Implementation Readiness Packet & Dashboard August 9, 2021
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Implementation Readiness Packet & Dashboard August 9, 2021 The Implementation Readiness Packet & Dashboard present a high-level view of Project Readiness to C-IV Counties with information related to C-IV Migration, BenefitsCal, the state- wide Self-Service Portal, and Central Print. Status will include key metrics related to the overall “health” of the Implementation effort based on measurable metrics and milestones. Project Milestones are identified by project team leads and CalSAWS Project leadership. The Packet & Dashboard serve to inform the Counties on the progression and completion of Key Project and County Milestones. The information contained in the document reflects data as of August 5, 2021. *An Implementation Readiness Milestone is a critical-path activity for the C-IV Migration, BenefitsCal, and Central Print Go-Live in September 2021. CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 1
Overall Project Readiness Executive Dashboard The Executive Dashboard presents a high-level view of Project Readiness in the form of a stop light indicator. Readiness statuses are presented for each Readiness Area. The status of each Readiness Area is determined by timely Milestone completion (see Key below). The Criteria for determining the Status (e.g., Not Started, On Schedule, =14 Days Late, Complete) of a Readiness Area is based on the Statuses of the individual Milestones within each Readiness Area. More detail on C-IV Migration, BenefitsCal, and Central Print progress can be found in later sections of the Implementation Readiness Packet. Area Category CalSAWS BenefitsCal Central Print Design – 100% complete 100% 100% N/A Development 100% 100% N/A Application System Test 100% 100% N/A User Acceptance Test 92% 71% N/A Usability Test N/A 85% N/A Design 100% 100% 100% Development 100% 100% 65% Integration System Test 98% 100% 8/20/21 Interface Partner Test 90% 97% 60% Infrastructure 71% 66% N/A Technical Security Testing 72% 74% N/A Performance Testing 81% 66% N/A Conversion Readiness 93% 100% N/A Conversion Converted Data Test 100% 100% N/A Training Plan 100% 100% N/A Training Training Materials 100% 90% 90% Training Delivery 51% 09/17/21 9/24/21 Service Desk 62% 70% 10% Implementation System Operations 90% 99% 75% Prod Deployment Plans 100% 18% N/A Communications 100% 50% N/A Change Partner Readiness (County, etc.) N/A 30% N/A Not Started On Schedule =14 Days Late Complete CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 3
Overall Project Readiness Risks and Issues Risk Issue Future focused - - Present focused Not yet realized - - Can be created as a result of a risk being realized Uncertain, probable event or condition - - Can be a new item not identified as a risk Could have negative effect on objectives - - Cannot be resolved by the identifier Documented in the CalSAWS Risk Log - - Documented in the CalSAWS Issue Log Monitoring - No Risks are Realized No Issues at this Time Total Risks 5 3 0 Total Issues 0 0 0 High Medium Low High Medium Low CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 4
Overall Project Readiness Risks related to Migration Risk Level Risk Name Risk Description The Analytics hard-launch dashboard production release experienced delays in data refresh impacting CalSAWS (LRS). #236 – The scaling of Analytics • A single county (LA) data load was delayed due to batch processing exceeding 6:00 am. Dashboards for 58 Counties may High • Data refresh time is degrading for a single county volume in production processing. have an impact on system • Performance and measurements for a single county may not scale with the current performance configurations. • Staging environment performance results identified that the environment used for hard launch needs to align with the production environment. The CalSAWS production batch schedule does not always complete by 6am. As part of DDI #237 – The scaling of Batch for 58 there will be growth in both the count of batch jobs and volume of data as additional counties High Counties may have an impact on are converted into CalSAWS. This growth may add a challenge to batch completing on time. system performance Related Risk 236 addresses Analytics specifically. Risk 237 addresses mitigation activities to impact the entire batch cycle. #240 -- The scaling of CalSAWS Production Operations, including Batch Operations, to provide 40 As we expand to 58 counties and with continual activities to support policy, the consequences and 58 County support, without High of a misstep in executing the CalSAWS M&O batch schedule magnifies the potential impact to effectively taking into account the business operations and benefits to the participants. multi-county and multi-vendor CalSAWS ecosystem may impact business operations #248 -- The C-IV Imaging go live may not have images prior to The C-IV Converted Image transfer for documents scanned prior to February 28th, 2021, is High 2/28/21 due to delays in the C-IV currently at risk of not finishing prior to go live. image migration The execution of the C-IV Conversion Cutover activities in the 3 Mock Conversions have not resulted with the overall End-To-End performance to completing at or within 84 hours. Mock [New] #249 – C-IV Cutover Activities Conversion #3 (in July) completed in approx. 87 hours (or 2.5 hours past the 84 hours window). High are At-risk of Completing within the The team will work with the various project teams and cutover activities to mitigate the risk of Planned 84 hour window executing cutover activities past the 84 hours and thus impacting County Users start to their business day in CalSAWS. CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 5
Overall Project Readiness Risks related to Migration Risk Level Risk Name Risk Description #208 – CalHEERS release There have been persistent delays in CalHEERS achieving release readiness during the system test readiness delays may negatively cycle, introducing risk to the dependent CalSAWS production release date. Any CalHEERS delay will Medium impact CalSAWS delivery impact the timely delivery of business functionality, receipt of which is critical to the counties. timelines, slowing critical Additionally, date slips cause negative downstream planning and scheduling churn. updates to counties The state and federal partners have requested changes to the SAWS Systems in response to COVID- #226 – COVID-19 relief efforts 19 relief efforts. The scope and priority of these efforts are not fully known. The Consortium and Medium may impact CalSAWS DD&I vendors may need to allocate staff to support the relief efforts to get them implemented quickly. If schedule. resources from DD&I are shifted to focus on relief efforts, it could impact the CalSAWS DD&I delivery schedule. #235 – The BenefitsCal Project If either the BenefitsCal phase 1 implementation or the CalSAWS modifications for BenefitsCal phase Release 1.0 may be delayed Medium 1 cannot be completed in time for the September 2021 go-live, the combined go-live of CalSAWS due to integration with the and BenefitsCal phase 1 could be impacted. CalSAWS Interface CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 6
