REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Executive Summary
This semi‐annual Report on Project Management Oversight details Service Board efforts in
implementing their capital programs. Included are details on all state‐funded projects, regardless of
budget, and all systemwide projects with budgets of $10 million or more, regardless of funding
source. Information in this report was collected by direct interviews, project meetings, and
documented submissions from Service Board project management teams.

The RTA’s 2018‐2023 Regional Transit Strategic Plan, Invest in Transit, highlights $30 billion of
projects that are needed to maintain and modernize the region’s transit network. To maintain and
preserve the current system in a State of Good Repair (SGR), as well as address the backlog of
deferred SGR projects, requires a capital investment of $2 to $3 billion per year.

The Rebuild Illinois funding is planned to expedite overdue repair and replacement projects, reduce
the backlog of deferred improvements, and move the system toward a state of good repair. It
nearly doubles the previous five‐year regional capital program of $4.3 billion. The funds enable real
progress on the state of good repair, by allowing improvements and in some cases replace aging
system assets.

Although this has been a difficult year due to operating funding shortfalls related to COVID‐19, the
Service Boards are continuing with the implementation of their capital programs. This report
includes, for the first time, 13 Rebuild Illinois projects representing $655 million in Rebuild Illinois
funding. The 13 projects reported on have begun during this reporting period and have ongoing
activities. Many of these projects have milestone payment contracts so the expenditures are low as
milestones are in the process of being met. There are also many other Rebuild Illinois projects that
are under procurement and will be included in the next report.

The 52 projects detailed in this report together represent $5.7 billion worth of construction,
maintenance, and procurement. Many of these projects address outstanding capital needs, while
others are directed toward compliance with federal requirements or enhancing customer
experience, safety, and security.

All of the state funded projects are within budget. Three state funded projects were completed
during this reporting period. There was one change order executed during the current reporting
period. All executed change orders were for ongoing projects, mostly to add value and address
unforeseen conditions. Construction activities continued during the current COVID‐19 crisis by
following CDC recommendations at the job sites with no significant delays to the construction
projects.

RTA recognizes the commitment, collaboration, cooperation, and level of effort each Service Board
provided for this report. RTA is appreciative and pleased to note the exemplary and ongoing
commitment of transit agency personnel during this process. RTA will continue to work with the
CTA, Metra, and Pace to advocate for more capital funding at both the state and federal level to
ensure our transit system continues to prioritize and work towards a State of Good Repair.
Project Management Oversight - December 2020 - Regional Transportation ...
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Table of Contents
   Section I – State‐Funded Projects .........................................................................1
          Project List ................................................................................................2
          CTA ............................................................................................................3
          Metra .......................................................................................................6
          Pace .........................................................................................................18
          Budget Performance ...............................................................................27
          Schedule Performance ............................................................................28
          Change Orders ........................................................................................29

   Section II – Systemwide Projects over $10,000,000 ...........................................31
          Systemwide ............................................................................................32
          CTA ..........................................................................................................36
          Metra ......................................................................................................43
          Pace .........................................................................................................58

   Conclusion ...........................................................................................................66
Project Management Oversight - December 2020 - Regional Transportation ...
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Section I
State-Funded Projects

                                                                  1
Project Management Oversight - December 2020 - Regional Transportation ...
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Systemwide

STATE-FUNDED PROJECTS

SERVICE BOARD     PROJECT TITLE                                                             BUDGET
CTA               *5000-Series Rail Car Rehabilitation                                       $221,537,449
CTA               98th Street Rail Shop Bridge Replacement                                     $5,222,791
CTA               *Non-Revenue Vehicles – Diesel Locomotives                                     $473,165
Metra             *Union Pacific North Line Bridges (South 11 Bridges)                       $156,100,000
Metra             *Locomotive Purchase                                                       $138,916,300
Metra             Positive Train Control (PTC)                                                $85,000,000
Metra             Rehabilitation of Rolling Stock                                             $57,005,321
Metra             Union Pacific West Line Expansion                                           $44,500,000
Metra             Auburn Park New Station                                                     $20,000,000
Metra             Union Pacific North Line Bridges and Ravenswood Station                     $12,668,903
Metra             *Central Warehousing                                                        $10,000,000
Metra             *5 Station Design – Electric Line                                            $4,263,987
Metra             *Smart Gates                                                                 $1,500,000
Pace              Purchase 40' Compressed Natural Gas Buses                                   $49,000,000
Pace              *New I-55 Garage – Plainfield                                               $43,752,500
Pace              *New Northwest Division Garage – Wheeling                                   $43,135,380
Pace              Pace South Campus Project – Markham                                         $27,100,000
Pace              *River Division Expansion and Improvements                                  $21,260,000
Pace              *Bus Stop Improvements – Joliet Gateway Center                               $9,509,500
Pace              Purchase 15-Passenger Paratransit Buses                                      $7,290,500
Pace              *ADA Technology Upgrades and Transfer Centers                                $4,000,000
Pace              *Orland Square Mall Bus Stop Improvements                                      $640,000

Note #1: Amounts shown represent only the state-funded portions of overall project budgets.
Note #2: Projects listed in bold and with an asterisk are new projects from the Rebuild Illinois program.

                                                                                                            2
Project Management Oversight - December 2020 - Regional Transportation ...
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     5000‐Series Rail Car Rehabilitation
     Description:
          This project will provide for the quarter‐life
          overhaul of the 5000‐Series rail cars, which is
          an overhaul effort designed to be performed
          on each rail car at approximately six to seven
          year intervals. Schedule maintenance will
          include major component rebuilds and
          needed repairs to the car bodies. Additional
          work may include: replacing control groups,
          air conditioning units, truck assemblies,
          including traction motors, cables, batteries,
          brake calipers, axle assemblies, interior seat
          modifications and other critical components
          based on condition assessment.
     Status:
          The Phase 1 non‐critical work was for project administration and NTP was given in August 2020.
          CTA continued to perform training for items that are part of the Phase 2 Overhaul. The Phase 2
          work was awarded in October 2020 and continues to make headway. The first delivery of material
          is scheduled for June 2021.
     Budget:
          The project is on budget.
                                                      Budget      Obligated*       Expended*          Expended %
              Rebuild Illinois Budget             $221,537,449      $73,810,250                 $0         0%
              Overall Project Budget              $400,000,000     $140,555,121        $23,136,404         6%

     Schedule:
          The project is on schedule.
                                     Milestone                     Baseline Schedule      Actual (A) / Forecast
                         Phase 1 Notice‐to‐Proceed                   August 2020            August 2020 (A)
                         Phase 2 Notice‐to‐Proceed                   October 2020          October 2020 (A)
                         Substantial Completion                       June 2023                June 2023
     Highlights:
          This overhaul will improve the comfort, quality, and service reliability of the rail cars while reducing
          operating maintenance costs. Unscheduled maintenance will be significantly reduced as more rail
          cars are cycled through the overhaul program.

