2018: Trends in the purpose built student accommodation sector - Generating opportunities in a challenging and competitive market - Taylor Wessing

Page created by Phillip Martin
 
CONTINUE READING
2018: Trends in the purpose built student accommodation sector - Generating opportunities in a challenging and competitive market - Taylor Wessing
2018: Trends in the purpose built
student accommodation sector
Generating opportunities in a challenging
and competitive market
2018: Trends in the purpose built student accommodation sector - Generating opportunities in a challenging and competitive market - Taylor Wessing
2018: Trends in the purpose built student accommodation sector - Generating opportunities in a challenging and competitive market - Taylor Wessing
Contents
 1   Introduction
2    What’s going on in the market?
4    Reputation and demand
6    The chase for viable prime development sites continues
10   Rising construction costs – modular construction:
     getting the right fit
14   HMO licensing reform – disappointing news for PBSA
     providers
18   Taxing times ahead for offshore investors, but some
     positive news for developers
20   Staying ahead of the game
22   Taylor Wessing’s key predictions for 2018
24   Key contacts
2018: Trends in the purpose built student accommodation sector - Generating opportunities in a challenging and competitive market - Taylor Wessing
2018: Trends in the purpose built student accommodation sector - Generating opportunities in a challenging and competitive market - Taylor Wessing
Introduction
2017 was another strong year for the UK purpose built student
accommodation (PBSA) sector, with the cumulative value of investment
totalling £4.07bn, close to £1bn higher than the previous year and climbing
back towards the record level seen in 2015.

Knight Frank’s student property team estimates that the value of the
UK PBSA sector will hit £50bn by 2019.

In this year’s trends report, the Taylor Wessing student accommodation team
consider the continuing attractiveness of the sector to global investors. We
evaluate some of the challenges faced by different stakeholders that may
impact on decision making processes and further growth and look at where
the future opportunities might be for developers, investors and operators.

                                          1
1
What’s going on in the
market?
The cumulative value of investment in           Two significant portfolio deals that
2017 was £4.07bn, close to £1bn higher          completed in December 2017
than the previous year and climbing             (iQ Student Accommodation’s
back towards the record level seen              acquisition of the Regent Portfolio
in 2015. This was underpinned by the            for £869m and Arlington Property
investment strategies of some of the            Investors’ acquisition of the Study Inn
key players to consolidate and increase         Portfolio for £135m) brought to a close
market share.                                   another resilient year for the sector.
                                                Other significant transactions in 2017
2014       £1.5bn                               included acquisitions by Brookfield,
                                                CPPIB, Unite, GCP Capital, Europa &
2015                               £5.1bn       Generation Estates and Tristan Capital.
2016                 £3.1bn                     Q1 2018 showed signs of a further
                                                year of consolidation in the sector, with
2017                     £4.07bn
                                                Brookfield completing its acquisition
2018*                         £4.5bn            of the Enigma Portfolio for £520m
        *Projected                              and total investment in the quarter
                                                estimated to have exceeded £1bn. In
Source: Knight Frank (May 2018)                 June 2018, Property Week reported
                                                that Round Hill is understood to
                                                be in exclusive talks with Watkin
                                                Jones to forward fund seven PBSA
                                                developments with a GDV of £250m.

                                            2
Two further large portfolios of                  (the supply/demand dynamic, stability
existing stock are also being marketed           and resilience to economic downturns,
for sale. A number of new joint ventures         relatively low risk of tenant default
and funds have been announced                    and the reputation of UK academic
and new global investors are actively            institutions, amongst others) remain
seeking out opportunities to take a              compelling and will continue to drive
stake in the sector. All signs point to          future growth of the sector.
another strong year.
                                                 We anticipate that there will be fewer
Knight Frank’s Student Property Team             portfolios changing hands in 2018 but
estimates that the cumulative value of           a steady stream of high value single
investment transactions in 2018 will be          asset deals as market leaders continue
around £4.5bn and that the value of the          to consolidate their portfolios and
UK PBSA sector will hit £50bn by 2019.           grow their brands. We also envisage
                                                 further acquisitions of equity stakes in
In our view, the fundamental                     established investment and operating
characteristics and drivers that have            platforms and greater collaboration with
attracted increasing global investment           universities to revitalise some of the
into the asset class over the last 5 years       more tired stock.