Overall Project Readiness QA Status Icons QA has checked, verified, and recommended approval of item QA agrees with the status update QA disagrees with the status update Item is on the QA Watch List as resolution is critical for go-live readiness and may or may not be on the current risk list QA advises immediate corrective action above what is currently planned CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 7
County Readiness Dashboard Area Status Counties Application G 39 of 39 Counties Integration G 39 of 39 Counties Technical G 39 of 39 Counties Conversion G 39 of 39 Counties Training G 39 of 39 Counties Implementation G 39 of 39 Counties Change G 39 of 39 Counties *There are no County Issues and Risks as of August 5, 2021. Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 9
Application Readiness Design QA 8 of 8 Design Deliverables Approved 100% QA Reviewed 8 of 8 Design Deliverables and 594 SCRs 100% Development C-IV State Report County Planning and Execution Completed 100% Deployed CalSAWS Releases 19.11 - 21.07 100% System Test CalSAWS Master Test Plan Approved 100% Master QA Test Plan Approved 100% C-IV Converted Data Test Completed 100% C-IV Batch Regression Test Completed 100% System Test for Releases 19.11 – 21.07 100% QA Independent Test for Releases 19.11 – 21.07 100% User Acceptance Test (UAT) – CalSAWS Core CalSAWS UAT Support Plan Approved 100% CalSAWS UAT Readiness Report/Milestone Approved 100% Execution of User Acceptance Test (UAT) (Target 8/20/2021) 66% Pass Rate of User Acceptance Test (UAT) (Target 8/20/2021) 96% Application Readiness Risks and QA Watch List Risk 208 – CalHEERS release readiness delays may negatively impact CalSAWS delivery timelines, slowing critical updates to counties Risk 226 – COVID-19 relief efforts may impact CalSAWS DD&I schedule. Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 11
Application Readiness CalSAWS UAT for CalSAWS Core (Includes State Reports) UAT Status On Schedule • On-Track for CalSAWS Application which includes State Reports • 55 of 72 User Acceptance Testers, 6 SMEs, representing 23 counties participated in Week 8 of 10 • The following table provides the UAT execution results as of August 6, 2021 where the team has overall completed 66% of the test scenarios with a 96% pass rate (of completed scenarios) • Scenarios dropped from 941 to 919 due to removing LA and CalWIN specific functional scenarios Total CalSAWS UAT Not Executed In Progress Passed Failed Open Defects Scenarios CalSAWS UAT Execution 919 14.4% (133) 7.4% (68) 74.8% (687) 3.4% (31) 12 Exit Criteria Status 100% of UAT Test Cases have been executed • 74.8% of UAT Test Cases Passed • 3.4% Failed No Open Priority 1-High/Non-Cosmetic DD&I Defects • 0 1-High/Non-Cosmetic Defects have been opened to date Open Priority 2-Normal/Medium DD&I Defects have been analyzed and • 3 Severity 2-Normal/Medium Open defects categorized with the Consortium as either “go-live dependent” or “production • 9 Severity 3-Normal/Low Open defects deferral” workarounds have been communicated and a plan exists to resolve outstanding Defects by an agreed-upon date Resolved Defects have been documented in the change control tool • 100% of defects are being recorded in JIRA Test results and summary reports have been completed • Test results and summary reports have been submitted to-date and will continue to be submitted until UAT Exit CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 12
Application Readiness Open CalSAWS Core UAT Defects Defect Status • 12 Open CalSAWS Core Defects • All Defects at this time targeted for resolution prior to exiting UAT Open CalSAWS Core UAT Defects Open CalSAWS Core UAT Defects By Status BY Priority 6 6 5 4 3 3 2 3, 25% 2 1 1 0 2-Normal/Medium ASSIGNED DEVELOPMENT IN SYSTEM TEST Total 3-Normal/Low COMPLETE DEVELOPMENT 9, 75% CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 13
Conversion Readiness Conversion Readiness QA Generated Golden C-IV Converted Data Sets #0 - #6 100% 10 C-IV Epics Completed 100% C-IV Conversion Functional Design Approved and Developed 100% CalACES Master Conversion Plan Approved 100% Required Materials to Security Administrators in preparation for 1A Distributed 100% Mock Conversions #1, 2, & 3 for Cutovers 1A & 1B Completed 100% EDBC Match and Recon Completed 100% Perform mitigation strategies for Mock Conversion Cutover Risk during GDS #7 (Target 8/15/2021) 15% Complete Conversion Cutover 1A County Prep (Target 8/30/2021) 0% Complete Conversion Cutover 1B Go Live (Target 9/27/2021) 0% Converted Data Test (CDT) C-IV Converted Data Delivered for Conversion Data Test Execution 100% Conversion Data Test Completed 100% Conversion Readiness Risks and QA Watch List Risk 249 – C-IV Cutover Activities are At-risk of Completing within the Planned 84-hour window Not On =14 Days NS G Y R C Complete Started Schedule Late Late Mock Conversion – A dress rehearsal of the activities that are planned to be executed during cutover. These exercises allow the project to capture baseline information on the duration of these task and confirm order of operation. This will provide the project a picture on how it is doing against the window for cutover. CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 14
