Analysis of Resource Availability for Post-earthquake Reconstruction in Christchurch, New Zealand

Page created by Nicholas Young
 
CONTINUE READING
Analysis of Resource Availability for Post-earthquake
           Reconstruction in Christchurch, New Zealand

         Yan CHANG1, Suzanne WILKINSON2, Regan POTANGAROA3, Erica SEVILLE4
             1Research assistant, Department of Civil and Environmental Engineering, The University of Auckland
                                      (20 Symonds Street, Auckland 1010, New Zealand)
                                             E-mail: ycha233@aucklanduni.ac.nz
            2Associate professor, Department of Civil and Environmental Engineering, The University of Auckland
                                      (20 Symonds Street, Auckland 1010, New Zealand)
                                             E-mail: s.wilkinson@auckland.ac.nz
                                 3Associate Professor, School of Architecture (ScALA), Unitec
                           (Building 1, Carrington Road, Mt Albert, Auckland 1025, New Zealand)
                                               Email: rpotangaroa@unitec.ac.nz
                       4 Leader, Resilient Organisations Research Programme, University of Canterbury
                             (22 Kirkwood Avenue, Riccarton, Christchurch 8041, New Zealand)
                                             Email: erica.seville@canterbury.ac.nz

         This paper shows an understanding of the availability of resources in post-disaster reconstruction and
      recovery in Christchurch, New Zealand following its September 4, 2010 and February 22, 2011 earth-
      quakes. Overseas experience in recovery demonstrates how delays and additional costs may incur if the
      availability of resources is not aligned with the reconstruction needs. In the case of reconstruction following
      Christchurch earthquakes, access to normal resource levels will be insufficient. An on-line questionnaire
      survey, combined with in-depth interviews was used to collect data from the construction professionals that
      had been participated in the post-earthquake reconstruction. The study identified the resources that are
      subject to short supply and resourcing challenges that are currently faced by the construction industry.
      There was a varied degree of impacts felt by the surveyed organisations from resource shortages. Resource
      pressures were primarily concentrated on human resources associated with structural, architectural and land
      issues. The challenges that may continue playing out in the longer-term reconstruction of Christchurch
      include limited capacity of the construction industry, competition for skills among residential, infrastruc-
      ture and commercial sectors, and uncertainties with respect to decision making. Findings provide implica-
      tions informing the ongoing recovery and rebuild in New Zealand.

        Key Words : Post-disaster reconstruction, the built environment, resource availability, New Zealand

1. INTRODUCTION

   New Zealand is prone to natural hazards. Past experience in New Zealand has demonstrated an ability to
cope with small-scale natural disasters, but the recent September 4, 2010 and February 22, 2011 earthquakes in
Christchurch test New Zealand’s ability to tackle a large-scale event. Overseas experience in recovery dem-
onstrates how delays and additional costs may be incurred if the availability of resources is not aligned with the
reconstruction needs1,2,3). In the case of reconstruction following Christchurch earthquakes, access to normal
resource levels will be insufficient and will cause significant delays to the rebuilding of the city. Resource
pressures including shortages of materials, components, specialised skills, and professionals are likely to affect
the implementation of disaster recovery projects, in terms of pricing, quality and timeliness.
   The Christchurch earthquakes have provided a unique opportunity to capture post disaster information, and
solve long term disaster management problems, specifically around the problem of how to resource the re-
construction of a major damaged New Zealand city. It is clear that there has been significant damage to resi-
dential property, commercial buildings and infrastructure following the two earthquakes in Christchurch. The

