EXECUTIVE SUMMARY

The City of Buda five year Capital Improvements Plan (CIP) is a planning tool to help the City forecast the timing
and funding of future capital projects. The Plan is reviewed and updated annually as part of the annual budget
development process. Projects are derived from the Buda 2030 Comprehensive Plan as well as infrastructure
specific master plans. Projects are also identified through staff observations, citizen comments, and development
trends occurring in and around the City. A staff team that includes representatives from the Public Works, Parks,
Planning, Engineering, and Finance departments work together to develop the project scopes and to prioritize
needs. Input on the document is also solicited from the Parks Commission and the Planning and Zoning
Commission in order to account for the impact of growth on the City's infrastructure system.

The inclusion of a project in the Capital Improvements Plan does not guarantee that the City will design or
construct the project in the time frame noted in the document. Project funding and construction is always subject
to change, and the CIP will be evaluated annually by the City Council in order to prioritize projects and identify
funding sources based on needs and the availability of funding. Some projects shown in the CIP may be
constructed by private development as it is needed to serve future development with or without participation by
the City of Buda. Projects such as these are shown in the CIP to reflect the City's master plans and to help identify
how future projects may impact the existing infrastructure network.

Identified funding sources noted in the document are representative of funding options but are not an guaranty of
project funding or source. The City Council will annually evaluate funding availability to determine the best funding
source as part of the annual budget process. Project costs are shown at today's dollars. No inflationary factor is
included in the projections. Most project costs are based on early estimates as typically no engineering has been
completed on the project. The costs of projects in the document will be reviewed and updated during the annual
review to adjust for cost changes.

                                 Breakdown by Project Type
                                              6%
                                                         14%
                                                                                 Parks
                                                               6%                Facilities
                                                                                 Water
                                 40%                                             Wastewater
                                                               23%               Transportation
                                                                                 Drainage

                                                   11%

                                                           2
City of Buda, TX 2019 2023 - Capital Improvements Plan
DEFINITIONS & ACRONYMS

Below is a list of terms and acronyms used in this document.

ADA. The Americans with Disabilities Act of 1990.

ARWA. Alliance Regional Water Authority. Formerly the Hays Caldwell Public Utility Authority.

ASR. Aquifer Storage and Recovery.

BEDC. The Buda Economic Development Corporation. Also referred to as the "EDC."

BODs. Biochemical oxygen demand.

CIP. Capital Improvements Plan. The five year planning document used by the City of Buda to plan out capital
expenditures.

COs. Certificates of Obligation bonds.

FM. Farm to Market roadway or wastewater force main, depending on the context.

FY. Fiscal Year.

GOs. General Obligation bonds.

HCISD. Hays Consolidated Independent School District.

HDPE. High-density polyethlyne is a strong thermoplastic used for piping.

HOA. Home owners association.

LF. Linear Feet.

LS. Lift station.

MG. Million gallons.

MGD. Million gallons daily.

Parks Capital Fund. A fund of the City of Buda that accounts for Park Dedication Fees that are charged during the
development process. These fees are used to make improvements to the City's park system.

PVC. Polyvinyl chloride pipe.

Rd. or St. Road or street.

RM. Ranch to Market roadway.

ROW. Right of way.

Sq. Ft. or SF. Square foot.

TCEQ. Texas Commission on Environmental Quality.

                                                        3
City of Buda, TX 2019 2023 - Capital Improvements Plan
TSS. Total suspended solids.

WWTP. Wastewater Treatment Plant.

                                    4
City of Buda, TX 2019 2023 - Capital Improvements Plan
ALL PROJECT SUMMARY
                                            Project                                     Prior                                 Fiscal Year
                                             Name                                       Years            19         20            21             22          23         Future        Total
Park Projects
  P00    City Park                                                                      5,884,000              -          -             -               -          -             -    5,884,000
  P01    Summer Pointe Park Improvements                                                  400,000              -          -             -               -          -             -      400,000
  P02    Stagecoach Park Restroom                                                         130,600              -          -             -               -          -             -      130,600
  P03    Garison Park Development                                                               -              -    400,000     3,600,000               -          -             -    4,000,000
  P04    Sports Complex Field Improvements                                                      -        491,808          -             -               -          -             -      491,808
  P05    Greenbelt Improvements (Downtown Plan)                                                 -              -    100,000       700,000               -          -             -      800,000
  P06    Eastside Community Park Land Acquisition                                               -              -          -             -       3,750,000          -             -    3,750,000
  P07     Recreation and Aquatic Center                                                         -              -          -             -               -     75,000     8,000,000    8,075,000
  P08    Bradfield Park Improvements                                                            -              -     50,000             -               -          -             -       50,000
  P09    City Park Trails and Disc Golf Course                                                  -              -          -             -         150,000          -             -      150,000
  P10    Green Meadows Park Improvements                                                        -              -    125,000             -               -          -             -      125,000
  P11    Stagecoach Park Improvements                                                           -              -          -       105,000               -          -             -      105,000

Facility Projects
  F01     Public Works Facility                                                                 -              -          -                 -   3,250,000    250,000     3,250,000    6,750,000
  F02     Convention Center                                                                     -              -          -                 -           -          -             -            -
  F03     Visitor's Center and Main Street Office Remodel                                       -         75,000    400,000                 -           -          -             -      475,000

