POLCEVERA COLLAPSE - GENOA DISASTER EXPOSES MAJOR ENGINEERING VULNERABILITIES
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Inside: Facing Down The Floods p29 Interview: Sir James Bevan p20 New Civil Engineer S E P T E M B E R 201 8 POLCEVERA COLLAPSE GENOA DISASTER EXPOSES MAJOR ENGINEERING VULNERABILITIES
New Civil Engineer MAINTENANCE IS KEY TO PREVENT ANOTHER POLCEVERA MARK HANSFORD EDITOR structure such as the Polcevera viaduct in Genoa In the UK, every structure, from culverts under roads to multi-span A should never, ever collapse. Anywhere in the world. It certainly should never happen in a western European country such as Italy. viaducts, must be visually inspected every two years. Every six years they must be investigated by people within hand touching distance of the components, with reports made on their condition, followed up by Investigations into the cause of the collapse will be programmed and budgeted corrective maintenance works. thorough and will be pored over by bridge engineers worldwide. Al- The owner and operator of Morandi’s bridge, Autostrade, has in- ready a number of theories are circulating – but until the investigation sisted it was aware of this need, and that it, too, had its bridge under is completed, it is only possible to speculate. routine maintenance and constant surveillance. Clearly a large part of “ What should be said is that the Polcevera viaduct was amazing in the investigation needs to focus on just what that maintenance and its time, and its designer, Riccardo Morandi, was a genuine innovator. surveillance was, and how it was deemed sufficient. New Civil Engineer’s founding editor, Sydney Lenssen, visited the Genoa viaduct in 1965 and insists it was a miracle in its day. And he re- calls that despite reservations about the “unusual design”, Morandi’s Many bridges of that era are in ambition was infectious and he was heralded as a genius at the time. Morandi was determined to explore the concept that evolved into the same situation because no cable-stayed technology and was equally determined to push the use of prestressed concrete. bridge designers of that era foresaw the Clearly it would never be built in the same way today. Cable stay long-term durability issues and excessive technology has massively advanced. But that does not mean Morandi designed a bad bridge. traffic loads. No one did. It is now emerging that Morandi’s bridge has required considerable maintenance over the years – we have pictures that clearly show strap- ping around many critical beams, and have confirmed that plans were But back here in the UK there is no room for complacency. Despite in place to strap the section that failed. the warnings from the Humber, Severn and others, and despite the There is no shame in that: many bridges of that era are in the same lauded inspection regime, the Hammersmith flyover nearly became an situation, principally because no bridge designers of that era foresaw international incident of our own when major defects were detected the long-term durability issues and excessive traffic loads that would just before the start of the 2012 Olympics – prompting immediate clo- affect their structures. No one did. sure and urgent remedial works. In the aftermath of Polcevera, Highways England has reassured road Some clever, award-winning engineering has now restored that users that its bridges of that are age under control. But that is only structure to full use, but it was a very near-thing at the time. because here in the UK we have had our warnings and acted on them: So that has to be the lesson. There are thousands of 1960s and 1970s severe cable corrosion first detected in the Humber Bridge warned bridges worldwide, many of them as unique as Morandi’s in their de- that the Severn and Forth Road bridges may need intensive remedial sign, and all of them in various states of (dis)repair. Keeping them go- works and constant, 24-7, monitoring. In all three cases dehumification ing is clearly going to become an ever more invaluable skill. of tendons and acoustic monitoring keep the structures serviceable. l Mark Hansford is New Civil Engineer’s editor A U G U S T 2 01 8 | NEW CIVIL ENGINEER 3
Contents NEW CIVIL ENGINEER SEPTEMBER 2018 MAGAZINE OF THE INSTITUTION OF CIVIL ENGINEERS 03 Comment, 29 World View: Analysis & News Facing Down The Floods 06 Lighthouse: How engineers can help cities to change 16 Experts dismissed Florida bridge cracks hours before collapse 22 Your View: ICE governance procedures divide membership 08 Special Report: Polcevera Viaduct Collapse The latest thinking on flood management is to accept the inevitability of nature. That means coastal villages in the UK accepting they cannot hold back the sea, while London and 08 Structure’s vulnerabilities revealed New York are tackling the problem through design. 09 Plans reveal viaduct was to be scrapped 10 Blue skies, police, debris and twisted 30 Overview: accepting that flooding 38 New Civil Engineer’s Flood remains: Report from the scene is inevitable is the first step in Management Forum line-up preparing areas for a quick recovery revealed 12 Construction images reveal structure’s complexity 34 New York is designing a defence 40 Debate: The future for Sustainable system that works for all, London is Drainage Systems appears rosier in 14 Highways England reassures UK planning for the next century the wake of new government policy road users 4 NEW CIVIL ENGINEER | SEPTEMBER 2018
eer Engin New C ivil Get news delivered daily Weekl y Wrap and analysis delivered weekly with our newsletters. Sign-up at newcivilengineer.com 20 Interview: 24 Business EDITORIAL TEAM Sir James Bevan Culture EDITORIAL ENQUIRIES Email: nceedit@emap.com Editor Mark Hansford (020) 3953 2821 mark.hansford Deputy Editor Alexandra Wynne (020) 3953 2822 alexandra.wynne Contributing Editor Jackie Whitelaw jackie.whitelaw@btinternet.com Associate Editor Emily Ashwell (020) 3953 2094 emily.ashwell 20 The chief executive of the 24 How Bryden Wood is saving clients News Editor Rob Horgan Environment Agency discusses the time and money by breaking down (020) 3953 2087 rob.horgan challenges he faces as climate change projects and building them off-site Technical Reporter continues its impact Katherine Smale (020) 3953 2044 katherine.smale 44 Tech 49 Market Chief Sub Editor Excellence Report Andy Bolton (020) 3953 2823 | andy.bolton Designer James McCarthy james.mccarthy@emap.com Graphic Artist Anthea Carter ben.anth@lunestudio.co.uk Technical Editor Emeritus Dave Parker dave.parker CUSTOMER SERVICES customerservices@nce.co.uk 44 How two inflatable weirs are 49 Infrastructure Insight report protecting Leeds city centre from in association with McGinley future flooding Support Services S E P T E M B E R 2 018 | NEW CIVIL ENGINEER 5
