G. H. MITCHELL ELEMENTARY SCHOOL - COMMUNITY PRESENTATION JUNE 13, 2019 - Bridgewater School Building ...

Page created by Zachary Greene
 
CONTINUE READING
G. H. MITCHELL ELEMENTARY SCHOOL - COMMUNITY PRESENTATION JUNE 13, 2019 - Bridgewater School Building ...
G. H. MITCHELL ELEMENTARY SCHOOL
BRIDGEWATER, MA

COMMUNITY PRESENTATION
JUNE 13, 2019

                                   Raymond
                                   Design Associates
G. H. MITCHELL ELEMENTARY SCHOOL - COMMUNITY PRESENTATION JUNE 13, 2019 - Bridgewater School Building ...
RECAP | PROJECT TO DATE
                                                                                                                                                                                          Fall, 2019:
                                                                                                                          April – July 2019:
February 2015:                                                                                                                                                               Anticipated town-wide
                                                                                                                          Development of schematic design
Roof Collapse at                                                                                                                                                           ballot to vote for funding
                                                                                                                          and cost estimates
Mitchell Elementary                                                                                                                                                          design/construction of
                                                  November 2017 – May 2018:                                                                                                         the new Mitchell
School followed by                                                                                                        Community Workshops and
                                                  Public procurement, Interviews,                                                                                                Elementary School
sprinkler system                                                                                                          Public Presentations to gather
                                                  Selections, and MSBA approvals for
pipe failure that led                                                                                                     input and comments on the new
                                                  hiring of Owner’s Project Manager
to flooding of                                                                                                            Mitchell School design
                                                  and Architect
“Central Wing”

                                                                                                                                                    We Are Here

             January 14, 2016:                                            June 2018 – April 2019:
             Statement of Interest submitted to                           Study of location/site options (7 sites                                           August 2019:
             Massachusetts School Building                                studied), grade configuration options                                             Anticipated MSBA Board of
             Authority (MSBA)                                             (PreK – 2 or PreK-3), and existing                                                Directors meeting to receive
                                                                          conditions of building and site at 500                                            approval of Schematic Design.
             February 15, 2017:
                                                                          South Street.
             MSBA voted Mitchell ES into                                                                                                                    Next step, Funding the Project!
             Eligibility Period.
                                                                           PreK-2 Grade Configuration selected
             June 10, 2017:                                                Location at 500 South Street selected
             Bridgewater voters approve
             $800,000 to fund Feasibility Study                           MSBA approval and invitation to
                                                                          Schematic Design phase.

                                                                                       Community Presentation | June 13, 2019                                                                           2
G. H. MITCHELL ELEMENTARY SCHOOL - COMMUNITY PRESENTATION JUNE 13, 2019 - Bridgewater School Building ...
SCHEMATIC DESIGN | NEW CONSTRUCTION – STUDY OPTION “C6.1”

On April 10, 2019 the MSBA approved the Preferred Option (C6.1) and invited the project to proceed in to the
Schematic Design Phase

 MEETS EDUCATIONAL REQUIREMENTS

 SAFETY & SECURITY CONCERNS ADDRESSED

 BETTER PARKING AND VEHICLE CIRCULATION

 SUSTAINABILITY AND ENERGY EFFICIENCY

 BETTER STUDENT HEALTH AND WELLNESS FACILITIES

 ONE CENTRAL ENTRANCE AND ONE MAIN OFFICE

 MOST EFFICIENT / BEST VALUE OPTION
                                               http://bridgewaterschoolproject.com/why-build-option-c6-1/

                                             Community Presentation | June 13, 2019                            3
G. H. MITCHELL ELEMENTARY SCHOOL - COMMUNITY PRESENTATION JUNE 13, 2019 - Bridgewater School Building ...
COMMUNITY WORKSHOP | PUBLIC FEEDBACK

The Bridgewater School Building Committee hosted two “interactive”
community workshops on May 8th and June 6th to give members of the
public a chance to view some of the new school plan details and provide
feedback and comments on the following topics:

         Educational Spaces
         Site Plan
         Community/Shared Spaces
We asked the people who attended:

         What do you like?
         What could be better?
Here is an overview of the feedback we received …

                                              Community Presentation | June 13, 2019   4
G. H. MITCHELL ELEMENTARY SCHOOL - COMMUNITY PRESENTATION JUNE 13, 2019 - Bridgewater School Building ...
COMMUNITY WORKSHOP | PUBLIC FEEDBACK

             What do you like?                                                       What could be better?

