Standard: Numbering and Titling Specification - Standard Number: HPC-9CA-01-0002-2012 - Horizon Power
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Document Control Revision 17 Author Name: Claire Hand Claire Digitally signed by Claire Hand Position: Engineering Drawing System Specialist Hand Date: 2020.06.01 19:28:33 +08'00' Reviewed By Name: Robert Golding Digitally signed by Robert Golding Position: Drawings and CAD Systems Date: 2020.06.02 22:15:53 +08'00' Specialist Endorsed By Name: Sandeep Magan Digitally signed by Sandeep Magan Date: 2020.06.03 Position: Engineering Services Manager 09:21:02 +08'00' Approved By Name: Marc Beckx Digitally signed by Marc Beckx Position: Manager Engineering and Project Date: 2020.06.04 Services 15:26:06 +08'00' Date Created/Last Updated 26 May 2020 Review Frequency* 3 years Next Review Date 26 May 2023 * Frequency period is dependent upon circumstances– maximum is 5 years from last issue, review, or revision whichever is the latest. If left blank, the default must be 1 year unless otherwise specified. Revision Control Revision Date Description 17 26/05/2020 Numbering and Titling Documents updated and combined. HPC-9CA-01-0003-2012 Drawing Titles and HPC-9CA-01-0004-2013 Standard Drawing Numbers superseded by incorporating into this standard. Refer to Appendix A for Full Revision History. STAKEHOLDERS The following positions must be consulted if an update or review is required: EPCM Contracts Manager Senior Engineer Secondary Systems Engineering Services Manager Major Project Directors Asset Managers DM# 9118921 HPC-9CA-01-0002-2012 Page 2 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
TABLE OF CONTENTS 1 PURPOSE .................................................................................................... 5 2 COMPLIANCE .............................................................................................. 5 3 OWNERSHIP ................................................................................................ 5 4 REFERENCES ............................................................................................. 5 5 DEFINITIONS AND ABBREVIATIONS ........................................................ 5 6 GENERAL REQUIREMENTS ...................................................................... 7 6.1 Request for Numbers ............................................................................................... 7 7 DOCUMENT NUMBER STRUCTURE AND CODING ................................. 8 7.1 Legacy Drawings ...................................................................................................... 8 Current drawing number vs legacy ( Including Western Power) ............................................ 8 South Hedland and Hedland Projects..................................................................................... 8 7.2 Structure ................................................................................................................... 8 Location Drawing Number Convention ................................................................................... 8 Transmission Line Drawing Number Convention ................................................................... 8 Concept and Tender Drawing Number Convention................................................................ 9 Standalone Power Systems Numbering Convention............................................................ 10 Document Numbering Convention........................................................................................ 11 8 REDLINE NUMBERING ............................................................................. 12 9 REVISION NUMBERING ............................................................................ 13 9.1 Revision Description............................................................................................... 14 9.2 Cancelled deliverables ........................................................................................... 14 9.3 Superseded deliverables ........................................................................................ 14 9.4 File name ............................................................................................................... 14 File names for legacy drawings ............................................................................................ 14 10 STANDARDS DOCUMENTS AND NUMBERS ......................................... 15 10.1 Standard drawings numbering ............................................................................... 15 10.2 Distribution Standards Drawings ............................................................................ 16 10.3 Distribution Standards Drawings Versioning .......................................................... 17 10.4 Standards Document Numbering ........................................................................... 17 11 DRAWING TITLING ................................................................................... 19 11.1 Titles ....................................................................................................................... 19 DM# 9118921 HPC-9CA-01-0002-2012 Page 3 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
APPENDIX A - REVISION INFORMATION ............................................................. 20 APPENDIX B - LOCATION CODES (NUMBERING & TITLING) ............................ 21 APPENDIX C - FACILITY CODES (NUMBERING) ................................................. 28 APPENDIX D - DISCIPLINE CODES (NUMBERING) ............................................. 29 APPENDIX E - DOCUMENT AND DRAWING TYPES (NUMBERING & TITLING) 31 APPENDIX F - DRAWING TITLE REFERENCES ................................................... 42 APPENDIX G - TRANSMISSION LINE PREFIX ..................................................... 46 APPENDIX H - LEGACY NUMBERING .................................................................. 48 APPENDIX I - WESTERN POWER LEGACY DRAWING NUMBERING STANDARD ........................................................................................................ 52 DM# 9118921 HPC-9CA-01-0002-2012 Page 4 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