Lighthouse ICE VIEWPOINT Engineers can help cities adapt to change “ t is not unusual for Resilience is a much wider Civil engineers I the British to talk issue than dealing with extreme about the weather. In weather events. We know that play a valuable fact, many consider it the global population is growing a national pastime. – putting greater demands on our role in safeguarding the future of the However, the recent infrastructure – as much as we know unprecedented temperatures – that some networks are beginning to across not only the country but much of the northern hemisphere BY ART WE creak under the pressures of age. Work is being done to mitigate global population – have made these meteorological MASTER this from various quarters. musings a bit more urgent. W H AT W O U L D The ICE’s inclusive cities Commuters sweltering on the MASTER US strand of thought leadership Engineering Conference – is helping London Underground may seem work is investigating how cities urban leaders develop resilience like an inconvenience but in Tokyo, can handle changes in usage, strategies, with Sydney unveiling nearly 6,000 people have been resulting from factors such as the one earlier this year, following the rushed to hospital with suspected night time economy, or changes examples of Bristol and Glasgow. heatstroke or heat exhaustion since in users resulting from the ageing These strategies unite people, April as the mercury hit more than population. This will help to develop projects and priorities to seek 41˚C. The pressures on our cities future resilience and inform the out new solutions for collective can and will directly impact the decisions made by civil engineers on resilience challenges. health and wellbeing of individual the ground. This way of thinking illustrates inhabitants. Meanwhile, the National how civil engineers play a valuable This summer has put our urban Infrastructure Commission has role in safeguarding the future of the infrastructure under a particular published the National Infrastructure global population. By offering up pressure and potentially questioned Assessment (NIA) which takes a their expertise and providing their its resilience. But much as one long-term approach to planning and technical know-how, they are often swallow doesn’t make a summer, one recognises the population and climate at the front end of these resilience “ hot summer doesn’t make a crisis. challenges we face. strategies. The NIA includes a clear desire With these separate initiatives for investment in the transport setting the agenda and the work This summer networks of city regions, while of civil engineers playing such an has put our preparing for 100% electric vehicle sales by 2030. Empowering city important part in their success, we can see yet again the profession’s urban infrastructure regions to take charge of their own infrastructure networks is an integral potential to transform lives and safeguard the future for all of us. under a particular part of the ICE’s devolution agenda and will help to build the resilience Translating these initiatives and activities into civil engineering pressure and that the UK’s cities require. solutions will be one of the primary The Rockefeller Foundation’s 100 bulwarks against the growing potentially questioned resilient cities initiative – which challenges we face. its resilience is involved with and which will be speaking at the upcoming Global l Send comments on the Lighthouse to policy@ice.org.uk 6 N E W C I V I L E N G I N E E R | S E P T E M B E R 2 01 8
BIM. ACCURATE PIPE DESIGN at your fingertips FREE! CONNECT TO BETTER FEATURING REVIT CONTENT PACKAGE • Quickest way to a complete ‘as built’ pipe system • Precise designs with intelligent assistance Download yours today! • Fully integrated Bill of Materials Download now at wavin.com/bim CONNECT TO BETTER
POLCEVERA Polcevera Viaduct Collapse VIADUCT COLLAPSE Engineers reveal Milan GENOA Venice A structure’s Corsica Adriatic S Sea Po ITALY vulnerabilities Tyrrhenian Sea Sardinia N Sicily 150km 1km N Katherine Smale 1.1km long viaduct, including one of three 90m high towers collapsed on in Genoa IN THIS 14 August during a thunder storm. REPORT Engineers have suggested a potential cause for its collapse nvestigators examin- could be that the heavy rain washed I ing the scene of the p09 ground from underneath the tower, Polcevera collapsed Polcevera Bridge was undermining its foundations. The River viaduct, more familiar- mooted for bridge’s foundations were undergoing ly known as Morandi strengthening works at the time of bridge, have found damage and replacement collapse, according to Italian high- corrosion to the main stay cables on ways operator Autostrade. 250m collapsed section the collapsed section of the bridge, p10 However, while one source close New Civil Engineer can reveal. Report from to the investigation said that nothing Cables encased 90m Sources close to the investigation was being ruled out at this stage, he in concrete the scene told New Civil Engineer that failure of said that the foundations for the col- the cables – which were encased in lapsed tower “appeared to be stable”. 45m concrete to protect them from the el- p 12 New Civil Engineer’s founding edi- Polcevera River ements – may be behind the collapse. The unusual tor Sydney Lenssen – who visited the “I have heard that video footage structure site during its construction in 1965 from the CCTV cameras on the bridge explained – believes that other factors are more just before the collapse showed likely to have caused the collapse. concrete being exploded off the main Lenssen said: “It looks like the p 14 Immediate concerns centre stay because of the violence of some structure has collapsed around the on the stability of the remaining of the cables snapping underneath,” Lessons for foundations, rather than the founda- viaduct one investigation source said. the UK tions causing the collapse. It comes after Italian fire chiefs “I suspect that one of the supports expressed concern for the safety of from underneath has given away. workers sifting through the rubble That or the cables above have suf- beneath the remaining structure. fered from corrosion.” Luca Ponticelli, a structural engi- Past president of the Institution of neer for Italy’s national fire brigade Structural Engineers Ian Firth agreed Corpo Nazionale dei Vigili del Fuoco, that corrosion of the cables was a told New Civil Engineer that the likely cause of collapse. bridge is now unbalanced. “As this reinforced and prestressed “I’m sure that the elastic deforma- concrete bridge has been there for tions on the pillar were immediately 50 years, it is possible that corrosion absorbed at the collapse but now of tendons or reinforcement may be new viscous or plastic deformations a contributory factor,” he said. “In are progressing on the loaded side. addition, ongoing work on the bridge “So it begs the question, is the may or may not be partly responsible bridge able to bear this new load for the collapse.” condition?” Autostrade has until the end of Thirty-eight people were killed August to produce a report on its when a 250m long deck section of the inspection and maintenance regime. 8 NEW CIVIL ENGINEER | SEPTEMBER 2018