                                                         - 301 -
incremental damage and losses from the ongoing aftershocks present a unique challenge for Christchurch
recovery and rebuilding. In particular, increasing demands on the repair and reconstruction in the quake af-
fected areas will challenge New Zealand construction sector in terms of resources and capacity.
   This study aims to develop an understanding of the availability of resources that are required for repair and
rebuilding of the damaged built environment. The research project is intended to monitor and evaluate resource
availability as the repair and reconstruction proceeds on an on-going basis, to inform the construction industry
and recovery planning for the greater Christchurch region. The 'Resource Availability for Christchurch
Earthquake Reconstruction' (RACER) online survey is an important part of project, surveying construction
industry practitioners and recovery participants across varied recovery sectors: residential housing, commer-
cial buildings, and infrastructure. This paper presents the findings from the survey and in-depth interviews
with key representatives of the construction industry and recovery agencies between November 2011 and
January 2012.
   The study found that there was a varied degree of impacts felt by the recovery organisations from resource
shortages. Resource pressures were primarily concentrated on human resources associated with structural,
architectural and land issues. The study highlighted the importance of information flows and work patterns
required for effective recovery. Resource availability, however, was not a key constraint to recovery over the
three months of recovery in Christchurch (November 2011- January 2012). It is anticipated to play a big part
once the reconstruction and recovery in Christchurch gains momentum in 2012. To reduce likely resource
pressures, strong leadership, robust decision making, consistent messages, and strategic business planning, and
market planning are needed to improve recovery operations.

2. LITERATURE REVIEW

   Increased complexities and uncertainties in a post-disaster environment mean that delivery of reconstruction
projects is complex and challenging4). As such, the ways in which conventional construction resources for
building are procured may not be able to cope with recovery challenges posed by a large-scale disaster, such as
the Christchurch earthquakes5,6,7).
   A number of studies have focused on exploring the efforts to improve the performance of reconstruction
projects (e.g. 8)-13)), and on advocating a series of community and government initiatives in disaster mitiga-
tion (e.g. 14)-18)). Previous research shows that there is much unknown about the ways in which communities
and countries recover and rebuild after a disaster. In particular, the literature is mostly sketchy on the under-
standing of resource management for reconstruction post disaster. On-the-ground realities differ from theo-
retical studies and the implications of a large-scale disaster for longer term reconstruction are still not fully
understood. Of the research evidence available on resource management, it tends to show that post-disaster
recovery projects after a major event are more likely to suffer resource shortages19,20,21) and supply disrup-
tion22,23). These resourcing problems can transform into final recovery project failures such as cost overruns3,24)
and deferred delivery25,26) in the disaster affected areas.
   For instance, after the 2004 Indian Ocean tsunami, a lack of building materials such as sand, stone, cement,
timber and brick in Indonesia created a major bottleneck for housing recovery23,25,27). Prior to the Christchurch
earthquakes of 2010 and 2011, the shortage of aggregate, human resources and heavy equipment were iden-
tified as one of the potential constraints to the recovery process in New Zealand if a large-scale disaster were to
strike28,29). The longer term effects caused by resource shortages following a disaster can be ‘socio-economic
displacement’, which was manifested in tsunami impacted Indonesia and Sri Lanka in forms of inflationary
chaos25,30) and cost surge22). As Jayasuriya et al. observed, the impact of the tsunami had intensified resource
shortages that existed pre-event in Sri Lanka, fuelled inflation, constrained the government’s fiscal capacity,
and adversely affected housing reconstruction30). These problems, combined with procurement deficiencies of
the implementing agencies and resourcing-induced environmental degradation, reduced the overall effec-
tiveness of recovery in tsunami-impacted countries31,32).
   On the other hand, a number of experiences have shown positive results when resource bottlenecks are dealt
with by appropriate post-disaster policies. Taking the Tangshan earthquake (1976) recovery as an illustration,
resourcing in this situation was not a threat to post-quake physical reconstruction whereby, “A master plan was
formulated, heavy equipment was purchased and industrial plants were established to produce reconstruction
materials”33). A number of scholars such as Ye & Okada34) and Sullivan35) have recognized that desirable
post-disaster reconstruction could only be made possible by systematic recovery planning with a focus on
making the resources required available for long-term reconstruction. In addition, when examining their

                                                     - 302 -
post-tsunami reconstruction involvement, many non-government organisations (NGOs), international
non-government organisations (INGOs) such as the International Red Cross and Red Crescent (IFRC)32), and
the UN agencies such as United Nations Development Programme (UNDP)31,36) also highlighted the impor-
tance of resource availability as being an integral constituent in the ultimate efficacy of post-disaster recovery
efforts.
   While these findings have clear implications for resourcing reconstruction, little attention has been given to
an overall and systematic analysis of the underlying resource vulnerabilities and constraints inherent in a
longer term recovery process. Many studies concerned with resource deployment and allocation are mainly
targeted at emergency response to meet short-term humanitarian relief needs after a disaster (e.g. 37)-39)).
This study aims to develop and apply a resource management framework for reconstruction projects following
the Christchurch earthquakes. Critical resource management needs for the built environment sectors of resi-
dential housing, commercial building, and infrastructure will be studied.