                                             3
2
Reputation and demand
Whilst we cannot ignore the press                  2018 UCAS cycle at the 24 March deadline –
coverage on the potentially adverse                difference between cycle and 2017 cycle
impact that Brexit will have on the                            10

quality and demand for UK higher                                5

education, is that anything more than                          -0

political rhetoric? We have yet to see                         -5

any real evidence of a downturn in                            -10
                                                   per cent

global demand.                                                -15

                                                              -20
The major UK universities continue to                         -25
score well in the reputation rankings                         -30
(the current list of the best universities                    -35
in the world published by Times Higher                        -40
Education is led by two UK universities
for the first time) and the latest UCAS                             2009        2011           2013   2015          2017

figures indicate that demand for places                                    UK
                                                                           EU (excluding UK)
                                                                                                        Not EU
                                                                                                        All domiciles
remains strong.
                                                   Source: UCAS Analysis and Insights
                                                   (5 April 2018)

World University Rankings 2018 (UK entrants)
   1   University of Oxford                             36           King’s College London
  2    University of Cambridge                     =54               University of Manchester
  8    Imperial College London                           76          University of Bristol
 16    UCL                                         =80               University of Glasgow
=25    London School of Economics and                     91         University of Warwick
       Political Science
                                                         97          Durham University
=27    University of Edinburgh
                                                   Source: The Times Higher Education World
                                                   University Rankings 2018

                                               4
5
3
The chase for viable
prime development sites
continues
Against that backdrop of buoyant                 Mayor in his Annual Monitoring Report
investment appetite and strong                   (AMR). For the 2017-18 academic year
demand, developers continue to seek              the annual rental cost for affordable
out opportunities to bring forward new           PBSA must not exceed £6,051 which
schemes in the right locations. However,         equates to a weekly rent of £159 for a
planning policy, high community                  38-week contract. The next AMR will be
infrastructure levies, rising construction       published in July 2018.
costs and the impact of competing land
uses on the availability of land (amongst        However, the 2016 Guidance specifically
other constraints on the development             excludes from the requirement PBSA
pipeline) have created a challenging             developments where the provider has
environment to navigate.                         a nominations agreement with one
                                                 or more academic institutions that
The spotlight on affordability continues         specifies that the accommodation will
to present a challenge to the                    be occupied by students of the relevant
viability of new PBSA schemes. The               institutions and where the continuance
Supplementary Planning Guidance                  of the agreements for as long as the
issued by the Mayor of London in March           local authority considers appropriate
2016 requires new development of                 is secured by a planning condition or
PBSA to include an element of provision          agreement.
that is affordable for students. We
considered the 2016 Guidance in detail
in our 2017 Trends Report. It requires
the element of affordable PBSA to
be the “maximum reasonable amount
subject to viability” and the annual
rental cost for the affordable PBSA
not to exceed a figure published by the

                                             6
The draft new London Plan issued                 Further, the draft Policy H17 requires
by the Mayor in December 2017                    35% of student bedrooms in all new
and setting out a policy takes the               PBSA to be affordable. If that threshold
affordability requirements a step                is not met, a scheme will be considered
further. Draft Policy H17 (see page 8)           under the viability tested route in
requires that all PBSA “must either be           line with part E of Policy H6 and the
operated directly by a higher education          Mayor’s Affordable Housing and Viability
institution or the development must              SPG. This application of the affordable
have an undertaking in place from                housing threshold to all PBSA marks a
initial occupation, to provide housing           shift in approach to the current London
for students at one or more specified            Plan which only seeks affordable
higher education institutions, for as long       housing where there is no nominations
as the development is used for student           agreement in place.
accommodation”.

