Engineering Justification Paper Winkfield South East Offtake Pre-heating and Volumetric/Pressure Control system replacements - Final Version Date: ...
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Engineering Justification Paper Winkfield South East Offtake Pre-heating and Volumetric/Pressure Control system replacements Final Version Date: December 2019 Classification: Highly Confidential
1. Table of Contents 2 Introduction ........................................................................................................................................ 3 3 Equipment Summary ........................................................................................................................... 5 4 Problem Statement ............................................................................................................................. 9 5 Probability of Failure ......................................................................................................................... 12 5.1 Failure rate .................................................................................................................................................12 5.2 Probability of Failure Data Assurance ........................................................................................................14 6 Consequence of Failure ..................................................................................................................... 15 7 Options Considered ........................................................................................................................... 17 7.1 Component replacement ...........................................................................................................................18 7.2 Refurbish components ...............................................................................................................................18 7.3 Replace on failure .......................................................................................................................................18 7.4 Repair on failure .........................................................................................................................................19 7.5 Do nothing ..................................................................................................................................................19 7.6 Replacement of volumetric Control Valves and gas preheating system ....................................................19 7.7 Options Cost Details ...................................................................................................................................22 7.8 Options Cost Summary Table .....................................................................................................................22 8 Business Case Outline and Discussion ................................................................................................ 23 8.1 Key Business Case Drivers Description .......................................................................................................23 8.2 Business Case Summary .............................................................................................................................25 9 Preferred Option Scope and Project Plan ........................................................................................... 26 9.1 Preferred option .........................................................................................................................................26 9.2 Asset Health Spend Profile .........................................................................................................................26 9.3 Investment Risk Discussion ........................................................................................................................26 Appendix A - Acronyms ........................................................................................................................ 29 Appendix B - References....................................................................................................................... 30 2
SGN Trans – 002Wink1 – EJP Dec19 2 Introduction This project is one element of the Transmission Integrity programme within Southern Network for RIIO GD2. The integrity programme is generally health driven considering the health of gas Transmission Assets - Offtakes, Local Transmission System (LTS) Pipelines, Pressure Reduction Stations (PRS) and ancillary assets. ‘Health’ includes condition (corrosion, cracking, spalling etc.) and reliability (in-service defects etc.). In terms of engineering justification, the Authority has proposed the following model to differentiate between ‘major projects’ requiring justification in accordance with Appendix A guidance and ‘asset health’ projects justified in accordance with Appendix B. Guidance for engineering justification This project is to rebuild both the heating and pressure reduction systems on Winkfield South East Offtake. This project also includes the replacement of a remote boundary control system that controls the maximum operating pressure to 38 BarG at a downstream valve site at Ripley in Surrey, thereby maximising the available diurnal storage within the South East LDZ. Other systems on site are not impacted by this proposal. General Background Winkfield South East Offtake supplies gas into the South East Local Distribution Zone (LDZ) from the National Gas Transmission system (NTS). The NTS began life around 1965 as a single pipeline and spurs transporting methane from Algeria and imported into Canvey Island to the Leeds area. In 1966, the NTS was extended to a new terminal at Easington, where it is understood the first natural gas was beached. In 1969 the NTS was significantly extended with connections to the Bacton terminal and, in the South East, to Winkfield and beyond into the South East LDZ. Records indicate that Local Transmission System pipelines (LTS) from Winkfield to Ripley and Mogador were commissioned late in 1969. Winkfield South East Offtake was therefore one of the first sources of gas into the LDZ and is therefore one of the oldest offtakes now at least 50 years old. Today, the primary roles of an offtake are as follows: • Filter the gas to at least 10µm, • Meter the gas volume to meet the requirements of the UNC for custody transfer, 3 December 2019
