References List 2008 2021 - Inprocess
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Document Control Document Title Inprocess References List 2008 - 2021 Date 23 June 2021 Document Reference 2021.3 Author Josep Anton Feliu/Mar Prada All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 2
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Inprocess delivered a dynamic simulation study in order to German analyze the dynamic behavior of a 3-stage compressor Dynamic Aspen Equipment Compressor DSS for Gas Turbo 2021 Qatar Oil & Gas driven by a gas turbine with speed variation for various Simulation Study Manufacturer for Compressors for an HYSYS Manufacturer transient operations. The simulation scenarios evaluated the for Compression a Qatar oil upstream field adequacy of the antisurge valve sizing, the ESD valve Systems company requirements, this may be hot or cold gas as needed as well as the confirmation settle-out conditions of the system. Inprocess developed a dynamic simulation model in Aspen HYSYS of the compression system with the objective of determining its adequacy and the need for any additional protection system that might be required. Therfore, German Inprocess analyzed the adequacy of the anti-surge valve Dynamic Simulation Dynamic Compressor Aspen Equipment size and its timing to avoid surge during the compressor Study for the 2021 Iraq Oil & Gas Simulation Study Manufacturer shutdown; we evaluated the requirements of a hot/cold gas treatment HYSYS Manufacturer for Compression (US Office) for bypass valve; we confirmed the settle-out conditions of the compressors in an Systems an Iraq oil& field system; we demonstrated the effectiveness of the control oil field operator system in different scenarios such as variation of the feed gas pressure, turndown or blocked outlet; we performed the compressor system start-up to validate the start-up procedure, confirm the process control performance, verify the trip settings and identify possible limitations. Inprocess helped the client in the development of a steady state simulation model of the triple effect evaporator system to be used by client to improve the understanding of the Japanese Petrochemic process, its constraints and interactions, in order to improve Steady State Model Aspen the current and future operation of the triple effect columns. Steady State Multinational 2021 Spain Operator als; Bulk development of the Simulation Petrochemical HYSYS The project was carried out in three phases: a) To study the triple effect Chemicals Modelling Study company historical data of the plant during one-year and looking for evaporator (Spanish site) issues or bad operations; b) To build a steady state model of the plant, the model was calibrated to a representative day; c) To analyse with the model a number of operational scenarios Inprocess will adapt its Historian_Link application to the German needs of this client, operator of an FPSO in the Danish Connection of an UniSim Instrumentatio Instrumentation 2021 Denmark Oil & Gas sector of the North Sea, who wants to connect the OTS that Operator Training Operator Training Provider for a Design n Provider Inprocess is currently developing for them with the historian System (OTS) System to the plant French Oil&Gas database in a way that it is possible to upload operating Historian database Operator conditions recorded in the historian and use them as initial conditions for an OTS exercise All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 3
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Inprocess has developed an Operator Training Simulator (OTS) for Ascensus Specialties’ hydrogen producing plant located in Elma, Washington (USA). This hydrogen plant is part of the Ascensus production plant that meets the growing, global demand for high-quality Sodium Borohydride, reactive and alkali metals, boranes, and related chemical compounds. Inprocess project comprises the design, engineering, Development of a delivery, testing and installation of the OTS, as well as direct-connect OTS Aspen Fine training scenarios and project management. For the Operator Training US Chemicals 2021 USA Operator for a steam-reformer HYSYS Chemicals execution of this project, Inprocess has been using Aspen System (OTS) Company hydrogen producing HYSYS® Dynamics as the process simulation engine, plant Emerson’s SimulatePro as the DCS emulation package, and Inprocess Infrastructure Suite (IIS) to provide all the required data connectivity and instructor functionalities. This Direct-Connect OTS by Inprocess utilizes a high-fidelity dynamic model of the process, including the following plant areas: Natural Gas Preparation, Catalytic Reformation furnace, Catalytic Shift conversion, PSA, Vent Gas Recovery, Waste Heat Recovery/Steam Generation, and Water Treatment. Inprocess is in charge of developing the emulated OTS that will comprise the processing facilities and their associated Operator Training utilities of four Habshan fields. Implementation Simulators for four Services processing facilities Aspen Consulting & The Operator Training Simulator OTS will be developed for Operator Training 2021 UAE Oil & Gas the main process units in Habshan 0, Habshan 1, Habshan Provider for a (and their HYSYS Services System (OTS) 2 and Habshan 4; as well as their associated Utilities. The UAE National Oil associated utilities) Company in four Emirates scope for this project includes the complete delivery and oil&gas fields commissioning of the OTS including design, development, engineering, configuration, training, and commissioning activity for this emulated ABB 800xA Simulation for new Taking advantage of the dynamic simulation model Dynamic FPSO Operator throttle valve Aspen developed for the OTS currently in use in the FPSO, our 2021 Ghana Operator Oil & Gas Simulation in a WestAfrican upstream High HYSYS client requested us to carry out additional operability Modelling Study field Pressure Fuel Gas analysis of the throttle valve located upstream of the Compressors compressors in the high pressure fuel gas system. In-House Technical This german refinery operator requested one of the Steady State German Support during the Aspen Inprocess engineers to work on-site to provide Technical 2021 Germany Operator Refining Simulation Refinery development and HYSYS Support to the refinery engineers during the development of Modelling Study Operator usage of the refinery the Steady State model of the refinery unit and as well to unit SS model monitor its usage and the benefits obtained from it. All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 4
