ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN

Page created by Travis Maxwell
 
CONTINUE READING
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
ENGEN

ENGEN ZENEX BLEND PLANT (ZBP)
DECOMISSIONING
STAKEHOLDER ENGAGEMENT REPORT

14 JUNE 2021                    DRAFT
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
ENGEN ZENEX BLEND
PLANT (ZBP)
DECOMISSIONING
STAKEHOLDER
ENGAGEMENT REPORT
ENGEN

TYPE OF DOCUMENT (VERSION)
DRAFT

PROJECT NO.: 41102362
DATE: JUNE 2021

WSP
BUILDING C
KNIGHTSBRIDGE, 33 SLOANE STREET
BRYANSTON, 2191
SOUTH AFRICA

T: +27 11 300-6141
F: +27 11 361 1301
WSP.COM

                                  WSP Environmental (Pty) Ltd.
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
QUALITY MANAGEMENT

ISSUE/REVISION                      FIRST ISSUE                        REVISION 1                   REVISION 2   REVISION 3

Remarks                             Draft

Date                                June 2021

Prepared by                         Alice Moropa

Signature

Checked by                          Carla Elliott
                                                     Elliott, Carla
                                                     (ZACE00769)
Signature                                            2021.06.17
                                                     16:12:16
                                                     +02'00'

Authorised by                       Nigel Seed
                                                                Digitally signed by Seed, Nigel
                                                                (ZANS00325)
Signature                                                       DN: cn=Seed, Nigel (ZANS00325),
                                                                ou=Active,
                                                                email=Nigel.Seed@wsp.com
                                                                Date: 2021.06.17 17:01:14 +02'00'

Project number                      41102362

Report number                       01

File reference                      G:\000 NEW Projects\41102362 - Engen LOPB ZPB Consolidation\42 ES\2-
                                    REPORTS\01-Draft\ZBP

WSP is an ISO9001:2015, ISO14001:2015 and OHSAS18001:2007 certified company
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
SIGNATURES

PREPARED BY

Alice Moropa
Environmental Consultant

REVIEWED BY
            Elliott, Carla
            (ZACE00769)
            2021.06.17
            16:12:45
            +02'00'

Carla Elliott,
Associate

This report was prepared by for the account of ENGEN, in accordance with the professional services agreement.
The disclosure of any information contained in this report is the sole responsibility of the intended recipient. The
material in it reflects Engen’s best judgement in light of the information available to it at the time of preparation.
Any use which a third party makes of this report, or any reliance on or decisions to be made based on it, are the
responsibility of such third parties. Engen accepts no responsibility for damages, if any, suffered by any third
party as a result of decisions made or actions based on this report. This limitations statement is considered part
of this report.
The original of the technology-based document sent herewith has been authenticated and will be retained by
WSP for a minimum of ten years. Since the file transmitted is now out of WSP’s control and its integrity can no
longer be ensured, no guarantee may be given to by any modifications to be made to this document.
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
PRODUCTION TEAM
CLIENT

Project Manager                      Luvasan Hirchan

WSP

Environmental Assessment Practitioner Alice Moropa

Environmental Specialist             Carla Elliott

Environmental Specialist             Nigel Seed
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
TABLE OF                              1        INTRODUCTION ........................................ 6
                                      1.1      PURPOSE OF THIS REPORT.................................. 6
CONTENTS                              1.2      OBJECTIVE OF THE STAKEHOLDER
                                               ENGAGEMENT PROCESS ...................................... 6

                                      2        STAKEHOLDER NOTIFICATION .............. 7
                                      2.1      AUTHORITY CONSULTATION ................................ 7
                                      2.2      ADVERTISEMENT .................................................... 7
                                      2.3      PUBLIC NOTICES .................................................... 7
                                      2.4      WRITTEN NOTIFICATION ....................................... 7
                                      2.5      STAKEHOLDER DATABASE .................................. 8
                                      2.6      DRAFT IMPACT ASSESSMENT REPORT
                                               DISCLOSURE ........................................................... 8
                                      2.7      FURTHER STAKEHOLDER ENGAGEMENT .......... 8

ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING                                                                            WSP
Project No. 41102362                                                                                               June 2021
ENGEN
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
TABLES
                                      TABLE 1:         INTERESTED AND AFFECTED
                                                       PARTIES NOTIFICATIONS...........7