*Obligated and Expended amounts as of October 2020.

                                                                                                                   3
Project Management Oversight - December 2020 - Regional Transportation ...
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     98th Street Rail Shop Bridge Replacement
     Description:
          The purpose of this project is to repair damage due to a water
          infiltration condition at the penthouse level employee entrance
          and receiving room at the 98th Street Rail Shop. The rail shop is
          approximately 49,000 square feet and was built in 1969 with an
          expansion in 1993. CTA rail cars are maintained and repaired at
          this facility, and it is part of the 98th Street Yard, one of the
          largest yards in the CTA System. This project is intended to bring
          elements of the rail shop facility to a state of good repair.
     Status:
          Design for this project is completed. Construction work on the
          Rail shop bridge deck is ongoing. Phase 1 and 2 of construction
          (the lower levels of repair) have been completed. The contractor
          is currently restoring the penthouse level of this rail shop.
     Budget:
          The project is on budget.
                                                      Budget       Obligated*      Expended*       Expended %
             State-Funded Budget                      $5,222,791     $4,437,065      $1,308,354       25%
     Schedule:
          The project is behind schedule due to delays with procurement of materials.
                                     Milestone                     Baseline Schedule   Actual (A) / Forecast
                         Notice to Proceed                           January 2020        January 2020 (A)
                         Substantial Completion                     November 2020         December 2020

     Highlights:
          The 98th Street bridge is approximately 60 feet long and connects the State Street expressway
          overpass to the upper level of the rail shop employee entrance. The connecting bridge has
          suffered extensive damage through the years and is in need of replacement. The bridge concrete
          deck is not adequately sloped which causes rain water to enter the shop building. This project will
          provide a new access bridge and canopy, new concrete deck, window replacement, plumbing and
          masonry work.

*Obligated and Expended amounts as of October 2020.

                                                                                                                4
Project Management Oversight - December 2020 - Regional Transportation ...
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     Non-Revenue Vehicles – Diesel Locomotives
     Description:
          This project will provide for the replacement of
          CTA’s diesel locomotive snow fighters. The self-
          propelled      locomotives       with     special
          attachments to remove snow and ice during
          severe winter weather conditions are able to
          operate and clear system track, so that CTA can
          safely power up the system to restore/provide
          sevice. When traction power is down, this
          equipment will also be used to move rolling
          stock to secure locations.
     Status:
          CTA gave the manufacturer the Notice-to-Proceed in August 2020. The first vehicle is expected to
          be delivered in Q3 of 2022.
     Budget:
          The project is on budget.
                                                      Budget          Obligated*        Expended*       Expended %
              Rebuild Illinois Budget                   $473,165             $14,999             $0          0%
              Overall Project Budget                  $22,731,013           $478,180        $26,237         0.1%

     Schedule:
          The project is on schedule.
                                Milestone                           Baseline Schedule       Actual (A) / Forecast
                    Notice-to-Proceed                                 August 2020             August 2020 (A)
                    Substantial Completion                           November 2022            November 2022
     Highlights:
          The locomotives have been in service from 1981 and 1986 and have exceeded their life
          expectancies. CTA’s Operation Management identified the condition of this equipment as poor and
          of the highest priority for replacement.

*Obligated and Expended amounts as of October 2020.

                                                                                                                     5
Project Management Oversight - December 2020 - Regional Transportation ...
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Union Pacific North Line Bridges Phase 2 (11 South)
    Description:
         This project involves the replacement of 11
         bridges on the Union Pacific (UP) North Line
         from Cornelia Avenue southward to Fullerton
         Avenue, and the rehabilitation of the Addison
         Street bridge. The structural scope of work will
         include the replacement of existing stone
         abutments, replacement of steel spans, new
         ballasted bridge decks, and retaining wall
         construction and embankment landscaping.
         Also, some track work will be accomplished
         between the bridges, including the replacement
         of wood ties with concrete ties to ensure
         reliable train operations.
    Status:
         A contract for design was advertised for bid and awarded. A Notice to Proceed with the design has
         been issued by Metra in June 2020. Site surveys and inspections have been completed. Design
         activities are ongoing and the design documents are progressing towards the 30% design milestone.
         Professional Services contract for NEPA activities is being prepared to go out to bid.
    Budget:
         The project is on budget.

                                                        Budget        Obligated*     Expended*         Expended %
            Rebuild Illinois Budget                    $156,100,000     $6,055,830               $0              0%
            Overall Project Budget                     $162,100,000     $6,055,830               $0              0%
    Schedule:
         The project is on schedule.
                               Milestone                      Baseline Schedule      Actual (A) /Forecast
                    Design Notice to Proceed                      June 2020             June 2020 (A)
                    Design Completion                          September 2022         September 2022
                    Project Substantial Completion             December 2024           December 2024

    Highlights:
         These bridges are over 100 years old. They are showing signs of increased deterioration and
         have exceeded their useful life. These bridges cannot be repaired economically and must be
         replaced to provide uninterrupted commuter service.

*Obligated and Expended amounts as of November 2020.

                                                                                                                6
Project Management Oversight - December 2020 - Regional Transportation ...
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Locomotive Purchase
    Description:
         This project involves the purchase of up to
         forty‐two (42) remanufactured diesel
         locomotives which will allow for increased
         horsepower, lower emissions, and greater fuel
         efficiency than the current fleet average.

    Status:
         As part of this project, Metra has previously purchased 21 F‐59H1 Locomotives. All 21 Locomotives
         have been received and accepted. A new requisition was processed for additional new or
         remanufactured diesel locomotives. The bids have been received and a contractor has been selected
         for the purchase of a base order of 15 remanufactured diesel locomotives. The Rebuild Illinois
         funding is allocated for this purchase. The cores for the first 10 locomotives are currently being built.
         The first locomotive is expected to be delivered in January 2022.
    Budget:
         The project is on budget.
                                                         Budget           Obligated*       Expended*        Expended %
                    Rebuild Illinois Budget             $138,916,300      $137,150,000               $0               0%
                    Overall Project Budget              $186,576,796      $164,307,500      $27,157,500              15%

    Schedule:
         Project is on schedule.
                                    Milestone                          Baseline Schedule    Actual (A) / Forecast
                       Notice to Proceed (15 Locomotives)                 April 2020           April 2020 (A)
                       15 Locomotive Order Completion                   December 2022         December 2022

    Highlights:
         The current Metra locomotive fleet is reaching the end of its useful life, or has exceeded its useful
         life, and needs replacement. Purchase of additional locomotives will increase Metra's spare ratio,
         which will improve service reliability. Newer locomotives may reduce maintenance costs.

*Obligated and Expended amounts as of November 2020.