Conversion Readiness C-IV Conversion Cutover Window Risk Risk– The execution of the C-IV Conversion Cutover activities in the 3 Mock Conversions have not resulted with the overall End-To-End performance completing at or within 84 hours. Mock Conversion #3 (in July) completed in approx. 87 hours (or 2.5 hours past the 84 hours window). The team has logged Risk #249 and will work with the Users Begin various project teams on cutover activities to mitigate the risk of executing cutover activities past the 84 hours and Day thus impacting County Users start to their business day in CalSAWS. Legends: Thursday Friday Saturday Sunday M onday Expec ted Baseline 9/23/21 10:00 PM 9/23/21 11:00 PM 9/24/21 12:00 AM 9/24/21 10:00 AM 9/24/21 11:00 AM 9/24/21 12:00 PM 9/24/21 10:00 PM 9/24/21 11:00 PM 9/25/21 12:00 AM 9/25/21 10:00 AM 9/25/21 11:00 AM 9/25/21 12:00 PM 9/25/21 10:00 PM 9/25/21 11:00 PM 9/26/21 12:00 AM 9/26/21 10:00 AM 9/26/21 11:00 AM 9/26/21 12:00 PM 9/26/21 10:00 PM 9/26/21 11:00 PM 9/27/21 12:00 AM Performs Per Plan 9/23/21 6:00 PM 9/23/21 7:00 PM 9/23/21 8:00 PM 9/23/21 9:00 PM 9/24/21 1:00 AM 9/24/21 2:00 AM 9/24/21 3:00 AM 9/24/21 4:00 AM 9/24/21 5:00 AM 9/24/21 6:00 AM 9/24/21 7:00 AM 9/24/21 8:00 AM 9/24/21 9:00 AM 9/24/21 1:00 PM 9/24/21 2:00 PM 9/24/21 3:00 PM 9/24/21 4:00 PM 9/24/21 5:00 PM 9/24/21 6:00 PM 9/24/21 7:00 PM 9/24/21 8:00 PM 9/24/21 9:00 PM 9/25/21 1:00 AM 9/25/21 2:00 AM 9/25/21 3:00 AM 9/25/21 4:00 AM 9/25/21 5:00 AM 9/25/21 6:00 AM 9/25/21 7:00 AM 9/25/21 8:00 AM 9/25/21 9:00 AM 9/25/21 1:00 PM 9/25/21 2:00 PM 9/25/21 3:00 PM 9/25/21 4:00 PM 9/25/21 5:00 PM 9/25/21 6:00 PM 9/25/21 7:00 PM 9/25/21 8:00 PM 9/25/21 9:00 PM 9/26/21 1:00 AM 9/26/21 2:00 AM 9/26/21 3:00 AM 9/26/21 4:00 AM 9/26/21 5:00 AM 9/26/21 6:00 AM 9/26/21 7:00 AM 9/26/21 8:00 AM 9/26/21 9:00 AM 9/26/21 1:00 PM 9/26/21 2:00 PM 9/26/21 3:00 PM 9/26/21 4:00 PM 9/26/21 5:00 PM 9/26/21 6:00 PM 9/26/21 7:00 PM 9/26/21 8:00 PM 9/26/21 9:00 PM 9/27/21 1:00 AM 9/27/21 2:00 AM 9/27/21 3:00 AM 9/27/21 4:00 AM 9/27/21 5:00 AM 9/27/21 6:00 AM 9/27/21 7:00 AM 9/27/21 8:00 AM 9/27/21 9:00 AM Risk, Impac t, Mitigation Critical Path / Cutover Hours 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 Milestone - C-IV Cutover Start Run C-IV Batc h Sc hedule Tec hOps / Imaging / PRT / Etc . Exec ute C-IV Transformations Run LA CalSAWS Batc h Sc hedule Execute Limitied Batch Sched ule Exec ute C-IV LA Dependent Transformations DBA Ac tivities Performance Tune DBA Related Activities Perform Interfac e Partner Validation EDBC Match Reporting Performance Tune Ac c enture CalSAWS Smoke Test Run Concurrent w / Click-Thru Exec ute County Clic k-Thru (Spec ial URL) Review Go/ No-Go Criteria and Assess for Go-Live Milestone - 1B- C-IV Cutover Complete Mitigation Action Items: 1. Execute GDS #7 Conversion Run* on Production AWS environments. 2. Remove Stage Gate Reviews from the Critical Path saving 1.5 hours. 3. Limit the LA CalSAWS Batch Schedule to only those jobs necessary for the Migration of C-IV to CalSAWS. 4. Execute Smoke Testing in parallel with County Click-Thru saving 1 hour. Note: GDS #7 Conversion Run is executing from Monday, Aug. 2nd thru Aug. 15th CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 15
Integration Readiness Interface Partner Testing QA Established CalSAWS Connectivity with New State Partners – 1 of 1 server completed - CMSP 100% Establish CalSAWS Connectivity with C-IV County Interface Partners 100% Execute Interface Testing with C-IV County Partners 100% Execute Interface Testing with State Partners – 50 of 53 test scripts passed [Target -> 07/31/2021) 94% Execute Interface Testing with Consortium Partners 100% Confirm CalSAWS cloud server production cutover connectivity EBT (FIS) (Target TBD) 0% Confirm configuration changes to support transactions out of CalSAWS have been deployed to the Partner Production 0% Environment – CalHEERS (Target 09/13/21) Confirm configuration changes to support transactions out of CalSAWS have been deployed to the Partner Production 0% Environment – eICT (CalWIN) (Target 08/16/21) Development & System Test Establish CalSAWS Connectivity with BenefitsCal APIs (Application Programming Interfaces) – Test Environment 100% Establish CalSAWS Connectivity with BenefitsCal APIs (Application Programming Interfaces) – Production (Target -> 08/19/2021) 95% Integration Readiness Risks and QA Watch List QA – Completion of Interface Testing Notes: • CalSAWS Consortium Interface Partners include: EICT (CalWIN) & OCAT • CalSAWS State Interface Partners include: CalHEERS, WIS, WDTIP (OSI), MEDS (DHCS), EBT (FIS), CMIPS (OSI), CDSS (DSS), CCSAS (DCSS), and CMSP Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 16
Interface Partner File Exchange Test State Partners State Partners SERVER AND WEB SERVICE CONNECTIVITY INTERFACE TESTING TARGET COMPLETION STATE PARTNER TARGET COMPLETION DATE STATUS STATUS DATE CalHEERS June 10, 2021 Complete July 16, 2021 Complete CCSAS (DCSS) N/A N/A August 5, 2021 Completed CDSS (DSS) N/A N/A July 16, 2021 * Behind Schedule CMIPS (OSI) N/A N/A July 2, 2021 Complete CMSP June 14, 2021 Complete July 9, 2021 Complete EBT (FIS) June 16, 2021 Complete July 31, 2021 * Behind Schedule MEDS (DHCS) N/A N/A August 3, 2021 Complete WDTIP (OSI) N/A N/A July 31, 2021 Complete WIS (DSS) N/A N/A July 31, 2021 Complete Notes: • CDSS (DSS): SCR CA-231585 submitted to update the EBT Fraud Alert processing logic in the CalSAWS. Code delivery targeted for August 2, 2021, for testing to proceed on August 4, 2021 • EBT (FIS): Meeting scheduled on August 4, 2021 between CalSAWS Consortium, CalSAWS build team, and OSI to discuss the implementation timeline proposed by FIS. Teams are actively conducting Network and SFTP testing between August 4th an August 12th. CalSAWS has proposed a production FIS-EBT AWS cloud network cutover weekend of August 14th. Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 17
Application/Technical Readiness: Imaging QA Functionality Functional Development, System Test, and Release Deployment Completed 100% Performance Testing Hyland Platform Performance test (cycles 1 & 2) 100% Performance and Stress Testing for CalSAWS Go-Live Completed (Target → 09/17/2021) 60% Security Testing Penetration Penetra Testing for Hyland Platform (Target → 09/21/2021) 10% Images Migration Upload, restore, and transform database transfer – UAT Primary Option (Target → 07/26/2021) 100% Upload, restore, and transform database transfer Production Primary Option (Target → 08/23/2021) 30% DMS (Database Migration Service) Transfer – Backup Option (Target → 08/12/2021) 50% Disaster Recovery Test (coincides with CalSAWS DR Test) (Target → 08/15/2021) 0% Verify All Documents Migrated from Legacy Storage Device (Target → 08/29/2021) 100% Upload Image Legacy Data to Hyland Production (Target → 08/13/2021) 100% Ship Image Legacy Data to Hyland AWS 100% Distribute CIT for Counties to install Webscan Kit and Virtual Printer 100% User Acceptance Test (UAT) - Imaging Execution of User Acceptance Test (UAT) 100% Pass Rate of User Acceptance Test (UAT) (Target 08/27/2021) 98% Technical Readiness Risks and QA Watch List Risk 248: Delays in the C-IV Image Migration Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 18