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Dynamic Simulation Aspen Revalidation by dynamic simulation of some of the valves in Flare Systems Study to revalidate 2021 Belgium Operator Refining this Belgian refinery Belgian Refinery HYSYS Analysis the NC3 valves in the refinery Dynamic Japanese FPSO Dynamic Simulation OLGA 2021 USA EPC Oil & Gas Dynamic Simulation Study to analyze the operational Simulation constructor Studies for the behaviour of the subsea lines that connect the many Modelling Study (USA office) FPSO subsea lines wellheads with the FPSO The simulation project main purpose was to deliver to the EPC the results of the dynamic simulation studies in order to evaluate (with the new data, after an improvement study to Dynamic Simulation optimize the operating modes and to increase the NH3 and Study for a Steam & Aspen Bulk Urea production) the response of the system and the Dynamic 2021 Qatar EPC suitability of the protective controls and devices currently Power Generation Simulation Italian EPC HYSYS Chemicals System in an installed in the Steam & Power System. Modelling Study Ammonia and Urea To validate the planned strategy, it was considered complex necessary to carry out operating tests using an already existing dynamic simulation model for both Steam and CO2 Networks, after updating and improving it, before carrying out the necessary series of simulation scenarios. Update and improvement of an Aspen Dynamic 2021 Italy EPC Natural Gas An existing dynamic model already built and delivered by existing dynamic Simulation Italian EPC HYSYS Inprocess in a different framework was required to be simulation model Modelling Study udpated for a different client application already develivered by Inprocess Brazilian Training Simulator Aspen Bulk Inprocess entered into a framework agreement with client to Operator Training Chemical for the chlorine 2021 Brazil Operator develop a series of training tools based on dynamic HYSYS chemicals System (OTS) Company processing system simulations (OTS). The initial project has been to develop an in a VCM complex OTS for the chlorine processing system in the VCM plant PDH plant in the Inprocess has developed a Digital Twin (rigorous dynamic Spanish site of a Aspen Petrochemic Online Digital Twin 2021 Spain Operator simulation model) of two units of the PDH complex Online German for the depropanizer HYSYS als (depropanizer and C3 splitter) and has connected it online Appplication chemicals unit in the PDH plant with the instrumentaiton database. The DT will then serve to company monitor equipment performance and to run what-if studies Migration of an Process Bulk Client decided to change the online platform where the Process existing Inprocess VMGSim 2021 Denmark Technical Support existing OTS that was delivered by Inprocess was being Licensor OTS to a new Licensor chemicals & Consultancy hosted. Client requested technical support to facilitate the client's online migration project from the old platform to the new one platform All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 5
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Under the contract with the FPSO constructor, client will deliver six centrifugal compressor trains: one low pressure (LP), three medium pressure (MP) and two high pressure Swiss Dynamic Simulation (HP), which are all driven by fixed speed electric motors. Dynamic Study for six Compressor Aspen Equipment The whole application will have the following capacities for Simulation Study compressors trains 2021 Senegal Oil & Gas Manufacturer for each compression system: for Compression in a FPSO offshore HYSYS Manufacturer a Japanese • LP - One Train with 100% capacity Systems Senegal FPSO • MP - Three trains with 50% capacity each constructor • HP - Two trains with 100% capacity each. Client has requested Inprocess to carry out a Dynamic Simulation Study for all these FPSO Compressors The existing Export Gas Compressor in the offshore gas plant, is expected to become a bottleneck beyond year 2021 to handle the forecasted export gas profile. During a FEED Abu Dhabi office Dynamic Dynamic Simulation Aspen United Arab study, it was proposed to augment the export gas handling of an Egyptian 2021 EPC Natural Gas Simulation Study Study for Off Gas capacity by operating Amine Bypass Unit Compressor in EPC working for HYSYS Emirates for Compression Compressor at at an ‘export mode’ permanently in parallel with the Export Gas a Middle East Systems Offshore Gas Plant Compressor and to install a new Off Gas Compressor to NOC handle low pressure gas. The detailed dynamic simulation study needed to determine the adequacy of the proposed arrengement After deciding to increase production in an Emirates field to 85 MSTBOPD of crude oil, the depressurization, MDMT and De-Pressurisation, United Arab hydrates formation study already carried out by Inprocess in Emirates EPC MMDT and Hydrate OLGA 2020 EPC Oil & Gas HIPPS or other 2015 needed to be updated with the new production levels for an Emirates study for the 85 Emirates Depressurization and compositions performing simulated topside NOC MBD Wellhead depressurizations for all WHT and pipelines determining the Towers minimum temperature achieved and determining if selected metals are valid and if hydrates will be formed All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 6
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Development and commissioning of a Lifecycle OTS whose main purpose will be to train the control room operators of an FPSO located in the gulf of Mexico. On top of that, because this OTS is going to be built following Inprocess’ Lifecycle approach: • Client's engineers will benefit from the results obtained with the dynamic simulation model (built in Honeywell’s UniSim Design) during the design phase of the FPSO’s topsides, • The proposed operating procedures will be validated and Japanese FPSO Lifecycle OTS for an UniSim tested in a preliminary Process Trainer (emulated OTS), Operator Training 2020 Mexico EPC Oil & Gas constructor FPSO to be located Design • The configuration of the Integrated Control and System (OTS) (Mexican office) in the Gulf of Mexico Safeguarding System (ICSS) provided by ABB will be checked out in a virtual FAT (against the results of the process simulation model), • The control room operators will be deeply trained well before first oil in the risk-free environment provided by the direct-connect OTS, • Client’s Operations team will be supported during the