3. RESEARCH METHODS

   The research will seek answers to the following significant questions:
   (1) What are critical resources during the earthquake recovery that have an impact on the reconstruction
       process?
   (2) What are the impacts from resource shortages?
   (3) What issues constrain the availability of the varied critical resources, and thus obstruct repair and re-
       building from proceeding as intended?
   (4) How can resource constraints be resolved?
To answer these questions, an on-line survey (www.recres.org.nz/survey) was established to survey the rebuild
participants across sectors on a three month basis. In-depth interviews with key representatives from the con-
struction industry and recovery agencies were undertaken between November 2011 and Febuary 2012. This
paper provides an overview of the results from both online database and interviews. The findings of this study
will be useful to inform the decision making and recovery planning for the ongoing recovery in New Zealand.

4. RESEARCH FINDINGS

   The sample of construction professionals and organisations was drawn from the New Zealand Construction
Industry Council (CIC) membership database. The invitation of survey response was distributed by each CIC
membership organisation through their internal network. The survey was launched in mid October 2011; as of
January 25, 2012, 155 respondents accessed the survey online. 61 surveys were fully completed and used to
prepare this paper. The survey respondents were primarily from consulting engineer companies and con-
structing businesses who had been involved in Christchurch earthquake rebuild (See Fig. 1).

                                                           Design, 2

                          Product               Other, 9
                       distribution, 4
                  Consenting/Cer
                     tifying, 1
                         Surveying, 0                               Consulting
                                                                   engineer, 28
                                         Constructing,
                                             17

                                   Fig.1 Sample of organisations surveyed

                                                       - 303 -
Of the respondent organisations, there are 28 consulting engineer businesses, 17 construction companies, 9
agencies including construction project clients, EQC Housing Project Management Office (PMO), and
Stronger Christchurch Infrastructure Rebuild Team (SCIRT). 4 organisations from the production distribution
sector responded to the survey, with businesses ranging from product manufacturer, importer and retailer, to
marketing. Only 1 consenting/certifying organisation responded to the survey. No response was received from
the surveying sector.
   Approximately 41% of respondents were from a large size organisation with more than 100 employees. 22%
are small organisations with 50 or fewer employees, and 18% are micro-sized organisations with 10 employees
or fewer. Of the 40% of large size organisations, more than half have head offices in Auckland, and 24% have
head offices in Canterbury. Only 4% of large sized are based in Wellington, Dunedin and Invercargill. The
others are from overseas mainly U.S. and Australia. In comparison, of those small and micro-sized organisa-
tions surveyed, the majority (79%) have their head office located in Canterbury. Approximately 80% earth-
quake recovery-related construction and new build activities took place in Christchurch City. Far less active
construction was undertaken in other two damaged districts of Waimakariri and Selwyn.