E 1967 1.1km 90m Opened Total length Height of pylons ADDITIONAL EXTERNAL Viaduct operator STEEL CABLES A10 Polcevera River tendered for steelwork retrofit Cornigliano Sestri Ponente GENOA Oregina POLCEVERA VIADUCT COLLAPSE A10 Sampierdarena ALEXANDRA WYNNE EXCLUSIVE Genoa airport SS1 The owner and operator of the Polce- N vera viaduct was actively tendering 1km Ligurian Sea for €20M (£17.9M) of structural ret- rofitting at the time of its collapse, as a stop gap while a complete upgrade of the major road network around Genoa was worked up. Tender documents seen by New PONTE POLCEVERA Civil Engineer reveal that the section of the viaduct that collapsed on 14 August, killing at least 38, was set ra for significant repairs along with the adjacent tower and stay cables. This would have kept the bridge serviceable while a major upgrade to the area’s strategic network was COLLAPSED SECTION delivered. A10 The main stay cables on both m sections were scheduled to be beefed up with new steel cables strapped to the surface of the existing concrete beams and attached to the deck and apex of the pylon with new steel an- chor blocks. In total 55t of steel was predicted to be required. Additionally, 35,000m2 of reinforced concrete on the deck, two towers, and their cables were to be shot- The foundations of the collapsed blasted and repaired, amounting to tower appear intact 1,200m3 of concrete. The works echo similar repairs carried out on the third tower, closest to the land, in the 1990s. This work is clearly visible on photographs of the bridge following its collapse. The contract notice was issued on the Official Journal of the European Union on 28 April and was for “struc- tural retrofitting of the Polcevera viaduct at km 000 + 551 of the A10 Genoa-Savona motorway”. Deadline for tenders was 11 June 2018. There is no evidence of the con- tract having been awarded by owner and operator Autostrade per L’Italia. Documents also reveal the opera- tor describes the Polcevera viaduct as a “strategic” asset and the only cable stayed structure on its road network. S E P T E M B E R 2 01 8 | NEW CIVIL ENGINEER 9
Polcevera Viaduct Collapse Blue skies, police, cranes, debris and twisted remains Looking down From the Scene Via Giorgio Katherine Smale Perlasca road the wreckage of the tower is just visible. rriving at the edge of A the cordoned off zone, the police guard all access points to what remains of the motor- way bridge leading out of Genoa. The surrounding streets are eerily quiet. All roads surrounding the bridge have been closed, all residents living below and around the Polceve- ra Viaduct, more familiarly known as of the 250m-long section lie below, The two still-standing piers look sta- Morandi bridge, have been evacuated with what appears to be a 15m sec- ble and no deflection of the remaining and told they may never be able to tion of the four-lane road deck lodged deck tip can be seen. Anchor blocks return to their homes. in the river valley. for the cable stays at deck level are With bright blue skies above, The deck must have mostly fallen still attached to the remaining towers and mountains rising magnificently out of view or broken up into smaller with no signs of distress, although the in the background the air is still and sections on impact, as the debris that twisted remains of the parapet can be it is hard to believe that thunder- can be seen from this vantage point seen hanging off the end. storms battered this area just two does not seem to be enough to fill the Maintenance inspection platforms days before. vast gap which has been left above. can be seen underneath the bridge In contrast to the picturesque late Looking down Via Giorgio Perlasca deck at the point of the haunch on Italian summer setting is the harsh road the wreckage of the tower is just the underside of the deck. marine environment with concrete visible. Around 15m sections At the top of what was the industrial looking buildings, brown of the tower legs are heaped in a middle pier, steel housing for the corrosion stains on their surface. vast pile of rubble. What look like concrete-encased main stays are Rescue workers with hard hats, post-tensioning cables can be seen brown and rusted. climbing gear and cutting equipment draping from one of the exposed Looking further east at the end come and go in fortified 4x4s. Helicop- faces of the concrete. pier, it is clear that work has taken ters and drones fly over the wreckage Two mobile cranes are helping with place to strengthen the main stays. and sirens punctuate the silence. the rescue effort and hydraulic break- Black cables run alongside the origi- The world’s media has descended ers can be heard hammering away, nal stays and over new grey saddles on the area and only journalists are trying to break up the larger lumps of at the top of the tower. allowed to pass onto the Via Renata concrete. Looking north west, the other side Bianchi bridge, which affords a clear Looking up to the remaining of the collapsed bridge can be seen. view of the foreboding wreckage towers, the deck of what should have Telecommunication wires hang down above and below in the distance. been the middle pier now stands from the collapsed face. The remaining two towers of isolated on one side. Trucks and cars that narrowly the Polcevera Viaduct can be seen It is clear that the bridge deck has escaped the fall still remain on top around 300m away on the east side of failed along its joint lines as the end of of the deck in a haunting reminder of a dry river bed. The twisted remains the still-in-place deck section is neat. the tragedy that occurred. 10 NEW CIVIL ENGINEER | SEPTEMBER 2018
RIDGIDRAIN AND RIDGISEWER E V E R Y T H I N G Y O U L O V E O N LY • Now available in 750mm Ridgidrain and Ridgisewer are the • Now available in 750mm and 900mm diameter same quality products you’ve always and 900mm diameter • Full range 100mm - 900mm known - but now they’re even bigger. • Full range 400mm - 900mm • Available in 3m lengths, Available in two new diameters; 750mm • Available in 3m lengths, 1.5m and 6m and 900mm, the new larger pipes have 1.5m and 6m • Can be cut to length on-site resistance to high traffic loads and • Can be cut to length on-site • Manufactured to SN4 or SN6 have long life durable polyethylene • Manufactured to SN4 • BBA HAPAS approved construction. They’re quick and easy to • KitemarkTM Accredited install, and compatible with our range of products and fittings. INCREASE THE POTENTIAL. Size up the benefits www.polypipe.com/bigger-range PCL-18-420 Joint Advert_NCE 265 x 210mm.indd 1 05/03/2018 16:15
