Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...

Page created by Manuel Mcgee
 
CONTINUE READING
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
Morley Ellenbrook Line (MEL)
- Project Definition Plan (PDP) Flooding
and Hydrology Report

Public Transport Authority Ÿ Malaga to Ellenbrook Rail Works   N
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
METRONET
                                                  Morley Ellenbrook Line (MEL) -
                                                  Project Definition Plan (PDP)
                                                  Flooding and Hydrology Report
                                                  MEL-MNO-ARUP-DR-RPT-0001

                                                  D – FINAL | 28 February 2020

This report takes into account the particular
instructions and requirements of our client.
It is not intended for and should not be relied
upon by any third party and no responsibility
is undertaken to any third party.

Job number 267138-00

Arup Pty Ltd ABN 18 000 966 165

Arup
Level 14 Exchange Tower
2 The Esplanade
Perth WA 6000
PO Box 5750
St Georges Terrace
Perth WA 6831
Australia
www.arup.com
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
Document verification

 Job title                                    Morley Ellenbrook Line (MEL) - Project Definition Plan                       Job number
                                              (PDP)                                                                        267138-00
 Document title                               Flooding and Hydrology Report                                                File reference

 Document ref                                 MEL-MNO-ARUP-DR-RPT-0001
 Revision                 Date                Filename                 MEL-MNO-ARUP-DR-RPT-0001
 A-Draft                  11 Sept             Description              DRAFT 50% Design Confirmation Stage
                          2019
                                                                       Prepared by            Checked by                   Approved by
                                                                                              Reviewer -Greg
                                                                                              Rogencamp
                                                                                              P1 manager - Julia
                                                                                              Summers
                                                                       SRE-Matt                                            SEM - Sunil
                                              Name                                            P2 & P3 manager -
                                                                       Stovold                                             Bhogal
                                                                                              Lyndsay Hammond
                                                                                              P4 & P5 manager - Alistair
                                                                                              Avern-Taplin
                                                                                              APM - Zoe Wilks
                                              Signature

 B                        22     Filename                              MEL-MNO-ARUP-DR-RPT-0001
                          Novemb Description                           WIP- 100% Design confirmation stage
                          er
                                                                       Prepared by            Checked by                   Approved by
                                                                                              Discipline Reviewer –
                                                                                              Greg Rogencamp
                                                                       Steven Voss                                         SEM - Sunil
                                              Name
                                                                                                                           Bhogal
                                                                                              Hong Vu

                                              Signature

 C- FINAL                 18 Dec              Filename                 MEL-MNO-ARUP-DR-RPT-0001
                          2019                Description              Final PDP Issue
                                                                       Prepared by            Checked by                   Approved by

MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup
C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
Discipline Reviewer –
                                                                                                Greg Rogencamp

                                                                                                P2 & P3 manager -                 SEM - Sunil
                                              Name                     SSteven Voss             Lyndsay Hammond                   Bhogal

                                                                                                P4 & P5 manager - Alistair
                                                                                                Avern-Taplin

                                              Signature

 D- FINAL                 28 Feb              Filename                 MEL-MNO-ARUP-DR-RPT-0001
                          2020                Description              Final PDP Issue – Updated to incorporate final PTA/
                                                                       METRONET comments and new inputs provided for Morley,
                                                                       Noranda and Whiteman Park precincts (as applicable) which
                                                                       were agreed with METRONET after the 100% PDP submission.

                                                                       Prepared by              Checked by                        Approved by
                                                                                                P2 & P3 manager -
                                                                       SRE-Matt                 Lyndsay Hammond                   SEM - Sunil
                                              Name
                                                                       Stovold                                                    Bhogal
                                                                                                APM – Zoe Wilks

                                              Signature

                                                                                      Issue Document verification with document                 

MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup
C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Contents
                                                                                                                                             Page

           1                Glossary                                                                                                            1

           2                Project description                                                                                                 2
                            2.1                Summary                                                                                          2
                            2.2                Status of Project Definition Plan                                                                4

           3                Scope development                                                                                                   7
                            3.1                Scope of Work                                                                                    7
                            3.2                Requirements                                                                                     8

           4                Basis of Design                                                                                                     9
                            4.1                Standards and Codes                                                                             9
                            4.2                Standard Units                                                                                  9
                            4.3                Design criteria                                                                                 9
                            4.4                Design life                                                                                    10
                            4.5                Deliverables                                                                                   10

           5                Design                                                                                                            11
                            5.1                Design Development                                                                             11
                            5.2                Design Risks, Assumptions, Issues, Dependencies,
                                               Opportunity and Constraints                                                                    32
                            5.3                Non-compliances                                                                                32
                            5.4                Third party verification                                                                       32
                            5.5                Constructability                                                                               32

           Appendices

           Appendix A –Drawings/ sketches

           Appendix B – RAATM

           Appendix C - SAR

           Appendix D – RAIDOC

           Appendix E – IDC Certificate

           Appendix F – IDR Closeout Record Log/ DRN and IDR register

           Appendix G Existing case

           Appendix H – Design case

           Appendix I – Impact maps

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           1                     Glossary
           Table 1 - Glossary
             Abbreviation                                       Description
             AMS                                                Arup’s Management System
             AEP                                                Annual Exceedance Probability
             ARI                                                Average Recurrence Interval
             BoD                                                Basis of Design
             BIM                                                Building Information Modelling
             CPE                                                Coordinating Project Engineer
             CAD                                                Computer Aided Drawing
             DRN                                                Document Review Notice
             DoT                                                Department of Transport
             DM                                                 Discipline Manager
             ELUP                                               Engineering and Land-Use Planning
             EMP                                                Engineering Management Plan
             GIS                                                Geographic Information System
             HV                                                 High Voltage
             IA                                                 Infrastructure Australia
             IDC                                                Interdisciplinary design checks
             IDR                                                Interdisciplinary Design Review
             LDC                                                Lead Design Consultant
             LV                                                 Low Voltage
             MRWA                                               Main Roads Western Australia
             MPU                                                Major Project Unit
             MEP                                                Mechanical, Electrical and Plumbing
             MEL                                                Morley-Ellenbrook Line
             N&I                                                Network and Infrastructure
             ONRSR                                              Office of the National Rail Safety Regulator
             PD                                                 Project Director
             PDP                                                Project Definition Plan
             PEs                                                Project Engineers
             PRS                                                Project Requirement Specification
             PTA                                                Public Transport Authority
             QA                                                 Quality Assurance
             RAIDOC                                             Risks, Assumptions, Issues, Dependencies, Opportunities,
                                                                Constraints
             RFI                                                Request for Information
             RAATM                                              Requirements analysis, allocation and traceability matrix
             SAR                                                Safety Assurance Report
             SiD                                                Safety in Design
             SMP                                                Safety Management Plan
             SER                                                Scope and Engineering Review
             SCADA                                              Supervisory Control and Data Acquisition
             SEM                                                Suppliers Engineering Manager
             SRE                                                Suppliers Responsible Engineers
             SESA                                               Systems Engineering and Safety Assurance
             SEMP                                               Systems Engineering Management Plan

