Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council

Page created by Ashley Klein
 
CONTINUE READING
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
        Monthly Review > May 2021

 Capital Works
Monthly Review
         May 2021

                                    1
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                                                                         Monthly Review > May 2021

OVERVIEW ........................................................................................................................................................ 3

SA F ET Y ............................................................................................................................................................ 4

1.1.        Summary ................................................................................................................................................ 4
1.2.        Incidents and Injuries ............................................................................................................................. 4
1.3.        Lost Time Injuries & Days Lost .............................................................................................................. 5
CA PI TAL PR O J E CT U PD AT E S ................................................................................................................ 6

2.1.        Capital Summary Report........................................................................................................................ 6
2.2.        Financial Performance ........................................................................................................................... 6
2.3.        Capital Projects Phases for May 2021................................................................................................... 8
2.4.        Key Contracts Approved for May 2021 .................................................................................................. 8
PO RTFO L IO M AN AG E M ENT O F FI CE ................................................................................................... 9

3.1         Monthly Achievements ........................................................................................................................... 9
DE S IG N S ER V IC E S ................................................................................................................................... 10

4.1         Design Summary Report...................................................................................................................... 10
4.2         Survey Office Summary Report ........................................................................................................... 10
CO NT RA CT S ER VI C E S ............................................................................................................................ 12

5.1         Resurfacing Reseal Program 2020/2021 ............................................................................................ 12
5.2         Caping Road, Bloomsbury Bridge Replacement ................................................................................. 13
5.3         Park Improvement Projects ................................................................................................................. 14
5.4         Koumala Water Quality Upgrade – Water Treatment Plant................................................................. 16
5.5         Yakapari Seaforth Road Shared Path Stage 1 - Seaforth Reservoir Road to Aviland Drive .............. 17
5.6         Yakapari Seaforth Road Shared Path Stages 2 & 3 - Seaforth Reservoir Road to Aviland Drive ...... 18
5.7         Pioneer River, Estuary Fish Habitat Improvement Project .................................................................. 19
5.8         Resurfacing Reseal Program 2021/2022 ............................................................................................ 20
5.9         Culvert Replacement Package ............................................................................................................ 20
MA JO R P RO J E CT S ................................................................................................................................... 21

6.1         Northern Entry Statement Bruce Hwy Ring Road Landscaping .......................................................... 21
6.2         Fifth Lane ............................................................................................................................................. 22
FI ELD S ER V IC E S ....................................................................................................................................... 23

7.1         Midge Point Water Network Upgrade .................................................................................................. 23
7.2         Milton St/ Alfred St Signalised Intersection .......................................................................................... 24

                                                                                                                                                                      2
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                                Monthly Review > May 2021

OVERVIEW
This report is for Capital Works Department activities during the month of May 2021. Significant items in this
period include:

•     One LTI incurred for the month.

•     The YTD capital project spend is $74.2M which is approximately $1.9M below the YTD forecast of
      $76.1M (approximately 97.5%).

•     Projects where construction was completed* during the May period include:

      o      Bus Shelter & Turnaround - Magee's Rd, Bloomsbury
      o      Shoulder Sealing, Mumby Street, Koumala - Bull Street to Andrew Street
      o      Long Distance Bus Facility, Victoria & Tennyson Streets
      o      Field of Dreams Museum - Ramp Replacement
      o      Bluewater Quay Café Roof and Exhaust Replacement
      o      MECC - PixPad Replacement
      o      Gargett Bore No. 1 Renewal
      o      Gargett Bore No. 2 Renewal
      o      Retic - Meter Replacement Planned
      o      Hogans Pocket Landfill, Cell 1 Batter Chute Repairs
      o      Retrofitting Permanent Shade Structures - Eimeo Esplanade parks
      o      Caping Road Bridge Replacement
      o      Library & Artspace Hearing Loops Installation
      o      Schapers Road, Glenella, Rehabilitation, Davey to Pioneer St
      o      Nell Baker Park, Marian - Critical Renewal
      o      Pioneer River, Estuary Fish Habitat Improvement Project
      o      Mogford Street, West Mackay Drainage Installation - Simpson to Field
      o      6 River Street - Demo Building and Salvage Operation
      o      Repairs to Pioneer River levee - UQID No.25 Replacement Outlet Structure
      o      Tourist Information Centre Roof Replacement

* Note construction means practical works were completed however project accounts remain open to close
  out financials and to manage defects and maintenance periods, and as constructed/handover documents.

