Implementation and Monitoring - Louth County Council

 
CONTINUE READING
Implementation and Monitoring - Louth County Council
Chapter 14
Implementation and
Monitoring
14 IMPLEMENTATION AND MONITORING
14.1 INTRODUCTION
The Draft Plan sets out the Council’s vision      Council may carry out a variation of the
and strategy for the sustainable                  Plan from time to time, where it is
development of the County over the                considered such amendments are
period 2021-2027. Included within the             warranted.
Draft Plan are a broad range of policy
objectives that provide a framework for           14.2 LEGISLATIVE BACKGROUND
the future growth and development of the          The Planning and Development Act 2000
County.                                           (as amended) provides under:
The Council has a statutory obligation to         Section 15 (1) that it shall be the duty of a
implement the provisions of the Draft Plan        Planning Authority to take such steps
and is committed to securing its                  within its powers as may be necessary for
objectives.                                       securing     the    objectives      of   the
The Council will continue to occupy a             Development Plan, and;
leadership role in progressing and                Section 15 (2) that the Manager of the
securing the policy objectives of the Draft       Planning Authority shall, not more than 2
Plan thereby enhancing economic                   years after the making of a Development
prosperity, promoting Drogheda and                Plan, give a report to the members of the
Dundalk as Regional Growth Centres,               authority on the progress achieved in
facilitating the transition to a low carbon       securing the objectives referred to in
County, promoting the County’s unique             subsection (1).
cultural, built and natural heritage,
developing communities, integrating land          14.2.1 Urban Area Plans and
use and planning as well as, ensuring                    Local Area Plans
sustainable use of natural resources.             An important driver of the Plan Strategy is
In providing this leadership role, the            to bring policies to a more detailed local
Council will foster a collaborative               level through Urban Area Plans and Local
approach with citizens, stakeholders,             Area Plans. The strategic and broad-
sectoral      interests,   and     adjoining      ranging policy objectives of the Draft Plan
authorities to achieve collective support         provide a general framework, but not
and successful implementation of the              necessarily the detailed treatment
Plan.                                             required for significant proposals in
The implementation of the Plan is also            certain areas.
dependant on a number of factors                  Urban/Local Area Plans will be prepared
including political support, Council funding      for the following settlements:
and the availability of capital from other             Drogheda – A Joint Urban/Local
sources. Due to the uncertain economic                    Area Plan is to be prepared in
climate as a result of COVID 19, the                      collaboration with Meath County
provision of funding may present a                        Council; and
challenge in the years ahead.                          Dundalk.
The Plan will also be regularly reviewed to       Local Area Plans will be prepared for the
assess progress, and to determine where           following settlements:
amendments are required. Therefore, the
                                                       Ardee and Dunleer.

                        Draft Louth County Development Plan 2021-2027

                                                                                                  14-1
14.3 SOURCES OF FUNDING
       14.3.1 Public Funding
       Funding for the various projects,                 The Climate Action Fund which aims to
       programmes and policy objectives of the           support initiatives that contribute to the
       Draft Plan will be dependent on capital           achievement of Ireland’s climate and
       funding from the government. The                  energy targets will leverage investment by
       Council’s own funds will also be allocated        public and private bodies. The Disruptive
       under the annual budget adopted by the            Technology Innovation Fund aspires to
       Elected Members each year. As previously          support Ireland’s innovation ecosystem
       referred to, the availability of funding over     and to drive collaboration between public
       the lifetime of the Plan is uncertain and         bodies, research, Small and Medium sized
       will be dependent on the medium and               Enterprises’ and industry.
       long term impacts of COVID 19 on the              Additional National and EU level
       national and international economy.               programmes include the Re-building
                                                         Ireland Action Plan, the Neighbourhood
       14.3.2 Development
                                                         Scheme, National Lottery Facility Funding,
              Contributions                              as well as other funding mechanisms
       It is considered reasonable that                  available from the various Government
       contributions be paid towards Local               Departments and other agencies.
       Authority investment in the provision of
       infrastructure and services by developers         14.3.4 Private Funding
       who benefit from such provision. The              14.3.4.1 Public Private Partnerships
       Council may, when granting planning               A Public Private Partnership (PPP) involves
       permission under Sections 34, 48 and 49           a partnership agreement between the
       of the Planning and Development Act (as           public and private sector for the delivery
       amended), attach conditions requiring the         of specific projects relating to public
       payment of financial contribution(s) in           services    and     infrastructure.    Such
       respect of public infrastructure and              approaches ensure a commitment to
       facilities, benefiting the development.           funding due to interlinked public and
       Details of such contributions are set out in      private assistance and aims at ensuring
       the Louth County Council Development              the most economically efficient manner of
       Contributions Scheme 2016-2021, which             development. Education, local services,
       came into effect on the 19th September            health, housing, public transport, roads,
       2016. This contribution scheme will be            solid waste, water/wastewater and other
       reviewed during the life of the Plan.             public services can benefit from the
       14.3.3 Additional Funding                         approach of a PPP.
              Sources                                    Other partnership approaches will be
       The Rural and Urban Regeneration and              pursued      with    state    and    public
       Development Funds arising from the                organisations. Such approaches can
       National Development Plan, in support of          involve/several different types of projects,
       the National Planning Framework and               including:
       other national strategies are available to          Design and build;
       support the implementation of Regional              Design, build and operate;
       and Local authority development plans               Design, build, operate and finance,
       and Local Economic and Community Plan                  and
       objectives.                                         Operating contracts.

