Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options

Page created by Milton Lane
 
CONTINUE READING
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme

Environmental Assessment of Viable Options

November 2011

MGE0262/1.3/CR0009

                                             rpsgroup.com/ireland
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

                                           TABLE OF CONTENTS

1        INTRODUCTION ........................................................................................................................ 1
2        SYNOPSIS OF ENVIRONMENTAL CONSTRAINTS STUDY .................................................. 2
3        PROPOSED FLOOD ALLEVIATION MEASURES ................................................................... 5
4        IMPACT ASSESSMENT ............................................................................................................ 9
         4.1        DO-NOTHING ................................................................................................................... 9
         4.2        PREFFERED SCHEME MEASURES .................................................................................... 10
                    4.2.1       Lough Corrib to Curraghmore Bridge ............................................................. 10
                    4.2.2       Montiagh South .............................................................................................. 11
                    4.2.3       Montiagh North ............................................................................................... 13
                    4.2.4       Claregalway Village ........................................................................................ 15
                    4.2.5       Kiniska ............................................................................................................ 19
                    4.2.6       Lakeview ......................................................................................................... 21
                    4.2.7       Caherlea/Lisheenavalla .................................................................................. 23
                    4.2.8       Carnmore/Cashla ........................................................................................... 30
                    4.2.9       Footbridge ...................................................................................................... 32
         4.3        CUMULATIVE IMPACTS.................................................................................................... 34
5        CONCLUSIONS ....................................................................................................................... 36
                    5.1.1       Socio-Economic.............................................................................................. 36
                    5.1.2       Archaeological, Architectural and Cultural Heritage....................................... 36
                    5.1.3       Terrestrial Ecology ......................................................................................... 36
                    5.1.4       Aquatic Ecology .............................................................................................. 37
                    5.1.5       Soils, Geology and Hydrogeology .................................................................. 37
6        REFERENCES ......................................................................................................................... 38

                                                 LIST OF FIGURES

Figure 3.1      Locations of Proposed Measures

Figure 3.2       Preliminary design for proposed footbridge at Claregalway

                                                  LIST OF TABLES

Table 2.1       Environmental Constraints identified during Stage 1 of the Study .................................... 2

MGE0260RP0005                                                           i                                                                   Rev. F01
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

1 INTRODUCTION

In May 2011 the Office of Public Works (the OPW) appointed RPS as environmental consultants for
the Clare River (Claregalway) Flood Relief Scheme. The Clare River and main tributaries form part of
the Corrib Clare Arterial Drainage Scheme, which was constructed in the late 1950’s and early 1960’s,
for which the OPW have a statutory maintenance responsibility. These original Arterial Drainage
Scheme works involved substantial widening and deepening of the existing channel and tributaries
with the purpose of providing outfall for the drainage of agricultural lands.

In March 2010 the OPW commissioned Ryan Hanley Consulting Engineers to undertake two studies.
The first related to the Clare River and its main tributary, the Abbert River, within a study area from
Corofin to Lough Corrib. The study was commissioned as a result of severe damage and disruption
caused by flooding in the area in November 2009. The second study related to the townlands of
Carnmore East and Cashla on the R339 Galway to Monivea Regional Road, which was also affected
by flooding in November 2009. These studies should be read together, and are referred to as the
Engineering Studies for the remainder of this report.

The OPW are now progressing the Flood Relief Scheme to design stage and the required
environmental outputs associated with the Scheme are set out in three distinct stages as follows:

     Stage 1
    - Environmental Constraints Study
    - Public Consultation

     Stage 2
    - Environmental Assessment of Viable Options
    - Screening for Appropriate Assessment

     Stage 3
    - Environmental Impact Statement (EIS)
    - Appropriate Assessment (if deemed necessary as a result of the Appropriate Assessment
        Screening).
    - Public Consultation

Stage 1 Environmental Constraints Study and Public Consultation were completed in early June. This
report fulfils one required element of Stage 2 – to complete an Environmental Assessment of Viable
Options for the proposed Flood Relief Scheme.

The Environmental Assessment of Viable Options is tasked with reviewing the assessment of the
environmental effects of the flood alleviation options that have been identified in the Engineering
Studies, and suggest mitigation measures, where feasible (as per Tender documents, December
2010). This review will inform the Design Team in refining or changing the preferred scheme option.
This assessment also includes the environmental effects of the proposed footbridge.

MGE0260RP0005                                          1                                       Rev. F01
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

2 SYNOPSIS OF ENVIRONMENTAL CONSTRAINTS STUDY

The purpose of completing the Environmental Constraints Study was to identify where constraints may
impact upon specific proposed flood relief measures and in so doing inform both the stakeholder
consultation and design process for the scheme from an environmental view point. This report should
be read in conjunction with the Environmental Constraints Study.

The Study identified a number of significant environmental constraints as follows (*refers to figure and
table numbers from the Environmental constraints Study Report):

Table 2.1     Environmental Constraints identified during Stage 1 of the Study

  CATEGORY                 SUB                    SOURCE                 CONSTRAINTS                 MAP/TABLE
                        CATEGORY                                                                    REFERENCE*

Socio                Land Use &             Galway County          •   Existing land uses           Figure 2.1
Economic             Communities            Development Plan       •   Fisheries                    Table 2.3
                                            2009 – 2015            •   Clare River Walkway
                                            Stakeholder                Project
                                            constraints

                                            Angler’s Guide to
                                            Game Fishing in
                                            the Western
                                            Fisheries Region
                     Material assets                               •   Existing road network –      Figure 2.1
                                                                       impact on commuters          Figure 2.14
                                                                   •   Energy infrastructure –
                                                                       overhead &                   Table 2.12
                                                                       underground network
                                                                       e.g. ESB lines, Bord
                                                                       Gáis supply
                                                                   •   Water mains and
                                                                       private wells
                                                                   •   Proposed new WWTP
                                                                       at Claregalway
                                                                   •   Local authority licensed
                                                                       discharges to the Clare
                                                                       River
                     Landownership                                 •   Liaison     with     local
                     and access                                        landowners in relation
                                                                       to works proposed
                                                                   •   Storage or disposal of
                                                                       excavated materials
Archaeology &                               Legislative            •   Three Protected              Figure 2.2
Cultural                                    Constraints                Structures
Heritage                                                           •   Two NIAH structures
                                                                                                    Tables 2.4.1 &
                                            Galway County          •   19 Archaeological            2.4.2
                                            Development Plan           Heritage sites (including
                                            2009 – 2015                52 separate RMP
                                                                       listings and a national
                                                                       monument)
                                            Assessment by          •   Three Areas of
                                            Irish Archaeological       Archaeological Potential
                                            Consultancy

MGE0260RP0005                                             2                                            Rev. F01
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

  CATEGORY                 SUB                    SOURCE                 CONSTRAINTS                  MAP/TABLE
                        CATEGORY                                                                     REFERENCE*