                                      FIGURES
                                      FIGURE 1 PROOF OF PLACEMENTS OF ADVERT
                                                   IN THE SOUTHLANDS SUN .......10
                                      FIGURE 2 PROOF OF PLACEMENTS OF ADVERT
                                                   IN THE MERCURY ......................11
                                      FIGURE 3 PROOF OF POSTER PLACEMENT AT
                                                   GROSVENOR LIBRARY .............14
                                      FIGURE 4 PROOF OF POSTER PLACEMENT AT
                                                   GROSVENOR LIBRARY .............14
                                      FIGURE 5 PROOF OF POSTER PLACEMENT AT
                                                   FAMILY GROCERY –
                                                   LIGHTHOUSE ROAD, BLUFF ....14
                                      FIGURE 6 PROOF OF POSTER PLACEMENT AT
                                                   ZBP SITE ENTRANCE ................14
                                      FIGURE 7 PROOF OF POSTER PLACEMENT AT
                                                   THE CUTLER PERMIT OFFICE .15
                                      FIGURE 8 PROOF OF POSTER PLACEMENT AT
                                                   THE CUTLER PERMIT OFFICE .15
                                      FIGURE 9 FORMAL LETTER FOR WRITTEN
                                                   NOTIFICATION ...........................18
                                      FIGURE 10 PROOF OF WITTEN NOTIFICATION
                                                   DISTRIBUTED VIA EMAIL ..........19

                                      APPENDICES
                                      A        ADVERTS
                                      B        POSTERS
                                      C        WRITTEN NOTIFICATIONS
                                      D        STAKEHOLDER DATABASE

ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING                                                         WSP
Project No. 41102362                                                                            June 2021
ENGEN
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
1 INTRODUCTION
1.1 PURPOSE OF THIS REPORT
Engen has appointed WSP Environmental (Pty) Ltd (WSP), as the Environmental Assessment Practitioner (EAP), to
manage the Basic Assessment process for the Zenex Blend Plant (ZBP) decommissioning environmental
authorisation application to the KwaZulu-Natal Department of Economic development, Tourism & Environmental
Affairs (EDTEA).
In terms of the National Environmental Management Act (Act 107 of 1998, as amended) (NEMA) and the
Environmental Impact Assessment (EIA) Regulations promulgated in Government Notice (GNR) 326 of 7 April
2017, a Basic Assessment (BA) process is required for the decommissioning and removal of facilities previously
used for storing dangerous goods.
Stakeholder engagement is a fundamental part of the BA process and aims to include potential Interested and
Affected Parties (I&APs) in the process by notifying them of the proposed project. The objectives of the stakeholder
engagement process are to:
—   Ensure an open and transparent BA and consultation process;
—   Enable stakeholders to register their interest and provide input into the BA process and share information; and
—   Ensure that all relevant issues are addressed as part of the BA process.
The stakeholder engagement process is being undertaken in accordance with the EIA Regulations. The process aims
to ensure that potential stakeholders are identified and provided with an opportunity to review the details of the
proposed project and to submit any issues and concerns.

1.2 OBJECTIVE OF THE STAKEHOLDER ENGAGEMENT
    PROCESS
The objectives of the stakeholder engagement process are as follows:
—   To ensure an open and transparent Impact Assessment and consultation process;
—   To identify and inform stakeholders of the proposed project and associated environmental authorisation process;
—   Provide an opportunity for stakeholders to raise all issues, concerns and questions and ensure that these are
    considered in the environmental authorisation process for the project;
—   Ensure that stakeholders have an opportunity to make a meaningful contribution towards decision making by
    the competent authority, and
—   Compile a Comment and Response Report (CRR) of all issues, concerns and questions raised during the
    stakeholder engagement process.
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
2 STAKEHOLDER NOTIFICATION
2.1 AUTHORITY CONSULTATION
A pre-application meeting was held on 10 February 2021 with EDTEA in order to discuss the Department’s
requirements for the application.
An environmental authorisation application was submitted to EDTEA on 5 May 2021and acknowledged by EDTEA
on the 6 May 2021 with the reference number: DM-0011-2021. Local and Provincial authorities were provided with
written notification via email. The notified authorities include:
—   Department of Economic Development, Tourism and Environmental Affairs (EDTEA)
—   KZN EDTEA: Coastal Unit
—   Department of Water and Sanitation (DWS)
—   KZN Department of Agriculture & Rural Development
—   KZN Amafa
—   eThekwini Municipality
—   Transnet National Port Authority (TNPA) (landowner).

2.2 ADVERTISEMENT
The EIA Regulations require that an advertisement be placed in a local newspaper or official gazette for a project of
this nature. An advert was published in the Southlands Sun and the Mercury on 23 April 2021 (Appendix A). The
advertisement formally announced the commencement of the application process and requested that I&APs register
their interest with the EAP.