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 1
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           2                     Project description

           2.1                   Summary
           The proposed Morley Ellenbrook Line (MEL) involves six integrated station
           precincts at Bayswater, Morley, Noranda, Malaga, Whiteman Park and Ellenbrook
           (and future-proofing for an additional station at Bennett Springs) and 21km of
           new track spurring from the existing Midland Line providing improved
           connections for existing and new communities in Perth’s northeast.

           Figure 1 – MEL project extents
           Arup, as Lead Design Consultant (LDC), is responsible for the preparation of a
           design that will allow the development of the Project Definition Plan (PDP). The
           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 2
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           design task has been divided into five geographical package areas and one site-
           wide rail systems package as displayed in Figure 1.

           The proposed rail line extends from the existing Bayswater Station on the
           Midland Line, north to Ellenbrook Town Centre. The design encompasses the rail
           stations and surrounding precincts of Bayswater (Package 1), Morley (Package 2),
           Noranda (Package 2b), Malaga (Package 3), Whiteman Park (Package 4) and
           Ellenbrook (Package 5) along with space-proofing for a station at Bennett
           Springs. In addition to station precincts, the design incorporates site wide civil and
           rail works within the project corridor and Tonkin Highway median. Major
           structural elements of the proposed rail alignment include grade separated
           structures (ramps, viaducts, dives, tunnels and new grade separated spans over and
           under the rail corridor).

           The purpose of the PDP design is to identify the site constraints, design solutions
           and clear direction for the project with measurable inputs for the Quantity
           Surveyor’s cost estimation. The PDP will be produced for, and in collaboration
           with, PTA/ METRONET. The design will deliver on or enable METRONET to
           meet its key requirements to:
                 Demonstrate sufficient survey and design evidence to confirm the chosen
                  route option will achieve the Project Requirements Specifications (PRS)
                  requirements, integration across disciplines, constructability, maintenance and
                  future proofing
                 Establish key design interfaces with proposed and existing features, design
                  constraints limitations and efficiencies
                 Provide project boundaries and definition to progress the Railway Enabling
                  Act, environmental impacts, land purchases and other key enabling activities.

           The following disciplines below have collaborated throughout the design process:

                 Rail Systems – Permanent Way, Overhead Line Equipment, Signalling,
                  Earthing and Bonding, High Voltage / Low Voltage / Traction Power,
                  Communications and Operational Technology, Main Cable Route and Transit
                  Space
                 Civils – Earthworks, Utilities, Drainage, Flooding and Hydrology, Highways,
                  Civil Structures and Geotechnical, including Foundations
                 Stations and precincts– Architecture, Transport Planning, Urban Design,
                  Station Structures, Mechanical, Electrical, Hydraulic station Fire Services
                 Specialist – Systems and Safety Assurance, Fire and Life Safety, Tunnel
                  Ventilation, Digital (GIS, BIM, Visualisation, 3D Modelling) and CAD.
           The PDP design will document the development of the multi-disciplinary
           engineering design and systems design for each function and/or interface to
           demonstrate that the proposed solution is consistent with the functional and
           performance requirements of METRONET.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 3
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
Morley Ellenbrook Line MEL - Project Definition Plan PDP Flooding and Hydrology Report - Project Definition Plan PDP ...
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           2.2                   Status of Project Definition Plan
           The MEL Draft PDP (Design Confirmation stage) was issued in August 2019 to
           METRONET/ PTA for review. The design produced for the December 2019 Final
           PDP Issue for each station precinct incorporated the first round of comments but
           was at various stages of development for each Package given there were some
           areas awaiting stakeholder and community feedback. In January 2020, final
           comments from PTA, METRONET and Main Roads WA were received and
           incorporated into the design.

           The below section seeks to provide clarity on the level of design as of February
           2020 for each discipline and package. This represents the final update to the MEL
           PDP design by Arup and its sub-consultants and as noted any further areas where
           design will need to progressed will be undertaken post PDP design by others.

           Package 1 – Baywater Station and Tonkin Tie-in
           A design for Package 1 – Baywater Station to Tonkin Entry was produced for
           MEL Draft PDP (Design Confirmation stage) and issued in August 2019. This
           allowed for the upgraded Bayswater Station and MEL tie-in to the Bayswater
           Station through to the Tonkin Entry and focussed on the area East of the Baywater
           platforms. An additional MEL Draft PDP (Design Confirmation stage) for the
           Baywater Turnback west of the platforms was issued on 29 October 2019.

           During the period between Design Confirmation and Final PDP Issue the
           Baywater Station and Turnback (BST) project progressed to tender design as a
           separate process. The shortlisted proponents were issued the Design Confirmation
           packages of MEL and a summary of risks and opportunities considered by the
           METRONET team for inclusion in that project. Arup has therefore not progressed
           any of the station or MEL tie-in to the Bayswater turnback design beyond Design
           Confirmation issue and as such these elements have not been re-issued for Final
           PDP issue.

           Documentation for Package 1 of the Final PDP Issue covers the line-wide
           elements east of the station to the Tonkin Highway entry.

           Package 2 – Morley Station and Tonkin Highway
           A design for Package 2 – Morley Station and Tonkin Highway was produced for
           MEL Draft PDP (Design Confirmation stage) and issued in August 2019. The
           design initially assumed that the Morley Bus Bridge would be installed adjacent to
           the in-situ Broun Avenue Bridge. During the intervening period between Design
           Confirmation Stage and FINAL PDP a decision was made by key stakeholders
           that Broun Avenue bridge would be demolished and replaced with an integrated
           Bus Bridge and Highway Bridge, the new Broun Avenue Bridge. This new design
           is reflected in the FINAL PDP Design Issue. In addition, minor comments were
           then received by stakeholders in January 2020 which were incorporated into the
           FINAL PDP submission in February 2020.