start- up of the FPSO by the Inprocess’ engineers which would have gained extensive process, control, and procedures knowledge during the development of the OTS Development of a dynamic simulation model of a C3 splitter Dynamic German Aspen Petrochemic in a PDH plant in order to improve the understanding of the Dynamic Simulation 2020 Spain Operator Simulation Study Chemical process, controls, constraints and interactions, in order to Study for a C3 HYSYS als for Process Company improve the current and future operation of the unit (e.g. Splitter Unit Control Analysis (Spanish site) hydraulic conditions and flooding limits, optimal sensitive tray, etc.) Dynamic Simulation Study to determine the revamp Dynamic Simulation Germany Dynamic Swiss Aspen Equipment possibilities of a compression system that included as driver Study for the 2020 Refining Simulation Study Compressors a fix-speed electrical motor, a speed increasing gear box revamping of an HYSYS Manufacturer for Compression Manufacturer and one-barrel compressor, type RV 35-4. For future existing Systems (German Office) operation the barrel compressor will be revamped and E- compression system motor and gear box will be reused Dynamic Swiss Aspen Equipment Feasibility study by dynamic simulation to determine the Feasibility Study for 2020 Germany Natural Gas Simulation Study Compressors adequacy of a 4-stage propylene compressor evaluating any Propylene HYSYS Manufacturer for Compression Manufacturer driver limitation during the start-up of the compression Compressor Systems (German Office) system All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 7
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Project to evaluate by dynamic simulation the Start-up of the Refrigeration Compressor in the Mixed Refrigerant Cycle Dynamic system. Simulation Study UniSim Equipment Additionally, Inprocess developed a software application that for Compression German MRC Simulation 2020 Germany Natural Gas facilitated Atlas Copco's engineers to interface with the Systems; Compressors Model and Design Manufacturer Dynamic Simulation model, allowing changing key selected Software Manufacturer Application data of the models and perform sensitivity analyses of the Extension and different predefined configurations. The application had a Programming library of different possible compressor configurations with the capability of expand it by users when required. Development of a Lifecycle Operator Training Simulator (LC- OTS) for Anna Nery Floating Production Storage and Offloading (FPSO) platform, which will be deployed at Petrobras' Marlim field in the Campos Basin. Although the LC-OTS's main purpose is to train the control room operators on a direct-connect OTS, Yinson, like it has Singapore Lifecycle OTS for an Aspen done before with other LC-OTS with Inprocess, will benefit Operator Training 2020 Singapore EPC Oil & Gas FPSO FPSO located in a HYSYS from a wider scope during the engineering phases including: System (OTS) Constructor Brazilian field * DynamicSimulation studies, operating procedures validation. * Early operators and engineers training with an Early- Emulated OTS. * Virtual commissioning of the ICSS configuration. * Processing facilities start-up support. * Post start-up support with the resulting Digital Twin. Inprocess has performed a complete dynamic model for the Engineering Studies Aspen FPSO topside facility. This dynamic model has been Dynamic 2020 Norway EPC Oil & Gas FPSO for Operations planned to be used for some initial verification of the process Simulation HYSYS Constructor Support for an unit during the initial phase of the production start of the Modelling Study FPSO plant. Up to fifteen different upset production scenarios hasve been tested in this project Depresurization calculations using dynamic simulation to Depressurization for Aspen accurtely determine the Minimum Design Metal Temperature HIPPS or other 2020 Mozambique EPC Natural Gas Italian EPC a Domestic Gas Unit HYSYS (MDMT) in a small domestic gas unit that is dedicated to Depressurization in Mozambique produce a stream of treated gas to be sent to local distribution grid Aspen Two-phase Flare System Revalidation project where the Study and HYSYS; PSVs of a plant section, associated to several services will Modelization of the Flarenet/As 2020 Spain Operator Refining Flare Systems Spanish be revalidated by simulation results for different possible system to discharge Analysis Refinery pen Flare operating contingencies. In the second project phase, the to flare of a refinery Analyzer complete flare network will also be revalidated with the new section loads calculated during the PSV revalidation phase All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 8
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Client was interested in developing a methodology to operate the liquid side of the 1st stage separator (having a Dynamic Process Control Aspen 2020 France Operator Oil & Gas slug catcher functionality) and improving the process control Simulation Study French E&P Dynamic Simulation HYSYS philosophy and the PID parameters of the 1st stage for Process Company Study for 1st Stage separator. Such a controlability study was carried out with Control Analysis Separator the help of a dynamic simulation model of the system and the subsequent analysis Collection of nine Generic OTSs for upstream units intended Generic OTSs for up UniSim Educational to train the students of an Iraq educational institution in the Oil & Gas 2020 Iraq Oil & Gas Operator Training to nine units in an operation of an Oil Gas Separation Unit, a Gas Compression Training Design Institution System (OTS) upstream Unit, a Gas Sweetening with Amines unit, a Dehydration Unit Institution in Iraq processing plant with glycol, an NGL Unit, an LNG Unit, an LPG Unit, an Energy Unit and a Treatment Unit Update of an OTS developed by Inprocess to the new Update of the Aspen 2020 Bolivia Operator Oil & Gas version of the DCS (Emerson DeltaV). Additionally, the Operator Training Spanish E&P existing OTS HYSYS dynmiac model was also updated with the inclusion of a new System (OTS) Company simulation model booster compressor, a new gas turbine and the associated with new equipment filters Planning for a platform production capacity increase, a flow assurance (steady state and transient) was required by the Flow Assurance operating company in order to ensure current equipment Multinational Analysis for an OLGA 2020 Saudi Arabia EPC Oil & Gas was capable to cope with the increase. After