KEKERENGU CLARENCE (MATARIKI) RAKAUTARA HAPUKU KAIKOURA TOWNSHIP PEKETA OMIHI GOOSE BAY (OTEMAKURA) OARO SH1 2017/2018 Consultation Document for the Draft Annual Plan Kaikoura District Council Reimagine Kaikoura Pōhewatia anō a Kaikōura A sustainable future for the Kaikoura District 2017/2018 Consultation Document for the Draft Annual Plan
Reach-out Reconnect Resilient Reevaluate Replenish Revitalise Reassess Repair Rebuild Research Rejuvenate Rediscover Review Rejoice Reimagine 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 2
RECOVERY VISION Kaikōura District recovers and moves forward as a great place to live – has a strong, well-connected community, is ecologically exemplary and economically prosperous. Image Andrew Spencer 3
RECOVERY GOALS Strengthen community resilience, safety Community and wellbeing; ensure everyone in the community has their essential needs met; and enhance quality of life for residents and visitors. Establish strategic partnerships to attract investment; develop support structures Economy to provide certainty around businesses and employment continuity; and explore avenues of economic diversification to enhance economic and social resilience. Build cost-effective and easily accessible Built infrastructure, transport networks, housing and buildings which are able to withstand Environment extreme weather events, flooding, tsunamis, earthquakes and landslides. Natural Restore, protect and enhance Kaikōura’s unique natural environment and Environment biodiversity and sustainably manage disposal of waste. Looking to Develop a comprehensive resilience monitoring and review system, and the Future investigate future opportunities presented by the earthquake for improving infrastructure and tourism. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 4
INTRODUCTION Welcome to the Kaikōura District Council’s Consultation Document for the Draft Annual Plan 2017/2018. The 14 November 2016 7.8 magnitude earthquake had wide reaching effects on our District. The damage to Council infrastructure, property and community facilities was extensive. As a result, Council plans, projects, funding and strategies have had to be significantly reviewed and updated. The 2017/2018 financial year is the third year of the current ‘Long Term Plan 2015/2025’ which is the main planning document for the Kaikōura District and where major decisions are made. The Long Term Plan will be fully reviewed in 2018. In the meantime this consultation document and the Draft Annual Plan 2017/18 outline plans for the next 12 months. This is a snap-shot of where we are now, the decisions we need to make and the work we intend to get done over the next year. This document focuses on the top matters of interest to our residents and ratepayers and would like to know what you think. The full Draft Annual Plan and supporting documents are available through www.kaikoura.govt.nz Once you’ve read this draft, please provide us with your feedback – instructions are on the final pages. Wakatau (Chief Kaikōura) wearing cloak, feathers in hair, holding a spear. He was killed by a fall from his horse in 1868. Original photo in possession of Mr Rangi Solomon, Oaro. Image courtesy of Kaikōura Museum. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 5
TABLE OF CONTENTS Message from the Mayor 7 Message from the Chief Executive Officer 8 New Focus – Community Development 11 New Focus – Economic Development 13 Deferral of Long Term Plan Projects 15 Infastructure Rebuild 16 Community Facilities and Buildings 19 Natural Hazards 20 Impact of Earthquake Costs on Financial Strategy, Rates Remissions and Rates 22 What does all this mean for your Rates? 25 Forecast Financial Statements 26 How to give us your feedback 27 Draft Annual Plan feedback 28 Pou at Takahanga Marae, Kaikōura. Image courtesy of Fairfax Media NZ/Marlborough Express. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 6
MESSAGE FROM THE MAYOR The earthquake that struck on 14 November 2016 continues to have far reaching impacts across our District – socially, economically and on our natural environment. For most of us the ‘third winter’ is very much a reality and the road to recovery is long. This year’s Annual Plan is a significant reprioritisation of Council workplans. Why reprioritise? Our infrastructure has been severely impacted so some planned work will need to be delayed to allow us to focus on the immediate rebuild. Council is facing an approximate forecast cost of $40M, roughly five times our annual spend. The ongoing isolation by road has directly affected 50.4% of our workforce and been felt widely by our businesses. The 1.5 metre uplift in the harbour has dramatically affected commercial operators who can currently only run 30-40% of scheduled tours. The isolation and reduction in tourist numbers has led to a marked decline for our accommodation and retail sectors. Socially we continue to see the after effects of the earthquake – temporarily displaced residents, the ongoing need for psychosocial