ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING STAKEHOLDER ENGAGEMENT REPORT ENGEN TYPE OF DOCUMENT (VERSION) DRAFT PROJECT NO.: 41102362 DATE: JUNE 2021 WSP BUILDING C KNIGHTSBRIDGE, 33 SLOANE STREET BRYANSTON, 2191 SOUTH AFRICA T: +27 11 300-6141 F: +27 11 361 1301 WSP.COM WSP Environmental (Pty) Ltd.
QUALITY MANAGEMENT ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2 REVISION 3 Remarks Draft Date June 2021 Prepared by Alice Moropa Signature Checked by Carla Elliott Elliott, Carla (ZACE00769) Signature 2021.06.17 16:12:16 +02'00' Authorised by Nigel Seed Digitally signed by Seed, Nigel (ZANS00325) Signature DN: cn=Seed, Nigel (ZANS00325), ou=Active, email=Nigel.Seed@wsp.com Date: 2021.06.17 17:01:14 +02'00' Project number 41102362 Report number 01 File reference G:\000 NEW Projects\41102362 - Engen LOPB ZPB Consolidation\42 ES\2- REPORTS\01-Draft\ZBP WSP is an ISO9001:2015, ISO14001:2015 and OHSAS18001:2007 certified company
SIGNATURES PREPARED BY Alice Moropa Environmental Consultant REVIEWED BY Elliott, Carla (ZACE00769) 2021.06.17 16:12:45 +02'00' Carla Elliott, Associate This report was prepared by for the account of ENGEN, in accordance with the professional services agreement. The disclosure of any information contained in this report is the sole responsibility of the intended recipient. The material in it reflects Engen’s best judgement in light of the information available to it at the time of preparation. Any use which a third party makes of this report, or any reliance on or decisions to be made based on it, are the responsibility of such third parties. Engen accepts no responsibility for damages, if any, suffered by any third party as a result of decisions made or actions based on this report. This limitations statement is considered part of this report. The original of the technology-based document sent herewith has been authenticated and will be retained by WSP for a minimum of ten years. Since the file transmitted is now out of WSP’s control and its integrity can no longer be ensured, no guarantee may be given to by any modifications to be made to this document.
PRODUCTION TEAM CLIENT Project Manager Luvasan Hirchan WSP Environmental Assessment Practitioner Alice Moropa Environmental Specialist Carla Elliott Environmental Specialist Nigel Seed
TABLE OF 1 INTRODUCTION ........................................ 6 1.1 PURPOSE OF THIS REPORT.................................. 6 CONTENTS 1.2 OBJECTIVE OF THE STAKEHOLDER ENGAGEMENT PROCESS ...................................... 6 2 STAKEHOLDER NOTIFICATION .............. 7 2.1 AUTHORITY CONSULTATION ................................ 7 2.2 ADVERTISEMENT .................................................... 7 2.3 PUBLIC NOTICES .................................................... 7 2.4 WRITTEN NOTIFICATION ....................................... 7 2.5 STAKEHOLDER DATABASE .................................. 8 2.6 DRAFT IMPACT ASSESSMENT REPORT DISCLOSURE ........................................................... 8 2.7 FURTHER STAKEHOLDER ENGAGEMENT .......... 8 ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING WSP Project No. 41102362 June 2021 ENGEN
TABLES TABLE 1: INTERESTED AND AFFECTED PARTIES NOTIFICATIONS...........7 FIGURES FIGURE 1 PROOF OF PLACEMENTS OF ADVERT IN THE SOUTHLANDS SUN .......10 FIGURE 2 PROOF OF PLACEMENTS OF ADVERT IN THE MERCURY ......................11 FIGURE 3 PROOF OF POSTER PLACEMENT AT GROSVENOR LIBRARY .............14 FIGURE 4 PROOF OF POSTER PLACEMENT AT GROSVENOR LIBRARY .............14 FIGURE 5 PROOF OF POSTER PLACEMENT AT FAMILY GROCERY – LIGHTHOUSE ROAD, BLUFF ....14 FIGURE 6 PROOF OF POSTER PLACEMENT AT ZBP SITE ENTRANCE ................14 FIGURE 7 PROOF OF POSTER PLACEMENT AT THE CUTLER PERMIT OFFICE .15 FIGURE 8 PROOF OF POSTER PLACEMENT AT THE CUTLER PERMIT OFFICE .15 FIGURE 9 FORMAL LETTER FOR WRITTEN NOTIFICATION ...........................18 FIGURE 10 PROOF OF WITTEN NOTIFICATION DISTRIBUTED VIA EMAIL ..........19 APPENDICES A ADVERTS B POSTERS C WRITTEN NOTIFICATIONS D STAKEHOLDER DATABASE ENGEN ZENEX BLEND PLANT (ZBP) DECOMISSIONING WSP Project No. 41102362 June 2021 ENGEN
