Sudbury-Hudson Transmission Reliability and Mass Central Rail Trail Project - Stow MA

Page created by Denise Conner
 
CONTINUE READING
March 13, 2020

      Ref: 12970.00/14424.00

      Hudson Conservation Commission
      78 Main Street
      Hudson, MA 01749

      Re: WDA Design Group Peer Review - Applicants' Response to Comments
          Sudbury-Hudson Transmission Reliability and Mass Central Rail Trail Project

      Dear Members of the Hudson Conservation Commission,

      The Applicants, NSTAR d/b/a Eversource Energy (“Eversource”) and the Massachusetts Department of
      Conservation and Recreation (“DCR”), are providing this response to comments received in a letter dated
      March 11, 2020, from the Hudson Conservation Commission’s third-party reviewer, WDA Design Group
      (“WDA”). This supplemental submission also includes additional information regarding the February 7,
      2020, email that was submitted to the Commission, which stated that the Project meets the definition of
      previously developed and degraded Riverfront Area (“RFA”), and the Project fully complies with the
      performance standards for RFA at 310 CMR 10.53(5) for “redevelopment within previously developed
      RFA.” In addition, portions of the regulatory compliance discussion for Bordering Land Subject to Flooding
      (“BLSF”) and Isolated Land Subject to Flooding (“ILSF”) were revised to reflect the plan revisions that were
      submitted to the Commission as a supplemental submission on February 7, 2020.

      This supplemental submission includes the following:

            Response to comments received from WDA in a letter dated March 11, 2020;
            Revised Bordering Land Subject to Flooding (“BLSF”) information including:
                    ›      Revised Section 5.1.5.1 Summary of Impacts discussion;
            Revised Isolated Land Subject to Flooding (“ILSF”) information including:
                    ›      Revised Section 5.1.2.1 Summary of Impacts discussion; and
                    ›      Revised ILSF Proposed Mitigation Measures;
            Revised Riverfront Area (“RFA”) information including:
                    ›      Revised 5.1.6 Summary of Impacts discussion;
                    ›      Revised RFA Proposed Mitigation Measures;
                    ›      Revised RFA Regulatory Compliance Summary demonstrating that the Project complies with
                           the performance standards at 310 CMR 10.58(5);

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 2

            Revised plan sheets 1, 18-37, 74, 75, 80-83, and 84-102 from the NOI plans in Attachment B with a
             cover sheet that is stamped and signed with a revision date;
            Revised plan sheets 1, C-07-C-26, D-02, and D-08 from the NOI plan in Attachment B with a cover
             sheet that is stamped and signed with a revision date; and
            An electronic copy of all of the above including full revised sets of the plans provided in Attachments
             B and C.

      Below is a list of comments and questions issued by WDA with a written response to each.

      NOI Plan Comments - Transmission Line along MBTA ROW

             1.     The 164 Sheet plan set as provided does not bear the seal or signature of a Professional
                    Engineer or Professional Land Surveyor. Sheet 1 is missing (possibly a cover sheet with stamp).
                    The plans are all dated "Jan 2020" in the title blocks. WDA recommends that final plan sets
                    have a final revision date (not just month and year) in the title block, or if a plan has no
                    changes as submitted, then "no change" noted in revision blocks or stamped and dated cover.
                    The Commission would reference final stamped and dated plans in an Order, and therefore will
                    require a clearly identified date(s) on those final plans.

                    A signed, stamped, and dated updated electronic version of the plans is being provided to the
                    Commission with this response to comments so it can be uploaded to the Commission’s website.
                    Based on a conversation with Hudson’s Conservation Agent Pam Helinek on March 11, 2020, full
                    sets of revised plans also will be submitted to the Commission once the plans are finalized and
                    the Commission is preparing to issue an Order of Conditions (“OOC”). The final plan sets will be
                    bound and will include a cover sheet that has a revision date with the month, date, and year and
                    is stamped and signed by a Professional Engineer.

             2.     It appears in areas where streams/bank are delineated those flag label callouts are shown on
                    the plans. Although the approved wetland and vernal pool boundary locations are shown, the
                    actual wetland or vernal pool flag label callouts are not. The final plans should have the
                    wetland and vernal pool flag labels shown.

                    The wetland and vernal pool flag labels have been added to the revised Construction Plan sheets
                    that are being submitted electronically to update the NOI plans that were originally included as
                    Attachments A and B in the submitted NOI.

             3.     The erosion control barrier north of Station 120+70 should be extended up the slope to
                    approximately Station 120+50.

                    The erosion control barrier has been extended to 120+50 as requested. Please see updated sheet
                    26 for the revised erosion control barrier location.

             4. At Station 123+50 to 124+10 north side, the revised plan shows this callout as “275 SF
                Disturbance to 100’ RFA,” while the original plan had this called out as “275 Permanent Impact

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 3

                    to 100’ RFA.” The Supplemental Document provided by VHB on February 7, 2020, specifically
                    Table 12, Station 109+90 to 124+90 lists the 275 of alteration under the Temporary Impacts.
                    The document should reflect this 275 SF within the Permanent Impact column.

                    This area of impact is correctly called out on the revised plan as temporary. As discussed within
                    the February 7, 2020 supplemental submission, the only area of permanent impact associated
                    with the Project is the paved 10-foot-wide MCRT. All other areas of disturbance will be restored
                    upon completion of the Project and will continue to protect the interests of the MWPA.

             5.     Approximately 52,129 SF of alteration is proposed within the RFA between Stations 105+90 to
                    124+90 (plan Sheets 25-27), yet no restoration plantings aside from the "General Construction
                    Corridor Seed Mix" is called for (Plan Sheet 131, Schedule C). It appears that there are areas
                    along this stretch that could accept shrub and or tree plantings without potential impact to the
                    subsurface transmission line vault, or the 2' wide gravel shoulders. We would recommend that
                    the Applicants review this area and provide some additional plantings for work within this RFA
                    and show those changes on revised Plan Sheets submitted to the Commission.

                    The RFA between Stations 105+90 to 124+90 was evaluated to determine whether additional
                    woody restoration plantings would be appropriate. The Project Site within this area has been
                    reduced to the extent possible to minimize work within the RFA, including an 18-foot-wide
                    construction platform, and most of the limit of work within this area is limited to the construction
                    platform. There will be narrow spaces outside of the bike path shoulders and transmission line
                    duct bank (less than 2 feet) that will remain and will not be periodically mowed which, although
                    narrow, could possibly support limited woody species. In addition, three slightly wider areas were
                    identified throughout this RFA, which includes:

                    1) An area to the north of the construction platform from approximately Station 115+75 to
                       116+40 that is approximately 700 square feet.
                    2) Two areas to both the north and south of the proposed manhole at approximately Station
                       120+00 to 121+80. To the north, the area is approximately 1,370 square feet and to the south
                       the area is approximately 1,175 square feet.
                    3) An area to the south of the construction platform from approximately Station 123+20 to
                       124+40 that is approximately 850 square feet.