A majority of the bedrooms in the
development must be covered by such
an undertaking. If the PBSA is not
secured for use by students and for
occupation by one or more specified
higher education institutions, it will not
be considered PBSA or meeting a need
for PBSA and the development proposal
will be considered large-scale purpose-
built shared living and assessed by the
requirements of Policy H18.

                                             7
H17                                               In its response to the consultation on
                                                    the draft new London Plan, the British
  A. Boroughs should seek to ensure that
  local and strategic need for purpose-built        Property Federation (BPF) has raised
  student accommodation is addressed,               a number of concerns and suggestions
  provided that:                                    for further review. These include:
  1. at the neighbourhood level, the
  development contributes to a mixed and            ff   a concern that requiring a link to
  inclusive neighbourhood                                a higher education institution will
  2. the use of the accommodation is                     limit access to PBSA for students
  secured for students                                   of smaller institutions and put
  3. the accommodation is secured for                    more pressure on the conventional
  occupation by members of one or more                   residential housing stock
  specified higher education institutions
                                                    ff   the lack of clarity in the draft policy
  4. at least 35 per cent of the                         as to what constitutes a nominations
  accommodation is secured as affordable
                                                         agreement, the length of term
  student accommodation as defined
  through the London Plan and associated                 required and the percentage of
  guidance                                               beds within a scheme that would
  5. the accommodation provides adequate                 constitute an “undertaking” – higher
  functional living space and layout.                    education institutions may be
  B. Boroughs, student accommodation                     reluctant to contractually commit
  providers and higher education institutions            early in the design process prior to
  are encouraged to develop student                      planning approval being given and
  accommodation in locations well-                       will also have concerns at how the
  connected to local services by walking,                requirements can be reconciled with
  cycling and public transport, but away                 accounting treatment considerations
  from existing concentrations in central
  London as part of mixed-use regeneration
  and redevelopment schemes.

Source: The London Plan: The Spatial
Development Strategy for Greater London –
Draft for Public Consultation (December 2017)

                                                8
ff   concerns that the 35% affordability           The consultation closed on 2 March
     requirement will further constrain            2018. We await the outcome, but
     the development of private PBSA               do not expect to see any significant
     in London which will apply further            amendments to draft Policy H17.
     pressure on the capital’s wider
     housing stock                                 Further, we anticipate that local
                                                   planning authorities across the UK will
ff   querying the justification for applying       follow suit and adopt similar policies to
     the affordable housing threshold to           address the affordability issue. This will
     all PBSA, even where nominations              place a further strain on the financial
     have been agreed – the BPF believes           viability of potential new PBSA projects
     that schemes in London which can              and developers will be working hard to
     demonstrate that they directly link           try to counterbalance the impact by
     with a higher education provider              interrogating other development costs,
     should have the 35% affordability             including the costs of construction.
     requirement removed and that where
     100% of the rooms in the student
     development meet the affordability
     criteria, there should be no need
     for a nominations agreement with a
     university.

The BPF’s concern about the VAT
consequences of requiring a link to
specified higher education institutions
should be alleviated by the outcome of
the Summit Electrical case which we
consider in the tax update on page 18.

                                               9
4
Rising construction costs
– modular construction:
getting the right fit
The costs of construction continued to              structure, up to full apartments, where
rise throughout 2017, with both material            only the central core is constructed
and labour costs on the increase.                   on site and the rest of the building is
AECOM’s cost indices, published in                  constructed off-site.
Building Magazine on 19 March 2018,
state that between Q4 2016 and Q4                   The benefits of modular construction
2017, the building cost index rose 4.2%             mainly derive from cost savings – whilst
and the mechanical cost index rose                  modular construction is often more
4%. Such increases are forecast to                  expensive than standard construction,
continue into 2018 with increases in                the shortened construction period on
input costs offsetting any predicted                site more than compensates. Work
deflationary effects. As a consequence,             on the ground can be carried out in
many developers, in both student                    parallel with the construction of the
accommodation and other sectors,                    modules and, because the modules are
are looking at ways to mitigate the                 constructed in a factory setting, delays
effects of the current market and to                due to adverse weather are mitigated.
protect margins, and one of the ways                In addition, less labour is required on
in which developers are seeking to                  site as the majority of the work can
do this is through the use of modular               be carried out at the factory utilising
construction.                                       local labour. There does need to be a
                                                    critical mass of construction to make
Modular construction (also referred                 modular construction financially viable
to as ‘off-site construction’) can mean             given that it is, effectively, a production
anything from small prefabricated                   line that needs to be set up specific
elements such as bathroom ‘pods’ or                 to a particular building or a number
façade systems constructed in a factory             of buildings to the same specification
away from the construction site, and                (150+ rooms has been suggested as a
delivered to site fully fitted out and tiled        guide).
ready to be incorporated into the on-site

