Enhancements Delivery Plan England and Wales - Entry Into Service (EIS) schedule March 2021 - Network Rail

Page created by Nicole West
 
CONTINUE READING
OFFICIAL

Enhancements Delivery Plan
England and Wales
Entry Into Service (EIS) schedule

March 2021
Network Rail’s obligation
The Enhancements Delivery Plan for England and Wales sets out the enhancements commitments that Network Rail has made to the Department for Transport and to other funders. Its
purpose is to provide transparency about the status of these schemes and to provide visibility of our plans to customers, stakeholders and the public.
Network Rail’s obligation is to publish Entry Into Service (EIS) milestones which represent the completion of our works to change the capability of the railway infrastructure. It will be for
passenger and freight operators to decide how and when to begin to use enhanced infrastructure.
In Control Period 6 we will agree enhancements with our funders through the Investment Decision Framework (IDF) and the Department for Transport’s (DfT) Rail Network Enhancement
Pipeline (RNEP) process. These have been developed following the Memorandum of Understanding which was developed and agreed between Network Rail and the DfT in 2016.1
Network Rail and funders will only commit to the delivery of an enhancement once we have developed the programme sufficiently to have a good understanding of its outputs, cost and
scope. This will allow us to make a Final Investment Decision (FID) to deliver these works. As such, EIS milestones will only be published in this plan once a scheme has passed a FID. It is
only at this point that there is sufficient certainty of outputs that NR can reasonably be held to account for the delivery of the programmes.
For all programmes that are yet to reach the point of taking a FID, DfT publish these in their RNEP document, which is updated annually: https://www.gov.uk/government/publications/rail-
network-enhancements-pipeline-autumn-2019-update
A separate Enhancements Delivery Plan is published to describe our Enhancements obligations in Scotland: https://www.networkrail.co.uk/who-we-are/publications-and-resources/

Contacting Network Rail
One of the reasons that Network Rail publishes an Enhancements Delivery Plan is to provide visibility of funded enhancements to potential third-party investors and to other railway
undertakings to assist them in planning their businesses. Enquiries related to specific schemes for these purposes should be addressed to the Principal Programme Sponsor, or other listed
contact, responsible for each programme. They are named in the document against each programme and their contact details are listed below.
General enquiries should be addressed to Network Rail using the contact details provided on our website: https://www.networkrail.co.uk/communities/contact-us/
Crossrail – Colin Prime, Principal Programme Sponsor – colin.prime@networkrail.co.uk
Thameslink – Paul Cumbers, Programme Manager – paul.cumbers@networkrail.co.uk
North of England Programme – Phase 5 – Andy Morgan, Principal Programme Sponsor – andrew.morgan@networkrail.co.uk
West Anglia Main Line Capacity, Kings Lynn to Cambridge 8 car, and Felixstowe Branch Capacity Enhancement – Sarah Jane Crawford, Principal Programme Sponsor –
sarahjane.crawford@networkrail.co.uk
East Coast Main Line Enhancements Programme – Ed Akers, Principal Programme Sponsor – edward.akers@networkrail.co.uk
Midland Main Line Programme, Market Harborough LSI – Gavin Crook, Principal Programme Sponsor – gavin.crook@networkrail.co.uk
New Cross Grid & Ashford to Ramsgate journey time improvement – Mark Ellerby, Senior Commercial Scheme Sponsor – mark.ellerby@networkrail.co.uk
Transpennine Route Upgrade (Intermediate Interventions only - Leeds Station Capacity improvements) – Kieran Dunkin, Principal Programme Sponsor – kieran.dunkin@networkrail.co.uk
Great Western Electrification and Capacity – Charles Varey, Principal Programme Sponsor – charles.varey@networkrail.co.uk
Thames Valley EMU Capability Works – Mike Foss, Principal Programme Sponsor – mike.foss@networkrail.co.uk
West of England DMU Capability, and Bristol East Junction Remodelling – Michelle Scogings, Principal Programme Sponsor – michelle.scogings@networkrail.co.uk
Reading, Ascot to Waterloo train lengthening programme and Denmark Hill Station – Kate Warner, Director of Sponsorship – kate.warner@networkrail.co.uk
Peak Forest to London freight – Thomas Drury, Sponsor – tom.drury@networkrail.co.uk
Doncaster to Immingham W12 gauge clearance & Northern Ports and Transpennine Capacity – Richard Iggulden, Senior Development Manager – richard.iggulden@networkrail.co.uk

1   https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/509545/mou-dft-network-rail-rail-enhancements.pdf
OFFICIAL