Jim Carless
Director Capital Works

                                                                                                                 3
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                                   Monthly Review > May 2021

SAFETY
1.1.       Summary

In May 2021:

       •   Eleven safety interactions were undertaken.
       •   Two site safety inspections were undertaken.
       •   91% of monthly action plans activities were carried out.

One incident was reported in May

1.2.       Incidents and Injuries

The following incidents involving a contractor was reported:

       •   While on-site for a prestart meeting a dog attacked; latching onto left sleeve and scratching arm but
           didn't manage to bite.

Each incident is investigated, and appropriate corrective measures implemented to reduce future risks.

                                                                                                                   4
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                                    Monthly Review > May 2021

1.3.       Lost Time Injuries & Days Lost

                                                            2018-19              2019-20              2020-21
                   Department                          LTI
                                                                 Days
                                                                            LTI
                                                                                      Days
                                                                                                 LTI
                                                                                                            Days
                                                                 Lost                 Lost                  Lost
 Contract Services
 Design Services
 Field Services
 Major Projects                                                                                   1         10
 Portfolio Management Office
 Capital Works Total                                    0             0      0             0      1         10

For the 2020-21-year, one lost time injury has been recorded.
       •   In April, A worker slipped on wet grass injuring their knee. Ten days were lost in May as they
           recovered.

                                                                                                                   5
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                                                                                   Monthly Review > May 2021

CAPITAL PROJECT UPDATES
2.1.          Capital Summary Report

Following is the capital financial summary for the YTD delivery to end of May 2021.

The current approved 2020/21 amended budget is $108.5M.

The YTD capital project spend is $74.2M which is approximately $1.9M below the YTD forecast of $76.1M
(approximately 97.5%). The top five projects underspent account for $1.7M of this variance. Context and
comments on each variance can be found on page 7 of this the report.

The project spend to the end of May is $74.2M, approximately $34.3M below the 20/21 Amended Budget of
$108.5M (68.4% delivered against 20/21 Amended Budget).

2.2.          Financial Performance

The table below summarises the year to date financial summary for the 2020/21 Capital program at the end of
May 2021.

                                               Capital Projects Expenditure 2020/2021
                                                                                  May 2021
                                                                                                                                                                       % Spent of
                                                 Original Budget (inc                                                                                 % Spent of YTD   Approved
                       Department                        Carryovers)        Approved Budget       Current Forecast       YTD Forecast      YTD Actual       Forecast      Budget
Development Services                                       3,589,180                309,924               283,018            242,798         215,325         88.68%          69%
Organisational Services                                        5,788              1,132,622             1,106,638            447,720         397,072         88.69%          35%
Community & Client Services                                  257,963              1,214,280             1,182,179            532,309         552,530        103.80%          46%
Engineering                                                2,091,110              1,653,166             1,662,270            988,062         728,368         73.72%          44%
Commercial Infrastructure                                  2,850,588              3,704,591             3,158,979          2,026,631        1,991,238        98.25%          54%
Procurement & Plant                                      10,826,231               8,621,217             8,377,639          6,764,927        6,028,193        89.11%          70%
Information Services                                       1,150,890              1,311,963             1,325,685          1,061,943         940,319         88.55%          72%
Works For Queensland Funding Project                       4,375,081              5,523,212             5,074,594          4,381,498        4,130,414        94.27%          75%
Works For Queensland Round 2 Funding Project                  21,759                 21,759                21,759             21,759                0         0.00%           0%
W4Q & Fed’s COVID Funding                                  6,782,253              8,273,768             7,831,644          5,303,981        5,432,161       102.42%          66%
NDRRA                                                      1,027,567              1,664,283             1,664,702          1,661,555        1,664,838       100.20%         100%
Capital Works Management                                            0                 8,000                 8,039                  39           7,908    20142.31%           99%
Design Program                                           14,439,895               4,284,756             3,998,916          2,879,356        2,602,658        90.39%          61%
Major Projects                                           23,742,119              18,814,491            17,707,617         14,176,723       13,405,093        94.56%          71%
Field Services                                           15,433,958              15,542,540            13,579,364         11,669,824       11,692,051       100.19%          75%
Contract Services                                        41,690,374              36,445,697            30,175,942         23,975,042       24,432,667       101.91%          67%
Portfolio Management Office                                  550,616                      0                      0                  0               0         0.00%           0%
Total                                            $     128,835,373      $      108,526,269    $       97,158,985     $    76,134,168    $ 74,220,834         97.49%       68.39%
Capital Expenditure                                    126,835,708             106,160,506            95,112,845          74,711,220      72,863,478         97.53%       68.64%
Operational Expenditure                                   1,999,665               2,365,762             2,046,141          1,422,948       1,357,356         95.39%       57.37%

