IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021

Page created by Edward Fitzgerald
 
CONTINUE READING
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
IL18 RIVER BRIDGE PROJECT
PUBLIC MEETING #1 SUMMARY
October 4, 2021
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
1.0      Introduction
 The existing IL 18 bridge over the Illinois River at the city of Henry was constructed in 1934. Due to the age and condition
 of the bridge, the Illinois Department of Transportation (IDOT) District 4 is evaluating potential improvement options for
 the bridge. The project study limits extend from the intersection of IL 18 and 3rd Street in Henry on the west to the
 intersection of IL 18 and IL 26 on the east (Figure 1). The IL 18 River Bridge Project study will take a detailed look at
 potential improvements to IL 18 and the bridge over the Illinois River.
 IDOT develops and implements projects using a three-phase process. The IL 18 River Bridge Project is currently at the
 beginning of Phase I: Preliminary Engineering and Environmental Studies. During this phase, IDOT will study a range of
 potential improvements, conduct public involvement activities, and complete an environmental analysis. The Phase I
 Study will determine the alignment, bridge type, and right-of-way needs for the project.
 The purpose of the project is to accommodate IL 18 traffic through the project area and across the Illinois River on a
 transportation system that is structurally sound, meets current design stands, provides a safe crossing for the public,
 reduces flooding over IL 18, supports regional connectivity needs, and meets the need of river traffic.
 IDOT hosted the first public open house
 meeting to kick-off the IL 18 River
 Bridge Project Phase I Study. The
 purpose of the meeting was to
 introduce the project and solicit
 feedback on the purpose and need.
 Interested persons visited the open
 house between 5:00 p.m. and 7:00
 p.m. IDOT provided information
 regarding the study schedule and
 process, purpose and need, public
 involvement activities, and Section 106
 and Section 4(f). Attendees had the
 opportunity to review exhibits, provide
 comments, and meet with IDOT and
 study team representatives on a one-
 on-one basis.
 The public meeting was held on August
 25, 2021 between the hours of 5:00
 p.m. – 7:00 p.m. at the Henry United
 Methodist Church Fellowship Hall on
 225 Lincoln Street, Henry, Illinois 61537.Seventy-one people attended the public meeting.
 This public meeting summary describes the tools used to announce and publicize the meetings, the information
 presented, and the comments received.

IL 18 River Bridge Project – Public Meeting #1 Summary                                                                     1
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
FIGURE 1 – PROJECT STUDY LIMITS

 2.0       Getting the Word Out

 2.1       MEETING EMAIL INVITATIONS
 An email invitation (Appendix A) was sent to every individual on the project mailing list. The first email was sent on August
 18, 2021. Two additional emails were sent on August 20 and 24 to the new people that signed up for the project mailing
 list on the project website.

 2.1.1     ADVERTISEMENTS
 Display advertisements announcing the meeting were placed in the following newspapers:
       •   Peoria Journal Star: August 10 and August 22, 2021
       •   Henry News-Republican: August 18 and August 25, 2021

IL 18 River Bridge Project – Public Meeting #1 Summary                                                                      2
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
FIGURE 2 – DISPLAY ADVERTISEMENT

 2.1.2      HOW DID ATTENDEES HEAR ABOUT THE MEETINGS?
 One question on the comment form that was distributed at the public meeting asked the attendees to indicate how they
 heard about the meeting. The results are summarized in Table 1.

 TABLE 1 – SUMMARY OF HOW ATTENDEES HEARD ABOUT THE PUBLIC MEETING

  Method                                                             Number of Responses
  Newspaper Ad                                                               2
  Project Email                                                              2
  Word of Mouth                                                              2
  Social Media                                                               2
  Elected Official                                                           1

IL 18 River Bridge Project – Public Meeting #1 Summary                                                              3
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
3.0       Public Meeting

 3.1       HANDOUTS
 When attendees arrived at the public meeting, yard signs directed them to the building entrances and additional signage
 in the building directed them to the registration table. At the registration table, the Project Team asked attendees to sign
 in and invited them to take a project newsletter (Appendix B).