Landscape &                                 Galway County             2 protected focal points      Figures 2.4
Visual                                      Development Plan           & views
                                            2009 – 2015
Ecology                                     Legislative            •   Compliance with the           Figure 2.6
                                            Constraints                Habitats and Birds
                                                                       Directives and National
                                                                                                     Tables 2.5 - 2.7
                                                                       legislation
                                            Stakeholder
                                                                   •   Designated habitats and
                                            constraints
                                                                       species Protected Flora
                                                                       and Fauna
                                            NPWS databases         •   Fisheries – salmonids,
                                                                       lamprey
                                            Published literature      Local Ecological
                                                                       Important Areas
Hydrology &                                 Stakeholder               Important fisheries           Figure 2.8
Water Quality                               Constraints                zones
                                                                      Compliance with the
                                                                                                     Table 2.2
                                                                       Water Framework
                                            Legislative                Directive
                                            constraints

                                            Western     River
                                            Basin Management
                                            Plan

Soils/Geology/                                                        Aquifer vulnerability         Figures 2.11 -
Hydrogeology                                                          Surface     water     and     2.13
                                                                       groundwater interaction       Tables 2.9 –
                                                                                                     2.12
Other                Waste                                         Requirement to handle,
Constraints          Management                                    store, remove and dispose
                                                                   of    waste      material    in
                                                                   accordance with relevant
                                                                   waste            management
                                                                   legislation
                     Traffic                                       - Crusheeny Bridge                Figure 2.14
                                                                       measures will lead to
                                                                       traffic diversions
                                                                   - Local roads in Montiagh
                                                                       North and Montiagh
                                                                       South townlands –
                                                                       Raising sections of
                                                                       access roads and
                                                                       increasing the size of a
                                                                       culvert in Montiagh
                                                                       South will cause traffic
                                                                       delays and possible
                                                                       diversions
                                                                   - Construction of the
                                                                       footbridge at
                                                                       Claregalway will cause
                                                                       traffic delays and
                                                                       disruption
                     Noise                                          Galway County Council           Figure 2.15
                                                                        Draft Action Noise Plan

MGE0260RP0005                                             3                                             Rev. F01
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

  CATEGORY                 SUB                    SOURCE         CONSTRAINTS                  MAP/TABLE
                        CATEGORY                                                             REFERENCE*

                                                               2008
                                                              Noise generated by the
                                                               timing        of     works
                                                               associated with the
                                                               implementation          of
                                                               alleviation      measures
                                                               may         impact      on
                                                               residential, commuting
                                                               and visitors to the study
                                                               area.
                     Air                                      Key       Indicators     of   Figure 2.16
                                                               Ambient Air Quality in
                                                               Ireland
                                                              Works associated with
                                                               implementation of flood
                                                               alleviation      measures
                                                               and      the     machinery
                                                               involved may generate
                                                               emissions and dust e.g.
                                                               bridge works, storage
                                                               and removal of waste
                                                               material etc.

MGE0260RP0005                                          4                                        Rev. F01
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

3 PROPOSED FLOOD ALLEVIATION MEASURES

The appointed design team have reviewed/altered/refined the proposed flood alleviation measures for
the Scheme. This has resulted following a review of the Engineering Reports (June and August 2010),
a review of the Environmental Constraints Report, June 2011 and analysis of comments received
during the public information evening held in Claregalway on the 8th of June 2011. In addition,
unsteady state modelling was undertaken, the purpose of which was to refine the measures proposed
by the Engineering Reports if deemed necessary.

Table 3.1 sets out the preferred flood relief scheme, and Figure 3.1 illustrates their locations.

Table 3.1 Summary of the Preferred Scheme

Summary      of  Potential       Proposed Measures                         Comments
Flood Relief Measures

1   Lough    Corrib    to             No measures proposed
    Curraghmore Bridge

2   Miontach South               2a   Raise approx. 1km of road, to a      Images 3.1 and 3.2 below show the
                                      minimum level of 8.60m OD.           road section proposed to be raised
                                 2b   Upsize existing road culvert in      and the existing culvert to be upsized.
                                      conjunction with road works
                                 2c   Clean Drains in existing vicinity
3   Miontach North               3a   Raise approx. 0. 460 km of road to   Images 3.3 and 3.4 below show the
                                 3b   a minimum of 9.0m OD.                road sections proposed to be raised.
                                      Raise approx. 0. 785 km of road to
                                      a minimum of 9.0m OD.
4   Claregalway Village          4b   Regrade Clare River channel          Images 3.5 and 3.6 show the location
                                      upstream of and under the            of the Nine Arches bridge and Clare
                                      Claregalway bridge                   River downstream of Claregalway
                                 4c   Fill gap in wall at An Mhainistir    bridge.
                                      housing estate
                                 4d   Provide local embankment at old
                                      Nine Arches bridge
5   Kiniska                      5a   Increase capacity of culverts on
                                      OPW C3/5 stream
                                 5b   Clean OPW stream C3/5

6   Lakeview                     6a   Provide surface water outlet         It was agreed that the outlet from the
                                      through fields and along N17 to      surface water drain from Lakeview
                                      upstream of Claregalway Bridge       would discharge to the Clare River
                                                                           upstream of the Claregalway bridge
                                                                           rather than downstream of the bridge
                                                                           as originally proposed.

                                                                           Images 3.7 and 3.8 illustrates the
                                                                           proposed route from the corporate
                                                                           park through Cúirt na hAbhainn
                                                                           Estate.
7   Gortatleva                        No additional measures proposed
                                      (Measures for Area 4 apply)

8   Caherlea/Lisheenavalla       8a   Replace Crusheeny Bridge             A Bridge Options Report was
                                 8b   Channel widening from 0.9km          prepared      by    RPS       which
                                      upstream of Crusheeny Bridge to      recommended the provision of a three
                                      Claregalway                          span bridge to minimise the in-river
                                 8c   Cleaning      and regrading  of      works. A Preliminary Report is
                                      Islandmore OPW C3/7 and F.799/1      currently being prepared to obtain
                                      arterial drains                      NRA approval. The bridge demolition

MGE0260RP0005                                           5                                                Rev. F01
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

                                 8d   Raise      local      road      in   and replacement is to be undertaken
                                      Caherlea/Lisheenavalla     (future   as advance works to ensure that the
                                      measure)                             works are progressed as soon as
                                                                           possible.

                                                                           Crusheeny Bridge Cross-Section
                                                                                                      Width
                                                                                                      (m)
                                                                            Parapet beam              0.5
                                                                            Raised verge / verge          1.0
                                                                            Hardshoulder / Hard Strip     -
                                                                            Carriageway                   2.75
                                                                            Central Reserve               -
                                                                            Carriageway                   2.75
                                                                            Hardshoulder / Hard Strip     -
                                                                            Raised verge / verge          1.5
                                                                            Parapet beam                  0.5
                                                                            Total Width                   9.0

                                                                           The channel widening works will result
                                                                           in a large amount of material being
                                                                           excavated. The majority of the
                                                                           excavation works are on the southern
                                                                           bank of the river, with some
                                                                           excavation on the northern bank in the
                                                                           vicinity and upstream of Crusheeny
                                                                           bridge. It is proposed that this material
                                                                           will generally be spread adjacent to
                                                                           the river as much as possible. The
                                                                           approximate quantities of materials to
                                                                                                            3
                                                                           be excavated is 305,000 m . This
                                                                           does not include the existing spoil
                                                                           heaps adjacent to the river which will
                                                                           also need to be removed in areas
                                                                           where channel widening works are
                                                                           proposed. The total volume is
                                                                           currently being quantified.