Application/Technical Readiness: Imaging Risk 248: Delays in the C-IV Image Migration Target Due Date 09/03/2021 Mitigation • July 26 – C-IV Imaging Database to be Converted, Upgraded, and ready for image validation in UAT • July 29 – All Images to be Available for Validation in UAT Environment • Aug 16 – Sync Process to be validated and in place for Production • Aug 23 – C-IV Production Imaging Database to be Converted, and Upgraded in Production • Sept 3 – Initial Production Validation to be Completed Imaging Workstream Summary Workstream Status Updates Legacy Images Export • All Legacy Images have been shipped to the Hyland AWS Datacenter C Process Legacy Images • All Legacy Images have been uploaded to Hyland Production and are ready to be C Import Process validated in the UAT Environment. Database Transfer - • Database transformation process is complete C UAT Database Transfer - • Database export transferred to Hyland G PROD • Transformation steps in progress Validation Process • Validation Criteria is being defined NS (8/16-9/3) • Validation SMEs are being identified Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 19
Application/Technical Readiness: Imaging UAT UAT Status On Schedule • On-Track for CalSAWS Imaging Admin • Imaging Admin Execution was completed June 28 – July 2, 2021 • Imaging Admin UAT Retest was completed July 19 – July 23, 2021 • The following table provides a summary of the UAT execution results where the team has overall completed 100% of the test scenarios with a 98% pass rate • Retest scheduled for the 1 remaining test case Aug 9 – 20, 2021 Total CalSAWS UAT Not Executed In Progress Passed Failed Open Defects Scenarios Imaging ADMIN Execution 59 0% (0) 0% (0) 98% (58) 2% (1) 4 Exit Criteria Status 100% of UAT Test Cases have been executed • 98% of Imaging UAT Test Cases Passed • 2% Failed No Open Priority 1-High/Non-Cosmetic DD&I Defects • 0 1-High/Non-Cosmetic Defects have been opened to date Open Priority 2-Normal/Medium DD&I Defects have been analyzed and • 1 Severity 2-Normal/Medium Open defects categorized with the Consortium as either “go-live dependent” or “production • 3 Severity 3-Normal/Low Open defects deferral” workarounds have been communicated and a plan exists to resolve outstanding Defects by an agreed-upon date Resolved Defects have been documented in the change control tool • 100% of defects are being recorded in JIRA Test results and summary reports have been completed • Test results and summary reports have been submitted to-date and will continue to be submitted until UAT Exit CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 20
Application/Technical Readiness: Imaging UAT Status On Schedule Defect Status • 4 Open CalSAWS Imaging UAT Defects Open Imaging UAT Defects By Open Imaging UAT Defects By Status Priority 1 1 1 1 1 0.8 0.6 25% 0.4 0.2 0 0 2-Normal/Medium 0 3-Normal/Low 75% Total CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 21
Application/Technical Readiness: Ad Hoc Reporting and Analytics C-IV Scope QA Functionality Replatform Development Completed 100% Established CalSAWS Connectivity with Ad Hoc Reporting – EDR Reporting 100% Established CalSAWS Connectivity with Ad Hoc Reporting – SFTP Reporting 100% 40 County System Test (Target 09/05/2021) 97% Establish CalSAWS Connectivity with Ad Hoc Reporting – APEX Reporting (Target 06/25/2021) 25% Application/Technical Readiness Risk and QA Watch List Establish CalSAWS Connectivity with Ad Hoc Reporting – APEX Reporting The established architecture for ad-hoc and EDR implemented to support C-IV and migrated as part of CalSAWS DDI has been identified for security hardening. Accenture Security has submitted a POAM (Plan of Action and Mitigation). Awaiting approval from Consortium Security to proceed with the network changes. Security teams are working through potential solutions to address identified items and mitigate the security risk. Changes must be made across a 177 sites. This affects ad-hoc JDBC access and access to CalSAWS from Unmanaged Laptops at Managed Counties over Extranet. Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 22
Application/Technical Readiness: Analytics C-IV Scope Performance Testing QA 40 County Performance Test (Target 09/21/2021) 75% Security Testing Penetration Testing for Platform (Target Date 09/14/2021) 0% Technical Readiness Risks and QA Watch List Risk 236: The scaling of Analytics Dashboards for 58 Counties may have an impact on system performance Risk mitigation items: • Action Item #1: The documentation of Analytics Performance Management plan - Completed May 2020 • Action Item #2: Demonstrate stability in batch job run times and adherence to 6am batch window over a 5– 10-day period - Completed Jan 2021 • Action Item #3: Initial batch performance testing (Analytics only) for 40 counties – In Progress through August 2021 Current Run Time Estimates based on current 40 county performance testing results: Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 23
Technical Readiness: Operations Monitoring QA Review Infrastructure services in ecosystem for coverage (Target 08/30/2021) 25% Rollback planning in Conjunction with Cutover Planning* (Target 07/30/2021) 95% *Rollback Plan has been sent to Consortium for review. Pending Consortium review. Incident Management Conduct table-top activities with support teams (Target 08/30/2021) 0% Disaster Recovery Exercise Disaster Recovery Test (Target 8/22/2021) 0% Batch Operations Batch Operations Review (Target -> 9/17/2021) 49% Performance Testing Online Performance and System Test for Cloud Enablement Completed 100% Complete Online Performance and Stress Testing (Target 9/24/2021) 60% Complete Batch Performance Testing (Target -> 9/03/2021) 70% Technical Readiness Risks and QA Watch List Risk 237: Scaling of Batch for 58 Counties Risk 240: The scaling of CalSAWS Production Operations, including Batch Operations, to provide 40 and 58 County Support Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 24
Technical Readiness: Operations Customer Service Center Readiness Call Center QA All SCRs in Production: 100% Transfer batch jobs required for Authentication and self-service functionality 100% Update IVR Contact Flows to leverage CalSAWS data 100% Regression Test of entire Contact Center solution and CalSAWS integration points 100% Cutover Activities (Target 9/27/2021) 0% Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 25