1 INTRODUCTION 1.1 PURPOSE OF THIS REPORT Engen has appointed WSP Environmental (Pty) Ltd (WSP), as the Environmental Assessment Practitioner (EAP), to manage the Basic Assessment process for the Zenex Blend Plant (ZBP) decommissioning environmental authorisation application to the KwaZulu-Natal Department of Economic development, Tourism & Environmental Affairs (EDTEA). In terms of the National Environmental Management Act (Act 107 of 1998, as amended) (NEMA) and the Environmental Impact Assessment (EIA) Regulations promulgated in Government Notice (GNR) 326 of 7 April 2017, a Basic Assessment (BA) process is required for the decommissioning and removal of facilities previously used for storing dangerous goods. Stakeholder engagement is a fundamental part of the BA process and aims to include potential Interested and Affected Parties (I&APs) in the process by notifying them of the proposed project. The objectives of the stakeholder engagement process are to: — Ensure an open and transparent BA and consultation process; — Enable stakeholders to register their interest and provide input into the BA process and share information; and — Ensure that all relevant issues are addressed as part of the BA process. The stakeholder engagement process is being undertaken in accordance with the EIA Regulations. The process aims to ensure that potential stakeholders are identified and provided with an opportunity to review the details of the proposed project and to submit any issues and concerns. 1.2 OBJECTIVE OF THE STAKEHOLDER ENGAGEMENT PROCESS The objectives of the stakeholder engagement process are as follows: — To ensure an open and transparent Impact Assessment and consultation process; — To identify and inform stakeholders of the proposed project and associated environmental authorisation process; — Provide an opportunity for stakeholders to raise all issues, concerns and questions and ensure that these are considered in the environmental authorisation process for the project; — Ensure that stakeholders have an opportunity to make a meaningful contribution towards decision making by the competent authority, and — Compile a Comment and Response Report (CRR) of all issues, concerns and questions raised during the stakeholder engagement process.
2 STAKEHOLDER NOTIFICATION 2.1 AUTHORITY CONSULTATION A pre-application meeting was held on 10 February 2021 with EDTEA in order to discuss the Department’s requirements for the application. An environmental authorisation application was submitted to EDTEA on 5 May 2021and acknowledged by EDTEA on the 6 May 2021 with the reference number: DM-0011-2021. Local and Provincial authorities were provided with written notification via email. The notified authorities include: — Department of Economic Development, Tourism and Environmental Affairs (EDTEA) — KZN EDTEA: Coastal Unit — Department of Water and Sanitation (DWS) — KZN Department of Agriculture & Rural Development — KZN Amafa — eThekwini Municipality — Transnet National Port Authority (TNPA) (landowner). 2.2 ADVERTISEMENT The EIA Regulations require that an advertisement be placed in a local newspaper or official gazette for a project of this nature. An advert was published in the Southlands Sun and the Mercury on 23 April 2021 (Appendix A). The advertisement formally announced the commencement of the application process and requested that I&APs register their interest with the EAP. 2.3 PUBLIC NOTICES The EIA Regulations require that site notices be fixed at places that are conspicuous to and accessible by the public at the boundary or on the fence or along the corridor of the site where the application will be undertaken or any alternative site. Four site notices were placed at the following locations on in May 2021 (Appendix B). — Grosvenor Library — Lighthouse Family Grocer - Lighthouse Road, Bluff — Entrance of ZBP Site — Entrance of Cutler Permit Office 2.4 WRITTEN NOTIFICATION Section 41 of the EIA Regulations states that written notices must be given to the stakeholders outlined in Table 1. Written notices (Annexure C) notifying stakeholders of the proposed development were distributed via email, and submitted by hand. Table 1: Interested and Affected Parties Notifications I&AP EAP COMMENT The occupiers of the site and, if the proponent or applicant is TNPA, who is the lessor and the landowner in control of the not the landowner or person in control of the site which the site was notified of the development via email. activity is to be undertaken, the owner or person in control of the site where the activity is or is to be undertaken and to any alternative site where the activity is to be undertaken; Owners, persons in control of, and occupiers of land adjacent The occupiers and owners of the adjacent land (Bidvest and to the site where the activity is or is to be undertaken and to Vopak) were notified of the application telephonically and any alternative site where the activity is to be undertaken; via email.