                                                                           Images 3.9 and 3.10 illustrate the
                                                                           existing bridge at Crusheeny and the
                                                                           view downstream from the bridge of
                                                                           the Clare River.
9   Carnmore/Cashla                   Drainage of floodwater from the
                                      affected area via a new drainage
                                      pipeline/open drain to a local
                                      surface water stream at Islandmore

In addition, a Footbridge is proposed for Claregalway, to be constructed alongside the Claregalway
Bridge. This Footbridge, is also assessed as part of this report. Figure 3.2 illustrates a preliminary
design for the footbridge.

Images 3.1 to 3.12 illustrate the locations of the various measures proposed.

MGE0260RP0005                                           6                                                  Rev. F01
Clare River (Claregalway) Flood Relief Scheme - Environmental Assessment of Viable Options
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Image 3.1 Road to be Raised                                Image 3.2 Existing culvert to be upsized

Image 3.3 Road to be Raised at Miontach                    Image 3.4 Road to be Raised at Miontach
North                                                      North

Image 3.5 Nine Arches Bridge                               Image 3.6 Clare      River   Downstream     of
                                                           Claregalway Bridge

Image 3.7 Cúirt na hAbhainn Estate                         Image 3.8 Claregalway Corporate Park

MGE0260RP0005                                          7                                          Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Image 3.9 Crusheeny Bridge                                 Image 3.10 Clare    River   Downstream   of
                                                           Crusheeny Bridge

Image 3.11 Proposed Start of Surface Water                 Image 3.12 Proposed Route of Surface Water
Drain                                                      Drain

MGE0260RP0005                                          8                                      Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

4 IMPACT ASSESSMENT

This section consists of an environmental assessment of each of the preferred flood relief measures.
Impacts have been described in accordance with the Glossary of Impacts set out in “Guidelines on the
Information to be contained in Environmental Impact Statements” (EPA 2002). Where relevant,
mitigation measures and/or environmental enhancement measures are proposed.

It should be noted that the assessment below and the potential mitigation measures set out may be
subject to refinement during the EIA process, which requires more in depth desktop analysis and an in
depth review of field inspections. Additional mitigation measures at EIA stage may be recommended
e.g. geophysical surveys and archaeological testing.

4.1    DO-NOTHING

In the absence of the flood relief measures proposed, impacts of periodic flooding are likely to
continue. Flooding in Claregalway town and in the Clare catchment above Claregalway Bridge is
caused exclusively by river floods, the characteristics of the river channel and their effect on the
discharge of high runoff volumes from the river catchment through Claregalway Bridge (Ryan Hanley,
2010). The flooding of the Clare River which followed the extreme rainfall in November 2009 caused
severe and prolonged hardship to businesses, to residents within the Clare catchment and to
commuters using the N17 and other minor roads in the vicinity. Flooding has also been recorded on
other occasions including the winter of 1990, December 1999, January 2005, and December 2006.

The worst affected areas from the November 2009 flood within the study area were:

•     Miontach townland downstream of Claregalway Bridge. One house was flooded, and a
      neighbouring house came close to flooding. Miontach townland was totally isolated by flooding;

•     Claregalway village, where access to the N17, housing estates (An Mhainister) and commercial
      properties (e.g. Arches Hotel) was hampered;

•     Kinishka townland – access road flooded but remained passable;

•     Lakeview – Cuirt na hAbhainn housing estate road flooded and houses almost flooded. Minor
      flooding in front of the park. Lakeview housing estate roads were at risk of flooding;

•     Gortatleva – land was flooded and one home flooded;

•     Caherlea/Lisheenavalla townlands where sixteen houses were completely flooded or were at risk
      of flooding. Local road access was hampered by raised water levels in turlough area;

•     Carnmore/Cashla – three houses were flooded, and seven houses and two business premises
      were at risk of flooding. Many houses were cut off by the flooding of local roads and the Regional
      Road R339. Land was also flooded.

Modelling undertaken by Ryan Hanley (2010) indicated that, serious flooding at Claregalway and in
the Crusheeny area with potential flood levels of 11.31m OD upstream of Claregalway Bridge and
13.93m OD at Caherlea/Lisheenavalla under potential future climate change conditions, would occur
under the ‘do-nothing scenario’.

MGE0260RP0005                                          9                                        Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Such events are likely to continue to exert disruption and hardship within the study area in the
absence of the flood relief scheme.

4.2     PREFFERED SCHEME MEASURES

4.2.1    Lough Corrib to Curraghmore Bridge

There are no works planned from Lough Corrib to Curraghmore Bridge. This part of the study area
suffers from flooding relating to lake levels in Lough Corrib, and the main impact of this flooding is on
agricultural land and bog. No property or property access was affected in this area in November 2009.
The N84 Headford road is raised above flood levels.

However the following is noted in terms of archaeology:
   - This area is characterised by the presence of an Area of Archaeological Potential (AAP)
      associated with the riverine environment around the Clare River (AAP1) and the surrounding
      bog land below Claregalway village is also an AAP (AAP2) (for the location of AAP1 and
      AAP2 –refer to Figure 2.2 of the Environmental Constraints Study).
   - Curraghmore Bridge is of modern construction and is of no architectural heritage merit.

MGE0260RP0005                                          10                                        Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

4.2.2    Montiagh South

Potential Impacts                                      Quality    Duration     Type                         Significance          Suggested Mitigation
                                                                                                                                  Measures/Environmental Enhancements
Terrestrial ecology
Local habitat disturbance at culvert and drain site    Negative   Short term   Reversible.           The    Slight                None required
(habitats comprise Improved Agricultural Grassland                             habitats at this location
GA1 and species-poor Wet Grassland GS4)                                        will    most        likely
                                                                               recolonise      naturally
                                                                               and return to their
                                                                               previous form.
Socio-economic
Disruption to local road users and services            Negative   Short term   Cumulative                   Significant           • Provide prior warning of road closure to
                                                                                                                                    road users.
                                                                                                                                  • Provide local diversion during works.
Aquatic ecology
2a: Raised road construction over and in proximity     Negative   Short term   Construction phase +         Slight local          A detailed design and method statement
to drain at M35606, 33525 has the potential to                                 Cumulative (inputs of        impacts due to        should be drawn up by the contractor indicating
contribute sediment and silt, with a risk of cement                            silt to Clare River) in      low value of          what measures will be taken to avoid, (a)
and hydrocarbon spills (diesel, hydraulic fluid) to                            association with other       drain habitat.        sediment or soil loss and; (b) hydrocarbon
the watercourse. There are many smaller drains                                 measures.                    Sluggish nature       contamination, associated with all aspects of
adjacent and perpendicular to both sides of the                                                             of drain means        the road construction phase, and how these will
existing road in this area, and whilst they have low                                                        that silt is likely   be monitored for effectiveness.
habitat value, they are conduits to the larger drain                                                        to settle within
and on into the Clare River, downstream, where                                                              the drain rather
there could be impacts on fisheries values there.                                                           than discharge
                                                                                                            immediately to
                                                                                                            the Clare
                                                                                                            .Works are
                                                                                                            outside the
                                                                                                            cSAC.