1 PURPOSE This Specification defines the requirements for Numbering and Titling of Engineering Technical Documents and Drawings for Horizon Power. This Specification also captures legacy numbering that was used as a convention prior to Horizon Power (previously Western Power and State Energy Commission of WA - SECWA) which is still used in current projects. 2 COMPLIANCE All personnel involved in the creation and/or revision of Engineering Technical Documents and Drawings will comply with this specification. This includes project participants, Contractors, Suppliers and Principal Representatives. 3 OWNERSHIP Documents created by, or on behalf of Horizon Power are an asset of value. Engineering Technical Document and Drawings are and shall remain the property of Horizon Power and are not for distribution outside of Horizon Power except where specifically authorised by Horizon Power. 4 REFERENCES Document Number Description HPC-9CA-01-0001-2012 Engineering Drawings, General Requirements, Practices and Preparation of Drawings / CAD Specification 5 DEFINITIONS AND ABBREVIATIONS Term Description Attribute A unique part of a document number. Contractor The provider of goods or services under the Contract Commercial Commercially related documents applicable to a contract and/or project Documentation Formal communication between two or more parties for example a letter or Correspondence memo. This code is used to define the broad content of the document differentiating Discipline code between for instance Mechanical and Quality. This code further defines the document into specific kind of documents being either discipline specific or used by many disciplines; for instance, a single line Document Type diagram is a unique document type associated to the Electrical discipline while document type plan is generic. DM# 9118921 HPC-9CA-01-0002-2012 Page 5 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
Term Description Documents are all documents created for the purposes of the Contract and/or Document project that contain specific information about the facility and/or equipment and include the electronic files of such documents. Drawing The Principal’s Drawing Management Group provides document management Management and control services. Including systematic registration, dissemination, control, Group status reporting and storage of Controlled Documents. Drawings are all drawings, plans, sketches and layouts created for the Drawings purposes of the Contract and/or project and include electronic files of such documents. Ellipse Enterprise Management System. Facility Primary area within the location that the drawing is most appropriate. Horizon Power Regional Power Corporation. Location Location of the Site that the drawing or document refers to. Outdated or obsolete numbering no longer in use / numbering may be used for Legacy existing sites and facilities for revisions. May not be used for new Sites and numbering drawings. A single project identifier assigned by for inclusion in all document numbers Project Identifier generated by Horizon Power or its Contractors. Originator A code to identify the organization responsible for the development of the (Correspondence document. Only) Principal Horizon Power (Regional Power Corporation) Principal Document A number allocated to a document by The Principal. Number Project Management Documents that communicate non-technical information regarding the project. Documentation Project A single project identifier assigned by Horizon Power for inclusion in all Identifier/Contract documentation numbers generated for the project; combined with the contract Number number to define a specific Supplier package identifier. The Horizon Power application used for storing and managing all Controlled ProjectWise Engineering Technical Documents, Drawings and relative Engineering Data. An Alpha, Numeric or Numeric Alpha code to track and define the version of a Revision document at a particular point in the lifecycle. Recipient (Correspondence/ A code to identify the receiving organization. Commercial Only) DM# 9118921 HPC-9CA-01-0002-2012 Page 6 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
Term Description Horizon Power Standard is a document or drawing that prescribes the Standard mandatory requirements for all Engineering work performed. A person or company that assumes by secondary contract some or all of the Subcontractor obligations of an original contractor. Sub Supplier A Supplier who provides goods or services to another Supplier. Supplier Providers of equipment. Formal information which includes text documents, databases, and drawings Technical that communicate technical information pertaining to the physical or functional Documentation requirements of a project. WBS Work Break Down Structure. Work The Supplier/Contractor Scope of Work and Services defined in the Contract. 6 GENERAL REQUIREMENTS All document authors will and are responsible for ensuring an appropriate document number is requested as per the instructions outlined in section 6.1 Request for Number; prior to development of a document. The Principal’s Document Control Group shall allocate all document and drawing numbers. Registrations are recorded in the Horizon Power’s Technical Document Management System (DMS) ProjectWise. Supplier/Contractor will assign a Principal Document Number to all documents which are generated as part of the execution of Work; including those produced by any Subcontractors or Sub suppliers. 6.1 Request for Numbers All requests for numbers shall be sent to Horizon Power Document Control. Email address: HPDC@horizonpower.com.au All requests for numbers shall be on the latest revision of the electronic form, HPA-0000000-DC-FRM- 0001. This is obtainable from Horizon Power Drawing Management Group. DM# 9118921 HPC-9CA-01-0002-2012 Page 7 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