Water Projects
 W01 ASR / Trinity Well                                                                 1,896,000              -          -     1,876,000               -          -             -    3,772,000
 W02 Alliance Regional Water Authority Phase 1B Project                                    28,810        109,533    195,493       410,767         515,631    753,081    12,519,823   14,533,138
 W03 Water Master Plan                                                                          -              -          -       175,000               -          -             -      175,000
 W04 East IH-35 12" Transmission Main Loop                                                      -              -    477,000     1,590,000               -          -             -    2,067,000
 W05 Advanced Metering Infrastructure (AMI) System                                              -        250,000    250,000       250,000         250,000    250,000     1,250,000    2,500,000
 W06 Old Black Colony Elevated Storage Tank                                                     -              -    603,000             -       1,272,000          -             -    1,875,000
 W07 FM 1626 12" Transmission Main Connection                                                   -              -          -             -               -    500,000             -      500,000
 W08 West IH 35 Transmission Main                                                               -              -    300,000             -               -          -             -      300,000
 W09 Old Black Colony Road 12" Transmission Main & Pressure Valve                               -              -          -     2,592,000               -          -             -    2,592,000
 W10 Old Black Colony Ground Storage Tank & Pump Station                                        -              -    304,500             -       2,030,000          -             -    2,334,500

Wastewater Projects
 WW00 Wastewater Treatment Plant Phase III Expansion & New Effluent Discharge Main     25,319,164               -         -             -              -            -            -   25,319,164
 WW01 Meadows at Buda Lift Station Expansion & New Force Main                             193,000               -         -             -              -            -            -      193,000
 WW02 Sportsplex Sewer Line Upsize                                                        450,000               -         -             -              -            -            -      450,000
 WW03 Wastewater Master Plan                                                              150,000               -         -             -              -            -            -      150,000
 WW04 Wastewater Manhole Rehabilitation                                                   202,880               -         -             -              -            -            -      202,880
 WW06 Garison Road Gravity Interceptor Replacement                                        874,000               -         -             -              -            -            -      874,000
 WW07 South Loop 4 Lift Station Replacement & Gravity Interceptor Extension                     -       1,500,000         -             -              -            -            -    1,500,000
 WW08 Decommission Old Night Hawk Lift Station                                                  -         135,000         -             -              -            -            -      135,000
 WW09 Northeast IH-35 12" Gravity Interceptor                                                   -               -   490,000             -              -            -            -      490,000
 WW10 Northwest IH-35 15" Gravity Interceptor                                                   -               -         -     1,472,000              -            -            -    1,472,000
 WW11 Bradfield/Lifschutz 12"/16"/18" Gravity Interceptor Expansion                             -               -         -             -        421,500    2,809,500            -    3,231,000
 WW12 Direct Potable Reuse (DPR) Feasibility Study                                              -               -   203,656       203,656              -            -            -      407,312
 WW13 Garlic Creek Basin Inflow & Infiltration Study                                            -               -    50,000             -              -            -            -       50,000
 WW14 Edwards Aquifer Recharge Zone Integrity Testing & Rehabilitation                          -               -         -             -         50,000            -            -       50,000

                                                                                                    5
City of Buda, TX 2019 2023 - Capital Improvements Plan
Mobility Projects
 T01     Roadway Impact Fee Study                               60,000             -           -           -           -           -   -      60,000
 T02     Pavement Management Study                                   -        55,000           -           -           -           -   -      55,000
 T03     Cabelas Drive at Old San Antonio Road Traffic Signal        -             -     218,000           -           -           -   -     218,000
 T04     Garlic Creek Parkway Study                                  -             -           -           -     350,000           -   -     350,000
 T05     Cabela's Connector                                          -       870,000     972,000           -           -           -   -   1,842,000
 T06     IH-35 to Old San Antonio Connector                          -             -     165,000           -           -           -   -     165,000
 T07     Downtown Streetscaping Improvements - Main St.              -             -           -   1,232,000           -           -   -   1,232,000
 T08     Pedestrian Crossing & Signal at Main and Ash Street         -       115,000           -           -           -           -   -     115,000
 T09     Old Black Colony Road Reconstruction                        -             -           -           -   5,000,000           -   -   5,000,000
 T10     West Goforth Road Reconstruction                            -             -           -           -   5,175,000           -   -   5,175,000
 T11     FM 2001 Pedestrian and Bicycle Path                         -             -     500,000           -           -           -   -     500,000
 T12     South Loop 4 Sidewalk (Downtown to Meadows at Buda)         -             -   1,302,500           -           -           -   -   1,302,500
 T13     FM 1626 and RM 967 Intersection Study                       -             -           -     240,000           -           -   -     240,000
 T14     Talley Loop Reconstruction                                  -             -     455,000           -           -           -   -     455,000
 T15     Oyster Creek Drive Reconstruction                           -             -     920,000           -           -           -   -     920,000
 T16     Green Meadows Lane Reconstruction                           -             -           -           -           -   1,400,000   -   1,400,000
 T17     Middle Creek Drive Reconstruction                           -             -           -           -           -   1,990,000   -   1,990,000
 T18     Transportation Master Plan                                  -       150,000           -           -           -           -   -     150,000
 T19     Old San Antonio Road Reconstruction                         -             -   3,000,000           -           -           -   -   3,000,000
 T20     Railroad Street Reconstruction Phase I                      -             -           -           -     750,000   2,000,000   -   2,750,000

Drainage Projects
  D01 Bonita Vista - El Secreto Cul-de-sac Drainage             86,000             -          -            -           -           -   -      86,000
  D02 Whispering Hollow Street Drainage                              -        40,000    370,000            -           -           -   -     410,000
  D03 Garlic Creek Tributary Under RM 967                            -             -    318,000            -           -           -   -     318,000
  D04 Ash/Main St. Intersection Flooding                             -       149,000          -            -           -           -   -     149,000
  D05 West Lifschutz Area Drainage                                   -             -          -    1,700,000           -           -   -   1,700,000
  D06 Drainage Master Plan                                           -             -          -      150,000           -           -   -     150,000
  D07 Lifschutz Central Area Drainage                                -             -          -            -   1,408,000           -   -   1,408,000

                                                                         6
City of Buda, TX 2019 2023 - Capital Improvements Plan
Parks Capital Improvement Program
                                                                            FY 2019 - 2023

The Parks improvement projects reflect projects identified thorugh the Parks, Recreation, Open Spaces, and Trails Master Plan and through the Parks Advisory Commission.
Funding for some projects is derived from Parkland Dedication Fees that are paid by new development in the City.