support and financial and insurance advice for homeowners through the personal rebuild process. I am extremely appreciative of all the financial and other support our District has received since the quake. Sources of support include: Environment Canterbury, the Ministry for Primary Industries, the Ministry for Business Innovation and Employment, the Ministry of Civil Defence & Emergency Management, the Ministry of Health, Lotteries and the Rata Foundation, the Red Cross, the Rural Support Trust, Te Rūnanga o Ngāi Tahu and Te Rūnanga o Ngāti Kuri, Te Puni Kōkiri, Whanau Ora Agencies, Sports Tasman, Sports NZ and JR McKenzie Trust and local organisations and individuals. This funding and collaborative support is essential to our District’s recovery and ensures we can continue to sustainably operate into the future. When residents of our District created the recently launched ‘Re- imagine Kaikōura’ Recovery Plan they recognised the long term nature of recovery and the long road ahead. The community’s passionate contributions to our Recovery Plan are testament to their resilience. The Annual Planning process is a critical part of our District’s recovery and rebuild. Council has to carefully manage its finances and workload to achieve the best it can for residents and ratepayers in the long term. The Recovery Plan, the Annual Plan 2017/18 and the Long Term Plan 2015-2025 will work together to create a future roadmap for our District. This consultation document is a chance for you to have your say about that plan. Winston Gray Mayor At the end of the day it’s not just about recovering what we had. It’s about enabling us to move into a new future and take Kaikōura from good to great. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 7
MESSAGE FROM THE CHIEF EXECUTIVE OFFICER Welcome, and thank you for taking the time to read the Kaikōura District Council’s Consultation Document for the Draft Annual Plan 2017/2018. I hope you’ll provide feedback and let us know your views. The 14 November quake caused sizeable damage to our infrastructure (water, wastewater, roads and community facilities and property). The scale of the damage is comparable to that faced by Christchurch after the Canterbury earthquakes. We have been left shaken, in some cases a little stirred, and facing significant issues. Re-imagining our District will take time, commitment and endurance. The Council will do everything possible to support the District as it recovers. Along the way we’ll face difficult choices between what must be done now, and what will need to wait and how we manage our finances to get the best solution for the District. After the quake the Recovery Team worked with the community to develop the Recovery Plan ‘Re-imagine Kaikōura’. Together they identified goals to work towards through the recovery and rebuild work. The Annual Plan for 2017/18 starts working towards these goals. These goals are; 1. Developing a sustainable economy 2. Rebuilding quality facilities and infrastructure 3. Enabling a strong and healthy community 4. Protecting and enhancing the natural environment 5. Striving for a resilient and positive future Next year’s review of the Long Term plan will build on this and confirm our future work programme. Here’s how the Council will work towards them in the next 12 months. 1. Developing a sustainable economy The isolation from the north, and intermittently from the south, has had a significant impact on our local tourism businesses. Other businesses are prospering from the increased construction activity. We will continue to work with the Canterbury Chamber of Commerce to drive business diversity and to source insurance and business advisers to help businesses through the changes. Ongoing business support is available through the $848k Business Recovery Grants Programme, funded by central government. Image Andrew Spencer Longer term we need to recover and further develop our tourism infrastructure such as the marina, harbour and airport. Such development takes time but we have identified the first steps and milestones, putting us on the road for long-term success. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 8
2. Rebuilding quality facilities and infrastructure Over the next 18-24 months Council needs to spend five times our normal annual infrastructure budget as part of the rebuild programme. Getting this rebuild programme done on time, within budget, and to the required standard is our top priority. Most things that the community takes for granted (clean safe water, operational sewerage system and safe roads) require extensive rebuild work. This is estimated to cost close to $40 million. In the next 18-24 months we will focus on; • road rehabilitation works down Mt Fyffe, Mill and Red Swamp roads • repair structural damage to bridges • re-install the main sewer line and replace pump stations • replace water reservoirs • repair sewer and water reticulation systems. In the short term we do not have the financial resources to replace and restore all existing community facilities. We are working with Sport Tasman, Sport NZ and the local sporting groups to assess the District’s needs and the affordability of new sport and recreational facilities. Tourist attractions are Kaikōura Districts’ main drawcard. Over 50% of our workforce is dependent on the tourism industry, so getting the harbour functional again by the next tourist season will be a significant achievement. We have made significant progress re- instating the harbour slipways both for recreational and commercial users. We are currently finalising the dredging and excavation in the South Bay harbour. We are appreciative of financial support from our operators as part of this restoration. 