(1) ‘Pinch point’ human resources and their impacts
   Both survey respondents and interviewees put forward their concerns about skills availability. The most
reported problematic human resources include: structural engineers, geotechnical engineers, draughtsperson,
and consulting engineer professions, such as electrical engineer, mechanical engineer, resource and envi-
ronmental engineer; and trades, such as carpenter, painting trades, and electrician.
   These findings align with the recovery needs posed by the current sequence of a construction work. It is not
surprising that emergency repairs and land zoning issues at that stage required a large number of structural
engineers and geotechnical engineers. Housing repair was also proceeding well, which placed a burden on the
availability of architects and essential trades such as electricians, painters, and carpenters.
   The majority of the survey participants (90%) indicated that they were affected by the shortages of skills.
The study found some interesting organisational differences in the impacts felt. For micro-sized organisations,
for example, the impact was primarily associated with time and cost overruns. For medium-sized organisa-
tions, shortages of human resources resulted in capacity limitations to grow their businesses. In comparison,
the large-sized organisations were commonly faced with challenges posed by the disproportionately increased
workloads against their normal level before the earthquakes.
   Apart from regular recruiting process, the study found a stronger partnering and formed alliance strategy
used by those small- and micro-sized organisations to reduce the above cited impacts. For instance, by part-
nering with other organisations of similar scale, and by providing good working conditions, these smaller sized
organisations were able to retain skilled expertise to sustain their business operations.
   The impacts felt by the two dominant survey respondent groups — consulting engineer and constructing
were also different. The sudden increased workloads following the September 4th earthquake had over-
whelmed capacity of the consulting companies. Most of them found it hard to fulfil the commitment to their
clients, and had to say ‘No’ to other work offers. In contrast, constructing organisations encountered problems
of delivering their projects in terms of quality, timeline, and staff morale, due to skills shortages. There was
also a frustration from the process of advertising and recruiting skills. Time waste was an issue in finding best
people for the job.

(2) ‘Pinch point’ physical resources and their impacts
   Of the surveyed respondents, 7% reported they were experiencing shortages of physical resources. The
identified ‘pinch point’ physical resources were specialist pipe fittings, cement and aggregate for making
concrete, reinforcing steel, structural steel, and other building products required for repair of houses and
commercial buildings, such as windows or glazing, exterior cladding materials and paint. The resource
shortage mainly affected constructing organisations in terms of construction delays.
   12% reported problems of acquiring construction machinery for rebuild projects in Christchurch. The
identified plants as being in short supply were (in descending order): truck, crane, loader, portable cabin, ex-
cavator, roller/paver, miscellaneous small tools, and scissor-lifter. The shortage of these operational tools was
coming from emergency repairs for both housing and infrastructural utilities. The impacts reported were par-
ticularly relevant to the activities of an organisation. For instance, lack of equipments such as roller/paver for
road work had an impact on other maintenance work outside the recovery area for thoseconsulting engineer
organisations. Shortage of trucks, excavators, and scissor lifters had an effect on the scheduling and levelling

                                                    - 304 -
of the projects taken by constructing organisations.

(3) Factors affecting the productivity of rebuild projects
   In a matrix examining construction productivity, respondents were asked to identify the factors that nega-
tively affected productivity of their construction work. Approximately 56% of respondents reported that they
were suffering low productivity, while 44% responded that they were not having productivity problems. Fig.2
shows the hierarchy of the factors contributing to the low productivity.

                             Fig.2 Factors affecting the productivity of rebuild projects

   The identified top five factors causing low productivity include (in descending order):
       • Waiting for council approvals
       • Delays in main contractor providing information
       • Excessive head contractor/client oversight or procedures
       • Inadequate work specification & changed specification after work began
       • Waiting for insurance agency Earthquake Commission (EQC) inspections/ approvals
   Following the September 4th earthquake in 2010, the Christchurch City Council had relaxed a number of
policies to streamline the consenting process for repair and rebuild. This result, however, casts inquires on the
effectiveness of those policies. Other seemingly intractable problems of low productivity stemmed from delays
in the main contractor providing information and the insurance agency EQC’s housing inspection and relevant
approval process. On-going aftershocks, errors occurred in the inspection process, lack of communication
between damage inspectors and site supervisors, and changed approval policies, had contributed to work
variations; and hence negatively affected rebuild project productivity.
   However, the study found that resource availability was not key in governing the productivity of the rebuild
projects at this stage. Improvements to productivity of recovery projects can be made by focussing on im-
proving processes and information supplied from those key decision makers such as insurance agency EQC
and recovery agencies.