                                                                                                                                                                                6
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                               Monthly Review > May 2021

Capital Spend by Department for May 2021

The table below summarises the year to date financial summary for the 2020/21 Capital program at the end of
May 2021.

Capital Expenditure Forecast 2020/21

The top five variances (underspend) between actuals and forecast for the month of May are:

 Project   Description                 Comments                                                   Variance
 10390     Plant & Equipment -         Ongoing supply issues combined with delayed delivery       ($736,733)
           Replacement Program         of large trucks requiring significant body builds e.g.,
                                       library truck and road patching truck.

 22013     Mackay Animal Pound         Construction works have incurred delays due to a           ($342,558)
           New Facility                number of matters including the following:
                                       - Wet weather
                                       - Construction issues realised during construction
                                       - Poor subgrade conditions encountered onsite
                                       - Awaiting material supply for remediation works of poor
                                       subgrade

 22317     MECC - Radio                Freight delays in the delivery of the equipment.           ($224,322)
           Microphone System
           Replacement

 52259     Fifth Lane Reconstruction   Contractor   delays     in    supplying     supporting     ($220,500)
                                       documentation. Project is running relatively on track.

 53902     Patch St & Cyril McKie      Construction works delayed due to wet weather during       ($250,070)
           Crt, Sarina Pavement        period where significant pavement material supply was
           Rehabilitation/R            expected. This has delayed some of these works.

                                                                                                               7
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                               Monthly Review > May 2021

2.3.    Capital Projects Phases for May 2021

The below graph shows the phases of capital projects as at the end of May 2021.

2.4.    Key Contracts Approved for May 2021

Contracts finalised and approved during May 2021 is valued at $11,023,458.76

Below is a listing of the key contracts awarded during the same period.

                                                  Design /        Amount Award
 Contract                                                                                Contractor
                                                Construction        (ex GST)
 MRC 2021-055 CCTV and Solar Lighting of         Construction      $744,467.06      J-Nine Pty Ltd T/A Roy
 Boat Ramps and Car Parks                                                           Powell Security

 MRC 2021-063 Package 1 Mackay                   Construction     $2,198,611.66     Seaforth Civil Pty Ltd
 Paradise Street, George Street to Henman
 Street Reconstruction

 MRC 2021-066 Asphalt and Bitumen                Construction     $3,027,073.71     RPQ Mackay Pty Ltd
 Release Package 21/22

 MRC 2021-078 Bedford Road Water Main            Construction      $593,213.00      Roebuck Civil Pty Ltd
 Replacement

 MRC 2021-080 Package 6 Juliet Street            Construction     $1,145,059.33     Bellwether Contractors
 Rehabilitation – George to Boddington                                              Pty Ltd
 Street

 MRC 2021-086 Package 7 Warland Street,          Construction     $2,968,794.00     Bellwether Contractors
 Stages 1,2,3                                                                       Pty Ltd

                                                                                                             8
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                                 Monthly Review > May 2021

PORTFOLIO MANAGEMENT OFFICE
3.1       Monthly Achievements

Following on from our presentation to the Executive Leadership Team in April of the Enterprise Project
Management Framework (EPMF) review, we have working on some priority actions which include:

      •   Working with People & Culture to develop some recommended training packages for EPMF users.
      •   Collaboration with stakeholders to understand where document duplication exists; and
      •   Networking with local private industry to undertake further benchmarking of the EPMF.