           Following the submission of the Final PDP Issue design in December 2019, a new
           Morley Station and precinct layout was selected by METRONET following

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 4
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           further consultation with stakeholders. A civil general arrangement (GA) plan
           [MEL-MNO-ARUP-CI-2150] and highways plan and profile [MEL-MNO-
           ARUP-HW-DRG-2225 and MEL-MNO-ARUP-HW-DRG-2226] only have been
           developed for this updated design. However, all other discipline design areas,
           drawings and requirements have not been updated to correspond with this new
           GA.

           The commentary contained within this report corresponds with the previous GA
           plan [MEL-MNO-ARUP-CI-2110]. The design will need be updated by others to
           reflect the new GA following PDP phase at the next stage of design (post PDP
           design).

           Package 2B – Noranda Station
           As of December 2019, the design development of Noranda station was on hold
           awaiting the outcomes of the community consultation in this area on the potential
           PnR layout. Therefore, no design for Noranda Station was undertaken before this
           time and the DRAFT and FINAL MEL PDP deliverables issued in August 2019
           and December 2019 do not contain station or precinct design drawings for this
           station.

           Following METRONET confirmation to proceed with the preferred layout, the
           design for Noranda station progressed in January 2020. It should be noted that
           during January and February 2020, only a preliminary design for Noranda station
           and precinct has been undertaken during PDP phase including architectural, civil
           engineering, highways, fire engineering, transport planning and urban design. The
           design will need be updated and progressed by others to reflect the proposed
           general arrangement (GA) [MEL-MNO-ARUP-CI-DRG-2210] and station design
           following PDP phase at the next stage of design (post PDP design).

           The design for Noranda Station and precinct is reflected in the FINAL PDP
           deliverables issued in February 2020.

           Package 3 – Malaga Station and Horse Swamp
           A design for Package 3 – Malaga Station and Horse Swamp was produced for
           MEL Draft PDP (Design Confirmation stage) and issued in August 2019. This
           design was subsequently updated following comments from stakeholders and
           issued as FINAL PDP in December 2019. Minor comments were then received by
           stakeholders in January 2020 which were incorporated into the FINAL PDP
           submission in February 2020.

           Package 4 – Whiteman Park Station and New Lord Street
           A design for Package 4 – Whiteman Park Station and New Lord Street was
           produced for MEL Draft PDP (Design Confirmation stage) and issued in August
           2019. This design was subsequently updated following comments from
           stakeholders and issued as FINAL PDP in December 2019. It should be noted that
           the submission in December 2019 did not include design for the precinct as this
           area was on hold awaiting final comments and endorsement from METRONET.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 5
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           The main features within this package have been retained with the key changes
           between Design Confirmation stage and Final PDP Stage including the following
           components:
               Addition of swales in parking bays (in line with WSUD principles)
               Retention of existing buildings in Whiteman Park
               Change bus interchange footprint (to “V” shape)
               Incorporation of a stream / swale in the car park matching an existing ‘tree
                 line’.

           Minor comments were received by stakeholders in January 2020 regarding the
           station and wider package area which were incorporated into the FINAL PDP
           submission in February 2020.

           Package 5 – Ellenbrook Station
           A design for Package 5 – Ellenbrook Station was produced for MEL Draft PDP
           (Design Confirmation stage) and issued in August 2019. This design was
           subsequently updated following comments from stakeholders and issued as
           FINAL PDP in December 2019. Minor comments were then received by
           stakeholders in January 2020 which were incorporated into the FINAL PDP
           submission in February 2020.

           No significant changes to the Ellenbrook Precinct have been made between
           Design Confirmation Stage at Final PDP Issue, however, an alternative GA
           [MEL-MNO-ARUP-CI-DRG-5150] has been produced to show where additional
           parking may be added in the future.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 6
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           3                     Scope development

           3.1                   Scope of Work
           The flood assessment is confined to Package 3 area only where the greatest flood
           risk to the proposed rail alignment was determined based on the hydrologic
           complexity of the Bennett Brook rail crossing and upstream Horse Swamp area.
           Elsewhere across the project, flood risk is considered to be low and will be
           managed through conventional drainage design assessment means; such as
           through the use of swale/basin infiltration and piped network conveyance
           mechanisms.

           3.1.1                 Package 0
           Not included in the Flooding and Hydrology scope.

           3.1.2                 Package 1
           Not included in the Flooding and Hydrology scope.

           3.1.3                 Package 2
           Not included in the Flooding and Hydrology scope.

           3.1.4                 Package 3
           The scope of Flooding and Hydrology within Package Area 3 is to:
           •      Assess the flood risk to both rail and nearby residential development within
                  the vicinity of Horse Swamp and Bennett Brook
           •      Undertake flood modelling to assess rail/road flood immunity and the flood
                  impact on adjacent properties to site works at the Bennett Brook Crossing and
                  at the pedestrian underpass at Whiteman Park Station.
           The indicative scope boundary is shown below within the blue polygon.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 7
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 2 - Indicative flood study boundary

           3.2                   Requirements
           Following discussions with METRONET and City of Swan, it was identified that
           previous endorsements by Department of Water (2015) supported additional flows
           to be directed into Horse Swamp as a means for addressing reports that it has been
           noticeably dry over previous years. Because of this, up to 3.3 m3/s of surface
           runoff has been reportedly allowed to be conveyed to Horse Swamp from
           developed areas to the east of New Lord Street during the 1% AEP event. This
           flow has, therefore, been accounted for in the hydrologic and hydraulic model
           development.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 8
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           4                     Basis of Design

           4.1                   Standards and Codes
           The surface water assessment, drainage design and protection works must
           conform with sound hydrological and hydraulic practices and must conform with
           the documents in Table 2:
           Table 2 – Precedence of reference documents for flooding and hydrology

               Precedence                          Title
               A                                   Australian Rainfall and Runoff: A Guide to Flood Estimation (2019)
               B                                   Department of Water and Environmental Regulation, Stormwater
                                                   Management Manual for Western Australia (2007)
               C                                   Department of Water and Environmental Regulation, Decision Process for
                                                   Stormwater Management in WA (2009)
               D                                   Austroads’ Guide to Road Design – Parts 5, 5A and 5B
               E                                   Institution of Engineers Australia, Australian Rainfall and Runoff: A
                                                   Guide to Flood Estimation. Volumes 1 and 2. (1998)
               F                                   Austroads Waterway Design – A Guide to the Hydraulic Design of
                                                   Bridges, Culverts and Floodways (1994)
               G                                   Subsurface Drainage of Road Structures. RJ Gerke, Australian Road
                                                   Research Board Special Report SR35 (1987)
               H                                   NAASRA Guide to the Design of Road Surface Drainage (1986)

           4.1.1                 Gaps in Standards/Code of Practice
           NA

           4.2                   Standard Units
           The International System of Units (SI units) will be used throughout.
           All design levels will be to Australian Height Datum (AHD) unless otherwise
           noted.
           All plan coordinates will be to Perth Coastal Grid PCG94 coordinates, based on
           the Geocentric Datum of Australia 1994 (GDA94).

