ENERGY SECURITY BOARD INTERIM RELIABILITY RESERVE - Response to submissions on Consultation Draft Interim Reliability Measure Rule July 2020 ...

Page created by Don Tucker
 
CONTINUE READING
ENERGY SECURITY BOARD INTERIM RELIABILITY RESERVE - Response to submissions on Consultation Draft Interim Reliability Measure Rule July 2020 ...
ENERGY SECURITY BOARD
INTERIM RELIABILITY RESERVE

      Response to submissions on
Consultation Draft Interim Reliability
                      Measure Rule
                           July 2020

                                     1
Contents
1.     Introduction........................................................................................................ 3
2.     Summary of issues raised in submissions and ESB’s response ................... 4
       2.1     Process undertaken by the ESB in recommending Interim Measures ......... 4
       2.2     Impact on affordability/prices from the Interim Reliability Reserve .............. 5
       2.3     Changes to the reliability standard .............................................................. 6
      2.4      Modelling of costs and benefits of the Interim Reliability Reserve ............... 6
      2.5      The role for out of market resources ........................................................... 8
      2.6      The role for multi-year contracting ............................................................ 10
      2.7      Interim Reliability Reserve interaction with other reforms .......................... 12
      2.8      Operation of the Interim Reserve .............................................................. 14
      2.9      Transparency of the Interim Reserve Costs .............................................. 15
      2.10 Interaction between RRO and Interim Reserve ......................................... 16
      2.11 Other interim reliability reserve issues ...................................................... 17
C Abbreviations and Technical Terms .................................................................. 18

                                                                                                                                2
1. Introduction
The Energy Security Board (ESB) has developed a set of changes to the National
Electricity Rules (Rules) to implement the temporary out-of-market capacity reserve
agreed to by Ministers at the March 2020 COAG Energy Council Meeting. On the 12th
May 2020 the ESB published draft Interim Reliability Measure Rules for consultation. 1

The ESB received non-confidential submissions from sixteen organisations, including
from regulators, industry groups, generators and customer groups:
   • Generators/retailers: AGL, CS Energy, EnergyAustralia, Engie, Ergon Energy
       QLD, ERM, Hydro Tasmania, Infigen, Origin Energy, Snowy Hydro, Stanwell
   • Industry bodies: Australian Energy Council
   • Consumer groups: Australian Aluminium Council, Major Energy Users, Energy
       Users Association of Australia, QLD Electricity Users Network.
   • Regulators: ACCC

The submissions are published on the ESB’s website. 2

They are summarised, together with the ESB’s response, in Chapter 2. The ESB, AEMC,
AER and AEMO have subsequently worked together to consider issues raised in
submissions and develop a set of recommended Rules to be submitted to Energy
Ministers.

1    Energy Security Board, Consultation on the Draft National Electricity Amendment (Interim Reliability Measure)
     Rule 2020, May 2020. Available at: http://www.coagenergycouncil.gov.au/publications/consultation-draft-
     national-electricity-amendment-interim-reliability-measure-rule-2020.
2    See above.
                                                                                                                     3
2. Summary of issues raised in submissions and ESB’s response
2.1 Process undertaken by the ESB in recommending Interim Measures

Respondents             Comments                                                                ESB response

AGL, CS Energy, EUAA,   Consultation on the Interim Reliability Reserve was not best            In undertaking the review between November 2019 and March 2020, the ESB
MEU, Origin Energy      practice, lacked public consultation prior to the decision to proceed   drew on the feedback from other recent reviews conducted by the AEMC and
Stanwell, QEUN          with the Reserve and Interim Reliability Measure, and the ability to    AER. The ESB also undertook informal consultation with a range of key
                        critique the ESB’s modelling and conclusions.                           stakeholders including the following organisations, the Australian Energy
                                                                                                Council, the Clean Energy Council, the Energy Users Association of Australia,
                        The implementation of the Interim Reliability Reserve undermines        Grattan Institute, the Public Interest Advocacy Centre.
                        a number of recent processes focused on energy reliability and
                        security in which consultation was broad and transparent.               The proposed rule changes are intended to be an interim solution that targets
                                                                                                resources that are not generally incentivised to participate in the market (ie
                        The QLD Electricity Users Network requests a list of stakeholder        respond to five-minute prices). This interim solution is proposed to be in place
                        engagement that was undertaken in preparing the response to             while the ESB and Market Bodies continue to work on longer term
                        COAG Energy Council.                                                    arrangements to improve reliability and security in a more enduring way. This
                                                                                                will be developed and implemented as a part of the Post 25 Work Program (eg
                                                                                                Two Sided Markets; resource adequacy mechanisms)

                                                                                                The Interim Reliability Reserve is intended to address the recent increased
                                                                                                use of the Reliability and Emergency Reserve Trader mechanism in some
                                                                                                regions. The Interim Reliability Reserve should allow AEMO to increase the
                                                                                                pool of resources available for out of market reserves and put downward
                                                                                                pressure on the cost of procuring these reserves when needed.