2b: Culvert replacement - method for replacement       Negative   Short term   Construction phase +         Slight local          As for 2a.
is undefined – potential to contribute sediment and                            Cumulative (inputs of        impacts due to
silt, with a risk of cement and hydrocarbon spills                             silt to Clare River) in      low value of
(diesel, hydraulic fluid) to the watercourse. As for                           association with other       drain habitat.
2a. Localised habitat disturbance.                                             measures.                    As for 2a.
                                                                                                            Works are

MGE0260RP0005                                           11                                              Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                          Quality    Duration     Type                      Significance       Suggested Mitigation
                                                                                                                                Measures/Environmental Enhancements
                                                                                                             outside the
                                                                                                             cSAC.
2c: Drainage operations - physical habitat disturbance     Negative   Short term   Construction phase        Moderate, local,   There is a huge amount of low value drain
and/or loss over a significant linear length of                                                              impacts, with      habitat in this vicinity, so cleaning of those
watercourse. There were a number of different                                                                slight impact      highlighted, whilst causing localised habitat
habitat types within the drains earmarked for cleaning,                                                      overall. Works     loss, will have negligible impact overall and will
most have only low value of local importance. The                                                            are mostly         not affect the integrity of this habitat type within
more easterly of the Montiagh South drains                                                                   outside the        the cSAC.
earmarked for cleaning, is a broad deep channel                                                              cSAC.
(probably a tributary), which nevertheless has no                                                                               All drainage operations should be carried out in
suitable salmonid habitat and is unlikely to be                                                                                 accordance     with    OPW’s     Environmental
important for lamprey ammocoetes given the                                                                                      Management       Protocols    and     Standard
absence of suitable spawning areas. The habitat                                                                                 Operating Procedures (SOP) (Appendix A)
however would be suitable for coarse fish such as                                                                               All drainage operations should be carried out in
roach, other cyprinids and perhaps small pike. The                                                                              close consultation with Inland Fisheries Ireland.
other drains in the Montiagh South area, centred
on M33918 33078 have no obvious fisheries value,                                                                                Cleaning of these channels should be delayed
although non-protected species such as 3-spined                                                                                 until late summer when all amphibians have
stickleback may be present.                                                                                                     adopted more terrestrial behaviour.

A high abundance of newt tadpoles in the more                                                                                   Both newts and frogs are protected under the
westerly drainage network at M 34194 32996. There                                                                               Wildlife Acts (1976 and 2000).
were also small frogs observed on land around the                                                                               Any disturbance to a newt breeding site would
drains. The area is clearly important for amphibians.                                                                           require a licence from NPWS and potentially a
                                                                                                                                compensation plan would need to be proposed
                                                                                                                                if the site was to be lost. Further investigation
                                                                                                                                of the drains in that area may be necessary to
                                                                                                                                see how much residual habitat will remain after
                                                                                                                                the proposed drainage.
2c: Drainage operations – mobilisation of silt during      Negative   Short term   Construction phase +      Moderate local     All drainage operations should be carried out in
in-channel works which may have impacts on                                         Cumulative (inputs of     impacts, with a    accordance      with    OPW’s     Environmental
fisheries values of the Clare River to which all drains                            silt to Clare River) in   possibility of     Management        Protocols    and     Standard
in this area are a conduit. The sluggish nature of                                 association with other    slight impacts     Operating Procedures (SOP) (Appendix A)
the drains in this vicinity means that silt is likely to                           measures.                 within the Clare
settle within them, but may become mobilised                                                                 River. Works       All drainage operations should be carried out in
during events.                                                                                               are mostly         close consultation with Inland Fisheries Ireland.
                                                                                                             outside the
None of these drains has recognisable salmonids                                                              cSAC.              Carry out works in a downstream direction so
fisheries habitat and are also unlikely to contain                                                                              that in-situ vegetation can act as a buffer to the
lamprey ammocoetes due to absence of suitable                                                                                   mobilisation of silt downstream to the Clare
spawning areas nearby. Non protected species                                                                                    River.

MGE0260RP0005                                               12                                           Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                      Quality    Duration     Type                       Significance     Suggested Mitigation
                                                                                                                           Measures/Environmental Enhancements
such as 3-spined stickleback may be present.
                                                                                                                           Undertake this measure in different sequence
There are no known spawning areas in the lower                                                                             to other measures to limit cumulative impacts.
section of the Clare, so low levels of silt that                                                                           Both the OPW and the Engineering Report
escape to the main channel would not impact                                                                                indicate that the Clare has a flow regime that
salmon redds.                                                                                                              does not favour excessive silt deposition and
                                                                                                                           limited intermittent inputs should have
                                                                                                                           negligible impact on the river, overall. Works
                                                                                                                           should be timed to occur in predicted low
                                                                                                                           rainfall period.
Archaeology and cultural heritage
The proposed road raising and upsizing the             Negative   Permanent    Irreversible               Significant      It is recommended that ground disturbances
existing road culvert may have an adverse impact                                                                           associated with the proposed works be
on archaeological features or deposits that have                                                                           monitored by a suitably qualified archaeologist.
the potential to be located beneath the current                                                                            Full provision should be made for the resolution
ground level within Area of Archaeological Potential                                                                       of any archaeological features or deposits that
2 (bogland). This would be caused by excavation                                                                            are discovered, should that be deemed the
required as part of the proposed scheme.                                                                                   most appropriate way to proceed.
No adverse impact is anticipated on AH 1
(children’s burial ground), as it is located 260m SW
of the proposed road works.
Soil, geology and hydrogeology
Imperceptible impact on soils and geology due to       Negative   Permanent    Residual                   Imperceptible    Any excavated soils/rock should be reused in
the disturbance and loss of soils and rocks during                                                                         the scheme or disposed in an appropriate local
works.                                                                                                                     waste facility.