           4.3                   Design criteria
           As a minimum the design must consider the following:
                  An assessment of surface water hydrology must be undertaken as part of the
                   assessment
                  Upstream flooding effects to the proposed bridge over Bennett Brook are to
                   have no adverse impacts to existing properties

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                               Page 9
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

                 The proposed bridge over Bennett Brook is to be designed to ensure a
                  minimum 500 mm freeboard to the bridge soffit during the 1% AEP
                 The railway formation and corridor must be drained to prevent scouring,
                  washaways or saturation.

           4.4                   Design life
           NA

           4.5                   Deliverables
           Table 3 lists the deliverables for the final PDP issue design stage.
           Table 3 – Final PDP design stage deliverables

               Doc Number                                            Doc Title

               OVERALL REPORT
               MEL-MNO-ARUP-DR-RPT-                                  MEL PDP PHASE – FLOODING AND HYDROLOGY
               0001                                                  REPORT

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 10
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           5                     Design

           5.1                   Design Development
           In order to quantify the impacts of the proposed design on catchment flooding,
           hydrologic and hydraulic analyses were undertaken for pre and post construction
           conditions. The following sections describe the approach which was undertaken to
           complete the flood impact assessment as well as summarising model development
           and key model results.

           5.1.1                 Catchment Overview
           The Bennett Brook catchment is a tributary of the Swan River and has a
           catchment area of approximately 173km2 (delineated to the Reid Highway /
           Bennett Brook Crossing). The extent of the catchment is shown in Figure 5,
           located in section 5.1.3.
           The proposed location where the proposed rail alignment will cross the Bennett
           Brook is just over 5km upstream of the Bennett Brook and Swan River
           confluence. An overview of the hydraulic model extent, location of the proposed
           rail alignment and the proposed road upgrade and Whiteman Park Station is
           shown in Figure 3.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 11
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 3 – Area of Interest

           5.1.2                 Available Data and Existing Studies
           Three existing studies have been undertaken in the area of interest for the Bennett
           Brook and Horse Swamp area. These existing studies were reviewed to provide
           context and guidance for hydrologic model parameters and model inflows.
           Findings of previous studies are discussed below.
           Swan and Helena Rivers Flood Study: Hydrology (HARC, 2016)
           HARC was contracted by the Eastern Metropolitan Regional Council to undertake
           a review of the design flood hydrology for the Swan River, with the intention of
           using the latest available techniques to establish flows for the 10% AEP event
           through to the probable maximum flood (PMF).
           The study utilised the RORB runoff routing program to simulate flood
           hydrographs for the full Swan Avon River system which has a catchment area of
           124,000km2.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 12
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                         Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                             Flooding and Hydrology Report

           Due to the difference in size of the study area between this broader catchment
           study, and the hydrological assessment of the Bennett Brook and Horse Swamp
           area, there is a limited amount of data and parameters that can be correlated in
           terms of hydrologic model calibration, particularly with there being limited data
           available for the lower end of the Swan River around Bennett Brook.
           The kc value adopted within the RORB model was varied per each interstation
           area, and the lower end of the model, including the Bennet Brook tributary utilised
           a kc value computed from C0.8 and dav. It was noted that there was limited gauging
           information that could be used to improve this estimate.
           A proportional loss model was adopted within the RORB model, with loss
           parameters also varying by interstation areas. The loss parameters adopted for the
           Swan River sub-catchments (including Bennett Brook) were 100mm initial loss
           and a proportional loss coefficient of 0.35. These loss parameters were adopted in
           the hydrological modelling developed by Arup for the Bennet Brook catchment
           which is discussed further in Section 5.1.3.
           Bennett Brook Flood Study (Gutteridge Haskins & Davey Pty Ltd, 1988)
           The aim of the Bennett Brook Flood Study was to estimate catchment runoff rates
           and consequently extent and level of flooding in Bennett Brook, between the
           Swan River confluence and Mussel Pool. The hydrological modelling undertaken
           for the Bennett Brook Flood Study utilised RORB version 3.7 and was completed
           in adherence with the 1987 version of the Australian Rainfall and Runoff
           Guidelines.
           The catchment modelled excluded a portion north of Gnangara Road as based
           upon field inspections and discussions with the Authority, the excluded area was
           highly permeable and unlikely to generate any runoff. Furthermore, Gnangara
           Road had no culverts to allow cross drainage and consequently in large events the
           flow would bank up behind the road embankment and eventually infiltrate into the
           ground. For this reason, the northern portion of the catchment was excluded from
           the Bennett Brook Flood Study. The hydrologic model which has been developed
           to assess the process rail alignment, covers the full Bennett Brook catchment,
           which is conservative in comparison to the study completed in 1988 as it includes
           the portion of the catchment north of Gnangara Road.

           The flows from the Bennett Brook Flood Study hydrological model were reported
           at several locations for various design events. The flows for the catchment
           reported at Marshall Road and Benara Road are summarised in the table below.
           Table 4 – Final PDP Issue design stage deliverables

             Reporting                                                                        Peak Flow (m3/s)
             Location
                                                 10 year ARI                   25 year ARI               50 year ARI            100 year ARI
             Marshall Road                       21                            30                        34                     41
             Benara Road                         38                            52                        59                     72

           Urban Water Management Plan: Lot 15 to 17 Woollcott Avenue, Whiteman
           Edge Local Structure Plan 1C (RPS, 2016)

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                                     Page 13
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           RPS produced an Urban Water Management Plan on behalf of Stockland
           Development Pty Ltd to support the subdivision of the western three-quarters of
           Whiteman Edge Local Structure Plan. The works included assessment of the
           existing environment, including geology, hydrology, surface hydrology and
           groundwater and also proposed various water conservation strategies. The
           hydrology assessment undertaken for this modelling was completed using
           XPSWMM. Catchment delineation and flow paths are shown in Figure 4.