2.3 PUBLIC NOTICES
The EIA Regulations require that site notices be fixed at places that are conspicuous to and accessible by the public
at the boundary or on the fence or along the corridor of the site where the application will be undertaken or any
alternative site. Four site notices were placed at the following locations on in May 2021 (Appendix B).
—   Grosvenor Library
—   Lighthouse Family Grocer - Lighthouse Road, Bluff
—   Entrance of ZBP Site
—   Entrance of Cutler Permit Office

2.4 WRITTEN NOTIFICATION
Section 41 of the EIA Regulations states that written notices must be given to the stakeholders outlined in Table 1.
Written notices (Annexure C) notifying stakeholders of the proposed development were distributed via email, and
submitted by hand.
Table 1: Interested and Affected Parties Notifications

I&AP                                                          EAP COMMENT

The occupiers of the site and, if the proponent or applicant is TNPA, who is the lessor and the landowner in control of the
not the landowner or person in control of the site which the site was notified of the development via email.
activity is to be undertaken, the owner or person in control of
the site where the activity is or is to be undertaken and to any
alternative site where the activity is to be undertaken;

Owners, persons in control of, and occupiers of land adjacent The occupiers and owners of the adjacent land (Bidvest and
to the site where the activity is or is to be undertaken and to Vopak) were notified of the application telephonically and
any alternative site where the activity is to be undertaken;    via email.
ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING - STAKEHOLDER ENGAGEMENT REPORT ENGEN
The municipal councillor of the ward in which the site and      The Ward Councillors (Ward 32 and Ward 66) were notified
alternative site is situated and any organisation of ratepayers of the application both telephonically and via email.
that represent the community in the area;

The municipality which has jurisdiction in the area;            A notification was sent to the eThekwini Municipality via
                                                                mail.

Any organ of state have jurisdiction in respect of any aspect   Notices were provided to the authorities listed in Section 2.1
of the activity; and                                            via email.

Any other party as required by the competent authority          If found necessary, stakeholders will be added on request by
                                                                EDTEA as the competent authority.

2.5 STAKEHOLDER DATABASE
Engen maintains an existing stakeholder database which was accessed included in the stakeholder database
(Appendix D). Other known stakeholders with a potential interest in the project were identified at the project outset.
This included all relevant authorities (government departments and the eThekwini Municipality), and the
surrounding community members / community representatives. Stakeholder database maintenance is ongoing.
Those who registered with an interest in the project as a result of the notification process are included in the
database.

2.6 DRAFT IMPACT ASSESSMENT REPORT DISCLOSURE
The Draft BAR will be distributed for public review for a period of 30 days from Tuesday 22 June 2021 to
Wednesday 21 July 2021.
Hard copies and/or electronic copies of the report will be provided to the following relevant regulatory and local
authorities for commenting:
—   EDTEA;
—   DWS;
—   KZNDARD;
—   KZN Amafa;
—   eThekwini Municipality; and
—   The Ward Councillor (Ward 32).
Stakeholder will be notified of the availability of the Draft BAR for review Online on the WSP website:
http://www.wspgroup.com/en/WSP-Africa/What-we-do/Services/All-Services-A-Z/Technical-Reports/

2.7 FURTHER STAKEHOLDER ENGAGEMENT
The below stakeholders have requested a site walkover at ZBP. WSP is in communication with Engen with regards
to this request. Should necessary approvals be granted for the site walkover, this will take place during the 30 days
stakeholder review period (Tuesday 22 June 2021 to Wednesday 21 July 2021):
—   South Durban Community Environmental Alliance (SDCEA), and
—   Community Development South Africa (COMDEV).
A comment and response report will be captured in the Final BAR, which will outline the comments received from
the stakeholders and responses provided by the applicant and EAP for consideration by EDTEA.
APPENDIX

A   ADVERTS
Figure 1 Proof of Placements of Advert in the Southlands Sun
Figure 2 Proof of Placements of Advert in the Mercury
APPENDIX

B   POSTERS
Figure 3 Proof of poster placement at Grosvenor Library   Figure 4 Proof of poster placement at Grosvenor Library

Figure 5 Proof of poster placement at Family Grocery –
Lighthouse Road, Bluff

                                                          Figure 6 Proof of poster placement at ZBP Site Entrance
Figure 7 Proof of poster placement at the Cutler Permit   Figure 8 Proof of poster placement at the Cutler Permit
Office                                                    Office
APPENDIX

C  WRITTEN
  NOTIFICATIONS
Figure 9 Formal Letter for Written Notification
Figure 10 Proof of Witten Notification distributed via email
APPENDIX

D  STAKEHOLDER
  DATABASE
CATEGORY                  ORGANISATION                                    SURNAME      NAME
Provincial Authorities    KZN EDTEA: Coastal Unit                         Parak        Omar

                          KZN EDTEA: HOD                                  Myeza        Sibusiso
                          EDTEA: eThekwini District EIA Component         Brijlal      Natasha

                          DWS                                             Ntombi       Madibe-Mngoma

Local Authorities         eThekwini Municipality: EIA                     Bathabile    Msomi