 3.2       OPEN HOUSE
 The open house featured a series of exhibits including a mix of display boards and aerial mapping that allowed attendees
 to understand the project, the overall process, and the purpose and need. Exhibits displayed at the meeting included:

       •   Project Overview
       •   Study Area Map
       •   Project Development Process
       •   Phase I
       •   Phase I Study Process
       •   Phase I Project Schedule
       •   Purpose and Need
       •   Public Involvement Activities
       •   Section 106 and Section 4(f)
       •   Land Acquisition

 These exhibits are located in Appendix C.

 4.0       Comments Received
 The Project Team encouraged participants to provide comments on the information presented at the meeting and to ask
 questions. Comments forms were available at the meeting. They were asked to either leave the form in the comment box
 at the meeting or to mail them to the Project Team at the address on the comment form. Self-addressed envelopes were
 provided. The comment period ended on September 10, 2021.

 4.1       COMMENT FORMS RECEIVED AT THE MEETINGS
 The comment forms distributed at the meeting included five main questions as well as an area to provide contact
 information. Four comment forms were received at the meeting, and one additional comment form was mailed in after
 the meeting (Appendix D). Listed below are the responses received to the five questions asked on the comment form.
 QUESTION 1:
 The purpose of this meeting is to give you an opportunity to learn more about the IL 18 River Bridge Project, speak with
 project representatives, and tell us what transportation issues and community values are most important to you. What
 transportation issues and community values do you want to see reflected in the draft Purpose and Need statement and
 considered during this study?
 Responses to Question 1:
       •   Not to displace our businesses.
       •   Make it safer for vehicles and large implements/farm/school buses, etc.
       •   Bridge needs to be replaced with design similar to new bridge at Spring Valley (lane width, shoulders).
       •   IDOT needs to discontinue pretreating with calcium chloride. Public should be able to survive “winter driving
           conditions”.

IL 18 River Bridge Project – Public Meeting #1 Summary                                                                      4
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
•     Old bridge needs to remain in service while new is constructed.
      •     I see no "community values" reflected in the purpose and need statement. The statement appears to only touch
            upon design, structural, and safety standards. In no way does the purpose and need touch upon community
            issues.
      •     We are 8 years minimum from new bridge. Please maintain the bridge we currently have.
      •     Because my home is rather close to Hwy 18, I am concerned about the location of the new bridge. If my home
            will be in its path, I would appreciate adequate advance notice so that I will have time to find a new home and
            get settled.
      •     It is very important that the current bridge not be shut down, as it would have a very negative effect on our
            community.
      •     Transportation issues: A wider bridge would be ideal. We are sure you are already aware of the flooding on east
            side of the bridge.
      •     Community values: a bridge to have character and for aesthetic appealing to the community. Attempt to keep
            the landing of the bridge as close to curved landing on the west side of the bridge. 15 foot concrete walls will not
            be very appealing to our current down town. The Illinois Rover and town view are a large attribute to our
            community, we would not like to lose that when crossing the bridge.
 QUESTION 2:
 The project team is also collecting information on the existing conditions in the study area. Please rank the top three
 factors that are most important to you, with “1” being most important and “3” being the least important.
 Responses to Question 2:

 TABLE 2– SUMMARY OF COMMUNITY FACTOR RANKING

  Topic                                                  Ranked “1”             Ranked “2”                   Ranked “3”
  Cultural/historic resources                                                                                    
  Public parks and recreational areas                                               
  Air quality
  Noise
  Agriculture
  Community/Neighborhood resources                                                                               
  Residential/commercial displacements                                            
  Visual/aesthetics                                                                                            
  Energy usage
  Travel options                                                                   
  Natural resources                                                                                              
  Project cost
  Other:

 QUESTION 3:
 How did you find out about this public meeting? Please check all that apply.