                                               10
Whilst historically ‘pre-fabs’ have had                    Interface – there needs to be
a bad reputation as being lightweight,                     clear risk allocation between
temporary looking, not durable,                            the structural engineer
depreciating in value and with a high            responsible for designing the frame
lifecycle cost exposure, quality is              or core, the mechanical and electrical
improving and with a maturing supply             engineer responsible for designing the
chain there are now a number of                  cabling and plumbing and the design of
products on the market which have                the modules, as there is less scope for
changed these perceptions.                       correcting ‘design clashes’ than when
                                                 traditional construction methods are
However, there are still a number of             used.
issues specific to modular construction
that need to be considered by developers                    Fixing design – modular
and funders, and we have summarised                         construction requires both the
some of the key legal points below.                         design of the overall project
                                                 and the detailed design to be fixed at
          Quality – quality control              an early stage, so that the modules can
          is potentially more difficult          go into production. Once that process
          than traditional construction          is underway design changes are very
as manufacturing issues are difficult            difficult and expensive to implement.
to rectify once the module is on site.
Developers and their funders need
to have a presence at the place of
construction to be able to monitor and
inspect the modules and identify any
issues before they leave the factory.
Rights of access and inspection to the
factory will be required along with a
right to be present for all tests carried
out on the modules.
                                            11
Payment – significant advance                       Insolvency Risk – in the
          payments are usually required                       event of insolvency of the
          to be made to the module                            module supplier, it will be
supplier, due to the bespoke nature of             difficult to find another supplier that can
the modules. Developers and funders                continue to deliver modules to the same
therefore need to ensure that there is             specification, and it will have a huge
sufficient security over the modules               impact on programme, certainly more
and the components within them at                  so than finding a contractor to continue
all stages of manufacture. This can be             to build out a traditional construction
achieved (to some extent) by third                 project. Therefore it is critical to
party bonds and vesting agreements.                understand the financial covenant
We have also seen funders take a                   strength of the modular supplier and
charge over the factory and plant where            obtain appropriate performance security
the modules are being constructed, but             through bonds or guarantees or to look
this may not be possible in many cases.            to cover off the risk through insurance.

           Title – there are two title                      Transit Risk/Insurance –
           issues which require specific                    the risk of damage to the
           consideration when it comes to                   modules in transit needs to
modular construction. One is ensuring              be considered and the risk allocated
that the developer or funder has title             appropriately, backed by suitable
over the constructed modules before                insurances.
their delivery to site. The second issue
is that often a developer will provide             Modular construction is clearly going
certain elements of the modules to                 to play a key part in the future of
the module supplier for the supplier to            construction and has the potential to
incorporate into the module, such as               revolutionise the construction market
tiles, or white goods, so any contract             but developers and funders must ensure
needs to deal with title in the developer’s        that these key risk areas are addressed
goods to ensure that title is retained.            if they are to reap the benefits.

