversity         EPBC Act referral (EPBC 2020/8696) made to the
 Biodiversity Conservation Act 1999     Land and Soils       Federal Department of Agriculture, Water and the
                                                             Environment (DAWE), as there is one species listed
                                                             under the EPBC Act at the Project (Malleefowl -
                                                             Leiopoa ocellata). DAWE decision on 31/7/20 that
                                                             Project is ‘not a controlled action’ and no further
                                                             assessment under EPBC Act is required.
 Environmental Protection Act 1986      Biodiversity         A large scale 10Mtpa Project (disturbance 2,600 ha)
 (EP Act) Part IV (and Administrative   Land and Soils       was referred to the EPA in December 2012 and
 Procedures 2012)                                            assessed as ‘Not Assessed – Public Advice Given on
                                                             22 April 2013.
                                                             No significant impact to any environmental factors
                                                             resulting from the Project.
 Environmental Protection Act 1986      Biodiversity         GWR has two active clearing permits that cover the
 (Part V)                                                    C4 development and associated haul road:
 Environmental Protection (Clearing                          1. CPS 6726/2 – 1,290 ha (expires August 2026)
 of Native Vegetation) Regulations
                                                             2. CPS 8915/1 – 60 ha (expires July 2023).
 2004
 Mining Act 1978 and Mining             Biodiversity         GWR has an approved Mining Proposal (MP) and
 Regulations 1981                       Land and Soils       Mine Closure Plan (MCP) (Reg ID 86015) for the C4
                                                             development including the crushing/screening plant
                                        Rehabilitation and   as outlined in this WApp application.
                                        Mine Closure         GWR also has an approved MP-MCP (Reg ID 55179)
                                                             for larger scale development at C4 (in addition to
                                                             Bowerbird and C3 deposits).
 Rights in Water and Irrigation Act     Water resources      GWR has a DWER (formerly DoW) Licence to take
 1914                                                        water:
                                                             •    GWL 202977(1) issued 27/06/2019 for the
                                                                  purposes of dust suppression
 Mines Safety & Inspection Act 1994     Safety               A Project Management Plan will be submitted to the
 and Mining Safety & Inspection                              DMIRS in accordance with this Act and Regulations.
 Regulations 1995                                            All operations will occur in accordance with the Act
                                                             and Regulations.

6.2     CONSULTATION
GWR has ongoing consultation with key project stakeholders and a summary of the
consultation undertaken to date is presented in (Table 6). No recent discussions have been
held with DWER.
A major stakeholder in the project are the Wiluna Native Title holders represented by Tarlka
Matuwa Piarku Aboriginal Corporation (“TMPAC”). Consultation with TMPAC is defined by
a Mining Agreement and Cultural Heritage Management Plan (“CHMP”). Copies of the
Mining Proposal will be provided to TMPAC in accordance with the above agreements. The
Wiluna Native Title holders were also briefed on the project when they participated in
Heritage surveys of the area and through the Relationship Committee and various
presentations to the TMPAC Board.

                                                       20
GWR Group Limited                                            Part V Licence Supporting Document

The other major stakeholder in the C4 Project is the current pastoral station owner, Toro
Energy. Toro Energy are aware of GWR’s plans and has voiced no objections or concerns.
GWR will continue to liaise with stakeholders during operations and in relation to closure
during the life of the project and will provide updates on closure developments on an
ongoing basis.
Consultation with stakeholders will continue throughout the life of the Project to ensure
stakeholder concerns and objectives are accounted for and the Register will be updated to
reflect further input from stakeholders.

                                           21
GWR Group Limited                                               Part V Licence Supporting Document

                                                       Table 6: Stakeholder consultation undertaken
   Date                Stakeholder*          Description of                   Stakeholder comments/issues                         Proponent response and/or resolution
                                             Consultation
14/02/06      DEC                            Site Visit         Site visit to show DEC the Wiluna West site.                     As a result of this site meeting, a quadrat-
              • Dr Neil Gibson                                                                                                   based sampling methodology was obtained
                                                                                                                                 by Jim’s Seeds, Weeds and Trees from Dr.
              GWR representatives                                                                                                Gibson.
23/05/07      DEC                            Project briefing   Overview of the Project provided.                                N/A
              GWR representatives            in Kalgoorlie
6/11/08       DEC                            Project briefing   Briefing outlined the results of the biophysical surveys         Subsequent survey        work   has   been
              • David Pickles                                   undertaken to date at the Project.                               undertaken by GWR.
              • Sandra Thomas                                   DEC raised concern over adequacy of 2006 SRE survey
              GWR representative                                (based on timing of survey). Further work suggested.
April and     DEC                            Meeting            Consultation with the DEC regarding the flora species Sida       Further survey work undertaken by KLA (in
August        • Western Australian                              picklesiana (formerly Sida sp. Wiluna). The species was first    conjunction with the WA Herbarium) which
2010            Herbarium                                       recorded by the DEC in the 2006 quadrat survey and later         recorded additional populations of the
              GWR representatives                               given a Priority 1 rating.                                       species extending up to 200km from the
                                                                Discussions were undertaken with the Curator and staff of        GWR      Project    (This  species    has
                                                                the WA Herbarium regarding two undetermined specimens            subsequently been downgraded to a Priority
                                                                showing superficial similarities to this species (considered a   3 species).
                                                                new taxon at this time).
2010          Central Desert Land Council    Correspondence     Provide copy of Mining proposal with conceptual MCP.             No concerns or issues.
              Representing Tarlpa NTC
2010          Wiluna Shire council members   Meeting            Presentation on the Wiluna West project and JWD.                 No concerns or issues.
              GWR representatives
Ongoing       Tarlpa Native Tile Claimants   Triennial          Regular briefings with the NT relationship committee.            No concerns or issues.
from 2010                                    Meetings
Ongoing       Lupton family (Lake Way        Informal           Periodical Informal discussion giving updates on projects.       No concerns or issues.
from 2010     Pastoralist sub-leasee)        discussions
                                             about project
2010          DMP                            Meeting            Provided overview of JWD Project before submission.              Comments provided and acted on.
              • Janine Cameron
27/01/12 &    DMP                            Consultation       Advice from the NVB, DMP (Ryan Mincham) sought
30/01/12      • Ryan Mincham                                    regarding the requirement for an Autumn fauna survey.
              GWR representatives

