Connecting Central Europe with the sea - Ljubljana, 6th June 2019
Connecting Central Europe with the sea

                Ljubljana, 6th June 2019
Connecting Central Europe with the sea - Ljubljana, 6th June 2019
Port of Koper – efficient combination of cost,
time and energy savings
                 • more than 2.000 Nm shorter maritime route – up to 7
                   days shorter transit time by sea (if “slow steaming” at 12 knots)

                                                                                                              distance from TOKYO to
     HAMBURG
  ROTTERDAM
                                                                                                   KOPER
                                                                                                   8.500 Nm
         KOPER

                                                                                         ROTTERDAM
                                                                                         10.500 Nm
                       Port Said

                                                                                       HAMBURG
                                                                                       10.750 Nm
Connecting Central Europe with the sea - Ljubljana, 6th June 2019
At the intersection of European transport
corridors                  Baltic – Adriatic corridor
                                                        Amber corridor

  Mediterranean corridor

                                           KOPER           Alpine – Western Balkan corridor
Connecting Central Europe with the sea - Ljubljana, 6th June 2019
About the Company
                                                                   • concession granted for the management
 established in      • public limited company listed on the          of the port area until 2043
                       Ljubljana stock exchange                    • invests in infrastructure and

1957                 • terminal operator of all 12 specialized
                       terminals – multi-purpose port
                                                                     suprastructure in the port area
                                                                   • national spatial plan for the development
                                                                     of the port adopted in 2011

     maritime
throughput in 2018   • container throughput: 988.499 TEU         1st container terminal in the Adriatic
     24              • cars throughput: 754.409 units            Among largest port for cars in the Mediterranean
   million tons

                        1,400 +                                  • EU core port of the TEN-T network
                        employees in the Luka Koper Group        • important gateway for supply of CEE markets
Hinterland markets                 Poland
                                       Containers, Cars,
                                       General cargo

                                        Czech R.
                                        Containers, Cars,
                                        General cargo

Austria:                               Germany
Absolute market leader - more than
7 M tonnes of various goods handled    Containers, Cars,
every year                             General cargo

Slovakia:                             Romania
Container market leader               Containers

Hungary:                              Croatia,Bosnia&
Container market leader
+ cars, electronics,                  Herzegovina,Serbia
agro/food/fodder                      Containers, Cars, General
                                      cargo

Slovenia:                             Bulgaria
Domestic port                         Containers
Maritime throughput history
                                                                                Containers (TEU)
ton                                                                                  Cars (units)
total maritime throughput

              30.000.000                                                                  1.200.000

              25.000.000                                                                  1.000.000

              20.000.000                                                                  800.000

              15.000.000                                                                  600.000

              10.000.000                                                                  400.000

               5.000.000                                                                  200.000

                      0                                                                   0

                            2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
                                                   ton   TEU   cars
Leading container terminal in North Adriatic
                                                                                      Trieste
 TEU                                                                         Venice         Koper
                                                                                                    Rijeka
1.200.000

1.000.000
                                                                                            KOPER 2006: 218.970 TEU
                                                                                            KOPER 2018: 988.499 TEU
 800.000
                                                                                            Total 4 ports 2018: 2,6 M TEU
                                                                                            KOPER share: 38,0%
 600.000

 400.000

 200.000

       0

            2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
              Rijeka (AGCT)   Trieste (TMT)   Venice (Vecon + VIT)   Koper
Efficient and competitive railway services
                                                                Wroclaw

                                                                                            Katowice
                                                   Melnik

                                                                       Ostrava

                                                                       Paskov                 Žilina              Košice

                                                                Wien                   Bratislava
                             München                                                         Dunajska Streda
                                                        Linz
                                                                                                  Budapest
                                   Salzburg
                                                                       Graz
Current capacity:                             Villach                                                                     Arad
                                                                       Maribor
85-87 trains/day                                                Ljubljana
                                                                              Zagreb
                                  Padova
                                                                                                               Belgrade
                                                        KOPER
Container block-trains:
12-13 arrivals/departures daily
Port of Koper modal split
          Loaded/unloaded                                                      of total
                                                                               throughput
          wagons & trucks arrivals                                             (tons)

350.000

300.000

250.000
                                                                               59 %         41 %
200.000

150.000

100.000

 50.000

     0
           2011   2012    2013    2014       2015     2016      2017   2018

                    loaded/unloaded wagons          no. of trucks

                                                                       100 %
Major infrastructure construction works 2014 - 2020
SECOND TRACK DIVAČA – KOPER

Photo: Peter Kleva
The significance of the construction of the Second track Divača – Koper
railway line

