MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
ADANI GROUP – THE PROMOTERS

ADANI ENTERPRISES LIMITED           INFRASTRUCTURE GROUP

        Adani Wilmar Ltd.                       Mundra Port & SEZ
        Adani Power
                                                Dahej SCPT
        Adani Real Estate
                                                Dholera Port & SEZ
        Adani Agrifresh &                       Adani Logistics Ltd.
        Agrilogistics
                                                Gujarat Adani Energy
                                                Ltd
                                                Inland Conware Pvt
                                                Ltd
           Group Turnover is US $ 3.6 billion

                                                                    2
MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
MUNDRA PORT & SPECIAL ECONOMIC ZONE

Our Vision

 To evolve as an international calibre business port on the
 foundations of technological excellence, state-of-the-art
 infrastructure and logistics and a competitive customer
 focus.

Our Mission

 To develop, assimilate and manage knowledge; to apply
 the acquired expertise across the globe for the benefit of
 stakeholders; to do so profitably.

                                                              3
MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
Mundra – Focussed on Growth
Second Container Terminal

  Two berths having a total quay length of 632 meters
  Capable of berthing 8000+ TEU containers vessels
   Estimated terminal handling capacity of 0.9 million Teus
   4 RMQCs & 12 RTGs from the 1st year of commissioning
   Huge backup area for Container Yard & Rail Terminal

                                                              4
MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
Dry/Break-Bulk
               Liquid

                                         CT 2

                                                T2

Ro-Ro berths

                                         MPT
                                                     5
MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
Mundra Coal Terminal
   A View from the Sea

                         6
MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
Unloading facilities

Coal berth has 2 Mobile Harbor cranes
(Gottwald) with a handling capacity of 750
TPH each
                                             7
MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
The Conveyor

Mechanized Handling System
3.5 kms long conveyor system with a
import capacity of 1500 TPH and export
capacity of 1000 TPH
                                         8
MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
Mundra Coal Yard

A Coal Stackyard with a capacity of about
400,000 Metric Tonnes
                                            9
MUNDRA PORT & SPECIAL ECONOMIC ZONE - Natural Gateway to the Hinterland 11
MUNDRA PORT

                                    INDIA’S LARGEST PRIVATE SECTOR PORT

NATURAL DEEP DEPTH OF 17.5 METERS

                CLOSEST PORT TO THE NORTHERN AND WESTERN HINTERLAND

INDIA’S FIRST PORT TO DEVELOP ITS OWN PRIVATE RAILWAY LINE

              INDIA’S FIRST NOTIFIED MULTI-PRODUCT SPECIAL ECONOMIC ZONE

                                                                          10
But even this is not enough for our
future needs :
Adani 2600 MW
Tata 4000 MW Power Plants

                                      11
Presenting
Mundra Bulk Terminal, Wandh

 The biggest Coal Handling
   Terminal in the World

                             12
Planned capacities

• Can handle upto 40 Million Tonnes of Coal
  per year
• Estimated requirement for the Adani and
  TATA Power Plants is 26 Million Tonnes
• Marine facilities planned to berth full
  Capesize vessels

                                            13
JETTY / UNLOADING FACILITY

Type of Jetty     :          ‘L’ Type
                      (‘T’ type for Phase-II)
Berth Length      : 636 Meters.
Berth Width           : 26 Meters.
Available Draft   : 21 Meters.
Max. Size of Ship : 2,00,000 DWT
Type of Unloader : Grab Bucket

No.of Unloader    : 6 Nos (Phase -1)
Cap of Unloader : 2000 TPH Each
                  (Rated)
Conveyor Cap      : 6000 TPH x 2 Nos
                    (Rated)
Unloading Cap     : 80000 TPD / Berth.
                                                   14
STORAGE YARD

This consists of Dredge sand filling of yard, GSB layer, Ground
improvement, Yard drainages, Stacker rail foundations, Rails & fixtures,
Storm anchors and wind shield.

Dimension of Yard    :   1500 x 600 Mtr.
Storage Capacity     :   24 Lakh CUM
Stacking Height      :   8 to 10 Mtr.
No. of track         :   4 Nos + 1 No. *
No. of Yards         :   8 Nos + 2 Nos *
No.of Eqpts         :    6 Nos + 2 Nos *
Type of Eqpts        :   Stacker cum
                         Reclaimers

*+ for Phase -II
                                                                     15
STORAGE YARD WINDSHIELD

To contain dust nuisance and spread
of coal cargo.
Wind shield / fence will be
provided all around the stock yard
area.

Tentative Height of wind shield is about
18 to 20 Mtr.

Multi Perforated transparent sheets
are provided to break the velocity of
wind and to create eco - friendly
environment.

                                           16
SHIP UNLOADER

Type of Unloader   : Grab Bucket

No.of Unloaders    : 6 Nos

Cap of Unloadesr   : 2000 TPH each

Ship size          : Capesize

                                         17
CONVEYORS, FOUNDATIONS AND STRUCTURES.

• Total length of conveyor 35 Kms. includes,
    - 6000 TPH conveyor of length 27 Kms with belt width 2200mm.
    - 4000 TPH conveyor of length 8 Kms. with belt width 1800mm.
•   Coal will be conveyed from jetty to the stack yard by two streams of
    Conveyor 6000 TPH each.
•   Stacking will be carried out in the yard @ 6000 TPH.
•   Reclaiming will be carried out @ 4000 TPH.
•   Single gallery with two conveyor streams (one working & one stand
    by) will be provided to cater the need of UMPP, APPL, Trading and
    Steel plant.

                                                                       18
STACKER / RECLAIMER

Stacking Cap          : 6000 TPH

Reclaiming Capacity   : 4000 TPH

                                   19
RAPID WAGON LOADING SYSTEM

• Time require to load
 the rake : 60 to 90
 minutes

                                       20
DUST SUPPRESSION SYSTEM

State-of-Art Dust Suppression system will be provided at the stockpiles
and at the Discharge point as well as Feed point of conveyors in the
transfer towers to control the dust generated during loading & unloading
Operations.

                                                                     21
INFRASTRUCTURE FACILITIES

Green Belt Development – A commitment to the Environment

                                                           22
MUNDRA Port & Coal Terminal
Committed to Environmental Excellence

                                        23
Thank You