                                                                                  22
GWR Group Limited                                      Part V Licence Supporting Document

   Date               Stakeholder*   Description of                 Stakeholder comments/issues                         Proponent response and/or resolution
                                     Consultation
20/02/12      EPA                    Meeting - GWR    The Chairman and Mark Jefferies raised the following points:     All agencies were met with and
              • Dr Paul Vogel        met with the     1. Metalliferous drainage at neutral pH – looking at AMD was     issues    addressed     in  the
              • Mr Mark Jefferies    OEPA to             correct but must include neutral drainage for such            subsequent submissions.
              GWR                    discuss the         elements as selenium, etc.
              • Craig Ferrier        Wiluna West
                                                      2. Ensure that the studies investigate the cumulative impacts
              • Mick Wilson          Project
                                                         and compare to the regional environment.
              • Paul Leidich
              KLA                                     3. Contact DEC to ensure they are happy with the lack of
              • Keith Lindbeck                           autumn fauna surveys (as with the DMP).
                                                      4. Contact DEC to obtain comment on the impact of the
                                                         project on the PEC.
                                                      5. Contact DoW to discuss availability of groundwater for the
                                                         project and potential impact on other users.
                                                      6. Discuss clearing permit requirements with DMP
                                                      7. Discuss implications of export through the Port of
                                                         Esperance with the DoT.
21/02/12      DEC                    Correspondence   Correspondence with David Pickles (letter), DEC seeking
and 9/03/12   • David Pickles        (letter and      advice on the requirement for autumn fauna survey at the
              • Sandra Thomas        email)           project (as three Spring fauna surveys have been undertaken
                                                      previously).
                                                      Email correspondence received from Sandra Thomas, EMB,
                                                      DEC advising that: “Based on the available information, an
                                                      Autumn fauna survey does not appear to be required.”
20/06/12      DoW                    Meeting          GWR presented a summary of the Project, hydrogeological          N/A
              • Yolanda Brookes                       investigations and the proposed water supply and
              • Chris O'Boy                           dewatering strategy. The strategy for water licensing was
              • James MacIntosh                       presented.
              • Tina Taraborrell                      The DoW was supportive of the proposed approach noting
              GWR representatives                     that all key DoW requirements had been addressed.
26/06/12      DEC                    Correspondence   Correspondence to David Pickles (letter), providing results of
              • David Pickles        (letter)         the SRE 2011 survey.
28/08/12      DEC                    Meeting          GWR provided an update on the Project and advice sought          GWR provided the required information to
              • Sandra Thomas                         from the DEC on the impact of the Project on the Wiluna          the DEC.
              • Val English                           West PEC. DEC outlined the information they require
              • Julie Futter                          (vegetation and flora data) to enable them to make their
              • Daniel Coffey                         assessment on the impact of the Project.

                                                                        23
GWR Group Limited                                            Part V Licence Supporting Document

   Date                Stakeholder*         Description of                 Stakeholder comments/issues                     Proponent response and/or resolution
                                            Consultation
              GWR representatives
              • Craig Ferrier
              • Mick Wilson
              KLA
              • Keith Lindbeck
20/02/13      Mid-West Road Safety          Meeting          JWD Project and proposed road transport objectives.          Ongoing discussions.
21/02/13      Committee
10/04/13      Mt Magnet Shire
10/07/13      Meekatharra Shire
26/02/14      Cue Shire
              Menzies Shire
              Yalgoo Shire
9/04/13       Sandstone Shire               Meeting          JWD Project and proposed road transport objectives.          Ongoing Discussions.
31/10/13      MRD
28/11/13      GWR representatives
29/01/14
6/02/14
19/02/14
7/03/14
7/05/14
21/11/13      Wiluna Shire                  Meeting          Presentation of project and discussions on road transport.   Comments provided and acted on.
27/11/13      GWR representatives
28/01/14
5/02/14
18/02/14
18/02/14      Sandstone Shire               Public meeting   JWD Project and proposed transport objectives.               Comments provided and acted on.
              General Public
              GWR representatives
2014          Central Desert Land Council   Correspondence   Provide copy of Mining MCP for any feedback.                 No concerns or issues.
              Representing Tarlpa NTC
6/03/14       Native Title Claimants        Annual General   Annual Function for all claimants.                           No concerns or issues.
              GWR representatives           Meeting
7/04/14       Pastoralist                   Exploration      Exploration objectives.                                      Consent to program.
              • Jim Quadrio                 Activities
              • Alan Bloor
              GWR representatives