7 DOCUMENT NUMBER STRUCTURE AND CODING 7.1 Legacy Drawings Current drawing number vs legacy ( Including Western Power) Legacy drawing numbering convention shall only to be used in the scenario of an existing drawing (built during the legacy drawing numbering phase) undertaking an upgrade to the already constructed infrastructure. The legacy drawing numbering convention must not be used in the design/ commissioning phases of any new facilities. Horizon Power Drawing Management Group will allocate all legacy drawing numbers. Refer to Appendix H.2 South Hedland and Hedland Projects South Hedland and Hedland projects used a different numbering format as shown in Appendix H.1. Moving forward the new numbering drawing convention will be used. 7.2 Structure Location Drawing Number Convention Principal’s Representative will use the following numbering convention. Table 7-2-1 Location Drawing Number Convention AAA - AA - AA - AAA - NNNN - NN Location Doc. Sequence Sheet - Facility - Discipline - - - Code Type Number Number Note: No spaces shall be created before or after any attribute; including the hyphen. For Example HDT-SS-EL-LAY-0001-01 1. Location Code – Location of the Site, refer to Appendix B 2. Facility Code - For a list of Facility codes, refer to Appendix C 3. Discipline - The discipline selected will be the most appropriate for the content of the document. Note that this is not necessarily the discipline that originates the document. Refer to Appendix D 4. Document Type – For a list of document types, refer to Appendix E 5. Sequence – Document Control will assign a four-digit sequential number to all documents, so each resulting number is unique. 6. Sheet Number - Document Control will assign a two-digit sequential number Transmission Line Drawing Number Convention The Transmission Line drawing identifier shall include the substations at both ends of the line, with the following rules governing the order of precedence:- DM# 9118921 HPC-9CA-01-0002-2012 Page 8 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
1) Power stations (energy sources) shall have the highest order of precedence 2) Terminal Yards shall be the next in the order of precedence 3) This will be followed by Zone substations, as the lowest order of precedence 4) If the line connects two locations of equal precedence, then the location with the higher alphabetical order will take precedence. Examples: SHP - SHT 31 (SHP takes precedence as it is a Power Station and SHT is a Terminal Yard) KRT - BUL 81 (KRT takes precedence as it is a Terminal Yard and BUL is a Zone Substation) HDT - SHT X1 (both locations are Terminals, i.e. equal precedence. HDT takes precedence as it is higher on the alphabetical order) Principal’s Representative will use the following numbering convention. Table 7-2-2 Transmission Line Drawing Number Convention AAAAAAAA - AA - AA - AAA - NNNN - NN Transmission Doc. Sequence Sheet - Facility - Discipline - - - Line Code Type Number Number Note: No spaces shall be created before or after any attribute; including the hyphen. For Example: KRTDMP81-TL-EL-RPL-0001-01 1. Transmission Line Code – Transmission Line codes, refer to Appendix G 2. Facility Code - For a list of Facility codes, refer to Appendix C 3. Discipline - The discipline selected will be the most appropriate for the content of the document. Note that this is not necessarily the discipline that originates the document. Refer to Appendix D 4. Document Type – For a list of document types, refer to Appendix E 5. Sequence – Document Control will assign a four-digit sequential number to all documents, so each resulting number is unique. 6. Sheet Number - Document Control will assign a two-digit sequential number Concept and Tender Drawing Number Convention To differentiate current drawings from Tender / Concept drawings, Project specific drawing numbers shall be allocated. This allows the current drawing to remain available for active projects. The new project drawing will copy the content from the live drawing. The current drawing shall be referenced in the title block of the new project drawing. Once the project is confirmed by the HP Project Manager, the current drawing will be checked out for Modification and the concept drawing shall be superseded. The current drawing will incorporate the changes from the concept as required. DM# 9118921 HPC-9CA-01-0002-2012 Page 9 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
Principal’s Representative will use the following numbering convention. Table 7-2-3 Concept / Tender Drawing Number Convention AAAAAAAA - AA - AA - AAA - NNNN - NN Project Doc. Sequence Sheet - Facility - Discipline - - - Number Type Number Number Note: No spaces shall be created before or after any attribute; including the hyphen. For Example: M0001557-TL-EL-LAY-0001-01 1. Project Number – The Job number applicable to the project defined by Ellipse 2. Facility Code - For a list of Facility codes, refer to Appendix C 3. Discipline - The discipline selected will be the most appropriate for the content of the document. Note that this is not necessarily the discipline that originates the document. Refer to Appendix D 4. Document Type – For a list of document types, refer to Appendix E 5. Sequence – Document Control will assign a four-digit sequential number to all documents, so each resulting number is unique. 6. Sheet Number - Document Control will assign a two-digit sequential number Standalone Power Systems Numbering Convention Principal’s Representative will use the following numbering convention. Table 7-2-4 Standalone Power Systems Drawing Number Convention AAA ‐ AA ‐ AA ‐ AAA ‐ NNNN ‐ NN Ellipse Asset or Doc. Sequence Location Code - Standard - Discipline - - - Sheet Number Type Number Project Identifier Note: No spaces shall be created before or after any attribute; including the hyphen. For Example: EHR-GS011-EL-DGA-0005-05 – Site Asset Specific Drawing Number EHR-GP2095-EL-DGA-0005-05 - Project Standard Specific Drawing Number (Across Multiple Sites) 1. Location Code – Location of the Site, refer to Appendix B 2. Generation Systems / Generation Project Identifier DM# 9118921 HPC-9CA-01-0002-2012 Page 10 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