                                              12
13
5
HMO licensing reform –
disappointing news for
PBSA providers
The approach to HMO licensing of                into the mandatory licensing regime,
student accommodation properties                although most of these properties will
varies greatly between different local          not be PBSA schemes as purpose-built
authorities. This trend looks set to            self-contained flats will be exempt.
continue, with the recent government
response to a consultation proposing            However, as many PBSA providers
to extend the scope of mandatory                will have experienced first-hand, it is
HMO licensing, without taking forward           not mandatory licensing that tends to
proposed licensing discounts for PBSA.          catch PBSA schemes but additional or
Indeed, the Licensing of House in               selective licensing introduced by the
Multiple Occupation (Prescribed                 relevant local authority.
Description) (England) Order 2018 (SI
                                                Additional licensing can be used to
2018/221) (“LHMO 2018”) brings into
                                                cover HMOs which are not subject to
force some of the changes promised
                                                mandatory licensing (e.g. HMOs that are
by the government as a result of its
                                                occupied by less than five people) while
consultation.
                                                selective licensing can cover properties
Most significantly, the extension of            which are not HMOs. For example,
mandatory licensing in the LHMO 2018            some local authorities have introduced
will mean that most HMOs that are               selective licensing regimes covering
occupied by five or more people who             all privately rented properties within a
do not form a single household will             specified area, including individual flats
require an HMO licence,regardless of the        and studios within PBSA schemes.
number of storeys. Mandatory licensing
currently only applies to HMOs of three
or more storeys. This change is expected
to bring another 160,000 properties

                                           14
The existing licensing exemption for              enforcement of licence conditions for
student accommodation schemes                     all purpose built HMOs. This decision
that are occupied by full time students           will be disappointing for PBSA providers
and managed by an educational                     who are already accredited through
institution pursuant to an approved               an approved code and may well see
code will continue to apply following             HMO licensing fees as a duplication of
implementation of the reforms. But                costs and a means of subsidising local
such exemption will not be extended to            authority enforcement in relation to
PBSA owned and managed by private                 problem properties.
landlords who have similarly adopted an
approved code of practice.                        The extension to the mandatory
                                                  licensing regime in the LHMO 2018,
The government did recognise in its               together with the government’s other
consultation paper that such licensing            reforms (such as obliging the Secretary
of PBSA schemes was not necessarily               of State to review these provisions
appropriate or proportionate, on the              at least every 5 years) will come into
basis that PBSA tends to be well-                 force on 1 October 2018. Transitional
managed and requires little local                 measures are included for HMOs that
authority intervention. Accordingly,              are already licensed under the selective
“significant discounts” on HMO licensing          licensing provisions, but which will be
fees for PBSA were proposed. This                 subject to the new regime from when
proposal was not taken forward in the             LHMO comes into force.
government’s response, nor in the
LHMO 2018, amid concerns that such
a discount may be seen as a barrier to
local authorities being proactive in their

                                             15
Moreover, although currently in               requiring the licence holder to ensure
draft form, the Licensing of Houses           that minimum floor areas are met
in Multiple Occupation (Mandatory             and maximum occupancy numbers
Conditions of Licences) (England)             are not exceeded in relation to rooms
Regulations 2018 stipulates certain           used as sleeping accommodation. This
mandatory conditions to be included in        may have an impact on the design of
HMO licences granted in England. The          PBSA schemes that are caught by
draft regulations include requirements        the mandatory or additional licensing
for HMO licences to impose conditions         regimes.

                                         16
17
6
Taxing times ahead for
offshore investors, but
some positive news for
developers
Changes announced at the Autumn                   2015 include a specific carve out for
Budget 2017 to the scope of capital               purpose built student accommodation
gains tax will affect many offshore               based on the number of bedrooms in the
property owners, including those in               building and the number of days they are
the student accommodation sector.                 occupied by students. It is not expected
It was announced that, from April                 that there will be any similar carve out
2019, capital gains tax will be extended          for student accommodation with these
further to non-residents investing in UK          rules – the stated aim is to establish a
commercial property. However, there               level playing field for taxation of non-
will be an automatic “rebasing” to April          residents and residents alike investing in
2019, which effectively means that gains          UK property.
accruing prior to April 2019 will not be
subject to tax for non-residents.                 Also relevant for the student
                                                  accommodation sector were the
The new rules will also apply to in-direct        decisions of the First-tier Tribunal and
disposals of UK commercial property               Upper Tribunal in Summit Electrical
(ie exits via the sale of shares or               Installations Limited v HMRC. This may
comparable interests).                            result in cash flow savings for many
                                                  student accommodation contractors
This will be a major change in the                who may find it more likely that they will
nature of taxation for non-residents              be able to avoid paying VAT on sub-
and will affect owners of student                 contractor’s charges.
accommodation that hold assets through
offshore vehicles. The non-resident
capital gains tax rules on UK residential
property that were introduced in April