Northern Train Lengthening – Lawrence Cheung, Senior Sponsor – lawrence.cheung@networkrail.co.uk
Gatwick Airport station – Stephen Diplock, Senior Commercial Scheme Sponsor – stephen.Diplock@networkrail.co.uk
South West Rail Resilience Programme – Julie Gregory, Senior Commercial Scheme Sponsor – julie.Gregory@networkrail.co.uk
Southampton Freight Train Lengthening – Lucy Phipps, Commercial Scheme Sponsor – lucy.phipps@networkrail.co.uk
London Euston Congestion Measures (platform 8-11 ramp) – Nick de Bellaigue, Programme Director – nick.Debellaigue@networkrail.co.uk
St Albans City Station Passenger Capacity Project (Second Footbridge) – Nicholas Wilton, Sponsor – Nicholas.Wilton@networkrail.co.uk
University Station (Birmingham) – Simon Clifford, Senior Sponsor – Simon.Clifford2@networkrail.co.uk
East West Rail Phase 2 – Peter Hume, Principal Programme Sponsor – peter.hume@networkrail.co.uk
Reading Independent Feeder – Jill Poyton, Senior Sponsor – Jill.Poyton@networkrail.co.uk
Hope Valley Capacity – Scott Meadley, Senior Sponsor – scott.meadley@networkrail.co.uk
Dartmoor Line-Exeter to Okehampton – Kevin Miller, Senior Sponsor – Kevin.Miller@networkrail.co.uk

Activities and Milestones

 Ref.       Programme        Project         Network       Narrative                              Output                                   Activity/          Original   Updated      Status
 Code                                        Rail                                                                                          Milestone          Agreed     Date(s)
                                             Contact                                                                                                          Date
 CR001      Crossrail        -               Colin Prime   The Crossrail project will deliver a   The Crossrail project benefits are as    Key Output 6a      May-20*    n/a          *Subject
                                                           new integrated railway route           follows:                                 - Full                                     to change
                                                           through central London from            • New Crossrail train services will      Infrastructure                             control
                                                           Reading and Heathrow in the west       provide direct links from Reading        Capability to
                                                           to Shenfield and Abbey Wood in         and Heathrow to Paddington in the        support Stage
                                                           the east. The joint sponsors of the    west to Shenfield and Abbey Wood         4 operations
                                                           Crossrail project, the DfT and TfL,    in the east. With up to 24 Crossrail     with sufficient
                                                           have set-up a company called           trains an hour running through the       time for testing
                                                           Crossrail Limited (CRL) to act as      central section in each direction (at    Key Output 6b      Dec-20*    n/a          *Subject
                                                           the delivery agent. Network Rail is    peak times) a total of 10% will be       - Full                                     to change
                                                           one of CRL’s delivery partners.        added to London’s rail-based             Infrastructure                             control
                                                           The responsibility for the design      transport capacity; and                  Capability to
                                                           and construction of the works          • 28 existing surface stations will be   support Stage
                                                           outside of the central tunnel          upgraded with many of these              5 operations
                                                           section - known as the ‘On             stations also receiving platform         (including
                                                           Network Works’ (ONW) - was             extensions.                              Ilford, Romford
                                                           transferred to Network Rail when                                                Stations) with
                                                           Royal Assent was granted to the                                                 sufficient time
                                                           Crossrail project in July 2008.                                                 for testing
 CR004      Thameslink       -               Elena         The DfT Thameslink Programme           High capacity infrastructure to          EIS                Dec-18     n/a –        Complete
                                             Stebbings     aims to provide a step change in       support 24 train paths per hour          Infrastructure                project is
                                                           capacity on an extended                between St Pancras and Blackfriars       Authorised                    complete
                                                           Thameslink network thus providing      stations.                                KO2 final
                                                           new journey opportunities,                                                      milestone
                                                           congestion relief and capacity for
                                                           future passenger demand.