In line with future planning for the LTFF, in May we released the 21/22 quarterly assessments dates for new
and renewal projects coming into the program, Asset owners need to have their Concept and Business Cases
in by the designated dates to be assessed and inclusion in the budget review process. To ensure adherence
to the designated dates in the weeks prior to rounds closing the Portfolio Management Office (PMO) will be
facilitating training sessions focusing on initiating and work flowing entries in SharePoint Online (The System).

Looking at improvement initiatives for the Program Development Review Group (PDRG), the PMO have been
working with Sustainability Officer Tim Ey for insight on identifying and documenting the Environmental
Sustainability aspects of project submissions. This work aims to improve the skillsets of our users for both
completing submissions and performing assessment responsibilities as part of the PDRG.

With the LTFF allocation of project funding and revised delivery year underway, the PMO team has continued
to work with individual delivery teams to develop individual programs of works for the 2021-2022 Capital Works
projects.

First pass master programming has been achieved with ongoing adjustments occurring as the scheduling team
make up lost time from the receipt of the initial financial information.

We are on target with the Master program planned for final time-line review and baselining in late July as per
previous years.

The PMO team have been working with stakeholders to improve project delivery visibility for reporting and
subsequent implementation into the Master Program.

We have been working closely with the Assets team to significantly reduce the value in the WIP, we are working
through introducing more defined processes, to close out projects in a timelier manner.

                                                                                                               9
Capital Works Monthly Review - May 2021 - Capital Works Monthly Review May 2021 - Mackay Regional Council
Capital Works
                                                                               Monthly Review > May 2021

DESIGN SERVICES
4.1     Design Summary Report

Overview

Design Services commenced and completed several notable design projects during this period.

Detailed design has commenced for the upgrade for Seaforth Esplanade. It involves several disciplines across
playground, landscape and civil components needed for this high-profile project.
Preliminary design options of the access shuttle-track for the mountain bike trail are being ground-proofed as
the project enters the feasibility stage of alignments determined through desk-top analysis. This will allow
concept estimates to be developed with a reduced contingency allowance through a better appreciation of the
anticipated risk components.

Designs Completed

     Pioneer River Shared path stage 2 connection to Gooseponds Creek
     Creek and Lorne Road intersection upgrade
     Boundary Road and Jack Connor Dr Intersection upgrade
     Sewer Pump Station Refurbishments
     Kelly’s Road, Dalrymple St, Field and McGinn, and Maud St Culvert replacements
     Victoria St footpath renewal
     Fursden St Water Main upgrade

Notable Designs in Progress:

•     Shakespeare Street widening immediately west of Nebo Road int.
•     Pioneer St and Glenella Richmond Rd Pavement Rehabilitation
•     Willets Road Shared Path Gooseponds Bridge
•     Multiple Reservoir Refurbishments

4.2     Survey Office Summary Report

Overview

The surveyors were kept busy in May completing many service locations for Capital Works projects. They
also completed additional survey for the Northern Beaches Community Hub and the Mountain Bike Trail Head
in Finch Hatton to progress the concept plans for these major projects.

Surveys were completed for:

     Anzac Av Accessibility Improvements
     Marwood Sunnyside Rd Shoulder Widening
     Bucasia Green Waste Facility
     Walkerston Green Waste Facility
     Walz La Drainage Investigation
     Additional survey for the Mountain Bike Trail Head in Finch Hatton
     Additional survey for the Northern Beaches Community Hub
     Service Locations –
             Evans Av Water Main
             Lester Hansen St Water Main
             Mackay Bucasia Rd Water Main
             Mirani Boldon Rd Culvert
             Phillip Street and North View Terrace, Mt Pleasant Water Main Upgrade
             Range Rd Water Main
             Seaforth Esplanade Reserve
             Yakapari Seaforth Rd Shared Pathway
     Sewer Pump Station Refurbishments 20/21 – Sunset Blvd, Magpie St, Patch St, Keeleys Rd

                                                                                                           10
Capital Works
                                                                                            Monthly Review > May 2021

Figure 1: Taking high accuracy GPS measurements at the Blacks Beach Reservoir. This is part of continued works to replace the
permanent survey marks that will be destroyed during the upcoming reservoir refurbishment. Working at heights procedures were
                                                     strictly implemented.

