APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
APA consortium update

     Christos Touramanis
    DUNE Collaboration Call
         3 April 2020
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
Outline
• Progress since the last Collaboration Meeting (31/01/20)

    - APA design, towards FDR

    - Transport Frame & Box design, review preparation

    - APA Boards, Task Force progress

    - Production Plan & QA/QC

• COVID-19 fallout on operations

• ProtoDUNE-II and FD I delivery

• Consortium groups and responsibilities

• Uncovered items (or lack thereof)

2    3 April 2020   C. Touramanis | DUNE C.C.
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
Two months of intense activity
In February – March we had weekly meetings:
• Consortium
• Preproduction engineering
• Transport Frame and Box
• Boards Task Force
• QA/QC
• Ad hoc in response to matters arising
All teams have been working full-time, many individuals making
exceptional contributions. A big thank you to all!
Close collaboration with TC, I&I: Compliance Office, QC …
We are in good shape and on track to meet our major milestones

3   3 April 2020   C. Touramanis | DUNE C.C.
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
APA design
• Complete design available
• In progress:
    - Validation of PD wires & connectors at PSL and Ash River
       • Impacted by COVID-19 situation and measures

    - Validation of APA integration in TPC at Ash River
       •     Impacted by COVID-19 situation and measures
    - APA analysis plan and document for FDR, PSL
       • Work starting in coordination with TC and Compliance Office

4    3 April 2020   C. Touramanis | DUNE C.C.
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
APA Transport Frame & Box
• On track for 60% design review in May/June
• Design practically final (Peter Sutcliffe, George Stavrakis, Liverpool)
• FEA almost complete (Ang Lee, Fermilab)
• Shock absorption suspension specified, waiting for external company
  final report (Peter)
• Handling at SURF understood, final scheme close to sign off (Justin
  Freitag, Fermilab)
• Box design final, allows for APA inspection/testing at intermediate
  stages of the journey from factory to underground (George)
• Documents for review will be ready in April
• Many thanks to Olga Beltramello (CERN), Jean-Louis Grenard
  (CERN), Mariana Zimbru (Compl. Office), Giuseppe Gallo (Fermilab),
  Dan Wenman (PSL) and others for advice and guidance
• Prototype construction, Jeff Nelson (W&M) and testing, Bill Miller (Ash
  River) to be scheduled depending on COVID-19 situation

5   3 April 2020   C. Touramanis | DUNE C.C.
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
Transport Frame & Box Design

                                                               Alum Profile Side
                                                               frames and
                                                               covers
                                                                       APA Supports
                                                                       and Anti
                                                                       Vibration Wire
                                                                       Rope Mounts

                                                              Transport Frame

                                                            APAs
                                               APA Covers

6   3 April 2020   C. Touramanis | DUNE C.C.
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
7   3 April 2020   C. Touramanis | DUNE C.C.
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
8   3 April 2020   C. Touramanis | DUNE C.C.
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
9   3 April 2020   C. Touramanis | DUNE C.C.
APA consortium update - Christos Touramanis DUNE Collaboration Call 3 April 2020 - Fermilab
FEA and codes compliance

10   3 April 2020   C. Touramanis | DUNE C.C.
Stability Analysis

11   3 April 2020   C. Touramanis | DUNE C.C.
Handling at SURF

12   3 April 2020   C. Touramanis | DUNE C.C.
APA Boards
• Task Force active (weekly meetings). Chair: Terry Shaw
• Subgroups for mechanical tolerance, voltage, IPC standards for
  HV trace spacing, hole tolerance and press pins (meetings as
  required)
• Many contributions from PSL (in addition to Andy Laundrie)
• HV IPC checks, some redesign (Andy, Anthony Ezeribe,
  Sebastien Prince): almost there
• Mechanical tolerances: a lot more than board thickness; good
  progress being made
• Custom MillMax press-fit pins: Terry in charge
Very impressive amount and depth of work done, good progress
being made. Huge thank you to the TF members!
13   3 April 2020   C. Touramanis | DUNE C.C.
Production & QA/QC
• Consortium working closely with DUNE QA leadership
• Weekly meetings
• Thanks to Jim Mateyak (Fermilab), Sebastien Prince and Guenette
  (Harvard), Gwenn Mouster (Lancaster)
• Revisiting the whole chain (Physics requirements) – (specifications
  and tolerances) - (QA/QC)
• Gwenn gathering all available documents to compile full set of
  production and QA/QC procedures
• Investigating “digital factory” platform to ensure identical APAs and
  strict QA adherence in all factories
• Examples of new developments: acceptance QC tools & jigs for frame
  bars, mesh frames (Daresbury, Liverpool, PSL)
• Automatic electronic wire tension system advancing well (Harvard)