                                                                                                                                                                                                  3
OFFICIAL

Ref.    Programme       Project         Network      Narrative                              Output                                     Activity/        Original   Updated      Status
Code                                    Rail                                                                                           Milestone        Agreed     Date(s)
                                        Contact                                                                                                         Date
CR005   North of        Phase 5 –       Andy         25kV AC overhead electrification       The North of England Programme             EIS              Mar-19     Jul-19       Revised &
        England         Manchester      Morgan       between Manchester Victoria and        (NoEP) delivers conditional outputs        Infrastructure                           Complete
        Programme       Victoria to                  the Bromley Street (Manchester)        which provide additional capacity for      Authorised
                        Stalybridge                  area, new grid supply point at         more services, improvements to line
                                                     Stalybridge, associated power          speeds to reduce journey times and
                                                     cable from Stalybridge to Ordsall      electrify specific routes in the region.
                                                     Lane for Phases 4 and 5 NWEP
                                                     and infrastructure improvements to
                                                     give journey time savings.
A003    West Anglia     -               Sarah Jane   The project will relieve               Infrastructure to allow for an             EIS              May-19     n/a –        Complete
        Mainline                        Crawford     overcrowding on the West Anglia        additional two trains per hour to          Infrastructure              project is
        Capacity                                     Main Line. This scheme is              operate from Tottenham Hale to             Authorised                  complete
        Increase                                     intended to address the medium-        Stratford compared to the December
                                                     term demand arising from               2014 Timetable in which two trains
                                                     industrial and residential             per hour currently operate. Network
                                                     developments in the vicinity of        Rail will also deliver infrastructure to
                                                     Tottenham Hale, Northumberland         allow these services to be extended
                                                     Park and the new Meridian Water        beyond Tottenham Hale to a new
                                                     development.                           station at Meridian Water (funded by
                                                                                            external stakeholders)
A006    Kings Lynn to   -               Sarah Jane   The project is to deliver the          These services will relieve current        EIS              Jul-20     11th Dec-    Revised &
        Cambridge 8                     Crawford     infrastructure required to enable 8-   peak hour overcrowding and meet            Infrastructure              20           Complete
        car project                                  car Govia Thameslink Railway           CP6 passenger demand forecasts.            Authorised
                                                     (GTR) services to run on the           Currently the service is operated by
                                                     King's Lynn to Cambridge route,        4-car units.
                                                     during the peak hours.
EC001   East Coast      Werrington      Ed Akers     The Programme is driven by a           DfT have agreed that the ECML              EIS              Apr-21     Nov-21       Revised &
        Main Line       Grade                        strategic priority to increase         Enhancements Programme should              Infrastructure                           On target
        Enhancements    Separation                   capacity, improve passenger            provide infrastructure which enables       Authorised
        Programme       Power supply                 experience and accelerate journey      these outputs:                             EIS              Mar-24     n/a –        On target
                        upgrade phase                times between key cities. The          • An increase in capacity from 6 to 8      Infrastructure              project is
                        2                            outputs include implementation of      Long-Distance High-Speed services          Authorised                  on target
                                                     the InterCity Express Programme        (LDHS) between London King’s
                        Kings Cross                                                                                                    EIS              Mar-21     Jun-21       Revised &
                                                     on the East Coast Main Line,           Cross and Doncaster and from 5 to
                        remodelling                                                                                                    Infrastructure                           On target
                                                     power supply upgrades and an           6 LDHS paths between Doncaster
                                                                                                                                       Authorised
                                                     improved track layout to the north     and Newcastle per hour
                        Stevenage                                                                                                      EIS              May-20     Aug-20       Revised &
                                                     of Peterborough.                       • Maintaining 2 freight tph, using
                        Turnback                                                                                                       Infrastructure                           Complete
                                                                                            diversionary routes as far as
                                                                                                                                       Authorised
                                                     DfT have noted that the outputs        practicable
                                                     listed here are to be treated as       • A reduction in journey times for the
                                                     conditional as trade-offs may still    fastest LDHS services to 4 hours
                                                     be needed to be made as further        from London to/from Edinburgh and
                                                     work is completed by NR to             2 hours to/from London to Leeds.
                                                     develop the timetable.