SGN Trans – 002Wink1 – EJP Dec19 • Measure the energy value of the gas (Calorific Value) to meet the requirements of the Gas (Calculation of thermal energy) Regulations, • Pre-heat the gas prior to pressure reduction to combat the effects of the Joule-Thomson effect, • Control the pressure and volume of gas into the LTS, these systems typically operate in volumetric mode with pressure overrides to ensure pressures do not exceed the Maximum Operating Pressure within the downstream system. • Odourise the gas to meet the requirements of the Gas Safety (Management) Regulations and the associated Gas Transporter’s Safety Case. Filtration, pressure control and pre-heating are typically designed in accordance with the Institution of Gas Engineers and Managers (IGEM) recommendations, IGEM/TD/13, Pressure regulating installations for natural gas, liquefied petroleum gas and liquefied petroleum gas / air. Site Specific Background The site at Winkfield has three offtakes on the site, which feed the South East LDZ, South LDZ and London North LDZ (which is owned and operated by Cadent). These systems are dedicated to each LDZ. The existing system feeding the South LDZ shares filtration with the system that feeds the South East LDZ. After the common filtration system, the pipework splits into two discreet systems, each having their own metering, odourisation, pre heating and pressure reduction systems. Overview Security 4 December 2019
SGN Trans – 002Wink1 – EJP Dec19 3 Equipment Summary Winkfield South East Pressure reduction system regulates the gas pressure from up to 75 BarG down to between 41 and 38 BarG and is protected by a high pressure override system that ensures the pipeline pressure downstream of Ripley does not exceed 38 BarG. This system is the only HP gas supply, from the west, into South East LDZ from the NTS Feeder Main 7. The other supplies into South East LDZ (Tatsfield, Farningham ‘A’, Farningham ‘B’ and Shorne) are all supplied from NTS Feeder Main No. 5. Winkfield South East offtake is therefore essential in providing SGN with partial resilience against a failure of Feeder main 5 adversely affecting gas supplies into one of the largest LDZs in the UK. Security Winkfield is the only supply into the 38BarG system from the west side of the network. 5 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Both Winkfield South and South East gas supply systems, share four ‘Swinney’ (‘SPX’ H-Type) gas filters. The system then splits to feed the South East LDZ and South LDZ separately. Example of four filters within the common South / South East gas filtration system The South East LDZ passes gas through a fiscal metering system used to accurately measure the energy transfer into the network. Currently, this is a removable orifice plate meter and carrier. ‘Daniels’ dual chamber, orifice plate and carrier The conditioned gas then passes through one of two ‘Robert Jenkins & Co Ltd’ built water bath heaters. These pre-heat the gas prior to pressure reduction to ensure the downstream gas and pipework is protected from the unavoidable, ‘Joules-Thompson’ freezing effect. 6 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Typical, Winkfield water bath gas pre-heater Stream slam-shut valves and control panels are critical to protect the downstream systems from fault driven over pressurisation. For both the South and Southeast systems, they are actuated ball valves, controlled by ‘Paladon’ built, pneumatic control systems. The slam-shut valves are buried, welded in line and also provide an inlet stream isolation facility. Above ground actuators on each of the buried slam shut valves 7 December 2019
SGN Trans – 002Wink1 – EJP Dec19 The volumetric flow and pressure regulators are ‘Valtek Engineering NEI-APE Ltd’ ‘Tiger Tooth’ Control Valves. These operate in series in ‘Monitor’ (stand-by) and ‘Active’(working) configuration. Example: ‘Valtek’ ‘Tiger Tooth’ globe Control Valves The Winkfield southeast system is forecast to provide 175,300 scm/h (4.2 mscm/day) of gas into the South East LDZ, during a 1 in 20 year, peak day, severe winter. Global population SGN has the following number of NTS Offtakes and PRS (Pressure Reducing Stations) within Scotland and Southern networks (as reported during the 2018/2019 RRP): Network Offtakes PRS Southern 12 157 Scotland 18 131 Pre-heating system The majority of these sites have gas pre-heating systems as follows: Type Southern Scotland Offtakes PRS Offtakes PRS Boilers / heat exchangers 6 133 6 44 Water-bath heaters 6 19 10 61 Electrical element - 3 - 4 Water-bath heaters on offtakes are typically around 1000 kwh heat output and similar in size and construction to those currently at Winkfield. Water-bath heaters on PRS are simpler and much smaller in size and are installed, where other types of heating systems are uneconomic to install and operate. Of the six remaining systems of large water bath heaters on offtakes within Southern, one system of three at Farningham will be replaced by the end of GD1, three other systems, comprising of Winkfield South, Winkfield South East and Mappowder are planned for replacement in GD2. One system of three will remain at Shorne offtake in Kent, which is currently a non-critical supply. 