The municipal councillor of the ward in which the site and The Ward Councillors (Ward 32 and Ward 66) were notified alternative site is situated and any organisation of ratepayers of the application both telephonically and via email. that represent the community in the area; The municipality which has jurisdiction in the area; A notification was sent to the eThekwini Municipality via mail. Any organ of state have jurisdiction in respect of any aspect Notices were provided to the authorities listed in Section 2.1 of the activity; and via email. Any other party as required by the competent authority If found necessary, stakeholders will be added on request by EDTEA as the competent authority. 2.5 STAKEHOLDER DATABASE Engen maintains an existing stakeholder database which was accessed included in the stakeholder database (Appendix D). Other known stakeholders with a potential interest in the project were identified at the project outset. This included all relevant authorities (government departments and the eThekwini Municipality), and the surrounding community members / community representatives. Stakeholder database maintenance is ongoing. Those who registered with an interest in the project as a result of the notification process are included in the database. 2.6 DRAFT IMPACT ASSESSMENT REPORT DISCLOSURE The Draft BAR will be distributed for public review for a period of 30 days from Tuesday 22 June 2021 to Wednesday 21 July 2021. Hard copies and/or electronic copies of the report will be provided to the following relevant regulatory and local authorities for commenting: — EDTEA; — DWS; — KZNDARD; — KZN Amafa; — eThekwini Municipality; and — The Ward Councillor (Ward 32). Stakeholder will be notified of the availability of the Draft BAR for review Online on the WSP website: http://www.wspgroup.com/en/WSP-Africa/What-we-do/Services/All-Services-A-Z/Technical-Reports/ 2.7 FURTHER STAKEHOLDER ENGAGEMENT The below stakeholders have requested a site walkover at ZBP. WSP is in communication with Engen with regards to this request. Should necessary approvals be granted for the site walkover, this will take place during the 30 days stakeholder review period (Tuesday 22 June 2021 to Wednesday 21 July 2021): — South Durban Community Environmental Alliance (SDCEA), and — Community Development South Africa (COMDEV). A comment and response report will be captured in the Final BAR, which will outline the comments received from the stakeholders and responses provided by the applicant and EAP for consideration by EDTEA.