                                                                                                Jurisdictional oversight will continue to play an important role in ensuring that
                                                                                                the risk of unnecessary amounts of emergency reserves being procured is
                                                                                                minimised.

                                                                                                                                                                                    4
2.2 Impact on affordability/prices from the Interim Reliability Reserve

ACCC, MEU, ERM      Concerned that these reliability measures will impose additional    The Interim Reliability Reserve is intended to address concerns about the
                    costs on consumers, particularly small consumers.                   increased reliability risk following the retirement of a number of baseload
                                                                                        generators (including the Hazelwood, Northern, Munmorah, Wallerawang and
                    Any marginal change in unserved energy from improved reliability    Anglesea power stations) and the subsequent increased use of the Reliability
                    in the wholesale market will make little difference to how          and Emergency Reserve Trader mechanism in some regions of the NEM.
                    consumers see reliability, yet the proposed change will
                    significantly increase the costs they see.                          Analysis undertaken by ACIL Allen for the ESB indicates that a jurisdiction that
                                                                                        just meets the current 0.002% standard could expect load shedding one in
                    The costs to consumers for the dispatching of RERT during           every three years on average – absent an intervention mechanism such as the
                    summer of 2019/20 were higher than the market price cap and so      RERT.
                    if the new reliability levels had applied for summer 2019/20 then
                    the process would have led to consumers paying more than was        The volume of reserves activated over recent years reflects the operational
                    necessary.                                                          requirements and actual lack of reserve conditions at the time.

                    The Interim Reliability Measure Rule is not one reform but three,   The Interim Reliability Measure will not necessarily result in an increase in the
                    all attempting to solve the same issue. ERM Power questions the     amount of reserves activated and could reduce the total cost to consumers of
                    need to adopt all of these arrangements at once, potentially        the reserves that are activated relative to what would have been procured
                    increasing costs for consumers at a time when many households       through short and medium notice RERT.
                    and businesses are facing serious financial and social pressures
                    as a result of the COVID-19 pandemic.                               The Interim Reliability Reserve should allow AEMO to increase the pool of
                                                                                        resources available for out of market reserves, putting downward pressure on
                                                                                        the cost of procuring these reserves when needed.

                                                                                        AEMO will need to consider the relative total costs to consumers and will be
                                                                                        subject to comprehensive reporting requirements. Jurisdictional oversight will
                                                                                        continue to play an important role in ensuring that the risk of unnecessary
                                                                                        amounts (and costs) of emergency reserves being procured is minimised.

                                                                                        The ESB will shortly issue a consultation paper on the changes required to be
                                                                                        made to the Retailer Reliability Obligation (RRO), in which it will discuss the
                                                                                        concerns about the interactions between the Interim Reliability Reserve and the
                                                                                        RRO.

                                                                                                                                                                            5
2.3 Changes to the reliability standard

Respondents             Comments                                                              ESB response

AEC, CS Energy, EUAA,   Several stakeholders questioned the 1 in 10-year standard and its     ACIL Allen undertook analysis that underpinned the ESB’s recommendations
MEU, Origin Energy,     alignment with community expectations.                                to COAG Energy Council. Their analysis found that the current reliability
Stanwell                                                                                      standard may not represent the most economically efficient trade-off between
                        The decision to increase the standard is also inconsistent with the   the cost incurred during load shedding and the cost of resources that would
                        findings of other recent reviews in this area.                        prevent load shedding (where Reliability and Reserve Emergency Trader
                                                                                              (RERT) offers were used as the best available indicator of the cost of
                                                                                              demand response and certain assumptions about the Value of Customer
                                                                                              Reliability). The analysis provides support for an interim tighter standard
                                                                                              under certain scenarios, including when there is sufficient demand response
                                                                                              at a cost that is lower than the cost of load shedding. An interim out of market
                                                                                              solution was chosen by the ESB as this approach would allow for greater
                                                                                              visibility and understanding of the availability and cost of demand side
                                                                                              resources in the NEM.

2.4 Modelling of costs and benefits of the Interim Reliability Reserve

Respondents             Comments                                                               ESB response

ACCC, ERM               The modelling results for NSW show that the costs of meeting the       In the case of the Residential Only scenario, the benefit-cost analysis
                        interim reliability standard in NSW are higher than the benefits.      showed that the costs exceeded the benefits of targeting 0.0006% USE in
                                                                                               the NSW simulation. However, the supply of demand side was relatively
                                                                                               limited in this scenario (an arbitrary decision to use existing AEMO
                                                                                               contracted levels). In the Reference case (higher value for VCR) and in the
                                                                                               two scenarios where the availability of demand side was doubled
                                                                                               (Expanded RERT), the benefits of targeting a USE of 0.0006% exceeded
                                                                                               the costs. There is nothing to suggest that the existing volume of RERT
                                                                                               contracts contracted by AEMO exhausts the supply of demand side in the
                                                                                               NEM. The analysis shows that the with realistic volumes of demand side
                                                                                               (evidenced by AEMO’s ability to contract under the RERT), the benefits of a
                                                                                               USE target between 0.0005 and 0.001% of USE exceeds the costs.