                                                                               24
GWR Group Limited                                               Part V Licence Supporting Document

   Date                Stakeholder*            Description of                 Stakeholder comments/issues                       Proponent response and/or resolution
                                               Consultation
September     Toro Energy (Pastoralist owner   Correspondence   Provided synopsis of Mine Closure Plan.                        No concerns or issues.
2014          for Lake Way Station)

2015          Central Desert Land Council      Meeting          Presented WWIOP Mining Proposal for review.                    No concerns or issues.
              Representing Tarlpa NTC
2018 and      Wiluna Shire                     Ongoing          Status of Golden Monarch project and use of Shire Roads        Ongoing discussions and no issues
2019          • Councillors                    meetings and
              • CEO                            discussions
              • Executive Manager
                Technical Services
5/07/18       Wiluna Native Title holders      TMPAC Board      Provided project update, which specifically included the       No concerns or issues
                                               Meeting          proposed open pit at Golden Monarch
8/08/18       DMIRS                            Phone            Advice sought regarding definition of ‘Fauna specialist’ as    GWR submitted a letter requesting approval
              •    Ryan Mincham                call/Email       stated in CPS 4006/2 as GWR has and intends to utilise the     for the Aboriginal Martu women to complete
                                                                Aboriginal Martu women to undertake targeted Malleefowl        the survey (former and future) with the CPS
27/08/18
                                                                assessments at the Project.                                    4006/3 application.
                                                                Ryan spoke to Lesley Polomka about this scenario and they
                                                                both agreed that the Aboriginal Martu women would be
                                                                suitably qualified to undertake this work. Ryan has provided
                                                                some further advice in relation to the process for seeking
                                                                approval as per the conditions on CPS 4006/2
19/08/2018    Wiluna Native Title holders      Survey           Ethnographic survey over proposed C4 Haul road                 Compliant   with         Cultural   Heritage
                                                                                                                               Management Plan
January       Bill (Manager) for Lupton        Informal         Advised that we were seeking to commence mining at             No concerns or issues
2019          family                           Meeting          Golden Monarch
27/02/19      Wiluna Native Title holders      Wiluna Native    Provided project update, which specifically included the       No concerns or issues
                                               Title holders    proposed open pit at Golden Monarch
25/03/19      DBCA                             Phone call       CLA contacted David to advise him of GWR’s intention to        Confirmed source of record and advised that
              •    David Pickles                                start mining at Golden Monarch, update on recent Sida          DBCA is only aware of their occurrence at
                                                                survey findings and to seek advice on the source of Boodie     Matuwa (>200km north) where they were re-
                                                                record (Bettongia. lesueur.graii) which shows in the DBCA      introduced. David advised he is relocating
                                                                threatened fauna search at Wiluna West.                        to the Karratha DBCA office within the next
                                                                                                                               fortnight.
10/4/19 –     Wiluna Native Title holders      Survey           Heritage survey over portion of proposed Golden Monarch        Compliant   with         Cultural   Heritage
12/4/19                                                         footprint and Eagle – Emu deposits                             Management Plan