Technical Readiness: Operations Risk 240: Scale Batch Operations to provide 40 & 58 County support Target Due Date 9/17/2021 Mitigation Process: • M&O Services Plan is currently in review and process changes have been instituted Organization: • Training / change management planning in process • Organization realignment tracking to plan Communications: • Feedback on current notifications is being included in design of updated notifications with joint design sessions progressing as planned • Pilot phase for new notifications is scheduled to start week of 8/9 Continuous Improvement: • Design of control totals to provide more business insight into batch operations are in progress and slightly ahead of schedule • Additional automated alerts to provide updates on batch execution are also in design Batch Operations Exit Criteria: • Batch Schedule updated and verified for C-IV processes – complete and verified during regression test • Updated procedures incorporated into the M&O Service Plan • Batch Operations organization realigned under Production Operations • Real Time Batch Monitoring in place • Updated batch notifications deployed to production • Targeted control totals and automated alerts developed and implemented CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 26
Technical Readiness: Performance Risk 237: Scaling of Batch for 58 Counties - Batch Performance Remediation • Daily batch is processing within the required batch window with additional changes to be implemented this week • Changes in the Daily cycle are being retested within the monthly cycles with additional performance changes planned for each cycle • Performance test environment is being upgraded to GDS6 with additional batch cycles planned for this week on the new data • 39 open remediation items • 25 are ready for retest this week. 13 items are in development and 1 item is being assessed. Work items are prioritized based on overall impact to the batch window Priority Batch Cycle Status* Areas of Focus Path to Green Green Target Date 1 Daily EBT Writer performance (CA-229084) Refactoring of EBT processing to be 8/11/2021 implemented this week to be retested by 8/9. 2 End of Month Super Trigger (CA-213387) Retest leveraging the Daily cycle 8/13/2021 performance improvements and incorporate additional Super Trigger improvements. 3 First Business Day Daily batch job performance Retest leveraging the Daily cycle 8/18/2021 performance improvements. 4 High Volume Central print (CA-231594) Server mount changes to be verified in 8/23/2021 Forms Batch server mount for bundling next Daily cycle run scheduled for 8/6. performance Central print changes to be delivered and verified by 8/6. 5 10-day Cutoff Retest leveraging the Daily cycle 8/27/2021 performance improvements. 6 Main Payroll Issuance thread performance (CA- Retest with the Daily cycle performance 8/31/2021 230579) improvements and incorporate the Issuance Thread performance changes. * Status is tracking toward cycle completion within targeted batch window CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 27
Technical Readiness: Performance Test Overview Identity Access Management (ForgeRock) ForgeRock (IAM) Services Invoked in all performance cycles CalSAWS - Core BenefitsCal API Analytics Imaging Platforms CalSAWS Online End to End Simulates functional Each platform runs Simulates functional workload against calsaws- isolated tests with in the workload against calsaws- core and supporting four walls of the platform core and supporting services (e.g analytics) + services (e.g analytics) Benefitscal functional Performance Incremental Workload Cycles workload • Workload 1= CalSAWS application 40 county load + ForgeRock • Workload 2 = Workload 1 + On Request reports (Analytics) workload • Workload 3 = Workload 2 + CalSAWS (BenefitsCal) Portal API workload • Workload 4 = Workload 3 + Imaging API workload CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 28
Technical Readiness: Performance CalSAWS + ForgeRock 40 County Online Performance Testing Performance Test Cycles • Cycle 1 – June 01 – Jun 30 (Complete) • Initial Golden Data Set with 40 County Data Load • Cycle 2 – July 30 – Aug 13 • Final Golden Data Set with 40 County Data Load and Fixes from Cycle 1 • Cycle 3 – August 23 – September 24 • Regression Test Cycles with fixes from Cycles 1 & 2 Performance Test Plan for each Cycle: • Execute in Production-like Performance environment with initial Golden Dataset available. • Run frequently-used transactions that generate the highest volumes in Production • Simulate usage of ~500 transactions per second (TPS). • Simulate ~14,000 users' login in a period of 20 minutes. Load of ~700 users per minute. As the load test is running, 200 users log on and off to simulate user session activity in Production. • The 14,000 users will be comprised of ~7,000 LA county users from ISD Test Active Directory and ~7,000 C-IV county users from ForgeRock user store • Execute 3 Load tests to confirm consistency • A “8-hour” Endurance test to ensure stability * ForgeRock is utilized throughout all testing scenarios Exit Criteria • Simulated Online transaction load of CalSAWS volume at peak hours meets SLA requirements with final Golden Dataset #6 • Performance results are successful and meet contractual SLAs – Online (Load and Endurance tests) CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 29
Technical Readiness: Performance CalSAWS + ForgeRock 40 County Online Performance Test – Cycle 1 Cycle 1 - Performance Test Findings with Golden Dataset #3 : • Users failing to login above load of ~11,000 users • Defect - Tune long running queries executed on Homepage screen. • Fix deployed with 21.07 release • Defect – Duplicate primary keys in Phone Number • Indexes recreated to resolve the issue. • The SQL changes from tested defect fix have helped to resolve the Users login issue. The test executed at expected load of ~500 TPS. • The exceptions and transaction level performance detail analysis is in progress. Cycle 1 Performance test results: Category SLA SLA Met % & Avg. Server Response SLA Met % & Avg. Server Response Time Time (Endurance Last hour) Peak - 98% [
Technical Readiness: Infrastructure Infrastructure QA Production Development and Conversion Environments Set up and Delivered 100% Technical Infrastructure Releases 19.10 - 20.11 Completed 100% SD-WAN & Extranet Network enablement for all C-IV Counties Completed 100% Kiosk/FACT Solution: Push software update to Kiosks at CalSAWS Counties (Target 09/15/2021) 0% Environment Deployment for Cloud Enablement and Provide Support Completed (Target 09/22/2021) 90% Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 31
Technical Readiness: Identity Access Management Functionality QA Functional Development Completed 100% System Test Completed for the Core CalSAWS, Imaging, Call Center 100% Hot-Hot Architecture Deployed 100% SIT BenefitsCal Release 1 ForgeRock Integration 100% Performance Stand Alone platform weekly testing 100% Performance Testing Integrated with BenefitsCal Release 1 100% Performance and Stress Testing as part CalSAWS Go-Live Completed (Target 09/21/2021) 60% Security Testing Penetration Testing Execution / Agreed-upon remediations (Target Date 09/14/2021) 0% C-IV User Migration Customer Service Center Completed 100% Learning Management System Completed 100% Mock Conversion #3 County Validation 1A & 1B Completed 100% CIV User Migration (remaining applications) as part of cutover 1A (Target 08/28/2021) 0% C4Yourself User Migration (Target 09/23/2021) 0% C-IV User Enablement 50% CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 32