                                                                                                                                                                             6
AEC, ERM, MEU   ACIL Allen’s modelling fails to consider the classes of customer most       ACIL Allen ran two types of customer analysis – all excluding agriculture
                likely to be subject to involuntary load shedding.                          and only residential customers (having the lowest USE over the 1-3 hour
                                                                                            outage period considered). They analysed the outages using the granular
                The Value of Customer Reliability indicates on average what                 VCR values that underpin the AER’s headline ‘anytime’ values, which are
                customers would be prepared to pay for lower levels of all supply           very averaged. The ACIL Allen analysis using VCR for residential only
                interruptions, which tends to be heavily influenced by recent events in     customers (lowest average VCR value) supports a USE target of between
                their respective distribution system, forty-one percent of respondents      0.0005% and 0.001%, especially where higher demand side participation is
                to the AER’s process indicated a willingness to pay of zero.                available.

                                                                                            ACIL Allen recognises that using average VCR values for consumers has
                                                                                            limitations. Ideally, the market price cap would be raised to the point where
                                                                                            individual customers responded based on their own circumstances.
                                                                                            However, in the current environment, it is a reasonable approach
                                                                                            considering that the market operates over a shared network.

                                                                                            Willingness to pay surveys have inherent limitations as they require
                                                                                            respondents to provide a response and these responses can be swayed by
                                                                                            a variety of influences, including recent experience. It might be argued that
                                                                                            customers with recent experience are more likely to provide an accurate
                                                                                            assessment of their willingness to pay. Similarly, it is not unusual that
                                                                                            customers with little or no disruption experience, should report a willingness
                                                                                            to pay of zero (why pay for something that in their mind they already have).

ERM             The closer the unserved energy forecasts are to meeting the interim         The statement that the closer unserved energy forecasts are to meeting the
                reliability standard, the less expensive it will be for reserve contracts   interim reliability standard, the less expensive it will be for reserve contracts
                to bring reliability back to within the interim standard, therefore the     to bring reliability back to within the interim standard, is true in the following
                ACIL Allen modelling approach is unstable.                                  sense:

                                                                                            •   The lower the demand, the less supply needed to meet that demand

                                                                                            •   Supply meeting the lower demand would be the lowest cost (assuming
                                                                                                a competitive market)

                                                                                            •   The resulting market clearing price will be lower

                                                                                            •   Supply meeting demand will be less expensive where there is less
                                                                                                demand to meet

                                                                                            It is also true that the greater the volume of demand side available, the less
                                                                                            expensive it will be to meet the interim standard. ACIL Allen developed four

                                                                                                                                                                                 7
scenarios to provide a range of outcomes. The results were consistent and
                                                                                             there is no indication of instability.

ERM                 The 2019 ESOO forecast does not include the supply provided by the       The existence or otherwise of the reserve generators in South Australia has
                    South Australian emergency diesel generators which have been             no effect on the broader analysis. The analysis used the AEMO ESOO data
                    transferred to market participants and will be bid in using the normal   to construct realistic USE data sets as an input to the analysis.
                    market process in the future.                                            Incorporating additional supply and removing USE from the data sets would
                                                                                             have been counter to the purpose of undertaking modelling with significant
                                                                                             volumes of USE.

ERM, CS Energy      The modelling does not provide an adequate assessment of costs           Undertaking modelling on the costs and benefits to support the COAG
                    and benefits, in large due to the use of ESOO 2023-24 projections        Energy Council decision was generic and time independent. It was not
                                                                                             designed to find the cost of meeting a particular standard in a particular
                                                                                             region in 2023-24 (the data set used in the modelling). The purpose of using
                                                                                             the 2023-24 data set was to easily extract realistic half hourly outage
                                                                                             sequences for the analysis. 2023-24 was the year modelled in the 2019
                                                                                             ESOO that had the highest USE numbers. ACIL Allen used this year as it
                                                                                             provided the richest data set to develop a series of simulations based on
                                                                                             the three states that provided significant levels of USE.

2.5 The role for out of market resources

Respondents         Comments                                                                  ESB response

Infigen             Given that the Market Price Cap is less than the average value of         The Interim Reliability Reserve is an interim measure designed to be a last
                    customer reliability, procuring demand response through the RERT          resort mechanism, intended to avoid distortions to the market and
                                                                                              minimise the cost of procuring out of market resources. The framework
                    therefore may allow for (arguably) more orderly load shedding, without
                                                                                              builds on the current Victorian jurisdictional derogation for RERT
                    needing to increase the Market Price Cap for all participants.            Contracting.

