MEMORANDUM Date: July 27, 2021 To: City of Baxter Utility Commission From: Aaron Warford Subject: 2022 Inglewood Drive Railway Crossing and Associated Roadway Improvements City of Baxter Municipal Project No.: 4121 BMI Project No. T42.120675 Background Bolton & Menk is the design consultant for the City of Baxter on this 2022 Inglewood Drive Railway Crossing and Associated Roadway Improvements (Inglewood Drive) project (www.inglewooddrive.com). The project focuses on the relocation of the Knollwood Drive traffic signal and railroad crossing to Inglewood Drive, pavement rehabilitation on Foley Road, public utility improvements, and an improved configuration for the Forthun Road and Isle Drive intersection. The project remains within the conceptual design and public input phase as stated in the previous project update as staff has continued coordination with MnDOT District 3 and MnDOT Central Office on geometrics and alternatives for all the TH 210 corridor. Contract discussions between BNSF and Benesch Associates on the railroad crossing designs are advancing. Public input such as an open house event and project updates were planned over this past month. Past options discussed with MnDOT for the Knollwood Drive/TH 210 intersection included: Open intersection with Full access, ¾ design, a Full Reduced Conflict Intersection (RCI), an alternative/modified design of an RCI and a temporary signal option. All alternatives except for the RCI were eliminated to ensure traffic controls and safety measures meet the goals of the Highway 210 corridor study and the overall vision for the Knollwood and Inglewood intersections. Continued conversations with MnDOT District 3 are being had to ensure the RCI is a cost-effective solution. Project Update as of July 27, 2021 Staff Updates On July 5, 2021, Aaron Warford was identified as the new Project Manager from Bolton & Menk for the project. His bio and background are attached and an email blast through the project website was sent out to the public of this staff change. Derek Arens, Design Engineer and Engineer of Record, and the overall design team remains on the project and will be the public contact moving forward as stated on the website. H:\BAXT\T42120675\1_Corres\C_To Others\Council Updates\2021-08\2021-08 T42120675 - Baxter Utilities Commision.docx
Name: Trevor Walter Date: 7/27/2021 Page: 2 Agency Coordination On July 8, 2021, the project staff met with Kelvin Howieson and Luke Wehseler from MnDOT District 3 along with Jamal Love from MnDOT’s Geometric Design Support Unit (GDSU) to discuss the proposed RCI at the Knollwood Ave/TH 210 intersection. The outcome was a design (attached) that still allows for the full effect of an RCI design type but reduces costs significantly from other concepts that have been shared. Offsetting the turn lane for the left U-turn movement further west eliminates the need for the turn lane overlap which causes the widening of Eastbound TH 210. On July 20, 2021, the Baxter City Council gave consensus to move forward with the offset turn lane RCI design (per attachment) with the understanding that MnDOT pays for the improvement. They asked City staff to get a commitment from MnDOT for funding in writing. Public Involvement An open house was held on Thursday, July 8, 2021, at the Council Chambers at City Hall. Updates to the website such as adding open house materials were applied. Concerns and questions from residents included: the City’s assessment policy, how are parcels going to be assessed/designed, request of (right/left) turn lanes at the intersection of Knollwood Drive/Foley Road, and consideration in addressing drainage issues along Foley Road that lead to icy conditions in the winter. A full recap of these comments and the project team responses will be included in an email blast along with posted on the website in the coming week. The website has an interactive map that the public can view and provide comments to the project. Responses to those comments will be addressed monthly. They will be both posted on the website along with being sent through the website’s email blast system to those that are signed up. Design The current layout of the project and one that was shared at the open house is available on the project website. The only component of the project that remains undecided is the RCI design as mentioned in Agency coordination. On July 12, 2021, MnDOT