FOUR YEARS OF SUCCESSFUL OPERATION AT THE EUXFEL - 2021 INTERNATIONAL CONFERENCE ON RF SUPERCONDUCTIVITY (SRF'21) - INDICO
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Four years of successful operation at the EuXFEL 2021 International Conference on RF Superconductivity (SRF’21) Julien Branlard, for the EuXFEL Linac Operations Team Hamburg, 28.06.2021
Overview 2017 - 2021 Introduction – the EuXFEL Availability • Layout • Monitoring • Operating hours • Systematic trip review • Max gradient experiment Some key accelerator components • Detuning Cavities • Gun • AH1 • Klystrons Outlook • Cryogenics • CW tests • Long(er) flat tops Linac Operation • MARWIN3 • Linac setup • Cavities operation • Dark current and field emitters | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 2
The EuXFEL Accelerator Facility layout • Injector: Gun, A1, AH1 • L1: 1x RF stations (A2 = 4 cryomodules) • L2: 3x RF stations (A3-A5 = 3x 4 cryomodules) • L3: 21x RF stations (A6 – A25 = 21x 4 cryomodules) Page 3
Introduction XFEL : user facility Milestones (some) Machine time (in hours) • Dec. 2016 Cool down COVID-19 • Apr. 2017 First beam • May 2017 First SASE Commissioning • Sep. 2017 First users • Jul. 2018 Max energy: 17.5 GeV Early users • Oct. 2018 3 SASE beamlines • Nov 2018 Max bunch (2700) • Jan. 2019 Parallel user run in all 3 beamlines • Feb. 2020 30 keV photon energy • May 2021 100% availability for 1 week | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 4
Gun Operation NRF gun Parameter space and typical operation • NRF gun, 1 window, 10 MW klystron • 56 MV/m, ~ 6MW • RF flat top 600 usec max (typ. 560 usec) • Fast ramp up (
AH1 3.9 GHz Parameter space and typical operation • 8 SRF cavities, no piezo • 80 kWpeak klystron (CPI) • QL = 3.3e6 (3-stub tuners) • Vector sum operation Eacc = 5-7 MV/m / cav. Courtesy R. Jonas Pk = 6.3 kW • Pulse shape 750 usec fill + 650 usec flat • dA/A = 0.02 % dP = 0.02 deg • No incident over the last 4 years • Very reliable operation | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 7
HPRF 1.3 GHz 10 MW MBK klystrons • Typically operated between 3 and 6 MW Courtesy V. Vogel • Early problems with cooling water pipes corrosion (through radiation) now replaced • In 4 years, 3 klystrons moved out of tunnel for repair (2 water damage, 1 cathode) • 1 week for complete klystron exchange • On average 3 klystron events per week (arcs, breakdown) • On-going campaign to operate at minimal modulator HV settings (85% from saturation) • Klystron lifetime management to minimize down time when break down | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 8
Cryogenics Performance and cold compressor XFEL RF shutdowns • Initial cool down Dec. 2016 (2 weeks) • Very stable cryogenic conditions Pdiss He pressure = 30 mBar +/- 0.1 mBar • Exchange cold compressor motors every He pressure 4 months as preventive maintenance • Down time for complete cold motor exchange He flow less than 36 hours Stable He level and flow • Dynamic heat load compensation via heaters Heater power Courtesy S. Barbanotti Heater compensation | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 9
Linac Setup Two modes of operation: • low-VS : for beam energies 11.0 – 14.0 GeV • high-VS : for beam energies 14.5 – 16.5 GeV High-VS (max gradient) Energy overhead by placing Energy overhead by ramping • Cavities operating at max gradient all stations on crest all stations to max SP more radiation coming from RF • Cavities operating with almost no RF overhead almost at quench limit • Couplers, klystrons running with more power more arcs, sparks, etc.. • Overall, operating on the edge more trips Page 11
Cavity operation 776x 1.3 GHz TESLA cavities Typical operation conditions • Average gradient + spread • Coupler power (x4 for peak power) • Measured Q0 = 1 x 1010 Courtesy N. Walker | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 12