                    After consulting with a licensed Landscape Architect, it was determined that planting this area of
                    RFA is problematic for nursery-grown woody shrubs and trees. Where the slopes are 2:1 or
                    greater, we have experience low survival rates with planted stock on other projects. Much of the
                    RFA to be restored will be subject to periodic mowing, leaving only narrow strips (2 to 3 feet
                    wide) adjacent to the 19-foot-wide maintained corridor available for planting. Planting this area
                    would create linear rows of plants that the Commission has already expressed concern about.
                    However, a seed mix containing seeds of alternate-leaved dogwood (Cornus alternifolia),
                    arrowwood (Viburnum dentatum), nannyberry (Viburnum lentago), and hazelnut (Corylus
                    americana) is proposed to be applied to these areas which would encourage woody vegetation to

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 4

                    grow. By starting the plants from seed, the woody plants will be randomly placed and it will allow
                    them to grow their root systems to adapt to the slopes, therefore ensuring a higher rate of
                    success.

             6.     There are no callouts on Plan Sheet 131 (Planting Schedule) for plantings within Riverfront
                    Areas, although some of the referenced Stations noted for crane mat restoration areas
                    (Schedule A; notably Stations 147+25 to 150+25) are located within RFA associated with Fort
                    Meadow Brook and the crane mat restoration there will occur within RFA. The Planting
                    Schedule should reflect any RFA areas that are to receive supplemental/restorative plantings
                    (shrubs/trees) beyond the noted seed mixes and beyond just crane mat footprints.

                    All plantings within Planting Schedule A: Crane Mat Restoration Areas on sheet 131 in the plans
                    that were included as Attachment B of the NOI are located within RFA and have stationing
                    associated with the species and numbers of proposed plantings. In Hudson, the planting schedule
                    proposes to plant 10 each of gray birch, red maple, serviceberry, black oak, common winterberry,
                    highbush blueberry, and silky dogwood from Station 147+75 to 148+50, which is entirely within
                    RFA and is located to the west of Fort Meadow Brook (“FMB). The planting schedule also
                    proposes to plant 10 gray birch, 10 red maple, 15 serviceberry, 15 black oak, and 10 each of
                    common winterberry, highbush blueberry, and silky dogwood from Station 149+00 to 150+25,
                    which is entirely within RFA that is located to the east of FMB.

                    In addition, as discussed within Comment 5, seeds for woody species are proposed within three
                    locations of RFA from Stations 115+75 to 116+40, 120+00 to 121+80, and 123+20 to 124+40.
                    This seed mix has been added to the planting schedules on sheet 131 in the NOI plans included
                    as Attachment B of the NOI and is noted as “Riverfront Area Restoration.”

             7.     WDA has requested that VHB submit two additional details to the Commission for review and
                    clarification, specifically on Plan Sheet 130 for the proposed crane mats near FMB. We have
                    requested that a typical cross section of the existing right of way (ROW) near FMB be added
                    showing the reference location of the adjacent bordering vegetated wetland, flood elevation
                    and water elevation. Secondly a cross section detail of the proposed crane mat showing detail
                    of the construction of the mat and materials as it relates to the existing ROW, wetlands, and
                    erosion controls to be utilized on or around the crane mats.

                    Additional details were added to the plan set as requested. A specific FMB “Typical Crane Mat
                    Restoration Cross-Section – Bridge 130” was added to sheet 130. This cross section used Station
                    148+00 as a representative area for the purposes of the detail. The bordering vegetated wetland
                    (“BVW”) and BLSF elevations were added onto the detail. However, there are no LUWW or Bank
                    impacts at FMB and there is no LUWW at Station 148+00, so water elevations were not added.
                    This detail only applies to FMB from Station 147+75 to 148+50 and Station 149+00 to 150+25.

                    In addition to the specific FMB crane mat restoration detail, two details were added to sheet 125
                    in the plans provided in Attachment B of the NOI. These details, “Conceptual Crane Mat Section
                    with Steel Sheeting” and “Conceptual Crane Mat Section without Steel Sheeting,” show
                    conceptual configurations for the construction of the crane mat locations. As indicated in Note 3
                    of both conceptual details, geotextile fabric will be installed underneath and around the crane

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 5

                    mats as an erosion and sedimentation control measure. These details are intended as a
                    conceptual, visual representation only; the actual configuration of the crane mats will stay within
                    the identified limits of work and will be determined by the contractor.

             8.     On Plan Sheets 29-30 and 184-188, and as further detailed in VHB Supplemental Letter dated
                    February 7, 2020 (attachment A, Table 1 and attachment B, Table 8) in regards to work within
                    the BLSF, the calculations show that there is a net increase of flood storage of 435.50 cubic
                    yards between Stations 142+30 to 154+90. Based upon our review of the cross sections and
                    other information we agree with the calculations. Please note that the net gain of flood
                    storage along the ROW is accomplished by removing a portion of the existing top surface
                    grade, down to the final grade for the paved pathway. This elevation change will result in a net
                    gain of flood storage but will mean that portions of the final pathway would be inundated (up
                    to 1-1.2' depth) during 100- year flood events. This may not be a Commission issue, but more of
                    a safety concern. The Commission may inquire of the Applicants regarding signage that alerts
                    path users of potential flooding danger in those specific locations.

                    Limited portions of other bike paths managed by DCR are periodically subject to flooding similar
                    to this path. DCR does not have a policy to restrict access to the path during flooding conditions.
                    No signage is currently planned to be displayed regarding the potential for the path to flood.
                    Please note that there are railings proposed on the side of the path in these areas that could be
                    used by a path user who entered flooded conditions and needed support.

             9.     On Plan Sheets 27-28 and 180, and as further detailed in VHB Supplemental Letter dated
                    February 7, 2020 (attachment C, Table 10) in regards to work within the ILSF, the Table
                    indicates a total of 760 SF of temporary disturbance, yet on Sheet 180, the cross sections
                    indicate that the grade of the ROW will be cut down and resulting in a overtopping of the
                    proposed pathway from the ILSF elevation of 194.2' to the adjacent BLSF elevation of 192.3'. Is
                    this shown correctly and if the ILSF elevation is allowed to overtop the pathway and flow into
                    the BLSF, is there a flood increase potential? The Engineer may need to clarify this area and
                    flood calculations for the Commission.