(4) Anticipation on resource availability over time
   61% of survey participants reported their anticipated changes to resource availability for the next three
months. The results from both questionnaire survey and interviews show a range of anticipated changes, re-
flecting an increase in the scale of impact and resource criticality. The challenge facing the construction in-
dustry and local recovery agencies can be summarised as follows:
       • If key recovery-related decisions are made, more construction activities will lead to a great demand
           on critical resources;
       • There will be competition for limited resources across sectors, organisations, and regions nationwide
           once the reconstruction gains the momentum;
       • Resourcing pressures would remain or even worsen if the repair and rebuild decisions and processes
           remain uncertain, and this would have a detrimental effect on the overall community recovery.

                                                        - 305 -
5. DISCUSSION AND CONCLUSION

   In order to reduce the impact of human resource shortages, the study found that it requires the decision
makers such as insurance agency EQC to provide a clear protocol of work procedures for housing repair and
rebuild; and the Canterbury Earthquake Recovery Authority (CERA) to provide a Master Plan for recovery in
ensuring forward certainty for both the affected communities and the construction industry. The tendency of
increased rebuild demands in 2012 supports the view that strategic skills training and education in construc-
tion-related subjects can enhance the resource pool and facilitate resource flows. However, there is also a
general concern that heavy recruitment of new staff to cover a short peak of workload during post-earthquake
recovery may leave a vacuum for construction sector once the rebuild peak has passed.
   Moreover, issues of low productivity of those surveyed seem particularly relevant for process and infor-
mation provided by key decision makers such as Christchurch City Council, EQC and recovery agencies,
which may further reinforce the reason why certainty required for going forward dominates the recovery
process. Rebuild and restoration of commercial structures and infrastructural utilities were expected to unfold
in mid 2012. Use of common-pool resources by those two sectors will reduce resource availability for housing
recovery. Good productivity is likely to be frustratingly patchy.
   The lessons from resource availability over the three months studied period are encouraging, yet the city
faces new challenges to deal with incipient resource pressures as the recovery of commercial building and
infrastructure fully starts. The reported patterns of increased construction demands rising from the Christ-
church recovery, together with the projection that there will be recovery plan, land and funding issue sorted,
results in quite dramatic forecasts of resource shortages for rebuild and repair over the next three months (from
February to April 2012).
   Many projected rates of growth in skills supply are inflated by enthusiasm for new sources that have yet to
prove themselves. Typical examples come from the government skill training package and seemingly relaxed
immigration policy. As in 2012 outlooks by the Government, the construction sector assumes that the skills
from outside Christchurch, particularly from Europe (given its current economic setting) would flow into the
country to meet the recovery demand. However, the immigrated construction workers may do not share a
similar understanding of how a project works and what rules and norms dominate in New Zealand. Man-
agement of these overseas resources depends on the cooperation of appropriate international institutions and
agencies at national, regional and local levels.
   A consensus emerged from the in-depth interviews regarding the conditions most likely to stimulate suc-
cessful processes for recovery. The insights gained from those interviewees provide starting points for ad-
dressing future challenges. Some of these will be institutional, such as streamlining consenting process and
improving insurance approval. Others will build from improved project management and resourcing strategies
within the construction sector. To combat the multiple challenges facing the physical built environment, a
transparent information disclosure system from EQC, CERA, and Christchurch City Council needs to be de-
veloped.
   In all, an important lesson from the empirical studies of resourcing construction projects in Christchurch is
that more solutions exist than expected. Resource availability was not found as a key constraint to the recovery
over the three months of reconstruction between November 2011 to January 2012. However, it is anticipated to
play a big part once the reconstruction and recovery in Christchurch gain momentum. Solving prospective
resource pressures involves two distinct elements: ensuring rebuild-related processes and institutional proto-
cols in place, and creating incentives to increase the both quantity and quality available to recovery in
Christchurch.

ACKNOWLEDGMENT: This research is funded and developed in collaboration with the Building Research
Association of New Zealand (BRANZ) and Resilient Organisations Research Programme
(www.resorgs.org.nz). The research team would like to give thanks to BRANZ and the Construction Industry
Council (CIC) membership organisations for facilitating and participating in data collection.