1. Rapidly growing demand for transportation of freight between Port of Koper and
   hinterland countries along with severe capacity constraints on the existing single
   railway track Divača – Koper necessitate construction of an additional railway
   line on this section.
2. The building of the Second track Divača – Koper railway line is the flagship
   logistic project in Slovenia.
3. Second Track Project will connect the port of Koper with the town of Divača
   and eliminate an important bottleneck of the core Mediterranean and
   Baltic-Adriatic TEN-T corridors.
4. The Second Track is vital for positioning of Slovenia as a key European
   transit country as well as for increasing competitiveness of rail transport
   compared to environmentally and operationally costly road traffic.
5. In addition in 2017 the Government initiated activities to amend the project
   scope and allow for construction of service tubes for tunnels T1, T2 and T8 in
   full diameter to enable the building of the additional railway track in parallel with
   the new railway track and to eventually remove the 45 km long outdated track.
Main elements and characteristics of the project
Key objectives of the project
Key Milestones of the project – part one

1. The 2TDK company was established by the Government of Republic of
Slovenia on 31 March 2016.
2. The building permit for the entire project was issued on 31 March 2016.
3. Act regulating the investment of the second railway track from Divača to
Koper (ZIUGDT) entered into force on 21 July 2018.
4. By decision, the Ministry of the Environment and Spatial Planning has
amended the building permit of 31 March 2016 on 6 August 2018 and
2TDK became holder of the building permit.
5. The Government of the RS approved payment of the first part of
company's share capital in the amount of EUR 20 mio on 30 August 2018.
6. The transfer of the investment from DRSI to 2TDK was completed in
November 2018.
7. Investment programme was adopted by the general Meeting of the
Company (the Government of the RS) on 24 January 2019 (required by
national legislation; prepared by Deloitte, the 2TDK‘s financial adviser).
Key Milestones of the project – part two

8. The Concession Act was adopted on 4 April 2019.
9. The Concession Agreement between 2TDK and the Government
of the Republic of Slovenia was signed on 9 Mai 2019. The
concession for the second track is awarded for 45 years from the
conclusion of the concession contract.
10. The Service level agreement (SLA) is currently being in the
process of preparation and harmonisation between relevant
stakeholders. We believe, that it will be signed in June 2019.
11. All the implementing regulations, related to the special revenues,
based on Act were adopted:
In order to cover financial obligations of the 2TDK, the Act is introducing
higher charges for the use of railway (payed to the 2TDK from the
SŽ-Infrastruktura) and availability payment payed to the 2TDK from the
state budget (sources for the availability payment are highway mark-up
and port tax).
Current state of the project - preparatory works in progress

1. Geological, geotechnical and hydrogeological surveys:
       - on-site investigations for additional geological, geotechnical and
       hydrogeological surveys completed.
       - no additional risk identified.
       - monitoring until September 2019.

2. Archaeological surveys:
       - works started in November 2018, after implementation of sheltering
       of the areas of the archaeological excavations and are well in progress.

3. Executive design:
       - the tender was published in November 2018;
       - It is envisaged, that the contract will be signed on 10 June 2019.
Current state of the project - preparatory works in progress

4. Access roads
        - contract signed on 15 December 2017 (vaule EUR 14,48 mio).
        - the contractor was introduced into the work in 25 January 2019.
        - works are in progress according to the timeline.

5. Construction of structures for bridging Glinščica Valley
        - the public tender        was     published    on   March       2019
          (design&build).
        - the deadline for the submision of tender proposals was 10 Mai
          2019.
        - 2TDK received three binding offers that are currently being in the
          process of evaluation.
        - start of works (executive design) is predicted in July 2019.
Throughput estimations till 2030
                                                                                                                    Multipurpose port (all cargo
   ton              total maritime throughput       containers          cars      TEU/units                         groups)
40.000.000                                                                          2.500.000

35.000.000                                                                                                       Expected accelerated growth of
                                                                                    2.000.000                    container traffic
30.000.000

25.000.000
                                                                                    1.500.000
                                                                                                            Important positon on car segment
20.000.000

                                                                                    1.000.000
15.000.000
                                                                                                         Regular supply of strategic fuels
10.000.000
                                                                                    500.000
 5.000.000
                                                                                                       New opportunities for general cargo related to
         0                                                                          0                  containers and alternative fuels
             2016    2017      2018       2019      2020         2025      2030

 Throughput                                      2018                          Estimation 2020          Development: 2030

 Total (tonnes)                                         24.048.618                        24.300.000                35.100.000
 Containers TEU)                                           988.499                         1.000.000                 2.000.000
 Vehicles (units)                                          754.409                           850.000                 1.250.000
Long term port development
                             INVESTMENTS until 2020

                             INVESTMENTS until 2030

                                2016 – 2020:
                                more than 300
                                million EUR

                                2021 – 2030:
                                additional 400 mln
                                EUR