Cavity operation 776x 1.3 GHz TESLA cavities Typical operation conditions RF regulation • Detuning (+/- 18.5 Hz) • dA/A < 0.01 % (typ. 0.007 %) Detuning Mean: 0 Hz RMS spread: 18.5 Hz • Loaded quality factor QL = (4.6 +/- 0.05) x 106 • dP < 0.01 deg. (typ. 0.007 deg.) QL Mean: 4.60 ×106 RMS spread: 0.05 ×106 Courtesy M. Omet | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 13
Dark Current Radiation in the Tunnel Monitoring radiation New field emitter detected (Sept. 2020) RadFet RadCon MARWIN3 Administrative limit 500 uSv/h A12 operating above its operational gradient Position [m] Page 14
Field emitters Example: A24.M2.C7 (Oct. 2019) and A18.M3.C4 (Sept. 2020) A24.M2.C7 • Procedure • Park MARWIN at peak neutron radiation (often located at quadrupole) sudden FE onset observed by RadCon • Detune / retune cavities one at a time until field emitter is found • Once found, detune field emitter (30-40 kHz) A18.M3.C4 administrative limit 500uSv/h Page 15
AVAILABILITY
Monitoring the RF Availability XTL live report GOOD week machine BAD week study few isolated short trips pathological 2x machine-level trips Page 17
Systematic Trip Review Closer look at availability since 2019 • Weekly review by linac ops team • Review / tag the trips of the week • Update database • 8D review for trips > 4hrs down time Clarify root cause and update DB Courtesy S. Köpfke Page 18
High-Voltage (high-VS) Experiment • 31.08 – 18.10.2020 7 weeks at low-VS 6.3 SEU / week 56 SEU / week 70 SEU • 19.10 – 22.11.2020 5 weeks at high-VS * 60 * Although the high-V linac configuration was only really needed for 1 user week 50 Total Low-VS High-VS 40 x6 30 Availability % 97.9 98.7 95.6 20 Total operation time days 125.2 90.4 34.8 10 Number of events 0 hrs 300 124 176 36 37 38 39 40 41 42 43 44 45 46 47 Total down time hrs 64.7 27.9 36.9 7 LLRF failures 6 Quenches 5 Total Low-VS High-VS Limiters x2-3 4 Trips hrs 40.1 13.5 26.6 3 Linac off (access) hrs 18.3 10.7 7.6 2 Ramp down hrs 3.5 1.8 1.7 1 0 Development hrs 1.9 0.8 0.8 36 37 38 39 40 41 42 43 44 45 46 47 Page 19
Cavity Detuning Film credit : Nick Walker ® To date 23 detuned cavities (out of 776x 1.3 GHz) Nb. cav Reason Remark 4 Coupler over heating 1 Waveguide specification error known BEFORE tunnel installation 4 Excessive field emission or too low quench Eacc 1 Excessive dynamic heat loss Soft quenching ? 12 – 2 Maximum gradient investigation (w/o piezo) 2 were retuned since. Possibly more to come 3 (New?) field emitters 1 is clearly new; the other 2 unclear. Emergency Detune • First triggered in 2020 due to COVID-19 • Unclear if staff on-site could guarantee cryo operation • Manually detune all 784 SRF cavities (16 hours) • Developed a “1-button” emergency detuning tool (45 mins) Notes: • does not track the cavity detuning (only motor steps) • A17 had been previously detuned to test the tool • A9 motor driver failure (cryomodule 1 & 2) • runs / tracks all 52 motor drivers in parallel • Cavities “normally” detuned stay detuned • Needed in unlikely case of uncontrolled warm-up | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 20
Outlook Some short- to mid-term goals • Maintain and keep pushing toward higher availability • Automation • System health • Support from machine learning and AI • R&D for a CW upgrade of the EuXFEL • RF control challenge: CW in vector sum 150 usec 750 usec 650 usec 50 usec • R&D to extend RF flat top w/o changing infrastructure • Explore QL and fill time parameter space • Use fill and fall time of modulator pulse | 4 years of operations at EuXFEL | Julien Branlard, 28.06.2021 Page 21
Thank you Courtesy A. Dehne Special thanks to my colleagues for their help gathering the material for this talk: Valeri Ayvazyan, Serena Barbanotti, Frank Brinker, Stefan Choroba, Marie Czwalinna, Winfried Decking, Andre Gössel, Rolf Jonas, Siegfried Köpke, Björn Lautenschlager, Manuel Mommertz, Sven Pfeiffer, Christian Schmidt, Tobias Schnautz, Matthias Scholz and Nick Walker Contact MARWIN1 MARWIN2 MARWIN3 Deutsches Julien Branlard Elektronen-Synchrotron MSK Julien.branlard@desy.de www.desy.de +49 (0)40 8998 1599
You can also read