                                                                                  25
GWR Group Limited                                              Part V Licence Supporting Document

   Date                Stakeholder*         Description of                  Stakeholder comments/issues                       Proponent response and/or resolution
                                            Consultation
6/05/19      Toro Energy (owner of Lake     Email             Advised that we were intending to commence mining at           Acknowledged        receipt   and   awaiting
             Way Station)                                     Golden Monarch and wished to convene meeting.                  response
             •    Greg Shirtliff
22/05/19     Wiluna Shire                   Meeting           Meeting, advised of Wiluna West project status and intention   No issues raised.
             • President                                      to commence mining at Golden Monarch
             • CEO
             • GWR representatives
27/06/19     DMIRS                          Email             DMIRS requested further information in relation to the         GWR clarified that the waste from the two
             • Maree Doyle                  correspondence    Golden Monarch MP (Reg ID 80069) including:                    deposits is similar.
             • Rob Irwin                    and Meeting       • Interaction between Golden Monarch and JWD pits              GWR committed to complete a detailed
             GWR                                              • Design of Golden Monarch WRD if JWD does not                 Golden Monarch WRD design and
             •    Mick Wilson                                    proceed and confirmation of waste characteristics           requested a further meeting to confirm the
                                                              • Clarification    of      areas      where        existing    suitability of the design.
                                                                 disturbance>approved disturbance.                           Clarification of disturbance areas will be
                                                              GWR arranged a meeting to discuss these items.                 provided to DMIRS.
9/07/19      DMIRS                          Meeting           GWR presented the design of the Golden Monarch WRD to          Golden Monarch MP and Mine Closure Plan
             • Maree Doyle                                    DMIRS. DMIRS provided advice in relation to back sloping       will be updated with this design information
             • Rob Irwin                                      the top surface of the WRD and other suggestions for           and resubmitted.
             GWR                                              inclusion in the MCP.                                          GWR will provide an outline of the
             •    Mick Wilson                                 The differences in existing and approved ‘disturbance’ were    disturbance on L53/115 (under separate
                                                              briefly discussed and DMIRS requested an outline of events     cover) for DMIRS review.
                                                              relating to this to assess.
19/08/19     Wiluna Native Title holders    Survey            Ethnographic survey over proposed C4 Haul road                 Compliant   with         Cultural   Heritage
                                                                                                                             Management Plan
6/09/19      Wiluna Shire Councillors       Council Meeting   Presented update on Wiluna West project including intention    No Issues
             Wiluna Executives                                to start mining at Golden Monarch
             General public
             GWR representatives
12-16        Wiluna Native Title holders    Survey            Archaeological survey over C4 deposit and haul road C4, C3,    Compliant   with         Cultural   Heritage
September                                                     Bowerbird, Eagle, Emu and Golden Monarch                       Management Plan
2019
November     Engagement with Wiluna Shire   Meetings, email   Establishment and finalising a Road Access Agreement           Finalised May 2020
2019 to      management, CEO, Works         and formal
May 2020     Manager and Shire President    agreement

                                                                                26
GWR Group Limited                                           Part V Licence Supporting Document

   Date               Stakeholder*        Description of                 Stakeholder comments/issues                           Proponent response and/or resolution
                                          Consultation
14/11/19     •    DMIRS – Maree Doyle     Phone            DMIRS queried timing of submission of Eagle and Emu MP             Submission delayed – this MP drafted in
             •    CLA – Belinda Clark                      as DMIRS are advising proponents that MP’s produced in             accordance with DMIRS (2020) guidance.
                                                           accordance with DMP (2006) guidelines will only be
                                                           accepted until February 2020.
20/11/19     •  DMIRS                     Meeting          Meeting held for GWR to provide overview of Eagle-Emu              DMIRS advice was incorporated into the
                Maree Doyle                                deposits and ascertain the most efficient approval pathway         MP.
             • Richard Smetana                             for clearing permit (and MP).
             GWR                                           DMIRS advised that Jan De Lange is the most appropriate
             • Mick Wilson                                 contact for geotechnical advice.
             • Adrian Costello
             CLA
             • Keith Lindbeck
                Belinda Clark
10/12/19     DMIRS                        Email            Email request for clarification regarding inclusion of             GWR have considered this advice in
             •    Maree Doyle                              Bowerbird infrastructure in the Eagle-Emu MP. DMIRS                preparation of this MP. As there are no
                                                           preliminary advice is that “inclusion of the Bowerbird             immediate plans to develop Bowerbird pit, it
                                                           infrastructure in the MP would provide greater flexibility with    has been left out of this MP.
                                                           land use (given the overlaps) or shifts in location/construction
                                                           of proposed infrastructure (provided the alterations do not
                                                           trigger the need for re-submission of an MP) once
                                                           development commences, mine closure planning,
                                                           compliance and reporting purposes”.
25/02/2020   Youno Downs Station          Phone            Project update                                                     Very supportive
             •    Marilyn Bernhardt
25/02/2020   Toro Energy (owner of Lake   Email            Request to catch up regarding project status                       No response
             Way Station)
             • Greg Shirtliff
12/03/2020   Wiluna Shire                 Meeting          Provided update on Wiluna West project including JWD,              No issues
             • DCEO                                        Golden Monarch, Eagle, Emu and C4
             • EA
             GWR
             •    Mick Wilson
27/03/2020   Youno Downs Station          Site Visit       Site visit Golden Monarch, Eagle, Emu, C4 and C4 haul road         Highly supportive
             •    Colin Bernhardt

                                                                             27
GWR Group Limited                                                     Part V Licence Supporting Document

   Date                Stakeholder*              Description of                    Stakeholder comments/issues                       Proponent response and/or resolution
                                                 Consultation
April 2020   • DMIRS – Maree Doyle               Phone               DMIRS contacted to advise of the two MP’s currently being      DMIRS acknowledged that an MCP is
             CLA – Belinda Clark                                     prepared for submission at the Project:                        required to submitted with each MP. It was
                                                                     1/ Eagle-Emu – DMIRS advised this submission has been          recommended that the C4 haul road MCP be
                                                                     delayed                                                        submitted separately (rather than a joint
                                                                     2/ proposed 18.6 km haul road from the C4 deposit - DMIRS      MCP).
                                                                     advised that a smaller scale operation at C4 is now
                                                                     considered viable and the proposed haul road will enable
                                                                     transport of iron ore to either the Geraldton or Esperance
                                                                     Port.
                                                                     DMIRS queried if the haul road was
GWR Group Limited                                              Part V Licence Supporting Document

7 ATTACHMENT 6A – EMISSIONS, DISCHARGES AND WASTE
7.1      POTENTIAL EMISSIONS
Potential emissions arising from the operation of the prescribed premises are:
•     noise;
•     dust; and
•     contaminated stormwater resulting from plant/ore stockpile area to the surrounds.
The management measures and controls to be implemented are summarised in the risk
assessment presented in Table 7.