8 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Volumetric Control Systems Volumetric flow control systems are typically used only on larger NTS offtakes. A number of SGNs offtakes in Scotland are relatively small and supply isolated, sole fed networks and are therefore pressure controlled. Downstream Transmission duty PRS’s are also pressure controlled. Control Valves are used for volumetric flow control, as they facilitate accurate ‘Set Point Control’ (SPC) and ‘Direct Valve Control’ (DVC) as required by SGNs Gas Control Centre, to maintain steady flowrates. Control Type Southern Offtakes Scotland Offtakes Volumetric Control 11 5 Pressure Control 1 13 Similar to the ‘Valtek’ Control Valves on the Winkfied Southeast system, ‘Severn’ ‘Drag’ - Type 200 Control Valves are the older version of the ‘Drag’ valve, now produced by ‘IMI CCI’. One system in Scotland was replaced prior to the start of GD1. Three systems exist within the Southern network; one system of two at Croydon PRS will be replaced before the end of GD1; a system at Braishfield ‘B’ remains and a refurbishment during GD1 has allowed these a short life-extension. It is planned to replace these in GD3. The third system of four is at Winkfield suppling gas into the south network. 4 Problem Statement Why are we doing it? Gas pre-heat prior to the pressure reduction process is currently provided by three obsolete water bath heaters at Winkfield southeast. One of the vessels of these water bath heaters, denoted ‘A’, has previously failed, which led to a major release of heating solution, comprising of water and antifreeze. The failure resulted in the loss of the 1500 kwh of gas pre-heating for the duration of the incident. All of the SGN water bath heaters at Winkfield are exhibiting high failure rates, with significant defects, including fatigue cracking, erosion within the tanks and numerous failures of the supporting pneumatic and instrumented control systems. Primary protection and safe isolation of the downstream system is provided by actuated ‘Cameron’ ball valves. The historical practice of actuating the PRS stream inlet valves as slam-shuts, in this case, large, buried ball valves, is no longer supported by IGEM/TD13. Inspection requirements include an initial test and then three more set point tests and corresponding timings to close. These tests are repeated every 6 months, to satisfy SGNs maintenance program and to comply with the requirements of the sites PSSR ‘Written Scheme of Examination’. This is to conform to the statutory Pressure Systems Safety Regulations 2000 (PSSR). Natural degradation and the significant number of tests, over the 50 year life of these valves, has undoubtedly, caused irrevocable wear and damage to the valve elastomer seats, seals and oil driven actuation system. These valves are failing the inspection test requirements carried out in accordance with the Pressure Systems Safety Regulations, due to excessive closure times. Previous investment in the replacement of the on the valve actuation control systems has reduced the closure times, however they still exceed the PSSR requirement. Failure of a slam-shut valve to close within acceptable time limits could lead to the over-pressurisation and damage to the South East LDZ downstream, pressure system. 9 December 2019
SGN Trans – 002Wink1 – EJP Dec19 ‘Valtek’ Control Valves are similar to ‘IMI CCI’ (Severn) Drag type 200 Control Valves. These valves comprise the primary elements of the volumetric control system and are demonstrating a loss of control on a regular basis with numerous faults being reported. Maintenance and refurbishment of these valves by ‘IMI-CCI’ has been attempted, but without significant improvement. The volumetric control system operates under the governance of a ‘boundary control’ system. A ‘boundary control’ system is used to negate the cost to increase the size of a downstream pipeline, where gas demand has increased beyond design forecast. ‘Boundary control’ will ensure that moderate and occasional increases in gas demand are met within the downstream network, without exceeding the Maximum Operating Pressure of the downstream pipeline. Therefore, additional funding is proposed, for the replacement of this essential, instrumented system, as part of the volumetric control system. The project will be deemed successful if delivered on time, in budget, to the SGN specification and with no impact to our customers. Impact of ‘do nothing’ approach Failure to carry out intervention and replace the existing water bath pre-heaters will leave the existing system at a real and increasing risk of failure! Controlled pre-heating is essential to combat unavoidable gas and pipework freezing following pressure reduction. This phenomenon is known as the ‘Joule-Thomson effect’. A differential pressure reduction of up to 50 bar will result in the loss in temperature of around 250C. Gas enters the site at temperatures down to +50C during winter, meaning that gas could leave the site at -200C, that is below the acceptable operating temperatures for the PRS equipment and downstream steel pipelines. The consequences include embrittlement, pipeline rupture, gas escapes, ignition and consequential fatalities. There is also the potential for a major loss of supply to customers and frost heave along the pipeline route, across roads, bridges and other transport infrastructure. Failure to deliver intervention to replace the slam-shut valve, overpressure cut-off devices will leave the downstream system at a real risk for over-pressurisation. The pipeline and pressure system to Ripley has a Safe Operating Limit (SOL) of 46.2 barg and then 41.8 barg from Ripley to Mogador, all as s defined by PSSR 2000 and IGEM/TD/13. These would be greatly exceeded by an inlet pressure of up to 75 barg. The consequences include pipeline rupture, ignition, fatalities and potential loss of major gas supplies to both industry and domestic customers. Failure to deliver the intervention to replace the volumetric control system will reduce the ability of the SGN Gas Control Centre to control flow-rates and could lead to possible over-pressurisation. This would increase reliance on the slam-shut valves. Assuming the slam-shut valves are replaced, the outcome would be a potential loss of supply to customers. How do we know we have achieved the outputs The project will be successful if delivered on time, within budget, to the SGN specification and with no impact on customers. Monitoring the site in real time’ through the gas control Distribution Network Control System (DNCS) - monitoring and recording the gas outlet temperature, pressure and flow performance. Inspecting results of routine maintenance and pressure systems inspections and reviewing faults. Narrative Real-Life Example of Problem Loss of heating would lead to extremely cold gas entering the downstream steel pipeline, over a period of time this could lead to embrittlement, frost heave and will induce additional stresses and shorten the life of 10 December 2019