Individual Site Assets will be allocated a unique identifier generated from Ellipse. (GS011) Project Standard Specific drawings that will be used across all sites will be allocated a Generation Project Identifier. Last four digits of the project number shall be used (GP2095) 3. Discipline - The discipline selected will be the most appropriate for the content of the document. Note that this is not necessarily the discipline that originates the document. Refer to Appendix D 4. Document Type – For a list of document types, refer to Appendix E 5. Sequence – Document Control will assign a four-digit sequential number to all documents, so each resulting number is unique. 6. Sheet Number - Document Control will assign a two-digit sequential number Document Numbering Convention Principal’s Representative will use the following numbering convention. Table 7-2-5 Document Numbering Convention AAAAAAAA - AAAAAAA - AAA - AA - AAA - NNNN Contract Number / PO Project NUMBER Location Sequence - - - Discipline - Doc. Type - Number (If Code Number Applicable ) Note: No spaces shall be created before or after any attribute; including the hyphen. For Example: M0001557-0000000-DMP-EL-RPT-0001 - Non Contractual M0001557-HP12345-DMP-EL-RPT-0001 Horizon Power Contractual Document M0001557-S123456-DMP-EL-RPT-0001 – Non Specific HP Contractual Documents ( EPCM) 1. Project Number – The Job number applicable to the project defined by Ellipse 2. Contract Number / Purchase Order Number – Unique Contract / Purchase Order Specific Identifier will be allocated by the Project. Please use the General Code (0000000) if a Contract number / PO Number is not applicable. Horizon Power specific Contracts shall use HPXXXXX for ease of Identification. Non Specific HP Contracts (Supplier ie.EPCM / Subcontractor contract number) shall use SXXXXXX and will be assigned to all supplier data documentation denoted by the prefix S 3. Location Code – Location of the Site, refer to Appendix B DM# 9118921 HPC-9CA-01-0002-2012 Page 11 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
4. Discipline - The discipline selected will be the most appropriate for the content of the document. Note that this is not necessarily the discipline that originates the document. Refer to Appendix D 5. Document Type – For a list of document types, refer to Appendix E 6. Sequence – Document Control will assign a four-digit sequential number to all documents, so each resulting number is unique. 8 REDLINE NUMBERING A redline drawing could be a hand or electronic mark-up drawing, showing the ‘as built\as constructed’ status of the drawing. The redline drawings are used to provide as constructed and up to date information to those who require it to proceed with Work; whilst the drawing is being back-drafted to an ‘as built’ status, if applicable. Redline drawings are not a formal revision and as such are to be numbered using the numbering conventions described within this document suffixed by one the following extensions. _REV RLMU – Redline Mark Up. _REV RLNC – Redline No Change. For Example: HDT-SS-EL-LAY-0001-01_0 RLMU Where there are multiple redline mark-ups on the same drawing number and revision then the suffix is to include a numeric identifier. For example; _RLMU1, RLMU2 etc. DM# 9118921 HPC-9CA-01-0002-2012 Page 12 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
9 REVISION NUMBERING All revisions of a document must be issued to Horizon Power Drawing Management Group in sequential order. Documents that skip revisions will be returned to the originator for correction. Principal shall consider all documents having an alpha revision to be in the review or approval cycle or to have an issue status of issued for review, issued for tender or information only. Controlled deliverables will be allocated a Revision as shown in the matrices below. Table 9-1 Revision Number for New Documents and Drawings Table 9-2 Revision Sequence for the Update of Existing Documents and Drawings DM# 9118921 HPC-9CA-01-0002-2012 Page 13 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
9.1 Revision Description The revision description describes the status of the document within the lifecycle of the document at a specific point in time. The revision description is different to the issue reason; which describes why a specific document is being transmitted. The Project Number shall be added to the IFC and As Built Revision Descriptions, e.g. “Issued for Construction for PN123456” “AS BUILT for PN123456” 9.2 Cancelled deliverables Where a deliverable is cancelled, the drawings shall be revised to the next revision, watermarked ‘CANCELLED’ and the revision description updated to reflect the reason for cancellation. Drawings are then delivered to Document Control to be uploaded onto ProjectWise. Please Note: HorizonCAD Build Contains a Status Tool for Watermarks 9.3 Superseded deliverables Where a deliverable is superseded by a new drawing number, the existing drawing shall be revised to the next sequential revision, watermarked “Superseded“ with the new drawing number and the revision description updated to reference the new drawing number The new drawing number shall reference the superseded number in the revision description e.g. ‘Supersedes drawing BGP-GN-EL-0007-01’. Drawings are then delivered to Document Control to be upload onto ProjectWise Please Note: HorizonCAD Build Contains a Status Tool for Watermarks 9.4 File name File names of drawings must follow the following conventions. BRM-SS-EL-LAY-0001- CAD file name 01_Rev.dgn BRM-SS-EL-LAY-0001- PDF file name 01_Rev.pdf File names for legacy drawings Existing drawings that have alpha-numeric file names (e.g. sdtcv01.dgn) should retain their file names if they contain Reference Files or Raster Images. Renaming such files with attachments can break the links from drafting software Bentley MicroStation. Files that do not have attachments shall be updated to the Drawing Number captured on the drawing (e.g. SS174-100-1_Rev.dgn) DM# 9118921 HPC-9CA-01-0002-2012 Page 14 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
10 STANDARDS DOCUMENTS AND NUMBERS 10.1 Standard drawings numbering Standardised numbering conventions are required to manage standard drawings used in construction, maintenance, projects and specifications, where quite often drawings reference other drawings. The drawing numbering convention can be broken down in to a number of parts. Each part represents a different step in the classification of the drawing type given in Table 10-1. Table 10-1 Standard Drawing Number Convention AAA - AA - AA - AAA - NNNN - NN Unique Doc. Sheet HPA - SD - Discipline - - Sequence - Type Number Number Note: No spaces shall be created before or after any attribute; including the hyphen. For Example: HPA-SD-EL-LAY-0001-01 1. Location Code – HPA signifying Standard, refer to Appendix B 2. Facility Code – SD signifying Standard, refer to Appendix C 3. Discipline - The discipline selected will be the most appropriate for the content of the document. Note that this is not necessarily the discipline that originates the document. Refer to Appendix D 4. Document Type – For a list of document types, refer to Appendix E 5. Unique Sequence Number – Document Control will assign a four-digit unique sequential number to all standard drawings, so each resulting number is unique from Table 10-2. 6. Sheet Number - Document Control will assign a two-digit sequential number Table 10-2 Standard Drawing Number Convention NNNN STANDARD DRAWING TYPE UNIQUE SEQUENCE 0000-0999 Distribution Overhead 1000-1999 Distribution Underground 2000-2999 Distribution General 3000-3999 Transmission Substation 4000-4999 Transmission Line 5000-5999 Transmission General 6000-6999 Generation Fossil 7000-7999 Generation Renewable Drawing file name convention is DrawingNumber_VersionNumber.dgn Example is: HPA-SD-EL-LAY-0001-01_3.dgn for revision 3 HPA-SD-EL-LAY-0001-01_3.pdf for revision 3 DM# 9118921 HPC-9CA-01-0002-2012 Page 15 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