IL 18 River Bridge Project – Public Meeting #1 Summary                                                                        5
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
Responses to Question 3:

 TABLE 3 – SUMMARY OF HOW PARTICIPANTS FOUND OUT ABOUT THE MEETING

  Source                                                                      Occurrences
  Elected Official                                                                 
  Project Email                                                                   
  Project Website
  Word of Mouth                                                                   
  Newspaper Advertisement                                                         
  Other: Social Media/Facebook                                                    

 QUESTION 4:
 What information did you hope to gather from this meeting? Please provide any thoughts you have on the helpfulness of
 information presented, meeting format, meeting venue, publicity efforts, or other meeting-related feedback.
 Responses to Question 4:
       •    A better understanding of the project.
       •    Factors that impact alignment and impacts upon existing property/land uses (parks, marina, road intersections).
       •    I was looking for possible alternative location for the bridge. Perhaps it’s too early for that.
       •    Design options and how or what the impact is going to be to the community.
 QUESTION 5:
 Additional comments regarding the project and/or today’s public meeting.
 Responses to Question 5:

       •    Make it unique. Something that stands out.
       •    We are 8 years minimum from new bridge. Please maintain the bridge we currently have.
       •    Good source of information for the status so far. Thank you for allowing the input.

 4.2        COMMENTS RECEIVED ON THE WEBSITE
 No comments were received at the project website during the public meeting comment period (ending September 10,
 2021).

 5.0        Next Steps
 The project team responded to each comment (if contact information was provided) with a letter addressing the
 questions, comments, and concerns stated (Appendix E). The information gathered at the public meeting and presented
 in this document will be incorporated in the environmental document. Input regarding the format and content of the
 meetings and the effectiveness of various communication strategies will be used to improve future public meetings and
 overall project communication.

IL 18 River Bridge Project – Public Meeting #1 Summary                                                                   6
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
6.0      Appendices
 Appendix A – Public Meeting Email Invitation

 Appendix B – Meeting Handout/Newsletter #1

 Appendix C – Meeting Exhibits

 Appendix D – Comment Forms Received

 Appendix E – Responses to Written Comments

IL 18 River Bridge Project – Public Meeting #1 Summary   7
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
Appendix A – Public Meeting Email Invitation

IL 18 River Bridge Project – Public Meeting #1 Summary                                      8
IL18 RIVER BRIDGE PROJECT PUBLIC MEETING #1 SUMMARY - October 4, 2021
IL 18 RIVER BRIDGE PROJECT

You’re Invited
Open House Public Meeting to Introduce the
IL 18 River Bridge Project
The Illinois Department of Transportation has launched a study for potential improvements to the
IL 18 Bridge over the Illinois River at Henry.
The study limits extend along IL 18 from the intersection of School Street and 3rd Street on the west
to the intersection of IL 18 and IL 26 on the east. The IL 18 Bridge is a critical transportation link
providing access across the Illinois River for the City of Henry, Marshall and Putnam counties, and the
surrounding region. The bridge is 87 years old and is approaching the end of its repairable life.
The meeting will introduce the project and solicit feedback on the purpose and need for improvements.
All persons interested in this project are invited to attend. The meeting will be conducted on an informal
basis with project displays and other information available for viewing. IDOT representatives will be
available to explain the project and answer questions. The public is encouraged to submit comments.

    Open House                                                  Henry United Methodist Church
                                                                Fellowship Hall
    IL 18 RIVER BRIDGE PROJECT
                                                                225 Lincoln Street
    Wednesday August 25, 2021                                   Henry, Illinois 61537
    5 p.m. – 7 p.m.