SGN Trans – 002Wink1 – EJP Dec19 the pipeline. This could lead to a failure of the Control Valves which could freeze in position, potentially over pressuring the network, or the downstream High Pressure pipeline could rupture due to induced stresses and ground movement. The 450mm diameter slam-shut valves are inspected every 6 months. These inspections have identified that the valves close well above the specified limits of 18 seconds. Analysis has proven that at low demand, the downstream system will over-pressurise with the valves closing at the times recorded in the table below. Winkfield AGI 450NS PSSR SSV Closing Times in Seconds SGN SSV 2017 2018 2019 IDENTIFICATION 1st 2nd 3rd Initial 1st 2nd 3rd Initial 1st 2nd 3rd 702492 SE 72s 68s 68s 59s 58s 56s 54s 45s 43s 42s 42s 702493 SE 40s 42s 42s 57s 56s 54s 51s 49s 47s 47s 47s There are currently no stream selection facilities at Winkfield, as prescribed by the industry standard IGEM/TD/13. Some protection against loss of supply in both streams, is currently achieved by staggering the slam-shut valve closing set-points i.e. working stream at 42.5 barg and Standby stream at 43.5 barg. This could lead to the working stream slam-shut valve closing prematurely, should the standby stream Control Valves fail and open! The critical auxiliary systems connected to the ‘Valkek’ Control Valves and actuators have been in continuous operation since 1983. Essential spares and replacement components for maintenance and repair are no longer available. This has caused stiction, excessive venting to atmosphere and very poor control. The following is an example of the very poor flow control: Winkfield South East 6 5.5 5 Flow (mscm/day) 4.5 4 3.5 3 2.5 2 00:27 00:54 01:21 01:48 02:14 02:41 03:08 03:35 04:02 04:29 04:55 05:22 05:49 06:16 06:43 07:10 07:36 08:03 08:30 08:57 09:24 09:51 10:17 10:44 11:11 11:38 12:05 Time Offtakes are designed to operate in volumetric control in either Set Point Control (SPC) or Direct Valve Control (DVC), the former involves the inputting of a set flowrate by the Gas Control Centre (GCC) and the site controlling at that set point. DVC involves the inputting of a valve position with the site stabilising at 11 December 2019
SGN Trans – 002Wink1 – EJP Dec19 that set point. The graph above shows the actual flowrate when GCC had requested a specific value of SPC, whereas the valves are unstable at the set point and are exhibiting drift and slow control. Spend Boundaries The spend of this project on the Winkfield South East LDZ Offtake is to replace both the PRS heating system and the pressure control system including the two stream slam-shut valves. It is not possible to refurbish either the slam-shut valves or the rotating vane, oil driven actuators; the soft seated ball valves are buried and have fully welded bodies that are also welded to the 75 barg inlet pipework. It is also not possible to refurbish the current 37 year old ‘Valtek’ Control Valves. There is insufficient space between the existing inlet and outlet stream isolation valves to install new slam-shut valves, Control Valves, heat exchangers and stream discrimination check valves. 5 Probability of Failure Background The failure rate and deterioration applied to calculate the CBA is consistent with the NARMs methodology. The key principle adopted in the methodology to facilitate the assessment of risk are: • Asset health equates to the probability that the asset fails to fulfil its intended purpose and thus gives rise to consequence for the network. • The consequences can be assessed in monetary terms • The risk is determined from the product of the number of failures and the consequence of those failures 5.1 Failure rate In the NARM framework ‘failure rate’ is used to calculate the Probability of Failure. The failure rate gives the rate of occurrence (frequency) of failures at a given point in time and may also include an age/time variable, known as asset deterioration, which estimates how this rate changes over time. The failure rate can be approximated by fitting various parametric models to observed data to predict failures now and in the future. Therefore, data that contributes towards monetised risk value has been thoroughly reviewed for each system under this investment. Failure modes In the NARMs methodology the failures are categorised into different Failure Modes. Below is list of all failure modes considered in the methodology and any data modification made to the model. 12 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Pressure control and filter • Release of Gas - relating to the failure of a pressure containing component on site leading to an unconstrained release of gas within and possibly off the site • High Outlet Pressure - failure of the Pressure Control system to control the pressure at least to within the Safe Operating Limit of the downstream system. This would typically require the concurrent failure of both regulators and the slamshut (failure to operate) within one Pressure Control stream. • Low Outlet Pressure - relates to the failure of the Filter and Pressure Control system to supply gas at adequate pressure leading to partial or total loss of downstream supplies • Capacity - where the system has insufficient capacity to meet a forecast 1:20 peak day downstream demand • General failure - relating to other failures not leading to either a safety, environmental or gas supply related consequence. Pressure Control Asset Attributes Modification Reason CONDITION_SCORE Changed from 3 to 4 The current score is listed as 2, ‘near new’ but the SE site is