Sources of Funding                                           Prior                                                                              2019-23
                                                             Years          19            20            21            22            23           Total

        Operating Fund                                               -             -              -            -             -            -               -
        Parks Capital Fund                                     530,600             -      175,000       105,000       150,000        75,000       505,000
        Fund Balance                                                 -             -              -            -             -            -               -
        Debt Proceeds                                        5,884,000             -      500,000      3,800,000     3,750,000            -      8,050,000
        Other - Hotel Occupancy Tax, Grants, etc.                    -      491,808               -     500,000              -            -       991,808

Total                                                        6,414,600      491,808       675,000      4,405,000     3,900,000       75,000      9,546,808

Uses of Funds                                                Prior
                                                             Years          19            20            21            22            23          Future         Total

Parks Projects:
  P00 City Park                                              5,884,000             -              -            -             -            -               -    5,884,000
  P01 Summer Pointe Park Improvements                          400,000             -              -            -             -            -               -     400,000
  P02 Stagecoach Park Restroom                                 130,600             -              -            -             -            -               -     130,600
  P03 Garison Park Development                                       -             -      400,000      3,600,000             -            -               -    4,000,000
  P04 Sports Complex Field Improvements                              -      491,808               -            -             -            -               -     491,808
  P05 Greenbelt Improvements (Downtown Plan)                         -             -      100,000       700,000              -            -               -     800,000
  P06 Eastside Community Park Land Acquisition                       -             -              -            -     3,750,000            -               -    3,750,000
  P07   Recreation and Aquatic Center                                -             -              -            -             -       75,000      8,000,000     8,075,000
   P08 Bradfield Park Improvements                                   -             -         50,000            -             -            -               -      50,000
  P09 City Park Trails and Disc Golf Course                          -             -              -            -      150,000             -               -     150,000
  P10 Green Meadows Park Improvements                                -             -      125,000              -             -            -               -     125,000
  P11 Stagecoach Park Improvements                                   -             -              -     105,000              -            -               -     105,000

Total Uses of Funds                                          6,414,600      491,808       675,000      4,405,000     3,900,000       75,000      8,000,000    23,961,408

Cumulative Balance
Sources Over/(Under) Uses                                            -             -              -            -             -            -

                                                                                   7
City of Buda, TX 2019 2023 - Capital Improvements Plan
City of Buda, Texas
                               Capital Improvement Program - Parks

                                                          City Park

Responsible Department:                     Parks                                                   CIP No.       P00

Financial Plan :
                   Prior                                   Projected
                   Years           19            20           21             22            23         Future        Total
                   5,884,000            -             -            -              -             -             -     5,884,000

Description :
City Park will serve as Buda’s signature park and recreation area, providing opportunities for festival gatherings as well as
improved service to the community’s everyday needs. A larger trails system will connect City Park to adjacent green
spaces, including Stagecoach Park, Bradfield Village Park and the Downtown Greenbelt, thereby leveraging their shared
amenities and creating an expanded recreational network. Project amenities planned for City Park include: water features,
amphitheater, playground improvements, improvements to the existing pavilion, native/natural areas, event parking, and
other improvements. City Park is approximately 51 acres in size.

                                    Insert map showing location of project or related picture

             Estimated Project Cost:                                   Project Task:                Duration (Months)
             Design/Engineering              1,122,000                 Planning/Design                      12
             ROW Acquisition                         -                 Right-of-way/Utilities                 -
             Construction                    4,762,000                 Construction                         14
             Other                                   -                 Total                                26
             Total                           5,884,000

             Funding Source:                                   Ongoing Operational Impact:
             Operating Fund                          -         Personnel                               -
             Debt                            5,884,000         Supplies & Materials                    -
             Grants/Other                            -         Repair & Maint.                         -
             Total                           5,884,000         Capital & Other                         -
Notes:                                                         Total                                   -
The San Antonio Rd. project (part of Prop 3) is expected to be bid concurrently with this project. It will also include
improvements to the intersection of San Antonio Rd., Garison Rd., and Main St. Construction is expected to begin in
January 2018 and last rougly 12-14 months.

                                                               8
City of Buda, TX 2019 2023 - Capital Improvements Plan
City of Buda, Texas
                              Capital Improvement Program - Parks

                                           Summer Pointe Park Improvements

Responsible Department:                     Parks                                                  CIP No.       P01

Financial Plan :
                   Prior                                  Projected
                   Years          19            20           21             22            23         Future        Total
                    400,000            -             -            -              -             -             -         400,000

Description :
Summer Pointe Park improvements will feature a splash pad facility, group pavilion approximately (20' x 30'), and a
restroom building. The splash pad will be a dynamic, zero-depth aquatic play area that provides endless hours of fun for
the entire family. The water feature will re-circulate water and combines the sensations of different water
movements—flowing, misting, and jetting. The restroom facility will be a multi-user restroom and will be designed to
contain the mechanical room for the adjoining splash pad. The group pavilion will accommodate approximately 40 park
patrons and will facilitate increased park rentals.