provided comments on the submitted ICE report for the proposed TH 210/Inglewood Drive intersection. MnDOT questioned the need for additional reports for TH 210/Knollwood Drive and Isle Drive/Forthun Road. Coordination on determining needs for the Isle Drive/Forthun Road is still in progress but the TH 210 Knollwood Drive one was created. On July 27, 2021, new and updated ICE reports for the TH 210/Knollwood Drive and TH 210/Inglewood Drive intersections were submitted to MnDOT D3 Traffic for review. (Attached) Only July 27, 2021, a geometric layout was submitted to MnDOT D3 for an official level 1 review by MnDOT GDSU for signoff on the design of the improvements on TH 210. Only July 27, 2021, a figure of the mini-RAB design of the Forthun Rd/Isle Drive intersection was submitted to the City. (Attached) The project traffic staff is continuing progress on the Glory Road/Isle Drive intersection ICE report. H:\BAXT\T42120675\1_Corres\C_To Others\Council Updates\2021-08 \2021-08 T42120675 – Baxter Utilities Comission.docx
Name: Trevor Walter Date: 7/27/2021 Page: 3 Project Development Between a transition of project managers and the determination of the project extents, a revised schedule has been compiled and is attached. FINANCIAL IMPLICATION None. With the RCI addition at TH 210/Knollwood Drive per MnDOT’s request, the continued goal of the project team is to keep all construction costs at the responsibility of MnDOT. Design costs to the consultant of Bolton and Menk will be processed through the City’s contract with the intention of it all being reimbursed by MnDOT. The intent is to have all contract scope creep and changes addressed and determined by the next project update. STAFF RECOMMENDATIONS None. Memo is for informational purposes only. COUNCIL ACTION REQUESTED None. Memo is for informational purposes only. H:\BAXT\T42120675\1_Corres\C_To Others\Council Updates\2021-08 \2021-08 T42120675 – Baxter Utilities Comission.docx
Aaron J. Warford, P.E. Principal Transportation Engineer Education Summary Bachelor of Science - Civil Engineering Aaron has the qualifications, experience, motivation, and work ethic to University of Minnesota effectively manage projects. He began his career in 1999, gaining experience in project management in both design and construction of county and MnDOT Master of Business Administration - Strategic highways, complex intersections, roundabouts, and ADA-compliant facilities. Management, University of Minnesota Aaron’s experience managing projects requiring extensive federal, state, local, and multi-agency coordination efforts offer a unique service to clients. His Registration success is rooted in effective stakeholder involvement; he understands and Professional Engineer, Minnesota appreciates that acceptance and approval for a project begins with those most affected and intimately connected. Aaron relates well to a broad spectrum of Continuing Education people, establishing trust through genuine and honest discussion. He places a • Systematic Development of Informed Consent, Hans high priority on maintaining effective communication with clients and project Bleiker team members. • Contract Administration • CPM Scheduling Experience • State Aid Seminar, MnDOT Roadway Design and Construction • TH 169 Grade Raise, Mankato to Saint Peter, MnDOT District 7 Organizations • TH 71 Improvements in Jackson, MnDOT District 7 Minnesota Society of Engineers and Surveyors • TH 61 Reconstruction, City of Red Wing, MN • TH 169 Reconstruction in Blue Earth, MnDOT District 7 • TH 61 Streetscape Improvements in White Bear Lake, MnDOT Metro • I-90/TH 43 Pavement Rehabilitation, MnDOT District 6 • TH 14/CSAH 41 Interchange, MnDOT District 7 • TH 19 Mill & Overlay, MnDOT District 6 • TH 78 Better Roads Project, MnDOT District 4 • CSAH 101 Infrastructure Replacement, Scott County, MN • CSAH 12 Reconstruction, Scott County, MN • TH 21/TH 3 Intersection Improvements, City of Faribault, MN • CSAH 44/CSAH 27, Scott County, MN • CSAH 19 Reconstruction, City of Albertville, MN • TH 10/TH 59 Railroad Embankment, City of Detroit Lakes, MN • TH 212 Design-Build Preliminary Engineering Design, Cities of Chaska and Eden Prairie, MN Contract Administration • I-494 from TH 5 to TH 55, City of Minneapolis, MN • Airside Tunnels at Minneapolis/St. Paul International Airport, Metropolitan Airport Commission • LRT Station at Minneapolis/St. Paul International Airport, Metropolitan Airport Commission • St. Paul Downtown Airport Perimeter Dike and Flood Prevention, Metropolitan Airport Commission