7.2      RISK ASSESSMENT AND MANAGEMENT SUMMARY
A summary of the potential environmental risks relevant to the Licence application and the
associated environmental management measures to be implemented to reduce these risks to
an acceptable level, are summarised in Table 7.
Based on GWR’s assessment of the Project siting (Attachment 7), it is considered that
vegetation, fauna, soil and groundwater are the only receptors. The closest residence dwelling
(pastoralist) is >20km away and the closest town is Wiluna (approximately 25 km away) from
the prescribed premises.
The residual risk assessment ratings are consistent with the risk assessment matrix used by
DWER as shown in (Table 8).

                                               29
GWR Group Limited                                                   Part V Licence Supporting Document

Table 7: Risk assessment and management summary for the crushing and screening plant
                                                                                                                                                                                                                                                Residual Risk

                                                                                                                                                                                                                                                 LIKELIHOOD

                                                                                                                                                                                                                                                              CONSEQUQ
                       Potential Emission Type and                                                                                                                  Impact Assessment/
       Activity                                                 Potential Receptors                Potential Pathway            Potential Adverse Impacts

                                                                                                                                                                                                                                                                            PRIORITY
                       Source                                                                                                                                       Proposed Controls

  OPERATIONS OF CRUSHING/SCREENING PLANT
 Operation of          Excessive dust generation from           Flora and vegetation               Air / wind dispersion        Decline in vegetation health and    Water to be used for dust suppression is not saline.

                                                                                                                                                                                                                                                                            Low
                                                                                                                                                                                                                                                              Slight
                                                                                                                                                                                                                                                 Unlikely
 Crushing/screening    crushing/screening plant, equipment                                                                      fauna habitat
 plant (including                                                                                                                                                   Crusher installed with appropriate water sprays to reduce dust
                       movements and ore handling and ore
 stockpiling of ore)                                                                                                                                                generation.
                       stockpiles
                                                                                                                                                                    Dust suppression sprinklers and sprays will be installed at the ROM
                                                                                                                                                                    feed hopper, transfer points and on the product stockpile to control
                                                                                                                                                                    levels of fugitive dust.
                                                                                                                                                                    Maximum moisture levels of the final product will be controlled to
                                                                                                                                                                    maintain operational efficiency from road haulage vehicles.
                                                                                                                                                                    Water trucks will be used around the plant and on the ROM and roads
                                                                                                                                                                    as required.
                                                                                                                                                                    Daily inspection of plant area will include observation of dust
                                                                                                                                                                    assessment and walking of plant site perimeter.
                       Noise –                                  Local fauna                        Air / wind dispersion        Noise may disrupt foraging          Closest sensitive receptor (rural residential dwelling) is located >20 km

                                                                                                                                                                                                                                                                    Low
                                                                                                                                                                                                                                                              Insignifica
                                                                                                                                                                                                                                                                        t
                                                                                                                                                                                                                                                Unlikely
                                                                                                                                behaviour                           from the Project
                       Equipment, machinery and vehicles
                       used during construction works                                                                                                               Operations will comply with the Environmental Protection (Noise)
                                                                                                                                                                    Regulations 1997.

                       Light spill generated during operation   Local fauna                        Air dispersion.              Light spill may disrupt nocturnal   Lighting design in areas that require night lighting will ensure light is

                                                                                                                                                                                                                                                                            Low
                                                                                                                                                                                                                                                              Insignifica
                                                                                                                                                                                                                                                 Unlikely
                       of plant                                                                                                 foraging behaviour                  directed to work areas and minimal light spill occurs (including use of
                                                                                                                                                                    directional lighting and covered lenses).