                                                                                                                     7
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     Positive Train Control (PTC) – System Integrator
     Description:
          The Positive Train Control (PTC) system is comprised of
          wayside, onboard, and central equipment, including
          signals, GPS, computer hardware and software, and
          various other communications components. The system
          integrator functions to combine these components
          through design, testing, and implementation.
     Status:
           System integrator planning and work activities support PTC implementation. Various testing is on‐
           going and interagency project status reports are being submitted. Training continues and recently
           included the development of instructional videos to supplement the CAD (Computer‐Aided
           Dispatching) training for dispatchers. Work continues on the deployment and testing of the Clear
           Path operating interface to other rail partners in the Chicago area. System Integrator is providing
           maintenance services for Metra’s configuration management system to collect, monitor, and
           resolve anomalies, changes, and defects.
           The overall project is on track for the federal PTC system certification by the end of the year. All
           required Metra lines are running in Revenue Service Demonstration and testing has been
           completed with all tenant operators. NICTD will start running on PTC in early December and all
           other tenants are running PTC operations. Metra anticipates that the PTC Safety Plan submitted
           to the FRA will be approved shortly.
     Budget:
           The project is on budget. The state‐funded budget amount is dedicated to the System Integrator.
           The overall project total includes additional federal and local funding.
                                                          Budget         Obligated*       Expended*        Expended %
                       State‐Funded Budget                $85,000,000     $85,000,000       $81,895,267       96%
                        Overall Project Total            $415,879,609    $376,958,032      $320,899,382       77%

     Schedule:
          The project is on schedule.
                                    Milestone                    Baseline Schedule      Actual (A) /Forecast
                          Contract Award                           August 2015            August 2015 (A)
                          Begin Implementation                     August 2015            August 2015 (A)
                          Subdivision Service Initiated                 ‐‐‐              October 2018 (A)
                          Substantial Completion                  December 2020           December 2020

          Metra is responsible for PTC implementation on the five corridors on which it owns/leases. Activities
          include on‐board vehicle, wayside, communications and Back Office Segment (BOS) hardware and
          software design, construction/installation, testing, Revenue Service Demonstration (RSD) and
          implementation of the PTC system in compliance with regulatory requirements.
*Obligated and Expended amounts as of September 2020.

                                                                                                                    8
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     Positive Train Control (PTC) – System Integrator (continued)
          Metra operates as a tenant on three lines on which PTC will be implemented by the other host
          railroads. Activities include on‐board vehicle hardware and software installations, testing, RSD, and
          interoperability with the host railroad PTC system in compliance with regulatory requirements.

          Finally, Union Pacific Railroad (UP) hosts Metra rail operations on three corridors. PTC
          implementation is the responsibility of the UP, in which UP will host Metra’s BOS for PTC operations.
                                                                                             Party Responsible to
                                     Line Name                            Owner
                                                                                             Lead PTC Installation
                     BNSF Railway (BNSF)                                   BNSF                     BNSF
                     Heritage Corridor (HC)                          Canadian National        Canadian National
                     Milwaukee District North (MD‐N)                       Metra                    Metra
                     Milwaukee District West (MD‐W)                        Metra                    Metra
                     Metra Electric District (MED)                         Metra                    Metra
                     North Central Service (NCS)                     Canadian National        Canadian National
                     Rock Island District (RID)                            Metra                    Metra
                     SouthWest Service (SWS)                     Norfolk Southern / Metra*          Metra
                     Union Pacific North (UP‐N)                        Union Pacific             Union Pacific
                     Union Pacific Northwest (UP‐NW)                   Union Pacific             Union Pacific
                     Union Pacific West (UP‐W)                         Union Pacific             Union Pacific
                    *Some segments of the SouthWest Service line are owned by Metra and others by Norfolk Southern

          The table below shows the progress on the Revenue Service Demonstration for the five corridors
          that Metra owns/leases and is responsible for PTC implementation.

                                                                               Revenue Service
                                                        Line Name            Demonstration Date
                                                                             Actual (A) / Forecast:
                                         Milwaukee District North (MD‐N)         June 2020 (A)
                                         Milwaukee District West (MD‐W)          June 2020 (A)
                                         Metra Electric District (MED)         January 2020 (A)
                                         Rock Island District (RID)            October 2018 (A)
                                         SouthWest Service (SWS)                 May 2019 (A)

     Highlights:
           There are 4 core elements of the PTC system:
               Prevent train‐to‐train collisions.
               Stop over speed derailments.
               Inhibit movement of a train through a switch left in the “wrong” position.
               Block unauthorized incursion into roadway work zones.

*Obligated and Expended amounts as of September 2020.

                                                                                                                     9
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     Rehabilitation of Rolling Stock (Final)
     Description:
          Metra is rehabilitating locomotives and bi-level commuter
          rail cars. The locomotives are being rebuilt with overhaul of
          the diesel engine, traction alternator, head end power
          alternator and gear box, replacement of the control system,
          coupler and draft gears, revamping of the trucks, installation
          of secondary engine room door and painting. The rail cars
          are being renovated with replacement of couplers, yokes,
          draft gears, weather stripping, seats, floors, walls, window
          and door mechanisms, application of tube style diaphragms,
          renewal of the 480-volt and control train lines and repair of
          heating and lighting systems.
     Status:
          Locomotive and rail car units are being rebuilt as part of an ongoing rolling stock rehabilitation
          program. The 42 F40PH-2 locomotives, 99 Nippon Sharyo rail cars, 27 of the MP36 locomotives, 20
          Budd rail cars, and 57 of the BNSF Budd rail cars identified for this project have completed the
          rehabilitation program.
     Budget:
          The project completed on budget with all funds expended. Metra has reprogrammed some unused
          funds from other state grants and they were added to this project.
                                                       Budget        Obligated*       Expended*         Expended %
                               Locomotives             $29,891,267    $29,891,267       $29,891,267        100%
                                   Rail Cars           $27,114,054    $27,114,054       $27,114,054        100%
                       Overall Project Total           $57,005,321    $57,005,321       $57,005,321        100%

     Schedule:
          The project was completed on schedule. Progress was being measured with production rates.
                             Vehicle                        Baseline Production     Actual Production
                             F40PH-2 Locomotive                  30 Weeks              26-30 Weeks
                             MP36 Locomotive                     103 Days           Program Complete
                             Nippon Sharyo Rail                   28 Days                28 Days
                             Budd Rail Car                       100 Days           Program Complete
                             BNSF Budd Car                        15 Days           Program Complete
     Highlights:
          This project will lower maintenance costs. For locomotive rehabs, fuel costs will, also, be lowered
          and air pollution and the regional economy health will be improved. For rail car rehabs, the
          reliability and quality of service for commuters will be improved.

*Obligated and Expended amounts as of October 2020.