14   3 April 2020   C. Touramanis | DUNE C.C.
COVID-19 situation
• Everybody working form home: design, engineering, review
  preparations continuing
• In touch with many suppliers who are still partially working
• On-site hands-on work:
     - Daresbury, Liverpool workshop: closed

     - FNAL workshops closed by not affecting APA work

     - PSL: evolving situation, basically closed

     - Ash River: continuing with reduced staff; can build on protoDUNE-II
       volume
     We are not changing our schedules for now on the assumption that the
     lockdowns will create a (small) global shift to the whole project

15    3 April 2020   C. Touramanis | DUNE C.C.
Delivering for ProtoDUNE-II and FD 1
• Based on existing schedule:
     - ProtoDUNE-II requires 4 APAs in late 2021: we can deliver that even
       with a few months lost due to COVID-19
     - With the full complement of UK and US factories we are on track to
       have 150 APAs for FD 1 by mid-2024
     - With all “money in the bank” in the UK we will deliver 152 APAs by
       May 2027 (25 APAs / calendar year at full production)

We don’t see any reasons at this point to change our schedule
and milestones

16    3 April 2020   C. Touramanis | DUNE C.C.
Institutes and deliverables
                                   Institution                     Country                                          Deliverables
University of Cambridge                                            UK        Testing and assembly of wire boards; QA/QC
Daresbury Laboratory - Science and Technology Facilities Council   UK        APA production site; winding machines
Lancaster University                                               UK        Testing and assembly of wire boards; QA/QC; APA assembly
University of Liverpool                                            UK        Transportation frame, box & organisation; steel procurement; APA assembly
University of Manchester                                           UK        Procurement and testing of wire boards; APA assembly
University of Sheffield                                            UK        Mesh panels; testing and assembly of wire boards; APA assembly
University of Sussex                                               UK        Testing and assembly of wire boards
Brookhaven National Laboratory                                     USA       Simulation studies on signal shapes and transparency of ionization electrons
University of Chicago                                              USA       APA production site, Grounding mesh frames
Colorado State University                                          USA       Studies of wire vibration in LAr and induced electronic noise
Harvard University                                                 USA       QA/QC management, wire tension measurements
University of Houston                                              USA       G-plane wire boards
University of Iowa                                                 USA       APA frames
University of Mississippi                                          USA       Studies on mesh frames
Northern Illinois University                                       USA       Cold electronics adapter boards
Syracuse University                                                USA       G-bias boards
University of Texas at Arlington                                   USA       X-plane wire boards
Tufts University                                                   USA       Participation in APA assembly
College of William & Mary                                          USA       U/V-plane wire boards, APA transport crates
University of Wisconsin-Madison, Physical Sciences Laboratory      USA       APA production site, CR boards, APA frames, Yokes and structural tees
Yale University                                                    USA       APA production site

       17          3 April 2020      C. Touramanis | DUNE C.C.
Opportunities for further contributions
• We don’t have uncovered items in our production plan

• There will be opportunities for contributions in QA, integration,
  installation, operations and analysis in ProtoDUNE-II

• The same will be true at SURF for the Far Detector modules

18   3 April 2020   C. Touramanis | DUNE C.C.
Summary
• A lot of very impressive progress and convergence in the last
  two months
• A lot still to be done but I am confident that we will be having the
  planned reviews this summer and the first APAs before the end
  of the calendar year

• We see no show stoppers in our plans

A very special thank you from myself and the whole consortium to
Alberto Marchionni for his outstanding dedication and attention
                          to every detail!

19   3 April 2020   C. Touramanis | DUNE C.C.