                                   Insert map showing location of project or related picture

             Estimated Project Cost:                                  Project Task:                Duration (Months)
             Design/Engineering                      -                Planning/Design                        -
             ROW Acquisition                         -                Right-of-way/Utilities                 -
             Construction                      400,000                Construction                           6
             Other                                   -                Total                                  6
             Total                             400,000

             Funding Source:                                    Ongoing Operational Impact:
             Operating Fund                          -          Personnel                             -
             Debt                                    -          Supplies & Materials              5,000
             Grants/Other                      400,000          Repair & Maint.                 15,000
             Total                             400,000          Capital & Other                       -
Notes:                                                          Total                           20,000
Funding source is the Parks Capital Fund. The Summer Pointe Park improvements will include a splash pad, pavilion, and
restroom.

                                                              9
City of Buda, TX 2019 2023 - Capital Improvements Plan
City of Buda, Texas
                              Capital Improvement Program - Parks

                                            Stagecoach Park Restroom

Responsible Department:                    Parks                                                 CIP No.       P02

Financial Plan :
                   Prior                                Projected
                   Years          19           20          21            22             23         Future        Total
                    130,600            -            -           -             -              -             -         130,600

Description :
Install an additional men's and women's ADA restroom facility at Stagecoach Park.

             Estimated Project Cost:                                Project Task:                Duration (Months)
             Design/Engineering                     -               Planning/Design                        4
             ROW Acquisition                        -               Right-of-way/Utilities                 -
             Construction                     130,600               Construction                           3
             Other                                  -               Total                                  7
             Total                            130,600

             Funding Source:                                 Ongoing Operational Impact:
             Operating Fund                         -        Personnel                           -
             Debt                                   -        Supplies & Materials                -
             Grants/Other                     130,600        Repair & Maint.                1,300
             Total                            130,600        Capital & Other                     -
Notes:                                                       Total                          1,300
Funding source is the Park Fund fund balance. The fund balance is comprised of previous developer paid parkland
development fees.

                                                           10
City of Buda, Texas
                           Capital Improvement Program - Parks

                                           Garison Park Development

Responsible Department:                  Parks                                                    CIP No.       P03

Financial Plan :
                   Prior                                Projected
                   Years        19            20           21             22             23         Future        Total
                       -             -       400,000     3,600,000             -              -             -     4,000,000

Description :
Phase I of Garison Park development which includes the parking areas, trails, water access headquarters, and prairie land
restoration. Future phases of the project would include the construction of a nature center and restoration of the
McCaughan homestead.

                                 Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering             400,000                  Planning/Design                        6
             ROW Acquisition                      -                  Right-of-way/Utilities                 -
             Construction                 3,600,000                  Construction                           6
             Other                                -                  Total                                12
             Total                        4,000,000

             Funding Source:                                    Ongoing Operational Impact:
             Operating Fund                       -             Personnel                                 -
             Debt                         3,500,000             Supplies & Materials                      -
             Grants/Other                   500,000             Repair & Maint.                    77,500
             Total                        4,000,000             Capital & Other                           -
Notes:                                                          Total                              77,500
Grant application through Texas Parks and Wildlife Department for Garison Park development. Operational impact is
combined personnel, supplies, and repairs based on Design Workshop report. The City will seek to identify other grant and
foundation funding for the park, as available.

                                                            11
City of Buda, Texas
                           Capital Improvement Program - Beautification

                                      Sports Complex Field Improvements

Responsible Department:                   Parks                                                   CIP No.       P04

Financial Plan :
                   Prior                                 Projected
                   Years         19            20           21             22            23         Future         Total
                       -        491,808             -            -              -             -             -         491,808

Description :
Add a lighting system consisting of lighting, electrical and structural components to the softball/baseball fields. This will
allow teams to utilize the fields more times of the year and opens up the facility to host tournaments. Luminaires will be
constructed with a die-cast aluminum housing or external hail shroud to protect the luminaire reflector system. All exposed
components shall be constructed of corrosion-resistant material and/or coated to help prevent corrosion. All exposed steel
shall be hot dip galvanized per ASTM A123. All wiring shall be enclosed within the crossarms, conduit, pole, or electrical
components enclosure. All outdoor structures shall be equipped with lightning protection meeting NFPA 780 standards.

                                  Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering               10,000                 Planning/Design                        -
             ROW Acquisition                       -                 Right-of-way/Utilities                 -
             Construction                    481,808                 Construction                           2
             Other                                 -                 Total                                  2
             Total                           491,808

             Funding Source:                                   Ongoing Operational Impact:
             Operating Fund                        -           Personnel                              -
             Debt                                  -           Supplies & Materials              30,000
             Grants/Other                    491,808           Repair & Maint.                        -
             Total                           491,808           Capital & Other                        -
Notes:                                                         Total                             30,000
The funding could be made from the Hotel Occupancy Tax. The ongoing operational impact is the assumed increase for
electricity.

                                                                12
City of Buda, Texas
                           Capital Improvement Program - Beautification

                                 Greenbelt Improvements (Downtown Plan)

Responsible Department:                  Parks                                                    CIP No.       P05

Financial Plan :
                   Prior                                Projected
                   Years        19            20           21             22             23         Future        Total
                       -             -        100,000      700,000             -              -             -         800,000

Description :
The Greenbelt Park (Action 5, 2015 Downtown Master Plan) is intended to be configured for every-day use as a beautiful
contemplative signature public space in Downtown Buda as well as a location for events. Walkways should encompass the
event lawn area, and new garden-like landscaping should be installed in the area between the lawn and Main Street to
create a vegetative buffer. A terminus sight-line feature should be incorporated at the end of Elm Street and the Greenbelt
Park. As part of the project, improvements to the gazebo are needed including replacement of wooden steps with an ADA
accessible ramp and upgrades to the electrical system for special events.