approaching 40 years old. Some of the Control Valves were overhauled in 2010 and this gave little improvement in performance. There have been a number of occasions that the control system has lost control of the outlet pressure. KIOSK_CONDITION Changed from 0.5 to 1 The SE pressure control equipment is not protected by a kiosk at Winkfield, therefore the kiosk condition was changed to 1 to make this node neutral. HIGH_OUTLET_PRESSURE 0 to 2 The primary protective devices on both streams are unable to protect the downstream network. The slam-shut valves have failed tests 3 years in row and currently have two ‘PSSR’ A2 faults recorded, based on the time taken to close the valves. Network analysis has shown that the excessive timings to close, could over-pressurise the downstream network. PC_RELEASE_OF_GAS_PRI 0 to 2 The faults specified above could also lead to complete failure of downstream asset and therefore, it also has an impact on RELEASE_OF_GAS node 13 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Preheating • Release of Gas - relating to the failure of a pressure containing component on site leading to an unconstrained release of gas within and possibly off the site • High Outlet Temperature - relating to the failure of the preheating system to provide the correct heat input for that associated site gas flow rate resulting in high outlet temperatures • Low Outlet Pressure - relates to the failure of the preheating system to provide the correct heat input for that associated site gas flow rate resulting in low outlet temperatures • Capacity - where the system has insufficient capacity to meet a forecast 1:20 peak day downstream demand • General failure - relates to other failures not leading to release of gas, low/high outlet temperature or capacity failures. Preheating Asset Attributes Modification Reason CONDITION_SCORE Score updated from 2 to 3 The current score is listed as 2, ‘as new’ but the Winkfield South East pre-heating system is nearly 40 years old and not had any significant integrity work. The auxiliary pressure breakdown and control equipment has reached the end of operational life. KIOSK_CONDITION Changed from 0.5 to 1 Current score set to 0.5 however there is no kiosk on site therefore, KIOSK_CONDITION changed to 1 to make this node neutral NO_EFFECT_PRI Changed from 0 to 3 15 failures has been recorded over the last 6 years for this system. This equates to 2.5 faults per year. 5.2 Probability of Failure Data Assurance Below are the failure rates derived from the model for each failure mode: Preheating Failure Mode 2021 2022 2023 2024 2025 2026 Release of Gas 0.033 0.039 0.046 0.054 0.063 0.074 General Failure 0.605 0.711 0.834 0.979 1.148 1.348 High Outlet Temp 0.006 0.006 0.008 0.009 0.010 0.012 Low Outlet Temp 0.394 0.463 0.543 0.637 0.748 0.877 Failure Rate – Preheating 14 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Pressure Control Failure Mode 2021 2022 2023 2024 2025 2026 High Outlet Pressure 0.408 0.408 0.444 0.496 0.554 0.618 Low Outlet Pressure 0.208 0.208 0.227 0.253 0.282 0.315 Release of Gas 0.433 0.433 0.472 0.527 0.588 0.656 General failure 0.105 0.105 0.114 0.127 0.142 0.159 Failure rate – Pressure Reduction 6 Consequence of Failure The below Matrix plots the credible failure modes against how severely it will affect each of the consequences. These are colour coded to give a visual representation of the likely impact: Failure Consequence Environmental Failure Mode Security of Supply Safety Impact Impact Security of Supply would be lost for a Pressure Regulating Equipment significant quantity of No direct effect No direct effect (Both Slamshuts Closed) customers with both slamshuts closed Safety impact is elevated If overpressurisation compared to escape Carbon emissions causes a significant Pressure Regulating Equipment within the site, as this proportionate to escape, security of (Overpressurisation of Outlet) could affect pipework the volume of the supply could be within proximity to the escape affected general public Safety impact is elevated compared to escape If brittle fracture causes within the site, as this Carbon emissions Preheating Equipment (Failure at a significant esacpe, could affect pipework proportionate to winter, brittle fracture due to cold security of supply could within proximity to the the volume of the temperatures) be affected general public (although escape chilling will be most severe closer to the site). In the NARM methodology Consequence of Failure is analysed for each failure mode and every Consequence of Failure has an assigned Probability of Consequence (PoC). This is determined through consequence analysis techniques such as: • Statistical analysis of associated failure data • HAZOP techniques (Risk assessment) • Historic incident data • GIS (Geographic Information System) analysis • Network modelling analysis Each Consequence of Failure in the model have an associated financial cost (Cost of Consequence), based upon the type and scale of impact, representing a monetary risk value. These Consequence of Failure are split into the following categories: • Customer Risk – Loss of supply • Health and Safety Risk – Death, injuries, property damage, etc. 15 December 2019