                                                                                                                                11
Capital Works
                                                                                  Monthly Review > May 2021

CONTRACT SERVICES
5.1   Resurfacing Reseal Program 2020/2021

Overview

The resurfacing and rehabilitation program comprises resurfacing works on various streets and roads around
the region. Resurfacing includes two types of treatments, one being Asphalt on urban streets and roads, the
other Bitumen Spray Resealing on rural roads. Resurfacing works are carried out to protect the pavement and
extend the road pavement life.

Project Status

                                                 Completion
 Activity         Delivery     Start Date                            Budget              Comments
                                                   Date
 Asphalting Works 2020/2021
 Construction     External       Early               Early         $2,115,379   Works program significantly
                                 March               June                       complete, expect completion by
                                                                                end of May and as constructed
                                 2021                2021
                                                                                information supplied by early
                                                                                June.
 Resealing Works 2020/2021
 Construction     External        Early               Mid           $870,202    Works Commenced, approx.
                                  April              June                       60% complete to date,
                                                                                forecasted completion of
                                  2021               2021
                                                                                physical works by mid-June
                                                                                and line marking and as
                                                                                constructed info by end of June
 Total Resurfacing Reseal Program 2020/2021                       $2,985,581

Recent Project Activities

     Fulton Hogan have completed the asphalting works, line marking to be completed on the final roads
      expected handover documentation to be completed early June.
     The RPQ have progressed well towards the end of the month with several sites completed, some issues
      arising from the contractor supplied spray rates which are significantly higher than tendered allowances,
      Council working with Contractor to confirm conformity with specification, current program has RPQ
      finishing prior to the end of June.

                                          Figure 2: Kinchant Dam Road Works

                                                                                                             12
Capital Works
                                                                                          Monthly Review > May 2021

5.2   Caping Road, Bloomsbury Bridge Replacement

Overview

The Caping Road timber bridge crossing is located on the O’Connell River approximately 9km north of
Bloomsbury. It is a low-level river crossing servicing an isolated agricultural community with the bridge regularly
inundated preventing access. During inundation the bridge is regularly damaged. A recent condition
assessment found several components in poor condition requiring replacement. It was determined to construct
a new bridge to replace the existing floodway crossing. The new structure once completed will significantly
improve the level of service to impacted residents with improvements to freight efficiency for market access by
graziers.

Project Status

                                                 Completion
 Activity          Delivery     Start Date                             Budget                   Comments
                                                   Date
 Construction      External       Late              Early            $1,381,339       Construction completed in
                                November           May 2021                           early May 2021.
                                  2020

Recent Project Activities

     Construction completed and bridge opened to traffic as of 04 May 2021.

                               Figures 3 & 4: Bridge and approach construction complete

                                                                                                                  13
Capital Works
                                                                               Monthly Review > May 2021

5.3   Park Improvement Projects

Overview

Council is delivering a program of Park renewals for the community to provide well designed parks and open
space networks which cater for the changing needs of the community and to promote outdoor social and
recreational activities.

The equipment in the playgrounds has been in service for more than the prescribed operational life and has
been assessed as requiring replacement. Work in these parks includes the replacement and/or adjustment to
the softfall edging, softfall depth and/or sub-soil drainage servicing these playgrounds as well as hard
landscaping and soft landscaping, to various extents depending on the park.

The Park upgrades are at various locations within the region including, Sarina, South Mackay, Eimeo, Ooralea,
Marian and Shoal Point.

Project Status

                                        Completion
 Activity          Delivery   Start Date                         Budget                Comments
                                          Date
 Ron Anderson Park & Busuttin Drive Park
 Construction      External      Mid           End of           $494,981      Contractor to address
                              November      February 2021                     outstanding defects by end of
                                2020                                          June

 Canecutters Park
 Construction      External     January        Stage 1          $685,999      Stage 1 works are complete
                                 2021         Complete                        on site.
                                               Stage 2
                                                 Mid                          Stage 2 – Vegetation and
                                                                              trees removed. Rest of the
                                             August 2021
                                                                              works to commence in late
                                                                              June 2021

 Nell Baker Park

 Construction      External       Mid       10th May 2021       $430,047      Practical Completion
                               February                                       Reached
                                 2021
 Cone Street Park
 Construction      External      Early        Early June        $347,001      Additional scope and
                                 March          2021                          inclement weather (rain) has
                                 2021                                         impacted scheduled
                                                                              completion

Recent Project Activities

Ron Anderson and Busuttin Park

     Ron Anderson and Busuttin Parks are completed.
     Minor defects to be rectified by the Ron Anderson playground equipment supplier and a minor
      compliance issue with the Busuttin shelter roof clearance height which is currently being addressed.