                    The Federal Emergency Management Agency (“FEMA”) completes county wide hydrologic and
                    hydraulic studies in order to determine flood elevations from various storm events. These studies
                    are summarized in the FEMA Flood Insurance Studies (“FIS”) and Flood Insurance Rate Map
                    (“FIRM”). The FIS within the study area is the Middlesex County FIS No 25017CV001C, which is
                    dated revised July 6, 2016. This FIS includes a macro-scale study of the hydrology of the
                    rivers/stream studied including the Assabet River Branch No. 4, which is the flooding source for
                    the BLSF at the area in question with a Base Flood Elevation (“BFE”) of 192.3. The FIS reports that
                    the discharge-frequency data was defined using regional equations which relate basin
                    characteristics to stream flows for the 10, 2, and 1- percent annual chance flow. The 1-percent
                    chance flow as a result of the macro-scale study of the hydrology is used to determine the BFE of
                    192.3 of the Assabet River Branch No. 4.

                    Regional equations (used within this FIS) are a valuable tool in macro-scale hydrologic studies to
                    estimate peak flow rates within streams and rivers using basin characteristics (slope, drainage

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 6

                    area, cover type, etc). In short, they provide a conservative estimate of peak flow rates to be used
                    in hydraulic modeling to determine flood elevations. Given that they are macro level conservative
                    estimates, the hydraulic modeling estimates would not be impacted by a very minor change
                    within the watershed and micro-level ponding area such as the proposed grade change along the
                    ILSF. Therefore, the conservative estimate of peak flows used in the FEMA FIS for the Assabet
                    River Branch No. 4 would not be impacted by the proposed Project because it is a minor change
                    to the overall macro-scale analysis and accordingly there would be no impact to the BFE of 192.3.

                    Furthermore, the FEMA flood zone in this area is Zone A, which is an area subject to the 1%
                    annual chance event based on approximate study methods. Because this area was delineated
                    using approximate methods, the Project team took a very conservative approach and used the
                    closest available upstream BFE of the Assabet River No. 4 of 192.3 which over 600-feet
                    upstream. Therefore, if this area was studied in detail, it would likely result in a reduced BFE to
                    account for the drop in flood elevation over the 600-foot stretch.

             10. On Sheet 31, there appears a hatched area (cross hatch) near Station 165+55 to 168+00
                 indicating a "vernal pool" this appears to be an error on the plan. This does not show on prior
                 ORAD or current MCRT plans.

                    The cross hatch on sheet 31 indicates the Kane Perkins driveway easement, which is shown
                    because it crosses the MBTA ROW. In comparison to the vernal pools on sheet 41 (Vernal Pool 1),
                    sheet 42 (Vernal Pool 2), and sheet 43 (Vernal Pool 3), the cross hatch for the vernal pools is
                    smaller and aligns with the hatch in the legend.

             11. On Sheet 25, Station 107+90, there is an existing 30" clay culvert that runs SE to NW under the
                 ROW conveying an unnamed perennial stream and connecting wetland 1 to Wetland 2. The
                 culvert is shown as to be retained. Since the culvert is proposed to be retained is there
                 documentation as to its age, current condition and future viability. The Commission should
                 request documentation from the Applicant and Engineer as to the status of the culvert and a
                 contingency plan in case of damage during construction.

                    The existing 30-inch clay culvert located beneath the railroad embankment at Station 107+90 was
                    evaluated by VHB Structural Engineers in March 2017. The culvert is inside of a stone box and did
                    not exhibit any visible structural inadequacies at the time of the inspection, aside from some
                    decay of the north stone headwall, which is not a concern for the Project and does not affect its
                    function. The proposed design provides for over 4 feet of cover between the estimated top of the
                    culvert and the bottom of the proposed duct bank; thus, no damage to the culvert is expected to
                    occur during construction. Furthermore, the headwalls of this culvert are approximately 15 feet
                    outside of the proposed limits of grading for the Project and are not anticipated to be impacted
                    by project activities. However, should any damage to the existing culvert occur during
                    construction, Eversource will install a new reinforced concrete pipe having the same dimensions,
                    shape, and inverts as the existing culvert.

             12. On Sheet 35, Station 206+10, there is an existing 24" clay culvert that runs SW to NE under the
                 ROW conveying and unnamed intermittent stream and connecting wetland 10 to Wetland 11.
                 The culvert is shown as to be retained. Since the culvert is proposed to be retained is there

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 7

                    documentation as to its age, current condition and future viability. The Commission should
                    request documentation from the Applicant and Engineer as to the status of the culvert and a
                    contingency plan in case of damage during construction.

                    The existing 24-inch clay culvert located beneath the railroad embankment at Station 206+10 was
                    evaluated by VHB Structural Engineers in March 2017. Visual inspection of the pipe indicated
                    cracking along the ends of the pipe, likely due to a tree on top of the northeast corner of the
                    pipe. The pipe was clear inside, with no apparent collapsing. Eversource has proposed to cut the
                    tree on top of the northeast corner of the pipe in an effort to avoid further cracking. The
                    proposed design will incorporate a 4’x1’ transmission line configuration in this location to provide
                    for approximately 1.25 feet of cover between the estimated top of the culvert and the bottom of
                    the proposed duct bank; thus, no damage to the culvert is expected to occur during construction.
                    Furthermore, the ends of this culvert are over 5 feet outside of the proposed limits of grading for
                    the Project and are not anticipated to be impacted by project activities. However, should any
                    damage to the existing culvert occur during construction, Eversource will install a new reinforced
                    concrete pipe having the same dimensions, shape, and inverts as the existing culvert.

             13. The Commission should discuss with the Applicant regarding a weekly/biweekly site
                 inspection/construction monitoring report (aside from any required SWPPP/EPA NPDES
                 reporting}, or a schedule that is appropriate to the level of work. The report should note where
                 work is occurring, type of work, weather conditions, and if any erosion control or other issues
                 are identified and timeframes for repair or remediation. A point of contact/report preparer
                 should be identified to the Commission and the report could be emailed directly to the CC
                 Agent. The Commission could make this a Special Condition in the Order.

                    The Applicants will follow reporting requirements included in the Order of Conditions (“OOC”).