SGN Trans – 002Wink1 – EJP Dec19 • Environmental risk • Other financial Risk – Repair, Maintenance, etc. Consequences Pressure Control and Filter The following consequence measures were identified for Filter and Pressure Control assets: • DS Gas Escapes – an Increase in gas escapes in the downstream network due to low outlet temperatures • Loss of Gas – a loss of gas arising from the Filters & Pressure Control asset itself or the downstream network • Explosion – an explosion, either at the Filters & Pressure Control asset itself or in the downstream network • PRS Site Failure – a site failure resulting in loss of supply to downstream domestic, commercial or industrial consumers Figure below outlines the event tree diagram for Pressure control and Filter Preheating The following consequence measures were identified for Pre-heating assets: • DS Gas Escapes – an Increase in gas escapes in the downstream network due to low outlet temperatures • Loss of Gas – a loss of gas arising from the Pre-heating asset itself or the downstream network • Explosion – an explosion, either at the Pre-Heating asset itself or in the downstream network • Ground Heave – Events resulting in damage to structures, roads and other assets due to low outlet temperatures • PRS Site Failure – a site failure resulting in loss of supply to downstream domestic, commercial or industrial consumers 16 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Figure below outlines the event tree diagram for Pressure control and Filter 7 Options Considered Within this Engineering Justification Paper for there are 4 options which have been considered and discussed to address the pre heating and pressure control at Winkfield South East Offtake. The 4 core options being considered are as follows: • Replace on Failure • Repair on Failure • Pre-Emptively Replace • Pre-Emptively Repair When considering this intervention, we have done so following our 4R strategy. This strategy is designed to maximise the asset life and minimise the capital expenditure of intervention and in doing so sets out an order of preference for the intervention type. This order is key in delivering customer value and focuses on the lighter intervention options of repairing and refurbishing the asset before considering more severe interventions such as full replacements of the existing assets. See below for an illustration of our 4r 17 December 2019
SGN Trans – 002Wink1 – EJP Dec19 strategy: Diagram of 4R Strategy. Repair and Refurbish options at the top are considered before resorting to Replace or Rebuild at the bottom Following this strategy, the options of a reactive repair or proactive refurbishment are typically considered ahead of proactively rebuilding the site or carrying out a replacement reactively. 7.1 Component replacement It is not possible to replace or refurbish the existing slam-shut valves, these are fully welded, in-line, actuated and buried ball valves. It is also not possible to refurbish the Control Valves as, there is insufficient room to install new Control Valves and stream selection check valves, between the existing stream isolation valves. 7.2 Refurbish components Refurbishment of components could derive a short-term extension of the life of the asset. However, refurbishment has already been attempted to both the pre-heating and volumetric Control Valve systems with limited or no success. 7.3 Replace on failure With the time necessary to source and replace this critical equipment (Control Valves and slam-shut valves) being at least 50 weeks, should the equipment fail, the system would not be available for an unacceptable period and potentially two winters. This would render the downstream network at a high risk for failure of gas supply. The replacement of the water bath heating system would take approximately eighteen months to complete, therefore this is not a viable option. 18 December 2019
SGN Trans – 002Wink1 – EJP Dec19 7.4 Repair on failure With very long lead times for replacement Control Valves, this option has been discarded. Dismantling and repairing the heating system, could typically take a minimum of twelve to twenty weeks, therefore this is not a viable option, as the SE Offtake would not have any standby heating capacity, should a second water bath heater fail. 7.5 Do nothing The system is not compliant with IGEM/TD/13 and if one of the existing water bath heaters fails, there will be no stand-by facility within the heating system. The poor performance of the slam-shut valves could lead to an over pressurisation of the downstream network. Therefore, this option has been discarded. 7.6 Replacement of volumetric Control Valves and gas preheating system Replace the gas preheating system and the flow/pressure control systems. This will include the installation of heat exchangers, supporting boiler house and pressure reduction unit, to supply LP gas to the boilers. The pressure control system will include the installation of new Control Valves, that will be volumetrically controlled to accurately deliver the required daily flow rate, with protective pressure overrides. New slam- shut valves to protect the downstream system from over-pressure, that will also have a stream discrimination facility to protect the stand by stream from prematurely closing. This system will also have a ‘boundary control’ system to ensure the pressure at the remote point (Ripley in Surrey) will not exceed a pressure of 38 BarG. Other options, such as full rebuild of all systems on site, have not been considered as they represent unnecessary expenditure to replace currently functioning or ‘fit for purpose’ assets. The technical detail of the option i.e. capacity, system rating, availability etc. The proposed new PRS streams at Winkfield, System 1, South East, will be designed to meet the predicted load growth for the next ten years, i.e. 10 mcmd (416.67 kscmh) and meet a pre-heat requirement of 3,014 kwh. The PRS will be twin stream with 100% stand-by facility for the second stream, in accordance with IGEM TD/13. Each stream will contain a fast-acting Slam-shut valve, ‘Monitor’ Control Valve, ‘Active’ Control Valve and a stream discrimination facility (non-return valve), to ensure that each stream operates independently. The system will also be rated for an inlet pressure range from 75 BarG down to 40 BarG and outlet pressure range between 42 BarG down to 21 BarG. The ‘Boundary Control’ system at Winkfield will limit the pipeline operating pressure to 38 BarG at Ripley. 19 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Winkfield site schematic Security Plan Security 20 December 2019