receiving a Flow Assurance EPC for a increase in existing pipelines simulation models in SPS and OLGA, Analysis Middle East production in a Inprocess did update them with newer information. With the NOC Middle East field updated models, Inprocess executed different simulation scenarios (SPS for Steady State, OLGA for Transient) in order to obtain results to confirm the project objectives. Inprocess was requested to develop a dynamic simulation model of a depropanizer column, part of a PDH plant, in Spanish branch Dynamic Simulation Dynamic Aspen order to help to solve client's current issues with the of a Study for the 2020 Spain Operator Petrochem Simulation Study multivariable process controller in operation and to support multinational controllability and HYSYS for Process client's plan to increase production the following year. Once chemical debottlenecking of a Control Analysis the rigorous model will be ready, it will also be used to infer company Depropanizer Unit the values of certain process variables that are difficult (if not, impossible) to measure in the real plant The project main objective is to build a dynamic simulation model for the rich and lean gas segregation pipelines in the Phase 2 of the UniSim country national gas grid. The results obtained for a series of Dynamic Omani EPC for Dynamic Simulation 2020 Oman EPC Natural Gas scenarios, carried out with the model will allow identifying Simulation a Middle East Study for the Design potential problems both, in steady state conditions, when Modelling Study Gas company debottlenecking of a blending composition changes (up to six cases), and in gas grid transient conditions when either some of the consumers trip or some of the suppliers also do. All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 9
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Dynamic Simulation Aspen Dynamic Simulation Study (DSS) for a BOG compression Dynamic Study for a series of 2020 Mozambique EPC Natural Gas system in order to analyse different operating scenarios and Simulation Italian EPC Boil-Off Gas HYSYS upset cases and considering all the piping, controls and Modelling Study Compressors in an equipment handling BOG in the abovementioned plant. African LNG plant Dynamic Simulation Study of an Ethylene Refrigeration Dynamic Dynamic Simulation Compressor, for only one initial condition, to evaluate if the Swiss Simulation Study Study for Ethylene Aspen Equipment acceleration phase during the start-up to identify driver Compressors 2020 Germany Petrochem for Compression Refrigeration HYSYS Manufacturer limitation or requirement based on the calculated load curve Manufacturer Systems Compressor (ERC) and if the compressor behaviour in the compressor map when the system accelerates Development of the Lifecycle Operator Training Simulator (LC-OTS) for Almirante Barroso (MV32) Floating Production Storage and Offloading (FPSO) platform, which will be installed in the Búzios field, offshore Brazil. The MV32’s LC- OTS will be installed in the same training centre in Rio Lifecycle Operator where Inprocess is already deploying LC-OTS for MV30 and Major FPSO Training Simulator MV31 FPSOs. Operator Training constructing and UniSim for Almirante 2020 Singapore EPC Oil & Gas System (OTS) operating Design Although the LC-OTS's main purpose is to train the control Barroso (MV32) company room operators on a direct-connect OTS, client will benefit FPSO from a wider-scope during the engineering work including: Flare system validation, operating procedures drafting, early operators and engineers training with an emulated OTS, virtual commissioning of the ICSS configuration, start-up and post start-up support. Spanish Oil Flare system Aspen Revalidation study for the flare system of a butadiene plant, Flare Systems Major revalidation study HYSYS; comprising the resizing of a number of safety valves, 2020 Spain Operator Petrochem Analysis (petrochemicals for the butadiene Aspen Flare together with the revalidation of the flare network, by steady branch) plant Analyzer state simulation Slug and Pigging Flow Assurance Flow Assurance study for two pipelines and two different Portuguese EPC Analysis for a OLGA 2020 Portugal EPC Oil & Gas Analysis scenarios for each one Libyan O&G field Italian EPC for HIPPS Study for an HIPPS or other Aspen Dynamic Simulation Study for a HIPPS protection system in an FPSO FPSO in Angola 2020 Angola EPC Oil & Gas Depressurization HYSYS order to determine the setpoint of operation constructor coast Dynamic Dynamic Simulation Dynamic Simulation Study to determine the correct setup of Compressors Aspen Equipment Simulation Study for a 2020 USA Oil & Gas the turbo expander machinery, its process control and its Manufacturer HYSYS Manufacturer Modelling Study Turboexpander protection system All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 10
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Dynamic Process Norwegian EPC Simulation of a Dynamic hydraulic study for an oil export pipeline. The Flow Assurance for a Norwegian North Sea OLGA 2020 Norway Operator Oil & Gas possibility of wax deposition along the line was also Analysis Oil & Gas installation Oil investigated Company Export System Planning for a future Operator Training System to be Dynamic developed following the concept of Lifecycle Simulator, FPSO Dynamic Simulation Aspen Simulation 2020 Norway EPC Oil & Gas Inprocess' client requested to start separately the dynamic Constructor Model of a FPSO HYSYS Modelling Study simulation studies around the equipment to be installed in the processing facilities of an FPSO A cracker plant was having trouble when operating the Steady State propane/propylene splitter distillation column. Inprocess Austrian Modelling of a C3 Steady State oversaw building the steady state simulation model and Petrochemical splitter and de- Aspen Simulation 2019 Sweden Operator Petrochem running a Sensitivity Analysis in order to evaluate the options Company, ethanizer distillation HYSYS Modelling Study to limit propylene losses in the bottom stream and to analyse Swedish site columns in a cracker how MAPD can be limited to the maximum allowable plant concentration in the column with the current instrumentation. Dynamic Simulation The French compressor manufacturer providing the Dynamic French Study for the equipment to a Russian LNG plant required Inprocess to Simulation Study Aspen Equipment Compressor Overhead 2019 Russia Natural Gas determine by means of dynamic simulation the protection for Compression HYSYS Manufacturer