Examples of legacy standard drawing numbers1 superseded by this Section 10.1: HPA-DL-S-3002-01 HPA-SD-E-0001-01 This example indicates that the drawing is for all of Horizon Power (HPA), the facility is distribution line (DL) or Standard (SD), the discipline is structural (S) or electrical (E). The sequential number starts with ‘3’, so it is a general arrangement or ‘0’. The remainder of numbers are determined as required, the first is the drawing number, and the last is the sheet number. 10.2 Distribution Standards Drawings Drawings that are added to existing distribution design and construction manuals shall follow the legacy- numbering format for that manual, e.g. Distribution Construction Standard, Distribution Substation Manual, Distribution Design Catalogue. An example of drawing number for the Distribution Construction Standard is shown below: R3-1 (Title: Insulators - Reference chapter) H16-2/4 (Title: LBS with bypass switch & 2 bushing TX - High Voltage chapter) U9 (Title: Universal Pillar Installation Guide – LV Underground chapter) The first letter indicates the chapter of origin (e.g. High Voltage chapter). The number is the sequential drawing number within that chapter and ‘-x’ for sheets. Drawing file name convention is DrawingNumber_VersionNumber.dgn Format is AB-C-D_E e.g. R3-1_2.dgn or H16-2-4_3.dgn and same for .pdf A – Chapter of the standard eg. R; H B – Sequential number of construction type eg. 3; 16 C – Alternate construction type of same sequential number eg. 1; 2 D – Sheet number of drawing where multiple sheets (numeric) eg nil; 4 E – Revision number (numeric) eg, 2; 3, is separated by underscore “_” An example of drawing number for the Distribution Substation Manual is shown below: DSM-3-02 SHT 1 DSM-3-02 SHT 2 The first three letters indicate the manual of origin, the second number (3) indicates the chapter of origin (Substation Arrangements). The final number is the drawing number. Drawings from this manual frequently have multiple sheets, but the sheet number is not formally part of the drawing number. Note: the Distribution Substation Manual is being gradually incorporated into the Distribution Construction Standard as Chapter G. 1 Superseded standard HPC-9CA-01-0004-2013: Standard Drawing Numbers DM# 9118921 HPC-9CA-01-0002-2012 Page 16 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
An example of drawing number for the Distribution Design Catalogue is shown below: PO15 (Pole) TX1-2 (Transformer) LU11 (Universal Pillar) The first portion (consisting of letters) indicate the chapter of origin (Transformers). The remainder is the designation of the Compatible Unit (CU). Drawings from this manual frequently address multiple CUs, which differ from each other by the bill of materials. For PO15 drawing revision 1, the drawing file name will be PO15_1.dgn If there is more than 2 sheets on the drawing, the sheet numbers will be presented with a dash and revision with an underscore for the filename. For example TX1 has sheet 1 and sheet 2 on version 3, the drawing file names will be TX1-1_3.dgn and TX1-2_3.dgn 10.3 Distribution Standards Drawings Versioning Note that Distribution Construction Standards have revision numbers as letters, for historical reasons. When these are revised, they should be transitioned to numbered revisions. For example, an existing drawing of revision C would be superseded by a new drawing marked revision 4. The convention of the date on all distribution standards drawings and revisions will be dd/mm/yy format. 10.4 Standards Document Numbering A legacy system of standards document numbering will be retained since the convention has been in use and cross-referenced in multiple documents that relate to compliance and regulatory obligations. The numbering format is contained in the Standards Register (DM#1918455) that is used to maintain the currency and review period of standards within Horizon Power. Table 10-3 shows the numbering convention for standards documents. Table 10-3 Standards Documents Number Convention HPC - X A A - XX - NNNN YYYY Doc. Engineering Work Sequential Registration HPC - - Category - Type Area Type Number year Note: No spaces shall be created before or after any attribute; including the hyphen. For Example: HPC-8DJ-12-0002-2019 – LV Connected Battery Energy Storage Systems 1. Location Code – HPC signifying Standard Document 2. Document Type – 8 signifying Specification 3. Engineering Area – D signifying Electrical 4. Work Type – J signifying Requirements DM# 9118921 HPC-9CA-01-0002-2012 Page 17 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
5. Category – 12 signifying Generation Renewable 6. Sequence – 0002; Document Control will assign a four-digit sequential number to all documents from the register (DM#1918455), so each resulting number is unique. 7. Year – 2019; year the standard number was generated and registered Refer to the Standards Register (DM#1918455) for the numbering format and convention details. DM# 9118921 HPC-9CA-01-0002-2012 Page 18 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