Canecutters Drive Park

     Stage 1 works are complete on site.
     Stage 2 – Removal of vegetation complete. Balance of work to commence in late June 2021.

                                                                                                           14
Capital Works
                                                                                           Monthly Review > May 2021

                              Figures 5 & 6: Canecutters Park Stage 1 works are complete

Nell Baker Park

    Practical Completion reached and site handover inspection held with Park’s representative.
    Project finalisation in progress with As cons submission being collated.
    Minor defects/omissions being addressed by the contractor such as signage and gate small variation.
    16-week landscape establishment and maintenance period commenced.

Cone Street Park

     Several activities completed including, irrigation system, picnic shelter installation, concrete footpath
      with tactiles and pedestrian bridge.
     Basketball concrete finish being assessed/reviewed by council.
     Soft landscaping progressing
     Program delayed due to additional scope and inclement weather (rain)

                                  Figures 7 & 8: Cone Street Park Works progressing

                                                                                                                   15
Capital Works
                                                                                        Monthly Review > May 2021

5.4   Koumala Water Quality Upgrade – Water Treatment Plant

Overview

This project comprises the design and construction of a new water treatment plant in Koumala, Water Tower
Road.

The proposed project works includes the direct treatment of raw water being softened with the use of an ion
exchange softening process.

Project Status

                                                 Completion
 Activity        Delivery      Start Date                               Budget                     Comments
                                                   Date
 Construction    External         Mid               Early           $2,563,301.00        Works currently progressing
                               December           December                               as planned.
                                 2020               2021

Funds have been obtained from 2019-21 Local Government Grants and Subsidies Program.

Recent Project Activities

     30% and 60% treatment plant design review complete with hazard and operability study workshop held
      on 7 May 2021.
     90% design review workshop was held on 26 May 2021 – comment register actions to be actioned by
      Clean Teq Water.
     Possession of site given at the end of April. Clean Teq civil works sub-contractor has completed site
      establishment and bulk earthworks.

                   Figure 9: Bulk earthworks for proposed Water Treatment Plant in Koumala completed

                                                                                                                  16
Capital Works
                                                                                      Monthly Review > May 2021

5.5   Yakapari Seaforth Road Shared Path Stage 1 - Seaforth Reservoir Road to Aviland Drive

Overview

This project comprises the construction of Stage 1 of a shared pathway from the existing path end in front of
Seaforth State School to Aviland Drive. The shared pathway will provide greater connectivity and safety for
school students and residents along Yakapari Seaforth Road.

Mackay Regional Council has been successful in obtaining ‘Works for Queensland’ Funding to contribute
towards this pathway project.

Project Status

                                                    Completion
 Activity          Delivery      Start Date                               Budget               Comments
                                                      Date
 Construction       External       Early               End of          $697,233.98      Works recommenced on
                                  February           June 2021                          site on 4 May 2021 and is
                                    2021                                                progressing

Recent Project Activities

     Drainage pipe installation, concrete driveway crossover and concrete kerb construction in progress.
     Works on footpath impacted by shallow cable that required relocation by Telstra – cable relocation has
      been completed and construction has recommenced and is progressing well.

                                 Figure 10: Concrete driveway crossover constructed

                                                                                                               17
Capital Works
                                                                                      Monthly Review > May 2021

5.6   Yakapari Seaforth Road Shared Path Stages 2 & 3 - Seaforth Reservoir Road to Aviland Drive

Overview

This project comprises the construction of Stage 2&3 of a shared pathway from the existing path end stage 1
works through to midway between Prince Charles Avenue and Palm Avenue. The shared pathway will include
elevated walkways across waterway areas and provide greater connectivity and safety for school students and
residents along Yakapari Seaforth Road.

Mackay Regional Council has been is funding stage 2 and 3 from its Accelerated capital works program for
pathway project.

