INTEGRATED NATIONAL ELECTRIFICATION PROGRAMME (INEP)
ADDITIONAL
ELECTRIFICATION PROGRESS                                       NEW HOUSEHOLD ELECTRIFICATION STRATEGY
                                                                                                                                      NON-GRID ASPECTS
• Just above 6 million households were connected to the
   grid between 1994 and June 2014.                            On the 26 June 2013, the
                                                                                      he             ensure more connections,       • More municipalities can be
• In 1994 access to electricity was 36% , to date 88%          Cabinet approved the                  including a workshop on          assisted, but Councils are                Department of Energy
   households have been electrified.                           implementing of the nenew             the Plan to which all            not taking resolutions with              Matimba House, 192 Visagie Street
                                                                                                                                                                               Corner Paul Kruger & Visagie Street

• In the period from 2002 to 2013/14, 82 517 households
                                                                                                                                                                                          Pretoria, 0002
                                                                                                                                                                                 Private Bag x96, Pretoria, 0001

                                                                                   atio
                                                               Household Electrification             members of Cabinet would         regards to non-grid                         Switchboard: (012) 406 7803
                                                                                                                                                                                       info@energy.gov.za

   were supplied with non-grid technology (Solar panels –
   Renewable Energy)                                           Strategy based on the                 be invited to; and               implementation; (1) agree                   www.energy.gov.za

  • Eastern Cape - 48 532                                      following focus areas:
                                                                                 eas               d. The consideration of the        that non-grid be installed in               http://www.facebook.com/pages/
                                                                                                                                                                                  Department-of
                                                                                                                                                                                       artment- -Energy/316555815114240
                                                                                                                                                                                                             5

  • Kwazulu Natal - 46 532                                     a. The defining off universal
                                                                                    un                proposed delivery targets,      municipal area and (2) that                 #Energy_ZA

  • Limpopo - 13 381                                              access as 97% % of                  taking into consideration       a maintenance programme
• Non-grid electrification programme will in future not only      households, s, as full              views with regard to:           is been put in place.
   be implemented in concessionary areas, but in other areas                 tion is unlikely to
                                                                  electrification                                                   • The Department will be
                                                                                                   • the proposed change to the
   of the country, through the Master Plan Strategy.                       ible due to growth
                                                                  be possible                                                         conducting a non-grid
                                                                                                     delivery dates for universal
                                                                        elay in the process of
                                                                  and delays                         access from 2014 to 2025         electrification pilot in the
  CONNECTIONS BETWEEN 1994 - 2014
                                                                  formalising
                                                                     malis      informal                                              informal settlements of the
                                                                   ettlem
                                                                  settlements;                     • the concern that the new         Nelson Mandela Metro
      Province                   Electrified Houses:                                                 proposed target of 270 000
                                 Municipalities & Eskom        b. The electrification of about                                        Municipality. The intention
                                                                                                     households will contribute       is to provide total non-grid    Free State sponsored by
                                                                  90% of households through          to the backlog with regard
      Eastern Cape                    1 081 459                                                                                       solutions in a form of          Anglo Platinum. The fuel
                                                                  grid connection and the rest       to the targets set by the
      Free State                       370 260                    with high-quality non-grid                                          lighting in the houses, as      cell technology has never
                                                                                                     Presidential Infrastructure      well as security lights in a    been tested for rural
                                                                  solar home systems or other        Coordinating Commission
      Gauteng                          694 814                                                                                        form of solar street lights.    electrification and is a
                                                                  possible technologies based        (PICC); and
      KwaZulu Natal                   1 006 108                   on cost effective options in                                        The pilot will assist us in     ground breaking project for
                                                                  order to address current and     • funding provided by the          formulating policy in the       the country to learn more
      Limpopo                         1 043 401                                                      National Treasury to speed       future.                         about this sources of
                                                                  future backlogs;
      Mpumalanga                       575 352                                                       up connections                 • A fuel cell generation pilot    energy and whether it can
                                                               c. The development of a                                                                                be considered in the future
                                                                  master plan to increase                                             project has been installed in
      Northern Cape                    136 280                                                                                                                        for electrification purposes.
                                                                  efficiency in planning and                                          Moqhaka Municipality in
      North West                       694 505                    the delivery process to
      Western Cape                     403 150
      Total                           6 006 221

                  INTEGRATED
                     NATIONAL
              ELECTRIFICATION
                 PROGRAMME
                        (INEP)
INTEGRATED NATIONAL ELECTRIFICATION PROGRAMME (INEP)
USING THESE RULES, IT IS EXPECTED TO DEPLOY AROUND 300 000 SOLAR HOME
                                                                                                                  WAY - FORWARD
SYSTEMS AND REACH UNIVERSAL ACCESS FOR FORMAL HOUSEHOLDS IN 2025
                                                                                                                  Focus on
                                                                                                                  • management of roll out;
                                                                                                                  • maintenance challenges and
SOUTH AFRICA                                                                                                      • further information on planning in relation to grid
Total Connections 2013 - 2025                                                                                       roll out.
MILLION HOUSEHOLDS
                                     Provincial non-grid potential                                                Need to transform the pilot non-grid programme to
                                                                                                                  a sustainable programme in order to contribute to
NON - GRID    10%           0.3      Thousand households                                    37                    the target of universal access by 2025:
                                                                                                                  a. Current concessioner/service providers
                                                                                                                     programme to be transformed to a non-grid utility
                                                                                                                     model;
                                                                                      4       26
                                                                           16                                     b. Need model that will attract long-term non-grid
                                                                                                                     entities that can run programme in a sustainable
                                                                                                   84                manner;
                                                                                 11                               c. Based on an national master plan to determine
                                                           28                                                        grid and non-grid areas;
              90%           3.1
GRID                                                                                                              d. Roll-out and maintenance of systems and
                                                                                                                  e. No only rural areas, but also to address backlogs
                                                                                73                                   in informal urbanized areas.
                                                                                                                  • Implementation of Master Plan
                                                                                                                  • INEP need to be more involved in projects
                                                     19
                                                                                      The highest potential for      undertaken by municipalities to ensure they
                                                                                      Non-grid is in KZN and         deliver on targets set. Creating of the steering
                                                                                      Eastern Cape                   committees in the provinces with assistance by
                                                                                                                     Municipality Infrastructure Support Agency to
                                                                                                                     assist the non performing municipalities
Time to electrify
formal households         2025 1                                                                                  • The Department should annually revise the cost
                                                                                                                     per connection subsidy to keep up with price
                                                                                                                     increases of electrification materials
                                   1. Assumes existing INEP annual funding and DoHS contribution of R2,000        • Municipalities should fast track procurement
                                      per household for new RDP houses (40,000 houses per annum);                    processes and Council resolutions to enhance
                                      assumes total of 50,000 new formal households per year from DoHS
                                                                                                                     the pace of electrification within their area. Giving
                                      formalization process
                                                                                                                     municipalities R1,5mil each for the pre
                                                                                                                     –engineering
Department of Energy
Matimba House, 192 Visagie Street
Corner Paul Kruger & Visagie Street
           Pretoria, 0002
  Private Bag x96, Pretoria, 0001
   Switchboard: (012) 406 7803