11 DRAWING TITLING Titles of drawings in general will conform to the five-line format as described within this specification. All drawings shall be appropriately titled to clearly identify the location and item depicted by the drawing. Existing drawings being revised which do not conform to the current specification titling are to be updated to conform to this standard. 11.1 Titles To standardise the approach of drawing titling and assist in the data base search functions. The following shall apply: 1. Title Line 1 shall have the Geographical location, refer to Appendix B, e.g. KARRATHA TERMINAL No Deviation from these parameters shall be permitted 2. Title Line 2 shall be the Facility Type, Equipment Type or Switchyard Area, refer to Appendix F No Deviation from these parameters shall be permitted. 3. Title Line 3 shall contain a description of the type of drawing, refer to Appendix E Page 30 to 32 No Deviation from these parameters shall be permitted 4. Title Line 4 describe the area, item of plant or other information covered by the drawing. It should include identification by circuit number, bay number or any other information to describe the applicability of the drawings. The layout of the line should follow circuit number, voltage, circuit type and description. The description may be 1 or 2 lines 5. Title Line 5 (Optional) As above Some Typical Drawings (numbers and titles) as follows Number DMP-SS-EL-MAT-0001-01 Title Line 1 DAMPIER SUBSTATION Title Line 2 AUXILIARY POWER SUPPLIES Title Line 3 MATERIAL LIST Title Line 4 440V AC SUPPLY & Title Line 5 CHANGEOVER BOARD Number HDT-SS-EL-SCH-0001-01 Title Line 1 HEDLAND TERMINAL Title Line 2 PROTECTION Title Line 3 SCHEMATIC DIAGRAM Title Line 4 HDT508 22kV REACTOR 52C Title Line 5 DC PROTECTION DM# 9118921 HPC-9CA-01-0002-2012 Page 19 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
APPENDIX A - REVISION INFORMATION (Informative) Horizon Power has endeavoured to provide standards of the highest quality and would appreciate notification of errors or queries. Each Standard makes use of its own comment sheet which is maintained throughout the life of the standard, which lists all comments made by stakeholders regarding the standard. The document DM# 1539733 can be used to record any errors or queries found in or pertaining to this standard, which can then be addressed whenever the standard gets reviewed. Date Rev No. Notes 02/11/11 3 Added Location Codes for Rio Tinto Power Stations & Substations 01/12/11 4 Added Location Code for Carnarvon Solar Farm 25/01/12 5 Added Location Codes for Utah Point & Rottnest 24/05/12 6 Added Location Codes for new BHP Substations 30/05/12 7 Changed Document into a Standard 29/10/12 8 Reformatted and document and project numbering added Renamed, reformatted and project document numbering modified and 21/01/13 9 new document types added 16/04/13 10 Added Location Codes for South Hedland Terminal Document Revised to incorporate the addition of one more numerical field in part 4 of the drawing number for the South Hedland Project, 10/05/13 11 and to split the project numbering and document numbering parts into separate documents. Removed location codes and referenced CS#10 for ‘single source of 29/10/14 12 truth’. Added revision control Changed title from Generating Drawing Numbers for New Sites post Western Power to Drawing Numbers. Merged with GHD version 12. 07/12/17 13 Added new sections for Standards Drawings, WP standard template drawings. 17/01/2018 14 New CS 10 Number 13/12/2019 15 Issued for Review 07/05/2020 16 Numbering and Titling Documents Updated and Combined. Numbering and Titling Documents updated and combined. 26/05/2020 17 HPC-9CA-01-0003-2012 Drawing Titles and HPC-9CA-01-0004- 2013 Standard Drawing Numbers superseded by incorporating into this standard. DM# 9118921 HPC-9CA-01-0002-2012 Page 20 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
APPENDIX B - LOCATION CODES (NUMBERING & TITLING) DMP-SS-EL-MAT-0001-01 CODE LOCATION TYPE HPA HORIZON POWER REGION AST ANDERSON STREET SUBSTATION SUBSTATION AYN ARDYALOON COMMUNITY AYN ARDYALOON POWER STATION POWER STATION BLG BALGO COMMUNITY BGB BEAGLE BAY COMMUNITY BGB BEAGLE BAY POWER STATION POWER STATION BEN BENTLEY TOWN BEN BENTLEY SUBSTATION SUBSTATION BYA BIDYADANGA COMMUNITY BYA BIDYADANGA POWER STATION POWER STATION BLA BILLILUNA COMMUNITY BRM BROOME TOWN BRM BROOME POWER STATION POWER STATION BUL BULGARRA SUBSTATION SUBSTATION LOM CAMBALLIN / LOOMA TOWN LOM CAMBALLIN / LOOMA POWER STATION POWER STATION CLB CAPE LAMBERT SUBSTATION SUBSTATION CRN CARNARVON TOWN CRG CARNARVON POWER STATION POWER STATION DM# 9118921 HPC-9CA-01-0002-2012 Page 21 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE LOCATION TYPE CRD CARNARVON RENEWABLE - DERMS POWER STATION CRN CARNARVON SUBSTATION SUBSTATION CRL CORAL BAY TOWN CRL CORAL BAY POWER STATION POWER STATION CRS CORAL BAY SOLAR FARM SOLAR FARM CRL CORAL BAY WIND FARM WIND FARM CUE CUE TOWN CUE CUE POWER STATION POWER STATION DMP DAMPIER TOWN DMP DAMPIER SUBSTATION SUBSTATION DEN DENHAM TOWN DNP DENHAM POWER STATION POWER STATION DBY DERBY TOWN DBY DERBY POWER STATION POWER STATION DRN DJARINDJIN COMMUNITY DRN DJARINDJIN POWER STATION POWER STATION EKI EAST KIMBERLEY REGION EPI EAST PILBARA REGION ESP ESPERANCE TOWN EHR ESPERANCE HARBOUR ROAD SUBSTATION SUBSTATION EHR ESPERANCE POWER STATION POWER STATION EHR ESPERANCE WIND FARM WIND FARM EXP EXMOUTH TOWN EXP EXMOUTH POWER STATION POWER STATION DM# 9118921 HPC-9CA-01-0002-2012 Page 22 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE LOCATION TYPE FDS FAIRWAY DRIVE SUBSTATION SUBSTATION FIT FITZROY CROSSING TOWN FIT FITZROY CROSSING POWER STATION POWER STATION BRM FREDERICK STREET SUBSTATION SUBSTATION GPR GAP RIDGE SUBSTATION SUBSTATION GAS GASCOYNE REGION GJN GASCOYNE JUNCTION TOWN GJ GASCOYNE JUNCTION POWER STATION POWER STATION HC HALLS CREEK TOWN HC HALLS CREEK POWER STATION POWER STATION HDR HARDING RIVER DAM SUBSTATION SUBSTATION HDT HEDLAND TERMINAL TERMINAL HTN HOPETOUN TOWN HTP HOPETOUN POWER STATION POWER STATION BPS IPP - BOODARIE POWER STATION POWER STATION BKN IPP - BROCKMAN SUBSTATION SUBSTATION CBS IPP - CAPE LAMBERT BULK SUPPLY POWER STATION DBS IPP - DAMPIER BULK HANDLING SUB SUBSTATION DMS IPP - DAMPIER MAIN SUBSTATION SUBSTATION FIH IPP - FINUCANE INNER HARBOUR SUB SUBSTATION FIN IPP - FINUCANE ISLAND SUBSTATION SUBSTATION FOH IPP - FINUCANE OUTER HARBOUR SUB SUBSTATION GWY IPP - GOLDSWORTHY SUBSTATION SUBSTATION HPS IPP - HEDLAND POWER STATION POWER STATION DM# 9118921 HPC-9CA-01-0002-2012 Page 23 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE LOCATION TYPE HDS IPP - HOPE DOWNS SUBSTATION SUBSTATION HBI IPP - HOT BRIQUETTE IRON POWER STATION POWER STATION JAD IPP - JUNA DOWNS SUBSTATION SUBSTATION KRP IPP - KARRATHA POWER