SGN Trans – 002Wink1 – EJP Dec19 The basis for the cost estimate/unit cost Following an initial costed design by Rush Construction, in report “SGN GD2 Mechanical & Civil Budget Analysis” SGN Trans - 002Wink1 - EJP Dec19_SupportingCosts.pdf the costings were reviewed by SGN Major Projects using experience from GD1. These costs are indicated in the table below: WINKFIELD S.E. Investment summary Commercial Confidentiality The perceived benefits of the option Removal of immediate risk to customers, for both security of supply following a failure of the regulators, with the associated long lead time on key pieces of equipment and risk of exposing the outlet to extremely 21 December 2019
SGN Trans – 002Wink1 – EJP Dec19 cold gas with the potential creating gas leaks, frost heave or poor control of the regulators. Also reduces the risk of a standby stream failure being able to shut of gas supplies through both streams of regulators. Delivery timescales 2021 - Design 2023 - Procurement 2024/5 - Main Works Contractor, including decommissioning and removal of redundant system Key assumptions made Major projects identified additional costs from the desk top exercise, removal of the existing large water bath heaters. With the cost of the main works contractors increasing significantly, based on experience of current projects. Any other items that differentiate the option from the others considered A number of interventions have been considered. However, the benefits of all but one are considered inadequate in mitigating the current issues. Only the intervention to replace relevant components – pre-heating and volumetric / pressure control system is deemed adequate in resolving the outstanding issues. 7.7 Options Cost Details Table – Options Technical Summary Option First Year of Final Year of Volume of Equipment / Total Cost Spend Spend Interventions Investment Design Life 1. System replacement (Full heating and 2021 2025 1 45 years £8.23m Pressure control Systems) 7.8 Options Cost Summary Table Table – Cost Summary Option Cost Breakdown Total Cost (£m) 1. System replacement (Full Commercial Confidentiality £8.23 heating and Pressure control Systems) Projects costing have been achieved through the following process and includes contingency numbers, efficiencies and overheads to give the total gross cost: 22 December 2019
SGN Trans – 002Wink1 – EJP Dec19 • Initial scoping of works including design parameters, • Desk-top feasibility study using design consultants with full awareness of GD1 projects, • Contact with manufacturers. • Additional assessment by Project Managers to take into account local site conditions, constraints and costing information based on recent projects. Including increasing significantly the cost for the main works contractors. • Review by Asset Manager. 8 Business Case Outline and Discussion Winkfield South East offtake is an important feed into the South East LDZ of Southern Network. The current LDZ peak 1 in 20 demand is 43.205mscm/d, of which 4.207mscm/d is provided by Winkfield South East offtake. As a result of the degree of resilience in offtake capacity, the loss of this offtake would not immediately affect customers, although, as this site is the only feed into the west of the system, diurnal storage capacity would be curtailed for the South East LDZ comprising around 2.3m customers. Offtake Name Capacity (mscm/d) Current Winter Failure - No. of (mscm/d) Customers Lost Winkfield SE 10.000 4.207 - At other times, the loss of Winkfield South East will significantly reduce the gas supply resilience. The current anticipated probabilities of failure for the pre-heating system are 0.394 failures per annum (low outlet temperature) and 0.605 (general failures). The probabilities of failure of the volumetric / pressure control system is 0.408 (high outlet pressure) and 0.433 (release of gas). All of these probabilities are high for a critical asset. Only one option is deemed adequate to reduce the probability of failure of the pre-heating and volumetric / pressure control systems and to mitigate the consequences of failure at Winkfield South East offtake. 8.1 Key Business Case Drivers Description Table – Summary of Key Value Drivers Option Desc. of Option Key Value Driver No. Baseline Repair on Failure Potential, long term loss of supply to customers, safety and environmental impact due to cold fracturing 1 Preheating and pressure The main drivers for this project are safety and licence control systems condition. replacement Failure to replace the pressure reduction system could lead to an over pressurisation incident on the South East LDZ Local Transmission System. With a potential for a failure /rupture of part of the downstream system. Failure to replace the heating system at Winkfield South East LDZ, there is potential for SGN to have to supply gas that is 23 December 2019
SGN Trans – 002Wink1 – EJP Dec19 not heated, this could lead to ground movement, frost heave and failure of the regulators to control. The boundary control system does not meet current safety standards and needs to be replaced with a Safety Instrumented System. Table – Summary of CBA Results NPVs based on Payback Periods (absolute, £m) Option Desc. of Option Preferred Total Forecast Total No. Option Expenditure 2030 2035 2040 2050 NPV (Y/N) (£m) Baseline Repair on Failure N -0.36 -29.91 -3.64 -6.53 -10.13 -18.62 Option 1 Absolute 1 Y -8.58 -10.80 -7.33 -8.27 -9.01 -9.93 NPV Option 1 NPV 1 Y -8.58 -10.80 -3.69 -1.74 1.12 8.70 relative to Baseline 24 December 2019
SGN Trans – 002Wink1 – EJP Dec19 8.2 Business Case Summary Table 05 - Business Case Matrix System Replacement Capex (£m) 8.23 Number of Interventions 1.00 Carbon Savings ktCO2e (GD2) 6884.21 Carbon Savings ktCO2e /yr 1376.84 Carbon Emission Savings (30yr PV, £m) 2.85 Other Environmental Savings (30yr PV, £m) 0.00 Safety Benefits (30yr PV, £m) 17.46 Other Benefits (30yr PV, £m) 0.52 Direct Costs (30yr PV, £m) -7.98 NPV (30yr PV, £m) 12.85 High Carbon Scenario Carbon Emission Savings (30yr PV, £m) 4.27 High Carbon NPV (30yr PV, £m) 14.27 SE - Winkfield Offtake - System 2 - 0 10 20 30 40 50 60 (5.00) (10.00) (15.00) (20.00) (25.00) (30.00) (35.00) Baseline Option 1 25 December 2019