                                                                                                                                                                                            4
OFFICIAL

Ref.      Programme       Project           Network        Narrative                               Output                                    Activity/          Original   Updated      Status
Code                                        Rail                                                                                             Milestone          Agreed     Date(s)
                                            Contact                                                                                                             Date
EM001     Midland Main    London to         Gavin Crook    This Enhancements Programme is          Key Output 1 for Entry into Service       EIS                May-20     Aug-20       Revised &
          Line            Corby                            part of a rail industry programme       Infrastructure Authorised:                Infrastructure                             Complete
          Programme -     Electrification                  that aims to transform travel to and    • Provision of 25kv electrification       Authorised -
                          and Capacity                     from London on the Midland              from the existing limits at Bedford to    Platform
          Key Output 1
                                                                                                   Kettering and Corby; providing
                          Upgrade                          Mainline during CP5 and CP6 and                                                   Lengthening
                                                                                                   traction power for 2 electric
                                                           improve the links between the core
                                                                                                   passenger train services.                 EIS                May-20     Jan-21       Revised &
                                                           centres of population and               • Enabling of improved journey times      Infrastructure                             Complete
                                                           economic activity in the East           through the delivery of key               Authorised -
                                                           Midlands and South Yorkshire.           infrastructure schemes                    Kettering
                                                                                                   • Additional capacity for a 6th Long-     Stabling
                                                                                                   Distance High-Speed service to            Facility
                                                                                                   serve between St Pancras and
                                                                                                   Kettering / Corby; and 3 freight paths    EIS                May-20     Jan-21 &     Missed &
                                                                                                   per hour between Bedford and              Infrastructure                Apr-21       Complete
                                                                                                   Kettering
                                                                                                                                             Authorised -
                                                                                                   • The capability of the network will
                                                                                                                                             Prioritised
                                                                                                   be enhanced through the extension
                                                                                                   of platforms at key stations south of     electrified
                                                                                                   Leicester                                 route
                                                                                                   • New stabling facilities will also be    EIS                Aug-20     Jan-21 &     Missed &
                                                                                                   provided at Kettering.                    Infrastructure                Apr-21       Complete
                                                                                                                                             Authorised -
                                                                                                                                             Full electrified
                                                                                                                                             route
ES003k    Market          -                 Gavin Crook    The driver for the project is to        The project will provide infrastructure   GRIP 6             Jun-19     n/a –        Complete
          Harborough                                       increase the line speed through         to increase the line speed between        Infrastructure                project is
          LSI                                              Market Harborough in                    Kettering and Wigston South               Authorised                    complete
                                                           order to support a journey time         Junction timing points in order to
                                                           improvement between London and          enable a reduction in Sectional
                                                           Sheffield.                              Running Time (SRT).
K004      New Cross       -                 Mark Ellerby   The project will provide increased      The project is a strategic upgrade        GRIP 6             Mar-20     n/a –        Complete
          Grid                                             traction power supply capacity for      and is part renewal funded in its         completion                    project is
                                                           DC electric services in South           replacement of existing obsolete          and EIS                       complete
                                                           London, North Kent and Sussex. It       66kV equipment and connections.
                                                           is required to provide additional       To provide base traction power
                                                           base capacity in the area for future    supply capacity for increased DC
                                                           train service increases.                electric train services into London in
                                                                                                   line with predicted future growth.
LNE001b   Transpennine    Leeds Station     Kieran         Additional capacity at Leeds            Leeds Station Capacity                    Phase 1 EIS        Dec-19     n/a –        Complete
          Route           Capacity          Dunkin         Station to support the operation of     Enhancements - Additional capacity                                      project is
          Upgrade –       improvements                     longer trains and additional            at Leeds Station to support the                                         complete
                                                           services on several routes. Leeds       operation of longer trains and                                                       Complete
          Intermediate                                                                                                                       Phase 2 EIS        Dec-20     n/a –
                                                           Station Capacity Enhancements           additional services on a
          Interventions                                                                                                                                                    project is
                                                           will also support the delivery of the   number of routes. The project will be
                                                           DfT’s infrastructure assumptions        delivered in the following phased                                       complete
                                                           within the Northern and                 strategy:                                 Phase 3 EIS        Dec-21     n/a –        On target
                                                           Transpennine franchise                  • Phase 1 - Recontrol of the                                            project is
                                                           commitments.                            signalling control system to the York                                   on target
                                                                                                   Rail Operating Centre (ROC)