                                 Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering              100,000                 Planning/Design                        9
             ROW Acquisition                       -                 Right-of-way/Utilities                 -
             Construction                    650,000                 Construction                           6
             Other                            50,000                 Total                                15
             Total                           800,000

             Funding Source:                                            Ongoing Operational Impact:
             Operating Fund                        -                    Personnel                     8,000
             Debt                            800,000                    Supplies & Materials          1,000
             Grants/Other                          -                    Repair & Maint.                   -
             Total                           800,000                    Capital & Other                   -
Notes:                                                                  Total                         9,000
Project was identifed in the 2015 Downtown Master Plan. The space is already utilized for markets and craft fairs.
Improvements will naturally tie into the future use of the former Library located at 303 Main Street.

                                                               13
City of Buda, Texas
                           Capital Improvement Program - Parks

                                 Eastside Community Park Land Acquisition

Responsible Department:                   Parks                                                  CIP No.       P06

Financial Plan (thousands of dollars) :
                 Prior                                  Projected
                 Years        19              20           21             22            23         Future        Total
                       -            -              -            -      3,750,000             -             -     3,750,000

Description :
All existing Community and Regional Parks are located on the west side of IH-35. The residents on the eastern side of
Buda do not have easy access to a community park. An approximately 50 acre site for a future community park on the
east side of IH-35 should be identified and acquired while land values remain relatively affordable. While land acquisition
for a community park is a priority, development of the park might not be needed for another 5 to 10 years. PRIORITY: high
for identifying park site; long-term for developing the park. Colocate adjacent to a future maintenance facility.

                                                                                         Need for future
                                                                                           Community
                                 Insert map showing location of project or related picture
                                                                                              park

             Estimated Project Cost (000's):                        Project Task:                Duration (Months)
             Design/Engineering                 -                   Planning/Design                        -
             ROW Acquisition            3,750,000                   Right-of-way/Utilities                 -
             Construction                       -                   Construction                           -
             Other                              -                   Total                                  -
             Total                      3,750,000

             Funding Source:                                     Ongoing Operational Impact:
             Operating Fund                        -             Personnel                          -
             Debt                          3,750,000             Supplies & Materials               -
             Grants/Other                          -             Repair & Maint.                    -
             Total                         3,750,000             Capital & Other                    -
Notes:                                                           Total                              -
Identified in 2012 Parks Master Plan. Potential funding sources include bonds, private donations, in-kind services,
certificates of obligation, general fund, park development fees.

                                                               14
City of Buda, Texas
                           Capital Improvement Program - Parks

                                          Recreation and Aquatic Center

Responsible Department:                   Parks                                                    CIP No.       P07

Financial Plan :
                   Prior                                 Projected
                   Years         19            20           21             22            23          Future        Total
                       -              -             -            -              -         75,000     8,000,000     8,075,000

Description :
The only swimming facilities in Buda are private or semi-private, located at six (6) HOA parks or the YMCA. The HOA
pools can only be used by the residents who live in those neighborhoods, and the YMCA pool is available to anyone with a
paid membership. The 2012 Parks Master Plan recommends the city should conduct a feasibility study prior to FY 2022 to
determine the community's interest in a facility and potential locations. PRIORITY: medium - target level of service - 1 pool
for every 20,000 residents

                                  Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                 Duration (Months)
             Design/Engineering               455,000                Planning/Design                         -
             ROW Acquisition                        -                Right-of-way/Utilities                  -
             Construction                   3,420,000                Construction                            -
             Other                                  -                Total                                   -
             Total                          3,875,000

             Funding Source:                                            Ongoing Operational Impact:
             Operating Fund                    75,000                   Personnel                       -
             Debt                           3,800,000                   Supplies & Materials            -
             Grants/Other                           -                   Repair & Maint.                 -
             Total                          3,875,000                   Capital & Other                 -
Notes:                                                                  Total                           -
Initial cost would be to conduct a feasibility study and to develop schematic plans. Full design and construction would
occur in the future. This project could be included in a future bond election.

                                                                15
City of Buda, Texas
                           Capital Improvement Program - Parks

                                          Bradfield Park Improvements

Responsible Department:                  Parks                                                   CIP No.       P08

Financial Plan :
                   Prior                                Projected
                   Years        19            20           21             22            23         Future        Total
                       -             -         50,000           -              -             -             -         50,000

Description :
Installation of ADA accessible restrooms for trail and park users at Bradfield Park. Cost based on estimate of constructing
in-house or relocating a composting facility over from Stagecoach Park.

                                 Insert map showing location of project or related picture

             Estimated Project Cost:                                Project Task:                Duration (Months)
             Design/Engineering                    -                Planning/Design                        4
             ROW Acquisition                       -                Right-of-way/Utilities                 -
             Construction                     50,000                Construction                           3
             Other                                 -                Total                                  7
             Total                            50,000

             Funding Source:                                 Ongoing Operational Impact:
             Operating Fund                        -         Personnel                           -
             Debt                                  -         Supplies & Materials                -
             Grants/Other                     50,000         Repair & Maint.                1,300
             Total                            50,000         Capital & Other                     -
Notes:                                                       Total                          1,300
Funding source is the Park Fund fund balance. The fund balance is comprised of previous developer paid parkland
development fees.

                                                               16
City of Buda, Texas
                           Capital Improvement Program - Parks

                                      City Park Trails and Disc Golf Course

Responsible Department:                   Parks                                                   CIP No.           P09

Financial Plan :
                   Prior                                 Projected
                   Years         19            20           21             22            23         Future            Total
                       -              -             -            -        150,000             -             -             150,000

Description :
Due to Budget cuts, both trails and the disc golf course in the schematic design of City Park were eliminated. Texas Parks
and Wildlife offers reimbursable grants toward Trail Development to assist in offsetting costs. Connection of the trail would
be at Buda Elementary and FM 967. Design and installation of the first disc golf course for the City would be an additonal
site amenity that would complement the park. Local Disc Golf Clubs would be willing to assist in design and installation.
Disc Golf-$15,000, Trails-2,500 linear feet (6' concrete)=$105,000

                                  Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering               10,000                 Planning/Design                        6
             ROW Acquisition                       -                 Right-of-way/Utilities                 -
             Construction                    140,000                 Construction                           6
             Other                                 -                 Total                                12
             Total                           150,000

             Funding Source:                                        Ongoing Operational Impact:
             Operating Fund                   30,000                Personnel                                   -
             Debt                                  -                Supplies & Materials                        -
             Grants/Other                    120,000                Repair & Maint.                             -
             Total                           150,000                Capital & Other                             -
Notes:                                                              Total                                       -
Possible funding sources include a Texas Parks and Wildlife grant along with Parks Capital Fund.