Polcevera Viaduct Collapse Construction images 1 reveal true extent of Morandi’s vision From the archive The report details how each of the main towers is founded on a Rob Horgan KEY FACT reinforced concrete pile cap, in turn supported on large diameter bored piles, in many cases about 40m deep. ew Civil Engineer 19 67 One theory mooted by engineers is N exclusively reveals a Bridge that the heavy rainfall from the storm 1960s report detail- inaugurated may have washed ground away from ing the construction after four underneath the tower, undermining methods and designs its foundation and causing the base of years of behind the collapsed Polcevera via- the tower to rotate and collapse. duct bridge in Genoa. construction New Civil Engineer’s founding As New Civil Engineer went to press editor Sydney Lenssen obtained the search and rescue effort was still report during a visit to the Morandi ongoing in Genoa after an around bridge mid-construction in April 1965, 3 250m long section of the 11 span, in an organised tour promoting the pre-stressed concrete, cable stayed use of concrete in long-span bridge motorway bridge collapsed, killing at construction. Lenssen said that there least 38 people. were several “unusual” structural The 1965 report, obtained by New design elements which may have con- Civil Engineer, details the unusual tributed to the bridge’s collapse. structure’s key elements and the con- “At first look it doesn’t look like a struction techniques used to build it. fault in the foundations,” Lenssen told It also provides real insight into the New Civil Engineer. “I suspect that construction itself through a series of one of the supports from underneath photographs charting construction has given away. That or the cables progress and will likely be used in fu- above have suffered from corrosion.” ture investigations into the collapse. Construction of the towers was It explains how designer Riccardo fairly conventional, using steel form- Morandi viewed the single stay cable work, the Viadotto sul Polcevera per design more as a reinforced concrete l’Autostrada Genova-Savona report tie beam, with the cable’s steel outlines. But the method of encasing tendons encased in concrete. the steel tendons was more unusual. The deck was constructed as a Lenssen added: “Morandi was con- “ balanced cantilever with temporary vinced that covering the steel cables tie beams running 1m above the deck providing temporary support until the permanent tie beams were constructed. At the time It also details the construction of the bridge’s foundations, which high- it was a ways operator Autostrade per L’Italia terrifically ambitious was carrying out works on at the time of collapse. structure 12 NEW CIVIL ENGINEER | SEPTEMBER 2018
2 1. MAIN TOWER CONSTRUCTION Each tower is 100m tall and founded on a reinforced concrete pile cap, in turn supported on large diameter bored piles 2. DECK ERECTION Cantilever construction of the deck with temporary steel tie beans running 1m above the deck; stay cables hang from the tower before encasing in concrete 3. WORK OF GENIUS? At the time it was a terrifically ambitious structure, however strange the design More images at newcivilengineer.com would protect them but it looked very strange. The concrete casing was also built in two or three sections and I was straight away concerned how this would protect the cables from corrosion. “All suspension bridge cables suffer from corrosion, regardless of whether or not they are covered in concrete.” Despite his reservations about the “unusual design”, Lenssen said that Morandi’s ambition was infectious and he was heralded as a genius at the time. “Morandi was a bit of a genius and a very good businessman. At the time it was a terrifically ambitious structure, however strange the design was,” Lenssen said. “There’s no doubt that it was an unusual design. It was a highly unusu- al structure, almost a mish mash of bridge types. “It wasn’t a cable stay bridge even though it had cables, it wasn’t a typical cantilever bridge either and it had a lot of supports between the “ structures.” Morandi was a bit of a genius and a very good businessman S E P T E M B E R 2 018 | NEW CIVIL ENGINEER 13
Polcevera Viaduct Collapse No UK complacency af Highways England moves FIVE UK NEAR MISSIES to reassure UK post-Genoa 1. HAMMERSMITH FLYOVER Emergency closure in 2011 (pictured) 2. BOSTON MANOR Urgently closed and faced replacement in summer 2012 UK Reaction and regular regime for inspecting all structures, including bridges, on En- 3. HUMBER BRIDGE Alexandra Wynne KEY FACTS gland’s motorways and major A roads Corrosion threatended lifespan and taking any necessary action to help ensure they stay safe.” 4. FORTH ROAD BRIDGE 3 , 2 03 o bridges on the General inspections are undertaken Fears so acute a replacement was built N UK’s strategic road UK highways every two years with more detailed at a cost of £1.35bn network bear simi- structures principal inspections typically every larities to that of the deemed six years, involving close inspection 5. SEVERN BRIDGE collapsed structure in substandard of all parts of a structure. Unacceptable levels of corrosion Genoa, Highways England has said. Questions are now being raised Moved to respond to the catastro- as to how such a devastating bridge phe in Italy, the roads operator said £ 1. 3 5 b n collapse could happen in a European that while “a very small proportion” Cost of country, whose proximity to the UK of its structures are suspension or replacing appears to have triggered concerns cable stayed bridges, none were of a Forth Road around asset knowledge and safety “similar construction” to that of the here, which in turn has triggered Bridge Polcevera viaduct. Highways Engand’s assurances. The unusual statement comes as These assurances emphasise the concerns mount as to what the pos- UK’s confidence in the safety of its sible contributing factors were that own key bridge assets, which opera- led to the fatal collapse. Italian road tors in recent years have had cause operator Autostrade has confirmed for concern about and experience in that the bridge was undergoing resolving structural safety issues. maintenance work, when a 250m long The Humber, Severn and Forth platform of deck and a pier collapsed. bridges have all been subject to The operator said it had been serious maintenance interventions to strengthening the structure’s stem cable corrosion. Dehumidifica- foundations as part of scheduled tion of tendons and extensive acous- maintenance works, although it is not tic monitoring keep them in service. yet clear where this work was taking In addition, Transport for London place in relation to the collapsed was forced to close the vital 1960s section. Hammersmith flyover in late 2011 electroslag welds. Sources close to the investigation as a result of the discovery of a Fears were so acute that transport have also indicated that serious “serious structural defect” during minister at the time Mike Penning corrosion is visible in the failed a two-year monitoring exercise. said that work had already begun to structure. Scheduled repairs were made more look at replacing the structure. The statement by UK counterpart urgent as the problem was revealed On the local roads network, con- Highways England said of its road to be worse than earlier inspections cerns remain as to the vulnerability of network: “We have detailed design indicated. key structures. Research released by standards and quality control pro- Around six months later, a nearby the RAC Foundation last year found cesses to ensure bridges are designed section of the M4 – known as Boston that more than 3,000 council-main- and constructed to provide safe and Manor Viaduct – was also urgently tained road bridges were considered comfortable journeys for road users. closed following the discovery of “substandard”. “This is supported by a thorough cracks in the 1960s steel structure’s Analysis of data received from 199 14 NEW CIVIL ENGINEER | SEPTEMBER 2018