                                                                                                                                                                                                    5
OFFICIAL

Ref.    Programme         Project          Network       Narrative                             Output                                    Activity/          Original   Updated      Status
Code                                       Rail                                                                                          Milestone          Agreed     Date(s)
                                           Contact                                                                                                          Date
                                                         Note that further outputs for the     • Phase 2 - The relocking of 8No.
                                                         Transpennine Route Upgrade are        existing signalling interlockings to
                                                         being developed by Network Rail       provide additional signalling capacity
                                                         and will be published in this EDP     • Phase 3 - A new 8-car platform
                                                         as a separate programme               (platform 0) and longer train
                                                         (Transpennine Route Upgrade)          standages on platforms 6. Track
                                                         once they have completed a Final      remodelling and associated
                                                         Investment Decision.                  resignalling to the West end of the
                                                                                               station to provide greater operational
                                                                                               flexibility.
W001a   Great Western     Bristol          Charles       The electrification of the GWML       Extension of the electrification of the   EIS                Nov-19     6th Jan-     Missed &
        Electrification   Parkway to       Varey         facilitates the introduction of       Great Western Main Line (GWML)            Infrastructure                20           Complete
                          Cardiff (excl.                 electric train operation delivering   from Maidenhead (the furthest             Authorised
                          electric                       significant journey time              extent of the Crossrail infrastructure
                                                                                               works) to Cardiff, including power
                          operation in                   improvements on key intercity
                                                                                               distribution works and clearance
                          the Severn                     routes and high seating capacity
                                                                                               works.
                          Tunnel)                        trains on suburban services
                          Wootton                        including into London Paddington.                                               EIS                CP6        Apr-19       Complete
                          Bassett                                                                                                        Infrastructure
                          Junction to                                                                                                    Authorised
                          Chippenham
                          East
                          Severn Tunnel                  Commission the fixed                  Enables Class 387 EMU’s and other         EIS                6th Jan-   31st May     Complete
                          (electric                      conductor beam in the                 electric stock to operate between         Infrastructure     20         -20
                          operation)                     Severn Tunnel                         Bristol Parkway and Cardiff.              Authorised
W002b   Great Western     IEP: Specific    Michelle      The project provides infrastructure   Infrastructure capacity                   Bristol            Dec-19     n/a –        Complete
        Capacity          GWML             Scogings      capacity enhancements to enable       enhancements as outlined in the           Parkway 4th                   project is
        Enhancement       Capacity                       the delivery of the Intercity         client (DfT) remit “Infrastructure        platform - EIS                complete
        Programme         schemes                        Express Programme.                    Output Specification” (IOS5) to           - Infrastructure
                                                                                               enable the operation of an enhanced       Authorised
                                                                                               passenger timetable from December
                                                                                               2019. At Bristol Parkway station, an
                                                                                               additional platform face, signalling
                                                                                               and track works.
WX003   Reading,          Feltham          Kate Warner   The project supports the delivery     The project will provide infrastructure   EIS                Dec-19     n/a –        Complete
        Ascot to          Platform                       of the 2012 HLOS capacity metric      to enable the operation of 10 car         Infrastructure                project is
        Waterloo train    Extensions                     for London Waterloo which             services on the Reading to London         Authorised                    complete
        lengthening       and Level                      indicates that it is necessary to     Waterloo and Aldershot via Ascot to
        programme         Crossing                       provide capacity to accommodate       London Waterloo routes. This will
                          Closure                        an additional demand of 9,700         relieve overcrowding, particularly
                                                         passengers in the three-hour          between Virginia Waterloo and
                                                         morning peak.                         London Waterloo in the morning
                                                                                               peak.

                                                                                                                                                                                               6
OFFICIAL

Ref.      Programme        Project   Network      Narrative                             Output                                   Activity/        Original   Updated      Status
Code                                 Rail                                                                                        Milestone        Agreed     Date(s)
                                     Contact                                                                                                      Date
F006a     Felixstowe       -         Sarah Jane   To relieve capacity constraints at    The scope of works includes              EIS              Dec-19     n/a –        Complete
          Branch                     Crawford     the port of Felixstowe such that      provision of a new 1.4km passing         Infrastructure              project is
          Capacity                                freight demand from Felixstowe in     loop at Trimley, crossing upgrades,      Authorised                  complete
          Enhancement                             CP6 and CP7 can be met.               crossing closures, a new bridleway
                                                  The project will provide              bridge, new S&C units, provision of
                                                  infrastructure to enable operation    diversionary route for FTN and
                                                  of up to 47 freight train paths per   signalling enhancements for the new
                                                  day in each direction on the          layout.
                                                  branch line to and from the Port of
                                                  Felixstowe.
F006b     Doncaster –      -         Richard      W12 gauge enhancement from            Gauge clearance for W12 container        EIS              Jun-19     n/a –        Complete
          Immingham                  Iggulden     Doncaster, (both Hexthorpe Jnc        traffic on the branch line between       Infrastructure              project is
          W12 gauge                               and Marshgate Jnc) to Immingham       Immingham and the East Coast             Authorised                  complete
          clearance                               and Killingholme. There are 29        Main Line, connecting the port with
                                                  foul structures that need to be       the network of ‘high gauge’ container
                                                  cleared to achieve W12 clearance.     routes.
F006c     Northern Ports   -         Richard      Priority interventions to increase    Entails double tracking a 400m           EIS              Dec-19     Dec-20 &     Revised &
          and                        Iggulden     freight capacity between the Port     stretch at the port boundary and         Infrastructure              Sept-21      On target
          Transpennine                            of Liverpool and the WCML and         installing flashing yellow aspects at    Authorised
          capacity                                Transpennine routes. An increase      Earlestown to ease approach
                                                  from 1 to 2 freight train paths       control.
                                                  between the Port of Liverpool and
                                                  Earlestown.
F006d     Peak Forest to   -         Thomas       Provision of an extended run          Infrastructure to allow longer trains    EIS              May-19     n/a –        Complete
          London                     Drury        round facility at Buxton to enable    with a gross trailing weight of 2600 –   Infrastructure              project is
          Freight                                 freight trains to be routed to/from   3000 tonnes between Peak Forest          Authorised                  complete
          (Buxton,                                the routes to Hindlow and Great       and the Midland Mainline and
          Hindlow/                                Rocks.                                ultimately destinations in London
          Dowlow)                                                                       and the South East.
LNE001c   Northern train   -         Lawrence     Programme of works across LNW         The work, which consists of              EIS              Apr-20     n/a –        Complete
LNW008    lengthening                Cheung       and LNE routes, with deliverables     extending c.120 platforms at 60          Infrastructure              project is
                                                  required for each timetable change    stations, will enable longer rolling     Authorised                  complete
                                                  from December 2017 to May 2020.       stock to be operated by Arriva Rail
                                                                                        North (ARN) to provide increased
                                                                                        capacity for passengers.