                                                                17
City of Buda, Texas
                           Capital Improvement Program - Parks

                                         Green Meadows Park Improvements

Responsible Department:                    Parks                                                  CIP No.       P10

Financial Plan :
                   Prior                                Projected
                   Years        19             20          21             22             23         Future        Total
                       -             -        125,000           -              -              -             -         125,000

Description :
Green Meadows Park is in need of an additonal large pavillion due to the addition of the splash pad and the need for more
shade. An expansion of the parking lot, along with picnic tables and additional shade structures would complement the
park. Basketball court needs resurfacing and expansion. Add a shade structure to the current basketball court to make it a
pavilion and install a larger basketball court.

                                 Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering                10,000                Planning/Design                        3
             ROW Acquisition                        -                Right-of-way/Utilities                 -
             Construction                     115,000                Construction                           3
             Other                                  -                Total                                  6
             Total                            125,000

             Funding Source:                                         Ongoing Operational Impact:
             Operating Fund                         -                Personnel                              -
             Debt                                   -                Supplies & Materials                   -
             Grants/Other                     125,000                Repair & Maint.                        -
             Total                            125,000                Capital & Other                        -
Notes:                                                               Total                                  -
Due to installation of the splash pad in 2018, Funding is being sought in 2019. Funding is from the Parks Capital Fund.

                                                               18
City of Buda, Texas
                           Capital Improvement Program - Parks

                                           Stagecoach Park Improvements

Responsible Department:                    Parks                                                     CIP No.           P11

Financial Plan :
                   Prior                                  Projected
                   Years          19            20           21              22             23         Future            Total
                       -               -             -        105,000             -              -             -             105,000

Description :
Stagecoach Park, host site of the Annual Trail of Lights, is in need of electrical upgrades in order to avoid costly rental fees
for the annual festival ($12,500 annually). Trail improvements, including drainage improvements, are also needed to
ensure a safe trail system for users to enjoy.

                                   Insert map showing location of project or related picture

              Estimated Project Cost:                                   Project Task:                Duration (Months)
              Design/Engineering                10,500                  Planning/Design                        3
              ROW Acquisition                        -                  Right-of-way/Utilities                 -
              Construction                      94,500                  Construction                           6
              Other                                  -                  Total                                  9
              Total                            105,000

              Funding Source:                                           Ongoing Operational Impact:
              Operating Fund                         -                  Personnel                                  -
              Debt                                   -                  Supplies & Materials                       -
              Grants/Other                     105,000                  Repair & Maint.                            -
              Total                            105,000                  Capital & Other                            -
Notes:                                                                  Total                                      -
Possible funding source is the Parks Capital Fund.

                                                                  19
Municipal Facilities Capital Improvement Program
                                                                              FY 2019 - 2023

Facilities projects will be funded through a number of funding sources including General Obligation debt, cash, grants, and other sources as available.

Sources of Funding                                                Prior                                                                 2019-23
                                                                  Years         19         20         21         22           23         Total

          Operating Fund                                                  -     75,000          -          -           -           -       75,000
          Fund Balance                                                    -           -         -          -           -           -              -
          Debt Proceeds                                                   -           -         -          -   3,250,000     250,000    3,500,000
          Other                                                           -           -   400,000          -           -           -      400,000

Total                                                                     -     75,000    400,000          -   3,250,000     250,000    3,975,000

Uses of Funds                                                     Prior
                                                                  Years         19         20         21         22           23         Future        Total

Facility Projects:
  F01     Public Works Facility                                           -           -         -          -   3,250,000     250,000    3,250,000     6,750,000
  F02     Convention Center                                               -           -         -          -           -            -             -             -
  F03     Visitor's Center and Main Street Office Remodel                 -     75,000    400,000          -           -           -              -       475,000

Total Uses of Funds                                                       -     75,000    400,000          -   3,250,000     250,000    3,250,000     7,225,000

Cumulative Balance
Sources Over/(Under) Uses                                                             -         -          -           -           -

                                                                                     20
City of Buda, Texas
                           Capital Improvement Program - Facilities

                                               Public Works Facility

Responsible Department:                  Public Works                                             CIP No.       Fac01

Financial Plan :
                   Prior                                Projected
                   Years        19            20           21             22             23         Future        Total
                       -             -             -             -      3,250,000       250,000     3,250,000     6,750,000

Description :
Public Works is outgrowing its current facility located on Garison Rd. In order to keep pace with the growth and to provide
room for future expansion, Public Works would like to purchase a 20 acre site. Initially, an 8,400 sf (42' x 200')
maintenance building would be constructed on the site to provide room office space (3600 sf) and maintenance bay space
(4800 sf). The maintenance bay would allow 6 vehicle maintenance bays and 2 large equipment maintenance bays. The
site would provide ample room for equipment and inventory/supply storage. The site could also contain an impoundment
lot for the Police Department. Colocate adjacent to Future Eastside Park. Phasing is based on property acquisition, design,
and construction in separate consecutive years.