4.2.3    Montiagh North

Potential Impacts                                      Quality    Duration     Type                         Significance     Mitigation         Measures/Environmental
                                                                                                                             Enhancements
Terrestrial ecology
3a: Localised disturbance of Cutover bog habitats      Negative   Short Term   Reversible (the habitats     3a: Moderate     3a: Works should be minimised on the northern
on either side of the road. These habitats are                                 should naturally recover                      side of the road at this location, in order to
considered to be of Local Importance (Higher                                   post-construction)           3b: Slight       avoid the areas of species-rich marsh and
Value).                                                                                                                      cutover bog. Works here should be supervised
                                                                                                                             by an ecologist.
3b: Localised disturbance of Wet Grassland and

MGE0260RP0005                                            13                                         Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                        Quality    Duration     Type                       Significance          Mitigation          Measures/Environmental
                                                                                                                                  Enhancements
Marsh habitats on either side of the road. These                                                                                  3b: No mitigation required.
habitats are of Local Importance (Lower Value).
Socio-economic
Disruption to local road users and services              Negative   Short term   Cumulative                 Significant           • Provide prior warning of road closure to
                                                                                                                                    road users.
                                                                                                                                  • Provide local diversion during works.
Aquatic ecology
3a: - Raised road construction at, and near, the         Negative   Short term   Construction phase +       Significant local     The tributary upstream of the road has been
tributary running from Gortadooey, has the                                       Cumulative (inputs of      impact due to         recently maintained (20/7/11) and there is an
potential to contribute sediment and silt, with a risk                           silt to Clare River) in    fisheries             agreement between IFI and OPW about the
of cement and hydrocarbon spills (diesel,                                        association with other     values. Works         section downstream of the road where
hydraulic fluid) to the watercourse, which could                                 measures.                  are outside the       spawning gravels are present, however, a
impact on fisheries values identified in the lower                                                          cSAC.                 detailed design and method statement
section of stream. Silt can smother spawning                                                                                      should be drawn up by the contractor
gravels and benthic fauna upon which fish feed. It                                                                                indicating what measures will be taken to
can also abrade and clog fish gills, affecting                                                                                    avoid, (a) sediment or soil loss and; (b)
respiration.                                                                                                                      hydrocarbon contamination, associated with
                                                                                                                                  all aspects of the road construction phase,
There are indications from observations of this                                                                                   and how these will be monitored for
stream between the road bridge and the Clare                                                                                      effectiveness.           A     pre-construction
River confluence of a varied habitat including                                                                                    electrofishing survey is also recommended in
short riffles and shallow glides, and trout and                                                                                   order to assess the current status with regard
possibly brook lamprey spawn within the stream.                                                                                   to salmonids (probably only trout) and
This part of the stream is not earmarked for                                                                                      lamprey ammocoetes (probably only Brook
cleaning but would still be susceptible to siltation                                                                              lamprey) in the Gortadooey Stream.
from road raising and culvert replacement, which
could degrade the habitat.
3b: Raised road construction at, and near, a large       Negative   Short term   Construction phase +       Slight – due to       A detailed design and method statement
(4m) sluggish drain at M36155 34276 has the                                      Cumulative (inputs of      low gradient          should be drawn up by the contractor
potential to contribute sediment and silt, with a risk                           silt to Clare River) in    and flow in           indicating what measures will be taken to
of cement and hydrocarbon spills (diesel,                                        association with other     drain, where silt     avoid, (a) sediment or soil loss and; (b)
hydraulic fluid) to the watercourse. There are                                   measures.                  is likely to settle   hydrocarbon contamination, associated with
many drains along both sides of the existing road                                                           before reaching       all aspects of the road construction phase,
in this area, and whilst they have low habitat                                                              the Clare.            and how these will be monitored for
value, they are all conduits to the Clare River and                                                         Works are             effectiveness.
could have impacts on fisheries values there.                                                               outside the
                                                                                                            cSAC.
Archaeology and cultural heritage
The proposed road raising may have an adverse            Negative   Permanent    Irreversible               Significant           It is recommended that any ground
impact on archaeological features or deposits that                                                                                disturbances associated with the proposed

MGE0260RP0005                                              14                                          Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                      Quality    Duration      Type              Significance     Mitigation         Measures/Environmental
                                                                                                                   Enhancements
have the potential to be located beneath the                                                                       works that require the excavation of virgin
current ground level within Area of Archaeological                                                                 ground, be monitored by a suitably qualified
Potential 2 (bogland). This would be caused by                                                                     archaeologist. Full provision should be made
any excavation required as part of the proposed                                                                    for the resolution of any archaeological
scheme.                                                                                                            features or deposits that are discovered,
                                                                                                                   should that be deemed the most appropriate
                                                                                                                   way to proceed.
Soils, geology and hydrogeology
Imperceptible impact on soils and geology due to       Negative   Permanent     Residual          Imperceptible    Any excavated soils/rock should be reused in
the disturbance and loss of soils and rocks during                                                                 the scheme or disposed in an appropriate
works.                                                                                                             local waste facility.

4.2.4    Claregalway Village

Potential Impacts                                      Quality     Duration     Type                Significance     Mitigation  Measures/Environmental
                                                                                                                     Enhancements
Socio-economic
Disruption to local land users and anglers             Negative    Short term   Cumulative          Significant      • Provide prior warning of disruption to
                                                                                                                       land owners and angling clubs.
Potential for disruption to power supply. The          Negative    Short term   Residual            Slight           • Liaison with ESB is required prior to
110kv line to the west of Claregalway crosses the                                                                      any works being undertaken
Clare River approximately 0.3km west of the                                                                          • Prior notice to those supplied by this
Friary. A 38kv line roughly follows the route of the                                                                   linke required
main N17 road from north to south and crosses
the Clare River approximately 0.8km east of the
castle located in Claregalway village.          The
medium voltage 10KV ESB line follows the N17
primary road and crosses the Clare River in
Claregalway village.
Disruption to utilities: The village of Claregalway,   Negative    Short term   Residual            Slight           •   Liaise with Bord Gais regarding
and Lakeview townland, are also supplied with                                                                            potential disruption and provide prior
natural gas by An Bord Gais. The distribution                                                                            warning to facilitate works.
network follows the N18 from Carnmore Cross
Roads and turns right at the N18/N17 junction in
Claregalway to supply Claregalway village.

MGE0260RP0005                                            15                                  Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                      Quality          Duration     Type                        Significance       Mitigation  Measures/Environmental
                                                                                                                                    Enhancements
Terrestrial ecology
4b Destruction of potential otter holt and localised   4b Negative      Short Term   4b: Irreversible (loss of   4b: Major          4b: Otter holt should be monitored for
habitat disturbance.                                   Impact                        Otter holt may result in    4d: Moderate       activity, excluded (if necessary) and
4c Neutral Impact                                      4c     Neutral                the death of an animal)                        excavated under licence from the NPWS.
4d Localised habitat disturbance (Marsh habitat)       Impact
                                                       4d Negative                   4d:    Reversible   (the                       4d: Works should be minimised on the
                                                       Impact                        habitats should naturally                      eastern side of the road at this location, in
                                                                                     recover            post-                       order to avoid the area of species-rich Dry
                                                                                     construction)                                  Calcareous and Neutral Grassland. Works
                                                                                                                                    here should be supervised by an ecologist.