                   Project Website: www.IL18RiverBridgeProject.com

  For more information email us at: Contact@IL18RiverBridgeProject.com

The location of the meeting is accessible to persons with disabilities. If special accommodations or assistance are
needed, please contact Mr. Travis Wallenfang, IDOT Project Manager, by Friday August 20, 2021 at 309-671-3333,
by fax at 309-671-3498, by telecommunications device for the deaf (TTY) at 309-671-3450.
*State COVID guidelines at the time of the meeting will be followed, which may require precautions such as facial
  coverings, social distancing, and room occupancy limits.
Appendix B – Meeting Handout/Newsletter #1

IL 18 River Bridge Project – Public Meeting #1 Summary                                   9
IL 18 RIVER BRIDGE PROJECT
                                                     NEWSLETTER

Introduction
The existing IL 18 Bridge over the Illinois River at the city of Henry           Public Meeting #1
was constructed in 1934. Due to the age and condition of the bridge,
the Illinois Department of Transportation (IDOT) District 4 is evaluating
                                                                                 August 25, 2021
potential improvement options for the bridge. The project study limits           5 – 7 p.m.
extend from the intersection of IL 18 and 3rd Street in Henry on the west
                                                                                 Henry United Methodist
to the intersection of IL 18 and IL 26 on the east.
                                                                                 Church Fellowship Hall
About the Study                                                                  225 Lincoln Street
The IL 18 River Bridge Project study will take a detailed look at potential      Henry, IL 61537
improvements to IL 18 and the bridge over the Illinois River.
IDOT and its consultant team (i.e., the project study team) will inventory existing conditions of the IL 18
roadway and bridge, traffic and crash data, and environmental constraints as it moves forward in the
process. The project study team, with input from the public, will also develop and refine improvement options
(alternatives). The existing conditions, alternatives, potential impacts, and proposed mitigation will be detailed
in the project’s Environmental Document. The result of the study will be the selection of a preferred alternative
for improvements through the project study area that addresses identified transportation issues and serves
the area’s future needs.

                                                                                          Project Study Limits
                                                                                          County Border
IL 18 RIVER BRIDGE PROJECT

Project Development Process
IDOT develops and implements projects using a three-phase process. The IL 18 River Bridge Project is
currently at the beginning of Phase I: Preliminary Engineering and Environmental Studies. During this phase,
IDOT will study a range of potential improvements, conduct public involvement activities, and complete an
environmental analysis. The first part of Phase I will be conducted under a process called Planning and
Environment Linkages (PEL). This process is used for early collaboration to facilitate better planning and
provide for expedited reviews under the National Environmental Policy Act (NEPA). This Phase I Study will
determine the alignment, bridge type, and right-of-way needs for the project. When the study is approved, the
project will move forward with Phase II: Contract Plan Preparation and Land Acquisition. This phase includes
developing detailed contract plans and purchasing land for the project, if needed. Once funding and permits
are secured, the project moves into Phase III: Construction.

                   PHASE                                 PHASE                                      PHASE

                    I                                    II                                         III

             Preliminary
                                                Contract Plan
            Engineering &
                                                Preparation &                               Construction*
            Environmental
                                              Land Acquisition*
               Studies

                We are here                       *Currently included in IDOT’s Fiscal Year 2022 – 2027 Multi-year program

The NEPA Process
NEPA is a federal law that requires federally funded             Alternatives will be
projects, such as the IL 18 River Bridge Project,                evaluated for impacts on:
to analyze alternatives and identify potential effects
of those alternatives on the environment.                            Social and Economic Factors
An Environmental Document will be developed for                      Agriculture
the IL 18 River Bridge Project. When it is complete,                Historic Properties
the Environmental Document will identify the solution                Air quality
that will best address the transportation issues and
then detail how this solution was selected. The                      Noise
document will explain the potential impacts and                      Energy
benefits resulting from the project, and identify ways               Natural Resources – plants, water bodies,
to avoid or lessen the negative impacts. These efforts                 threatened and endangered species
help ensure that environmental resources and other
factors are integrated into project decisions.                       Special Lands – parks/recreation
IL 18 RIVER BRIDGE PROJECT