                                             18
The Upper Tribunal decision confirmed            As set out earlier in this report, this
that a planning permission condition             decision should also offer some
stating that a building has to be used           comfort to the concerns around the
for students attending a particular              VAT risk with the draft new London
university does not preclude a building          Plan and requirement for nominations
from being ‘designed as a dwelling’              agreements.
for VAT purposes. The restriction on
zero-rating by reference to separate use         The First-tier tribunal also determined
was concerned with situations where a            that if a relevant residential purpose
property was in effect legally dependent         certificate has been issued by the end
on another property, so that it was not          user to a contractor (which only allows
possible to dispose of the first property        a contractor to zero rate supplies) this
separately from the second.                      does not prevent a sub-contractor
                                                 from being able to treat the building
The restriction in this case was based           as designed as a dwelling and hence
on specified universities at which               zero rating its supplies on that basis.
the occupants studied, rather than               However, unfortunately this point was
particular properties. This was not a            not confirmed in the Upper Tribunal
prohibition on separate use and the              (because HMRC did not appeal this
building could be a dwelling. Where a            point). Therefore, this aspect of the
building is designed as a dwelling (or           decision should be met with some
a number of dwellings) this broadly              caution as HMRC’s guidance in the area
allows sub-contractors to zero rate their        has not yet changed.
supplies for VAT purposes.

                                            19
7
Staying ahead of the
game
Competition for the development pipeline          Forward funding perhaps requires a
has become fierce and in order to secure          greater reliance on the data providers in
prime product early, we are now seeing            the industry in analysing local markets
an increased “willingness” of investors to        and getting the pricing models right.
engage in forward funding arrangements
with developers, often prior to planning          These structures inevitably present
consent being obtained. Perhaps this              their own legal nuances that need to be
is more a tacit acceptance by some                addressed in negotiating the right deal
investors that early commitment to and            at the heads of terms stage.
funding of schemes is a necessity to stay
ahead of the game.

A typical forward funding structure

                      MARKET VALUE
                        OF LAND

                                                            Lease (25 years, rent
                        Conditional                         linked to net income)
  LANDOWNER /             Sale               FUND
   DEVELOPER             Contract
                                                                           OPERATING
                                                                              SPV
                                                         DEVELOPER’S
                        PROPERTY          Forward           PROFIT                  Assured
                                          funding                                   shorthold
                                         agreement                                  tenancy
                                                                                    agreements

                                                                           OCCUPIERS
                                        DEVELOPER

            PROFESSIONAL                 BUILDING
                TEAM                    CONRACTOR

                                      SUB-CONTRACTORS

                                             20
21
8
Taylor Wessing’s key
predictions for 2018
ff   Growth of hybrid co-living                  ff   Increased collaboration with
     schemes – reacting to the                        Universities – with limited
     constraints of the planning regime,              availability of land for new PBSA
     we envisage seeing more new                      and highly competitive land uses, we
     development schemes offering a mix               expect to see greater teaming up
     of PBSA and co-living targeting the              between developers, operators and
     graduate market.                                 Universities to upgrade or rebuild
ff   Launch of new operating platforms                existing stock.
     and brands – we expect to see the
     launch of new operating platforms
     and existing operators increasing
     their capex on brand differentiation
     and focusing on the legal protection
     of their brands.