                               Draft Louth County Development Plan 2021-2027
14-2
14.3.4.2   Bonds
To secure the satisfactory completion of         The Council will enforce the planning
development on a site which has been             legislation   to   ensure    that  the
granted planning permission, the Council         environmental, visual and economic
will require the giving of a cash bond to        development of the County is not
ensure     the     completion     of   the       jeopardised by inappropriate and
development to the satisfaction of the           environmentally damaging development
Council. This is covered under Section           and to ensure that the policies and
34(4)(g) of the Planning and Development         objectives of the Plan are implemented
Act 2000 (as amended). This bond may be          and adhered to.
requisitioned in part or in full where the
development has not been satisfactorily          14.4 MONITORING AND
completed and used by the Council to                  IMPLEMENTATION
ensure the satisfactory completion of the
                                                 The Planning Department of the Council is
development. This cash bond shall not be
                                                 the lead section responsible for
released until the estate is taken in
                                                 monitoring and implementing the Plan,
charge. The value of the cash bond will be
                                                 mainly      through     its   development
reviewed during the lifetime of the Plan
                                                 management function. However, it is
and each year thereafter each year in
                                                 important to note that this Plan co-
accordance with the Wholesale Price
                                                 ordinates the work and objectives of not
Index for the Construction Industry.
                                                 only of the Planning, Infrastructure and
14.3.4.3   Phasing                               Economic Development directorate but
                                                 also the Corporate and Emergency
The timely provision of supporting
                                                 Services, Operations, Housing, as well as
infrastructure and community facilities in
                                                 the Finance and Water Service
tandem with the development of areas is
                                                 directorates.
important in ensuring high quality,
sustainable development takes place. All         In some instances, the implementation of
large-scale development proposals shall          certain policy objectives may be the
be phased having regard to the delivery of       responsibility of external bodies such as
both physical and social infrastructure and      Irish Water, National Parks & Wildlife
orderly development.                             Service, Fisheries Ireland, National Roads
                                                 Authority,      Transport    Infrastructure
14.3.5 Enforcement                               Ireland, and the Environmental Protection
The Council has extensive powers under           Agency etc. The Planning Authority will
the Planning and Development Act 2000            work in collaboration with the relevant
(as amended) to take enforcement action          external body to assist in ensuring the
where unauthorised development has               implementation of the relevant policy
occurred, is occurring or where permitted        objective.
development has not, or is not being             The Draft Plan policy objectives are
carried out, in compliance with the              specific, measurable, achievable and
planning permission granted.                     realistic. However, a number are set
                                                 within a longer timeframe, thus they may
                                                 not be fully implemented over the lifetime
                                                 of this Draft Plan.

                       Draft Louth County Development Plan 2021-2027
                                                                                               14-3
On-going monitoring shall take account of        The 2-year Review shall monitor and
       residential development permitted in             assess the overall implementation policy
       settlements designated under the                 objectives including those pertaining to
       settlement hierarchy in order to ensure          the Core Strategy and the environmental
       compliance      with    the    population        objectives as set out in the Strategic
       allocations defined by the Core Strategy,        Environmental Assessment. Information
       and to adjust the approach to permitting         utilised to carry out the 2-year review
       development proposals in instances               shall come from a variety of sources
       where Core Strategy objectives are not           including other directorates, external
       being met.                                       bodies, the Central Statistic Office and the
                                                        Eastern and Midlands Regional Assembly,
       14.5 STATUTORY TWO YEAR                          who update their baseline data on a four-
            REVIEW                                      yearly cycle.
                                                        The Department are currently reviewing
       In accordance with Section 15 (2) of the
                                                        the Development Plan Guidelines and it is
       Planning and Development Act 2000
                                                        anticipated that these may contain more
       (amended), the Plan will be reviewed after
                                                        detail on the types of indicators to be
       2 years and a progress report will be
                                                        utilised in relation to monitoring and
       prepared by the Chief Executive on the
                                                        review of development plans thus the
       achievements in securing the policy
                                                        exact content of the statutory Two Year
       objectives of the Plan at that time.
                                                        Review will be determined at the time of
                                                        writing.

                              Draft Louth County Development Plan 2021-2027