Enhancements Delivery Plan England and Wales - Entry Into Service (EIS) schedule June 2020

Page created by Larry Curtis
 
CONTINUE READING
Enhancements Delivery Plan
England and Wales
Entry Into Service (EIS) schedule

June 2020
Network Rail’s obligation
The Enhancements Delivery Plan for England and Wales sets out the enhancements commitments that Network Rail has made to the Department for Transport and to other funders. Its
purpose is to provide transparency about the status of these schemes and to provide visibility of our plans to customers, stakeholders and the public.
Network Rail’s obligation is to publish Entry into Service (EIS) milestones which represent the completion of our works to change the capability of the railway infrastructure. It will be for
passenger and freight operators to decide how and when to begin to use enhanced infrastructure.
In Control Period 6 we will agree enhancements with our funders through the Investment Decision Framework (IDF) and the Department for Transport’s (DfT) Rail Network Enhancement
Pipeline (RNEP) process. These have been developed following the Memorandum of Understanding which was developed and agreed between Network Rail and the DfT in 2016.1
Network Rail and funders will only commit to the delivery of an enhancement once we have developed the programme sufficiently to have a good understanding of its outputs, cost and
scope. This will allow us to make a Final Investment Decision (FID) to deliver these works. As such, EIS milestones will only be published in this plan once a scheme has passed a FID. It is
only at this point that there is sufficient certainty of outputs that NR can reasonably be held to account for the delivery of the programmes.
For all programmes that are yet to reach the point of taking a FID, DfT publish these in their RNEP document, which is updated annually: https://www.gov.uk/government/publications/rail-
network-enhancements-pipeline-autumn-2019-update
A separate Enhancements Delivery Plan is published to describe our Enhancements obligations in Scotland: https://www.networkrail.co.uk/who-we-are/publications-and-resources/

Contacting Network Rail
One of the reasons that Network Rail publishes an Enhancements Delivery Plan is to provide visibility of funded enhancements to potential third-party investors and to other railway
undertakings to assist them in planning their businesses. Enquiries related to specific schemes for these purposes should be addressed to the Principal Programme Sponsor, or other listed
contact, responsible for each programme. They are named in the document against each programme and their contact details are listed below.
General enquiries should be addressed to Network Rail using the contact details provided on our website: https://www.networkrail.co.uk/communities/contact-us/
Crossrail – Colin Prime, Principal Programme Sponsor – colin.prime@networkrail.co.uk
Thameslink – Elena Stebbings, Senior Development Manager – elena.stebbings@networkrail.co.uk
North of England Programme – Phase 5 – Andy Morgan, Principal Programme Sponsor – andrew.morgan@networkrail.co.uk
West Anglia Main Line Capacity, Kings Lynn to Cambridge 8 car, Felixstowe Branch Capacity Enhancement – Sarah Jane Crawford, Principal Programme Sponsor –
sarahjane.crawford@networkrail.co.uk
East Coast Main Line Enhancements Programme – Ed Akers, Principal Programme Sponsor – edward.akers@networkrail.co.uk
Midland Main Line Programme, Market Harborough LSI – Gavin Crook, Principal Programme Sponsor – gavin.crook@networkrail.co.uk
New Cross Grid – Mark Ellerby, Senior Commercial Scheme Sponsor – mark.ellerby@networkrail.co.uk
Transpennine Route Upgrade (Intermediate Interventions only - Leeds Station Capacity improvements) – Kieran Dunkin, Principal Programme Sponsor – kieran.dunkin@networkrail.co.uk
Great Western Electrification and Capacity – Charles Varey, Principal Programme Sponsor – charles.varey@networkrail.co.uk
Thames Valley EMU Capability Works – Mike Foss, Principal Programme Sponsor – mike.foss@networkrail.co.uk
West of England DMU Capability – Michelle Scogings, Principal Programme Sponsor – michelle.scogings@networkrail.co.uk
Reading, Ascot to Waterloo train lengthening programme – Stewart Firth, Director, Route Sponsorship (Wessex) – stewart.firth@networkrail.co.uk
Peak Forest to London freight – Thomas Drury, Sponsor – tom.drury@networkrail.co.uk
Doncaster to Immingham W12 gauge clearance & Northern Ports and Transpennine Capacity – Richard Iggulden, Senior Development Manager – richard.iggulden@networkrail.co.uk