3. Enabling strong and healthy communities We are making a long-term commitment to community development, bringing on-board new staff with a community development focus. Council will continue to walk alongside our community, identifying needs and seeing how best we can facilitate support and assistance. The earthquake and resulting damage to property, possessions and people are traumatic events. For many, a sense of loss and anxiety is part of our ‘new normal’. Our staff continue to work with the CDHB and others to provide help to those who need it. Council is providing support for those navigating the insurance process. We encourage all residents to seek Image Andrew Spencer out the help and advice they need. I believe we have a prudent sustainable budget which enables the Council to restore and replace the damaged infrastructure and continue to provide the same level of services. Our debt is well within our cap and our debt servicing costs are affordable. While rates increases are inevitable, we have smoothed the rates increases over a period of three years to keep increases affordable for our community. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 9
The Council has also developed a rates relief package for earthquake and aftershock damaged properties that are; • damaged to the point of being uninhabitable • unsafe to occupy • or where their use has been significantly affected. Under this package owners of red-stickered and uninhabitable homes on less than one hectare will receive a 100% rates remission. Uninhabitable houses and farm buildings on land greater than one hectare, and commercial businesses which are red-stickered or unsafe to occupy, will receive a rates remission which has the effect of writing off rates leaving only those rates that would apply if the property were bare land. 4. Protecting and enhancing the natural environment One of the strongest themes found in the recovery planning process was how grateful everyone was to live in such a beautiful place. Protecting Kaikōura’s environment and natural beauty is a vital part of the rebuild and recovery work. In the short-term Council has received Government funding to develop a sustainable waste management plan to deal with quake related waste. This will cover things like asbestos management, infrastructure repairs and increased recycling support. We are currently reviewing all the natural hazards caused by the earthquake. This includes identifying the risks they pose and how these risks can be minimised or managed. 5. Striving for a resilient and positive future The vision for our District as outlined in the Recovery Plan is: ‘Kaikōura recovers and moves forward as a great place to live – has a strong, well- connected community, is ecologically exemplary and economically prosperous.’ For now, we are rebuilding our homes, businesses, Council facilities and infrastructure. We are re-establishing our access to the outside world. We are repositioning our tourism and economy. This Annual Plan builds on the Recovery Plan to put in place the structures and systems we need to achieve the future we have re-imagined together. Re-Imagine Kaikōura Pohewatia ano a Kaikōura Angela Oosthuizen Chief Executive Officer 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 10
NEW FOCUS - COMMUNITY DEVELOPMENT COMMUNITY Community development involves co-ordinating local social services and promoting community-led initiatives. This includes supporting youth, the elderly, people with disabilities and families by tackling issues such as social isolation, family violence, alcohol and other drug use. By focusing on community development Council will ensure the social elements of the District’s recovery are put in place to support residents. We are working with organisations including Police, Work and Income, Child Youth and Family, Te Tai o Marokura and Ministry of Social Development. Community development targets the following outcomes: • There is a safe environment for all • The community’s health and social service needs are met • The community’s cultures, arts and heritage are conserved and celebrated • People have wide ranging opportunities for learning and being informed • People are friendly and caring, creating a strong sense of community in our District • Public effect is given to the