             14. Wetland and other resource area flags as approved by the ORAD, or under a new Order should
                 be refreshed in the field prior to the start of construction (the Commission could condition this
                 to be just the flags directly adjacent to, or within 50' etc. of proposed work areas, instead of all
                 flags associated with the 4.7 mile route that may not be close to work areas).

                    All wetland resource area boundaries that were approved in the ORAD will be reflagged prior to
                    construction.

             15. The Commission should discuss with the Applicants how and where refueling of construction
                 vehicles will occur and unless unfeasible for certain aspects, re-fueling should occur outside of
                 sensitive areas or buffer zones.

                    Except for the crane that will be used for reconstruction the FMB bridge, where feasible, refueling
                    will not be permitted within the inner 100-foot RFA or within 100 feet of BVW, and, if possible
                    outside of the outer 200-foot RFA. Preferred fueling operations are at paved road crossings, if
                    practical. In addition, the Draft Construction Spill Prevention Control and Countermeasures Plan
                    that was provided as Attachment K in the NOI identifies the extensive measures that will be in
                    place during construction.

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 8

             16. All erosion control measures from Phase 1 (Eversource) should remain and be maintained
                 accordingly until Phase II (DCR path paving) is complete and all areas fully stabilized. Erosion
                 controls should not be removed until stabilized areas are reviewed by the Commission or their
                 Agent and ECB's approved for removal. Although this is noted as a General Condition #18 in
                 the DEP Order of Conditions Form 5, the Commission could expand or further define the
                 erosion control conditions if they deem necessary and add that as a Special Condition in the
                 Order.

                    All erosion control measures will be installed prior to the start of any earthwork during Phase I.
                    Eversource will be responsible for monitoring and maintaining all erosion control measures until
                    DCR begins Phase II construction. Once Phase II construction begins, DCR will assume
                    responsibility for maintaining erosion control measures, which will remain in place until the
                    Project Site is stabilized. Removal of the erosion control measures will not occur until approval is
                    received from the Commission’s Agent, or in accordance with any Special Condition of the OoC.

      NOI Plan Comments – Mass Central Rail Trail

             1.     This 31-sheet plan set as provided has the seal and signature of a Professional Engineer on the
                    cover sheet only. The date under the signature is January 2, 2020. The plans are all dated "Jan
                    2020" in the title blocks. WDA recommends that final plan sets have a final revision date in the
                    title block (not just month and year), or if a plan has no changes as submitted, then "no
                    change" noted in revision block or on stamped and dated cover sheet. The Commission would
                    reference final stamped and dated plans in an Order, and therefore will require a clearly
                    identified date(s) on those final plans.

                    Please see response to Comment 1 under NOI Plan Comments – Transmission Line along MBTA
                    ROW. The same update will be made for this plan set.

             2.     WDA received three revised sheets on February 7, 2020 from VHB for the MCRT plan set,
                    specifically sheets C- 01, C-03 and C-07. Sheet C-01 was updated to show the new wetland flag
                    BP-4A and updated wetland boundary and a revised callout for "612 SF of pavement and 983
                    SF of loam and seed in the 200' RFA". Sheets C-03 and C-07 were updated with callouts
                    referencing SF of pavement and loam and seed in the RFA and pavement and loam and seed in
                    BLSF respectively. These plans did not a have professional stamp or revision date.

                    Please see response to Comment 1 under NOI Plan Comments – Transmission Line along MBTA
                    ROW. The same update will be made for this plan set.

             3.     Sheet C-01 of the MCRT plans shows work located within both the 100' buffer zone and outer
                    200' RFA. Most of the work proposed here is located within previously disturbed or maintained
                    areas adjacent to the paved ARRT parking area and trailhead. Although there is work proposed
                    in the outer 200' RFA it is located as mentioned in disturbed areas and the existing paved
                    ARRT is located between the proposed work area and the actual perennial water body. The

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 9

                    Applicant has shown adequate erosion control measures and proposed stabilization and
                    plantings in this area.

                    No response required.

             4. Sheets C-04 and C-05 show planting symbols and species callouts for plantings in disturbed
                ILSF areas. Sheet C-09 shows planting within disturbed buffer zone (adjacent to Wetland #9).
                How were these locations determined for plantings, while other areas within RFA or adjacent
                to vernal pools or other BVW's do not indicate any additional tree/shrub vegetation beside the
                noted seed mix.

                    The AASHTO Guide for the Development of Bicycle Facilities states “depending on the height of
                    the embankment and the condition at the bottom, a physical barrier such as dense shrubbery,
                    railing or fencing may be needed.” Due to the steep slope and the elevation difference between
                    the top of the embankment and the bottom on sheets C-04, C-05, and C-09, a safety feature is
                    required. For aesthetic reasons, a landscaping option was chosen in these areas instead of fencing
                    or railing.

             5.     As noted previously in the review of the MBTA ROW Plans (comment #5), approximately
                    52,129 SF of alteration is proposed within the RFA between Stations 105+90 to 126+70, yet no
                    restoration plantings aside from the "General Construction Corridor Seed Mix" is called for
                    (Plan Sheet 131 of MBTA ROW Plans, Schedule C). It appears that there are areas along this
                    stretch that could accept shrub and or tree plantings without potential impact to the
                    subsurface utility vault, or the 2' wide gravel shoulders. We would recommend that the
                    Applicants review this area and provide additional plantings for work within the RFA and show
                    those changes on revised Plan Sheets. It should be clarified if plantings will be the
                    responsibility of DCR after paving in this area (Phase II) or Eversource following Phase I
                    completion, or a combination.

                    Please see response to Comment 5 under NOI Plan Comments – Transmission Line along MBTA
                    ROW. The shrub seed mix will be applied by Eversource following Phase I completion.

             6.     See comments #11 and #12 in MBTA ROW plan review section regarding clay cross culverts.

                    Please see response to Comment 11 under NOI Plan Comments – Transmission Line along MBTA
                    ROW.

             7.     See comment #13 in MBTA review.

                    Please see response to Comment 13 under NOI Plan Comments – Transmission Line along MBTA
                    ROW.

             8.     See comment #15 in MBTA review.

                    Please see response to Comment 15 under NOI Plan Comments – Transmission Line along MBTA
                    ROW.

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 10

             9.     According to the NOI submittal materials, DCR will be responsible for invasive species
                    management as part of any on-going future path management. Is this to be a condition in
                    perpetuity?

                    DCR will manage invasive species for the lifetime of the MCRT.