1
    https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/509545/mou-dft-network-rail-rail-enhancements.pdf
Northern train lengthening – Lawrence Cheung, Senior Sponsor – lawrence.cheung@networkrail.co.uk
Gatwick Airport station – Stephen Diplock, Senior Commercial Scheme Sponsor – stephen.Diplock@networkrail.co.uk
Bristol East Junction Remodelling – Michelle Scogings, Principal Programme Sponsor – michelle.Scogings@networkrail.co.uk
South West Rail Resilience Programme – Julie Gregory, Senior Commercial Scheme Sponsor – julie.Gregory@networkrail.co.uk

Activities and Milestones

 Ref.       Programme        Project         Network       Narrative                              Output                                     Activity/          Original   Revised      Status
 Code                                        Rail                                                                                            Milestone          Agreed     Date
                                             Contact                                                                                                            Date
 CR001      Crossrail        -               Colin Prime   The Crossrail project will deliver a   The Crossrail project benefits are as      Key Output 6a      May-20*    n/a          *Subject
                                                           new integrated railway route           follows:                                   - Full                                     to change
                                                           through central London from            • New Crossrail train services will        Infrastructure                             control
                                                           Reading and Heathrow in the west       provide direct links from Reading          Capability to
                                                           to Shenfield and Abbey Wood in         and Heathrow to Paddington in the          support Stage
                                                           the east. The joint sponsors of the    west to Shenfield and Abbey Wood           4 operations
                                                           Crossrail project, the Department      in the east. With up to 24 Crossrail       with sufficient
                                                           for Transport (DfT) and Transport      trains an hour running through the         time for testing
                                                           for London (TfL), have set-up a        central section in each direction (at      Key Output 6b      Dec-20     n/a –        On target
                                                           company called Crossrail Limited       peak times) a total of 10% will be         - Full                        project is
                                                           (CRL) to act as the delivery agent.    added to London’s rail-based               Infrastructure                on target
                                                           Network Rail is one of CRL’s           transport capacity; and                    Capability to
                                                           delivery partners.                     • 28 existing surface stations will be     support Stage
                                                           The responsibility for the design      upgraded with many of these                5 operations
                                                           and construction of the works          stations also receiving platform           (including
                                                           outside of the central tunnel          extensions.                                Ilford and
                                                           section - known as the ‘On                                                        Romford
                                                           Network Works’ (ONW) - was                                                        Stations) with
                                                           transferred to Network Rail when                                                  sufficient time
                                                           Royal Assent was granted to the                                                   for testing
                                                           Crossrail project in July 2008.
 CR004      Thameslink       -               Elena         The DfT Thameslink Programme           High capacity infrastructure to            EIS                Dec-18     n/a –        Complete
                                             Stebbings     aims to provide a step change in       provide 24 train paths per hour            Infrastructure                project is
                                                           capacity on an extended                between St Pancras and Blackfriars         Authorised                    complete
                                                           Thameslink network thus providing      stations                                   KO2 final
                                                           new journey opportunities,                                                        milestone
                                                           congestion relief and capacity for
                                                           future growth in passenger
                                                           demand on National Rail and
                                                           London Underground.
 CR005      North of         Phase 5 –       Andy          25kV AC overhead electrification       The North of England Programme             EIS –              Mar-19     May-19       Revised
            England          Manchester      Morgan        between Manchester Victoria and        (NoEP) delivers conditional outputs        Infrastructure                &            &
            Programme        Victoria to                   the Bromley Street (Manchester)        which provide additional capacity for      Authorised                    Jul-19       Complete
                             Stalybridge                   area, new grid supply point at         more services, improvements to line
                                                           Stalybridge, associated power          speeds to reduce journey times and
                                                           cable from Stalybridge to Ordsall      electrify specific routes in the region.
                                                           Lane for Phases 4 and 5 NWEP
                                                           and infrastructure improvements to
                                                           give journey time savings.
                                                                                                                                                                                                    3
Ref.    Programme       Project           Network       Narrative                              Output                                     Activity/        Original   Revised      Status
Code                                      Rail                                                                                            Milestone        Agreed     Date
                                          Contact                                                                                                          Date
A003    West Anglia     -                 Sarah Jane    The project will relieve               Infrastructure to allow for an             EIS –            May-19     n/a –        Complete