Hydro Tasmania                                                                                The framework will allow AEMO to procure reserves if the ESOO (or any
                    In response to the previous Enhancement to the RERT rule change in        update) forecasts that the Interim Reliability Measure will be exceeded.
                    2018, Hydro Tasmania presented a set of guiding principles:               AEMO will be allowed to enter multi year reserve contracts for up to three
                                                                                              years if the Interim Reliability Measure is exceeded for at least two years
                             1.   a last-resort response to maintain reliability;             including the first financial year.
                             2.   designed to ensure efficient market responses, and avoid    The proposed rule changes are intended to target resources that are not
                                  crowding out investment;                                    generally incentivised to participate in the market (ie respond to five-

                                                                                                                                                                            8
3.   activated rarely;                                            minute prices) and ultimately lower the cost of procuring out of market
                                                                                         resources.
                       4.   offered by truly additional capacity only (must be ‘out of
                                                                                         This interim solution is proposed to be in place while the ESB and Market
                            market’ reserves);                                           Bodies continue to work on longer term arrangements to improve reliability
                                                                                         and security in a more enduring way. This will be developed and
                       5.   transparent in nature (with a clearly understood process     implemented as a part of the Post 25 Work Program (eg Two Sided
                            for procurement, enactment and timely publication of         Markets; resource adequacy mechanisms)
                            RERT outcomes); and
                                                                                         AEMO will also need to consider the relative costs to consumers, including
                       6.   administered at the lowest-possible cost.                    whether a single year contract is more cost effective than a multi-year
                                                                                         contract (see below), and will be subject to comprehensive reporting
              Hydro Tasmania consider that the above guiding principles will most        requirements that will support an AEMC review that is required to be
              likely be met under the proposed rule change.                              undertaken by July 2023.
                                                                                         AEMO will also need to request single year as well as multi-year contracts.
Snowy Hydro   The Reliability and Emergency Reserve Trader (RERT), the current           Based on a suggestion by stakeholders (eg AGL), this will minimise
                                                                                         distortions to the wholesale market as it will encourage demand response
              out of market reserve, is a function conferred on AEMO to maintain
                                                                                         providers to consider becoming participants in the wholesale market where
              power system reliability and system security using reserve contracts.      possible, including through the new in-market demand response
              RERT in the Short-Notice or Medium-Notice RERT are currently               mechanism.
              appropriate tools which allows AEMO to purchase reserves 7 days and
                                                                                         Jurisdictional oversight will continue to play an important role in ensuring
              10 weeks respectively from the anticipated shortfall, providing an
                                                                                         that the risk of unnecessary amounts of emergency reserves being
              appropriate trade-off for maintaining sufficient levels of unserved        procured is minimised.
              energy in the NEM. There is a recognition that there is a trade-off with
              cost per unit of the Short-Notice RERT and Medium-Notice RERT
              being more expensive than a multi-year out of market capacity
              reserve.

              The out of market capacity reserve mechanism is instead non market
              based and suffers a complete lack of transparency in both the
              tendering phase and also the cost of using the service, which is
              ultimately borne by customers. The existing market design can be
              relied upon to support reliability in the long-term with the NEM.

AGL           Considers that there may be some benefits of multi-year contracting
              such as creating a greater pool of potential suppliers with more diverse
              system capabilities, along with potentially lower cost solutions when
              the contract is required for multiple years.
              However, these benefits need to be considered in the context of the
              impacts multi-year RERT contracting may also pose to the market, and
              ultimately to customers through possible impacts on other market
              participants and wholesale markets. These risks must be carefully
              managed, particularly measures to prevent over procurement of

                                                                                                                                                                        9
emergency reserves, avoiding indirect costs such as market
                    inefficiencies, and preserving the RRO framework.

                    There should be an expectation that out-of-market resources be made
                    in-market resources where feasible. This will reduce the distortions of
Stanwell            out-of-market procurement on the energy market.
                    Out-of-market procurement has the potential to cause distortions in the
                    energy market, including the withdrawal of generation capacity from
                    the market, dampen investment signals in capacity to participate in the
                    market, inefficient risk allocation, and unpredictable reliability reserve
                    costs
EUAA                The EUAA has also consistently argued in favour of in-market
                    measures to achieve the reliability standard as an over reliance on out-
                    of-market measures can lead to unnecessary costs for consumers
                    from unnecessary or inefficient procurement of RERT.
ERM                 A tighter reliability standard with an unchanged MPC and the potential
                    for out-of-market contracts of three years will possibly drive any new
                    supply to the RERT rather than moving into the market. This is likely to
                    distort the market as new entrants may try to strike a RERT contract
                    with AEMO rather than participate in the market and unscheduled
                    reserves (like demand response) could prefer to wait to strike a
                    contract with AEMO than to commit to participating in the market.
                    The proposed approach contains no change to the reliability settings. It
                    is therefore unclear how any new capacity would be expected to make
                    a return in the market and instead, potential new suppliers may be
                    incentivised to stay out of the market in the hope of striking a multi-
                    year contract with AEMO. As this capacity remains “off-market”, this
                    would also increase wholesale market prices above that which would
                    have otherwise occurred, further increasing costs to consumers.