spirit of the Treaty of Waitangi • There are wide ranging opportunities for people to contribute to local, regional and national organisations’ decisions that affect our District The Community Development team has; • identified currently available social services • identified emerging earthquake related needs and gaps • increased capacity where possible by working with existing agencies. We will ensure residents ongoing safety and wellbeing by; • ensuring that psychosocial support is provided • ensuring that short term accommodation needs are addressed throughout the rebuild process • ensuring residents and ratepayers are supported through the insurance process • advocating for youth programmes • supporting the Youth Council. Image Andrew Spencer Image Andrew Spencer 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 11
Impact on levels of New priority Cost and funding Impact on rates COMMUNITY service Total cost increases by $466k, Council received New roles support Eight new roles (mixture of funding of $198k near the social recovery Community permanent and 12-month the end of 2016/2017 to process as a critical Development fixed term contracts), largely be used for community part of our District’s funded by external grants. support coordinators. recovery. Impact on rates as per table on page 25. Goal: Strengthen community resilience, safety and wellbeing; ensure everyone in the community has their essential needs met; and enhance quality of life for residents and visitors. Image Andrew Spencer 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 12
NEW FOCUS - ECONOMIC DEVELOPMENT In the 2016/2017 Annual Plan Council started to broaden our focus from relying on tourism as the main economic driver for Kaikōura to encouraging wider economic Development. We realised we needed to build resilience into our economic base, encourage diversification and attract new business and investment. The lack of road access and isolation post-earthquake has reinforced that tourism, although vital to our District, is not enough to ensure our economic success. Broadening the focus for economic development will result in larger financial and other support for the District, ensuring Kaikōura has a future with employment opportunities, economic prosperity and new business opportunities. ECONOMY In the short term, economic recovery and development will focus on the recovery. Working with industry sector groups to meet specific needs and projects. This includes; • managing hospitality contracts between Compass and local hospitality providers • working with retailers to reinvigorate the retail space • working with Tourism on rolling out domestic marketing campaigns • facilitating the distribution of grants to viable local businesses to help them survive the winter • providing advice to businesses that are ineligible for the grant process through the regional business partnership program • working closely with the Canterbury Employers Chamber of Commerce, Canterbury Development Corporation and the Government on continuing support for businesses. Longer term, an economic development strategy will be needed. This will include working with local businesses to provide effective support and advice, possibly including formalising the local business forum and a developing a governance structure. The strategy will also include investigating key projects flagged in the recovery plan such as the commercial development of the harbour and airport and the setup of a marine research project. The first step for these projects is a feasibility Image Andrew Spencer study. New priority Cost and funding Impact on rates Impact on levels of service A new business association, Three new roles, plus Total cost of $285k, and a business mentor establishing a business Council receives programme, will be Economic association and a business subsidies of $253k. established to support Development mentor programme. Impact on rates as per local businesses get back Mosts costs funded by table on page 25. on their feet and make the Government grants. most of new opportunities. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 13
Goal: Establish strategic partnerships to attract investment; develop support structures to provide certainty around businesses and employment continuity; and explore avenues of economic diversification to enhance economic and social resilience. ECONOMY Image Andrew Spencer Image Dan Kerins Image Haley Baxter 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 14