 Possible rain-out space for Music Alley                             Would like sound proof barriers
 Playground areas                                                    Meeting space for Boy Scouts, Girl Scouts,
                                                                       Softball, etc.
 Multi-purpose community/shared spaces
                                                                      Senior / School Programming
 Single entrance / main lobby
                                                                      Garden space that can be shared with the
 Better security
                                                                       Senior Center
 Rainwater harvesting for irrigation
                                                                      Detail on managing access, traffic, and
 Charging stations for electric cars                                  speed on connection with Wally Kreuger
                                                                       Way
                                                                      Better handicap accessible parking for
                                                                       after-hours access
                                            Community Presentation | June 13, 2019                                  5
G. H. MITCHELL ELEMENTARY SCHOOL - COMMUNITY PRESENTATION JUNE 13, 2019 - Bridgewater School Building ...
SCHEMATIC DESIGN | EDUCATIONAL SPACES

 Grade levels in clusters
 Flexible classroom spaces to
  meet educational program
 Improved Special Education
  spaces
 STEM/STEAM environments
 Flexible layout / expansion
 One Main Entrance / Increased
  Security / Centralized Admin
 Natural daylighting
 Ground floor spaces for before
  and after school programs

                                   Community Presentation | June 13, 2019   6
SCHEMATIC DESIGN | SITE PLAN
 Increased # of parking spaces
  (approx. 302)
 Improved traffic and pedestrian
  circulation
 Student safety / secure play
  areas
 Improved accessibility
 Separate bus and car queues
  (approx. 63 cars can queue on-
  site)
 Separate bus exit on to RT 18
  (right turn only)
 Shaded areas and buddy
  benches in playgrounds

                                    Community Presentation | June 13, 2019   7
SCHEMATIC DESIGN | COMMUNITY-USE FEATURES
 Single, separate after-hours
  entrance
 High School sized basketball &
  volleyball court with 120
  bleacher seats
 Cafetorium with stage and
  seating for 375
  (one of the largest meeting
  spaces in town)
 Two-sided stage situated
  between Cafeteria and Gym to
  allow for expanded or programs
 Access to family playgrounds
  and outdoor learning spaces

                                   Community Presentation | June 13, 2019   8
PROJECT COSTS | ESTIMATED PROJECT BUDGET + REIMBURSEMENT
MITCHELL SCHOOL – NEW CONSTRUCTION                                                                                                                       Option C6.1

  FEASIBILITY STUDY
  (OPM, Designer, Environmental, Site, Other)
                                                                                                                                                         $800,000
  CONSTRUCTION
  (Demolition, Foundation, Shell, Interiors, Mechanical-Electrical-Plumbing & Fire Protection, Fixtures, Sitework)
                                                                                                                                                      $65,962,536
  “ SOFT COSTS”
  ADMINISTRATION, OPM, ARCHITECT, FF&E, OTHER MISC.                                                                                                   $11,430,000
  (Legal, Printing, Advertising, Utility, Permitting, Moving, Testing & Inspections, Furniture & Equipment, Other Project Costs)
  CONTINGENCY
  (Owners and Construction Contingency)
                                                                                                                                                       $3,960,000
TOTAL PROJECT                                                                                                                                         $82,152,536
                                                                                                                                   Anticipated Rate   Anticipated Cost
Anticipated MSBA Reimbursement Rate w/ Incentives for Eligible Costs                                                                       59.28%
    Example ineligible costs: legal fees, advertising, printing, moving, permits, utility costs
    Example capped costs: Construction Cost ($333/SF), Furniture, Fixtures and Equipment ($2,400/student), Site costs (8% max)
Estimated MSBA “Effective” Reimbursement Rate of Total Project Costs                                                                        40.00%
                                                            Anticipated MSBA Reimbursement (est. 40% of Total Project Cost)                           $32,861,014
                                                       Anticipated Town Share (est. 60% of Total Project Cost)                                        $49,291,522

                                                                               Community Presentation | June 13, 2019                                                    9
PROJECT COSTS | TAX IMPACT
                                                                             Amount Per Year
                                                              Average Single Family Home Value of $385,759
                                                                                                                                                                                                               Average Cost
                                                                                                                                                                                                                per Year for
                       $600                                                                                                                                                                                       Average
                                                                                                                                                                                                               Single Family
                               $482