Purpose and Need
The purpose of the project is to accommodate IL 18 traffic through the project area and across the Illinois
River on a transportation system that is structurally sound, meets current design standards, provides a safe
crossing for the public, reduces flooding over IL 18, supports regional connectivity needs, and meets the
needs of river traffic.
Project Needs:
• Structural Integrity: Condition of the superstructure and substructure
• Design Standards: The narrow roadway deck does not meet current standards
• Safety Concerns: The narrow roadway increases the likelihood of crashes
• Regional Connectivity:
   − The bridge is an essential link connecting Marshall and Putnam counties and the surrounding region
   − Flooding over IL 18 often results in roadway and bridge closures resulting in adverse travel time

Bridge Condition
The bridge was constructed in 1934. In 1988, 54 years after its
construction, IDOT performed a major rehabilitation project on
the structure. The concrete bridge deck was completely replaced.
Deteriorated and damaged steel members as well as concrete
substructures were repaired. Since this last rehabilitation, vehicular
use, weather, and salt usage have caused deterioration to the structural
steel and concrete that form the piers and deck. Although the bridge has
undergone extensive repairs, it is approaching the end of its
repairable life.
IDOT inspects the bridge annually and will continue to repair the bridge
as necessary until the project is complete.

Schedule
The project is currently in Phase I, which includes preliminary engineering and an environmental study.
This phase should last approximately 24 months. In Phase I, proposed geometry, bridge type, environmental
concerns, and right-of-way requirements are identified. Phase I will conclude with design approval by the
Federal Highway Administration. Following this approval, IDOT can proceed into Phase II of the project
which includes final design and right-of-way acquisition.

 2021                                                  PHASE I                                                         2023

    Identify Problem/                       Develop & Evaluate                  Determine Preferred                  Phase I
 Develop Purpose & Need                        Alternatives                         Alternative                     Approval

                  We are here

                 Community Advisory Group Meeting     Public Meeting/Hearing   Environmental Coordination Meeting
IL 18 RIVER BRIDGE PROJECT

Public Involvement Activities
Public involvement is an important part of the Phase I study and includes many activities such as Stakeholder
Interviews, Community Advisory Group Meetings, Public Meetings, project website, and a newsletter.
The Stakeholder Interviews were conducted to engage stakeholders, share information, and foster
discussion by addressing specific project issues, allowing for more specialized discussions and input, and
aiding the general public in developing a better understanding of the project goals and objectives. Although
time does not permit every individual stakeholder to be interviewed, selections were made to gather input from
all types of stakeholders such as local agencies and organizations, members of the business community, and
affected property owners. During May and June of this year, the project study team conducted 17 stakeholder
interviews with 72 stakeholders in the region.
A Community Advisory Group (CAG) was established that includes county and municipal officials,
representatives of businesses, agricultural organizations, residents, and other members of the local
community with an interest in the project. The meetings with the CAG are designed to encourage timely
and meaningful opportunities for input and to encourage information sharing and collaboration. The first two
CAG meetings for this project were held in June and July of 2021 to discuss the project’s problem statement,
purpose and need, and potential alignment alternatives. Three additional CAG meetings will be held in
December 2021, April 2022, and December 2022.
Public Meetings and a public hearing will be large-scale meetings held to encourage public attendance
and foster public awareness of project developments and alternatives under study. These meetings also will
provide a forum for general public input, including concerns and comments regarding project alternatives.
Three public events are anticipated to coincide with major project milestones:
• P
   ublic Meeting #1 will be held on August 25, 2021, which is the project kickoff, providing information
  regarding the study process and objectives, additional outreach opportunities, the project purpose and
  need, and an opportunity for the public to share its perspectives and provide comments.
• P
   ublic Meeting #2 will present the alternatives that were further evaluated and their evaluation results;
  alternatives that will be carried forward; and evaluation methods.
   he Public Hearing will present the Environmental Document and preferred alternative. The public hearing
• T
  is part of a Federal requirement under the National Environmental Policy Act (NEPA). Stakeholders will have
  the opportunity to view and provide comments on the Environmental Document and preferred alternative.