             10. All erosion control measures from Phase 1 (Eversource) should remain and be maintained
                 accordingly until Phase II (DCR path paving) is complete and all areas fully stabilized. Erosion
                 controls should not be removed until stabilized areas are reviewed by the Commission or their
                 Agent and ECB's approved for removal. Although this is noted as a General Condition, #18 in
                 the DEP Order of Conditions Form 5, the Commission could expand or further define the
                 erosion control conditions if they deem necessary and add that as a Special Condition in the
                 Order.

                    Please see response to Comment 16 under NOI Plan Comments – Transmission Line along MBTA
                    ROW.

      NOI Plan Comments – Transmission Lines along Roadways

             1.     The Applicant's Engineer, VHB has submitted that the work associated with these plans are
                    exempt from WPA jurisdiction pursuant to 310 CMR 10.02(2)(b)1and 2. Specifically, 310 CMR
                    10.02(b)2.i. "that the installation of underground utilities within existing paved or unpaved
                    roadways within 100-foot Buffer Zone or Riverfront Area is exempt. Accordingly, impacts to
                    these resources are not included for the portion of the transmission line within existing public
                    roadways". We agree with this categorization as it meets the exemption as noted, and the
                    Applicant is proposing erosion control and stabilization measures as part of the work as
                    categorized in 310 CMR 10.02(b)1.

                    No response required.

             2.     Based upon our review of the work within the noted roadways proposed on these plans, it
                    appears that Sheets 4, 5, and 12-14 have work within the 100' buffer zone, and erosion control
                    barriers are shown protecting off-site adjacent resource areas. Sheets 16 and 17 would have work
                    within the 100' buffer zone to adjacent wetlands, although the buffer zone is not shown on these
                    two sheets. The buffer zone and adequate erosion controls should be shown on these two sheets
                    and revised, and dated sheets issued to the Commission.

                    As approved in the ORAD, the two wetlands on sheets 16 and 17 are isolated wetlands/potential
                    vernal pools and therefore do not have an associated 100’ buffer zone. However, erosion controls
                    are currently being added to the sheets as requested and will be provided to the Commission at a
                    later date.

             3.     Sheets 6-8 and 12-15 have work shown within Riverfront Area. The roadway utility work within
                    the RFA is exempt under 310 CMR 10.58(6)(b) which refers to the 310 CMR 10.02 (2)(b) 1 and 2
                    "minor activities". These sheets appear to have adequate erosion controls along perimeter work

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 11

                    areas, but the Commission should ask the Applicant to clarify if "silt sacks" are being utilized in
                    catch basins which may have associated culvert discharge points within RFA or Buffer Zone areas.

                    Appropriate erosion and sedimentation controls will be used at catch basin to protect the
                    stormwater management system. Page 14 of the Best Management Practices (“BMPs”) included as
                    Attachment I with the submitted NOI discusses the use of catch basin protection, including filter
                    bags.

             4. Please note that under the exemption provision for underground utilities that all trenches are
                to be closed at the completion of the workday. The Commission could make that a Special
                Condition in any future Order. All erosion control measures should remain and be maintained
                accordingly until final paving is complete. Erosion controls should not be removed until areas
                are reviewed by the Commission or their Agent and ECB's approved for removal.

                    All trenches for the underground transmission line will be closed at the completion of each
                    workday.

      Wildlife Habitat Comments

             1.     If the Commission does not yet have a copy of the Corridor Management Plan and Box Turtle
                    Protection Plan, they should request one be submitted for their records and any future
                    reference.

                    Copies of the Draft Corridor Management Plan and Draft Eastern Box Turtle Protection Plan are
                    included for the Commission’s reference.

      Engineering/Stormwater Management Comments

             1.     The engineer should review the Checklist for Stormwater Report. It appears some items may be
                    applicable for Stormwater Standards 3, 4, 5 and 9, but have not been checked. (completed)

                    The Checklist for Stormwater Report was revised and provides clarifications in red text.

             2.     There is a statement in the Stormwater Report (pg. 49) stating the check dams result in an
                    "effective" longitudinal slope of two percent in all swales. Is there a calculation or reference to
                    support this?

                    The check dams have been located within the swales (see Construction Plans Sheets 24-43) to
                    provide a minimum effective slope of 2% (the slope from the top of one check dam to the top of
                    the next check dam) where the longitudinal slope of the swale exceeds 2%. The spacing for a 6-
                    inch high check dam has been calculated to be 100 feet for slopes between 2% and 3%; 50 feet
                    for slopes between 3% and 4% and 30 feet for slopes between 4% and 5%. The swales have been
                    designed so that the longitudinal slope does not exceed 5%.

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 12

             3.     The Stormwater Report Section 3 Regulatory Compliance, Standard 9: Operation and
                    Maintenance Plan references an Operation and Maintenance (O&M) Plan, but O&M Plan was
                    not provided for review.

                    An O&M Plan has been prepared and a pdf is included as an attachment to this supplemental
                    submission.

             4. The plans indicate portions of the path will be flooded during the larger design storm events.
                Is there a policy in place regarding access to the path when flooded? Will this policy be posted
                along the path with signage or other means?

                    Please see response to Comment 8 under NOI Plan Comments – Transmission Line along MBTA
                    ROW.

             5.     Some of the HydroCAD output data says "Tc
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 13

      5.1.5           Revised Land Subject to Flooding (310 CMR 10.57)

     5.1.5.1          Revised Bordering Land Subject to Flooding

                      Summary of Impacts

                      The Project was designed to fully comply with all applicable performance standards for BLSF and
                      will result in a net gain of 433.5 cubic yards of flood storage.

                      As outlined in Tables 8 and 9, the Project will result in permanent and temporary impacts to BLSF
                      at two locations within the Project Locus. The first area (between Station 131+10 and 132+00) is
                      just west of Chestnut Street and is associated with an unnamed perennial tributary to the
                      Assabet River that is located north of the Project Locus. The second area (between Station
                      142+50 and 164+00) is east of Chestnut Street and is associated with Fort Meadow Brook. In all
                      cases, permanent disturbance is due to the paved surface proposed for the MCRT and temporary
                      disturbance includes all areas outside of the paved MCRT. All disturbed areas outside the limits
                      of the paved MCRT will be revegetated with native species once construction is complete.
                      impacts in both locations are due to paving the MCRT. Table 8 identifies the square footage of
                      impact in each area; Table 9 summarizes the changes to flood storage volume.

                      There is no BLSF along the MCRT Connection nor along the component of the Project within
                      public roadways.

     5.1.5.2          Revised Isolated Land Subject to Flooding

                      Summary of Impacts

                      The Project was designed to fully comply with the applicable performance standards for ILSF.