Manufacturer Compressor in an requirements (anti-surge circuit, hot gas bypass valve Systems LNG train requirements, etc.) for the overhead compressor Dynamic Simulation The French compressor manufacturer providing the Dynamic French Study for the equipment to a Russian LNG plant required Inprocess to Simulation Study Aspen Equipment Compressor Regeneration 2019 Russia Natural Gas determine by means of dynamic simulation the protection for Compression HYSYS Manufacturer Manufacturer Compressor in an requirements (anti-surge circuit, hot gas bypass valve Systems LNG train requirements, etc.) for the regeneration compressor The client wanted to process an alternative feedstock (from bio sources) into their PDH and PP3 plants, and it was in need of testing the evolution of the concentration of this alternative Austrian Dynamic Simulation Dynamic feedstock at the exit of the polymerization plant, once the Petrochemical Model for a Propane Aspen Simulation 2019 Belgium Operator Petrochem feedstock tank at their logistic partner was connected to the Company, dehydrogenation HYSYS Modelling Study pipeline feeding the PDH plant. Therefore, a dynamic Belgian site plant simulation model of the plant was built, and it was used to determine the residence time of the new feedstock, after switching from the traditional one. All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 11
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Inprocess built the dynamic model of the flare network of a propane dehydrogenation plant for an Italian engineering company who was in charge od carrying out a safety gas Dynamic Flare evaluation in the plant Dynamic Italian EPC for Network Analysis for Final client was facing a problem with the Flare system for Simulation an Austrian safety gas which the reduction load applied was not properly supported Aspen Modelling Study; petrochemicals evaluation in a 2019 Belgium EPC Petrochem by a simulation, and the HIPS implementation is not enough HYSYS Flare Systems company Propane to close the safety gap coming from a LOPA analysis. Analysis (Belgian Site) dehydrogenation Inprocess carried out a flare simulation for the design (PDH) plant scenario (power failure) in order to check if the time- dependence of the overpressure phenomena can give additional credit to close the safety gap going to safe reduce the flare design. Flare Systems Multinational Inprocess carried out the revalidation of the Flare System of Analysis for a Flare Systems Chemical Aspen a propane dehydrogenation plant by means of process Propane 2019 Spain Operator Petrochem Analysis Company, HYSYS simulation, simulating contingencies and revalidating system dehydrogenation Spanish site dimensions plant FEED Flow Italian EPC for a Assurance Study for By means of transient simulation of the pipeline using OLGA, Flow Assurance Russian O&G an Oil Export OLGA 2019 Italy EPC Oil & Gas Inprocess carried out a FEED study for the oil export pipeline Analysis company Pipeline to a Tank from the processing facilities to the tank farm vessels Farm French Dynamic Compressor Dynamic simulation Inprocess built a dynamic simulation model of the three- Simulation Study Manufacturer for study for a three Aspen Equipment stages compression system to validate the sizing of the 2019 Indonesia Oil & Gas for Compression an Indonesian stages centrifugal HYSYS Manufacturer proposed anti-surge valves and the configuration of the Systems Oil&Gas compression system recycle loops company Dynamic Simulation Inprocess updated an existing dynamic simulation case in Dynamic Process for a high-pressure order to match Steady State conditions, according to H&MB, Aspen Simulation Licensor division gas circuit in a 2019 Italy EPC Refining in order to tune up controllers and instrumentation as well as HYSYS Modelling Study of an Italian EPC hydroconversion to check dynamics to verify that in three different scenarios, type unit no overpressure and overtemperature will occur All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 12
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type During the start-up of two units of a green refinery lots of operational problems were detected, actually leading to the impossibility of starting them. Inprocess created a dynamic DSS to study start- simulation model of the units and helped out the engineers Dynamic up procedures for Aspen there to find During the start-up of two units of a green refinery Simulation Italian EPC 2019 Italy EPC Refining two units in a green HYSYS lots of operational problems were detected, actually leading Modelling Study refinery to the impossibility of starting them. Inprocess created a dynamic simulation model of the units and helped out the engineers there to find and define the right procedure to smoothly start the refinery units Due to the construction of new processing facilities in Emirates EPC gathering centre of an oil & gas field, new desalter treating Dynamic Dynamic Simulation working for an Aspen trains need to be built. Inprocess did carry out the dynamic Simulation Study for Desalter 2019 Kuwait EPC Oil & Gas Middle East HYSYS simulation of such series of desalter trains in order to assess Modelling Study trains in new GCs NOC their dimensions, their desalting capacity, and their control and safety strategy for start-up and shutdown sequences A surge analysis of a 121 km long crude oil export pipeline, Surge Analysis Italian EPC for a between two tan farms, was carried out by Inprocess using Study for a Crude Flow Assurance Russian Oil OLGA with PVTSim in order to determine the adequate line Oil Export Pipeline OLGA 2019 Iraq EPC Oil & Gas Analysis Company in size (48"), the NPSHA for booster and shipper pumps, the between two tank Middle East cool down as well as testing other different operational and farms (121 km) emergency situations Client wanted an updated Aspen Flare Analyzer model of their Spanish site of a Flare Network Flarenet/As flare network (93 sources relieving). Inprocess built the model Flare Systems German Evaluation for the Bulk pen Flare 2019 Spain Operator and run the proposed scenarios (Power Failure, Cooling Analysis Chemicals whole producing site Chemicals Analyzer Water Failure, Instrument Air Failure and Fire) and suggested company (several plants) possible ways of overcoming the detected bottlenecks Inprocess’ refinery experts did analyse the status of the existing Hydrogen Network with the aim to investigate Feasibility Study for different alternatives to optimize hydrogen utilization at the Hydrogen Serbian Refining Hydrogen Network Aspen 2019 Serbia Operator Refining refinery. Afterwards, Inprocess, in collaboration with its EPC Network Study Company Modelling and HYSYS partner, did conduct the Technical and Economic Evaluation Optimization of the proposed alternatives as well as created the required technical documentation for the selected solution. All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 13