                                                                                                                 10
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     Union Pacific West Line Expansion
     Description:
           This project is part of a public-private partnership
           between Metra and the Union Pacific Railroad
           (UPRR) to construct a new third main line track.
           The segments funded under this project are
           located between mileposts 10.0 and 11.8 in
           Maywood and Melrose Park (eastern section) and
           between mileposts 32.1 and 38.4 in West Chicago
           and Geneva (western section).
     Status:
           Construction activities are mostly completed for the eastern section. Work was completed along the
           east abutment of the Des Plaines river bridge and fencing was installed. Melrose Park station
           construction activities are completed. The Maywood Station platform is completed along with
           lighting. The outstanding activities at Maywood Station include sidewalks and ramps leading to the
           station as well as landscaping. The construction portion of the western section of the project will go
           out for bid in Q1 of 2021 once Metra and UPRR finalize the agreement. The procurement efforts will
           be led by UPRR.
     Budget:
           The project is on budget. The state funding below provides for portions of the project design,
           environmental study, land acquisition, and construction. Metra and the Union Pacific Railroad are
           sharing these costs. The overall project total cost referenced below includes Union Pacific railroads
           expected cost for the project.
                                                             Budget                     Obligated*     Expended*       Expended %
              State-Funded Budget                            $44,500,000                 $15,102,256     $15,098,721            34%
              Metra Portion                                  $47,261,212                 $19,863,468     $17,788,724            38%
              Overall Project Total **                      $124,939,627
     Schedule:
           The project is on schedule. Milestones for the Western Section will be established once the project goes
           out for bid.
                                                                           Baseline
                                                      Milestone                           Actual (A) /Forecast
                                                                           Schedule
                                               Design Completion         March 2016         March 2016 (A)
                 Eastern Section Construction Notice to Proceed         November 2017 November 2017 (A)
                 Eastern Section Construction Substantial Completion December 2020          December 2020
     Highlights:
           The addition of a third main line track will eliminate key bottlenecks and allow Metra to add more
           service, including more express trains, on the line. The potential for freight interference will also be
           mitigated.

*Obligated and Expended amounts as of October 2020.
** Obligations and Expenditures are tracked for the Metra portion of the project cost

                                                                                                                               11
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Auburn Park New Station
    Description:
         This project is for the construction of a new
         station in the Auburn Park area on the Rock
         Island District in Chicago. The station will
         adhere to ADA standards and Metra’s station
         design guidelines. This new station will include
         an island 8-car asphalt platform, lighting,
         elevator access, sheltered passenger warming
         facilities, and a stair and elevator headhouse
         tower. Retaining wall improvements, visual
         information and station signage will also be
         constructed.
    Status:
         The contract to demo the bridge was awarded, Notice-to-Proceed was given in August 2020 and
         demolition is expected to be completed by the end of the year. Metra finalized the real estate
         acquisition of the building in November and demolition will continue to February 2021. The design
         for the new station is completed and the bridge lift design is 40% complete.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                     State-Funded Budget                 $20,000,000    $16,500,000        $192,151               1%
                    Overall Project Budget               $21,572,495    $18,072,495       $1,739,647              8%

    Schedule:
         Project is on schedule.
                                    Milestone                      Baseline Schedule   Actual (A) / Forecast
                        Design Award                                  April 2019          April 2019 (A)
                        Construction Award                            April 2021            April 2021
                        Substantial Completion                      December 2022        December 2022

    Highlights:
         A new station in the Auburn Park community will increase transit accessibility for the surrounding
         neighborhood. Benefits of this new station will also include a reduction in congestion on the Dan
         Ryan Expressway.

*Obligated and Expended amounts as of November 2020.

                                                                                                                12
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     Union Pacific North Line Bridges and Ravenswood Station

     Description:
          The project scope includes the construction of a
          new station for the inbound half of the
          Ravenswood Station and the replacement of 11
          bridges on the UP North Line.

          The station will have longer platforms that are
          covered, lighting, stairs, ramps, warming shelters,
          and landscaping. Work on the bridges replaces the
          existing stone abutments, retaining wall
          construction, steel spans, and decks.

     Status:
          Construction continues with the bridge project.
          The General Contractor completed the erection of
          the remaining superstructures and Union Pacific
          performed the track cutover. The contractor
          began demolishing all remaining structures and
          also working on phase 3 civil work.

          Now that the dependent bridge work was
          completed in this reporting period, the station
          contractor was able to continue work on this
          project. The station contractor is remobilized on
          site and continues to work on the new station
          buildout.
     Budget:
          The project is on budget.
                                                        Budget        Obligated*     Expended*       Expended %
                       State‐Funded Budget              $12,668,903    $12,668,903     $12,608,903           100%
                        Overall Project Total           $47,699,764    $46,410,483     $26,212,772            55%

*Obligated and Expended amounts as of October 2020.

                                                                                                             13
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

     Union Pacific North Line Bridges and Ravenswood Station (continued)

     Schedule:
          The bridge and station projects are behind schedule due to Union Pacific review time and approve
          the project drawings as well as issues obtaining permits for the project. The Ravenswood station
          schedule is also behind schedule due to extended time for UP to perform the track shift and delays
          on the bridge work.

                                    Milestone                     Baseline Schedule   Actual (A) / Forecast
                       Design Completion                            February 2013      December 2013 (A)
                       Notice of Award – Station                       July 2017          July 2017 (A)
                       Notice to Proceed – Station                   August 2017        August 2017 (A)
                       Substantial Completion – Station              January 2020         August 2021
                       Notice of Award – Bridges                   September 2017     September 2017 (A)
                       Notice to Proceed – Bridges                 November 2017      November 2017 (A)
                       Substantial Completion – Bridges                May 2020           March 2021

     Highlights:
          The existing bridges are over 100 years old and can no longer be economically repaired and
          maintained. Thus, they have reached the end of their useful life. The construction completed in
          2015 for the outbound tracks over the same 11 streets. The new bridges will last for more than 100
          years. At Ravenswood station, the current structure for the inbound side is just a bare platform. The
          design and construction will deliver riders a new station to provide convenience, safety, and security.
          This station will also be ADA accessible.

*Obligated and Expended amounts as of October 2020.

                                                                                                              14
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

      Central Warehousing
    Description:
         This project includes an acquisition of an
         existing warehouse facility located in the city
         of Harvey that is sufficient to develop a
         centralized warehouse for parts, equipment,
         and signal materials which support the
         operation and maintenance activities of the
         commuter railroad system.

    Status:
         The environmental site assessment has been
         completed for the site. Wire transfer for the
         land purchase has been processed for closing. Metra will be securing the property with fencing and
         completing a full builing and site assessment as part of the predesign activities for builing expansion.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                    Rebuild Illinois Budget              $10,000,000     $6,907,034       $6,637,839             66%

    Schedule:
         Project is on schedule.
                                   Milestone                       Baseline Schedule   Actual (A) / Forecast
                        Property Acquisition                        November 2020      November 2020 (A)
                        Project Completion                          December 2024        December 2024

    Highlights:
         This project will consolidate all warehouse operations to provide a singular, central location for
         materials. This consolidation will allow Metra to better manage our inventory of materials through
         better tracking and reduction of ordering redundancies.