Aquatic ecology
4b: Mortality to in-channel flora and fauna owing      Negative         Long-term    Construction phase +        Significant, but   All drainage operations should be carried
to, in-channel, mechanical, works along the Clare                                    cumulative (in              largely            out    in   accordance     with   OPW’s
River from 900m upstream Crusheeny Bridge to                                         association with other      unknown until      Environmental Management Protocols
Claregalway Bridge. It is unknown what methods                                       measures)                   methods are        and Standard Operating Procedures
are proposed to carry out ‘regrading’ works and                                                                  defined. Works     (SOP) (Appendix A). Particular attention
methodology will exert a considerable bearing on                                                                 are within the     should be given to SOP for white-clawed
impact significance.       For example, channel                                                                  cSAC.              crayfish.
dewatering for works to occur in the dry will have
different effects than in-channel works in the wet.                                                                                 All drainage operations should be carried
Crayfish were not identified in the stretch near the                                                                                out in close consultation with Inland
bridge, but access was limited by construction                                                                                      Fisheries Ireland.
works. Otter spraint with white clawed crayfish                                                                                     Works in the dry give rise to the potential
remains were recorded here during 1981 and                                                                                          to rescue and relocate crayfish if they are
1991 studies, but these records are now too old to                                                                                  present (unlikely) and they emerge from
be reliable indicators of current presence. Also,                                                                                   refuges during a draw down. However, in
otters can range considerable distances and                                                                                         the event that channel works occur in-
crayfish remains may not have been those of local                                                                                   channel – this would cause direct mortality
populations. At present it is unlikely that crayfish                                                                                as it is unlikely that animals could be
are present in any great numbers, if at all, near                                                                                   efficiently trapped/captured and removed.
the bridge since habitat is poor-to-sub optimal with
swift flows, a lot of bedrock, embedded boulder,                                                                                    All efforts should be made to minimise the
and very little marginal habitat owing to                                                                                           loss of crayfish and methods and resulting
channelisation. But the possibility of presence                                                                                     channel      characteristics  should    be
can not be entirely ruled out.                                                                                                      conducive to habitat reinstatement and
                                                                                                                                    recolonisation. This may be very difficult,
                                                                                                                                    if not impossible given the depth of
                                                                                                                                    excavation proposed.           Given the
                                                                                                                                    significance of this measure, further
                                                                                                                                    investigations may be necessary to

MGE0260RP0005                                            16                                               Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                       Quality    Duration     Type                        Significance       Mitigation        Measures/Environmental
                                                                                                                               Enhancements
                                                                                                                               determine the overall significance should
                                                                                                                               this part of the river become uninhabitable
                                                                                                                               for crayfish following measures.
                                                                                                                               A pre-construction electrofishing survey is
                                                                                                                               recommended in the riffle/rapid section
                                                                                                                               downstream of Claregalway Bridge.
4b: Changes to hydromorphology and flow                 Negative   Long term    Construction phase and      Significant -      IFI     in-house   experts    should   be
dynamics, in particular, the loss of a riffle/rapid                             residual                    careful            commissioned to assist in the detailed
downstream of the bridge where loss of flow                                                                 mitigation may     design of the channel regrading and
diversity will result in changes to the benthic                                                             well reduce the    reinstatement. Retaining finer substrate
fauna, perhaps a decrease in diversity and loss of                                                          degree of          elements within the regraded stretch will
more sensitive species that inhabit faster flows.                                                           impact but the     be a challenge because the regrading is
Fish also utilise these areas, but the densities are                                                        habitat            likely to uncover mainly bare bedrock.
unknown.                                                                                                    alteration will
                                                                                                            remain             IFI in Galway have suggested that a
This is the only section of turbulent water and                                                             significant in     deeper low flow channel should be cut
cascade / boulder weir throughout this part of the                                                          terms of           parallel to the southern bank throughout
Clare. It provides significant re-aeration potential                                                        reduced habitat    the regraded stretch to facilitate fish
and is likely to contribute to an elevated density of                                                       diversity for      passage during very low flows.
juvenile salmon and trout in the waters within 50                                                           salmonids in
to 100m downstream. In low flows it provides a                                                                                 Consider reinstating similar habitat at the
                                                                                                            particular.        downstream end of the regraded section,
depth of water upstream of as far as the bridge                                                             Works are
and beyond. The loss of this feature may see a                                                                                 possibly by using similar sized boulders
                                                                                                            within the         excavated during regrading works in the
reduction in densities of younger salmon and trout                                                          cSAC.
in that stretch. It may lead to very shallow water                                                                             upstream section. The design could
upstream during very low flows making fish                                                                                     incorporate     the   creation   of    flow
passage difficult.                                                                                                             characteristics similar to the existing
                                                                                                                               situation by grading the channel
The section beneath the bridge and upstream of it                                                                              specifically towards the downstream end.
is already quite uniform and the habitat probably                                                                              The rapid/riffle should be qualitatively
won’t change significantly as a result of                                                                                      electrofished to determine fisheries
deepening.                                                                                                                     values.
4b: Mechanical works in the river will lead to          Negative   Short term   Construction phase          Moderate to        Define methodology.
increased suspended solids levels which may                                                                 Significant, but
abrade the gills of any juvenile salmon in the area                                                         largely            All drainage operations should be carried
increasing the risk of stress or disease.                                                                   unknown until      out    in   accordance     with   OPW’s
                                                                                                            methods are        Environmental Management Protocols
                                                                                                            defined.           and Standard Operating Procedures
                                                                                                                               (SOP) (Appendix A)
                                                                                                                               All drainage operations should be carried

MGE0260RP0005                                             17                                         Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                        Quality    Duration     Type                         Significance       Mitigation      Measures/Environmental
                                                                                                                                 Enhancements
                                                                                                                                 out in close consultation with Inland
                                                                                                                                 Fisheries Ireland.
4b: Habitat disturbance and loss associated with         Negative   Short term   Construction   phase    +    Moderate to        Define methodology.
regrading of channel. Given that crayfish are                                    Cumulative                   Significant, but
unlikely to exist here in any great numbers, if at                                                            methods as yet     All drainage operations should be carried
all, the impacts will mostly affect salmonids and                                                             unknown.           out    in   accordance     with   OPW’s
lamprey.                                                                                                                         Environmental Management Protocols
                                                                                                                                 and Standard Operating Procedures
Loss of the riffle/rapid has been discussed, and                                                                                 (SOP) (Appendix A)
may be significant given the rarity of the habitat
unit. The rest of the habitat is a long glide which is                                                                           All drainage operations should be carried
well represented on the Clare and is of less                                                                                     out in close consultation with Inland
significance.                                                                                                                    Fisheries Ireland.

4b: The section of deepened channel may cause            Positive   Long term    Residual                     Slight to          Modelling of the drop in upstream water
changes to hydromorphology in (an unknown                                                                     moderate, but      levels would be useful to determine the
length of) the channel upstream of the proposed                                                               unknown until      full impact significance. It may be that a
works. The effects could be, for example, reduced                                                             levels are         small weir is required to maintain
depths and alteration to flow dynamics, such as                                                               defined.           upstream water levels, however, the
increased local velocities which may affect aquatic                                                                              creation of riffles and runs is also
habitat. For example, increased upstream                                                                                         desirable for fisheries. It is probably
velocities may benefit fauna by the creation of                                                                                  important that any lowering of the water
riffle areas and clean, bouldery glides which are                                                                                levels upstream during regrading occurs
more optimal habitat for juvenile salmon and trout                                                                               in such a way that levels drop slowly so
and sensitive macroinvertebrate species.                                                                                         that fish occupying marginal habitat can
                                                                                                                                 escape to the main channel. There would
                                                                                                                                 need to be a well defined low flow channel
                                                                                                                                 incorporated in the design to ensure fish
                                                                                                                                 passage and low flow connectivity. The
                                                                                                                                 creation of an upstream riffle/rapid area
                                                                                                                                 that may result could compensate for the
                                                                                                                                 loss of the downstream riffle/rapid.
4c: Wall blocking will have no impacts                   Neutral    N/A          N/A                          No impact          N/A

4d: The extent of this is unclear and the                Negative   Short-term   Construction phase +         Imperceptible to   Sediment      run-off     control   during
embankment material has not been defined.                                        Cumulative (inputs of silt   Slight,            construction and settling phase.
Freshly excavated earthen embankment material                                    to   Clare    River)   in    depending on
could contribute sediment to the Clare River                                     association with other       materials used.
causing damage to fish gills.                                                    measures.