                                 Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering              250,000                 Planning/Design                        8
             Property Acquisition          3,250,000                 Right-of-way/Utilities                 8
             Construction                  2,500,000                 Construction                         12
             Other                           750,000                 Total                                28
             Total                         6,750,000

             Funding Source:                                        Ongoing Operational Impact:
             Operating Fund                        -                Personnel                             -
             Debt                          6,750,000                Supplies & Materials                  -
             Grants/Other                          -                Repair & Maint.               15,000
             Total                         6,750,000                Capital & Other                       -
Notes:                                                              Total                         15,000
The current facility and site is lacking expansion space due to growth of the Parks and Recreational facility. The current
site, combined with the P&R and PW, lacks employee parking, lacks adequate site space for housing department trucks,
heavy construction equipment, material and parts storage and site area laydown for materials. The current facilities
building also lacks office space expansion for staff.

                                                            21
City of Buda, Texas
                           Capital Improvement Program - Facilities

                                                  Convention Center

Responsible Department:                  Administration                                            CIP No.       Fac02

Financial Plan :
                   Prior                                  Projected
                   Years        19           20              21            22             23         Future        Total
                       -             -            -               -             -              -             -             -

Description :
The Buda EDC and the Tourism Department conducted a study to determine the feasibility of constructing and operating a
convention center. Initial market research indicates that a 22,000 square foot convention center would be viable in Buda.
The study was conducted by CBRE in 2017. The study evaluated a variety of locations in the Buda area. Funding for the
project is unknown as a public-private partnership would be the preferred project delivery method.

             Estimated Project Cost:                                  Project Task:                Duration (Months)
             Design/Engineering                       -               Planning/Design                        -
             Property Acquisition                     -               Right-of-way/Utilities                 -
             Construction                             -               Construction                           -
             Other                                    -               Total                                  -
             Total                                    -

             Funding Source:                                        Ongoing Operational Impact:
             Operating Fund                           -             Personnel                             -
             Debt                                     -             Supplies & Materials                  -
             Grants/Other                             -             Repair & Maint.                       -
             Total                                    -             Capital & Other                       -
Notes:                                                              Total                                 -
Funding for the project would likely come from a combination of hotel tax funds and possibly an economic development
agreement with a private development group.

                                                             22
City of Buda, Texas
                           Capital Improvement Program - Facilities

                               Visitor's Center and Main Street Office Remodel

Responsible Department:                    Administration                                          CIP No.       Fac03

Financial Plan :
                   Prior                                 Projected
                   Years         19            20           21             22             23         Future        Total
                       -          75,000       400,000            -             -              -             -      475,000

Description :
This project would remodel the former Public Library for use as a Visitor's Center, Main Street office space, and community
rental space. The 5,200 square foot facility was constructed in 1993. The scope of the remodel has not yet been defined
as the City is working with an architecture class at Texas State University to develop reuse and layout ideas. The goals of
the remodel would be to create a new visitor's center, office space for Main Street and Tourism staff, and to create a multi-
functional space that can be used by staff to prepare for events and for community groups to host meetings. The remodel
could range from aesthetic improvements and upgrades to full renovation and structural modifications. Rough cost
estimate is determined based on $75 per square foot for renovations.

                                  Insert map showing location of project or related picture

             Estimated Project Cost:                                  Project Task:                Duration (Months)
             Design/Engineering                75,000                 Planning/Design                        4
             Property Acquisition                   -                 Right-of-way/Utilities                 -
             Construction                     400,000                 Construction                           6
             Other                                  -                 Total                                10
             Total                            475,000

             Funding Source:                                       Ongoing Operational Impact:
             Operating Fund                         -              Personnel                               -
             Debt                                   -              Supplies & Materials                    -
             Grants/Other                     475,000              Repair & Maint.                         -
             Total                            475,000              Capital & Other                         -
Notes:                                                             Total                                   -
No ongoing operational impact is expected as this is an existing facility. Possible funding sources include the Hotel Tax
Fund as the facility will be officing the Tourism Department.

                                                             23
Water Capital Improvement Program
                                                                                  FY 2019 - 2023

The City serves potable water to residential and non-residential customers of the City of Buda. Not all residents are provided water by the City of Buda as
Monarch and the South Buda WCID serve portions of the city. The proposed water capital projects are needed to extend services to growing areas of the city,
upsize infrastructure to increase the city's service capacity, the development of new water sources, and overall projects that improve the city's efficiency to
deliver safe and reliable water.

Sources of Funding                                                          Prior                                                                   2019-23
                                                                            Years       19          20          21           22          23          Total

        Operating Fund                                                         28,810   250,000      250,000     425,000      250,000     250,000    1,425,000
        Fund Balance                                                                -         -            -           -            -           -            -
        Utility Debt                                                        1,896,000         -    1,684,500   5,682,000    3,817,631           -   11,184,131
        Impact Fees                                                                 -   109,533      195,493     410,767            -   1,253,081    1,968,874
        Other                                                                       -         -            -           -            -           -            -

Total                                                                       1,924,810   359,533    2,129,993   6,517,767    4,067,631   1,503,081   14,578,005

Uses of Funds                                                               Prior
                                                                            Years       19          20          21           22          23         Future         Total

Water Projects:
 W01     ASR / Trinity Well                                                 1,896,000         -            -   1,876,000            -           -             -    3,772,000
 W02     Alliance Regional Water Authority Phase 1B Project                   28,810    109,533     195,493     410,767      515,631     753,081    12,519,823    14,533,138
 W03     Water Master Plan                                                          -         -            -    175,000             -           -             -     175,000
 W04     East IH-35 12" Transmission Main Loop                                      -         -     477,000    1,590,000            -           -             -    2,067,000
 W05     Advanced Metering Infrastructure (AMI) System                              -   250,000     250,000     250,000      250,000     250,000     1,250,000     2,500,000
 W06     Old Black Colony Elevated Storage Tank                                     -         -     603,000            -    1,272,000           -             -    1,875,000
 W07     FM 1626 12" Transmission Main Connection                                   -         -            -           -            -    500,000              -     500,000
 W08     West IH 35 Transmission Main                                               -         -     300,000            -            -           -             -     300,000
 W09     Old Black Colony Road 12" Transmission Main & Pressure Valve               -         -            -   2,592,000            -           -             -    2,592,000
 W10     Old Black Colony Ground Storage Tank & Pump Station                        -         -     304,500            -    2,030,000           -             -    2,334,500