*Obligated and Expended amounts as of November 2020.

                                                                                                                15
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    5 Station Design – Electric Line
    Description:
         This project is for the design of 5 stations on the
         Metra Electric Line. The project includes the
         following stations: 79th St, 87th St, 95th St,
         103rd St and 111th St. The project elements
         may include the replacement and/or
         rehabilitation of station platforms, new lighting,
         gatehouse/head          house        rehabilitation,
         replacement of leaking roofs, installation of new
         warming shelters, new platform amenities, and
         other related work. The project may also include
         wayfinding signage or other station identifiers.
    Status:
         Professional Service contract for design was advertised and awarded. A Notice to Proceed was issued
         by Metra in May 2020. Site surveys and inspections have been completed. Design activities are ongoing
         and the design is currently at 10% completion. Once design is completed, the station construction
         contracts will be bid out separately.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                    Rebuild Illinois Budget               $4,263,987     $4,263,987                $0       0%

    Schedule:
         Project is on schedule.
                                   Milestone                       Baseline Schedule   Actual (A) / Forecast
                        Design Notice to Proceed                      May 2020            May 2020 (A)
                        100% Design                                 December 2021        December 2021

    Highlights:
         This project is part of Metra’s ongoing effort to bring commuter rail stations into compliance with
         the requirements of the Americans with Disabilities Act (ADA) of 1990. Platforms, station structures,
         and pedestrian routes to Metra train platforms will comply with ADA design requirements.

*Obligated and Expended amounts as of November 2020.

                                                                                                                16
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Smart Gates
    Description:
         This project involves upgrades to protected grade
         crossings to improve safety and reliability of grade
         crossing protections. This project will fund
         upgrades of circuitry at these grade crossings to the
         latest technology. Metra will install monitors to
         remotely check the condition of the grade crossing
         protection system. When a monitor detects an
         anomaly, the system will send notice to the back
         office and dispatch a signal maintainer to perform
         repairs.
    Status:
         Metra has utilized a Blanket Agreement for the purchase of Relay Cases to be utilized at the following
         Smart Gates locations: 72nd Street, 80th Place, 81st Street, and 90th Street on the Metra Electric
         District. Metra has started the design in-house and installations will be done by Metra workforce
         starting in the summer. At this time the project includes 14 locations, full implementation will be
         completed with future PayGo funding.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                    Rebuild Illinois Budget               $1,500,000        $634,480        $34,480               2%

    Schedule:
         Project is on schedule.
                                     Milestone                     Baseline Schedule   Actual (A) / Forecast
                        Design Completion                            March 2021            March 2021
                        Installation Completion                     December 2021        December 2021

    Highlights:
         The Illinois Commerce Commission is requiring remote monitoring of protected grade crossings on
         all new projects in their 2019-2023 safety plan. Smart Gates will increase reliability of crossing gates
         by dispatching signal maintainers to fix malfunctions earlier than they would otherwise be detected
         by physical inspection.

*Obligated and Expended amounts as of November 2020.

                                                                                                                17
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Purchase 40’ Compressed Natural Gas Buses (Final)
    Description:
         Purchase new 40’ Compressed Natural Gas (CNG)
         buses for fixed route service. The current grant
         will provide for a minimum of 91 CNG buses.
         Fueling for these buses will be provided through
         a retrofit at Pace South Division in Markham,
         funded through other sources and completed in
         March 2016.
    Status:
         Pace awarded a production contract in February
         2015. Previous reports had a total of 102 buses,
         all of which were received and placed in service. Pace executed a change order to procure an additional
         6 CNG buses using federal funds, those buses have been delivered in July 2020. The total number of
         buses ordered under this contract is 108. The CNG bus contract is in the process of close out.
         Concurrently, remaining state funds were used to procure seven 40’ diesel buses as part of another
         contract; which covers a purchase of (85) 40’ diesel New Flyer buses. Pace has received 84 buses from
         this order with the remaining bus to be delivered by December 1. The diesel buses funded with the
         state funding have been delivered.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                      State-Funded Budget                $49,000,000    $48,876,478      $48,385,000       99%

    Schedule:
         Project is on schedule.
                                    Milestone                      Baseline Schedule   Actual (A) / Forecast
                        Contract Award                               February 2015      February 2015 (A)
                        CNG Retrofit Complete                          June 2015         March 2016 (A)
                        91 Bus Delivery                                June 2016        October 2017 (A)
                        11 Bus Delivery                                June 2018           July 2018 (A)
                        6 Bus Delivery                                  July 2020          July 2020 (A)
                        7 Diesel Bus Delivery                       November 2020      November 2020 (A)

    Highlights:
         Pace has initiated service out of the South Division for these buses, and long-term operational cost
         savings are expected. Pace’s research has shown that despite CNG buses being initially more
         expensive to procure than diesel buses, they have been shown to make up the cost difference prior
         to the end of their useful lives thru operational savings.

*Obligated and Expended amounts as of November 2020.

                                                                                                                18
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    New I-55 Garage - Plainfield
    Description:
         This project is for architectural and
         engineering services, and construction of a
         Pace bus maintenance and storage facility
         in   Plainfield.   In    addition,    road
         improvements using concrete will be
         funded to accommodate the new facility.
    Status:
         Pace       has      entered      into     an
         Intergovernmental Agreement (IGA) with
         the Village of Plainfield. Per the IGA the
         Village of Plainfield is executing a Design-
         Build Agreement with Northern Builders to design and construct the Pace I-55 Plainfield Bus Garage
         on Pace's behalf. Once the design is completed and agreed to by Pace, the Village will execute a
         Design-Build Amendment under the Design- Build Agreement with Northern Builders to construct
         the facility. Once the construction is completed, Plainfield will transfer ownership of the property to
         Pace. The 95% design documents are currently under review. The contractor mobilized on site in
         early November and continues to do site work and utility hook-ups for the site as design continues.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                    Rebuild Illinois Budget              $43,752,500    $43,752,500         $28,152         0%

    Schedule:
         Project is on schedule.
                                    Milestone                      Baseline Schedule   Actual (A) / Forecast
                        Construction Notice to Proceed              November 2020      November 2020 (A)
                        100% Design                                  January 2021         January 2021
                        Substantial Completion                      December 2021        December 2021

    Highlights:
         The current Pace Heritage Division garage was built in 1926 with renovations in 1985 and is exceeding
         its capacity, useful life, and cannot support further growth of the agency’s successful I-55 Bus-on
         Shoulder service. A new garage in Plainfield will allow further expansion of service on the I-55
         corridor, reduce deadhead times and alleviate overcrowding at Heritage.

*Obligated and Expended amounts as of November 2020.