MGE0260RP0005                                              18                                        Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                      Quality    Duration     Type                  Significance       Mitigation  Measures/Environmental
                                                                                                                        Enhancements

Archaeology and cultural heritage
The proposed works will impact on the banks and        Negative   Permanent    Irreversible          Significant        It is recommended that an underwater
bed of Clare River (AAP 1), due to the deepening                                                                        archaeological survey be undertaken
of the channel. This has the potential impact upon                                                                      within the relevant sections of the channel
archaeological features or artefacts such as                                                                            to be affected by the proposed
organic remains/artefacts or archaeological                                                                             development. Subject to site investigation.
deposits. Riverine environments are often a focus
for human activity from prehistory onwards and                                                                          Underwater survey should be carried out
are areas of archaeological potential. (It should be                                                                    by an archaeologist licenced to the
noted that massive alterations were made to the                                                                         Department of Arts, Heritage and the
                        th
river during the late 19 century, which may have                                                                        Gaeltacht. Full provision should be made
impacted on any such remains).                                                                                          available for the resolution of any
                                                                                                                        archaeological deposits, should that be
                                                                                                                        deemed the most appropriate way to
                                                                                                                        proceed.
Nine Arches Bridge is a protected structure (BH        Negative   Permanent    Reversible            Moderate           It is recommended that the construction of
2). It is possible that the construction of the                                                                         the      embankment       be    undertaken
proposed embankment will adversely impact on                                                                            sympathetically to the setting of the
the setting of the structure.                                                                                           bridge, especially with regards to views of
                                                                                                                        the structure form the existing main road
                                                                                                                        through Claregalway village.
Soils, geology and hydrogeology
Regrading the channel may induce additional            Positive   Permanent    Residual              Slight             Reduction in water table levels may
groundwater flow where the water table rises                                                                            reduce the potential for groundwater
above the base of the channel. This should lead to                                                                      flooding.
improved drainage in the area.

4.2.5    Kiniska

Potential Impacts                                      Quality    Duration       Type                    Significance   Mitigation Measures/Environmental
                                                                                                                        Enhancements
Socio-economic
Disruption to local land users                         Negative   Short term     Cumulative              Significant    Provide prior warning of disruption to land
                                                                                                                        owners.

MGE0260RP0005                                            19                                   Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                      Quality    Duration     Type                        Significance      Mitigation Measures/Environmental
                                                                                                                             Enhancements
Disruption to power supply: There is a 20Kv ESB        Negative   Short term   Cumulative                  Significant       • Liaison with ESB is required prior to
line northeast of Claregalway village which follows                                                                             any works being undertaken
the local road from Caraunkeelwy townland to                                                                                 • Prior notice to those supplied by this
Kiniska townland and ends at the tributary of the                                                                               linke required
Clare River at Kiniska townland.
Terrestrial ecology
Negative - potential for loss of or damage to EU       Negative   Short term   Reversible                  Major             Works should be minimised on the eastern
Annex I habitat ‘Molinia meadows on calcareo                                                                                 side of the road at this location, in order to
us, peaty or clayey-silt-laden soils (Molinion                                                                               avoid the area of Annex I habitat. Works
caeruleae)(6410)’ within Lough Corrib cSAC.                                                                                  here should be supervised by an ecologist.

Aquatic ecology
5a: Culvert replacement - method for replacement       Negative   Short term   Construction phase +        Slight local      A detailed method statement should be
is undefined, but there is potential to contribute                             Cumulative (inputs of       impacts due to    drawn up by the contractor indicating what
sediment and silt, with a risk of cement and                                   silt to Clare River) in     low value of      measures will be taken to avoid sediment
hydrocarbon spills (diesel, hydraulic fluid) to the                            association with other      drain habitat.    or soil loss associated with all aspects of
watercourse. Localised habitat disturbance.                                    measures.                   Works are         the construction phase and how these will
                                                                                                           outside the       be monitored for effectiveness.
                                                                                                           cSAC.
5b: Drainage operations - physical habitat             Negative   Short term   Construction phase          2c: Moderate      Carry out works in a downstream direction
disturbance and/or loss over a significant linear                                                          local, impacts,   so that in-situ vegetation can act as a
length of watercourse. The habitat was of low value                                                        with Slight       buffer to the mobilisation of silt
and only of local importance and there were existing                                                       impact overall.   downstream to the Clare River.
discharges to the stream that probably impact on                                                           Works are
water quality.                                                                                             mostly outside    Undertake this measure in different
                                                                                                           the cSAC.         sequence to other measures to limit
There was no suitable spawning habitat for                                                                                   cumulative impacts. The Clare has a flow
salmonids, lamprey or crayfish habitat observed in                                                                           regime that does not favour excessive silt
this drain, and none of these groups are expected to                                                                         deposition and limited intermittent inputs
be present. It is possible that species such as 3-                                                                           should have negligible impact on the river,
spined stickleback may be present.                                                                                           overall. Time works to occur in predicted
                                                                                                                             low rainfall period.
The proposed works will impact on the banks and        Negative   Permanent    Irreversible                Significant       It is recommended that an underwater
bed of a small stream included within the                                                                                    archaeological survey be undertaken
designation of AAP 1, due to the cleaning of the                                                                             within the relevant sections of the stream
channel. This has the potential to impact upon                                                                               to be affected by the proposed
archaeological features or artefacts such as                                                                                 development. Subject to site investigation.
organic remains/artefacts or archaeological
deposits. (It should be noted that alterations were                                                                          Underwater survey should be carried out
                                         th
made to the stream during the late 19 century,                                                                               by an archaeologist licenced to the

MGE0260RP0005                                            20                                     Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                      Quality            Duration          Type                         Significance     Mitigation Measures/Environmental
                                                                                                                                          Enhancements
which may have impacted on any such remains).                                                                                             Department of Arts, Heritage and the
                                                                                                                                          Gaeltacht. Full provision should be made
                                                                                                                                          available for the resolution of any
                                                                                                                                          archaeological deposits, should that be
                                                                                                                                          deemed the most appropriate way to
                                                                                                                                          proceed.
It is possible that excavation work associated with    Negative           Permanent         Irreversible                 Significant      It is recommended that any ground
increasing the size of existing culverts, may have                                                                                        disturbances     associated    with    the
an adverse impact on previously unrecorded                                                                                                proposed works that require the
archaeological features or deposits that may exist                                                                                        excavation of virgin ground, be monitored
within the area.                                                                                                                          by a suitably qualified archaeologist. Full
                                                                                                                                          provision should be made for the
                                                                                                                                          resolution of any archaeological features
                                                                                                                                          or deposits that are discovered, should
                                                                                                                                          that be deemed the most appropriate way
                                                                                                                                          to proceed.