Project Status

                                                   Completion
 Activity          Delivery      Start Date                               Budget               Comments
                                                     Date
 Construction      External       Contract        End of August          $1,672,026     Preliminary enabling
                                 Awarded              2021                              works has been
                                 beginning                                              undertaken by Council
                                 May 2021                                               and the site is ready for
                                                                                        construction works to
                                                                                        commence. Contractor
                                                                                        schedule to establish on
                                                                                        site early June 2021

Recent Project Activities

     Preliminary works clearing works and service location Ch 850 – 2240

                                             Figure 11: Clearing works

                                                                                                                    18
Capital Works
                                                                                     Monthly Review > May 2021

5.7   Pioneer River, Estuary Fish Habitat Improvement Project

Overview

This project is aimed at enhancing recreational and tourist fishing experiences via complex marine habitat
installations adjacent to three designated fishing platforms in Mackay’s Pioneer River. The three locations are
adjacent to the Bridge Road, Brisbane Street, and Carlyle Street fishing platforms which are linked by the
Bluewater Trail.

This project is partly funded by Queensland Government’s Works for Queensland COVID program and partly
funded by Mackay Regional Council.

Project Status

 Activity        Delivery     Start Date    Completion Date                Budget            Comments
 Construction     External      March           Separable                 $503,797    Practical completion
                                2021          Portion A and B                         reached
                                               completed 30
                                                April 2021.

Recent Project Activities

     Deployment of structures at Brisbane, Carlyle St sites and Bridge Rd site completed. As cons
      documentation currently being reviewed.
     Minor additional works identified. Fishing Rod Holders being procured and installed at Brisbane and
      Carlyle St locations.

                                      Figures 12 & 13: River Street installation

                                         Figure 14: Bridge Road installation

                                                                                                             19
Capital Works
                                                                              Monthly Review > May 2021

5.8   Resurfacing Reseal Program 2021/2022

Overview

The resurfacing and rehabilitation program comprises resurfacing works on various streets and roads around
the region. Resurfacing includes two types of treatments, one being Asphalt on urban streets and roads, the
other Bitumen Spray Resealing on rural roads. Resurfacing works are carried out to protect the pavement and
extend the road pavement life.

Project Status

                                             Completion
 Activity         Delivery    Start Date                      Budget                 Comments
                                               Date
 Asphalting Works 2021/2022
 Construction     External       May           August        $1,829,182    Works awarded to RPQ
                                 2021           2021

 Resealing Works 2021/2022
 Construction     External       May           August       $ 1,889,184    Works awarded to RPQ
                                 2021           2021
 Total Resurfacing Reseal Program 2021/2022                 $ $3,718,366.00

Recent Project Activities

     RPQ have been awarded the works and are currently prepping permits for road closures to be
      undertaken prior to works starting, a significant ramp up is expected in June.

5.9   Culvert Replacement Package

Overview

The culverts were identified through the MRC Overmass Vehicle Bridge & Culvert Assessments completed by
in 2017 which involved several inspections and load assessments to determine if the existing culverts could
support over mass limit vehicle loads, 3 sites were identified as constraints. These sites are Kinchant Dam
(KD01) Rocky Waterholes Wallingford Road (RW7) and Rocky Waterholes Wallingford Road (RW9): the works
include the treatment of the upstream and downstream channels, and improvement of pedestrian access.

Project Status

                                             Completion
 Activity         Delivery    Start Date                      Budget                 Comments
                                               Date
 Construction     External       May           August        $2,064,700    Works awarded to Pentacon.
                                 2021           2021

Recent Project Activities

     Pentacon have been awarded the works and are currently planning for mobilisation to site on 31 May
      2021. Culvert Delivery is scheduled for next week, community engagement has been undertaken.
      Notification to bus routes and emergency services has been completed. Kinchant Dam road will remain
      open under traffic control however Rocky Waterholes sites will be closed to traffic.

                                                                                                        20
Capital Works
                                                                                     Monthly Review > May 2021

MAJOR PROJECTS
6.1     Northern Entry Statement Bruce Hwy Ring Road Landscaping

Overview

To enhance the Northern entry into Mackay, the newly constructed roundabout required landscaping /
revegetation work inclusive of pivotal infrastructure such as signage, irrigation system, solar and lighting.
The project saw the introduction of over 8,000 plants including 42 rare grass trees.