                                                                                                                19
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    New Northwest Division Garage - Wheeling
    Description:
         This project is for the design and construction of a new
         Northwest Garage to replace the existing Northwest
         Division. In 2018, Pace purchased a 23-acre site with
         existing 430,000 square foot building to replace its
         existing Northwest Division. The Wheeling facility will
         be equipped with a Compressed Natural Gas (CNG)
         vehicle fueling station designed to supply an all-CNG
         bus fleet. The new facility will be a full service, fully
         furnished and equipped, heavy duty bus repair,
         maintenance, and storage garage. Occupancies will
         include Pace Vanpool Services and Graphics
         Department including Pace’s Print Shop.
    Status:
         Pace has entered into a contract for the design of the Wheeling facility. At this time the comments
         are being incorporated on the 100% design. The design is expected to be finalized by the end of the
         year. Pace also entered into an Intergovernmental Agreement (IGA) with the Village of Wheeling,
         who is responsible for the design and improvements to Old Willow Road. Construction activities for
         the road improvements have been substantially completed in October.
    Budget:
         The project is on budget. A small portion of the Rebuild Illinois funding will be used for the design
         ($1,882,880). The rest of the state funding will be used for the construction of the facility as well as
         the design and construction of Old Willow Road improvements.
                                                         Budget        Obligated*      Expended*        Expended %
                    Rebuild Illinois Budget              $43,135,380     $1,173,105        $158,422         0%

    Schedule:
         Project is on schedule.
                                    Milestone                      Baseline Schedule   Actual (A) / Forecast
                        100% Design                                 December 2020        December 2020
                        Construction Notice to Proceed                May 2021              May 2021
                        Substantial Completion                      December 2022        December 2022

    Highlights:
         The original Northwest garage building in Des Plaines was built in 1962, and had some renovation
         work done in 1994, at this time it is overcrowded, and well beyond its useful life. The new garage will
         support the implementation of Rapid Transit service on the Pulse Milwaukee and Dempster Lines,
         increase bus storage capacity as well as future growth. Pace plans on replacing diesel buses at the
         new facility with an all-CNG bus fleet.

*Obligated and Expended amounts as of November 2020.

                                                                                                                20
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Pace South Campus Project - Markham
    Description:
         This project is for the design and engineering,
         construction, project management, and any associated
         equipment and services for three facilities for the Pace
         South Campus in Markham. The three facilities are the
         Active Transit Management Center which will serve as a
         new Acceptance Facility, Office Building, and associated
         site work including a Bus Operator Training Course.
    Status:
         Pace amended an existing contract with Bloom
         Companies, the original designer for the South Holland
         Acceptance Facility, to include the modified design for the Pace South Campus Design which is to be
         located in Markham. The project team continues to advance the plans of the Acceptance Facility
         incorporating the review comments, advance the programming of the new office building per Pace's
         input and continues the work on the Civil Site plans incorporating the review comments as well as
         the bus driving facility. The design is 100% complete with the final comments from Pace to be
         incorporated and the design to be finalized in December.

    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                      State-Funded Budget                $27,100,000     $1,688,763       $1,001,907        4%

    Schedule:
         Project is on schedule.
                                    Milestone                      Baseline Schedule   Actual (A) / Forecast
                        100% Design                                 December 2020        December 2020
                        Construction Notice to Proceed                May 2021              May 2021
                        Substantial Completion                      December 2022        December 2022

    Highlights:
         Pace made a decision to move the Acceptance Facility originally planned for South Holland to
         Markham as part of the South Campus development. The original design for the South Holland
         Acceptance Facility will be modified to include additional facilities planned for the Pace South
         Campus project.

*Obligated and Expended amounts as of November 2020.

                                                                                                                21
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    River Division Expansion and Improvements
    Description:
         Pace intends to expand and improve its existing
         River Division bus garage onto newly acquired
         property south of the existing garage. It will be
         designed to accommodate storage, servicing,
         maintenance, and associated program areas for
         an additional 75 buses, 26 paratransit and 6
         non-revenue vehicles in addition to other
         improvements to modernize the existing
         facility.
    Status:
         Pace has entered into a contract for
         Architectural and Engineering services for pre-
         design and design services. The contractor is in the process of completing pre-design activities. Site
         assessments, site surveys and data collection are underway, and a preliminary expansion site layout
         is scheduled to be provided in February. Discussions regarding the purchase of the adjacent property
         continue. A possible cell tower re-location may be required as it is located on the adjacent property.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                    Rebuild Illinois Budget              $21,260,000     $2,013,715          $7,613         0%

    Schedule:
         Project is on schedule.
                                   Milestone                       Baseline Schedule   Actual (A) / Forecast
                        Design Notice to Proceed                     October 2020       October 2020 (A)
                        100% Design                                 December 2021        December 2021

    Highlights:
         This garage was built in 1989 and is in need of improvements. Expanding and renovating the 63,000
         sq. ft. garage would support the agency’s new I-90 Express service and consolidate buses currently
         housed in a facility in East Dundee, eliminating over half a million dollars in annual lease costs. In
         addition, the East Dundee facility does not have onsite fueling and can only support light
         maintenance activities.

*Obligated and Expended amounts as of November 2020.

                                                                                                                22
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Bus Stop Improvements – Joliet Gateway Center
    Description:
         This project will construct a new bus turnaround
         facility to serve the nine Pace routes that will connect
         with the upgraded transportation center in
         downtown Joliet on the Metra Rock Island District
         and Heritage Corridor lines, as well as Amtrak routes.
    Status:
         The City of Joliet and Pace entered into an
         Intergovernmental Grant Agreement for this project.
         Pace continues to meet with the city of Joliet officials
         regarding advancing the project. The overall Joliet
         Gateway Terminal project is being managed by the City of Joliet. The City of Joliet prepared 100%
         design and bid the larger Intermodal Transportation Project, of which the Bus Turnaround
         Component is a part of. The winning bidder was not chosen for the project due to improper DBE
         documentation submitted with the proposal. The City of Joliet rebid the project and the proposal
         evaluation process has been completed. A contract is expected to be awarded by the end of the year.
    Budget:
         The budget includes $1,709,500 from prior years’ state program and $7,800,000 from the Rebuild
         Illinois state program.
                                                         Budget        Obligated*        Expended*        Expended %
                     State-Funded Budget                  $1,709,500                $0               $0             0%
                    Rebuild Illinois Budget               $7,800,000                $0               $0             0%
                       Total State Budget                 $9,509,500                $0               $0             0%

    Schedule:
         Project is on schedule.
                                    Milestone                      Baseline Schedule     Actual (A) / Forecast
                        Notice to Proceed                            January 2021           January 2021
                        Substantial Completion                      December 2021          December 2021

    Highlights:
         The overall Multi-Modal Transportation Center project is being managed by the City of Joliet. Pace
         has committed to funding the improvements of the bus turnaround facility.