                                                                                                                                                                                      7
OFFICIAL

Ref.       Programme         Project         Network   Narrative                              Output                                      Activity/        Original   Updated      Status
Code                                         Rail                                                                                         Milestone        Agreed     Date(s)
                                             Contact                                                                                                       Date
IFDfT008   Gatwick           -               Stephen   The project will provide a new         By improving pedestrian journeys            EIS              Nov-22     n/a –        On target
           Airport station                   Diplock   station concourse above the            within the station, the scheme will         Infrastructure              project is
                                                       existing station platforms with        contribute to Network Rail’s                Authorised                  on target
                                                       increased space for passengers         objectives to deliver a safe, efficient
                                                       and an improved connection to          and reliable rail service. The scheme
                                                       Gatwick Airport South Terminal via     will help to meet Network Rail’s
                                                       the NR footbridge. It will also        commitment to put improved
                                                       include additional platform work,      accessibility at the heart of its station
                                                       refurbishment of the existing          re-designs. The scheme will also
                                                       station concourse and                  help to meet the Department for
                                                       overbridges. The project will          Transport’s objectives for improving
                                                       enable improved passenger              journeys and providing safe, secure
                                                       access via new stairs and lifts,       and sustainable transport. The
                                                       while it also aims to provide          scheme was recommended by the
                                                       increased circulation space and a      Interim Report of the Airports
                                                       modern open plan ticket retailing      Commission in 2013.
                                                       hub.
W016       South West        Phase 1         Julie     The South West Rail Resilience         The output of this programme is to          Resilience       Jul-20     n/a –        Complete
           Rail Resilience   (Marine         Gregory   Programme aims to provide a            deliver a robust level of resilience for    delivered                   project is
           Programme         Parade,                   resilient railway for the south-west   the next 100 years, considering                                         complete
                             Dawlish)                  of England. The only railway line      climate change including sea level
                             Phase 2                   connecting much of Devon and all       rise. The level of resilience to be         Resilience       Aug-22     n/a –        On target
                             (Colonnade to             of Cornwall to the rest of the UK      delivered equates to reducing the           delivered                   project is
                             Coastguard’s              rail network runs along the            probability of the railway being                                        on target
                             Ramp,                     vulnerable coastal section             closed for more than a week to one
                             Dawlish)                  between Dawlish Warren and             in 100 years; the probability of a
                             Phase 3                   Teignmouth. This stretch of            closure between 2 days and a week           Resilience       Sep-23     n/a –        On target
                             (Parson’s                 railway is subject to the twin         to no more than once every 20 years         delivered                   project is
                             Tunnel North              threats of coastal and geotechnical    on average and all other smaller                                        on target
                             Portal)                   encroachment. In 2014 the railway      disruption events to be reduced
                                                       here was closed for 6 weeks            compared to current levels.
                                                       following the breaching of the sea
                                                       wall at Dawlish and a subsequent
                                                       landslip of cliffs near Teignmouth.