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type • Revalidation of the plant PSVs: Calculation of the discharge load from every service protecting the units, for Aspen every defined contingency and calculation of the sizing of Modelling and Study HYSYS; the services (only for those PSVs whose dimensions are of the Flare System Flare Systems Spanish Flarenet/As not known) of the Conversion 2019 Spain Operator Refining Analysis Refinery pen Flare • Flare network revalidation: Determination of the services Section of the Analyzer; affected by the common contingencies and development Refinery Flaresim of a flare network model, in order to determine its hydraulic behaviour and possible limitations. • Flare revalidation: Seal and Tip design and radiation study Development of a Minimum Metal Temperature Study for the Minimum Metal Gas-Lift Compressor System in an oil & gas field (offshore Temperature Study Abu Dhabi) using BLOWDOWN technology available in Spanish EPC HIPPS or other (FEED) for a Gas- Aspen Aspen HYSYS. This technology has been incorporated by working for and 2019 Abu Dhabi EPC Oil & Gas Depressurization Lift Compression HYSYS Aspentech in Aspen HYSYS keeping the code unchanged in Emirates' NOC System in an Abu order to maintain the accuracy of the original depressurization Dhabi offshore field technology developed by Dr. Graham Saville and Prof. Stephen Richardson Dynamic Simulation Dynamic Dynamic Simulation Studies, with different operational Study of the Gas Simulation Study FPSO Aspen scenarios, to calculate sizes of equipment and of safety Injection 2019 Ghana Operator Oil & Gas for Compression Constructor HYSYS devices for the Gas Injection compressor installed in a FPSO Compressor in an Systems in Africa FPSO in Ghana Dynamic study to confirm the design of the Anti-Surge Valve, Dynamic Simulation including the trim characteristic, and to evaluate the need of Dynamic Swiss Study for three hot gas bypass valve; to detect potential reverse rotation of Simulation Study Aspen Equipment Compressor compression 2019 Indonesia Oil & Gas the compressor; to perform the compressor system start-up, for Compression HYSYS Manufacturer Manufacturer systems in an oil & including interfaces with the process sequence identification Systems gas plant of required starting torque, starter driver sizing, and the required acceleration limitations German PSVs and Flare Engineering An Inprocess modelling expert remotely supported the EPC Flare Systems network revalidation UniSim Company for a 2019 Germany EPC Refining firm to carry out a PSVs and flare network revalidation study Analysis for a German Design German for a refinery in Germany refinery Refinery Dynamic Dynamic Simulation Studies, with different operational British DSS for the LLP and Simulation Study Aspen Equipment scenarios, to calculate sizes of equipment and of safety Compressor LP compressors in a 2019 Senegal Oil & Gas for Compression HYSYS Manufacturer devices for the LLP and LP compressors installed in a FPSO Manufacturer FPSO in Africa Systems in the west coast of Africa All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 14
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type The compressor manufacturer wanted Inprocess to build a Swiss Dynamic Dynamic simulation dynamic model and to run simulation scenarios to determine Compressor Simulation Study study for a booster Aspen Equipment if their compressor design was satisfying final client needs to Manufacturer for 2019 Uzbekistan Oil & Gas for Compression compressor station HYSYS Manufacturer boost the pressure of a declining field to keep desired an Uzbek oil & Systems (two stages) discharge pressure (by moving from one-stage to two-stages gas company compression system) An Operator Training System for the Ammonia, Urea and Methanol plants (plus the associated Utilities plant) has been built for a fertilizers company in Malaysia. The dynamic Operator Training process model has been built using UniSim Design, the Malaysian Operator Training System for an UniSim Bulk emulation of the Yokogawa DCS has been included in the Fertilizers 2019 Malaysia Operator System (OTS) Ammonia, Methanol Design Chemicals process model, the Advanced Process Control Module has Company and Urea Plant been connected to the process model and the emulated HMI has been developed with Inprocess Instructor Station that is also acting as the communication hub for the whole of the system Dynamic Dynamic study to Simulation Study FPSO select adequate Aspen Dynamic Simulation studies carried out for different 2019 Ghana EPC Oil & Gas for Compression Constructor compressors in an HYSYS compressor alternatives in order to select the best suited one Systems FPSO EPC (Italian Dynamic analysis of Dynamic Inprocess carried several operation scenarios to determine office) working a steam network in Aspen Simulation 2019 Bahrain EPC Refining the operability of the steam network of the utilities section of for a Middle East a desalination plant HYSYS Modelling Study a desalination plant in Middle East NOC during shutdown A dynamic model of one section of the sulphur oxide gas treatment plant has been built in Aspen HYSYS dynamics to Dynamic Dynamic Model and Spanish help client engineers to improve current process control Simulation Study Technology Transfer Aspen Metallurgical 2019 Spain Operator Metallurgy setup. The model development activity will be supported by a for Process for a Sulphur Oxide HYSYS Company series of knowledge transfer sessions that will guide control Control Analysis Plant engineers on how to benefit from the dynamic simulation results to improve plant controllability Steady State Model An existing Steady State model in Aspen HYSYS will be Steady State Canadian Improvement and Aspen Process Bulk reviewed and enhanced in terms of convergence time and Simulation Process Exergy Analysis of a 2019 Canada HYSYS Licensor Chemicals redundant information. Once validated, the model will be used Modelling Study Licensor Compressed Air to identify potential energy improvements by exergy analysis Storage System Depressurization Dynamic FPSO and re- Dynamic Study to determine the operating procedure for the Aspen Simulation Constructor in pressurization 2019 Ghana Operator Oil & Gas switch from automatic to manual in the gas export line from HYSYS Modelling Study Singapore dynamic study for a FPSO to the continent gas export sealine All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 15