                                                    - 306 -
REFERENCES
1) Resilient Organisations (2006) Barriers to Post-Disaster Reconstruction. Resilient Organisations Research Report. Wellington,
   Resilient Orgnisations.
2) Zuo, K., R. Potangaroa, S. Wilkinson, and J. O. B. Rotimi (2009) "A project management prospective in achieving a sustainable
   supply chain for timber procurement in Banda Aceh, Indonesia". International Journal of Managing Projects in Business 2(3):
   386-400.
3) Chang, Y., S. Wilkinson, R. Potangaroa, and E. Seville (2010) "Resourcing challenges for post-disaster housing reconstruction: A
   comparative analysis". Building Research and Information 38(3): 247-264.
4) Alexander, D. (2004). "Planning for post-disaster reconstruction", I-Rec 2004 International Conference 'Improving Post-Disaster
   Reconstruction in Developing Countries', Coventry, UK.
5) Barakat, S. (2003) Housing reconstruction after conflict and disaster. Humanitarian Practice Network. Humanitarian Policy Group,
   Overseas Development Institute (ODI).
6) Masurier, J. L., J. Rotimi, and S. Wilkinson (2006). "A comparison between routine construction and post-disaster reconstruction
   with case studies from New Zealand", 22nd ARCOM Conference on Current Advances in Construction Management Research,
   Birmingham, U. K.
7) Jha, A. K., J. D. Barenstein, P. M. Phelps, D. Pittet, and S. Sena (2010) Safer Homes, Stronger Communities: A Handbook for
   Reconstructing after Natural Disasters. Washington DC, The World Bank.
8) Ofori, G. (2002). "Construction Industry Development for Disaster Prevention and Response", I-Rec 2002 International Conference
   on Post-disaster Reconstruction:' Improving Post-Disaster Reconstruction in Developing Countries', Montreal.
9) Lizarralde, G. (2004) Organisational system and performance of post-disaster reconstruction projects, Universite de Montreal. Ph.D
   thesis.
10) Lorch, R. (2005) "What lessons must be learned from the tsunami". Building Research and Information 33(3): 209-211.
11) Makhanu, S. K. (2006). "Resource mobilization for reconstruction and development projects in developing countries: Case of
   Kenya", I-Rec 2006 International Conference on Post-Disaster Reconstruction: 'Meeting Stakeholder Interests', Florence, Italy.
20)
12) Ahmed, K. I. (2008) Challenges and opportunities of post-disaster shelter reconstruction: the Asian context. I-Rec 2008 Interna-
   tional Conference on 'Building resilience: achieving effective post-disaster reconstruction'. Christchurch, New Zealand.
13) Mumtaz, H., S. H. Mughal, M. Stephenson, and J. K. Bothara (2008). "The challenges of reconstruction after the October 2005
   Kashmir Earthquake", 2008 Annual NZSEE Technical Conference, Wairakei, Taupo, New Zealand, NZSEE
   http://db.nzsee.org.nz/2008/Contents.htm.
14) Schilderman, T. (2004) "Adapting traditional shelter for disaster mitigation and reconstruction: Experiences with community-based
   approaches". Building Research and Information 32(5): 414-426.
15) Wu, J. Y., and M. K. Lindell (2004) "Housing reconstruction after two major earthquakes: The 1994 northridge earthquake in the
   United States and the 1999 Chi-chi earthquake in Taiwan". Disasters 28(1): 63-81.
16) Burby, R. (2005) "Have State Comprehensive Planning Mandates Reduced Insured Losses from Natural Disasters". Natural
   Hazards Review 6(2): 67-81.
17) Kenny, S. (2005) "Reconstruction in Aceh: Building Whose Capacity". Community Development Journal 42(2): 206-221.
18) James, E. (2008) "Getting ahead of the next disaster: recent preparedness efforts in Indonesia". Development in Practice 18(3):
   424-429.
19) UN-Habitat (2005) Post-conflict, natural and human-made disasters assessment and reconstruction. Governing Council of the
   United Nations Human Settlements Programme Twentieth session. Nairobi, UN-Habitatt. Pre-session document HSP/GC/20/5.
20) Steinberg, F. (2007) "Housing reconstruction and rehabilitation in Aceh and Nias, Indonesia — rebuilding lives". Habitat Inter-
   national 31(1): 150-166.
21) Kennedy, J., J. Ashmore, E. Babister, and I. Kelman (2008) "The meaning of 'build back better': Evidence from post-tsunami Aceh
   and Sri Lanka". Journal of Contingencies and Crisis Management 16(1): 24-36.
22) Jayasuriya, S., and P. McCawley (2008) Reconstruction after a Major Disaster: Lessons from the Post-tsunami Experience in
   Indonesia, Sri Lanka, and Thailand. ADB Institute Working Paper No. 125, ADB Institute.
23) Zuo, K., and S. Wilkinson (2008) Supply chain and material procurement for post disaster construction: the Boxing Day Tsunami
   reconstruction experience in Aceh, Indonesia. CIB W89 International Conference on Building Education and Research BEAR 2008.
   Heritance Kandalama, Sri Lanka.
24) Koria, M. (2009) "Managing for innovation in large and complex recovery programmes: Tsunami lessons from Sri Lanka". In-
   ternational Journal of Project Management 27(2): 123-130.
25) Nazara, S., and B. P. Resosudarmo (2007) Aceh-Nias Reconstruction and Rehabilitation: Progress and Challenges at the End of
   2006. Tokyo, Asian Development Bank Institute.
26) Boen, T. (2008) Reconstruction of houses in Aceh, three years after the December 26, 2004 tsunami. International Conference on
   Earthquake Engineering and Disaster Mitigation, http://know.brr.go.id/dc/reports/20080408
27) Asian Development Bank (2007) Proposed loan for the reconstruction of the cement production facility in Aceh, Asian Devel-
   opment Bank.
28) Brunsdon, D., and S. Smith (2004). "Summary notes from the infrastructure workshop", New Zealand Recovery Symposium,
   Wellington, the Ministry of Civil Defence and Emergency Management.
29) Singh, B. (2007) Availability of Resources for State Highway Reconstruction : A Wellington Earthquake Scenario Civil and
   Environmental Engineering Department. Auckland, The University of Auckland. Master thesis.
30) Jayasuriya, S., P. Steele, D. Weerakoon, M. Knight-John, and N. Arunatilake (2005) Post-tsunami Recovery: Issues and Challenges
   in Sri Lanka. ADBI Discussion Paper, Asian Development Bank Institute.
31) United Nations Development Programme (2005) Survivors of The Tsunami: One Year Later, United Nations Development Pro-
   gramme (UNDP).
32) International Federation of Red Cross and Red Crescent Societies (2006) Annual Report 2006, International Federation of Red