        Mainline                          Crawford      overcrowding on the West Anglia        additional two trains per hour to          Infrastructure              project is
        Capacity                                        Main Line. This scheme is              operate from Tottenham Hale to             Authorised                  complete
        Increase                                        intended to address the medium-        Stratford compared to the December
                                                        term demand arising from               2014 Timetable in which two trains
                                                        industrial and residential             per hour currently operate. Network
                                                        developments in the vicinity of        Rail will also deliver infrastructure to
                                                        Tottenham Hale, Northumberland         allow these services to be extended
                                                        Park and the new Meridian Water        beyond Tottenham Hale to a new
                                                        development.                           station at Meridian Water (funded by
                                                                                               external stakeholders)
A006    Kings Lynn to   -                 Sarah Jane    The project is to deliver the          These services will relieve current        EIS –            Jul-20*    n/a          *Subject
        Cambridge 8                       Crawford      infrastructure required to enable 8-   peak hour overcrowding and meet            Infrastructure                           to change
        car project                                     car Govia Thameslink Railway           CP6 passenger demand forecasts.            Authorised                               control
                                                        (GTR) services to run on the           Currently the service is operated by
                                                        King's Lynn to Cambridge route,        4-car units.
                                                        during the peak hours.
EC001   East Coast      Werrington        Ed Akers      The Programme is driven by a           DfT have agreed that the ECML              EIS              Apr-21*    n/a          *Subject
        Main Line       Grade                           strategic priority to increase         Enhancements Programme should              Infrastructure                           to change
        Enhancements    Separation                      capacity, improve passenger            provide infrastructure which enables       Authorised                               control
        Programme       Power supply                    experience and accelerate journey      these outputs:                             EIS              CP6        n/a –        On target
                        upgrade phase                   times between key cities. The          • An increase in capacity from 6 to 8      Infrastructure              project is
                        2                               outputs include implementation of      Long-Distance High-Speed services          Authorised                  on target
                                                        the InterCity Express Programme        (LDHS) between London King’s
                        Kings Cross                                                                                                       EIS              Mar-21     n/a          *Subject
                                                        on the East Coast Main Line,           Cross and Doncaster and from 5 to
                        remodelling                                                                                                       Infrastructure                           to change
                                                        power supply upgrades and an           6 LDHS paths between Doncaster
                                                                                                                                          Authorised                               control
                                                        improved track layout to the north     and Newcastle per hour;
                        Stevenage                       of Peterborough.                       • Maintaining 2 freight tph, using         EIS              May-20     Aug-20       Revised &
                        Turnback                                                               diversionary routes as far as              Infrastructure                           On target
                                                        DfT have noted that the outputs        practicable;                               Authorised
                                                        listed here are to be treated as       • A reduction in journey times for the
                                                        conditional as trade-offs may still    fastest LDHS services to 4 hours
                                                        be needed to be made as further        from London to/from Edinburgh and
                                                        work is completed by NR to             2 hours to/from London to Leeds.
                                                        develop the timetable.
EM001   Midland Main    London to         Gavin Crook   This Enhancements Programme is         Key Output 1 for Entry into Service        EIS              May-20*    n/a          *Subject
        Line            Corby                           part of a rail industry programme      Infrastructure Authorised:                 Infrastructure                           to change
        Programme -     Electrification                 that aims to transform travel to and   • Provision of 25kv electrification        Authorised -                             control
                        and Capacity                    from London on the Midland             from the existing limits at Bedford to     Platform
        Key Output 1
                                                                                               Kettering and Corby; providing
                        Upgrade                         Mainline during CP5 and CP6 and                                                   Lengthening
                                                                                               traction power for 2 electric
                                                        improve the links between the core
                                                                                               passenger train services.                  EIS              May-20     Aug-20*      Revised
                                                        centres of population and              • Enabling of improved journey times       Infrastructure                           &
                                                        economic activity in the East          through the delivery of key                Authorised -                             *Subject
                                                        Midlands and South Yorkshire.          infrastructure schemes;                    Kettering                                to change
                                                                                               • Additional capacity for a 6th Long-      Stabling                                 control
                                                                                               Distance High-Speed service to             Facility