DEFERRAL OF LONG TERM PLAN PROJECTS Earthquake-damage significantly affected most things that the community takes for granted (clean safe water, operational sewerage system and safe roads). These are critical to the functioning of the District and as such are the priority for Council funds. Council cannot fund both the infrastructure rebuild and all Long Term Plan projects as planned. In some cases, the projects from the Long Term Plan will be incorporated into the rebuild. Image Andrew Spencer The table below lists Long Term Plan projects affected by the earthquake, their new anticipated cost, new estimated delivery date and the reason for the change: Long Term Projects Project Cost Timing Rationale Old Beach Road Intersection $420k in 2017 to 2021/2022 Reassess in Long Term Plan BUILT 2018, 2019, 2020, Bridge Replacements $100k Addressed as part of Rebuild 2021 Re-alignment of SH1 $ 658k 2021 Reassess in Long Term Plan Planned Roading in 2017/2018, Partially addressed as part of $80k Rehabilitation 2018/2019 Rebuild Replace water main line $ 330k in 2017/2018 Restoration already undertaken Replace reservoirs $ 55k 2017/2018 Addressed as part of Rebuild South Bay marina Upgrade $494k 2017/2018 Addressed as part of Rebuild Community Sports centre $3.4M 2019/2020 To be externally funded Ludstone Road Drainage $220k 2017/2018 Reassess in Long Term Plan New priority Cost and funding Impact on rates Impact on levels of service Rebuild goes ahead, restoring Reduction in long Defer Long Term Plan As per table on all core earthquake-affected term plan capital projects as outlined. page 25. infrastructure. Long Term Projects costs for 2017/18. are delayed. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 15
INFRASTRUCTURE REBUILD Infrastructure rebuild costs will be shared between the Kaikōura District Council (KDC), New Zealand Transport Agency (NZTA) and Central Government, represented by the Ministry of Civil Defence & Emergency Management (MCDEM). NZTA will fund 95% of the costs of all eligible earthquake related local roading repairs, MCDEM will cover 60% of eligible water, stormwater and wastewater infrastructure costs, and KDC and its insurers will fund the balance. Our new Rebuild Director will work with a Rebuild Steering Group that includes the three major funders of the rebuild. Together they will provide the experienced advice and support we need to deliver the rebuild within the funding constraints and timelines. We’re also bringing on additional building inspectors and upgrading our building processing and inspection systems to help with the increased number of building consents being received post-quake. For most earthquake-damaged infrastructure there are several rebuild options ranging from do nothing to return to service to restoring it to levels better than pre-earthquake. Council will carefully consider all options for each aspect of the rebuild and choose the options that achieve the best outcomes and level of service for the district as a whole. BUILT Goal: Build cost-effective and easily accessible infrastructure, transport networks, housing and buildings which are able to withstand extreme weather events, flooding, tsunamis, earthquakes and landslides. Image Andrew Spencer 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 16
Significant Rebuild Projects: Local Roads Overlays Length (m) The 2015-25 Long term Plan identified a roading Mt Fyffe Road 2910 rehabilitation programme which had been deferred until funding was available to complete Hawthorne Road 705 a percentage of the programme economically. However, the road repairs that are required Mill Road 700 following the earthquake mean that some of our roading rehabilitation can now be done at the Red Swamp Road 500 emergency subsidy rate of 95%, instead of the standard subsidy rate of 51%. Total 4815 Bridges The earthquake damaged five single lane bridges beyond repair – Gillings Lane, Hawthorne Road, Rorrisons Road, Evans Bridge and Scotts Road. These will be replaced as part of the rebuild. The seven span 125m long Glen Alton bridge was substantially damaged. A business case will be developed discussing all potential options and ensuring all stakeholders have input into the final decision. In the meantime Council is BUILT upgrading the road on the south bank to a reasonable four-wheel drive standard, however due to the requirement to cross the Wharekiri Stream this is not an all weather access. Image KDC Water Work required as part of the rebuild includes; • Urban and rural water reticulation repairs in Mill Road, Gillings Lane and Hawthorne Road • Replacing tanks in the Kincaid scheme • Replacing and repairing damage in the Fords 1 and 2 reservoirs • Repairing minor damage to the Fords 3 reservoir, Peninsula reservoirs and Ocean Ridge bores • A replacement bladder and an appropriate holding down system for the Ocean Ridge timber tank • Ensuring the quality of the Peketa water supply either by securing a new water supply or filtering and treating existing supply in perpetuity. Wastewater Work required as part of the rebuild includes; • Repairing or replacing the aeration lagoon • Replacing the sewer main along Lyell Creek from the Lyell Creek pump station to the 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 17