                      There is one ILSF that is partially located within the Project Locus in Hudson and the Project will
                      result in 760 square feet of temporary impacts to ILSF due to grading (cut) and vegetation
                      removal (see Table 10 below). This ILSF is associated with a forested isolated wetland (Wetland
                      5); however, the ILSF impacts are upslope on the raised railroad embankment and will not impact
                      the wetland itself. There are no permanent impacts within ILSF associated with this Project.

                      Proposed Mitigation Measures

                      The Project will result in 760 square feet of temporary impacts to ILSF. However, impacts to the
                      ILSF are a cut, not a fill, and will result in an increase of 99.07 cubic yards of flood storage.
                      Therefore, mitigation for a loss in flood storage volume is not required. Once construction is
                      complete, all disturbed areas will be loamed and seeded with a native seed mix and a portion of
                      the ILSF will be planted with native shrubs as part of Phase 2 construction.

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 14

      5.1.6           Revised Riverfront Area (310 CMR 10.58)
                      Summary of Impacts

                      The Project was designed to fully comply with all applicable performance standards for RFA and
                      will provide an improvement to the previously degraded areas.

                      There are five locations of RFA within the Project Locus:

                             MCRT and Underground Transmission Line along the MBTA ROW
                              ›     Station 105+90 to 124+90: Associated with unnamed perennial stream east of Wilkins
                                    Street
                              ›     Station 146+45 to 151+10: Associated with Fort Meadow Brook
                             MCRT Connection to the ARRT
                              ›     Station 10+20 to 10+80: Associated with an unnamed perennial tributary to the Assabet
                                    River, north of the existing ARRT.
                             Underground Transmission Line within Public Roadways
                              ›     Station 18+40 to 26+70: Associated with an unnamed perennial stream south of Forest
                                    Avenue, near the intersection with Marlboro Street.
                              ›     Station 50+00 to 60+40: Associated with an unnamed perennial stream currently
                                    conveyed through a culvert beneath Forest Avenue, just west of Glendale Road.

                      Installation of underground transmission lines within existing paved roadways within RFA is
                      exempt pursuant to 310 CMR 10.02(2)(b)1. Accordingly, the amount of RFA within existing public
                      roadways is not included in the total RFA on the Project Locus and impacts are not included for
                      the portion of the transmission line that is within existing public roadways.

                      The existing RFA within the Project Locus in Hudson for the portion of the Project that is within
                      the MBTA ROW and the MCRT Connection to the ARRT is 219,261 square feet. As outlined in
                      Table 12, the Project will result in 23,558 square feet of permanent impacts to RFA (10.7 percent
                      of total RFA) from paving the MCRT. The Project will also result in 41,232 square feet of
                      temporary impacts to RFA (18.8 percent of total RFA) due to installation of the underground
                      transmission line, construction of the MCRT base, site grading, and the placement of crane mats
                      to accommodate reconstruction of Bridge 130 (Fort Meadow Brook bridge).

                      Proposed Restoration and Mitigation Measures

                      The Project was designed to avoid and minimize impacts to RFA to the extent practicable by:

                                 Reducing the construction platform width to 18 feet from Station 112+87 to 120+75;
                                 Using a retaining wall from Station 119+00 to 124+95 (at the Hudson and Stow municipal
                                  border);

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 15

                             Reducing the construction platform with to 18 feet from Station 146+66 to 174+85 and
                              from Station 150+15 to 151+10 (Fort Meadow Brook area);
                             Using steel sheeting at Fort Meadow Brook to minimize the limit of disturbance; and
                             Placing all but one manhole (at Station 120+75 to 121+25) outside of RFA.

                      In addition, the following restoration and mitigation measures will be implemented in RFA:

                             Erosion and sediment controls will be installed to protect the associated waterbodies.
                             Crane mats at Fort Meadow Brook will be in place for the minimum duration necessary and
                              will be removed immediately upon completion of activities where the use of a crane is
                              required.
                             Following removal of the crane mats, the area where mats were placed will be restored by
                              raking and re-grading the soil (if necessary due to soil compaction).
                             The crane mat area will be stabilized with jute mesh erosion control blankets and planted
                              with native herbaceous and woody plant species (see crane mat restoration detail and
                              planting schedule for the crane mat restoration areas on sheets 130 and 131 in the NOI
                              plans in Attachment B). The trees and shrubs will be planted after Phase 2 construction is
                              completed to avoid disturbing and/or damaging the plants. If necessary, the area will be
                              reseeded with an appropriate seed mix that will allow for the regrowth of indigenous, non-
                              invasive herbaceous species to supplement natural recruitment.
                             After Phase 1 is constructed, all disturbed areas outside of the 14-foot gravel base will be
                              loamed and seeded with the seed mix shown on sheet 131 in the NOI plans in Attachment
                              B.
                             After Phase 2 is completed, DCR will loam and seed the two-foot shoulders on either side of
                              the MCRT so that all permanently disturbed areas except for the 10-foot wide MCRT are
                              revegetated.
                             Once the Project is complete, all areas outside of the 19-foot-wide final maintained width
                              will be allowed to naturally revegetate with woody vegetation.

                      Regulatory Compliance Summary

                      As discussed in Section 5.1.1 above, both phases of the Project qualify as limited projects for
                      relief from certain provisions of 310 CMR 10.58 for work in RFA. In addition, because the RFA in
                      the Project Locus is previously developed from the former railroad ROW operations, including
                      degraded areas where the ballast, rail, and ties are located, the Project is a redevelopment
                      project that proposes reuse of degraded and previously developed areas subject to 310 CMR
                      10.58(5). The Project fully complies with all applicable performance standards at 310 CMR
                      10.58(5), which requires compliance with 310 CMR 10.58(4) and (b), but not (c) and (d).

                      As outlined below, the Project fully complies with the provisions of 310 CMR 10.58(4)(a) and (b):

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 16

                      10.58(4)(a) The work shall meet the performance standards for all other resource areas within
                                  Riverfront Area. When work in the RFA is also within the buffer zone to another
                                  resource area, the performance standards for the RFA shall contribute to the protection
                                  of the interests of M.G.L. c. 131 § 40 in lieu of any additional requirements that might
                                  otherwise be imposed on work in the buffer zone within the RFA;

                                           As presented in detail in Sections 5.1.3 and 5.1.4, the Project was designed to fully
                                           comply with the performance standards of other wetland resource areas that overlap
                                           RFA within the Project.