           Figure 4 – XPSWMM Model Geometry (RPS, 2016)
           The peak flow rate for the 1% AEP event for the outflow drain to Horse Swamp is
           3.3m3/s. The hydrologic model was calibrated to replicate this peak flow rate for
           the 1%AEP event.

           5.1.3                 Hydrologic Modelling
           A XP-Rafts model was developed to simulate the routing of rainfall throughout
           the study catchment and produce inflow hydrographs for application to the
           hydraulic model.
           XPRafts Overview
           XPRafts is a non-linear runoff routing model suitable for both urban and rural
           catchments. It uses the Laurenson non-linear runoff routing approach to develop a
           stormwater runoff hydrograph from either recorded rainfall or design rainfall
           based upon IFD data and temporal patterns. XPRafts can utilise a number of loss
           models including initial/continuing, initial/proportional and ARBM water balance
           model. Hydraulic routing can also be tailored to the catchment characteristics by
           utilising either simple Manning’s based lagging or the Muskingum-Cunge
           method.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 14
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Hydrologic model geometry
           The hydrologic model boundary has been delineated down to the Reid highway
           encompassing a total area of 173km2. The catchment has been further delineated
           into 13 subareas creating various reporting locations within the catchment for
           application to the hydraulic model. The catchment includes a combination of both
           undeveloped rural areas and developed residential areas. Consequently, the
           Bennett Brook catchment comprises of a combination of both pervious and
           impervious areas. The geometry of the hydrologic model is shown in Figure 5.

           Figure 5 – Hydrologic model geometry
           Hydrologic model parameters
           The hydrologic model was developed utilising the latest available data from the
           2019 Australian Rainfall and Runoff guidelines. This information was sourced
           from both IFD and datahub web sources.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 15
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Within the hydrologic model, routing between catchments has been defined by
           use of manually calculated lag times and an initial/proportional loss approach was
           adopted for all sub catchment areas. A summary of model parameters is
           summarised in Table 5.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 16
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                              Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                                  Flooding and Hydrology Report

           Table 5 – Summary of hydrologic model parameters

             Parameter                                                                         Value
             Hydrologic Approach                                                               ARR 2019 – Ensemble Method
             IFD extraction point (Lat/Long, decimal degrees)                                  -31.818, 115.924
             Date of data download                                                             18th of July 2019.
             Temporal pattern zone                                                             Southern & South Western Flatlands (FLTWest)
             Loss approach                                                                     Initial/Proportional
             Initial loss (mm)                                                                 100
             Loss coefficient                                                                  0.35
             Routing Method                                                                    Lag times calculated based upon low velocities
                                                                                               due to wide channels and low slopes.

           Hydrologic Model Outputs and Model Validation
           Due to the limited data available to calibrate the Bennett Brook hydrologic model,
           information has been sourced from previous studies and tools such as the
           Regional Flood Frequency Estimation Model (RFFE) to provide validation to the
           hydrologic model outputs.
           There are some gauges in the adjacent catchments. However, they do not provide
           data of sufficient quality to assist in model calibration. There are also several
           gauges located along the Swan River. However, these gauges are for the broader
           catchment and are located upstream of the Bennett Brook confluence.
           It is noted that there is a gauge downstream of the area of interest along the
           Bennett Brook. The gauge data extends from 1988 onwards. However, the flows
           and levels recorded appear to be controlled by the downstream storage area, as
           flows range from 0m3/s to only 4.5m3/s. Consequently, while some gauge data
           exists, there is minimal data which can be utilised to aid in the calibration of the
           hydrologic model.
           The work completed by HARC in 2016 suggests that a 100mm initial loss and a
           proportional loss coefficient of 0.35 provides a reasonable calibration across most
           of the Swan River sub catchments, of which the Bennett Brook is located. These
           loss values were adopted within the XPRafts model in conjunction with data from
           the latest Australian Rainfall and Runoff guidelines including temporal patterns
           and IFD data. Utilising this information, the suite of ensemble events was
           simulated through XPRafts. Results indicated that for a 1% AEP event, the critical
           duration was shown as 72 hours for the Bennett Brook catchment, with a peak
           flow of 43.9m3/s. The box and whisker plot showing the spread of peak flow rates
           across multiple durations is shown in Figure 6.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                                          Page 17
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 6 – 1% AEP Box and Whisker Plot
           In comparison, the RFFE estimates for this catchment suggest a 1% AEP peak
           flow of 48.7m3/s, which is within 10% of the hydrologic model. The peak flow
           rate from the hydrologic model is also in the vicinity of values presented in the
           Bennett Brook Flood Study completed in 1988, which reported that at Marshall
           Road a 1% AEP of 41m3/s was expected. The reporting location for the XPRafts
           model is just downstream of the Marshall Road location reported in the Bennett
           Brook Flood Study.
           Initial results for the 2% AEP and 10% AEP events indicated that utilising the
           same loss parameters of 100mm initial loss and a proportional loss coefficient of
           0.35 resulted in disproportional peak flood estimates for the smaller events which
           did not align with available validation data such as the RFFE model estimates. As
           described in the work by HARC, the difficulty introduced by a proportional loss is
           that it is considered to vary with AEP, and due to the lack of available calibration
           data, the ability to identify a proportional loss coefficient for each AEP is
           unrealistic. Consequently, a pragmatic approach was adopted to scale the 1% AEP
           flood hydrograph by equivalent ratios of the RFFE estimates.
           The raw data from nearby gauged catchments utilised for the RFFE estimates was
           analysed and once catchments with areas significantly larger the Bennett Brook
           catchment or shape factors which were dissimilar were excluded, a linear
           relationship was developed relating the peak flow estimate to the catchment area.
           These relationships for the 1% AEP, 2% AEP and 10% AEP events are shown in
           Figure 7 to Figure 9.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 18
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 7 – Linear Relationship of Catchment Area to RFFE Peak Flood estimates
           for a 1% AEP Event

           Figure 8 – Linear Relationship of Catchment Area to RFFE Peak Flood estimates
           for a 2% AEP Event