after Italian experience Billions needed to bring Italy’s bridges up to date MARK HANSFORD a useful life of 100 years. “Today part of the Morandi viaduct A “Marshall Plan” costing “tens of bil- has collapsed, which will probably lions of euros” is needed to bring the lead to complete demolition and tens of thousands of bridges across replacement of the work,” added Italy that have exceeded their design Occhiuzzi. “The element in common life up to standard, a leading Italian is the age of the structures: most of research body has demanded. the Italian road infrastructures (road The call has been made in the bridges) have exceeded 50 years of wake of the collapse of the Polcevera age, which correspond to the useful viaduct by the largest public research life associated with the reinforced institution in Italy, the National Re- concrete works made with the tech- FIVE ITALIAN COLLAPSES search Council (NRC). nologies available after World War II.” It cites a sequence of collapsing Occhiuzzi stressed that the Polce- 1. PETRULLA VIADUCT Italian road infrastructure that has vera viaduct, more commonly known Collapsed in 2014 after post- become “a worrying regularity” for as the Morandi bridge, owes its name tensioning failed some years and highlights that age to the “brilliant designer/executor is the common factor, with most of the work, one of the names that, 2. ANNONE FLYOVER of the infrastructure in Italy built together with Freyssinet (France), Heavy load caused collapse in 2016 of reinforced concrete in the 1950s Leonhardt (Germany) and Maillart and 1960s. It adds that severe cost (Switzerland), changed the concept of 3. ADRIATIC MOTORWAY pressures following the Second World bridges in Europe and in the world”. Overpass collapsed during War meant that compromises were Built between 1963 and 1967, maintenance work in March 2017 often made between capital cost and Occhiuzzi described it as an exam- longevity of the structures. ple of “absolute rationalism” and 4. TANGENZIALE DI FOSSANO “In practice, tens of thousands rejected suggestions that it was badly Collapsed in April 2017 (pictured) of bridges in Italy have exceeded, designed. today, the lifespan for which they He also said there was no immedi- 5. POLCEVERA VIADUCT were designed and built,” said NRC ate reason to doubt Autostade’s main- Collapsed in August 2018 killing 38 director of the Institute of Construc- tenance regime, instead suggesting tion Technology, Antonio Occhiuzzi. that more development was required “ “In many cases, the foreseeable costs in monitoring systems. of the 207 local highway authorities for the extraordinary maintenance in the UK shows that 3,203 struc- that would be necessary for these tures over 1.5m in span were unfit to carry the heaviest vehicles, including bridges exceed those associated with demolition and reconstruction. Tens of lorries of up to 44t. This represents around one in 23 of the roughly “The figures necessary for the modernisation of road bridges in Italy thousands of 72,000 bridges on the local network. Highways England said that it would be expressed in tens of billions of euros,” he added. “To avoid trage- bridges in Italy have would seek to assess potential for les- sons to be learned once the ensuing dy such as Genoa, a sort of ‘Marshall Plan’ for Italian road infrastructures exceeded the lifespan investigations into the causes of the would be indispensable, based on the for which they were Italy bridge collapse are complete, replacement of most Italian bridges and a report issued. with new structures characterised by designed and built S E P T E M B E R 2 018 | NEW CIVIL ENGINEER 15
MORE The Edit NEWS TRANSPORT D L R-S T Y L E S C H E M E More JOINS PROPOSALS coverage F O R H E AT H R O W L I N K E S S E N T I A L N E W S & I N F O R M AT I O N online at A £375M light rail scheme to F R O M N E W C I V I L E N G I N E E R .C O M newcivil Heathrow has been submitted to the engineer.com Department for Transport (DfT) as part of its call for ideas on third-party funded projects. Submitted by Spelthorne Council, the DLR-style scheme is in direct competition to bids by the Windsor Link Railway and Heathrow Southern Rail. The scheme proposes a light rail link from Staines-upon-Thames to the airport, with a new Staines station part of the proposal. The council claims the light rail line would put Staines on the map as a “centre for business growth and investment” and release “huge untapped potential” to Heathrow, by reducing journey times to seven minutes. Spelthorne Council group head for regeneration and growth Heather Morgan claims that other proposals for traditional “heavy” rail access were “unacceptable” and would take up too much space. Experts dismissed cracks in KEY STATS TRANSPORT MARK CARNE URGES Florida bridge hours before NETWORK RAIL TO ‘ R A D I C A L LY R E F O R M’ 862t collapse killed six people Weight of ALLIANCING MODEL trussed Outgoing Network Rail chief executive Florida bridge Mark Carne has urged his successor INFRASTRUCTURE In the report, it said the team to implement “radical reform” to Shocking photos of cracks on a had met for two hours on the that collapsed improve the track operator’s Florida bridge, taken days before it morning of 15 March before alliancing process. On his last official collapsed killing six people, have concluding that the cracks did not day at the helm, Carne urged been released by US authorities. The compromise the structural integrity incoming chief executive Andrew Florida International University (FIU) of the bridge. The bridge collapsed Haines to “aggressively embrace” bridge, a 53m long, 862t concrete three hours later. new technologies to improve the trussed structure, was under network’s reliability. construction when it collapsed onto “The performance of the railway a live eight lane road below on 15 for passengers is not good enough “ March, killing five people in vehicles and has been getting worse,” Carne and one bridge worker. told New Civil Engineer. “This The cracks were dismissed as highlights the fact that the being structurally insignificant on 13 and 14 March, according to an The cracks interactions with train operating companies must improve. update on the incident released by the National Transportation Safety were dismissed I think we have taken alliancing about as far as you can within the Board (NTSB). The NTSB also said it had as being structurally current industry structure. “Therefore more radical reform obtained photos of cracks from 10 insignificant on 13 is needed to create aligned teams March, but did not include these in working seamlessly across the the report. and 14 March industry in the interest of passengers.” 16 NEW CIVIL ENGINEER | SEPTEMBER 2018