                                                                                                                                                                                               4
Ref.      Programme       Project         Network        Narrative                               Output                                    Activity/          Original   Revised      Status
Code                                      Rail                                                                                             Milestone          Agreed     Date
                                          Contact                                                                                                             Date
                                                                                                 serve between St Pancras and              EIS                May-20     Aug-20*      Missed &
                                                                                                 Kettering / Corby; and 3 freight paths    Infrastructure                             *Subject
                                                                                                 per hour between Bedford and              Authorised -                               to change
                                                                                                 Kettering.                                Prioritised                                control
                                                                                                 • The capability of the network will
                                                                                                                                           electrified
                                                                                                 be enhanced through the extension
                                                                                                                                           route
                                                                                                 of platforms at key stations south of
                                                                                                 Leicester.                                EIS                Aug-20*    n/a          *Subject
                                                                                                 • New stabling facilities will also be    Infrastructure                             to change
                                                                                                 provided at Kettering.                    Authorised -                               control
                                                                                                                                           Full electrified
                                                                                                                                           route
ES003k    Market          -               Gavin Crook    The driver for the project is to        The project will provide infrastructure   GRIP 6             Jun-19     n/a –        Complete
          Harborough                                     increase the line speed through         to increase the line speed between        Infrastructure                project is
          LSI                                            Market Harborough in                    Kettering and Wigston South               Authorised                    complete
                                                         order to support a journey time         Junction timing points in order to
                                                         improvement between London and          enable a reduction in Sectional
                                                         Sheffield.                              Running Time (SRT).
K004      New Cross       -               Mark Ellerby   The project will provide increased      To provide base traction power            GRIP 6             Mar-20     n/a –        Complete
          Grid                                           traction power supply capacity for      supply capacity for increased DC          completion                    project is
                                                         DC electric services in South           electric train services into London in    and EIS                       complete
                                                         London, North Kent and Sussex. It       line with predicted future growth.
                                                         is required to provide additional
                                                         base capacity in the area for future
                                                         train service increases.
                                                         The project is a strategic upgrade
                                                         and is part renewal funded in its
                                                         replacement of existing obsolete
                                                         66kV equipment and connections.
LNE001b   Transpennine    Leeds Station   Kieran         Additional capacity at Leeds            Leeds Station Capacity                    Phase 1 EIS        Dec-19     n/a –        Complete
          Route           Capacity        Dunkin         Station to support the operation of     Enhancements - Additional capacity                                      project is
          Upgrade –       improvements                   longer trains and additional            at Leeds Station to support the                                         complete
                                                         services on several routes. Leeds       operation of longer trains and                                                       Complete
          Intermediate                                                                                                                     Phase 2 EIS        Dec-20     n/a –
                                                         Station Capacity Enhancements           additional services on a
          Interventions                                                                                                                                                  project is
                                                         will also support the delivery of the   number of routes. The project will be
                                                         DfT’s infrastructure assumptions        delivered in the following phased                                       complete
                                                         within the Northern and                 strategy:                                 Phase 3 EIS        Dec-21     n/a –        On target
                                                         Transpennine franchise                  • Phase 1 - Recontrol of the                                            project is
                                                         commitments.                            signalling control system to the York                                   on target
                                                                                                 Rail Operating Centre (ROC)
                                                         Note that further outputs for the       • Phase 2 - The relocking of 8No.
                                                                                                 existing signalling interlockings to
                                                         Transpennine Route Upgrade are
                                                                                                 provide additional signalling capacity
                                                         being developed by Network Rail
                                                                                                 • Phase 3 - A new 8-car platform
                                                         and will be published in this EDP