                                            22
ff   A highly competitive market with             ff   Innovative operating – we expect
     potential new entrants to the                     operators to look at more innovative
     sector – we expect to see an                      pricing models and opportunities
     increase in the number and scale                  to maximise income outside of
     of acquisitions of equity stakes in               academic semesters.
     established investment and operating         ff   Beyond the UK – established
     platforms and intense competition for             investors in PBSA in the UK looking
     the development pipeline leading to               to other European and global
     more speculative forward funding of               opportunities.
     prime new development schemes.
ff   A focus on innovation in the
     delivery of new PBSA – as well
     as an increase in adoption of
     modular construction, we envisage
     an increased uptake of proptech
     solutions to improve efficiencies in
     the delivery of PBSA.

                                             23
9
Key contacts

    Paul Leamy (Real Estate)                               Natasha Cooper (Corporate)
    Partner, London                                        Senior Associate, London
    +44 20 7300 4656                                       +44 20 7300 4871
    p.leamy@taylorwessing.com                              n.cooper@taylorwessing.com

    Alistair Watson (Planning and Environment)             Harriet Revington (Tax)
    Partner, London                                        Senior Associate, London
    +44 20 7300 4240                                       +44 20 7300 7109
    a.watson@taylorwessing.com                             h.revington@taylorwessing.com

    Heather Buttle (Banking and Finance)                   Charlotte Chambers (Corporate)
    Partner, London                                        Senior Associate, London
    +44 20 7300 4141                                       +44 20 7300 4201
    h.buttle@taylorwessing.com                             c.chambers@taylorwessing.com

    Robert Young (Tax)                                     Daniel Williams (Banking and Finance)
    Partner, London                                        Associate London
    +44 20 7300 4201                                       +44 20 7300 4739
    r.young@taylorwessing.com                              dr.williams@taylorwessing.com

    Jill Hamilton (Construction)
    Senior Counsel, London
    +44 20 7300 4868
    j.hamilton@taylorwessing.com
                                                 We would welcome the opportunity
                                                 to explore any of the issues
    Chris Komodromou (Real Estate)               identified in this report with you in
    Senior Associate, London
    +44 20 7300 4269                             greater detail.
    c.komodromou@taylorwessing.com

    Hanna Ross (Real Estate)
    Senior Associate, London
    +44 20 7300 7154
    h.ross@taylorwessing.com

    Emma Tait (Planning and Environment)
    Senior Associate, London
    +44 20 7300 4952
    e.tait@taylorwessing.com

                                           24
Europe
                                                    Austria: Vienna | Klagenfurt        Netherlands: Amsterdam |
                           Americas                 Belgium: Brussels                   Eindhoven
United States: New York* | Menlo Park*              Czech Republic: Prague | Brno       Poland: Warsaw

                                                    France: Paris                       Slovakia: Bratislava

                                                    Germany: Berlin | Düsseldorf |      Ukraine: Kiev
                                                    Frankfurt | Hamburg | Munich        United Kingdom: London |
                                                    Hungary: Budapest                   London Tech City | Cambridge

                                                                                             Asia
                                                                                             China: Beijing | Shanghai
                                                                                             Hong Kong: Hong Kong
                                                                                             Singapore: Singapore
                                                                                             South Korea: Seoul
                                                                                             Vietnam: Ho Chi Minh City | Hanoi

                              Middle East
               Saudi Arabia: Riyadh | Jeddah
                                 UAE: Dubai

                                                        Taylor Wessing locations:              Office        Associated firm
                                                                                              *Representative office

                                                        Taylor Wessing entities operate under one brand but are legally distinct, either being or
                                                        affiliated to a member of Taylor Wessing Verein. Taylor Wessing Verein does not itself
                                                        provide services. Further information can be found on our regulatory page at
                                                        www.taylorwessing.com.

                                               25
Europe > Middle East > Asia                                                                  taylorwessing.com
© Taylor Wessing LLP 2018
This publication is intended for general public guidance and to highlight issues. It is not intended to apply to specific circumstances
or to constitute legal advice. Taylor Wessing’s international offices operate as one firm but are established as distinct legal entities.
For further information about our offices and the regulatory regimes that apply to them, please refer to: www.taylorwessing.com/
regulatory.html

TW_002107_06.18
You can also read