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 19
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                     Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                         Flooding and Hydrology Report

           Figure 9 – Linear Relationship of Catchment Area to RFFE Peak Flood estimates
           for a 10% AEP Event
           Using the linear relationships shown scaling factors for the 2% and 10% AEP
           events were determined. A summary of peak flood estimates and scaling factors
           are shown in Table 6. The corresponding inflow hydrographs for application to
           the hydraulic model are also shown in Figure 10.
           Table 6 – Summary of Peak Design Flows

             AEP Event                         Peak Flow (m3/s)                        Critical Duration (mins)      Temporal Pattern
             10%                               23.9                                    Scaled off 1% AEP event by a factor of 54% based
                                                                                       upon analysis of RFFE peak flows.
             2%                                36.0                                    Scaled off 1% AEP event by a factor of 82% based
                                                                                       upon analysis of RFFE peak flows.
             1%                                43.9                                    4320                          4
           *Peak flows have been reported at catchment C2b.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                                 Page 20
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 10 – Summary of Main Upstream Inflow Hydrographs (C2b) for Bennett Brook
           Hydraulic Model
           The flows which have been applied to the Whiteman Park area have been based
           upon the peak flow of 3.3m3/s as reported by the existing RPS report which has
           utilised more detailed modelling using XPSwmm to represent the catchment and
           storages within the urban area. Similarly, to the main hydraulic model inflow, the
           Whiteman Park area has been scaled by a factor of 82% and 54% for the 2% AEP
           and 10% AEP events respectively.

           5.1.4                 Hydraulic Modelling
           Model Overview
           The hydraulic modelling for the assessment of the Bennett Brook rail crossing has
           been completed using TUFLOW. TUFLOW is a two-dimensional unsteady flow
           model which estimates flood levels and velocities throughout a fixed grid area by
           solving two-dimensional depth averaged momentum and continuity equations for
           free surface flow. Within the hydraulic model, all one-dimensional elements such
           as culverts and pipes are managed by the ESTRY solver which utilises St-Venants
           equations. TUFLOW and ESTRY engines are hydrodynamically linked to ensure
           continuity between 1D and 2D domains.
           The version of TUFLOW which has been utilised for this study is the 2018-03-
           AD release which features the Heavily Parallelised Compute (HPC) solver. In
           short, the HPC solver uses adaptive time steps and GPU processing to decrease
           the simulation run time.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 21
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                        Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                            Flooding and Hydrology Report

           Model Development
           A basic summary of the model is presented in Table 7 and shown in Figure 11.
           Table 7 – Hydraulic Model Summary

             Parameter                                                               Information
             Model Build Development Date                                            November 2019
             AEP’s Events Assessed                                                   10%, 2% and 1% AEP
             Hydrologic Modelling Approach                                           Inflows determined through XPRafts hydrologic model and
                                                                                     applied through SA polygons within the 2d domain.
             TUFLOW Version                                                          2018-03-AD-iSP (HPC GPU)
             Model Extent                                                            Refer to Figure 11
             Grid Size                                                               5m x 5m
             Topographic Data                                                        5m national DEM (ELVIS, 2019), 2m LiDAR (Department
                                                                                     of Environment and Water, 2019) and 2m gridded survey
                                                                                     data (Main Road WA, 2019).
             Roughness                                                               Spatially varying roughness values which align with
                                                                                     standard industry values. Refer to Table 8 below which
                                                                                     outlines the adopted values.
             Eddy Viscosity and Turbulence                                           Smagorinsky (default)
             Downstream Model Boundary                                               Height Time boundary – based upon constant water level
             Hydraulic Model Time Step                                               Adaptive timestep
             Modelled Scenarios                                                      Existing (pre construction) and Design cases (post
                                                                                     construction).

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                                    Page 22
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 11 – Hydraulic model schematic
           Model Extent
           The model extent is shown in Figure 11. The upstream boundary along Bennett
           Brook has been defined approximately 1km upstream of the proposed alignment.
           The Horse Swamp area has also been included in the model, with the upper end of
           the model extending past the eastern side of New Lord Street to enable the
           proposed diversion drains and proposed road and rail alignments to be
           represented.
           Model Boundaries
           All inflow boundaries within the hydrologic model have been represented by flow
           vs time boundaries (QT) applied through either boundary condition lines, or
           source area polygons. Model inflows are based upon XPRafts outputs.
           All outflow boundaries are based upon height-discharge (HQ) relationships.
           TUFLOW develops height-discharge relationships based upon the topography

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 23
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           elevations along the boundary line, and the downstream energy slope. Model
           boundaries are shown in Figure 11. An initial water level was also defined in the
           Horse Swamp area, as highlighted in Figure 11.
           Model Topography
           The topography which has been utilised within the hydraulic model development
           has utilised a combination of both 5m gridded data derived from LiDAR (Elvis,
           2019), 2m LiDAR data (Department of Environment and Water, 2019) throughout
           critical project areas, and 2m gridded data derived from survey through the New
           Lord Street Area (Main Roads WA, 2019).
           In addition to the base gridded topography data, a number of topographic
           modifications have been enforced in the model. These modifications include:
                        Drainage channels and gully representation through the Horse Swamp area
                         and on the eastern side of Lords Road
                        Design scenario topographic changes such as proposed road and rail
                         embankments.
           Roughness Values
           Material roughness has been applied on a categorical basis. Specific roughness
           values for each category applied in the model are detailed in Table 8. The spatial
           representation of Manning’s ‘n’ values is shown in Figure 12.