STATION POWER STATION LPS IPP - LAMBERT POWER STATION POWER STATION MAO IPP - MARANDOO SUBSTATION MSM IPP - MILLSTREAM SUBSTATION MSM IPP - MILLSTREAM SUBSTATION SUBSTATION NPS IPP - NELSON POINT SUBSTATION SUBSTATION NGA IPP - NIMINGARRA POWER STATION PWA IPP - PANAWONICA SUBSTATION PDC IPP - PDC OTHER BHP IPP - PORT HEDLAND SUBSTATION SUBSTATION RYL IPP - ROY HILL SUBSTATION SUBSTATION SGP IPP - SHAY GAP SUBSTATION SUBSTATION SRY IPP - STRELLEY SUBSTATION SUBSTATION TPE IPP - TOM PRICE TOWN WAS IPP - WEST ANGELES SUBSTATION WCT IPP - WICKHAM 1 OPERATIONS POWER STATION POWER STATION JGL JIGALONG COMMUNITY KLU KALUMBURU COMMUNITY KLU KALUMBURU POWER STATION POWER STATION KRT KARRATHA TOWN DM# 9118921 HPC-9CA-01-0002-2012 Page 24 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE LOCATION TYPE KTP KARRATHA TEMPORARY POWER POWER STATION KTS KARRATHA TEMPORARY SUBSTATION SUBSTATION KRT KARRATHA TERMINAL TERMINAL KIM KIMBERLEY REGION KUN KUNUNURRA TOWN KPC KUNUNURRA PARRYS CREEK SUBSTATION SUBSTATION KUG KUNUNURRA POWER STATION POWER STATION KUN KUNUNURRA SUBSTATION SUBSTATION LAK LAKE ARGYLE TOWN LAK LAKE ARGYLE SUBSTATION SUBSTATION LAV LAVERTON TOWN LAV LAVERTON POWER STATION POWER STATION LEO LEONORA TOWN LEO LEONORA POWER STATION POWER STATION MLB MARBLE BAR TOWN MLB MARBLE BAR POWER STATION POWER STATION MKA MEEKATHARRA TOWN MKA MEEKATHARRA POWER STATION POWER STATION MEN MENZIES TOWN MEN MENZIES POWER STATION POWER STATION MID MIDWEST REGION MMG MOUNT MAGNET TOWN MMG MOUNT MAGNET POWER STATION POWER STATION MNM MOUNT NEWMAN MINING SUBSTATION SUBSTATION DM# 9118921 HPC-9CA-01-0002-2012 Page 25 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE LOCATION TYPE MGP MUNGALLAH POWER STATION POWER STATION MRO MURCHISON RADIO ASTRONOMY POWER STATION MDR MURDOCH DRIVE SUBSTATION SUBSTATION NRS NORSEMAN TOWN NRS NORSEMAN POWER STATION POWER STATION NUL NULLAGINE TOWN NUL NULLAGINE POWER STATION POWER STATION ONS ONSLOW TOWN OWP ONSLOW POWER STATION POWER STATION OLT ONSLOW SOLAR SOLAR FARM OLT ONSLOW TOWN ZONE SUBSTATION SUBSTATION ORD ORD RIVER HYDRO POWER STATION POWER STATION PBO PARABURDOO TOWN PCK PEGS CREEK SUBSTATION SUBSTATION PIL PILBARA (NWIS REGION PSN POINT SAMPSON TOWN PSN POINT SAMPSON SUBSTATION SUBSTATION PHD PORT HEDLAND TOWN RPS REDBANK POWER STATION POWER STATION ROE ROEBOURNE TOWN ROE ROEBOURNE SUBSTATION SUBSTATION RTP ROTTNEST ISLAND REGION RTP ROTTNEST ISLAND POWERSTATION POWER STATION SAN SANDSTONE POWERSTATION POWER STATION DM# 9118921 HPC-9CA-01-0002-2012 Page 26 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE LOCATION TYPE SAN SANDSTONE TOWN SHP SOUTH HEDLAND POWER STATION POWER STATION SHT SOUTH HEDLAND TERMINAL TERMINAL GLD SOUTH REGION REGION SWC SOUTH WEST CREEK SUBSTATION SUBSTATION SHL STOVEHILL SUBSTATION SUBSTATION UTP UTAH POINT SUBSTATION WBN WARBURTON COMMUNITY WRN WARMUN COMMUNITY WRN WARMUN POWER STATION POWER STATION WFD WEDGEFIELD SUBSTATION SUBSTATION WKI WEST KIMBERLEY REGION WPI WEST PILBARA REGION WCT WICKHAM TOWN WIL WILUNA TOWN WIL WILUNA POWER STATION POWER STATION WYN WYNDHAM TOWN WPS WYNDHAM EMERGENCY POWER STATION POWER STATION WYN WYNDHAM SUBSTATION SUBSTATION YAL YALGOO TOWN YAL YALGOO POWER STATION POWER STATION YGA YUNGNORA COMMUNITY YGA YUNGNORA POWER STATION POWER STATION DM# 9118921 HPC-9CA-01-0002-2012 Page 27 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
APPENDIX C - FACILITY CODES (NUMBERING) DMP-SS-EL-MAT-0001-01 CODE FACILITY BS BATTERY ENERGY STORAGE SYSTEM DE DEPOTS DL DISTRIBUTION LINES GF GEOTHERMAL FARM GS GENERATION SYSTEMS ( SPS) HF HYDRO FARM HG HYBRID GENERATION SYSTEM HY HYDROGEN POWER STATION PS POWER STATIONS SD STANDARD ** ONLY USE FOR HP STANDARD NUMBERING** SF SOLAR FARM SS SUBSTATIONS AND SWITCHYARDS TF TIDAL FARM TL TRANSMISSION LINES WF WIND FARM DM# 9118921 HPC-9CA-01-0002-2012 Page 28 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
APPENDIX D - DISCIPLINE CODES (NUMBERING) DMP-SS-EL-MAT-0001-01 CODE DESCRIPTION AD ADMINISTRATION AR ARCHITECTURAL BD BUSINESS DEVELOPMENT / STRATEGIC MARKETING CI CIVIL CS COMMISSIONING CM COMMUNICATION SYSTEMS CN CONSTRUCTION/CONSTRUCTION MANAGEMENT CO CONTRACTS DC DOCUMENT CONTROL EL ELECTRICAL EN ENVIRONMENTAL EP EPCM ES ESTIMATING FA FABRICATION FI FINANCE GE GEOLOGY & GEOTECHNICAL HS HEALTH & SAFETY HR HUMAN RESOURCES IM INFORMATION MANAGEMENT IS INFORMATION SYSTEMS/ICT IX INSPECTION SERVICES DM# 9118921 HPC-9CA-01-0002-2012 Page 29 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION IC INSTRUMENTATION & CONTROL LA LANDSCAPE LO LOGISTICS AND MATERIAL MANAGEMENT MA MAINTENANCE ML MATERIALS/METALLURGY ME MECHANICAL MT METERING MD MULTI DISCIPLINE OP OPERATIONS PA PLANNING APPROVALS AND LAND DEVELOPMENT PC PROJECT CONTROLS AND PLANNING PI PIPING PM PROJECT MANAGEMENT PT PROCUREMENT QA QA/QC RI RISK SD SAFETY IN DESIGN (ENSMS) SR SAFETY & RISK SC SCADA SE SECURITY ST STRUCTURAL SU SURVEYING /GIS DM# 9118921 HPC-9CA-01-0002-2012 Page 30 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
APPENDIX E - DOCUMENT AND DRAWING TYPES (NUMBERING & TITLING) DMP-SS-EL-MAT-0001-01 CODE DESCRIPTION PROJECT MANAGEMENT AGC AGREEMENT AGN AGENDA COE CLOSE OUT EVALUATION FNO FILE NOTE FRM FORM HDD HANDOVER DOSSIER IMG IMAGE IST INSTRUCTION LTR LETTER MEM MEMORANDUM MOM MINUTES OF MEETING PHT PHOTO ORG ORGANISATION CHART POS POSITION DESCRIPTION PRS PRESENTATION PPL PROPOSAL / TENDER SUBMISSION TO CLIENT SOW SCOPE OF WORK AND/OR SERVICES STR STRATEGY DM# 9118921 HPC-9CA-01-0002-2012 Page 31 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION PROJECT CONTROLS BUD BUDGET CST COST REPORT CTR COST TIME RESOURCE EST ESTIMATE PCR PROJECT CHANGE REQUEST PGR PROGRESS REPORTS VAR VARIATION WBS WORK BREAKDOWN STRUCTURE CONTRACTS ADD RFP ADDENDUM AWL CONTRACT AWARD COVER LETTER BKG BANK GUARANTEE CBE COMMERCIAL BID EVALUATION CDA CONFIDENTIALITY DEED/AGREEMENT CEC CONTRACT EXECUTION CHECKLIST CLA CLARIFICATION/DEPARTURE CLM CLAIM COT CONDITIONS OF TENDERING CRV CONTRACT VARIATION CTS CONTRACT SECURITY DM# 9118921 HPC-9CA-01-0002-2012 Page 32 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION DEE DEED OF SETTLEMENT EOI EXPRESSION OF INTEREST EVL TENDER EVALUATION EXC EXECUTED CONTRACT INV INVOICE ITT INVITATION TO TENDER LOI LETTER OF INTENT MOU MEMORANDUM OF UNDERSTANDING NOD NOTICE OF DELAY NOV NOTICE OF VARIATION NSP NOTICE OF SUCCESSFUL PROPOSAL NUP NOTICE