                      10.58(4)(b) No project may be permitted within the RFA which will have any adverse effect on
                                  specified habitat sites of rare wetland or upland vertebrate or invertebrate species … or
                                  certified vernal pool habitat;

                                           The Project will not have any adverse effect on specified habitat of rare species. The
                                           Project was reviewed by NHESP and conditional no-take determinations were issued
                                           (see Attachment H). See Section 5.1.7 for further discussion regarding rare species
                                           and consultation with NHESP.

                                           In addition, the following paragraphs present a summary of how the Project will fully
                                           comply with the performance standards for redevelopment within previously
                                           developed RFA, as per 310 CMR 10.58(5):

                      10.58(5)             Notwithstanding the provisions of 310 CMR 10.58(4)(c) and (d), the issuing authority
                                           may allow work to redevelop a previously developed riverfront area, provided the
                                           proposed work improves existing conditions. Redevelopment means replacement,
                                           rehabilitation or expansion of existing structures, improvement of existing roads, or
                                           reuse of degraded or previously developed areas [emphasis added]. A previously
                                           developed riverfront area contains areas degraded prior to August 7, 1996 by
                                           impervious surfaces from existing structures or pavement, absence of topsoil,
                                           junkyards, or abandoned dumping grounds.

                                           The RFAs that extend into the Project Locus are previously developed from the
                                           construction and operation of the railroad ROW, including degraded areas occupied
                                           by the steel rails, wooden ties, and stone ballast within a linear footprint that is 11
                                           feet wide. Therefore, all work in RFAs within the Project Site, including both the
                                           transmission line and MCRT components, is within previously developed RFA, and
                                           the 10-foot paved surface of the MCRT is designed to be located within the
                                           footprint of the existing 11-foot-wide degraded area.

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 17

                      10.58(5)(a) At a minimum, proposed work shall result in an improvement over existing conditions
                                  of the capacity of the riverfront area to protect the interests identified in M.G.L. c. 131
                                  § 40.

                                           The Project will result in an improvement over the existing conditions of the capacity
                                           of the RFA to protect the interests of the Act. The Project will improve the RFA by
                                           reducing the total footprint of the degraded area by 1 foot in width throughout the
                                           RFA, which results in a reduction in degraded area of 1,984 square feet. In addition,
                                           except for the 10-foot-wide paved MCRT, the remaining previously developed area
                                           within the proposed limits of work, including existing areas of recent activity where
                                           there is limited or no vegetation, will be restored with dense native vegetation, and
                                           trees and shrubs will be planted at the Fort Meadow Brook crossing. Please refer to
                                           sheet 131 in Attachment B for the proposed planting schedule.

                                           The Project will also improve the RFA at the Fort Meadow Brook crossing. Currently,
                                           the bridge is degraded, portions of it were burnt in a fire, and there is erosion at the
                                           abutments. The new bridge will consist of new abutments that will be constructed
                                           landward of the existing abutment locations and steel sheeting will be installed
                                           around the abutments to provide scour protection. As mentioned above, this area
                                           will also be loamed, seeded, and planted with trees and shrubs which will stabilize
                                           the banks and enhance current conditions.

                                           In addition to reducing the footprint of the currently degraded areas, restoring all
                                           areas with native vegetation, and stabilizing the banks of Fort Meadow Brook to
                                           prevent erosion, the Project will improve the capacity of the RFA to protect the
                                           wildlife habitat interest of the Act by removing the existing rails and ties, which
                                           extend approximately four to five inches above the ground and create a barrier to
                                           wildlife movement, particularly for reptiles and amphibians. For example, turtles have
                                           difficulty climbing over the rails and are therefore required to travel to widely spaced
                                           crossing points such as existing culverts to cross the railroad embankment. The
                                           Project will remove the obstruction and create a flat unobstructed path that is more
                                           readily traversed by small wildlife such as turtles and migrating salamanders.

                    10.58(5)(b)            Stormwater management is provided according to standards established by the
                                           Department.

                                           Stormwater management during construction will comply with all applicable
                                           standards. Per 310 CMR 10.05(6)(m)6, the Stormwater Management Standards
                                           (SMSs) for the post-construction phase shall apply to the maximum extent
                                           practicable to footpaths, bike paths, and other paths for pedestrian and/or non-
                                           motorized vehicle access. The Project was designed for the final condition of the
                                           paved MCRT to meet the SMS to the maximum extent practicable and includes an
                                           open stormwater system with vegetated filter strips and water quality swales with

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 18

                                           check dams to provide treatment. The MCRT will require 10 feet of paving and
                                           runoff will sheet flow to the vegetated shoulders, providing an additional
                                           opportunity for stormwater to infiltrate before it enters the swales. The swales were
                                           designed to convey water to appropriate discharge points to maintain existing
                                           drainage patterns and were sized such that they can accommodate a two-year storm
                                           to meet DCR’s standards and, according to the stormwater analysis, frequently
                                           meeting the 10-year storm requirements of the SMS as well.

                                           The end use of the Project will be the MCRT and therefore is not anticipated to
                                           increase pollutant loads within the Project Locus above the existing conditions. The
                                           MCRT will be used by pedestrians and bicyclists, which will not contribute
                                           contaminants to the path surface. Other than in emergency situations, motor vehicle
                                           access along the path will be limited to bi-weekly mowing over the shoulders and
                                           annual mowing over the duct bank and swales by DCR, inspections by Eversource
                                           approximately once every three years, and other maintenance as needed by both
                                           Eversource and DCR. In addition, the MCRT will not be plowed or treated in the
                                           winter. Therefore, there will be little to no contaminants on the path surface to be
                                           washed off by stormwater runoff. For additional details regarding stormwater
                                           management, please refer to the Stormwater Report in Attachment M.

                    10.58(5)(c)            Within 200-foot riverfront areas, proposed work shall not be located closer to the river
                                           than existing conditions or 100 feet, whichever is less, or not closer than existing
                                           conditions within 25-foot riverfront areas, except in accordance with 310 CMR
                                           10.58(5)(f) or (g).

                                           The Project is not located closer to the river than existing conditions. The existing
                                           degraded and previously disturbed RFA extends through the entire RFA and to the
                                           edge of the Fort Meadow Brook crossing. In addition, as discussed in 310 CMR
                                           10.58(5)(a), the Project includes reconstructing the bridge at the Fort Meadow Brook
                                           crossing, which will improve current conditions by installing new abutments
                                           landward of the existing abutments, installing steel sheeting, and stabilizing the
                                           streambanks with native vegetation to prevent erosion. The Project also provides
                                           restoration in the form of revegetation with native species of the RFA, which is
                                           addressed in 310 CMR 10.58(5)(f).