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Aspen Revalidation of the After several successful previous projects, the refinery owner HYSYS; Flare Systems Spanish PSVs protecting the has requested Inprocess to carry out another project to Flarenet/As 2019 Spain Operator Refining Analysis Refinery coker, the HGO and revalidate the sizing of the Pressure Safety Valves protecting pen Flare the CLE & LVN some other units in the refinery (Coker, HGO, CLE & LVN) Analyzer Swiss Compressors The main objective of the project was to deliver a dynamic DSS for a Dynamic Manufacturer simulation study for a compression system to confirm the compressor train Simulation Study (German Aspen Equipment viability of eliminating VDS, though the verification of the changing from VSD 2019 Germany Refining for Compression branch) for an HYSYS Manufacturer operation under a number of defined procedural and upset drive/control to fixed Systems Oil Major conditions. The model will allow evaluating the design and speed drive operating in identifying potential problems. Qatar Inprocess has developed a dynamic simulation model of the three compression systems designed to work in a FPSO German Dynamic Simulation Dynamic offshore Brazil with the objective of determining the anti-surge Compressor Study for three Simulation Study Aspen Equipment requirements for the three systems; to evaluate the Manufacturer for Different 2019 Brazil Oil & Gas for Compression HYSYS Manufacturer compressor start-up procedures and the driver ability to an FPSO Compressor Trains Systems provide sufficient torque at the settle out pressure with/without constructor Systems in a FPSO soft starter; and to evaluate an emergency shutdown or trip event. Inprocess has developed a dynamic simulation model of the Spanish Dynamic Simulation Dynamic chilling water network in Aspen HYSYS in order to help client Synthetic Study for the rubber Aspen Simulation 2019 Spain Operator Petrochem to determine hydraulic bottlenecks in its chilling water network Rubber plant chilling water HYSYS Modelling Study and to help client to find solutions that could lead to its Producer network removal The main objective of the project is to deliver a dynamic Dynamic Simulation Dynamic simulation study for the Feed Gas Booster compression German Study for Feed Gas Simulation Study Aspen Equipment system and for the Boil-Off Gas compression system in order Compressors Booster Compressor 2019 Germany Natural Gas for Compression HYSYS Manufacturer to confirm its proper operation under several defined Manufacturer and Boil Off Gas Systems procedural and upset conditions. The model will allow Compressor evaluating the design and identifying potential problems. Operator Training Simulator for a Gas Utilization Plant that will Operator Training use Siemens PCS7 as distributed control system. Inprocess Middle East Operator Training Simulator for a gas Aspen has developed a direct-connect OTS, with a dynamic model Control Systems 2019 Iraq EPC Natural Gas System (OTS) plant in Basrah HYSYS of the process based on Aspen HYSYS, the emulation of the Implementor (Iraq) Siemens DCS based on PCS7Sim and SIMIT, and an instructor station developed with Inprocess Instructor Station All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 16
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Within the innovation process on going, client is evaluating the use of Aspen Plus to perform integrated process simulation models for High-Octanes Technologies, more specifically MTBE, ETBE and TAME synthesis and related side reactions. Process Client is currently simulating the whole process (reaction, Steady State Licensor division On-site Support for product separation and reactant recovery) using different Simulation of an Italian Aspen Plus MTBE Aspen Plus 2019 Italy EPC Petrochem tools with an important effort related to the integration of the Modelling Study engineering Reactor Modelling results from one tool to the other until a stable convergence is company reached. The reason of this is linked to the reliability of each tool results that were confirmed over the years with data coming from several operating plants all over the world. Client requested Inprocess its support to implement the whole of the existing models and routines into a single process simulation tool, like Aspen Plus. Inprocess and client will jointly devote R&D resources to Research, Development of a Norwegian Oil develop a software tool capable of detecting process Development and Bad Actors Aspen and Gas 2019 Norway Operator Oil & Gas anomalies due to the deviation between the real equipment Innovation Detection HYSYS company behaviour and that expected from a rigorous first-principles (R+D+I) Application dynamic process simulator Inprocess updated and upgraded an existing simulation system for the complexes of Fluidized Catalytic Cracking Upgrading of an (FCC) and Mild Hydrocracker (MCC) to the new process existing Operator Operator Training Greek Refining UniSim simulator (UniSim Design), matching current plant conditions. Training Simulator 2019 Greece Operator Refining System (OTS) Company Design On top of the new model, Inprocess created an Operator for an MHC refinery Training Simulator, simulating the Honeywell control system unit and the safety system with Proconex software and developing the instructor capabilities with Inprocess Instructor Station Operator Training Inprocess developed an OTS for an old topping complex in Simulator of a the refinery, developing the process model with UniSim Operator Training Greek Refining UniSim continuous catalytic 2019 Greece Operator Refining Design, simulating the Honeywell control system and the System (OTS) Company Design reforming refinery safety system with Proconex software and developing the unit instructor capabilities with Inprocess Instructor Station Inprocess developed an OTS for continuous catalytic Operator Training reforming unit in the refinery, developing the process model Operator Training Greek Refining UniSim Simulator of a 2019 Greece Operator Refining with UniSim Design, simulating the Honeywell control system System (OTS) Company Design topping refinery unit and the safety system with Proconex software and developing the instructor capabilities with Inprocess Instructor Station All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 17