                                                                                                                           30
GWR Group Limited                                             Part V Licence Supporting Document

                                                                                                                                                                                                                                          Residual Risk

                                                                                                                                                                                                                                          LIKELIHOOD

                                                                                                                                                                                                                                                       CONSEQUQ
                    Potential Emission Type and                                                                                                               Impact Assessment/
       Activity                                           Potential Receptors                Potential Pathway              Potential Adverse Impacts

                                                                                                                                                                                                                                                                       PRIORITY
                    Source                                                                                                                                    Proposed Controls

                    Release of contaminated storm water   Soil and vegetation adjacent       Movement                  of   Soil contamination inhibiting     Ore stockpile and crusher area is bunded to prevent surface flows

                                                                                                                                                                                                                                                       Minor

                                                                                                                                                                                                                                                                       Medium
                                                                                                                                                                                                                                          Unlikely
                    runoff to the environment             to the area                        contaminated         surface   vegetation growth and survival,   outside of this area with all runoff directed towards the trench located
                                                                                             water runoff to land and       and health impacts to fauna.      at the southern end of the plant area.
                                                          Groundwater of beneficial use
                                                          – none, groundwater is ~50 m       infiltration to groundwater    Contamination of groundwater.     Bund is constructed around the plant area.
                                                          bgl                                Hydrocarbon or chemical
                                                                                                                                                              All hydrocarbons and dangerous goods on site will be stored and
                                                                                             spill
                                                                                                                                                              handled according to the applicable sections of the Dangerous Goods
                                                                                                                                                              Safety Act 2004, Dangerous Goods Safety (Storage and Handling of
                                                                                                                                                              Non-Explosives) Regulations 2007 and Dangerous Goods Safety
                                                                                                                                                              (Explosives) Regulations 2007.
                                                                                                                                                              Chemical storage areas will be bunded with a containment capacity
                                                                                                                                                              equivalent to 110% of the capacity of any tank or 25% of the total
                                                                                                                                                              capacity of an interlinked system.
                                                                                                                                                              Regular inspection of bunded areas to ensure capacity is maintained.
                                                                                                                                                              Washdown effluents will report to oil/water interceptor/separator.
                                                                                                                                                              Spillages will be cleaned up and disposed of as per appropriate SDS,
                                                                                                                                                              relevant environmental and safety guidelines and the site’s
                                                                                                                                                              environmental procedure.
                                                                                                                                                              Absorbent materials will be used under machinery which is likely to leak
                                                                                                                                                              oil while under service or repair in the workshop or on stand-down.
                                                                                                                                                              Any release which is likely to cause pollution or environmental harm will
                                                                                                                                                              be reported to the DWER in accordance with Section 72 of the EP Act.

                    Generation of excessive gaseous       Local fauna                        Air dispersion.                Amenity impacts                   Ensuring motorised equipment used on site are regularly serviced and

                                                                                                                                                                                                                                                                       Low
                                                                                                                                                                                                                                                       Insignificant
                                                                                                                                                                                                                                          Unlikely
                    atmospheric emissions from the                                                                                                            maintained.
                    crushing/screening plant.
                                                                                                                                                              Monitoring of gas emissions through the National Pollutant Inventory
                                                                                                                                                              (NPI) and National Greenhouse and Energy Reporting System
                                                                                                                                                              (NGERS).

                                                                                                                    31
GWR Group Limited                                                                                       Part V Licence Supporting Document

Table 8: Risk Criteria
Likelihood                        Consequence
                                  Slight                       Minor                  Moderate                       Major                     Severe
Almost Certain                           Medium                      High                     High                       Extreme                   Extreme
Likely                                   Medium                    Medium                     High                           High                  Extreme
Possible                                      Low                  Medium                   Medium                           High                  Extreme
Unlikely                                      Low                  Medium                   Medium                       Medium                       High
Rare                                          Low                    Low                    Medium                       Medium                       High

  Likelihood                                        Consequence
  The following criteria has been used              The following criteria has been used to determine the consequences of a risk occurring:
  to determine the likelihood of the risk /
  opportunity occurring.                                             Environment                                          Public Health* and Amenity (such as air and
                                                                                                                          water quality, noise, and odor)

  Almost             The risk event is              Severe           •     on-site impacts: catastrophic                  •     Loss of life
                     expected to occur
  Certain            in most
                                                                     •     off-site impacts local scale: high level or    •     Adverse health effects: high level or
                                                                           above                                                ongoing medical treatment
                     circumstances
                                                                     •     off-site impacts wider scale: mid-level or     •     Specific Consequence Criteria (for
                                                                           above                                                public health) are significantly
                                                                                                                                exceeded
                                                                     •     Mid to long term or permanent impact to
                                                                           an area of high conservation value or          •     Local scale impacts: permanent loss
                                                                           special significance^                                of amenity
                                                                     •     Specific Consequence Criteria (for
                                                                           environment) are significantly exceeded

  Likely             The risk event will            Major            •     on-site impacts: high level                    •     Adverse health effects: mid-level or
                     probably occur in                                                                                          frequent medical treatment
                                                                     •     off-site impacts local scale: mid-level
                     most circumstances
                                                                                                                          •     Specific Consequence Criteria (for
                                                                     •     off-site impacts wider scale: low level
                                                                                                                                public health) are exceeded
                                                                     •     Short term impact to an area of high
                                                                                                                          •     Local scale impacts: high level impact
                                                                           conservation value or special
                                                                                                                                to amenity
                                                                           significance^
                                                                     •     Specific Consequence Criteria (for
                                                                           environment) are exceeded