SGN Trans – 002Wink1 – EJP Dec19 9 Preferred Option Scope and Project Plan 9.1 Preferred option The preferred option is to rebuild both the heating system and pressure reduction systems. This would ensure the risks associated with equipment on site is efficiently managed and the risk to gas supply system is reduced. 9.2 Asset Health Spend Profile The anticipated asset spend profile is as follows: Asset Health Spend Profile (£m) 2021/22 2022/23 2023/24 2024/25 2025/26 Post GD2 System Replacement 0.33 1.82 4.91 1.17 0.00 0 GD/2 Yr 1 (22/23) GD/2 Yr 3 (24) GD/2 Yr 4 •Detailed Design •Materials Procurement (25) •Construction •Commissioning 9.3 Investment Risk Discussion Sensitivities have been applied to the Transmission Integrity CBAs as follows: • Variations in Capex project cost have been applied for the range -10% to +20%. These are considered realistic ranges based on our experience in GD1 and the likely pressures on cost in relation to the procurement of materials and main contracts. • Variations in methane levels (and therefore environmental impact) have been considered to take account of the anticipated introduction of hydrogen. SGN have committed to a ‘net zero’ carbon network by 2045. In practice that means no methane by that date. Also, while the use of hydrogen in distribution is being actively investigated and hydrogen is currently being introduced into a network for the first time since the conversion to natural gas, it is considered very unlikely that hydrogen will be injected on a wider scale until RIIO-GD3. For these reasons, methane levels have been considered in three ranges: aggressive early transition, mid-case and late transition. 26 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Figure 1: Methane / hydrogen transition – sensitivities The current version of the CBA template, version 4, already acknowledges that methane is estimated to be 28 times more damaging than CO2. This figure is taken from the IPCC Fifth Assessment Report published in 2014. Since this figure is derived from the latest science, it is not considered prudent to test for sensitivity in this area. Sensitivity in the value / cost of carbon is already included within the CBA template with base-case and high-case scenarios mapped out. These sensitivities are considered sufficient in our CBA. Low Mid High Capex (£m) 7.41 8.23 9.88 Number of Interventions 1 1 1 Carbon Savings ktCO2e (GD2) 6,884 6,884 6,884 Carbon Savings ktCO2e /yr 1377 1377 1377 Carbon Emission Savings (30yr PV, £m) 2.8 2.8 2.8 Other Environmental Savings (30yr PV, £m) 0 0 0 Safety Benefits (30yr PV, £m) 17.5 17.5 17.5 Other Benefits (30yr PV, £m) 0.5 0.5 0.5 Direct Costs (30yr PV, £m) -7.2 -8.0 -9.6 NPV (30yr PV, £m) 13.7 12.9 11.2 Project payback has not been carried out as part of this analysis due to the effect of the Spackman approach. For a cash-flow traditional project payback period please see scenario 4 of our Capitalisation Sensitivity table. Consumers fund our Totex in two ways – opex is charged immediately though bills (fast money – no capitalisation) and capex / repex is funded by bills over 45 years (slow money – 100% capitalisation). The amount deferred over 45 years represents the capitalisation rate. Traditionally in ‘project’ CBA’s the cashflows are shown as they are incurred (with the investment up front which essentially is a zero capitalisation rate). Therefore, we have developed scenarios that reflect both ways of looking at the investment – from a consumer and a ‘project’. 27 December 2019
SGN Trans – 002Wink1 – EJP Dec19 The scenarios are summarised as follows: • Scenario 1 - we have used the blended average of 65%, used in previous iterations of this analysis. • Scenario 2 - we have represented the Capex and Opex blend for the two networks, as per guidance. • Scenario 3 - addresses our concerns on capitalisation rates whereby Repex and Capex spend is deferred (100% capitalisation rate) and Opex is paid for upfront (0% capitalisation rate). • Scenario 4 - this reflects the payback period in ‘project’ / cash-flow terms and provides a project payback. We have taken a view of the NPV in each of the scenarios, with the exception of scenario 4, at the 20, 35 and 45 Year points, to demonstrate the effect of Capitalisation Rate on this value. Scenario 1 2 3 4 Capex (%) 65 38 100 0 Opex (%) 65 38 0 0 Repex (%) 100 100 100 0 Output NPV (20yr PV, £m) 2.20 1.83 3.20 NPV (35yr PV, £m) 12.87 12.85 13.31 NPV (45yr PV, £m) 19.08 19.10 19.36 Payback 16.00 17.00 11.00 18.00 28 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Appendix A - Acronyms Acronym Description BarG Measurement of pressure above atmospheric pressure (gauge) in units of Bar CBA Cost Benefit Analysis CGS City Gate Station – A pressure reduction system supplied from the intermediate pressure system and feeding either low or medium pressure systems DS Downstream GD1 Gas Distribution – Price Control for 2013 to 2021 GD2 Gas Distribution – Price Control for 2021 to 2026 HAZOP Hazard and Operability Study HI4 Health Index – Asset condition approaching or at end of serviceable life, intervention required HP High Pressure (Natural Gas above 7 barg) IGEM Institution of Gas Engineers and Managers IP Intermediate Pressure (Natural gas 2 BarG to 7 barg) KPI Key Performance Indicator LTS Local Transmission System Kscm Thousand cubic meters per hour LP Low Pressure (Natural gas less than 75 m barg) MP Medium Pressure (Natural Gas 75 mbarg up to 2 barg) NARM Network Asset Risk Measure Mcmd Million cubic meters day rate PE Polyethylene PoC Probability of Consequence PRI Pressure Reducing Installation PRS Pressure Reduction Station PSSR Pressure Systems Safety Regulations 2000 RIIO Revenue = Incentives + Innovation + Outputs Scm/h Standard cubic metres per hour (Flow) TD/13 IGEM/TD/13, Pressure regulating installations for natural gas, liquefied petroleum gas and liquefied petroleum gas/air µm Micron, Micrometre = one-millionth of a meter WBH Water Bath Heater 29 December 2019
SGN Trans – 002Wink1 – EJP Dec19 Appendix B - References 1. Author: Rush Construction. Report SGN GD2 Mechanical & Civil Budget Analysis. Report reference: SGN Trans - 002Wink1 - EJP Dec19_SupportingCosts.pdf 30 December 2019
You can also read