 We encourage and welcome Public Comments throughout the project. At Public Meeting #1, there will
 be comment sheets available for attendees to fill out or to mail back to the project study team. The public
 can also send comments to Contact@IL18RiverBridgeProject.com or fill out the online comment form at
 www.IL18RiverBridgeProject.com. When the environmental document is published, a formal public
 comment period will be held which will include the public hearing.
Appendix C – Meeting Exhibits

IL 18 River Bridge Project – Public Meeting #1 Summary                                   10
IL 18 RIVER BRIDGE PROJECT

                              Project Overview
•   IL 18 Henry Bridge was constructed in 1934
•   Bridge was rehabilitated (deck replacement/substructure repairs) in 1988
•   1,719-foot long structure with 6 through truss and 7 approach spans
•   Bridge width is 22.6 feet – Functionally Obsolete
•   $SSURDFKURDGZD\ÀRRGLQJLVVXHV
•   Aging bridge is reaching the end of its repairable life
IL 18 RIVER BRIDGE PROJECT

                                   Study Area Map
Study Limits: Intersection of IL 18/3rd Street in Henry to Intersection of IL 18/IL 26

 29

                         Sc
                             ho
                                                                         Sawmill Lake

                             ol
             HENRY
                              St
                      d St
                   3r                                               er
                                  18                      i s Riv
                                                        o
              18                                  Illin

                                                                             26

                                                    Putnam County                                18

                                                    Marshall County
                                             18

                                                                               County Border

                                                                    26         Project Study Limits
IL 18 RIVER BRIDGE PROJECT

       Project Development Process

    PHASE                                      PHASE                                           PHASE

      I                                         II                                             III

 Preliminary
                                 Contract Plan
Engineering &
                                 Preparation &                                             Construction*
Environmental
                               Land Acquisition*
   Studies

  We are here

                *Currently included in IDOT’s Fiscal Year 2022 – 2027 Multi-year program
IL 18 RIVER BRIDGE PROJECT

                                                Phase I
Environmental Studies
 ƒ Environmental Document
   – Social and Economic Factors
   – Agriculture
   – Historic Properties
   – Air Quality / Noise
   – Energy
   – Natural Resources: plants, water bodies,
     threatened and endangered species
   – Special Lands: parks/recreation
Engineering Studies
 ƒ Roadway
 ƒ Structural
 ƒ Hydraulics
Context Sensitive Solutions (CSS)
 ƒ Understand values of community
 ƒ Obtain public feedback early and often
IL 18 RIVER BRIDGE PROJECT

                                   Phase I Study Process
                                                               2021                                                                              2022                                                2023