*Obligated and Expended amounts as of November 2020.

                                                                                                                  23
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Purchase 15-Passenger Paratransit Buses
    Description:
         State funding under this project will
         provide for the purchase of new 15-
         passenger paratransit vehicles under
         an indefinite delivery/indefinite
         quantity contract, with orders placed
         as funding becomes available.

    Status:
         A contract was executed with Midwest Transit for the purchase of 84 paratransit vehicles in August
         2017. All 84 vehicles have been delivered and accepted. The final vehicle was delivered on June 18,
         2018. A grant amendment was executed to increase the scope quantity to allow for purchase of
         additional vehicles. Pace had to rebid this project due to a bid protest on the prior procurement.
         Pace has completed a second procurement process and a contract has been awarded in November.
         The first order is planned for 210 vehicles. 23 of the paratransit vehicles in this order will be funded
         with the state funds remaining in this grant, the other vehicles will be purchased with federal
         funding.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*     Expended*         Expended %
                      State-Funded Budget                 $7,290,500     $7,290,500      $5,248,294        72%

    Schedule:
         The project is on schedule.
                                    Milestone                    Baseline Schedule    Actual (A) /Forecast
                        First Vehicle Delivery                    November 2015         March 2018 (A)
                        Last Vehicle Delivery                       May 2016             June 2018 (A)
                        23 Additional Vehicles Delivery             June 2021              June 2021

    Highlights:
         Cost savings from previous paratransit vehicle purchases have been reallocated to this project,
         allowing Pace to purchase more vehicles.

*Obligated and Expended amounts as of November 2020.

                                                                                                                24
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    ADA Technology Upgrades and Transfer Centers
    Description:
         Pace plans to improve ADA-related technology
         that will include various software, mobile
         applications and internet platforms to provide
         immediate access to customers for general
         information. In addition, this project also
         includes a transfer location project in
         Schaumburg which currently houses a former
         United States Post Office facility. Pace intends to
         construct an ADA transfer location on this
         property, which is adjacent to the Northwest
         Transportation Center, and would provide
         connections to fixed-route services in addition
         to ADA paratransit services.
    Status:
         On the technology upgrade projects, Pace has executed a contract with Trapeze Software Group Inc.
         for ParaCutter scheduling services to assist with the fall 2020 runcut. Pace is currently in the process
         of acquiring land for the new Northwest ADA transfer center facility. A contract for architectural and
         engineering services has been awarded. The consultant is currently preparing documentation for the
         Schaumburg Zoning Board to get the property rezoned.
    Budget:
         The project is on budget.
                                                         Budget        Obligated*      Expended*        Expended %
                    Rebuild Illinois Budget               $4,000,000        $267,165           $172         0%

    Schedule:
         Project is on schedule.
                                    Milestone                      Baseline Schedule   Actual (A) / Forecast
                        ParaCutter implementation                   December 2020        December 2020
                        A/E Notice to Proceed                        October 2020       October 2020 (A)

    Highlights:
         These upgrades of new software and hardware will provide a better customer experience and
         improve service reliability, safety, and travel time information to our riders. In addition, Pace has
         committed to providing accessible transportation for the ADA community and has located a facility
         in Schaumburg for an ADA transfer center.

*Obligated and Expended amounts as of November 2020.

                                                                                                                25
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

    Orland Square Mall Bus Stop Improvements (Final)
    Description:
         This bus boarding and alighting area will
         accommodate Pace fixed route service,
         the Tinley Park/Orland Square On-
         Demand service, and ADA Paratransit
         service. The project includes the design
         and construction of the bus stop
         improvements. The mall would no longer
         allow Pace to drop off passengers at the
         entrance and the bus stop had to be
         relocated.
    Status:
         Pace has entered into a License Agreement with Orland, L.P. (the mall) for the design, construction,
         permitting and installation of the bus stop improvements. At this time both the design and
         construction activities have been completed. Pace intends to pass-through state bond funds to
         Orland, L.P. and request reimbursement from IDOT for any costs paid with Pace funds.
    Budget:
         The project is on budget.
                                                         Budget       Obligated*      Expended*        Expended %
                    Rebuild Illinois Budget                $640,000        $522,079       $475,278        74%

    Schedule:
         Project is on schedule.
                                    Milestone                     Baseline Schedule   Actual (A) / Forecast
                        Contract Award                               April 2019          April 2019 (A)
                        Substantial Completion                      October 2020       October 2020 (A)

    Highlights:
         The project has been completed under a Licensed Agreement with Orland L.P.

*Obligated and Expended amounts as of November 2020.

                                                                                                               26
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Systemwide

STATE FUNDED PROJECTS – BUDGET PERFORMANCE

 STATUS                           QUANTITY
 On Budget                              22
 Under Budget                            0
 Over Budget                             0

                     PERCENTAGE OF TOTAL PROJECTS

                                                      On Budget

                                                      Under Budget

                                                      Over Budget

                           100%

                                                                             27
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Systemwide

STATE FUNDED PROJECTS – SCHEDULE PERFORMANCE

 STATUS                                        QUANTITY
 On Schedule                                          20
 Behind Schedule                                       2
 Ahead of Schedule                                     0

                            PERCENTAGE OF TOTAL PROJECTS

                                9%

                                                                  On Schedule

                                                                  Behind Schedule

                                                                  Ahead of Schedule

                                         91%

Projects Behind Schedule
 SB       PROJECT                               REASON
          98th Street Rail Shop Bridge
 CTA                                            Contractor was unable to procure material in time.
          Replacement
          Union Pacific North Line Bridges      Additional time needed for Union Pacific approval as
 Metra
          and Ravenswood Station                well as obtaining permits

                                                                                                       28
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Systemwide

STATE FUNDED PROJECTS – CHANGE ORDERS

 STATUS                                             QUANTITY
 Projects With Change Orders                                     2
 Projects Without Change Orders                                 20

Note: Some projects may have executed multiple change orders.

                            PERCENTAGE OF TOTAL PROJECTS

                           9%

                                                                     Projects Without
                                                                     Change Orders
                                                                     Projects With Change
                                                                     Orders

                                  91%

Projects With Change Orders
                                                                                   NUMBER OF
 SB           PROJECT
                                                                                   CHANGE ORDERS
 Metra        Positive Train Control (PTC)                                         14
 Metra        Union Pacific North Line Bridges and Ravenswood Station              8

                                                                                                   29
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Systemwide

STATE FUNDED PROJECTS – CHANGE ORDER REASONS

 REASON                            QUANTITY              COST
 Added Value                               15      $14,155,844
 Unforeseen Conditions                      5         $234,580
 Errors and Omissions                       1          $35,949
 Time Extensions                            1               $0
 TOTAL                                     22     $14,426,373

The change order quantities and cost amounts represent the cumulative total for the 22
currently ongoing state-funded projects. The total cost of change orders represents less than
1% of the overall total budget of the state funded projects. All change orders were executed
within the project budgets.