                                                                                                 (platform 0) and longer train
                                                         as a separate programme
                                                                                                 standages on platforms 6. Track
                                                         (Transpennine Route Upgrade)
                                                                                                 remodelling and associated
                                                         once they have completed a Final
                                                                                                 resignalling to the West end of the
                                                         Investment Decision.
                                                                                                 station to provide greater operational
                                                                                                 flexibility.
                                                                                                                                                                                                  5
Ref.    Programme         Project          Network         Narrative                             Output                                    Activity/          Original   Revised      Status
Code                                       Rail                                                                                            Milestone          Agreed     Date
                                           Contact                                                                                                            Date
W001a   Great Western     Bristol          Charles         The electrification of the GWML       Extension of the electrification of the   EIS                Nov-19     6th Jan-     Missed &
        Electrification   Parkway to       Varey           facilitates the introduction of       Great Western Main Line (GWML)            Infrastructure                20           Complete
                          Cardiff (excl.                   electric train operation delivering   from Maidenhead (the furthest             Authorised
                          electric                         significant journey time              extent of the Crossrail infrastructure
                                                                                                 works) to Cardiff, including power
                          operation in                     improvements on key intercity
                                                                                                 distribution works and clearance
                          the Severn                       routes and high seating capacity
                                                                                                 works.
                          Tunnel)                          trains on suburban services
                          Wootton                          including into London Paddington.                                               EIS                CP6        Apr-19       Complete
                          Bassett                                                                                                          Infrastructure
                          Junction to                                                                                                      Authorised
                          Chippenham
                          East
                          Severn Tunnel                    Commission the fixed                  Enables Class 387 EMU’s and other         EIS                6th Jan-   31st May     Complete
                          (electric                        conductor beam in the                 electric stock to operate between         Infrastructure     20         20
                          operation)                       Severn Tunnel                         Bristol Parkway and Cardiff.              Authorised
W002b   Great Western     IEP: Specific    Michelle        The project provides infrastructure   Infrastructure capacity                   Bristol            Dec-19     n/a –        Complete
        Capacity          GWML             Scogings        capacity enhancements to enable       enhancements as outlined in the           Parkway 4th                   project is
        Enhancement       Capacity                         the delivery of the Intercity         client (DfT) remit “Infrastructure        platform - EIS                on
        Programme         schemes                          Express Programme.                    Output Specification” (IOS5) to           - Infrastructure              complete
                                                                                                 enable the operation of an enhanced       Authorised
                                                                                                 passenger timetable from December
                                                                                                 2019. At Bristol Parkway station, an
                                                                                                 additional platform face, signalling
                                                                                                 and track works.
WX003   Reading,          Feltham          Stewart Firth   The project supports the delivery     The project will provide infrastructure   EIS                Dec-19     n/a –        Complete
        Ascot to          Platform                         of the 2012 HLOS capacity metric      to enable the operation of 10 car         Infrastructure                project is
        Waterloo train    Extensions                       for London Waterloo which             services on the Reading to London         Authorised                    complete
        lengthening       and Level                        indicates that it is necessary to     Waterloo and Aldershot via Ascot to
        programme         Crossing                         provide capacity to accommodate       London Waterloo routes. This will
                          Closure                          an additional demand of 9,700         relieve overcrowding, particularly
                                                           passengers in the three-hour          between Virginia Waterloo and
                                                           morning peak.                         London Waterloo in the morning
                                                                                                 peak.
F006a   Felixstowe        -                Sarah Jane      To relieve capacity constraints at    The project will provide infrastructure   EIS                Dec-19     n/a –        Complete
        Branch                             Crawford        the port of Felixstowe such that      to enable operation of up to 47           Infrastructure                project is
        Capacity                                           freight demand from Felixstowe in     freight train paths per day in each       Authorised                    complete
        Enhancement                                        CP6 and CP7 can be met.               direction on the branch line to and
                                                           The scope of works includes           from the Port of Felixstowe.
                                                           provision of a new 1.4km passing
                                                           loop at Trimley, 4 Crossing
                                                           upgrades, 6-foot crossing
                                                           closures, a new bridleway bridge,
                                                           5 new S&C units, provision of
                                                           diversionary route for FTN and
                                                           signalling enhancements for the
                                                           new layout.