Technical Readiness: Identity Access Management User Enablement Topics Category Topic Resolution Status Target Due Date 1. Add banner to login page to guide users 2. Replace text reading "User Name or Email" in login C-IV First-time County feedback that users will be unsure box with "User Name" Complete 30-Jul-21 Login which account to use to for first time login 3. Update the look and feel of the ForgeRock Non- Production environment Users that are re-activated but do not log Update security policy to provide users 60 more days Security Policies in are disabled again each night via Complete 30-Jul-21 to log in upon re-activation security policy 1. CIT distributed informing Delegated Administrators County feedback that Delegated of user status change capabilities Delegated Administrators will be unsure how to re- 2. Each County has a delegated Admin Complete 4-Aug-21 Administration enable identities 3. Scheduled two Delegated Administrator training sessions The Implementation and Change Management Counties do not have sufficient Teams are preparing a full log-in process guide, as Communication In Progress 13-Aug-21 communication/information well as a Help Hints for logging in Infographic to be distributed to the C-IV Counties ~3,000 C-IV users have multiple accounts; Implementation Team to include in the login guide may not be able to provide unique email Communication that if a user has two logins in C-IV, they need In Progress 13-Aug-21 address on first time log in and could lead separate email addresses in ForgeRock to inability to access system ServiceNow "Login Issues" workflow does not route to County Delegated ServiceNow team assessing workflow updates to Help Desk Administrators trained to resolve them; route to Tier 1 County Delegated Admin groups In Progress 18-Aug-21 Escalations instead, routes to Tier 3 Application Teams before Tier 3 groups to Tier 3 teams not staffed to handle Tier 1 migration ticket loads CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 33
Technical Readiness: Security Application Security QA CalSAWS Scans/Remediation Completed 100% YBN Scans/Remediation – Scan Completed/Remediation in progress 100% Penetration Testing Signed with 3rd party to conduct Testing - Completed 100% Penetration Testing as part CalSAWS Go-Live Completed (Target Date: 09/21/2021) 30% Penetration Testing Execution / Agreed-upon remediations (Target Date 09/14/2021) 0% Security Hardening Database Hardening (Target Date 08/15/2021) 83% Unmasked Non- Production Environments Hardening (Target Date 08/27/2021) 13% Vulnerability Management (Security Ops) Ecosystem Coverage (Target Date 08/31/2021) 95% Patching Cadence (Target Date 08/01/2021) 100% Security Plan SSP Review/Approved 100% Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 34
Training Readiness Training Plan QA C-IV Master Training Plan Approved & QA Assessment Completed 100% Training Environment Transition Plan Approved 100% Consortium Training Plan for C-IV Migration Approved 100% Imaging Training Plan Approved 100% Training Materials C-IV Migration WBTs (29), Quick Guides (63), and Reference Guides (27) Completed 100% Training Materials Loaded into the LMS 100% 109 Training Materials Reviewed by QA – Job Aids, Quick/Reference Guides, WBTs 100% Training Development 153 Training SCRs Implemented in Releases 19.11 - 21.07 and Verified by QA 100% Training Delivery LMS Configured in the Cloud 100% Early Training Users Added into the LMS 100% LMS unique logins (Target 09/24/2021) 40% ServiceNow Updated to Accommodate LMS Requests from the C-IV Counties 100% Imaging Train the SME Sessions Hosted (Target 8/26/2021) 0% Early Training Supported and Completed (Target 8/27/2021) 50% Analytics Training/Engagement w/the C-IV Counties Completion (Target 9/15/2021) 60% General Training Supported & Completed (Target 9/24/2021) 0% Future Training Metric - % WBT Completion by County during General Training Future Training Metric – LMS unique Logins during General Training Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 35
Change Readiness Communications QA C-IV Change Management Plan Approved & QA Assessment Completed 100% Task Management Plan for Training, Change Management and Implementation completed 100% IMAGING: Created a Change Management Plan (including Communications Plans & Stakeholder Engagement 100% Plans) IMAGING: Completed Change Management Plan 100% Submitted FCED Plan for Change Management 100% Achievements Communications Targeted Topics • 13 Infographics Distributed • 10 Presentations Delivered (350 • 3 News Blasts Distributed attendees per sessions) Change Network Champions User Readiness Surveys • 9 Monthly Meetings Conducted (+350 • 4 Surveys across 14,000+ Users attendees each meeting) Administered (56% average response rate) Just in Time Demonstrations • T-3 Week Change Readiness • 5 Demos Delivered (2.5-3 hours each, Assessment Survey planned for average 900 attendees per sessions) 09/13/21 Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 36
Implementation Readiness Service Desk QA LRS ServiceNow and C-IV CA SDM Ticket Systems Migrated to Consortium-owned SNOW 100% ServiceNow Training for County Helpdesks and Gainwell Completed 100% Distribute enhanced communications to County Help Desks regarding transition from C-IV instance of ServiceNow to CalSAWS 0% instance Host the County Prep Phase Command Center (Target -> 09/23/2021) 0% Command Center Staff created as Fulfillers and trained in ServiceNow reporting (Target -> 08/24/2021) 30% System Operations C-IV Counties Access to the Sandbox Environment Provided 100% Engage the Counties on Staff Profile/Security Administration updates (Target -> 08/27/2021) 80% Production Deployment Plans C-IV Deployment Readiness Plan Approved & QA Assessment Completed 100% County Implementation Points of Contact Identified 100% Conducted Walkthrough of Initial Implementation Readiness Packet with C-IV Counties 100% Finalize Post-Deployment Approach 100% Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 37