           Table 8 – Material Classifications

             ID       Material Description                                                                Manning’s n
             1        Rural cleared land (default)                                                        0.040
             2        Riparian Vegetation (open pervious with trees)                                      0.090
             3        Waterbody                                                                           0.030
             4        Road                                                                                0.025
             5        Urban                                                                               0.200
             6        Open vegetation moderate – shrubs                                                   0.060
             7        Waterway area – cleared post construction                                           0.050

           Structure Blockage
           The proposed design structures, including both the single span bridge and the
           culverts at the Bennett Brook crossing and at New Lords Street crossing, have
           been represented within the hydraulic model without inclusion of blockage
           factors. This approach has been adopted due to the design being in a concept
           phase, and the proposed rail and road levels in the Bennett Brook crossing and
           Whiteman Park precinct being significantly higher than the 1% AEP water level.
           However, it is recommended that in the detailed design phase, sensitivity
           assessments be undertaken for culvert blockage scenarios.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 24
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 12 – Roughness definition

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 25
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           5.1.5                 Existing Case Results
           In order to establish the baseline flood results, the 10%, 2% and 1% AEP events
           were run through the existing case hydraulic model. Flood maps presenting the
           height, depth and velocity results for these scenarios have been presented in
           Appendix I.
           The 1% AEP flood extent throughout the Bennett Brook area remains primarily
           contained in the main channels, with peak depths of between 1.4m to 1.8m along
           the centre of the Bennett Brook alignment. There are minor breakouts along
           portions of the main channel, with depths in these areas typically ranging from
           100mm to 500mm. Velocities throughout the channel are typically below 1m/s.
           The water levels and velocities for the existing case events at the centre of the
           proposed Bennett Brook Bridge are summarised in the table below.
           Table 9 – Existing flood behaviours at the proposed Bennet Brook bridge crossing

             AEP (%)               Depth (m)                                    Water Level (mAHD)       Velocity (m/s)

             1%                    1.07                                         16.23                    0.90

             2%                    0.97                                         16.14                    0.87

             10%                   0.75                                         15.91                    0.76

           5.1.6                 Proposed Design Details
           Within the hydraulic model extent, there are two locations that interact with either
           the main or minor channel areas. These areas are at the proposed crossing of
           Bennett Brook, and the proposed Whiteman Station and New Lords Road
           upgrade. An overview of the design elements at is shown in Figure 13 and Figure
           14 for the Bennett Brook and Whiteman Station areas respectively.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 26
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 13 – Proposed Bennett Brook Crossing
           The proposed design at the Bennett Brook crossing features a 26m single span
           bridge with 2 / 600 Reinforced Concrete Pipes (RCPs) each side of the bridge.
           The soffit level of the bridge is approximately 17.15mAHD.
           The bridge has been represented within the hydraulic model through use of a
           layered flow constriction region and the culverts have been represented as part of
           a 1D network layer.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 27
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Figure 14 – Whiteman Street Park Precinct
           Through the Whiteman Park Station area, the rail alignment will be a viaduct, and
           will have minimal impact on the local flood behaviours. However, there are
           numerous other design features such as the design upgrade to New Lord Street
           and the inclusion of a pedestrian underpass which would impact flow paths and
           local drainage.
           The proposed design features a 1.5m deep trapezoidal drain with a 2m wide base.
           The drain will tie into the culvert crossing under Youle-Dean Road and divert
           flow through around the pedestrian underpass to the 2 / 1050 RCP proposed, as
           shown in Figure 14.
           The key intention for modelling the Whiteman Park Area is to ensure that the
           proposed pedestrian underpass has adequate flood immunity to remain accessible
           in a 1% AEP event.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 28
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           5.1.7                 Design Case Results and Impact Assessment
           The design case results are generally similar to the existing case results with
           isolated areas where impacts are observed due to the proposed design. The
           impacts to flood behaviours are discussed in the following sections.
           Impact Assessment at Bennett Brook Crossing
           The impacts of the proposed Bennett Brook crossing are isolated to the area
           immediately upstream of the alignment and does not have significant impact to
           adjacent properties. Design case maps are shown in Appendix J and flood impact
           maps are shown in Appendix K. The impact of the proposed design on flood level
           and extent is shown spatially in the figure below.

           Figure 15 – 1% AEP flood impact (Design Case minus Existing Case)

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 29
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                         Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                             Flooding and Hydrology Report

           As shown in Figure 15, the flood extent is increased upstream of the proposed
           crossing. However, these increases are primarily in the direction of open
           undeveloped area and has negligible impacts on adjacent properties.
           With regards to changes in levels and peak velocities, a maximum afflux of
           approximately 430mm is observed upstream of the bridge structure and an
           increase in peak flood velocities of 1.7m/s.
           Design case flood levels, velocities and flood impact are summarised in the table
           below for all simulated AEP events.
            Table 10 – Design case flood behaviour at proposed Bennet Brook bridge crossing

             AEP             Depth (m)              Water Level                Velocity              Change in Peak       Change in Peak
             (%)                                    (mAHD)                     (m/s)                 Flood Level (m)      Flood Velocity (m/s)

             1%              1.50                   16.66                      2.59                  0.43                 1.69

             2%              1.33                   16.49                      2.39                  0.36                 1.52

             10%             0.97                   16.13                      1.93                  0.22                 1.17

           Whiteman Park Pedestrian Underpass Flood Immunity
           Model results indicate that the current design of pedestrian underpass under New
           Lord Street achieves the required 1% AEP immunity. The cycle path adjacent to
           New Lord Street acts as a levee for the local catchment flows and keeps flooding
           away from the pedestrian underpass.
           It is recommended that for future stages of design, more detailed modelling of this
           area be undertaken both from a hydrologic and hydraulic perspective. The flood
           model has been developed to inform the pedestrian underpass flood immunity
           however, does not capture the detailed drainage within this area of works
           including the recent upgrades to New Lord Street, the proposed Whiteman Park
           Station and any impacts that the adjacent urban residential developments may
           have on the area.

           5.1.8                 Future Works
           There are a number of items which required further investigation in order to arrive
           at a suitable level of analysis for detailed design. These include:
                        Detailed modelling of Whiteman Park area to capture detailed surface
                         water drainage around the recent upgrades to New Lord Street. Depending
                         on outlet locations of surface water drainage systems, flood behaviours
                         may vary throughout the Whiteman Park area
                        To facilitate detailed design for the bridge, additional storm events would
                         need to be simulated through the hydrologic and hydraulic model,
                         specifically the 1:2000 AEP event. The 1:2000 AEP event is required for
                         both understanding bridge loading and for the design of appropriate scour
                         protection measures

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                                     Page 30
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

                        It is also noted that further design optioneering could be undertaken in
                         order to reduce afflux. Bridge optimisation options could include
                         increasing the span length or adding additional cross drainage structures in
                         the adjacent embankment
                        As part of the detailed design phase, sensitivity analyses including culvert
                         blockage scenarios should be undertaken to ensure that blockage of
                         proposed structures does not result in adverse flood impacts
                        Future flood studies of the Bennet Brook catchment would benefit from a
                         detailed assessment utilising a design storm dependant loss model.