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type A major FPSO constructing and operating company has awarded Inprocess the construction of an Operator Training Simulator for their new Carioca (MV30) Floating Production Storage and Offloading (FPSO) platform, which is soon to be installed off the coast of Brazil (in the Sepia field). These fields produce a natural gas with a high CO2 content, thus a careful Major FPSO Lifecycle project and design of the processing facilities in the FPSO is required as Operator Training constructing and OTS for one FPSOs UniSim well as precise operating procedures in order to be able to 2019 Brazil Operator Oil & Gas System (OTS) operating to be located Design adequately process the fluids produced. The OTS being built company offshore Brazil to train the control room operators are, however, part of a wider-scope simulation lifecycle project which will include dynamic simulation studies to be executed before the actual construction of the topsides, as well as validation of the proposed operating procedures, checkout of the ICSS databases, operator training, start-up support and post start- up updates. A major FPSO constructing and operating company has awarded Inprocess the construction of an Operator Training Simulator for their new Guanaraba (MV31) Floating Production Storage and Offloading (FPSO) platform, which is soon to be installed off the coast of Brazil (in the Libra field). These fields produce a natural gas with a high CO2 content, Major FPSO Lifecycle project and thus a careful design of the processing facilities in the FPSO Operator Training constructing and OTSs for one FPSO UniSim is required as well as precise operating procedures in order 2019 Brazil Operator Oil & Gas System (OTS) operating to be located Design to be able to adequately process the fluids produced. The company offshore Brazil OTS being built to train the control room operators are, however, part of a wider-scope simulation lifecycle project which will include dynamic simulation studies to be executed before the actual construction of the topsides, as well as validation of the proposed operating procedures, checkout of the ICSS databases, operator training, start-up support and post start-up updates. Slovak EPC for Dynamic Simulation Dynamic EPC dynamic simulation studies to verify basic engineering a Slovak Study for Ethylene Aspen Simulation 2019 Slovakia EPC Petrochem calculations for the facilities of the storing complex of an petrochemicals Storing Facility HYSYS Modelling Study ethylene production plant company Subcooling Section Inprocess will take advantage of existing models in Aspen OTS for a Dynamics to build an OTS based on Aspen HYSYS Dynamics Operator Training German Resins Hydrogenated Aspen Bulk to train control room operators on the behaviour of the plant 2019 Germany Operator System (OTS) Company Hydrocarbon Resin HYSYS Chemicals that is controlled by a PCS7 Simatic from Siemens. Inprocess plant Instructor Station will be the software acting as data hub and providing the Instructor functionalities All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 18
Inprocess Technology & Consulting Group, S.L. Pedro i Pons 9-11 · E-08034 BARCELONA · www.inprocessgroup.com Inprocess References List: 2008-2021 Process Company Project Type Customer Project Title Year Country Industry Short Description Simulator Type Software Steady State model Inprocess will build new steady state standalone models for Extension and Norwegian expansion and two new fields to be integrated with an existing CORF model. Programming; Exploration & Aspen software extension 2019 Norway Operator Oil & Gas Models will be fed with real plant data from PI system. Steady State Production HYSYS upgrade for a North Software extensions will be upgraded to cope with the new Simulation Company Sea field feeds Modelling Study The purpose of this hydraulic analysis was to establish the line size requirements for the new transfer lines from PADs Spanish EPC for Flow Assurance and Main Transfer line forming a Fish Bone Network for the Flow Assurance an Emirates oil Study for an oil field OLGA 2019 Abu Dhabi EPC Oil & Gas Oil Gathering Network. The analysis also evaluated and Analysis company in Middle East identified the various problems that could be faced during start-up, shutdown, pigging operations of the gathering network facility A petrochemical complex in a coastal town in the Province of Cádiz (Spain) has awarded Inprocess a project to develop and implement an OTS and an ITS (3D VR) for its Linear Alkylbenzene (LAB) plant. The plant is currently updating its facilities – in a new upgrade project, valued at $110 million - to take advantage of the most modern, efficient DETAL technology now available. Petrochemical OTS and ITS for a By using Aspen HYSYS Dynamics for the simulation of both Operator Training Aspen Spanish greenfield DETAL 2019 Spain Operator Petrochem the processing plant and its process control, the Inprocess- System (OTS) HYSYS Company plant emulated OTS solution will also evolve to incorporate 3D Virtual Reality vision to simultaneously train control panel operators and field operators. As a side project benefit, Inprocess will invest in the development of the Digital Twin, the future basis for the OTS and ITS (3D VR), by creating an inferential variables generation tool to be used in Process Optimization applications. Steady State Aspen + Conceptual Client requested Inprocess technical support to help them to Bulk Simulation German EPC Design of Distillation Aspen Plus 2019 Germany EPC build a model in Aspen Plus that should help them to select Chemicals Modelling Study Sequence the best distillation sequence configuration Development of an Operator Training system for one FPSO Operator Training Brazil office of a located offshore Brazil. The dynamic model will be developed Operator Training System for one UniSim Dutch FPSO 2019 Brazil Operator Oil & Gas taking advantage of a previously built dynamic model for EPC System (OTS) FPSO located Design constructor studies. The control and safety system (from Siemens) will be offshore Brazil simulated with Siemens softcontroller based on SIMIT All information contained herein is confidential and may not be disclosed to a third party without the prior written consent of Inprocess Technology and Consulting Group, S.L. 23 June 2021 Inprocess Reference List 2008 - 2021 Page 19
You can also read