Mill Road pump station. Note: significant planning is required to reach the optimal solution due to extensive damage to the sewer and surrounding houses and related issues. It will be some time until the final shape of the land adjacent to Lyell Creek is known and a decision of the location of the sewer main can be finalised • 45 manholes requiring repair or replacement • Repairing various mains including, Mill Road Rising Main , Gravity Mains in Mt Fyffe, Hawthorne Road, Ocean Ridge and the Esplanade / West End • Repairing minor damage to the wastewater treatment plant pump station (WWTP), The Esplanade and Ocean Ridge Pump Stations • Repairing substantial damage to the Mill Road and Totara Lane Pump Stations and damage to the Hawthorne Road and Gillings Lane Pump Stations. Summary of Anticipated Costs and Funding: Below are the forecast costs and funding for the 2017/2018 financial year, not the total cost of the earthquake rebuild. Some costs have already been incurred in the period to 30 June 2017, and there are projects that will continue beyond 1 July 2018. Area Cost 2017/2018 Funding 2017/2018 Comments Does not include a permanent solution Local Roads Loan $280,000 $3,705,000 for access to the Clarence Valley; options & Bridges Subsidies 3,425,000 yet to be agreed Subsidies $1,242,000 Water $2,070,000 Insurance $202,000 Reserves $626,000 The government will fund 60% of repair BUILT Subsidies $2,257,800 of council owned essential infrastructure Wastewater $3,763,000 Reserves $266,000 (above a threshold) with the net cost (sewerage) Loan $1,239,200 covered by loan until insurance claims are settled. Subsidies $498,696 Stormwater $831,160 Insurance $312,464 Reserves $20,000 Image Andrew Spencer 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 18
COMMUNITY FACILITIES AND BUILDINGS The swimming pool, skate park, tennis courts and Jimmy Armers toilet facilities were all significantly damaged by the quake. Council investigations have shown that it would cost more to repair these than it would to replace them. At this stage the Council is not in a position to confirm the replacement or alternative options, or how these would be funded. Minor work to make the sites safe, tidy, or provide a bare minimum level of service has been completed. Council is continuing to investigate options and work with insurers. A solution for each facility will go into the Long Term Plan. External funding has been sourced by Sport Tasman for a feasibility study for the pool. The study should be completed by September 2017 and will look at community needs, assess site and facility options and develop a preferred option for discussion. Council and staff are currently working with Sport Tasman, Sport NZ and the local sporting groups to develop sport facilities in our District. In the short term external funding has been sourced to support sporting events. In the medium to long term we will identify a network of facilities that can meet our Districts needs both now and in the future. BUILT New priority Cost and funding Impact on rates Impact on levels of service Community facilities No impact for Temporary swimming pool in rebuild considered as As per table on 2017/18 financial place, minor repairs undertaken part of Long Term Plan page 25. year. to skate park and tennis courts. review in 2018. Image Andrew Spencer 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 19
NATURAL HAZARDS There were several localised hazard events triggered by the earthquake including rockfall, boulder roll, debris flow, slope stability, landslide, and shingle flows. Post-quake, Council has developed a workstream for each hazard, keeping the community informed through public meetings or direct contact. Council continues to investigate the risks posed by natural hazards, and prevent people and property from exposure to these risks, using legislative powers if required. Where there is a risk to life, properties have received a yellow or red placard, restricting access or preventing occupation. The situation is complicated - some affected properties have limited or no damage to their building, some of the hazards that pose life-risk are located on other land. In some cases, owners are not eligible for insurance cover or accommodation help, in others there is a question around who would fund any repair work or compensation. Residents need a long term solution. Council is working with central Government to develop this and is working hard to support and inform residents in the meantime. Council is working to make sure all geotechnical engineering work is not duplicated and all knowledge is shared; keeping costs down. NATURAL Image KDC 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 20