38_PERI_AD_PRINT_NCE_FP_DIGI-CONSTRUCTION_265x210_10-AUG-18_AWO.indd 1 06/08/2018 09:48
The Edit TRANSPORT TRANSPORT BUSINESS H I G H S P E E D 2 FA C E S BRIDGE LIFT COULD KEY STAT PETER B R ET T B O S S L E G A L B AT T L E HOLD KEY TO VOW S N O JO B S OVER ‘BOTCHED E L E C T R I F I C AT I O N O F £60M WI L L B E LO S T AF T E R PROCUREMENT’ G R E AT W E S T E R N L I N E Turnover STA N TEC TAK E OVE R of Stantec, High Speed 2 (HS2) is facing a fresh A specialist engineer in bridge lifts has The boss of Peter Brett Associates legal battle over plans to buy £2.8bn backed calls to raise a Grade II listed which is (PBA), which is to be taken over by of trains. Spanish manufacturer masonry arch bridge that is causing taking over Canadian consultancy Stantec, has Talgo has begun legal action after problems for the electrification of the Peter Brett vowed there will be no job losses due what it claims was a “botched Great Western Main Line. ElevArch to the move. Stantec and PBA have procurement” process. Talgo was rail business development manager signed a letter of intent for the named as one of five shortlisted John Kennils said it would be possible takeover, which is set to be finalised rolling stock suppliers to build trains to avoid demolishing the bridge by in September. The amount Stantec for the high speed line. It decided to jacking it up to create the required paid for PBA, which in 2017 had a launch legal action after Spanish clearance and then reprofiling the £60M turnover and £10M profit before rival CAF was added to the shortlist road on either side. It comes after tax, has not been revealed. PBA following its own legal challenge. Network Rail lost its application to chairman Keith Mitchell told New CAF was reinstated in June following demolish the Steventon bridge and Civil Engineer there will be no job the announcement that Bombardier replace it with one with a higher losses as a result of the sale. He said: and Hitachi were joining forces in clearance. ElevArch carried out a “What we are saying to both staff and their bid to win the contract. Talgo successful trial in 2016 to lift a clients is that we are very much has now lodged a complaint with the 160-year-old single span, 220t focused on business as usual. That’s High Court, claiming that project masonry arch bridge 900mm using 10, very important from our point of promoter HS2 Ltd “failed to exercise 50t jacks. Kennils believes similiar view as we have projects ongoing, rational judgment” when allowing works could be carried out at the we need to make sure we are very CAF back into the competition. Steventon bridge site. focused on that.” STRUCTURES ARCHITECTS TO RULE OVER TOWER ROW The UK’s top architectural bodies tower in St Petersburg. Gorproject have been asked to rule on a design has reported the Edinburgh-based dispute over Europe’s tallest firm to the Royal Institute of British skyscraper. The design team at Architects and Royal Incorporation of Russian studio Gorproject has Architects in Scotland. However, accused Scottish firm Kettle Kettle denies any wrongdoing and Collective of stealing the authorship said they “do not have a dispute”, for the design of the Lakhta Centre when contacted by New Civil Engineer. BUILD ON US Infrastructure projects thrive from a collaborative approach, accurate programme planning and exceptional operational output. We have the experience, expertise and resources to ensure a successful delivery. www.bacsol.co.uk enquiries@bacsol.co.uk 01276 674940 18 NEW CIVIL ENGINEER | SEPTEMBER 2018
Mapegrout Gunite FSD is a one component, fast setting, high strength development, ready to use and multipurpose spray mortar. The fibre – reinforced cementitious mortar can be applied using either dry or wet spray technique for repairs, regulating and smoothing underground structures. Email UTT@mapei.co.uk or visit www.UTT.mapei.com for more information regarding the UTT team and how Mapei’s range of products can be used for your underground project. 0121 508 6970 | mapei.co.uk
Sir James Bevan The Interview BY EMILY ASHWELL Walking the walk with the Environment Agency utside the office of “What you should not do is force Environment Agency people to choose between protect- O chief executive Sir James Bevan, London is sweltering in a full ing the environment on the one hand and growth on the other, be- cause if you force people to choose, blown 31˚C heatwave. particularly in India but also in the It is a stark reminder of the chal- UK, they will choose growth over lenges the Agency is facing in terms the environment. The answer is to dealing with climate change. say you don’t have to choose, you For the former diplomat, who has can do both,” he says. seen “up close and personal” what And that’s where engineers come happens when the environment in. Yes, Bevan says the Agency is not looked after, the role of the needs technically skilled engineers, Agency in managing and regulating but it also needs engineers who can the environment is immeasurable. build relationships with communi- Before Bevan took up his post ties and work in partnership with in November 2015, he was British ment of contaminated land, flood stakeholders. This will enable its High Commissioner in India. He risk management, water quality and schemes to protect and manage describes living in a country that water resources. the environment, as well as having is home to a sixth of the world’s Bevan says the biggest insight he wider benefits. population as “life enhancing”. But gained from his time in India is the “We’re here to create a better he also saw the consequences of philosophy of sustainable growth, place. That’s what good engineers environmental damage, such as the which is embedded in the Environ- do and that’s what we try to do,” Bhopal disaster, where in 1984 toxic ment Agency’s founding law. he says. “And the better place is “ gases leaked from a chemical plant not just about the concrete and resulting in thousands of deaths and the steel, it’s about the feel and the causing disabilities among the third economy and the community and all What you generation of children descend- those other things that maybe don’t ed from the victims. Elsewhere get talked about at engineering pollution has left some of the River Ganges biologically dead. should not do is school, and that’s our philosophy: we want to be a placemaking organi- “They always say if you think education’s expensive, try igno- force people to choose sation in the broadest sense.” These future schemes might look rance. Well, if you think regulation’s expensive, try not doing it. That’s between protecting like typical large infrastructure projects, for example a new Thames what happens, that’s a lesson to regulate well,” he says. the environment on Barrier will be needed by 2070, but there will also be schemes which Regulating industry and waste is the one hand and use natural measures to control one of the Agency’s responsibilities. flooding such as leaky dams. But Others include overseeing treat- growth on the other more schemes will combine both, 20 NEW CIVIL ENGINEER | SEPTEMBER 2018