2.6 The role for multi-year contracting

Respondents         Comments                                                                     ESB response

Infigen             While RERT is a valuable tool, we consider that in-market                    ACIL Allen undertook analysis that underpinned the ESB’s recommendations
                    mechanisms should be pursued where possible, such as Infigen’s               to COAG Energy Council. Their analysis found that the current reliability
                    proposed Operating Reserves framework. Infigen is concerned that             standard may not represent the most economically efficient trade-off between
                    procuring RERT resources for multiple years risks drawing valuable           the cost incurred during load shedding and the cost of resources that would

                                                                                                                                                                           10
demand response resources out of the market. This prevents their         prevent load shedding (where Reliability and Reserve Emergency Trader
                    use in delivering lower-cost retail contracts.                           (RERT) offers were used as the best available indicator of the cost of demand
                                                                                             response and certain assumptions about the Value of Customer Reliability).
                    We recommend that AEMO should only procure RERT to the extent            The analysis provides support for an interim tighter standard under certain
                    level needed to meet the agreed standard in the upcoming year,           scenarios, including when there is sufficient demand response at a cost that
                    with those contracts extended for multiple years only if AEMO has a      is lower than the cost of load shedding. An interim out of market solution was
                    high degree of confidence it will be required and AEMO can               chosen by the ESB as this approach would allow for greater visibility and
                    demonstrate that expected costs will be lower to consumers relative      understanding of the availability and cost of demand side resources in the
                    to sequential contracts.                                                 NEM.The Interim Reliability Reserve is an interim measure designed to be a
                                                                                             last resort mechanism, intended to avoid distortions to the market and
Aluminium Council   The Council has concerns that Contract terms of up to three years,       minimise the cost of procuring out of market resources. The framework builds
                    proposed in the Paper, are still only short term in the context of the   on the current Victorian jurisdictional derogation for RERT Contracting.
                    investment cycle for aluminium smelters, so do not fundamentally
                    offer a change to a smelters long term strategy. Also, three years       The proposed solution has been put in place to take care of immediate
                    does not provide a sufficient time horizon for investment which          reliability concerns. This interim arrangement will cease in March 2025. The
                    would allow smelters to enhance their capability to provide              proposed solution builds on interim arrangements in place for Victoria but can
                    additional services to the market.                                       now apply to other regions. This interim arrangement, along with the RRO,will
                                                                                             be reviewed by the AEMC in 2023. At the same time, the ESB and Market
Hydro Tasmania      It is integral that longer-term contracting for RERT is only             Bodies are currently working on longer term arrangements to improve
                    undertaken if clear and enduring reliability gaps are identified. The    reliability and security in a more enduring way. This will be developed and
                    paper suggests longer-term contracting should occur where there is       implemented as a part of the Post 25 Work Program (eg Two Sided Markets;
                    capacity shortfall two years out of the three years. We consider this    resource adequacy mechanisms).
                    appropriate.                                                             The maximum period AEMO will be allowed to enter a multi-year reserve
                                                                                             contract for the Interim Reliability Reserve is three years, and this will only be
Snowy Hydro         A multi-year out of market capacity reserve is fundamentally             permitted when there is forecast Interim Reliability Exceedance in at least
                    contrary to the design of the NEM. Any out of market capacity            two of the three years including in the first year. As noted above, where
                    reserve should be intended as a last resort mechanism, to deal with      AEMO is considering entering into a multi-year reserve contract, AEMO must
                    instances of genuine market failure, and should be rarely used.          have regard to whether it is a more cost-effective option, compared to
                    Snowy Hydro therefore strongly oppose the contract terms of up to        procuring single year contracts over the same period. To enable this
                    3 years. There is only one market in the NEM and all regulatory          comparison, AEMO must request from providers in its tender process single
                    settings should be calibrated to incentivise participation in the        year and multi-year bids.
                    market.
                                                                                             For multi-year contracts, the maximum volume that can be procured by
ERM                 By tightening the reliability standard, the volume of any RERT           AEMO in any financial year in any region to meet the Interim Reliability
                    procured is also likely to be higher than it would have been under       Measure shall be:
                    the existing reliability standard. This means that any potential
                    efficiencies from multi-year contracts may be lost by the higher
                    volumes of reserves needed in order to meet the interim reliability
                    standard.

                                                                                                                                                                             11
Origin agrees AEMO should only be permitted to enter into multi-             -   on an annual basis, no more than is reasonably necessary to
Origin Energy
                    year contracts of up to three years in length where: the forecast                address the largest Interim Reliability Exceedance identified during
                    level of unserved energy exceeds 0.0006 per cent for two out of the              the period for which the contract would apply, and
                    three years; and the multi-year contract is more cost effective than
                    entering into shorter duration contracts covering the same period.           -   with respect to the total amount of reserve procured over the
                                                                                                     contract term, no more than reasonably necessary to secure
AGL                 Considers that there may be some benefits of multi-year contracting
                    such as creating a greater pool of potential suppliers with more                 reliability of supply in the relevant region.
                    diverse system capabilities, along with potentially lower cost
                    solutions when the contract is required for multiple years.
                    However, these benefits need to be considered in the context of the
                    impacts multi-year RERT contracting may also pose to the market,
                    and ultimately to customers through possible impacts on other
                    market participants and wholesale markets.