Metra executed a change order in this reporting period for the Systems Integrator contract on
the Positive Train Control project. Change Order 14 was for an extension for continued support
to Metra's evolving Interoperable Train Control Messaging (ITCM) system, including introducing
new applications, interfaces, and other changes related to ITCM that include services such as
topology management, impact analysis, as well as upgrades to the platform.

                                                                                            30
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Section II
Systemwide Projects over $10,000,000

                                                                 31
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Systemwide

PROJECTS OVER $10,000,000

SERVICE BOARD    PROJECT TITLE                                                 BUDGET
CTA             Red Purple Modernization (RPM) – Phase 1                       $2,203,408,226
CTA             Purchase Rail Cars – Series 7000                                $719,817,768
Metra           Positive Train Control (PTC)                                    $415,879,609
CTA             5000-Series Rail Car Rehabilitation                             $221,537,449
CTA             O'Hare Line – Signal Upgrades & Special Trackwork               $207,100,000
Metra           Locomotive Purchase                                             $186,576,796
Metra           Union Pacific North Line Bridges (South 11 Bridges)             $162,100,000
Metra           Union Pacific West Line Expansion                               $124,939,627
Metra           Replace Bridges, 18th to 55th – Rock Island District            $120,278,505
Pace            Purchase 40' Compressed Natural Gas Buses                       $119,913,100
Pace            Purchase 30' Low-Floor Diesel Buses                               $80,261,908
Metra           New Bi-Level Cars                                                 $75,232,683
Pace            Purchase 15-Passenger Paratransit Buses                           $69,991,388
Metra           Locomotive Rehabilitation – F40 (Option 1)                        $64,116,900
Metra           Rehabilitation of Rolling Stock                                   $57,005,321
CTA             Ravenswood-Loop Connector Signal Renewal                          $50,000,000
Metra           Car Rehabilitation – Nippon Sharyo – Phase 3                      $49,816,810
Metra           Union Pacific North Line Bridges and Ravenswood Station           $47,699,764
Metra           Financial System Replacement                                      $46,469,931
Pace            New I-55 Garage – Plainfield                                      $43,752,500
Pace            New Northwest Division Garage – Wheeling                          $43,135,380
Pace            Purchase 40' Low-Floor Diesel Buses                               $41,786,531
Metra           Yard Improvements                                                 $40,589,115
CTA             Purchase Electric Buses                                           $35,475,352
Metra           Bridge A-32                                                       $34,473,222
Metra           Bridge Z-100 Replacement                                          $34,000,000
Metra           Commuter Car Rehabilitation – Budd                                $33,319,746
Metra           Traction Power System Augmentation – Metra Electric District      $32,275,623
Metra           Locomotive Rehabilitation - MP36                                  $30,802,491
Pace            Pace South Campus Project – Markham                               $27,100,000
CTA             Rail Car Overhaul – Series 2600                                   $25,314,552
CTA             Non-Revenue Vehicles – Diesel Locomotives                         $22,731,013
Metra           GPS Train Tracking                                                $22,119,383
Metra           Auburn Park New Station                                           $21,572,495
Pace            River Division Expansion and Improvements                         $21,260,000
Pace            Purchase Vanpool Vehicles                                         $20,011,499
Metra           Peterson-Ridge New Station                                        $18,629,765
Metra           Revenue Accounting System                                         $17,770,000

                                                                                           32
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

CTA     Systemwide Traction Power Upgrades                                  $15,166,629
Metra   Car Rehabilitation – Nippon Highliners                              $14,935,870
Metra   Car and Locomotive Cameras                                          $14,805,891
Metra   IT Components and Services                                          $14,384,813
Pace    Purchase 7-Passenger Vanpool Vehicles                               $13,899,800
Pace    Transit Signal Priority (TSP) Equipment and Installation Services   $12,943,374
Metra   Central Warehousing                                                 $10,000,000
Metra   Van Buren St Station                                                $10,000,000

                                                                                     33
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Systemwide

PROJECTS OVER $10,000,000 BY SERVICE BOARD – QUANTITY AND BUDGET

 SERVICE BOARD     PROJECTS                BUDGET
 CTA                         9       $3,500,550,989
 Metra                     26        $1,699,794,361
 Pace                      11         $494,055,480
 TOTAL                     46       $5,694,400,830

                  PERCENTAGE OF TOTAL PROJECTS

                       24%
                                                      Metra
                                                      CTA
                                     56%              Pace

                     20%

                    PERCENTAGE OF TOTAL BUDGET

                              9%
                                     30%                Metra

                                                        CTA

                                                        Pace

                        61%

                                                                                 34
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

Systemwide

PROJECTS OVER $10,000,000 BY TYPE OF PROJECT

 TYPE OF PROJECT                                     QUANTITY      COMBINED BUDGET
 Construction                                               17           $3,035,214,223
 Maintenance / Rehabilitation                               12            $756,041,043
 Procurement                                                17           $1,903,145,565

CTA

 TYPE OF PROJECT                                     QUANTITY           TOTAL BUDGET
 Construction                                                2           $2,253,408,226
 Maintenance / Rehabilitation                                4            $469,118,630
 Procurement                                                 3            $778,024,133
 TOTAL                                                       9           $3,500,550,989

Metra

 TYPE OF PROJECT                                     QUANTITY           TOTAL BUDGET
 Construction                                               11            $646,558,117
 Maintenance / Rehabilitation                                8            $286,922,413
 Procurement                                                 7            $766,313,832
 TOTAL                                                      26           $1,699,794,361

Pace

 TYPE OF PROJECT                                     QUANTITY           TOTAL BUDGET
 Construction                                                4            $135,247,880
 Maintenance / Rehabilitation                                0                      $0
 Procurement                                                 7            $358,807,600
 TOTAL                                                      11            $494,055,480

                                                                                     35
REPORT ON PROJECT MANAGEMENT OVERSIGHT – DECEMBER 2020

CTA

PROJECTS OVER $10,000,000

SERVICE BOARD   PROJECT TITLE                                               BUDGET
CTA             Red Purple Modernization (RPM) – Phase 1                    $2,203,408,226
CTA             Purchase Rail Cars – Series 7000                             $719,817,768
CTA             5000-Series Rail Car Rehabilitation                          $221,537,449
CTA             O'Hare Line – Signal Upgrades & Special Trackwork            $207,100,000
CTA             Ravenswood-Loop Connector Signal Renewal                       $50,000,000
CTA             Purchase Electric Buses                                        $35,475,352
CTA             Rail Car Overhaul – Series 2600                                $25,314,552
CTA             Non-Revenue Vehicles – Diesel Locomotives                      $22,731,013
CTA             Systemwide Traction Power Upgrades                             $15,166,629