Medmerry, in West Sussex, was England’s first managed realignment of the open coast. It involved the construction of a 7km long, 3m to 4m high earth bund, but it also created wetlands which are now a bird sanctuary. “ such as in Pickering, Yorkshire, where natural flood management such as What gets ment Agency staff out of bed is the life-changing effects we can have leaky dams and the planting of 40,000 trees, combined with installation of a KEY FACTS me and when we can give people a much bet- ter sense of security by knowing they flood storage reservoir upstream has slowed peak river flow by 15-20%. £2.6bn Environment Agency can go to sleep and not worry about flooding, and knowing we don’t just “The future is more upstream man- Value of staff out of bed is the protect them against floods but help life-changing effects agement, some concrete and steel, growth, placemaking and the wider and then also being prepared to ac- Environment benefits that come from being better Agency’s cept we will never be able to prevent all flooding,” says Bevan. we can have protected.” These wider benefits include six-year flood “Climate change is likely to drive enabling communities to get decent more flooding, and therefore the rest protection insurance and ensuring that flood risk of the answer is about making sure programme What we want from ourselves and our does not deter investors. our cities and communities are more suppliers is that we bear down as far Bevan says climate change is the resilient when it happens.” as possible, as close to zero use of biggest threat to the UK in the long The Environment Agency is current- £300M single use plastic,” he says. term and the Agency works with ly procuring a £1.5bn flood defence The framework will help deliver the government at all levels to shape the Value of framework, which includes one lot Agency’s £2.6bn six-year programme response, from the 25 Year Environ- worth £300M for professional services professional to better protect 300,000 homes and ment Plan launched by prime minister including design and consultancy, and services work businesses from flooding. It is the im- Theresa May in January, to staff one lot worth up to £1.2bn for pro- pact this work can have on people’s embedded in major projects such as gramme delivery. The new commer- being let lives that Bevan says gets him, and High Speed 2. cial arrangements should be in place under the his staff, out of bed in the morning. Bevan says he took the helm of an by July next year. He sees the Agency as becoming innovative, collaborative, delivery Agency’s As the organisation tries to “walk the “fourth blue light” in the way it focused Environment Agency where the walk” in terms of sustainability, flood defence responds to incidents. engineering is part of its DNA. He it will also ask contractors to do the framework The Cumbria floods in December wants to see more of this, with the same, through more efficient use of 2015 hit when Bevan was just six days body becoming “pacier”. sustainable materials, but also includ- into the job. According to the Met Of- Bevan wants the Agency and its ing ditching single use plastic cups in fice, a new record for two consecutive engineering to be known and loved, staff kitchens – something which Bev- rain days was set when 405mm fell at because its impact on our future is an has had a hands-on role in doing Thirlmere. crucial. since the Environment Agency moved “I went up there and stood in the “Unless we both manage down into its Westminster office. homes of people whose lives had demand and manage up supply, “When we got into this building… been wrecked by flooding. It’s not just including in major new infrastructure we had a nice little kitchen, but it also a physical thing that happens, it’s an investment, in 20 or 30 years’ time had a container full of plastic cups, emotional thing and it can have quite the lines between supply and demand so we ripped it off the wall. That’s an severe long-term consequences,” says will cross and there won’t be enough example of us trying to walk the walk. Bevan. “What gets me and Environ- water for the country,” he concludes. S E P T E M B E R 2 018 | NEW CIVIL ENGINEER 21
system that ensures complex buildings are built and maintained Your View so that they are safe for people to live in for many years after the original construction”. Indeed Dame Hackitt uses the word “system” 301 times and refers to the need for “a holistic or ‘whole system’ approach to new construction and LET TERS TO THE EDITOR refurbishments”. AND COMMENTS ONLINE David Blockley, Emeritus Professor University of Bristol, d.blockley@ bristol.ac.uk ICE support of new build. It’s the kind of STRUCTURES OUT OF TOUCH sexy stuff that guys in black ties can MISSED ASPIRATIONS INSTITUTION? @ talk about. Again, I can’t relate to it. It seems nonsensical to me to build new things when you can’t even Although they read as unnecessary The recent controversy about the look after what you already have. and mean-spirited, John Roberts’ ICE not consulting adequately with It simply increases the nation’s comments about the beautiful members about governance changes volume of decaying stock. competition-winning design of the left me somewhat underwhelmed. If all this sounds like the whinging Tintagel Bridge do raise a very If, like me, you work in the north Read more of someone unhappy in his job, it important point (Your View, last of England as a municipal engineer letters at isn’t. I love my job, I’ve thoroughly primarily involved in maintenance www.newcivil enjoyed my career and I have plenty schemes, the Institution possibly engineer.com of positive things to be getting on never felt much like your Institution with. I simply make the point that anyway. perhaps I love my work despite the I view the ICE as a networking ICE, rather than because of it and club, seemingly run from afar by that it’ll take rather more than a a collection of consultants and bit of consultation to sort out the contractors who meet at a very disconnect with me and any other plush office at Great George Street members like me. that I’ve only had occasion to visit Jon Tuson (M) jon.tuson@bolton. about three times in 30 years. I see a gov.uk lot of pictures of engineers at black tie events in London that seem PROFESSION completely at odds with the day to day of my work. I don’t begrudge SYSTEM OF THOUGHT people these events but, on a Tintagel: Architect’s dream? personal level, I simply can’t relate Mark Hansford rightly asks what our to them. biggest infrastructure challenges month). There are far too many Moreover, the argument that the are (Comment, last month). infrastructure projects in the UK ICE is a learned organisation that May I suggest