Post Deployment Support Communication Activity Approach # Summary Medium Target Audience Team Planned Date Customer 1. Go-Live Packet CIT All C-IV Users September Engagement Security County Prep Phase Command AWS 2. Administrators, IPOCs, Implementation 8/30/21 – 9/23/21 Center Support Connect PPOCs, TPOCs Post-Deployment Support 3. Orientation for Office-Level Virtual Call Office-Level Support Implementation September Support Customer Post-go-live Meeting with 4. Virtual Call Advocates/CBOs Engagement / 9/27/21 - 10/8/21 Advocates/CBOs BenefitsCal 5. County Stakeholder Call Virtual Call County Stakeholders Implementation 9/27/21 - 11/5/21 Daily High-Priority Issue 6. Email IPOCs, PPOCs, TPOCs Implementation 9/27/21 - 11/5/21 Summary Update CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 38
BenefitsCal Readiness CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 39
BenefitsCal Readiness Project Milestones The BenefitsCal project monitors overall operational readiness through four (4) key milestones. These milestones are significant events in development and readiness toward the September 2021 Go-live for the BenefitsCal system for C-IV counties. Additional milestones will be defined for the November 2021 readiness for YBN replacement (LA County). Evaluation Decision Key Milestones Status Go? Notes Start Date Date Yes, ST One partner defect failing 20 Report eNOA reports (CSPM-30827), select Exit System Test G 07/16/21 07/23/21 test cases in progress for multi devices (20%) and language (40%). Exit UAT G 08/20/21 09/03/21 On-track Production Dry Run NS 08/06/21 08/13/21 Not started Production Green-Light NS 09/06/21 09/10/21 Not started Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 40
Application Readiness Design QA Design Deliverables Approved 100% System Security Plan (SSP) Approved 100% Development Completed 100% of Increment 1 and 2 100% Completed 100% of Increment 3 100% System Test Execute System Test – Increment 1 100% Execute System Test – Increment 2 100% Execute System Test – Increment 3 98% User Acceptance Test (UAT) Execution of User Acceptance Test (UAT) (Target 08/20/21) 53% Pass Rate of User Acceptance Test (UAT) (Target 08/20/21) 90% Usability Test Complete Usability Test for Release 1.0 ( Target 08/20/21) 85% Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 41
Application Readiness System Test Status and Exit Pass Rate Target 90% Pass Rate Actual 95% System Test Complete Date: July 16, 2021 System Test Remaining Items • One partner defect failing 20 eNOA reports (CSPM-30827) • One partner defect failing 6 Appointment test cases (CSPM- 30877) • SIT validation in progress for the following: code drop 2- ADA multi-devices (20%), multi-language (40%) 60% CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 42
Application Readiness Independent Test Status and Exit BenefitsCal Independent Test Results Code Drop 1 • 81 scripts executed • 91% passed of completed scenarios Code Drop 2 • 107 scripts executed • 62% passed of completed scenarios Not In Test Cycle Total Scenarios Executed Progress Pass Fail Blocked 0% 0% 91% 9% 0% BenefitsCal Independent Test (Code Drop 1) 81 (0) (0) (74) (7) (0) 33% 2% 41% 24% 0% BenefitsCal Independent Test (Code Drop 2) 164 (53) (4) (67) (40) (0) Exit Criteria Status • 100% of Independent Test Cases Executed for Code Drop 1 All SIT test cases within the test execution plan are executed, unless mutually agreed upon • 91% pass rate by Deloitte, Consortium, at Consortium’s discretion. • 65% of Independent Test Cases Executed for Code Drop 2 • 62% pass rate There are no Severity 1 (High) or Severity 2 (Medium) defects in unresolved status. • No 1-High/Non-Cosmetic Defects have been opened to date Defects with severities- Severity 3 (Low) or Severity 4 (Cosmetic) in unresolved status have a • 33 2-Normal/Medium Defects are open mutually agreed upon plan for resolution by Deloitte, Consortium. • 21 3-Low Defects are open All test cases in Atlassian X-ray JIRA Plugin are passed for the functionality under test, unless • 100% of defects60% are being recorded in JIRA mutually agreed upon by Deloitte, Consortium. Test results are documented. • Test results and summary reports have been completed CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 43
Application Readiness UAT Status and Exit • On-Track for BenefitsCal • Week 7 of 12 • 30 User Acceptance Testers, 7 SMEs, representing 18 counties scheduled for Week 7 of 12 • Overall completed 53% of the test scenarios with 90% pass rate User Acceptance Test (UAT) Exit Criteria Status • 53% of UAT Test Cases Executed All UAT test cases within the test execution plan are • 90% of UAT Test Cases passed executed successfully, at Consortium’s discretion • 10% Failed Note: These numbers are significantly different from last week. Blocked (89) scenarios were included in the pass percentage calculation but is no longer included in that bucket. • 0 Severity 11-High/Non-Cosmetic Open Defect There are no Severity 1 (High) or Severity 2 (Medium) • 33 Severity 2-Normal/Medium Open defects (10 recommended for rejection and defects in unresolved status. 9 available in UAT waiting to be tested as of 08/02/21, 6 depending on partners) • 53 Severity 3-Normal/Low Open defects (19 recommended for rejection and 9 Defects with severities- Severity 3 (Low) or Severity 4 available in UAT waiting to be tested as of 08/02/21) (Cosmetic) in unresolved status have a mutually agreed • 1 Severity 4-Cosmetic Open defects (1 available in UAT waiting to be tested as of upon plan for resolution by Deloitte, Consortium. 08/02/21) All test cases in Atlassian X-ray JIRA Plugin are passed for • 100% of defects are being recorded in JIRA the functionality under test, unless mutually agreed upon by Deloitte, Consortium. 60% • Test results and summary reports have been submitted to-date and will continue Test results are documented. to be submitted until UAT Exit CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 44
Integration Readiness Design QA Design Deliverables Approved 100% Development Completed 100% of Increment 1 and 2 100% Completed 100% of Increment 3 100% System Test Execute 100% of partner test cases within System Test 100% Interface Partner Test Execute 100% of the Interface Partner Testing 100% Partner 1-High 2-Med 3-Low 4-Cosmetic TOTAL ForgeRock 0 11 2 2 15 CalSAWS 0 11 6 0 17 Hyland 0 1 0 0 1 BenefitsCal 0 0 0 0 0 33 TOTAL 0 23 8 2 (+13 from last week) Integration Readiness Risks and QA Watch List Risk 235 – The BenefitsCal Project Release 1.0 may be delayed due to integration with the CalSAWS Interface QA – Coordination and confirmation with GetCalFresh QA – Testing outcomes toward exit criteria Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 45