Waste Minimisation An important part of the earthquake recovery is the careful management of the thousands of tonnes of additional waste, particularly hazardous materials. The demolition and rebuild work needs to be done quickly but waste needs to be managed properly so we do not create environmental and health problems now or in the future. Our District has received a $670,000 grant to help Council rebuild our waste facilities, recycle as much as possible of the huge increase in waste and carefully manage hazardous waste like asbestos. There is a significant risk to community health and wellbeing from hazardous waste such as chemicals like bleach or ammonia; herbicides or pesticides like glyphosate; paints, fuels and oxidisers. These are often left behind during the evacuation or abandonment of buildings, and can contaminate or complicate the demolition process. Homeowners will be offered assistance with asbestos and hazardous substance checks in exchange for providing information in regards to structural engineering, demolition methods, site information and waste disposal options. This will help us ensure the site is safe to work on, best practice health and safety methods are followed, a reputable contractor is used, District and Regional plans and Heritage New Zealand rules are followed, and a legal disposal method is used. Proper deconstruction will mean only clean-fill waste with little residual waste. Benefits to our community will include protecting the health and wellbeing of the Kaikōura Community, and natural environment, reduced health and safety risks, effective management of post-earthquake demolition waste and being cost effective or neutral to Council. Goal: Restore, protect and enhance Kaikōura’s unique natural environment and biodiversity and sustainably NATURAL manage disposal of waste. Image Dan Kerins Image Dan Kerins 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 21
IMPACT OF EARTHQUAKE COSTS ON FINANCIAL STRATEGY, RATES REMISSIONS AND RATES Council is faced with a significant financial burden to restore our infrastructure to its pre-earthquake condition, while placing as little stress on our ratepayer and business community as possible. Earthquake Cost and Funding The total cost of the earthquake is currently estimated at $40M, which includes $25M to replace assets, $6.7M to reinstate the harbour, and $7.8M in response, recovery and temporary repairs. Funding is currently assumed to come from a variety of sources, in addition to council loans, reserves and rates. This includes; • Local Authority Protection Programme (LAPP) • Material damage insurance • NZTA subsidies for local roads • Other government subsidies • Harbour user contributions The Council’s Finance Strategy sets a debt limit at $12M, which includes an allowance for emergency events of $2M. This Draft Annual Plan provides for our loans to reach up to $9 million in 2017/2018 and up to $10 million in the next three years. As a low-growth district, our loan interest should be no more than 10% of total revenue, and we forecast to achieve 4.63% in 2017/2018 (which is $462,235). Image Andrew Spencer 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 22
Financial Assumptions • The government will (“frontload”) fund the 3 waters 60% to assist the council with cash flow and the council can seek additional support to assist the rebuild • The government has recognised the council’s additional statutory activities as a result of the earthquake and some additional support from the government is factored into assumed revenue • $6m government grant for harbour with external contributions from operators for shortfall • NZTA will pay a 51% subsidy rate for normal roading maintenance, and 95% for earthquake related damage to local roads and bridges • Loan funding for Council earthquake shortfall will be externally financed at fixed interest rate over a repayment period of 20 years • Assumption of full contribution from Material Damage insurers and LAPP, except for material damage for the harbour (assumed not paid) • Address smoothing of rates increases over a period of time – by raising cashflow loans and utilising all available cash reserves Level of uncertainty • The timing of projects and receipts from funders are extremely fluid, with some projects already underway and others expected to carry over to subsequent years. Similarly, the timing of incoming funds from subsidies and insurance claims are based on best estimate but are extremely likely to differ from predictions • Risk of further events which could exacerbate the estimates damage and increase costs • Further investigations around leak detection and CCTV footage may reveal further reticulation damage which may lead to escalated costs • Risk that insurance payments may not eventuate or be at the level predicted • Risk of price and material increases from contactors as time progresses • Risk of land impacted by natural hazards resulting in increased costs • Financial risks due to interest rate increases • Risk of funding contributions not eventuating at the predicted levels from the Crown or NZTA • Associated infrastructure project risks may escalate costs • Valuations (for rateable values) are yet to be undertaken with regard to damaged land and buildings; which will affect rates on individual properties as well as require other (undamaged) properties to take up the shortfall in rates. Financial position prior to Quake At the end of October 2016, prior to the earthquake, our financial position was constrained, but stable. Since the earthquake, the council has received $2 million from the Canterbury District Health Board to repay debt, $1 million advance from LAPP, and $3.46 million in advances from the government. These advances will be fully spent as at 30 June 2017, with further funding sought. Rates Sensitivity 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 23