  Possible           The risk event                 Moderate         •     on-site impacts: mid-level                     •     Adverse health effects: low level or
                     could occur at                                                                                             occasional medical treatment
                                                                     •     off-site impacts local scale: low level
                     some time
                                                                                                                          •     Specific Consequence Criteria (for
                                                                     •     off-site impacts wider scale: minimal
                                                                                                                                public health) are at risk of not being
                                                                     •     Specific Consequence Criteria (for                   met
                                                                           environment) are at risk of not being met
                                                                                                                          •     Local scale impacts: mid-level impact
                                                                                                                                to amenity
                                                                                                                          •     Specific Consequence Criteria (for
  Unlikely           The risk event will            Minor            •     on-site impacts: low level
                                                                                                                                public health) are likely to be met
                     probably not occur
                                                                     •     off-site impacts local scale: minimal
                     in most                                                                                              •     Local scale impacts: low level impact
                     circumstances                                   •     off-site impacts wider scale: not                    to amenity
                                                                           detectable
                                                                     •     Specific Consequence Criteria (for
                                                                           environment) likely to be met

  Rare               The risk event may             Slight           •     on-site impact: minimal                        •     Local scale: minimal to amenity
                     only occur in
                                                                     •     Specific Consequence Criteria (for             •     Specific Consequence Criteria (for
                     exceptional
                                                                           environment) met                                     public health) met
                     circumstances

                                                                          32
GWR Group Limited                                                    Part V Licence Supporting Document

8        ATTACHMENT 7 – SITING AND EXISTING ENVIRONMENT
8.1      RECEPTORS
The distances to sensitive land uses are summarised in Table 9.
                    Table 9: Receptors and distance from activity boundary
    Sensitive Land Uses                      Distance from Prescribed Activity
    Residential premises                     No residences or other sensitive land uses within 25 km
                                             have been identified.
                                             Pastoral Lease/homestead is located 20 km from the
                                             Project.
                                             Wiluna is located approximately 25 km to the northeast.
                                             No closer residences have been identified.

8.2      SPECIFIED ECOSYSTEMS
DWER’s Guidance Statement: Environmental Siting (November 2016) lists Specified
Ecosystems and Designated Areas and relevant databases which are considered in risk
assessments undertaken by DWER. The distances to specified ecosystems are
summarised in Table 10.

                    Table 10: Specified Ecosystems and Designated Areas
 Specified ecosystems                       Distance from the Premises
 Ramsar Sites                               None identified within 100 km.
 DBCA Managed Lands and Water               There are no conservation reserves or DBCA managed lands in
                                            the project area.
                                            The closest nature reserve is Wanjarri Nature Reserve is 85 kms
                                            southeast.
                                            The nearest conservation area is Mooloogool Station (DBCA
                                            managed land) which is located approximately 52 kms
                                            northwest.
 Ecological   communities     (TECs   and   Project is located within the Wiluna West vegetation complexes
 PECs)                                      (BIF) Priority 1 Ecological Community (PEC)
 Biological Component                       Distance from Premises
 Threatened/ Priority Flora                 No Threatened flora recorded at the Project.
                                            Closest Priority flora (Eremophila congesta P1) is located 200m
                                            east of the plant area.
 Threatened /Priority Fauna                 Malleefowl (Vulnerable (EPBC and DBCA)) – records of
                                            inactive/extinct mounds at the north end of the ROM/crusher
                                            area.
                                            Brush-tailed Mulgara (Priority 4) - within sandplain spinifex
                                            habitat approximately 6 km north of the ROM/crusher area.
 Hydrography WA 250K – Surface Water        Some minor non perennial watercourses in the area.
 Polygons
                                            The Lake Way drainage system lies approximately 30 km to the
                                            east of the proposed clearing area, whilst Lake Mason is
                                            approximately 95 km south-southwest.
                                            No rivers, lakes or significant surface water bodies at the Project
                                            area.
 Contaminated Sites                         None recorded in DWER’s Contaminated Sites database.

                                                33
GWR Group Limited                                                  Part V Licence Supporting Document

    Other relevant ecosystem values         Distance from the Premises
    Potential  groundwater      dependent   None identified within 25 km of the premises.
    ecosystems
    Groundwater and water sources           Distance from the Premises
    Public Drinking Water Source Areas      None within 100 km.
    RIWI Act                                Premises is located within the East Murchison Groundwater
                                            Management Area
                                            Premise is not located within a Proclaimed Surface Water
                                            Management Area.