OF UNSUCCESSFUL PROPOSAL PCO PURCHASE ORDER POP PROPOSAL OPENING RECORD POR PURCHASE ORDER REQUISITION PQL PRE-QUALIFICATION PRC PROGRESS CLAIM QTE SUPPLIER QUOTATION RFA RECOMMENDATION FOR AWARD RFS RECOMMENDATION FOR SHORTLIST RFI REQUEST FOR INFORMATION DM# 9118921 HPC-9CA-01-0002-2012 Page 33 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION RFP REQUEST FOR PROPOSAL RFQ REQUEST FOR QUOTATION SDR SUPPLIER DATA REQUIREMENTS (SDRL) SOR SERVICE ORDER SSJ SOLE SOURCE JUSTIFICATION TBE TECHNICAL BID EVALUATION TDP TECHNICAL DEVIATION PROPOSAL / CONCESSION REQUEST TRA DOCUMENT TRANSMITTAL VAQ VARIATION APPROVAL REQUEST WCO WORKS CONTRACT QUALITY ALT SAFETY ALERT CKL CHECKLIST AUD AUDIT REPORT CAR CORRECTIVE ACTION REQUEST CAT CALIBRATION AND TEST RECORD FAT SUPPLIER TESTING DOCUMENTS FTC FUNCTION TEST CERTIFICATE GDE GUIDE IAI INSPECTION ASSESSMENT INSTRUCTION ITP INSPECTION & TEST PLAN DM# 9118921 HPC-9CA-01-0002-2012 Page 34 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION ITR INSPECTION & TEST REPORT NCR NON-CONFORMANCE REPORT POL POLICY PRO PROCEDURE PQS SUPPLIER PRE-QUALIFICATION QAN QUALITY ALERT NOTICE QSS QUALITY SHOP SURVEY WOI WORK INSTRUCTION DOCUMENT CONTROL DRF DRAWING REQUEST FORM PDM PROJECT DISTRIBUTION MATRIX TEM TEMPLATE ENGINEERING AEL AUTHORISED ENGINEERS LIST BOD BASIS OF DESIGN BOM BILL OF MATERIALS CAL CALCULATION CER CERTIFICATE CHT CHART COC CERTIFICATE OF COMPLETION CPK CONSTRUCTION WORK PACK DM# 9118921 HPC-9CA-01-0002-2012 Page 35 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION DEC DESIGN CRITERIA DAS DATASHEET EDQ EQUIPMENT DATA QUESTIONNAIRE ENM ENGINEERING ANALYSIS MODEL FLC FLOWCHART FRP FORTNIGHTLY REPORT HMS HAZARDOUS MATERIAL SCHEDULE HZR HAZARD REPORT IDX INDEX IOM INSTALLATION AND OPERATIONS MANUAL JOB JOB BOOK / DOCUMENT INDEX LST LIST (E.G. EQUIPMENT, LINE TIE-INS, BATTERY LIMITS ETC.) MAN MANUAL MAP MAPS MTX MATRIX MDL MASTER DOCUMENT LIST MDR MANUFACTURER'S DATA REPORT MRP MONTHLY REPORT MST METHOD STATEMENT MTO MATERIAL TAKE OFF PHI PHILOSOPHY DM# 9118921 HPC-9CA-01-0002-2012 Page 36 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION PLN PLAN REC RECORD REF REFERENCE REG REGISTER REQ REQUISITION RPT REPORT SCO CONTRACT SPECIFICATION SDL SUPPLIER DOCUMENT / DRAWING LIST SFT SOFTWARE SPC SPECIFICATION SRL SUPPLIER REQUIREMENT LIST SST STANDARD SPECIFICATION TEN TECHNICAL NOTE /STUDY TQR TECHNICAL QUERY VIP VALUE IMPROVEMENTS WRP WEEKLY REPORT DRAFTING (DRAWING TYPES) ALM ALIGNMENT SHEET APL AREA PLAN AMT ARRANGEMENT ASY ASSEMBLY DM# 9118921 HPC-9CA-01-0002-2012 Page 37 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION BLK BLOCK DIAGRAM CPT CONCEPT DRAWING CON CONNECTION DIAGRAM DES DESCRIPTIVE DET DETAIL DNG DRAINAGE DRAWING ELE ELEVATION FND FOUNDATIONS GAR GENERAL ARRANGEMENT HAZ HAZARDOUS AREA INS INSTALLATION DETAIL INC INTERCONNECTION DIAGRAM KEY KEY DIAGRAM LAY LAYOUT LSP LIGHT & SMALL POWER LOC LOCATION PLAN MAF MANUFACTURER DRAWING MAT MATERIAL LIST MOD MODEL NET NETWORK DIAGRAM OIN OVERHEAD INSTALLATION DM# 9118921 HPC-9CA-01-0002-2012 Page 38 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION ONE OVERHEAD NETWORK OSE OVERHEAD SERVICES PIP PIPING SUPPORT DRAWING PLA PLAN PFD PROCESS FLOW DIAGRAM PRF PROFILE DRAWING RAT RATING DIAGRAM RPL ROUTE PLAN SCD SCHEDULE SCH SCHEMATIC DIAGRAM SEC SECTION DRAWING SFD SIGNAL FLOW DIAGRAM SLD SINGLE LINE DIAGRAM SIP SITE PLAN SUT SITE UTILISATION SIW SITE WORK SKT SKETCH STW STEELWORK DRAWING SYS SYSTEM FUNCTION DIAGRAM TAB TABLE TER TERMINATION DIAGRAM DM# 9118921 HPC-9CA-01-0002-2012 Page 39 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION UIN UNDERGROUND INSTALLATION UNE UNDERGROUND NETWORK UGS UNDERGROUND SERVICES WID WIRING DIAGRAM CONSTRUCTION CIR CONSTRUCTION INSPECTION REPORT COS CONSTRUCTION STRATEGY FCN FIELD CHANGE NOTICE FIR FIELD INSPECTION REPORT FQY FIELD QUERY JSA JOB SAFETY ANALYSIS POB PERSONS ON SITE REGISTER SIN SITE INSTRUCTION SQR SITE QUERY COMMISSIONING CDR DAILY REPORT CMM COMMISSIONING METHOD STATEMENT CMS COMMISSIONING MANAGEMENT SYSTEM GENERATED DOCUMENT CPL COMMISSIONING PUNCH LIST CPS COMMISSIONING PARAMETER SETTINGS CRP COMMISSIONING REPORT DM# 9118921 HPC-9CA-01-0002-2012 Page 40 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
CODE DESCRIPTION COM COMMISSIONING PROCEDURE CWP COMMISSIONING / COMPLETIONS WORK PACK DOS COMMISSIONING DOSSIER NOE NOTICE OF ENERGISATION OTP OPERATION TEST PROCEDURE TRN TRAINING DOCUMENTS DM# 9118921 HPC-9CA-01-0002-2012 Page 41 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
APPENDIX F - DRAWING TITLE REFERENCES FACILITY TYPE, EQUIPMENT TYPE OR SWITCHYARD AREA ***Line TWO of the Title*** DESCRIPTION REMARK ALARMS SCHEMATICS AUXILIARY POWER SUPPLIES AC SUPPLIES & DISTRIBUTION BUILDING INTERNAL PLANS BATTERY ENERGY STORAGE SYSTEM BUSBARS DRAWINGS ASSOCIATED WITH RIGID BUSBARS CIRCUIT BREAKERS CAPACITOR BANKS COUPLING CAPACITORS CONDUCTORS CIVIL SCHEDULES & ACCESSORIES (INCLUDING SEALING CABLING ENDS) CONSUMER MAINS INCLUDES TERMINAL PALMS, ADAPTOR PLATES & CONNECTORS SPACERS COMMUNICATIONS INCLUDES PILOT WIRE SYSTEMS CONTROL PANELS MIMIC TYPE CONTROL SCHEMATICS CABLE TRENCHES DM# 9118921 HPC-9CA-01-0002-2012 Page 42 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
DESCRIPTION REMARK CURRENT TRANSFORMERS CURRENT & VOLTAGE TRANSFORMERS COMBINED CT & VT CABLE TRAYS DC SUPPLIES DEPOTS DISCONNECTOR DISTRIBUTION NETWORK DISTRIBUTION SUBSTATION DISTRIBUTION CONNECTION EARTHING EARTHING COMPENSATORS ELECTRICAL CONTROL ROOM EQUIPMENT ENCLOSURES MARSHALLING BOX, FUSE BOX ELECTRICAL RESTRICTED USE EARTH SWITCH FENCES FIRE PROTECTION GEOTHERMAL FARM GENERAL PROPERTY DETAILS ETC. GENERATION SYSTEMS HYDRO FARM DM# 9118921 HPC-9CA-01-0002-2012 Page 43 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
DESCRIPTION REMARK HYBRID GENERATION SYSTEMS HEAT RECOVERY SYSTEM HYRDOGEN POWER STATION INTERCONNECTION LINES INSULATORS INSULATOR SET HARDWARE LABELS SCHEDULES AND DETAILS LIGHTING LANDSCAPING LINE TRAPS MICROGRID METERING PROTECTION CUBICLE ARRANGEMENT & WIRING DIAGRAMS PROTECTION RACKS ARRANGEMENT & WIRING DIAGRAMS PROTECTION SCHEMATICS POWER STATION REACTORS ROADS RTU CUBICLE SWITCHBOARD SCADA DM# 9118921 HPC-9CA-01-0002-2012 Page 44 of 54 Print Date 25/05/2020 © Horizon Power Corporation Uncontrolled document when downloaded. Refer to CS10 for current version.
You can also read