With annual rates of less than $5.8M in 2016/2017, our sensitivity to rate increases is extreme. An increased cost of only $58,000 equates to a 1% rate increase for our
WHAT DOES ALL THIS MEAN FOR YOUR RATES? The properties below are examples of the impact on rates for those property locations, types and rating values based on actual properties Council has been benchmarking for over 15 years. Uninhabitable properties would be subject to rates remissions which are not shown. Rates shown are inclusive of GST, but they exclude Environment Canterbury rates, water meter charges and rural water charges (if applicable). New Rates Proposed Change in Change in Area capital 2016/2017 rates Rates (%) Rates ($) value ($) ($) 2017/2018 Residential – Whitby Place 270,000 1,816.41 1,932.99 6.42% 116.58 Residential – Bayview 255,000 1,781.68 1,895.94 6.41% 114.26 Street Residential – Esplanade 460,000 2,256.34 2,402.22 6.47% 145.88 Residential – Beach Road 350,000 2,001.64 2,130.56 6.44% 128.92 Residential – South Bay 520,000 2,395.26 2,550.40 6.48% 155.14 Residential – Oaro 255,000 1,326.61 1,386.67 4.53% 60.06 Residential – Ocean Ridge 115,000 1,189.68 1,317.76 10.77% 128.08 (bare land) Commercial – Beach Road 1,350,000 12,159.72 12,739.51 4.77% 579.79 Commercial – Beach Road 730,000 5,963.85 6,287.52 5.43% 323.67 Commercial – West End 1,150,000 9,648.07 10,186.10 5.58% 538.03 Commercial – Beach Road 760,000 5,408.67 5,783.12 6.92% 374.45 Accommodation – 1,070,000 5,418.24 5,727.31 5.70% 309.07 Scarborough Street Rural – Inland Kaikōura 8,350,000 14,477.60 15,446.95 6.70% 969.35 Road Rural – Kekerengu 4,560,000 7,848.53 8,377.63 6.74% 529.10 Semi-rural – Schoolhouse 4,650,000 9,174.08 9,749.22 6.27% 575.14 Road 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 25
FORECAST FINANCIAL STATEMENTS Forecast Statement of Revenue & Expense Annual Plan Long Term Plan Draft Annual Plan 2016/2017 2017/2018 2017/2018 $000’s $000’s $000’s Rates (after remissions) 5,784 5,983 5,876 Water meter charges 130 170 130 User fees & charges 1,285 1,406 2,249 Grants & subsidies 522 771 13,180 Development contrib. 30 80 - Interest revenue 39 63 12 Other revenue 1,026 1,042 2,238 TOTAL REVENUE 8,816 9,515 23,685 Operating expenses 9,083 9,264 12,875 Net surplus/(deficit) (267) 251 10,810 Gains (asset valuations) - - - TOTAL REVENUE & EXPENSE (267) 251 10,810 Forecast Statement of Financial Position Annual Plan Long Term Plan Draft Annual Plan 2015/2016 2017/2018 2017/201 $000’s $000’s $000’s Current assets 2,602 3,828 4,216 Non- current assets 172,098 173,027 167,409 TOTAL ASSETS 174,700 176,855 171,625 Current liabilities 2,496 3,708 2,998 Non-current liabilities 8,806 8,184 8,025 Total Liabilities 11,302 11,892 11,023 TOTAL NET ASSETS 163,398 164,963 160,602 Ratepayers equity 80,595 81,292 77,181 Special funds 1,546 2,243 2,164 Asset reval. reserve 81,257 81,428 81,257 TOTAL EQUITY 163,398 164,963 160,602 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 26
HOW TO GIVE US YOUR FEEDBACK WHAT YA RECKON? We want to hear what you think of our Draft Annual Plan • Weds 31st May, 5.30pm - 7.30pm, If you want to Memorial Hall, Kaikoura. 1 hear from us in • Fri 2nd June, 2pm - 4pm, Kekerengu Hall. person, attend one • Sat 27th May, 2pm - 4pm, of the community Goose Bay Fire Shed. meetings • Tues 6th June 7pm - 9pm, Lynton Downs Primary School, Inland Road. Either detach and 2 Remember to let us know if you fill out the form wish to speak to Council about your provided or write feedback at the Hearings on us a letter or email June 26th. Send it to Council 3 Kaikōura District Council PO Box 6 no later than 4pm 34 Esplanade Kaikōura Tuesday 20th June 2017 P: (03) 319 5026 F: (03) 319-5308 E: kdc@kaikoura.govt.nz W: www.kaikoura.govt.nz Council will hear from anyone who wishes to speak at hearings on June 26th. THEN Council deliberates on all feedback and hearings on June 27th and WHAT? decides what changes to make to the Annual Plan. The Annual plan will be adopted on June 30th. 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 27
DRAFT ANNUAL PLAN FEEDBACK Name: Address: Do you want to speak to Council at the Draft Annual Plan hearing? YES / NO If yes, please include the following so we can contact you: Email: Phone: Tell us what you think of, community development, WHAT YA economic development, the earthquake rebuild, the natural environment and anything else you wish to say about the RECKON? Draft Annual Plan... (Attach other pages as necessary if you need to.) Please detach and return this form to Kaikoura District council no later than no later than 4pm Tuesday 20th June 2017 2017/2018 Consultation Document for the Draft Annual Plan - Kaikoura District Council 28