Aaron J. Warford, P.E., Principal Transportation Engineer Design Build • Design-Build Program Phase 1, MnDOT • I-494, TH 212, and Oronoco Design-Build Projects • Design-Build Program Phase 2, MnDOT • TH 610 and Bridges of Mower County Design-Build RFPs
LEGEND PROPOSED ROADWAY RAISED CONC. MEDIAN, CURB & GUTTER LANDSCAPING/GREEN SPACE KNOLLWOOD DR LIGHTING UNIT TYPE 9-40 150 SCALE IN FEET dgn gures\GDSU RCI_1. MAINTAIN EXISTING 3-WAY STOP (NB TRAFFIC DOES NOT STOP) \BAXT\T42120675\CAD\MS\fi STOP RIGHT THRU 12' FAIRVIEW RD 12' 10' SHLD 10' SHLD 10' SHLD 12' RIGHT (350') M MINNESOTA 12' THRU 12' THRU 12' THRU 12' THRU 12' THRU 12' THRU 12' THRU 12' THRU S-BUS-40 (c) 2021 Transoft Solutions, Inc. All rights reserved. AASHTO 2011 (US) 12' LEFT (350') 12' LEFT (350') 21 0 H: 12' THRU 12' THRU 12' THRU 12' THRU 12' THRU S-BUS-40 12' THRU 12' THRU (c) 2021 Transoft Solutions, Inc. All rights reserved. 12' THRU 12' THRU AASHTO 2011 (US) 12' THRU 10' SHLD 10' SHLD 10' SHLD 10' SHLD 30 AM BNSF RR 10: 10: 7/13/2021 PERIMETER 30 FT AREA 15 SF PERIMETER 30 FT AREA 15 SF 35 SF 35 SF REM REM PERIM ETER 50FT FT FT AREA 26 SQ 95 SQ REM FOLEY RD PERIMETER 50FT FT FT AREA 26 SQ 95 SQ PERIMETER 30 FT REM REM AREA 15 SF 35 SF PERIMETER 30 FT REM AREA 15 SF 35 SF PERIMETER 30 FT REM 35 SF AREA 15 SF DR . bm itbl OOD LLW tcfg KNO s. Chri pl or. pdf-col Loyd OFFSET TURN LANE RCI CONCEPT TH 210 BAXTER ACCESS STUDY BAXTER, MN
PROPOSED PROJECT SCHEDULE 2022 INGLEWOOD DRIVE RAILWAY CROSSING AND ASSOCIATED ROADWAY IMPROVEMENTS PROJECT BAXTER, MN Tuesday, July 27, 2021 MAJOR TASKS AND MILESTONES DATES REMARKS NOTES Proposals Due Friday, January 24, 2020 Award of Consultant Contract Tuesday, February 18, 2020 City Council Meeting Delay to coordinate improvements with TH 210 Study Project Construction delayed to 2022 Tuesday, June 2, 2020 Recommendations Receive Preliminary TH 210 Recommendations Thursday, February 18, 2021 Staff Review of Updated Project Layout Tuesday, March 2, 2021 Review Update Project Layout Tuesday, April 6, 2021 City Council Workshop Project Update Wednesday, June 2, 2021 Utilities Commission Meeting Railroad Diagnostic Meeting Tuesday, June 29, 2021 Scheduled in coordination with BNSF and Benesch ICE Report - TH 210 and Inglewood Drive Thursday, July 1, 2021 Project Update Wednesday, July 7, 2021 Utilities Commission Meeting Public Engagement Meeting Thursday, July 8, 2021 Receive Public Input (See Public Engagement Plan) Friday, July 9, 2021 Project Website and InputID Project Update Thursday, August 5, 2021 Utilities Commission Meeting Review Updated Feasibility Study Wednesday, September 1, 2021 Utilities Commission Meeting ICE Report - Isle Drive and Glory Road Friday, September 3, 2021 Review Updated Feasibility Study Tuesday, September 7, 2021 City Council Meeting Accept Feasibility Report and Order Improvement Hearing Tuesday, September 7, 2021 City Council Meeting Twice in local newspaper, one week apart, last notice First Published Notice for Improvement Hearing Wednesday, September 15, 2021 must be at least three days prior to hearing. City Mailed Notice for Improvement Hearing Monday, September 20, 2021 One notice at least 10 days prior to hearing. Second Published Notice for Improvement Hearing Wednesday, September 22, 2021 Must be at least three days prior to hearing. Improvement Hearing Conducted Thursday, September 30, 2021 Special City Council Meeting Resolution Ordering Improvement and Preparation of Plans Tuesday, October 5, 2021 City Council Meeting and Specifications Project Memorandum Friday, October 8, 2021 Required for Federal Aid Process Agreement - BNSF - License for Electrical Supply Line Friday, October 15, 2021 Agreement - BNSF - License for Bicycle Path/Pedestrian Friday, October 15, 2021 Walkway Agreement - BNSF - Grade Crossing Construction and Friday, November 19, 2021 Maintenance Agreement Final Plans, Specifications, and Estimate Wednesday, December 1, 2021 Internal Design Deadline Approve Plans and Specifications and Authorize Wednesday, December 8, 2021 Utilities Commission Meeting Advertisement for Bid Approve Plans and Specifications and Authorize Tuesday, December 21, 2021 City Council Meeting Advertisement for Bid Publication must be made at least three