The successful tenderer for this project was Urbanscapes and possession of site was granted 10th March 2021.
Practical completion was achieved on 10th May 2021.

Project finalisation has commenced, initiating the 16-week establishment & maintenance period.
Council & Urbanscapes are working collaboratively to close out outstanding items & complete the associated
As Constructed documentation.

Project Status

                                                   Completion
 Activity         Delivery       Start Date                              Budget               Comments
                                                     Date
 Construction      External        March               May                   $670k     Project Finalisation has
                                   2021                2021                            commenced, Practical
                                                                                       Completion achieved 10th
                                                                                       May 2021

                                          Figures 15 & 16: Completed works

                                                                                                                21
Capital Works
                                                                                      Monthly Review > May 2021

6.2     Fifth Lane

Overview

Fifth Lane Revitalisation project will provide an environment that will enhance the city centre and provide a
venue within the CBD to host community events.

The project will include the removal and replacement of the existing surface finish, modifications to inground
services, drainage and water connections, installation of a new electrical conduit and pit system along with the
provisions of a new electrical switchboard and associated event power and lighting installation.

Seaforth Civil were successful in securing the revitalisation works and are currently achieving all project
milestones. Construction of the Fifth Lane Revitalisation is approximately 60% complete.

Water main renewal works are also concurrently being completed in Fifth Lane by Council’s Mackay Water.

Project Status

                                                     Completion
 Activity         Delivery       Start Date                                 Budget             Comments
                                                       Date
 Construction     External        February              30 June             $0.575k     Project achieving key
                                    2021                 2021                           milestones.

                                       Figures 17, 18 & 19: Works in progress.

                                                                                                                22
Capital Works
                                                                                     Monthly Review > May 2021

FIELD SERVICES
7.1    Midge Point Water Network Upgrade

Overview

To install a new water main from the Kunapipi Road to the Midge Point Reservoir (approximately 1100m of
250mm pipe). There is an existing main in this area which will remain operational, though these works will
allow the reservoir to have dedicated inlet and outlet mains as opposed to the dual functioning main already
there. This new arrangement will prevent water bypassing the reservoir and going directly to customers.

Project Status

                                                      Completion
 Activity             Delivery         Start Date                      Budget                    Comments
                                                        Date
 Construction          Internal              Late        Mid          $778,064          Community is aware of
                                           May 2021   August 2021                       the works and no negative
                                                                                        feedback received at this
                                                                                        stage.

                                                                                        Works currently on
                                                                                        schedule and no budget
                                                                                        issues identified.

Recent Project Activities

      Community engagement meeting held 6/5/21 – no concerns raised with the proposed works.
      Design finalised
      Site established and alignment set out
      Materials procured
      Pipelaying commenced from reservoir end of the alignment.

Figure 20: Looking towards the reservoir                            Figure 21: Installing the main. Looking towards
                                                                    Kunapipi Rd from approx. CH200

                                                                                                                      23
Capital Works
                                                                                                      Monthly Review > May 2021

7.2     Milton St/ Alfred St Signalised Intersection

Overview

The project is a Roads to Recovery funded project and consists of the upgrade of the Milton Street and Alfred
Street intersection. The project includes the signalisation of the intersection with a “scramble” pedestrian
crossing for when there are events on at the adjacent showgrounds. Works include the upgrade of the water
infrastructure along Milton street, the installation of traffic lights (incorporating traffic into the showgrounds) and
traffic islands, and a renewed asphalt surfacing.

Project Status

                                                                 Completion
 Activity              Delivery           Start Date                                      Budget                    Comments
                                                                   Date
 Construction           Internal            Late                     Mid                $1,558,075        Delays have occurred due
                                          Nov 2020                June 2021                               to conflicting underground
                                                                                                          services from the Ergon
                                                                                                          substation.
                                                                                                          Long lead times on some
                                                                                                          procurement items have
                                                                                                          created further delays to
                                                                                                          final completion.

Recent Project Activities

       Central median islands poured – stencilling to be completed.
       All footpaths poured awaiting tactile and paver treatment.
       MRC electricians installed 50% of the traffic light posts – signals expected to be operational second
        week June.

      Figure 22: Looking south-west onto Milton St, Islands poured awaiting stencilling and light poles. Traffic signals part installed.

                                                                                                                                           24
You can also read