                                                             - 307 -
Cross and Red Crescent Societies (IFRC).
33) Mitchell, J. K. (2004). "Reconceiving Recovery", Recovery Symposium 2004, Napier, The Ministry of Civil Defence and Em-
  gergency Management.
34) Ye, Y., and N. Okada (2002). "Integrated relief and reconstruction management following a natural disaster", Second Annual
  IIASA-DPRI Meeting, Integrated Disaster Risk Management: Megacity Vulnerability and Resilience, Luxenburg, Australia.
35) Sullivan, M. (2003) "Integrated Recovery Management: A New Way of Looking at A Delicate Process". The Australian Journal of
  Emergency Management 18(2): 5-27.
36) United Nations Development Programme (2006) Construction Boom Analysis: Pilot analysis for bricks, United Nations Devel-
  opment Programme (UNDP).
37) Perry, R. W., and M. K. Lindell (2003) "Preparedness for emergency response: Guidelines for the emergency planning process".
  Disasters 27(4): 336-350.
38) Thompson, S., N. Altay, W. G. Green, and J. Lapetina (2006) "Improving disaster response efforts with decision support systems".
  International Journal of Emergency Management 3(4): 250-263.
39) Troy, D. A., A. Carson, J. Vanderbeek, and A. Hutton (2008) "Enhancing community-based disaster preparedness with information
  technology". Disasters 32(1): 149-165.

                                                             - 308 -
You can also read