8.3       CLIMATE
The Project area is located within the Murchison region which exhibits an arid climate
characterised by hot dry summers and mild dry winters (CALM, 2002).
The nearest official meteorological station is located at Wiluna, approximately 40 km
northeast of the project area (Wiluna Station 013012). Recordings of the local climatic
conditions commenced at Wiluna in 1898 (Bureau of Meteorology, 2020). Relevant
temperature, rainfall, wind, evaporation and humidity data for Wiluna are summarised
below.
Mean annual maximum temperature is 29.2ºC and mean annual minimum 14.3ºC. Daily
maxima above 35ºC are usual from December to February. Diurnal temperature variations
are commonly high throughout the year.
The area is semi-arid and has an average annual rainfall of 260.4 mm. Most of the rain falls
from January to March but the amount varies greatly both seasonally and annually. The
highest daily rainfall recorded is 124 mm in February 1995.
The average wind speeds at Wiluna vary throughout the year from 8.1–12.9 km/h in the
morning to 8.5-13.2 km/h in the afternoon.
Evaporation is high, particularly in the summer months (December to February inclusive)
and the average mean daily evaporation rate is 6.6 mm (annual calculated rate is 2,409
mm).
Humidity levels vary considerably both daily and yearly. The mean monthly 9.00 am relative
humidity varies from a low of 30% in November and December to a high of 65% in July.
The mean monthly 3.00 pm relative humidity varies from a low of 19% in October, November
and December to a high of 42% in June.

8.4     REGIONAL SETTING

8.4.1     IBRA Region
The Interim Biogeographic Regionalisation for Australia (IBRA) divides the Australian
continent into 89 bioregions and 419 subregions (DAWE, 2020a). The proposed clearing
area is located within the Murchison bioregion and the Eastern Murchison (MUR1)
subregion of the IBRA (Thackway and Cresswell, 1995).
The East Murchison subregion lies on the Yilgarn Craton’s “Eastern Goldfields” and
“Southern Cross” Terrains.
The East Murchison bioregion is characterised by Mulga Woodlands often rich in
ephemerals, hummock grasslands, saltbush shrublands and Halosarcia shrubland (Cowan
2001). The area is characterised by:
•     internal drainage;
•     extensive areas of elevated red desert sandplains with minimal dune development;

                                                34
GWR Group Limited                                                  Part V Licence Supporting Document

•     salt lake systems that are associated with the occluded Palaeodrainage system; and
•     broad plains of red-brown soils and breakaway complexes as well as red sandplains
      (Cowan 2001).

8.4.2    Soil-Landscape Zone
The project is located within the Salinaland Plains soil-landscape zone of the Murchison
Province (Tille 2006).
This zone which encompasses 132,450 km2, comprises sandplains (with hardpan wash
plains and some mesas, stony plains and salt lakes) on granitic rocks (and some
greenstone) of the Yilgarn Craton and comprises red sandy earths, red deep sands, red
shallow loams and red loamy earths with some red-brown hardpan shallow loams; salt lake
soils and red shallow sandy duplexes.

8.4.3    Land Systems
The Wiluna-Meekatharra area, covering 25,000 square miles, has been mapped and
described in 48 land systems, based on recurring patterns of topography, soils and
vegetation (Mabbut et al., 1963).
The prescribed premise is located on five Land Systems listed below (Mabbut et al., 1963):
•        Glengarry – Sandstone plateaux, summits and hillslopes supporting mainly dense
         mulga and other acacia shrublands, spinifex, and numerous low shrubs.
•        Yanganoo – Almost flat hardplan wash plains, with or without small wanderrie banks
         and weak grooving; supporting mulga shrublands and wanderrie grasses on banks.
•        Bullimore – Gently undulating sandplain with occasional linear dunes and stripped
         surfaces supporting spinifex grasslands with mallees and acacia shrubs.
•        Sherwood - Breakaways, kaolinised footslopes and extensive gently sloping plains
         on granite supporting mulga shrublands and minor halophytic shrublands.
•        Dural – Strongly undulating terrain on weathered mudstone and basalt supporting
         open mulga shrublands with mallee and spinifex.
The plant area is located within the Glengary land system.

8.5      GEOLOGY
The Wiluna West project covers a 25 km strike length over the Joyners Find Greenstone
Belt, near the northern margin of the Yilgarn Craton. The Joyners Find Greenstone Belt is
a narrow (5 km to 10 km) north-south striking greenstone belt comprising low ridges of BIF
(in the central and eastern portion) intercalated with mafic and ultramafic schists with minor
chert and clastic sediment horizons. The Joyners Find Greenstone Belt strikes north and
dips steeply to the west. Folds developed during the D2 deformation event are observed in
the BIF ridges as tight to isoclinal folds oriented north-south with west dipping axial planes.
The BIF ridges are variably deformed and intensely folded.
Two regional dextral shear zones are recognised: the Joyner’s Find Shear Zone (JFSZ)
strikes to the north through the centre of the belt and is parallel to the lithological strike; and
the Brilliant Shear Zone (BSZ) which is oriented north-northwest.
There are three main Banded Iron Formation (BIF) units which form ridges within the project
area (Units A, B and C). High grade DSO hematite mineralisation occurs within units B and
C with grade occurrences of up to 69% Fe. Iron mineralisation occurs within BIFs
surrounded by inter-bedded mafic and ultramafic schist units. The two main ridges show
distinctive mineralisation styles with B ridge showing a much lower proportion of remnant
bedding and generally a significantly higher portion of haematite especially in the top 20 m.
Mineralisation of the B ridge is also much more continuous along strike occurring semi-
continuously for over 15 km. The mineralisation on the C ridge typically occurs in a series

                                                35
You can also read