4.2.6     Lakeview

Potential Impacts                                 Quality     Duration               Type                  Significance        Mitigation Measures/Environmental Enhancements
Socio-economic
Disruption to local land users                    Negative    Short term             Cumulative            Significant         Provide prior warning of disruption to land owners.
Disruption to utilities: The village of           Negative    Short term             Residual              Slight              Provide prior warning of temporary disruption to Bord
Claregalway, and Lakeview townland, are                                                                                        Gais supplies if necessary to facilitate works.
also supplied with natural gas by An Bord
Gais. The distribution network follows the
N18 from Carnmore Cross Roads and turns
right at the N18/N17 junction in Claregalway
to supply Claregalway village.
Aquatic ecology
6a: Water quality changes associated with         Negative    Long-term              Cumulative (in        Moderate,           Use guidance and design of Sustainable Urban
                                                                                                                                                      1
increased run-off to Clare River from semi-                                          association with      perhaps             Drainage Systems (SuDS) to help reduce sediment

1
    http://www.irishsuds.com/guidance_criteria.htm

MGE0260RP0005                                            21                                                  Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                   Quality        Duration     Type                   Significance      Mitigation Measures/Environmental Enhancements
urban/industrial area as a point source. Such                                   other urban            Significant,      and pollutant loading to Clare River for more frequent
run-off, when drained by pipe systems,                                          discharges from        depending on      small run-off events. Hydrocarbon interception
results in run-off from virtually every rainfall                                the Claregalway        design and        systems should be included if car-parking areas and
event with high levels of pollution, particularly                               settlement) +          level of future   roads are contained within the drainage catchment.
in the first part of the run-off. It has been                                   Residual (ongoing      urban and/or
accepted that measure 6a. will not eliminate                                    inputs of pollutants   industrial        A detailed method statement should be drawn up by
2009 flood levels, but what it may do is                                        to Clare River)        development       the contractor indicating what measures will be taken
increase polluted run-off for small, more                                                              in the drained    to avoid sediment or soil loss associated with all
frequent, events which may have significance                                                           area.             aspects of the construction phase and how these will
in relation to the Clare fishery.                                                                                        be monitored for effectiveness.

6a: Construction phase - potential to               Negative       Short term   Construction           Moderate          Construct drain and lay pipe whilst leaving a 20m,
contribute sediment and silt, with a risk of                                    phase +                                  undisturbed buffer section between this and the Clare
cement and hydrocarbon spills (diesel,                                          Cumulative (inputs                       River. Only connect the lower end of the conduit once
hydraulic fluid) which can run-off from the                                     of silt to Clare                         all works upstream are complete and fines and spills
open sections of drain and be piped to the                                      River) in                                have been removed or settled.
Clare river.                                                                    association with
                                                                                other measures.                          A detailed method statement should be drawn up by
                                                                                                                         the contractor indicating what measures will be taken
                                                                                                                         to avoid sediment or soil loss associated with all
                                                                                                                         aspects of the construction phase and how these will
                                                                                                                         be monitored for effectiveness.
6a: Possible hydrological changes at                Neutral        Long-term    Residual               Imperceptible.    Provide stable boulder rip-rap reinforcement at outflow
discharge site to Clare River which can affect                                                                           to Clare River, if necessary, to prevent erosion.
benthic flora and fauna.          The channel
characteristics above Claregalway Bridge will
not present any issues in terms of this new
input, primarily because substrates are
generally embedded boulder and bedrock
with limited microhabitat for fauna.
The proposed works may impact on the                Negative       Permanent    Irreversible           Significant       It is recommended that an underwater archaeological
banks and bed of the Clare River due to the                                                                              survey be undertaken within the outfall location.
construction of a drainage outfall upstream of                                                                           Subject to site investigation.
the Claregalway Bridge. This has the
potential to impact upon archaeological                                                                                  Underwater survey should be carried out by an
features or artefacts such as organic                                                                                    archaeologist licenced to the Department of Arts,
remains/artefacts or archaeological deposits.                                                                            Heritage and the Gaeltacht. Full provision should be
(It should be noted that alterations were                                                                                made available for the resolution of any archaeological
made to the stream during the late 19
                                             th                                                                          deposits, should that be deemed the most appropriate
century, which may have impacted on any                                                                                  way to proceed.
such remains).

MGE0260RP0005                                                 22                                         Rev. F01
Clare River (Claregalway) Flood Relief Scheme
Stage 2 - Environmental Assessment of Viable Options

Potential Impacts                                 Quality        Duration              Type               Significance       Mitigation Measures/Environmental Enhancements

Archaeology and cultural heritage
It is possible that excavation work associated    Negative       Permanent             Irreversible       Significant        It is recommended that any ground disturbances
with the insertion of a surface water drain                                                                                  associated with the proposed works be monitored by a
through Lakeview to Claregalway, may have                                                                                    suitably qualified archaeologist. Full provision should
an adverse impact on previously unrecorded                                                                                   be made for the resolution of any archaeological
archaeological features or deposits that may                                                                                 features or deposits that are discovered, should that
exist within the area.                                                                                                       be deemed the most appropriate way to proceed.
Soils, geology and hydrogeology
Flooding in this area was as a result of          Positive       Permanent             Residual           Moderate           Measures should provide some            alleviation   to
groundwater flooding which is known to occur                                                                                 groundwater flooding in the area.
during winter months.
Surface water drain to be installed to drain
some portion of the flood water but
inundation will still occur during peak events.
This will result in a minor alteration to
groundwater levels and flow Residualions in
the vicinity of the flooding but there are not
groundwater        dependant       ecosystems
associated with these features.

4.2.7    Caherlea/Lisheenavalla

Potential Impacts                                      Quality              Duration       Type            Significance           Mitigation             Measures/Environmental
                                                                                                                                  Enhancements
Terrestrial ecology
8a Loss of bankside vegetation (scrub, earth           8a Negative          Short          Irreversible    8a: Slight             8a: None required
banks)                                                 8b Negative          Term                           8b: Significant        8b: Badger sett should be monitored for activity,
                                                       8c Negative                                         8c: Major              excluded (if necessary) and excavated under
8b Loss of bankside vegetation (scrub, dry             8d Neutral                                                                 licence from the NPWS. Works at this location
calcareous and neutral grassland and wet                                                                                          should be minimised and should be supervised
grassland), loss of badger sett.                                                                                                  by an ecologist.
                                                                                                                                  8c: Works at this location should be minimised
8c Potential direct impacts to an area of Annex I                                                                                 and should be supervised by an ecologist.
habitat ‘Molinia meadows on calcareous, peaty or

MGE0260RP0005                                            23                                                 Rev. F01
You can also read