                                                                                                                                                                                                 6
Ref.       Programme         Project   Network    Narrative                             Output                                      Activity/        Original   Revised      Status
Code                                   Rail                                                                                         Milestone        Agreed     Date
                                       Contact                                                                                                       Date
F006b      Doncaster –       -         Richard    W12 gauge enhancement from            Gauge clearance for W12 container           EIS              Jun-19     n/a –        Complete
           Immingham                   Iggulden   Doncaster, (both Hexthorpe Jn         traffic on the branch line between          Infrastructure              project is
           W12 gauge                              and Marshgate Jn) to Immingham        Immingham and the East Coast                Authorised                  complete
           clearance                              and Killingholme. There are 29        Main Line, connecting the port with
                                                  foul structures that need to be       the network of ‘high gauge’ container
                                                  cleared to achieve W12 clearance.     routes.
F006c      Northern Ports    -         Richard    Priority interventions to increase    Entails double tracking a 400m              EIS              Dec-19     Dec-20       Revised &
           and                         Iggulden   freight capacity between the Port     stretch at the port boundary and            Infrastructure                           On target
           Transpennine                           of Liverpool and the WCML and         installing flashing yellow aspects at       Authorised
           capacity                               Transpennine routes. An increase      Earlestown to ease approach
                                                  from 1 to 2 freight train paths       control.
                                                  between the Port of Liverpool and
                                                  Earlestown.
F006d      Peak Forest to    -         Thomas     Provision of an extended run          Infrastructure to allow longer trains       EIS              May-19     n/a –        Complete
           London                      Drury      round facility at Buxton to enable    with a gross trailing weight of 2600 –      Infrastructure              project is
           Freight                                freight trains to be routed to/from   3000 tonnes between Peak Forest             Authorised                  complete
           (Buxton,                               the routes to Hindlow and Great       and the Midland Mainline and
           Hindlow/                               Rocks.                                ultimately destinations in London
           Dowlow)                                                                      and the South East.
LNE001c    Northern train    -         Lawrence   Programme of works across LNW         The work, which consists of                 EIS              Apr-20     n/a –        Complete
LNW008     lengthening                 Cheung     and LNE routes, with deliverables     extending c.120 platforms at 60             Infrastructure              project is
                                                  required for each timetable change    stations, will enable longer rolling        Authorised                  on
                                                  from December 2017 to May 2020.       stock to be operated by Arriva Rail                                     complete
                                                                                        North (ARN) to provide increased
                                                                                        capacity for passengers.
IFDfT008   Gatwick           -         Stephen    The project will provide a new        By improving pedestrian journeys            EIS              Nov-22     n/a –        On target
           Airport station             Diplock    station concourse above the           within the station, the scheme will         Infrastructure              project is
                                                  existing station platforms with       contribute to Network Rail’s                Authorised                  on target
                                                  increased space for passengers        objectives to deliver a safe, efficient
                                                  and an improved connection to         and reliable rail service. The scheme
                                                  Gatwick Airport South Terminal via    will help to meet Network Rail’s
                                                  the NR footbridge. It will also       commitment to put improved
                                                  include additional platform work,     accessibility at the heart of its station
                                                  refurbishment of the existing         re‐designs. The scheme will also
                                                  station concourse and                 help to meet the Department for
                                                  overbridges. The project will         Transport’s objectives for improving
                                                  enable improved passenger             journeys and providing safe, secure
                                                  access via new stairs and lifts,      and sustainable transport. The
                                                  while it also aims to provide         scheme was recommended by the
                                                  increased circulation space and a     Interim Report of the Airports
                                                  modern open plan ticket retailing     Commission in 2013.
                                                  hub.