APPENDIX A ADVERTS
Figure 1 Proof of Placements of Advert in the Southlands Sun
Figure 2 Proof of Placements of Advert in the Mercury
APPENDIX B POSTERS
Figure 3 Proof of poster placement at Grosvenor Library Figure 4 Proof of poster placement at Grosvenor Library Figure 5 Proof of poster placement at Family Grocery – Lighthouse Road, Bluff Figure 6 Proof of poster placement at ZBP Site Entrance
Figure 7 Proof of poster placement at the Cutler Permit Figure 8 Proof of poster placement at the Cutler Permit Office Office
APPENDIX C WRITTEN NOTIFICATIONS
Figure 9 Formal Letter for Written Notification
Figure 10 Proof of Witten Notification distributed via email
APPENDIX D STAKEHOLDER DATABASE
CATEGORY ORGANISATION SURNAME NAME Provincial Authorities KZN EDTEA: Coastal Unit Parak Omar KZN EDTEA: HOD Myeza Sibusiso EDTEA: eThekwini District EIA Component Brijlal Natasha DWS Ntombi Madibe-Mngoma Local Authorities eThekwini Municipality: EIA Bathabile Msomi NGO's, CBO's & Associations WESSA Sarah Alcock Amafa Pawandiwa Bernadet South Durban ABM Singh Eurakha South Durban ABM Masombuka Fanele South Durban ABM Govender Anitha South Durban Community Environmental Alliance Samson Shanusha (SDCEA) GroundWork Euripidou Rico GroundWork Peek Bobby GroundWork Admin Coastwatch Schwegman C Neighbouring Land User Bidvest Terminals (Neighbouring land user) Priya Govender Vopak Mariam Haffejee ENGEN Stakeholders Community Member Resident Sarupdeo Pradeep Community Member Resident Palmer Beulah Community Member Resident Bonhomme Lee Community Member SDCEA D'sa Desmond Community Member ECSF Sayed Sammy Community Member ECSF Roskrige Sr Community Member ECSF Dandala Sindy Community Member ECSF Kistan Gopal Ps. Community Member ECSF Visagie Chris Ps. Community Member ECSF Ndlovu Mthokozisi Community Member ECSF Gomes Jennifer Community Member ECSF Usher Jeannette Esmeen Community Member ECSF Choudree Jean Community Member ECSF Van de Byl Isadora Community Member ECSF Visagie Elaine Community Member ECSF Steenan Bradley
Community Member ECSF Chinsamy Bobby Ganas Community Member ECSF Bhengu Bajabulile Community Member ECSF Newall Annette Community Member Merebank Community Trust Reddy Strini Community Member Merebank Community Trust Selvie Community Member Merebank Community Trust Naicker Daya Community Member Merebank Community Trust Coomar Raj Community Member Merebank Community Trust Essop Shahnaaz Community Member Merebank Community Trust Khalawan Shano Community Member Merebank Community Trust Ramdheen Roshan EThekwini Municipality Prinsloo JP EThekwini Municipality Snyman Aubrey ECSF Usher David ECSF Smith Victor Ganges Seconadry Reddy Deena Aplipore Primary Folkard Mr. St Mary's ML Sultan Primary Ramdheen Mr. Merebank Secondary Banprakash Timothy SAPS (Wentworth Police Station) Raddy Ballan EThekwini Municipality South Durban Basin ABM Singh Eurakha Parsee Rumtomjee Singh Mrs. Settlers Primary Lawrence Mr Settlers Primary Junagarth Primary Chetty Dr. PR Parther High Satyendra Mrs. Ocean View School Mkhize Mr. Nizam Road Primary Basdeo Mr. Fairvale Secondary (Wentworth Education Trust) Seidle Dale Wentworth Secondary (Wentworth Education Trust) Lamellate Faye Umbilo Secondary (Wentworth Education Trust) Muller Brain Wentworth Primary (Wentworth Education Trust) Small Hilda Austerville Primary (Wentworth Education Trust) Singh Mr Durban East Primary (Wentworth Education Trust) Timm Charlotte Gardenia Primary (Wentworth Education Trust) Oliver John Assegai Primary (Wentworth Education Trust) Abrahams-Field Odette Collingwood Primary (Wentworth Education Trust) Chand Colin Mondi Mbokazi Leonard SAPREF Myeza Londiwe SAPREF Khuzwayo Lindiwe SASDC Van Wyk Mark
Mangosuthu University of Technology Pillay Sandra Pump & Pipes Holdings Derek Ogle Ward Councillors Ward 66 - Bluff and Wentworth Zoe Moore Ward 32 - Clairwood and Bayhead Protus Mngonyama Landowner Transnet NPA Durban Cindi Cande Registered stakeholders Ex Bluff Ward Environmental & Coastal Conservation / Louise Colvin Resident of the Bluff and member if Cutler Forum Bluff Resident Logan Moodley Pump and Pipes Holdings (Pty) Ltd Derek Ogle Community Development South Africa (COMDEV) John Stuart