Technology Readiness Security Testing QA Conduct SAST code vulnerability scans (SAST) ( Target 08/13/21) 92% Conduct DAST code vulnerability scans (DAST) ( Target 08/13/21) 92% Pre-production launch third-party web application penetration testing (Target 08/13/21) 40% Performance Testing Execute 100% of Performance Test – Cycle 1 100% Execute 100% of Performance Test – Cycle 2 100% Execute 100% of Performance Test – Cycle 2 0% Performance Test Test Case Start Date End Date Status Execution Design Status 22 of 22 test Cycle 2 07/19/21 07/30/21 Complete cases designed 6 of 20 test Cycle 3 08/09/21 08/20/21 Not Started cases designed Infrastructure Start penetration test 100% Complete penetration testing (Target 08/27/21) 0% Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 46
Conversion Readiness Provide extract of the CBO and Admin users on UAT Conversion Readiness QA Create Pre-Production user accounts within ForgeRock for BenefitsCal admin users 100% Provide extract of the CBO and Admin users on UAT 100% Provide extract of regular users (non-CBO and non-admin users) account data from C4Y system on UAT 100% Converted Data Test 100% of conversion test scripts are written, loaded, and ready to execute 100% Execute Conversion Data Testing Rounds 1-2 100% Execute Conversion Data Testing Round 3 (Target 08/27/21) 0% 100% 8 of 8 Design Deliverables Approved 30% NS Not G On Y =14 Days C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 47
Training Readiness Training Plan QA Demo System for UAT training 100% Training Materials Deliver Training Quick Guides (Target 08/13/21). 100% Deliver Training Videos (Target 08/13/21). 90% Deliver Training Admin Guide (Target 08/13/21). 30% Training Delivery Deliver training for Tier 1 support (Target 09/17/21) 0% Deliver training for Tier 2 support (Target 09/17/21) 0% Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 48
Implementation Readiness Service Desk QA Customer Experience (CX) Dashboards (Target 08/27/21) 49% Plan service desk support and communications 100% County Service Desk staff to confirm sufficient capacity to support BenefitsCal users 100% Finalize incident intake (i.e., diagnostic questions) for Service Desk workers 100% Disseminate BenefitsCal training materials to Service Desk staff (Target 08/13/21) 0% System Operations Plan system operations support and communications (Target 08/06/21) 99% Confirm Command Center schedule and communication of said schedule 100% Define incident management process 100% Contingency Planning (Target 09/03/21) 100% Prod Deployment Plans Confirm that BenefitsCal Portal monitoring is in place (Target 09/03/21) 50% Confirm Consortium reviewed/approved the BenefitsCal cutover and BenefitsCal rollback plans (Target 09/17/21) 0% Conduct Production Cutover Mock Run (Target 09/10/21) 0% Decide to proceed with BenefitsCal Production Launch (Go-No Go Decision) (Target 09/21/21) 0% Launch BenefitsCal into production (Target 09/27/21) 0% Implementation Readiness Risks and QA Watch List QA – Finalization of Help Desk handoffs Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 49
Change Readiness QA Communications Review and approve go-live communications 100% Draft go-live communications 100% Confirm that staff have participated in preparatory meetings and trainings (Target 09/20/21) 0% Distribute go-live communications (Target 09/27/21) 0% Partner Readiness Confirm correspondence (mail and email) includes an updated reference to new BenefitsCal System (Target 09/03/21) 60% Confirm other Systems have updated their URL to point to the new BenefitsCal (Target 09/27/21) 20% Messages Messages Delivery Post Email Open Rate Emails Opened Attempted Delivered Rate C4Y New Benefits System (1) email 417,882 389,643 93.2% 23.7% 92,337 C4Y New Benefits System (2) email 417,882 396,010 94.7% 24.8% 98,171 Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 50
Central Print Readiness CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 51
Central Print Readiness Design QA Master Implementation Plan Approved 100% Requirements Verification Session Complete 100% Development Print File Parameters Identified 100% Print Centers Established 100% Configuration Load (Target 08/26/2021) 50% Test Connectivity Between Print Centers and Fulfillment Platform 100% 2D Barcode Testing 100% SoCal Print Center Component Testing 100% Existing Print Center Component Testing (Target 08/15/2021) 85% Connectivity Between CalSAWS and Central Print 100% Disaster Recovery Test (Target 08/20/2021) 25% Production File Test (Target 08/20/2021) 10% Training and Implementation Maintenance and Operations Plan Approved 100% Supply Readiness (Target 8/25/2021) 50% Training Readiness* (Target 8/20/2021) 90% Training Delivery (Target 9/24/2021) 0% Not On =14 Days NS G Y R C Complete Started Schedule Late Late CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 52
Central Print Testing Summary Status Test Comments Purpose: Verify the fit of envelope windows prior to purchase Complete Functionality - Envelope Fit File(s) Used: Test files which included print using each envelope type including changes from Release 21.07 Functionality - Release Purpose: Verify the print layout and envelope fit for printed items that were 21.07 (Participant to Complete changing with CalSAWS Release 21.07 Accenture’s system File(s) Used: Test files which included print changes from Release 21.07 testing) Purpose: Network penetration test for the Gainwell SFTP as a service connectivity in Security – Penetration Test Complete use and Facility Inspection Print Center on site inspection of physical security at the three print centers Purpose: Verify connectivity from CalSAWS AWS to Gainwell Print Centers including Complete Connectivity – Test File encryption and decryption of a test file File(s) Used: Small test print file Purpose: Verify connectivity from CalSAWS AWS to Gainwell Print Centers including Connectivity – Production In Progress encryption and decryption at volume Files File(s) Used: Full set of Los Angeles County print files from a production batch cycle Purpose: Verify the ability of the Central Print solution to complete a representative Performance - In Progress night’s production files in a time period that would result in same day mailing Performance and Load File(s) Used: Full set of Los Angeles County print files from a production batch cycle Purpose: Verify the ability of the Central Print solution to meet functional Functionality – requirements related to printing such as using PDF’s, insertion of return envelopes, In Progress Performance and Load etc. File(s) Used: Full set of Los Angeles County print files from a production batch cycle Purpose: Verify the ability of the Central Print solution to re-route a file to an Disaster Recovery – In Progress alternate print center Performance and Load File(s) Used: One of the Los Angeles County print files from a production batch cycle CalSAWS | August 9, 2021 Implementation Readiness Packet and Dashboard 53