                        Initiate CSS      CAG                 Public                        CAG                     CAG                Public                   CAG                Public
                        Process           Meetings            Meeting #1:                   Meeting #3:             Meeting #4:        Meeting #2:              Meeting #5:        Hearing:
                        • Stakeholder     #1 and #2:          • Project                     • Alternatives          • Preliminary      • Alternatives           • Environmental    • Preferred
 Context Sensitive        Interviews      • Project             Introduction                  to be Carried           Preferred          to be Carried            Document           Alternative
 Solutions/Public       • Context Audit     Introduction      • Purpose and                   Forward                 Alternative        Forward                • Public           • Environmental
                                                                Need                                                                   • Preliminary              Hearing            Document
   Involvement                            • Problem
                                            Statement                                                                                    Preferred                Preview
                                                                                                                                         Alternative
                                          • Purpose and
                                            Need
                                                                                                                                                                                                        A
                                                     Planning and Environment Linkages (PEL)                                                National Environmental Policy Act (NEPA)
                                                                                                                                                                                                        P
                        Environmental               Purpose and                  Develop                       Evaluate and                Identify Preferred            Final Environmental
                        Data Collection             Need                         Alternatives                  Screen Alternatives         Alternative                   Report                         P
    Planning and
Environmental Studies
                        • Environmental Surveys     • Identify the
                                                      transportation problems
                                                                                 • Meet Purpose and Need       • Identify alternatives
                                                                                                                 that meet purpose and
                                                                                                                                           • Identify alternative that
                                                                                                                                             best meets purpose and
                                                                                                                                                                         • Document Preferred
                                                                                                                                                                           Alternative, impacts,
                                                                                                                                                                                                        R
                        • Field Reviews                                          • Compare Social,
      PEL/NEPA
                                                      the project will address     Economic, and
                                                                                   Environmental Impacts
                                                                                                                 need and have the least
                                                                                                                 impacts
                                                                                                                                             need and minimizes
                                                                                                                                             impacts
                                                                                                                                                                           DQGPLWLJDWLRQLQ¿QDO
                                                                                                                                                                           environmental
                                                                                                                                                                                                        O
                                                                                                               • Narrow list of
                                                                                                                 alternatives to a few
                                                                                                                                                                           document
                                                                                                                                                                                                        V
                                                                                                                 to be carried forward                                                                  A
                                                                                                                                                                                                        L
                        Engineering Data                                         Develop and Evaluate Preliminary                          Further Develop               Final Engineering
                        Collection and Analysis                                  Alternatives                                              Engineering of                Reports
                        • Project Mapping          • Crash Analysis              • 3UHOLPLQDU\URDGZD\DOLJQPHQWDQGSUR¿OH                Alternatives to be            • Prepare Final
    Engineering         • Roadway and Structural   • Existing Drainage           • Preliminary structure studies                           Carried Forward                 Engineering Reports
                          Evaluation                 Patterns
      Studies                                                                    • Preliminary drainage and hyrdraulic studies             • Complete more detialed
                                                                                                                                             engineering of retained
                        • Survey/Geotechnical      • Field Reviews
                                                                                                                                             alternatives

                                                               2021                                                                              2022                                                2023
IL 18 RIVER BRIDGE PROJECT

                      Phase I Project Schedule
                                           Target Completion – 2 years

2021                                                                                                                                       2023
                                                             PHASE I

    Identify Problem/                          Develop & Evaluate                                   Determine Preferred             Phase I
 Develop Purpose & Need                           Alternatives                                          Alternative                Approval

                We are here
       JU
        JU
        AU 21
        SE

                                          DE

                                                               FE

                                                                                      AP
                                                                                       MA 22

                                                                                                           JU

                                                                                                                                NO
                                                                                                                                NO 2022
       N2
          L2

                                                                 B2

                                                                                                             N2
           PT

                                             C2

                                                                                      R2
           G2

                                                                                         Y2

                                                                                                                                   V
                                                                                                                                  V2
              0
              021

                                                                    022

                                                                                                                022
              202

                                               021

                                                                                           0
                                                                                           022

                                                                                                                                     022
               021

                  1

                                                       Public Involvement

                          Community Advisory Group Meeting   Public Meeting/Hearing        Environmental Coordination Meeting
IL 18 RIVER BRIDGE PROJECT

                                Purpose and Need
Purpose
 ƒ 7
    KHSXUSRVHRIWKHSURMHFWLVWRDFFRPPRGDWH,/WUDI¿FWKURXJKWKHSURMHFWDUHDDQGDFURVV
   the Illinois River on a transportation system that is structurally sound, meets current design
   VWDQGDUGVSURYLGHVDVDIHFURVVLQJIRUWKHSXEOLFUHGXFHVÀRRGLQJRYHU,/VXSSRUWVUHJLRQDO
   FRQQHFWLYLW\QHHGVDQGPHHWVWKHQHHGVRIULYHUWUDI¿F
Need
 ƒ Structural Integrity – Condition of the superstructure and substructure
 ƒ Design Standards – Narrow roadway deck does not meet current standards
 ƒ Safety Concerns – Narrow roadway increases likelihood of crashes
 ƒ Regional Connectivity –
   – Essential link connecting Marshall and Putnam counties and surrounding region
   – Flooding often results in roadway and bridge closures and adverse travel time
IL 18 RIVER BRIDGE PROJECT