2.7 Interim Reliability Reserve interaction with other reforms

Respondents         Comments                                                                 ESB response

Infigen             Facilitating an active two-sided market, where both supply and           The proposed rule changes are intended to be an interim solution that targets
                    demand participate in price setting, will allow for more efficient       resources that are not generally incentivised to participate in the market (ie
                    outcomes and contribute towards the National Energy Objectives.          respond to five-minute prices). This interim solution Is proposed to be in
                                                                                             place while the ESB and Market Bodies continue to work on longer term
                    The ESB should fast track the Two-Sided Market workstream, which         arrangements to improve reliability and security in a more enduring way. This
                    should reduce the need for RERT interventions and may also avoid         will be developed and implemented as a part of the Post 25 Work Program
                    the need for the proposed Demand Response Mechanism (avoiding            (eg Two Sided Markets; resource adequacy mechanisms)
                    the need for centrally determined baselines, and providing options
                    for residential consumers currently excluded under that scheme).

Aluminium Council   The proposed mechanism will only be triggered if the Electricity
                    Statement of Opportunities (ESOO), indicates a requirement for at
                    least two of the following three years including the summer of 2020-
                    2021. At this stage, forecasts indicate that it does not appear likely
                    to be triggered, reducing the bankability of this mechanism.
                    Smelters seeking to recontract are facing difficult decisions,
                    especially under current economic conditions. The Council believes
                    the ESB should consider how it can expedite these Interim
                    Reliability Reserve Rules to increase certainty in the bankability of
                    this mechanism.

                                                                                                                                                                            12
Ergon Energy     We note that the proposed interim reliability reserve does not
                 appear to impose extra risks on the wholesale market or retailers,
                 except where contracted plant is dispatched in competition with the
                 energy only market requiring intervention pricing. Ergon Energy
                 Retail expects that investors in peaking plant or demand response
                 that is currently out-of-market will seek reserve contracts from
                 AEMO rather than compete in the wholesale market where the MPC
                 is too low to provide a sufficient return for higher-cost peaking plant.
                 This could entrench the need for the ‘interim’ reliability reserve and
                 lock the NEM into two markets - an energy only market and a
                 reserve capacity contract market. Should this occur, Ergon Energy
                 Retail is concerned how this scenario will be resolved in the ESB’s
                 post 2025 market design.

Hydro Tasmania   The RERT interacts with the market broadly and impacts on
                 incentives/signals for investment in future capacity/storage and
                 resources. The ESB should continue to be clear on the intent of the
                 RERT and ensure it does not distort other market processes or
                 negatively impact on future market design choices being considered
                 in the post 2025 work.

Snowy Hydro      The ESB should consider the recommendations from their
                 consulting report if there are any changes to the reliability standard
                 through the post 2025 market design. The ACIL Allen Consulting
                 report notes that if there is a need for a tighter reliability standard
                 through the current NEM market arrangements then this can be
                 achieved through changes to the market settings. This approach as
                 the paper notes is the “most economically efficient approach as it
                 allows the market to naturally clear based on price”

Origin Energy    The operation of the mechanism and AEMO’s reserve procurement
                 activities should be reviewed by 1 July 2023 as proposed, with a
                 view to sunsetting the mechanism at that time. This would be
                 consistent with the view that the Interim Reliability Measure is
                 intended to be temporary, noting further consideration is being given
                 to the need for other more enduring reforms to the NEM framework
                 under the ESB’s Post-2025 work program.
CS Energy        There is a risk that this mechanism will crowd out any potential
                 demand response participation in the Wholesale Demand Response

                                                                                            13
Mechanism, a mechanism that has a material cost associated with
                   its implementation next year.
                   It is unclear how this mandate of increased community appetite will
                   align with the ESB’s longer-term market reform program and
                   whether it will allow potential new frameworks to be considered
                   appropriately. For example, there is an apparent conflict with the
                   two-sided markets design initiative which seeks to explore a desire
                   for consumers to opt for lower reliability.

2.8 Operation of the Interim Reserve

Respondents        Comments                                                                ESB response