weeks before last day to submit bids, at least once in official Bidding Publication Wednesday, December 22, 2021 newspaper and once in trade paper or First Class city newspaper. Project Update Wednesday, January 5, 2022 Utilities Commission Meeting By default bid remains subject to acceptance for 60 days Bid Opening Thursday, January 13, 2022 after the Bid opening. Resolution Ordering Assessment Hearing Tuesday, January 18, 2022 City Council Meeting Once in local newspaper at least two weeks prior to Published Notice for Assessment Hearing Sunday, January 23, 2022 hearing. Foley Road Improvements Mailed Notice for Assessment Hearing Monday, January 24, 2022 One notice at least two weeks prior to hearing Bid review with Utilities Commission Wednesday, February 2, 2022 Utilities Commission Meeting Assessment Hearing Tuesday, February 8, 2022 Special City Council Meeting Resolution Adopting Assessment Rolls Tuesday, February 15, 2022 City Council Meeting Appeals to district court must be made within 30 days End of Assessment Appeal Period Thursday, March 17, 2022 after adoption of the assessment roll. Resolution Awarding Construction Contract Tuesday, April 5, 2022 City Council Meeting Contractor has 15 days to deliver signed agreement, Notice of Award Wednesday, April 6, 2022 bonds, and insurance certificates. Public Service Announcement (e-mailed by City) Monday, April 11, 2022 City Mailed Notice for Public Information Meeting Monday, April 11, 2022 Pre-Construction Meeting Thursday, April 14, 2022 10:00 am at Baxter City Hall Public Information Meeting - Construction Monday, April 25, 2022 6:00 p.m. at Baxter City Hall Begin Construction Monday, May 2, 2022 24 Weeks of Full Time Construction Construction Complete Friday, October 14, 2022 Construction Substantially Complete MnDOT Layout Approval Wednesday, September 22, 2021 Final Plans, Specifications, and Estimate Wednesday, April 6, 2022 Internal Design Deadline Approve Plans and Specifications and Authorize Wednesday, April 6, 2022 Utilities Commission Meeting Advertisement for Bid Approve Plans and Specifications and Authorize Tuesday, April 19, 2022 City Council Meeting Advertisement for Bid Publication must be made at least three weeks before last day to submit bids, at least once in official Bidding Publication Wednesday, April 20, 2022 newspaper and once in trade paper or First Class city newspaper. Project Update Wednesday, May 4, 2022 Utilities Commission Meeting By default bid remains subject to acceptance for 60 days Bid Opening Thursday, May 12, 2022 after the Bid opening. Resolution Ordering Assessment Hearing N/A Assumes no assessments for work in Trunk Highway Published Notice for Assessment Hearing N/A Assumes no assessments for work in Trunk Highway Mailed Notice for Assessment Hearing N/A Assumes no assessments for work in Trunk Highway TH 210 Improvements Bid review with Utilities Commission N/A Assumes no assessments for work in Trunk Highway Assessment Hearing N/A Assumes no assessments for work in Trunk Highway Resolution Adopting Assessment Rolls N/A Assumes no assessments for work in Trunk Highway End of Assessment Appeal Period N/A Assumes no assessments for work in Trunk Highway Bid review with Utilities Commission Wednesday, June 1, 2022 Utilities Commission Meeting Assume 5 weeks for MnDOT bid review and MnDOT Bid Review and Approval Thursday, June 16, 2022 authorization Resolution Awarding Construction Contract Tuesday, June 21, 2022 City Council Meeting Contractor has 15 days to deliver signed agreement, Notice of Award Wednesday, June 22, 2022 bonds, and insurance certificates. Public Service Announcement (e-mailed by City) Monday, June 27, 2022 City Mailed Notice for Public Information Meeting Monday, June 27, 2022 Pre-Construction Meeting Thursday, June 30, 2022 10:00 am at Baxter City Hall Public Information Meeting - Construction Monday, July 11, 2022 6:00 p.m. at Baxter City Hall Begin Construction Monday, July 18, 2022 13 Weeks of Full Time Construction Construction Complete Friday, October 14, 2022 Construction Substantially Complete NOTES 1 City Council Meetings held on 1st and 3rd Tuesdays @ 7:00 p.m. 2 Utilities Commission Meetings held on 1st Wednesday @ 5:30 p.m. 3 All dates are subject to change, this is a living document. Dates may change based on coordination with other 2021 & 2022 projects and external agencies and their timelines. 1|1