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 31
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           5.2                   Design Risks, Assumptions, Issues, Dependencies,
                                 Opportunity and Constraints
           Design Risks, Assumptions, Issues, Dependencies, Opportunity and Constraints
           are tabulated in the project RAIDOC [MEL-MNO-ARUP-SA-REG-0003] which
           should be referred to when reviewing this report.

           5.3                   Non-compliances
           Any non-conformances to PTA standards have been listed as a deviation within
           the RAATM [MEL-MNO-ARUP-SA-REG-0004].
           No non-compliances were identified at the concept design phase, any further
           updates should be assessed at the next design phase.

           5.4                   Third party verification
           There has been no third-party verification as part of these works.

           5.5                   Constructability
           A constructability assessment has been undertaken by Agonis [MEL-MNO-
           AGON-CN-RPT-0003].

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 32
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

            Appendices
           Appendix A–Drawings/ sketches
           Please refer to Section 4.5 for drawing/ sketch numbers.

           Appendix B– RAATM
           Please refer to MEL-MNO-ARUP-SA-REG-0004.

           Appendix C- SAR
           Please refer to MEL-MNO-ARUP-SA-RPT-0002.

           Appendix D– RAIDOC
           Please refer to MEL-MNO-ARUP-SA-REG-0003.

           Appendix E– IDC Certificate
           Please refer to the following documents for the IDC certificate and accompanying
           information for each project package area:
           MEL-MNO-ARUP-PM-CERT-0000: PACKAGE 0
           MEL-MNO-ARUP-PM-CERT-0001: PACKAGE 0 (LINEWIDE
           COORDINATION DRAWINGS ONLY)
           MEL-MNO-ARUP-PM-CERT-2000: PACKAGE 2
           MEL-MNO-ARUP-PM-CERT-2001: PACKAGE 2 (NORANDA STATION
           AND PRECINCT ONLY)
           MEL-MNO-ARUP-PM-CERT-3000: PACKAGE 3
           MEL-MNO-ARUP-PM-CERT-4000: PACKAGE 4
           MEL-MNO-ARUP-PM-CERT-4001: PACKAGE 4 (PRECINCT ONLY)
           MEL-MNO-ARUP-PM-CERT-5000: PACKAGE 5

           Appendix F– IDR Closeout Record Log/ DRN and
           IDR register
           As above (Appendix E)

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 33
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
METRONET                                                                                                 Morley Ellenbrook Line (MEL) - Project Definition Plan (PDP)
                                                                                                                                     Flooding and Hydrology Report

           Appendix G Existing case

           MEL-MNO-ARUP-DR-RPT-0001 | D – FINAL | 28 February 2020 | Arup                                                             Page 34
           C:\PROJECTWISE\PER_PROJECTS\GLOBAL_ANDREW.SMETHERHAM\DMS70070\MEL-MNO-ARUP-DR-RPT-0001.DOCX
Peak water level
  (mAHD)
      0 - 8.85
         12 - 13
         13 - 14                                                                WHITEMAN
         14 - 15                                                                PARK
         15 - 16                                                                STATION

         16 - 17
         17 - 18
         18 - 19
         19 - 20
         20 - 21
         > 21

                                                                                                               FUTURE BENNETT
                          BENNETT BROOK                                                                        SPRINGS EAST
                          RAIL BRIDGE                                                                          STATION
                          CROSSING

                                          Project Title                                                                                                Consultant
Legend                                                                                                  Map scale
                                          PACKAGE 3 - MALAGA STN &
                                          HORSE SWAMP
         Cadastre                         Drawing Title                                                 Inset map scale
         Rail Alignment                   10% AEP Peak flood level - Existing
                                          case                                                                                                                 Level 4, 108 Wickham Street

         Flood model extent                                                                                                                                    Fortitude Valley, QLD 4006
                                                                                                                                                               Tel +61 (7)3023 6000 Fax +61 (7)3023 6023

                                          Job No                           Figure No
                                                          261422                       I1
                                          Coordinate System                Drawing Status              Dislclaimer
                                          GDA 1994 MGA ZONE 50                   PRELIMINARY
                                                                                                       © Arup Australia Pty Ltd 2019. All Rights Reserved

                                                                                                       Disclaimer: While all reasonable care has been taken to ensure the information contained
                                                                                            N          on this map is up to date and accurate, no warranty is given tha the information contained
                                                                                                       on this is free from the error or omission. Any reliance placed on such information shall be
                                                                                                       at the sole risk of the user. Please verify the accuracy of all information prior to using it.
                                              1            19/11/19   SV          HV                   This map is not a design document.

                                                                                                       Map data ©2019 Google
                                             Issue            Date    By         Chkd           Appd
Peak flood depth
  (m)
      0.0 - 0.5
         0.5 - 1.0
         1.0 - 1.5                                                              WHITEMAN
         1.5 - 2.0                                                              PARK
         >2.0                                                                   STATION

                                                                                                               FUTURE BENNETT
                          BENNETT BROOK                                                                        SPRINGS EAST
                          RAIL BRIDGE                                                                          STATION
                          CROSSING

                                          Project Title                                                                                                Consultant
Legend                                                                                                  Map scale
                                          PACKAGE 3 - MALAGA STN &
                                          HORSE SWAMP
         Cadastre                         Drawing Title                                                 Inset map scale
         Rail Alignment                   10% AEP Peak flood depth - Existing
                                          case                                                                                                                 Level 4, 108 Wickham Street

         Flood model extent                                                                                                                                    Fortitude Valley, QLD 4006
                                                                                                                                                               Tel +61 (7)3023 6000 Fax +61 (7)3023 6023

                                          Job No                           Figure No
                                                          261422                       I2
                                          Coordinate System                Drawing Status              Dislclaimer
                                          GDA 1994 MGA ZONE 50                   PRELIMINARY
                                                                                                       © Arup Australia Pty Ltd 2019. All Rights Reserved

                                                                                                       Disclaimer: While all reasonable care has been taken to ensure the information contained
                                                                                            N          on this map is up to date and accurate, no warranty is given tha the information contained
                                                                                                       on this is free from the error or omission. Any reliance placed on such information shall be
                                                                                                       at the sole risk of the user. Please verify the accuracy of all information prior to using it.
                                              1            19/11/19   SV          HV                   This map is not a design document.

                                                                                                       Map data ©2019 Google
                                             Issue            Date    By         Chkd           Appd
You can also read