                                                                                                                                                                                               8
OFFICIAL

Ref.   Programme       Project   Network       Narrative                               Output                                    Activity/        Original   Updated      Status
Code                             Rail                                                                                            Milestone        Agreed     Date(s)
                                 Contact                                                                                                          Date
W015   Bristol East    -         Michelle      Remodelling of the Bristol East         The outputs of the programme are:         EIS              Sept-21    n/a –        On target
       Junction                  Scogings      Junction has been identified as         - Additional capacity to support          Infrastructure              project is
       Remodelling                             playing an important role in the        service enhancements, including           Authorised                  on target
                                               future strategic development of the     MetroWest, and thus, support future
                                               rail network in the Greater Bristol     demand growth.
                                               area and Western Region.                - Resilience performance: de-
                                               Network Rail’s Western Route            confliction of moves at the station
                                               study identified that additional        area and the removal of the
                                               services into Bristol Temple            bottleneck at Filton Bank, delivering
                                               Meads were required to                  better performance and a more
                                               accommodate future rail demand.         reliable service for passengers.
                                               The remodelled layout of Bristol        - Reduction of asset maintenance
                                               East Junction will provide              times.
                                               additional capacity to support          - An average two-minute journey
                                               efficient running of future service     time saving on some London
                                               enhancements such as MetroWest          Paddington to Bristol services.
                                               and optimise the capacity works
                                               already delivered in the route.
F604   Southampton     -         Lucy Phipps   Enhance the network, enabling it        Most works are planned for delivery       EIS              Feb-21     n/a –        Complete
       Freight Train                           to operate freight trains of up to      during January and February 2021,         Infrastructure              project is
       Lengthening                             775 metres in length from the port      in three stages;                          Authorised                  complete
                                               of Southampton through to the           Stage 1 is the introduction of a
                                               West Midlands along the West            temporary buffer stop and putting
                                               Coast Main Line, thereby                out-of-use some Freight-only used
                                               increasing capacity of existing         lines. Stage 2 is the introduction of
                                               freight trains by circa 20%,            the Redbridge Goods Line and
                                               and supporting environmental            bringing the remodelled Maritime
                                               targets by enabling larger volumes      West to Redbridge into operational
                                               of goods to be transported across       use. Stage 3 is the introduction of all
                                               the country in a much more              remaining altered infrastructure into
                                               sustainable manner by freight           operational use and the raising of
                                               operators utilising the rail network.   line speeds.
S605   Denmark Hill    -         Kate Warner   After significant growth in             The central aim of this project is to     EIS              Jul-21     n/a –        On target
       Station                                 passenger numbers in recent             eliminate passenger crowding issues       Infrastructure              project is
                                               years, Denmark Hill’s current           at the station entrances and within       Authorised                  on target
                                               station layout severely constrains      the station by the provision of a
                                               pedestrian flow creating chronic        second northern station
                                               congestion. This is as a result of      entrance/exit on Windsor Walk.
                                               growing employment in the area          There will also be changes to
                                               (including two major hospitals          platforms including the provision of
                                               adjacent), a resulting increase in      new canopies, that will encourage
                                               the number of services that call at     the use of the new entrance.
                                               the station, including the relatively   Secondary aims are to reduce
                                               recent introduction of London           concerns over safety and dwell time
                                               Overground services that now            performance on the platforms, by
                                               operate through the station.            encouraging passengers to use the
                                                                                       eastern end of the platforms more.

                                                                                                                                                                                      9
OFFICIAL

Ref.       Programme        Project        Network        Narrative                               Output                                    Activity/         Original   Updated      Status
Code                                       Rail                                                                                             Milestone         Agreed     Date(s)
                                           Contact                                                                                                            Date
S636       Ashford to       -              Mark Ellerby   Support economic development in         Increase the current linespeed from       EIS               May-23     n/a –        On target
           Ramsgate                                       East Kent by increasing the             40 mph to 55 mph through track            Infrastructure               project is
           journey time                                   existing linespeed to reduce            enhancements and level crossing           Authorised                   on target
           improvement                                    journey times.                          works.
           (Phase 2)
LNWS602b   London           Platforms 8-   Nick de        The ramp, used by >40% of the           Demolition of three retail units and      EIS               May-21                  Revised &
           Euston           11 ramp        Bellaigue      station’s passengers, is the most       relocation of a platform level ticket     Infrastructure               Sep-21       On target
           Congestion       widening                      significant pinch-point at Euston       office to increase the useable ramp       Authorised
           Measures                                       and has been identified as the          width from 3.9 metres to the
                                                          highest priority measure required       maximum achievable width of 9.0
                                                          to address station congestion and       metres.
                                                          safety.
EM601      St Albans City   -              Nicholas       Significant passenger growth            Installing a second footbridge at St      EIS               Jan-22     n/a –        On target
           Station                         Wilton         meant St Albans City station was        Albans City Station will improve          Infrastructure               project is
           Passenger                                      identified as needing congestion        passenger comfort and journey             Authorised                   on target
           Capacity                                       relief in CP6.                          experience, including improving
                                                          Measures have been put in place         journey times through the station. It
                                                          to alleviate as far as practicable in   will also mitigate the potential
                                                          the short-term. A second                significant safety risk from
                                                          footbridge is the optimum solution      overcrowding, especially at times of
                                                          for the station going forward,          perturbation, which would otherwise
                                                          particularly during times of            require operational interventions.
                                                          perturbation and by easing the          Additionally, it will improve
                                                          issues of the use of Platform 2 for     operational flexibility in timetabling
                                                          evening peak services.                  trains in the evening peak.
LNWS610    University       -              Simon          The project involves enlargement        The project will deliver a new station    EIS               Aug-22     n/a –        On target
           Station                         Clifford       of University Station (Birmingham)      building with enhanced passenger          Infrastructure               project is
           (Birmingham)                                   to address current issues of            facilities; a second wider footbridge;    Authorised                   on target
                                                          crowding, congestion, safety and        a link footage to the University
                                                          performance at the station and to       campus and wider platforms.
                                                          accommodate projected growth in
                                                          passenger numbers over the next
                                                          25 years.
CR003a     East West Rail   -              Peter Hume     East West Rail (EWR) will               EWR Phase 2 will reinstate and            Infrastructure    Dec-24     n/a –        On target
           Phase 2                                        contribute to the Government’s          upgrade the route between Bicester        EIS to enable                project is
                                                          vision to unlock economic growth        Village and Bletchley, with               introduction of              on target
                                                          and new housing and employment          construction of a new station at          services
                                                          opportunities in the Oxford-            Winslow, and new ‘high level’             (expected
                                                          Cambridge Arc through the               platforms at Bletchley. This will allow   between Dec-
                                                          provision of improved rail              two trains per hour to operate            24 and Sept-
                                                          connectivity. EWR has a staged          between Oxford and Milton Keynes          25)
                                                          output with three Connection            Central, and will provide capacity for
                                                          Stages, the first of these -            a freight path every two hours in
                                                          Connection Stage 1 (Oxford to           each direction.
                                                          Milton Keynes) is supported by
                                                          Network Rail’s EWR Phase 2
                                                          project works.