AEC                Supports obligation on AEMO to have regard to whether total             The maximum period AEMO will be allowed to enter a multi-year reserve
                   payments are likely to be lower than a number of shorter-term           contract for the Interim Reliability Reserve is three years, and this will only be
                   reserve contracts.
                                                                                           permitted when there is forecast Interim Reliability Exceedance in at least
                   Latitude for reserve contracts to address an interim reliability        two of the three years including in the first year. As noted above, where
                   exceedance across multiple regions.                                     AEMO is considering entering into a multi-year reserve contract, AEMO must
                   Suggested Drafting Changes - Proposes to limit the volume               have regard to whether it is a more cost-effective option, compared to
                   procured by AEMO to no more than necessary for each year.               procuring single year contracts over the same period.
                   Disagrees with Clause 3.20.6(d)(4) not being applicable and             For multi-year contracts, the maximum volume that can be procured by
                   believes it should remain or be incorporated in 11.xxx5(d)
                                                                                           AEMO in any financial year in any region to meet the Interim Reliability
Stanwell           Further consideration should be given to whether interim reliability    Measure shall be:
                   reserve costs could be reduced by procuring multi-region reserve
                   contracts that simultaneously address interim reliability                   -    on an annual basis, no more than is reasonably necessary to
                   exceedances across multiple regions, with costs shared                           address the largest Interim Reliability Exceedance identified during
                   appropriately across regions on a user-pays basis.                               the period for which the contract would apply, and
Origin Energy      Origin considers Clause 11.xxx.4(i) should be strengthened by
                   specifying that procurement volumes associated with a given                 -    with respect to the total amount of reserve procured over the
                   contract (single or multi-year) should be capped at the level                    contract term, no more than reasonably necessary to secure
                   reasonably required to address an interim reliability exceedance,                reliability of supply in the relevant region.
                   having regard to any other reserve contracts entered into over the
                   same period.                                                            AEMO will need to consider the relative total costs to consumers and will be
                                                                                           subject to comprehensive reporting requirements. The final rule requires
AGL                In addition to the requirement that a multi-year contract can only be
                   entered if that would be more cost effective than entering              AEMO to request single year reserve contract bids (where it also requests
                   successive single year contracts, we suggest that AEMO should
                   only enter into a multi-year contract with a provider when there is a
                                                                                                                                                                           14
material saving in costs compared to a shorter contract with that         multi-year bids) that should support AEMO’s ability to assess and
                   provider.                                                                 demonstrate the benefits of entering multi-year contracts.
ERM                Re Clause 11.xxx.4 (i) (2) – ERM’s interpretation is that clauses 2 (i)
                   and (ii) are in conflict. Clause 2(i) suggests that any contract should   Clause 11.xxx.4(g) - The rule changes do not prevent the use of reserves
                   have a volume limit no larger than the largest exceedance over the        located in one region helping a different region. If AEMO can lower the costs
                   course of the contract’s duration. While clause 2(ii) seems to            of procuring reserves by sharing these across multiple regions, then it is able.
                   impose a volume limit for each year. The consultation paper               This would be subject to jurisdictional agreement.
                   describes the intent of this clause is that for multi-year contracts
                   “with respect to the contract term, no more than reasonably               Clause 3.20.6(d)(4) is not applicable because it refers to a low reserve
                   necessary to secure reliability of supply in the relevant region.”        condition trigger which is not relevant to an interim reliability reserve.

                                                                                             Clause 11.xxx.4 (i) (2) (ii) now includes the words “in total” to remove some
                                                                                             concerns about apparent confusion. Clause 11.xxx.4 (i) continues to provide
                                                                                             the flexibility needed by AEMO with limitations – this flexibility is mitigated by
                                                                                             the transparency and reporting elements that are incorporated into the
                                                                                             Interim Reliability Reserve rule changes.

2.9 Transparency of the Interim Reserve Costs

Respondents        Comments                                                                  ESB response

Hydro Tasmania     Hydro Tasmania supports all reasonable opportunities to enhance           The final rule now includes Rule 11.xxx.4(j) which requires AEMO to request
                   transparency around the operation of the RERT (without                    bids for single year reserve contracts (in the event it seeks multi-year bids),
                   compromising commercially sensitive information).                         which will support AEMO’s ability to assess and demonstrate the benefits of
                                                                                             entering multi-year contracts.
                   Costs for retailers should be as predictable as possible. While we
                   acknowledge that it is only ex-post that RERT costs will be known,        During consultation stakeholders requested that the costs of multi-year
                   AEMO should aim to provide as much guidance as is reasonably              contracts and the Interim Reliability Measure should be more transparent. It is
                   practicable to retailers so that they can forecast likely RERT costs      important to note that AEMO already have an obligation to report on costs
                   and pass-throughs.                                                        under 3.20.6(d)(i) which will apply to the Interim Reliability Reserve. However,
                                                                                             the final rule now includes additional requirements on AEMO to provide final
Snowy Hydro        Any new RERT measures and triggers must include greater                   bid data annually to the AEMC that will assist the AEMC in conducting its
                   transparency, to improve the ability of retailers to explain the costs    review by July 2023.
                   and benefits of emergency reserves to consumers and the industry
                                                                                             As the arrangements are an interim measure and the requirement on the
                   more broadly.
                                                                                             AEMC to conduct a review by July 2023, the implementation of a
                                                                                             Transparency Review and Report by the AER is not necessary.
                   Stanwell requests transparent reporting on the procurement costs
Stanwell           associated with the interim reliability measures. This will ensure the

                                                                                                                                                                              15
costs incurred to meet a reliability standard tighter than that
                   recommended by the Reliability Panel are visible to all stakeholders.
EUAA               We think that a useful addition to the rules change would be a
                   requirement for the AER to undertake a Transparency Review and
                   Report in relation to the level of detail and transparency contained in
                   quarterly and annual AEMO’s RERT Reports. This is the same
                   concept as the Transparency Report proposed by the ESB to
                   enhance oversight and increase transparency in the ISP rule
                   changes.