                       $500                             $433

                                                                                 $384                                                                                                                          Home Value
Amount per Year

                       $400                                                                               $346
                                                                                                                                   $311
                                                                                                                                                                                                               of: $385,759
                                                                                                                                                           $282
                                                                                                                                                                                    $251
                       $300
                                                                                                                                                                                                                      $355
                       $200

                       $100

                          $0
                                 1     2     3     4      5     6     7     8      9    10    11     12    13    14    15     16    17    18    19    20     21    22    23    24     25

                                                                                         Years

             1)   The worst impact will be the first yea r and then the debt service w ill decline as the principal is paid down. Impact based on the average assessed value home of $385,759 less MSBA reimbursement and proposed offsett ing
                  revenues and an assumed 3.5% interest rate.

                                                                                                            Community Presentation | June 13, 2019                                                                                               10
PROJECT COSTS | TAX IMPACT

                                                                                                     Rate per $1,000 - Year One

                                                                                                           School Building: $1.25

                                                                                                                Calculating Your Cost
                                                                                                   Assessed Property Value (From Your Tax Bill) / $1,000
                                                                                                                X (Rate per $1,000)
                                                                                                                    = Annual Cost

                                                                                                                  Example School Building

                                                                                                           $459,000 / $1,000 X $1.25 = $574

               (1)   Please note these are estimates and subject to change. The average assessed home value in Bridgewater is currently $385,759, and changes annually.
               (2)   Project cost estimates based on a 25 year bond
               (3)   The financial advisor has recommended we assume a conservative 3.5% interest rate.
               (4)   Other major Town projects that may require funding in the future are Fire Station, Roadways, and Drainage.

                                                                    Community Presentation | June 13, 2019                                                                11
FUNDING THE PROJECT | MSBA POLICY

                                MSBA Policy for Project Approval

• To qualify for any funding from the MSBA, the District must follow the MSBA statute and
  regulations.
• The Schematic Design submittal informs the basis of the approved project scope, schedule and
  Maximum Total Facilities Grant.
• In order for the MSBA to enter into a Project Scope and Budget Agreement with the District, the
  District must:
   • Submit a Schematic Design for the proposed project prior to the MSBA Board meeting
   • Receive approval from the MSBA Board for its proposed project
   • Return 3 signed copies of the Project Scope and Budget Agreement to MSBA
• In order for the MSBA to enter into a Project Funding Agreement with the District, the District must
  secure local authorization and funding within 120 days of the MSBA Board's vote.

                                           Community Presentation | June 13, 2019                        12
FUNDING THE PROJECT | MSBA POLICY

                    MSBA policy if Town fails to vote to appropriate funding

• A failed vote “will likely result in the school district being required to submit a new SOI and await
  invitation”. In a typical year, the MSBA receives more than 80 statements of interest and invites
  less than 15 districts in to their eligibility period. There is no guarantee that the district would
  receive another invitation to eligibility.

• Loss of $32 Million in potential state funds + reimbursement rates are subject to change in the
  future based on MSBA funding capacity and future changes to policy.

• The value of construction continues to rise at a steady rate. Construction cost reports list the
  Boston region at a 4.42% annual increase from January 2018 to January 2019. Any future project is
  estimated to have a greater construction cost due to industry-wide cost increases.

                                            Community Presentation | June 13, 2019                        13
SCHEDULE | ESTIMATED CONSTRUCTION SCHEDULE

                                Community Presentation | June 13, 2019   14
EVENTS | UPCOMING PUBLIC MEETINGS

     The Bridgewater School Building Committee will hold their next two meetings
              at the Bridgewater Academy Building, Council Chambers

                           6:30pm on Monday, June 17th

                            6:30pm on Monday, July 8th

    All Bridgewater School Building Committee meetings are open to the public.
 We encourage you to attend to hear updates on the project and share your feedback.

                                   Community Presentation | June 13, 2019             15
STAY INFORMED| PROJECT WEBSITE + EMAIL

              Please visit www.bridgewaterschoolproject.com
                  for more information or to sign up for our newsletters!

             If you would like to contact us directly, please send us an email at:
                   bridgewaterschoolproject@gmail.com

                          THANK YOU!
                                        Community Presentation | June 13, 2019       16
You can also read