one that he misses – including many major projects benefits all its members loses a – but which is highlighted on page – which are granted planning certain amount of credibility when 34 of the same issue in an article permission with insufficient detail its training arm, Thomas Telford Ltd, by Jackie Whitelaw – joined-up to be sure of the quality of the rarely organises courses north of thinking. built product, or where the quality Birmingham. It certainly offers more She quotes Transport for the West promised at planning stage is benefits to engineers who live in the Midlands’ Mike Waters as saying “we subsequently hugely eroded, and South East rather than those who have to change behaviours, hearts the public is left short-changed or live in the North. and minds”. But this applies not misled by clients and designers. I look at the figures quoted for only to the travelling public but The quality of infrastructure schemes like High Speed 2 (HS2) also ourselves as infrastructure built in the UK would be hugely and cringe. The £58bn for HS2 professionals and the way we think improved if the planning system compares with under £600,000 The Editor, about what we do. required projects to be as well that the government provided New Civil The swanky word for joined- designed as the Tintagel Bridge. In this year to maintain the 360-plus Engineer, up thinking is systems-thinking. turn, this would reward bold clients highway structures in Bolton. The This kind of mind-set is being and inspired designers, like English Telephone government is not awash with cash advocated by the Royal Academy Heritage, Ney & Partners and House, and cannot fund infrastructure of Engineering as well as being an William Matthews Associates, with maintenance and major capital 69-77 Paul important part of our reaction to the integrity and determination to projects like HS2, so choices have Street, London, Grenfell as stated by Dame Hackitt. build high-quality infrastructure to be made. The ICE, verbalised EC2A 4NQ In her report she writes “A cultural with lasting value. through New Civil Engineer, seems Email: nceedit@ and behavioural change... is now Martin Knight, Knight Architects to have come down firmly in emap.com required... to deliver an effective m.knight@knightarchitects.co.uk 22 NEW CIVIL ENGINEER | SEPTEMBER 2018
MAIN POINT ICE GOVERNANCE IN THE SPOTLIGHT YOUR VIEWS AND OPINIONS The ICE held a Special General meeting on 31 July in response to concerns about the ballot on the Institution’s corporate governance structure held earlier that month. The majority of the more than 200 people at the meeting voted for a new ballot and voted to censure the ICE for its lack of consultation with the membership about the proposed governance reforms. I attended the Special General Meeting at the ICE on 31 July the time of the membership ballot. Even after two hours of as a supporter of the resolutions and was not persuaded discussion I felt that we had barely begun to cover the impact by the arguments made against them. Several of those who of the changes. spoke against the resolutions said that to try to overturn the At the moment, the plans seem to me to amount to a results of the governance ballot would make the ICE appear bonfire of the ICE’s current rules and traditions, without clear to the outside world to be divided and may damage our justification. reputation, as if those could ever be reasons for not doing Personally, I believe that some trustees need what is right. to be directly elected by the members (the current All the resolutions were passed and the Council plan allows for three to be selected by some now has a lot of work to do. This situation could unknown process from the elected Council, have been avoided if the Council had been and a further nine to be appointed, so elected bold enough to postpone the governance representatives can always be outvoted). ballot when the SGM was requisitioned in Stephen King, Posted online on article early June instead of trying headed “ICE members vote for new ballot on to push their proposals through using a governance” somewhat disingenuous two-page spread of “FAQs” in July’s New Civil Engineer I voted against the SGM resolutions as I agree and on the ICE’s website. with the governance changes – they embody Gordon Heath (M retd), Pinner, Middlesex good practice recommended by government. The requisitioners want more consultation. I was one of those who voted for (most) of the Why? Don’t we trust our elected Council? Do we Council’s suggestions during the ballot, but I became want to be governed by referenda after Brexit? more and more concerned as additional details emerged about It’s good to have checks and balances – particularly from the plans. those of mature years. In the end I attended the SGM, and as a result of listening But whatever the merits of more consultation, this egregious to the arguments I decided to vote in favour of the resolutions challenge to Council is surely an unnecessary distraction being discussed (ie against the Council’s position). from the ICE’s proper business of assuring the nation’s There were very wide-ranging changes discussed or hinted infrastructure. at in the SGM that I had been completely unaware of at Mike Napier FICE STRUCTURES stop them trying. problems of access to the site have TINTAGEL TROUBLES It seems that one of the reasons been well-promulgated. So, how English Heritage selected this as the about this? The deck is separated at Well, what a kerfuffle over a little winning design is that it contains the centre – giving English Heritage footbridge! I refer, of course, to this unique and desirable feature of the opportunity for a “gap” – but the controversy surrounding the a “gap” between the mainland side structurally, each side leans against proposed Tintagel Castle footbridge and the island side, representing the other (pinned joint), with a slight (The Edit, last month), to be a transition from one space to arch at the centre for the lowest constructed under the auspices of another. However, if the real concern design temperature. This amounts English Heritage, to whom I have is that of visual intrusion, the most to a continuous structure, affording already written with concerns about slender design possible is surely slenderness. The pedestrian deck questions it might ask its designers. the right solution – afforded by a could show a “gap”, but the main I agree with the majority of John continuous structure, but disguised structure would be effectively Roberts’s letter “Flawed Design as “two 30m cantilevers reaching out continuous. Competitions” in the same issue, and and almost touching in the middle” Or is this engineering idea just too in particular with his observation that (English Heritage blurb). crazy for the architects? architects should never pretend to I’m no bridge designer, but I am Mike Franklin (F, retired) be engineers. Of course, that will not a construction engineer, and the mike_franklin@usa.net S E P T E M B E R 2 018 | NEW CIVIL ENGINEER 23