NGO's, CBO's & Associations WESSA                                         Sarah        Alcock

                          Amafa                                           Pawandiwa    Bernadet

                          South Durban ABM                                Singh        Eurakha

                          South Durban ABM                                Masombuka    Fanele

                          South Durban ABM                                Govender     Anitha

                          South Durban Community Environmental Alliance   Samson       Shanusha
                          (SDCEA)
                          GroundWork                                      Euripidou    Rico

                          GroundWork                                      Peek         Bobby

                          GroundWork                                      Admin

                          Coastwatch                                      Schwegman    C

Neighbouring Land User    Bidvest Terminals (Neighbouring land user)      Priya        Govender

                          Vopak                                           Mariam       Haffejee

ENGEN Stakeholders        Community Member Resident                       Sarupdeo     Pradeep

                          Community Member Resident                       Palmer       Beulah

                          Community Member Resident                       Bonhomme     Lee

                          Community Member SDCEA                          D'sa         Desmond

                          Community Member ECSF                           Sayed        Sammy

                          Community Member ECSF                           Roskrige     Sr

                          Community Member ECSF                           Dandala      Sindy

                          Community Member ECSF                           Kistan       Gopal Ps.

                          Community Member ECSF                           Visagie      Chris Ps.

                          Community Member ECSF                           Ndlovu       Mthokozisi

                          Community Member ECSF                           Gomes        Jennifer

                          Community Member ECSF                           Usher        Jeannette Esmeen

                          Community Member ECSF                           Choudree     Jean

                          Community Member ECSF                           Van de Byl   Isadora

                          Community Member ECSF                           Visagie      Elaine

                          Community Member ECSF                           Steenan      Bradley
Community Member ECSF                             Chinsamy         Bobby Ganas

Community Member ECSF                             Bhengu           Bajabulile

Community Member ECSF                             Newall           Annette

Community Member Merebank Community Trust         Reddy            Strini

Community Member Merebank Community Trust         Selvie

Community Member Merebank Community Trust         Naicker          Daya

Community Member Merebank Community Trust         Coomar           Raj

Community Member Merebank Community Trust         Essop            Shahnaaz

Community Member Merebank Community Trust         Khalawan         Shano

Community Member Merebank Community Trust         Ramdheen         Roshan

EThekwini Municipality                            Prinsloo         JP

EThekwini Municipality                            Snyman           Aubrey

ECSF                                              Usher            David

ECSF                                              Smith            Victor

Ganges Seconadry                                  Reddy            Deena

Aplipore Primary                                  Folkard          Mr.

St Mary's ML Sultan Primary                       Ramdheen         Mr.

Merebank Secondary                                Banprakash       Timothy

SAPS (Wentworth Police Station)                   Raddy            Ballan

EThekwini Municipality South Durban Basin ABM     Singh            Eurakha

Parsee Rumtomjee                                  Singh            Mrs.

Settlers Primary                                  Lawrence         Mr

Settlers Primary

Junagarth Primary                                 Chetty           Dr.

PR Parther High                                   Satyendra        Mrs.

Ocean View School                                 Mkhize           Mr.

Nizam Road Primary                                Basdeo           Mr.

Fairvale Secondary (Wentworth Education Trust)    Seidle           Dale

Wentworth Secondary (Wentworth Education Trust)   Lamellate        Faye

Umbilo Secondary (Wentworth Education Trust)      Muller           Brain

Wentworth Primary (Wentworth Education Trust)     Small            Hilda

Austerville Primary (Wentworth Education Trust)   Singh            Mr

Durban East Primary (Wentworth Education Trust)   Timm             Charlotte

Gardenia Primary (Wentworth Education Trust)      Oliver           John

Assegai Primary (Wentworth Education Trust)       Abrahams-Field   Odette

Collingwood Primary (Wentworth Education Trust)   Chand            Colin

Mondi                                             Mbokazi          Leonard

SAPREF                                            Myeza            Londiwe

SAPREF                                            Khuzwayo         Lindiwe

SASDC                                             Van Wyk          Mark
Mangosuthu University of Technology                    Pillay   Sandra

                          Pump & Pipes Holdings                                  Derek    Ogle

Ward Councillors          Ward 66 - Bluff and Wentworth                          Zoe      Moore

                          Ward 32 - Clairwood and Bayhead                        Protus   Mngonyama

Landowner                 Transnet NPA Durban                                    Cindi    Cande

Registered stakeholders   Ex Bluff Ward Environmental & Coastal Conservation /   Louise   Colvin
                          Resident of the Bluff and member if Cutler Forum

                          Bluff Resident                                         Logan    Moodley
                          Pump and Pipes Holdings (Pty) Ltd                      Derek    Ogle

                          Community Development South Africa (COMDEV)            John     Stuart