                    10.58(5)(d)            Proposed work, including expansion of existing structures, shall be located outside the
                                           riverfront area or toward the riverfront area boundary and away from the river, except
                                           in accordance with 310 CMR 10.58(5)(f) or (g).

                                           The Project is a redevelopment project that proposes reuse of existing degraded and
                                           previously developed areas in the RFA. The Project Locus is a former linear
                                           transportation corridor that currently crosses existing water bodies and their
                                           associated RFAs. There are existing culverts or bridges at each water body crossing.

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 19

                                           All work associated with the Project, including both the transmission line and MCRT
                                           components, is proposed entirely within the previously developed and degraded
                                           area. The Project does not propose expansion of the existing degraded or previously
                                           developed areas in the RFA.

                                           To the extent feasible, the Project has also been designed to locate work outside of
                                           RFA or toward the RFA boundary and away from associated waterbodies, including
                                           manholes. To avoid and minimize the placement of manholes, they were spaced as
                                           much as 1,900 feet apart as the curvature of the MBTA ROW allowed. Only one
                                           manhole is located within the outer 200-foot RFA; there are no manholes within the
                                           inner 100-foot RFA. The Project also provides restoration in the form of revegetation
                                           of the RFA, which is addressed in 310 CMR 10.58(5)(f).

                    10.58(5)(e)            The area of proposed work shall not exceed the amount of degraded area, provided
                                           that the proposed work may alter up to 10% if the degraded area is less than 10% of
                                           the riverfront area, except in accordance with 310 CMR 10.58(5)(f) or (g).

                                           The existing degraded area is greater than 10 percent of the total previously
                                           developed RFA in the Project Locus. Therefore, the Project is not limited to alteration
                                           of up to 10 percent of the RFA as prescribed in this performance standard. The
                                           Project is also proposing on-site restoration, which is addressed in 310 CMR
                                           10.58(5)(f).

                    10.58(5)(f)            When an applicant proposes restoration of on-site of degraded riverfront area,
                                           alteration may be allowed notwithstanding the criteria of 310 CMR 10.58(5)(c), (d),
                                           and (e) at a ratio in square feet of at least 1:1 of restored area to area of alteration not
                                           conforming to the criteria. Areas immediately along the river shall be selected for
                                           restoration. Alteration not conforming to the criteria shall begin at the riverfront area
                                           boundary.

                                           There is a total of 41,232 square feet of proposed temporary RFA disturbance and
                                           23,558 square feet of proposed permanent RFA disturbance associated with the
                                           Project. The only permanent disturbance is the 10-foot-wide paved MCRT, which will
                                           be within the 11-foot-wide degraded area. All areas of disturbance outside of the
                                           paved MCRT will be restored with native species, which meets the criteria of 1:1. In
                                           addition, the Project will reduce the amount of degraded area by 1,984 square feet
                                           by restoring the degraded area, reducing the amount of degraded RFA on the
                                           Project Locus by approximately 1 percent.

                                           Restoration shall include:
                                           1. Removal of all debris, but retaining any trees or other mature vegetation;

                                                 Any debris within the limits of work will be removed as part of the Project.
                                                 Existing trees and mature vegetation will be retained wherever possible within

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
Hudson Conservation Commission
      Ref: 12970.00/14424.00
      March 13, 2020
      Page 20

                                                 the RFA. Once the Project is completed, all disturbed areas outside of the 10-
                                                 foot MCRT paved surface will be restored with native vegetation to provide a
                                                 dense herbaceous cover and trees and shrubs are proposed at the Fort Meadow
                                                 Brook crossing. Please refer to sheets 130 and 131 in the NOI plans provided in
                                                 Attachment B for planting details.

                                           2.    Grading to a topography which reduces runoff and increases infiltration;

                                                 Within the proposed limits of work, the grading has been designed to reduce
                                                 runoff and increase infiltration. The RFA will be graded flat along the MCRT but
                                                 with a slight pitch to the either side to shed runoff. The dense herbaceous
                                                 growth adjacent to the MCRT will function as a vegetated filter strip to reduce
                                                 runoff and promote infiltration of stormwater runoff.

                                           3.    Coverage by topsoil at a depth consistent with natural conditions at the site; and

                                                 The Project Site within RFA is previously disturbed, consisting primarily of a filled
                                                 embankment to support the rails and maintain a relatively level alignment.
                                                 Except for the 10-foot-wide paved MCRT, all disturbed areas within the Project
                                                 Site will be covered with a minimum of four inches of clean topsoil consistent
                                                 with natural conditions and will be revegetated with native species.

                                           4.    Seeding and planting with an erosion control seed mixture, followed by plantings
                                                 of herbaceous and woody species appropriate to the site.
                                                 A restoration seed mixture will be used throughout the Project Site, which
                                                 contains a mixture of native species including Canada wild rye, little bluestem,
                                                 fox sedge, soft rush, New England Aster, woodland goldenrod, and joe-pye
                                                 weed (see sheet 131 in the NOI plans provided in Attachment B for seed mix).
                                                 Except for the 10-foot-wide paved MCRT, this seed mix will be applied in all
                                                 areas of proposed disturbance associated with the Project, which includes
                                                 approximately 1,984 square feet of existing degraded RFA. In addition to the
                                                 herbaceous vegetation, trees and shrubs will be planted at the Fort Meadow
                                                 Brook crossing. Please refer to sheet 131 in the plans in Attachment B for the
                                                 proposed planting schedules.

                    10.58(5)(g)            When an applicant proposes mitigation either on-site or in the riverfront area within
                                           the same general area of the river basin, alteration may be allowed notwithstanding
                                           the criteria of 310 CMR 10.58(5)(c), (d), or (e) at a ratio in square feet of at least 2:1 of
                                           mitigation area to area of alteration not conforming to the criteria or an equivalent
                                           level of environmental protection where square footage is not a relevant measure.
                                           Alteration not conforming to the criteria shall begin at the riverfront area boundary.
                                           Mitigation may include off-site restoration of riverfront areas, conservation restrictions
                                           under M.G.L. c. 184, §§ 31 to 33 to preserve undisturbed riverfront areas that could be
                                           otherwise altered under 310 CMR 10.00, the purchase of development rights within the

\\vhb\gbl\proj\Worcester\12970.00 Sudbury-Hudson-EV\reports\Construction
NOIs\Hudson\Supplemental Submissions\3-11-20 WDA RTC\Hudson_WDA_ RTC_3-13-
2020.docx
You can also read