                Public Involvement Activities
• Stakeholder Meetings – One-on-one meetings with stakeholders
• Context Audit – 6XUYH\WRLGHQWLI\FKDUDFWHULVWLFVWKDWGH¿QHWKHSURMHFW
• Community Advisory Group – Small group of local stakeholders
• Public Meetings – Large meetings open to the public to gather input and to provide
  updates on the project (2 meetings)
• Public Hearing – Large meeting open to the public to present the environmental
  document and the preferred alternative and to receive comments (1 meeting)
• Project Website – www.IL18RiverBridgeProject.com
IL 18 RIVER BRIDGE PROJECT

                   Section 106 and Section 4(f)
Section 106 of the National Historic
Preservation Act
 ƒ Consider the effects of federally funded
   projects on historic properties
 ƒ Identify historic properties, assess the
   effects and explore alternatives to avoid,
   minimize, or mitigate adverse effects
Section 4(f) Properties
 ƒ Publicly-owned public parks, recreational
   DUHDVRIQDWLRQDOVWDWHRUORFDOVLJQL¿FDQFH
   wildlife or waterfowl refuges; or lands from
   a historic site of national, state, or local
   VLJQL¿FDQFH
                                                                                                 Duck Ranch                          18
 ƒ Determine that there is no feasible and
   prudent alternative to avoid the Section 4(f)
   properties
 ƒ Includes all possible planning to minimize
   harm to the Section 4(f) properties
                                                      Example: Duck Ranch owned by the Illinois Department of Natural Resources is a Section 4(f) property
IL 18 RIVER BRIDGE PROJECT

             Land Acquisition

Phase I Study will identify project location, construction limits,
                     and right-of-way needs

Land acquisition cannot begin until Phase I study is approved

    Land acquisition follows federal regulations and offers
               are based on Fair Market Value
SCH
           HENRY

                                                         OO
                                   EDW

                                                            L ST
                                      ARD

                                                             REE
                                      STR

                                                              T
                                        EET
                            EET
                        STR
                  3RD
                         Central                 TREET
                          Park              2NDS

                                                                 R EET
                                                         N  T ST
                                                      FRO
                                                  Water
                                                  Works
                                                  Park
                       MA
                       RKE
                        T ST
                            REE
                             T

                                                                         IL-
                                                                          18

LEGEND
         County Line
                                                                         IL 18 RIVER BRIDGE PROJECT
SCH
                                                                                                           R

                                                        OO
                                                                                                        VE
                                                                                                      RI

                                                             LS
                                                                                                 IS
                  HENRY                                                                        NO
                                                                                                                                 SAWMILL LAKE

                                                              TRE
                                                                                            LI
                                                                                          IL

                                                                   ET
                                              EDW
                                                 ARD
                                                 STR
                                                   EET
                                     ET
                            S TRE
                        3RD         Central
                                     Park              2ND
                                                             STR
                                                                EET

                                                                              EET
                                                                           STR
                                                                      NT
                                                                   FRO
                                                               Water
                                                               Works
                                                               Park
                                MA
                                RKE
                                    T ST
                                     REE
                                       T

                                                                                    IL-
                                                                                    18
                                                                                                                                                IL-18

                                                                                                 PUTNAM COUNTY

                                                                                                 MARSHALL COUNTY

                                                                                                                            26
                                                                                                                           IL-
                                                                                                               IL-26

LEGEND
         County Line   Study Area
                                                                                                                       IL 18 RIVER BRIDGE PROJECT
Appendix D – Comment Forms Received

IL 18 River Bridge Project – Public Meeting #1 Summary                                11
Appendix E – Responses to Written Comments

IL 18 River Bridge Project – Public Meeting #1 Summary                                   12
You can also read