MEU                The MEU considers that greater transparency through more
                   comprehensive and timely reporting by AEMO in relation to the
                   RERT (how much RERT was required, what was used, what its cost
                   was, how much RERT is contracted for more than 12 months, etc)
                   and by doing so will increase the transparency of the RERT
                   process.

Origin Energy      Origin is supportive of the additional reporting requirements
                   proposed under 11.xxx.5(d). However, AEMO should also be
                   required to outline the payments made for each contract entered
                   into under the Interim Reliability Measure, noting that is a
                   requirement for contracts procured under the RERT framework.

2.10 Interaction between RRO and Interim Reserve

Respondents        Comments                                                                   ESB response

AGL                As the Interim Reliability Measure may have contracts running until        Clause 11.xxx.4 AEMO to have regard to the RERT principles, which aim to
                   2024/25, there are several years of overlap where a forecast breach        minimise impacts on customer bills and market distortions, and the potential
                   may be driving both retailer contracting and AEMO reserve
                                                                                              impact on the interaction with the Retailer Reliability Obligation.
                   contracting. AGL proposes that in the event the RRO is triggered,
                   AEMO should be cautious about procuring reserves for that
                   reliability gap before the RRO contract position date, to give retailers
                   every opportunity to secure contracts and to minimise the risk of
                   unnecessary procurement. AEMO’s decision around reserve
                   procurement and volumes should then be based on the most up to
                   date information.

                                                                                                                                                                         16
2.11 Other interim reliability reserve issues

Respondents             Comments                                                                   ESB response

Snowy Hydro             Snowy Hydro believes it is sensible to replace the Victorian               The Interim Reliability Reserve is intended to replace the need for the
                        Jurisdictional Derogation final rule for multi-year contracting of         Victorian Jurisdictional Derogation final rule for multi-year contracting.
                        RERT by a NEM wide approach. Jurisdictional RERTs can lead to
                        significant uncertainty for market participants in Victoria and
                        complications for AEMO’s management of power system operations
                        across regions with different RERT arrangements. In an
                        interconnected NEM, it is inefficient that possible future challenges
                        facing the market need be managed at a jurisdictional level.

ERM                     ERM Power notes the proposed approach that the ESOO will be                The ESB considered using the MTPASA and EAAP but decided to restrict it
                        used to determine if there is a breach of the Interim Reliability          to the ESOO because this is the most rigorous forecast, covers all 3 years
                        Standard. We do see that the MTPASA and EAAP can be a
                                                                                                   and is aligned with the trigger for the RRO. If there is a material change in
                        particularly important ‘sense check’ for the first two years given the
                        differences in approaches between the MTPASA and ESOO. We                  circumstances, then there is a rules requirement for AEMO to update the
                        are not arguing for an approach where a breach of the interim              ESOO. AEMO is constantly checking the various reliability assessments to
                        reliability standard in the ESOO is invalidated if there is no breach in   ensure consistency and understand any material differences in outcomes that
                        the MTPASA or EAAP. Rather, a material difference in forecasts             may indicate an ESOO update is warranted.
                        between the two should be seen as a cause to reconsider the need
                        for a multi-year contract.

QLD Electricity Users   Concerned that the 2020 ESOO will overforecast demand due to               AEMO has engaged economic consultants to consider the impacts of
Network                 COVID-19. Should small business demand, and business demand                COVID19 on key sectors of the economy, analysed meter data to monitor
                        in general, be overstated in the August 2020 ESOO it is possible the
                                                                                                   changes in residential and business sector consumption, and collaborated
                        T-1 instrument could be triggered as early as 2020-21 for the
                        following year.                                                            with the Forecasting Reference Group and Energy Networks Australia to
                                                                                                   consider the impacts on demand for the 2020 ESOO forecast.

AEC                     The enthusiasm to change the reliability standard must also be             AEMO’s demand forecasts will incorporate an assessment of the impact of
                        assessed in light of the COVID-19 pandemic. The COAG Energy                COVID19. More broadly, in light of the economic down turn, the final rule has
                        Council is concerned that the supply-demand balance has
                                                                                                   strengthened the checks and balances in relation to minimising costs to
                        tightened, and there is a risk that outages will occur. In contrast,
                        economic commentators are predicting Australia will experience a           consumers.
                        recession, which will reduce demand markedly. Furthermore, there
                        is no indication from market reports such as the Medium Term
                        Projected Assessment of System Adequacy that there will be any
                        shortfall within the next two years.

                                                                                                                                                                                17
C Abbreviations and Technical Terms

AEC           Australian Energy Council
AEMC          Australian Energy Market Commission
AEMO          Australian Energy Market Operator
AER           Australian Energy Regulator
COAG EC       Council of Australian Governments Energy Council
ESB           Energy Security Board
EUAA          Energy Users Association of Australia
MEU           Major Energy Users
NEL           National Electricity Law
NEM           National Electricity Market
NER           National Electricity Rules

                                                                 18
Contact details:
Energy Security Board
E: info@esb.org.au
W: http://www.coagenergycouncil.gov.au/energy-security-board

                                                               19
You can also read