                                                                                                                                                                                                  10
OFFICIAL

 Ref.     Programme        Project   Network        Narrative                           Output                                     Activity/         Original    Updated      Status
 Code                                Rail                                                                                          Milestone         Agreed      Date(s)
                                     Contact                                                                                                         Date
 W001c    Reading          -         Jill Poyton    Reading Independent Feeder          This project will improve reliability of   EIS               Apr-23      n/a –        On target
          Independent                               (RIF) will provide an additional    passenger services and support the         Infrastructure                project is
          Feeder                                    high-voltage power supply from      electric timetable, as well as             Authorised                    on target
                                                    the National Grid to the Great      providing greater flexibility for
                                                    Western Main Line (GWML).           maintenance regimes.
 CR005    Hope Valley      -         Scott          The scheme addresses poor           This scheme delivers upgraded rail         EIS               Dec-23      n/a –        On target
          Capacity                   Meadley        connectivity and passenger          infrastructure across the route            Infrastructure                project is
                                                    capacity in the Hope Valley         between Manchester and Sheffield           Authorised                    on target
                                                    corridor. The scheme will allow     to increase capacity and improve
                                                    more frequent passenger services    reliability, but also supports
                                                    to operate on the route while       economic growth and “levelling up”
                                                    maintaining access for freight      opportunities.
                                                    services.
 W616     Dartmoor Line-   -         Kevin Miller   This project will enable the        Upgrade of the infrastructure              Infrastructure    Target:     n/a –        On target
          Exeter to                                 restoration of regular year-round   between Okehampton and Coleford            EIS to enable     Autumn      project is
          Okehampton                                passenger services between          Junction will enable the Operator to       introduction of   2021        on target
          (Restoring                                Exeter and Okehampton.              introduce an initial two hourly            Passenger
                                                                                                                                                     Backstop:
          Your Railway)                                                                 passenger service, followed by an          Operations (2
                                                                                                                                                     12 Dec
                                                                                        hourly service between Okehampton          hourly)
                                                                                                                                                     2021
                                                                                        and Exeter St David’s, with some
                                                                                                                                   Infrastructure    31          n/a –        On target
                                                                                        services also serving Exeter Central.                        October -
                                                                                                                                   EIS to enable                 project is
                                                                                                                                   introduction of   2022        on target
                                                                                                                                   Passenger
                                                                                                                                   Operations
                                                                                                                                   (Hourly)

We’re transforming, making it easier for other organisations to invest in, and build on
the railway.
Providing valuable opportunities for other organisations to invest in and build on the railway reduces the tax-payer burden. The increased
competition drives down cost, while also increasing efficiency, creativity, and innovation.
Further information on Network Rail’s Open for Business initiatives can be found on our website: https://www.networkrail.co.uk/industry-
commercial-partners/third-party-investors/network-rail-open-business/
Contact details for our Business Development Directors in each region can also be found on our website:
https://www.networkrail.co.uk/industry-commercial-partners/third-party-investors/network-rail-open-business/opportunities-for-third-parties/

                                                                                                                                                                                          11
You can also read