                                                                                                                                                                                         7
Ref.   Programme         Project   Network    Narrative                              Output                                     Activity/        Original   Revised      Status
Code                               Rail                                                                                         Milestone        Agreed     Date
                                   Contact                                                                                                       Date
W016   South West        -         Julie      The South West Rail Resilience         The output of this programme is to         Phase 1          Jul-20     n/a –        On target
       Rail Resilience             Gregory    Programme aims to provide a            deliver a robust level of resilience for   (Marine                     project is
       Programme                              resilient railway for the south-west   the next 100 years, considering            Parade,                     on target
                                              of England. The only railway line      climate change including sea level         Dawlish) –
                                              connecting much of Devon and all       rise. The level of resilience to be        Resilience
                                              of Cornwall to the rest of the UK      delivered equates to reducing the          delivered
                                              rail network runs along the            probability of the railway being           Phase 2          Aug-22     n/a –        On target
                                              vulnerable coastal section             closed for more than a week to one         (Colonnade to               project is
                                              between Dawlish Warren and             in 100 years; the probability of a         Coastguard’s                on target
                                              Teignmouth. This stretch of            closure between 2 days and a week          Ramp,
                                              railway is subject to the twin         to no more than once every 20 years        Dawlish) –
                                              threats of coastal and geotechnical    on average and all other smaller           Resilience
                                              encroachment. In 2014 the railway      disruption events to be reduced            delivered
                                              here was closed for 6 weeks            compared to current levels.
                                              following the breaching of the sea
                                              wall at Dawlish and a subsequent
                                              landslip of cliffs near Teignmouth.
W015   Bristol East      -         Michelle   Remodelling of the Bristol East        The outputs of the programme are:          EIS              Sept-21    n/a –        On target
       Junction                    Scogings   Junction has been identified as        - Additional capacity to support           Infrastructure              project is
       Remodelling                            playing an important role in the       service enhancements, including            Authorised                  on target
                                              future strategic development of the    MetroWest, and thus, support future
                                              rail network in the Greater Bristol    demand growth.
                                              area and Western Region.               - Resilience performance: de-
                                              Network Rail’s Western Route           confliction of moves at the station
                                              study identified that additional       area and the removal of the
                                              services into Bristol Temple           bottleneck at Filton Bank, delivering
                                              Meads were required to                 better performance and a more
                                              accommodate future rail demand.        reliable service for passengers.
                                              The remodelled layout of Bristol       - Reduction of asset maintenance
                                              East Junction will provide             times.
                                              additional capacity to support         - An average two-minute journey
                                              efficient running of future service    time saving on a number of London
                                              enhancements such as MetroWest         Paddington to Bristol services.
                                              and optimise the capacity works
                                              already delivered in the route.

                                                                                                                                                                                     8
We’re transforming, making it easier for other organisations to invest in, and build on
the railway.

Providing valuable opportunities for other organisations to invest in and build on the railway reduces the tax-payer burden. The increased
competition drives down cost, while also increasing efficiency, creativity and innovation.

Further information on Network Rail’s Open for Business initiatives can be found on our website: https://www.networkrail.co.uk/industry-
commercial-partners/third-party-investors/network-rail-open-business/

Contact details for our Business Development Developers for each route can also be found on our website:
https://www.networkrail.co.uk/industry-commercial-partners/third-party-investors/network-rail-open-business/opportunities-for-third-parties/

                                                                                                                                               9
You can also read