Total                                                                       1,924,810   359,533    2,129,993   6,893,767    4,067,631   1,503,081   13,769,823    30,648,638

Total Uses of Funds                                                         1,924,810   359,533    2,129,993   6,893,767    4,067,631   1,503,081

Cumulative Balance
Sources Over/(Under) Uses                                                           -         -            -    (376,000)           -           -

                                                                                              24
City of Buda, Texas
                               Capital Improvement Program - Water

                                                      ASR / Trinity Well

Responsible Department:                     Public Works                                              CIP No.       W01

Financial Plan :
                   Prior                                   Projected
                   Years           19            20           21              22             23          Future         Total
                   1,896,000            -             -      1,876,000             -              -             -      3,772,000

Description :
Construction of a Trinity well that will allow for cycle testing during for an aquifer storage and recovery project. The well will
be sized and constructed for production capability. Temporary piping will be installed during cycle testing. Costs include the
installation of a small diameter monitor well that likely be required based on revised Barton Springs Edwards Aquifer
Conservation District (BSEACD) rules. Phase II of the project includes development of a Class D Edwards production well
and permanent pumping equipment. Phase II costs will be further refined during Phase I.

                           Raw Water
                           Storage                                           Water
                                   Insert map showing location of project or Treatment
                                                                             related picture
                                                      ASR                    Plant
                                                      Well

                                             Treated Water
                                                Storage

              Estimated Project Cost:                                    Project Task:                Duration (Months)
              Design/Engineering               499,700                   Planning/Design                      18
              ROW Acquisition                        -                   Right-of-way/Utilities                 -
              Construction                   2,665,000                   Construction                         18
              Other                            316,000                   Total                                36
              Total                          3,480,700

              Funding Source:                                          Ongoing Operational Impact:
              Operating Fund                         -                 Personnel                            -
              Debt                           3,396,000                 Supplies & Materials           20,000
              Grants/Other                           -                 Repair & Maint.                 5,000
              Total                          3,396,000                 Capital & Other                      -
Notes:                                                                 Total                          25,000
There is potential to utilize the well for Trinity production only if water quality proves to be adequate or blendable with
existing supplies. Depending on site location, land acquisition may be needed. $1,896,000 was issued in the 2017
Certificates of Obligation to fund the Phase 1 portion of the project.

                                                                   25
City of Buda, Texas
                              Capital Improvement Program - Water

                              Alliance Regional Water Authority Phase 1B Project

Responsible Department:                     Public Works                                             CIP No.       W02

Financial Plan :
                   Prior                                   Projected
                   Years          19            20            21             22             23         Future        Total
                     28,810       109,533       195,493       410,767        515,631       753,081    12,519,823    14,533,138

Description :
The Alliance Regional Water Authority is comprised of four primary entities: Buda, Kyle, San Marcos, and the Canyon
Regional Water Authority. The ARWA is developing a new groundwater supply source from the Carrizo Aquifer in Caldwell
County for its partners. Buda's retains a 5.08% interest in the ARWA project, which will be completed by 2023. This project
will provide Buda with an additional 0.68 MGD of base supply. Funding for this project will be issued through the Texas
Water Development Board's SWIFT program. The project will be constructed by the ARWA. The amounts represent the
City's debt service payments related to the project.

                                   Insert map showing location of project or related picture

             Estimated Project Cost:                                    Project Task:                Duration (Months)
             Design/Engineering                      -                  Planning/Design                        -
             ROW Acquisition                         -                  Right-of-way/Utilities                 -
             Construction                            -                  Construction                           -
             Other                          14,533,138                  Total                                  -
             Total                          14,533,138

             Funding Source:                                     Ongoing Operational Impact:
             Operating Fund                          -           Personnel                             -
             Debt                           14,533,138           Supplies & Materials                  -
             Grants/Other                            -           Repair & Maint.                       -
             Total                          14,533,138           Capital & Other                       -
Notes:                                                           Total                                 -
Project would be managed by the ARWA. City would pay its pro rata share (5.08%) related to the construction of the line.
The ARWA is pursuing funding thru the TWDB SWIFT program in order to secure low-cost financing. Debt service is
based on the 20 year repayment option.

                                                                 26
City of Buda, Texas
                           Capital Improvement Program - Water

                                                  Water Master Plan

Responsible Department:                  Engineering                                             CIP No.       W03

Financial Plan :
                   Prior                               Projected
                   Years        19           20           21             22             23         Future        Total
                       -             -            -       175,000             -              -             -         175,000

Description :
Create a long range water master plan to enable City staff to make the best informed decisions regarding development
commitments, long term CIP's, and future enhancements to water distribution system design an operation. The water
master plan will address long term needs. It will also evaluate the expansion of the recycled water service in order to
preserve the City's potable water supply.

                                Insert map showing location of project or related picture

             Estimated Project Cost:                                Project Task:                Duration (Months)
             Design/Engineering             175,000                 Planning/Design                      12
             ROW Acquisition                      -                 Right-of-way/Utilities                 -
             Construction                         -                 Construction                           -
             Other                                -                 Total                                12
             Total                          175,000

             Funding Source:                                        Ongoing Operational Impact:
             Operating Fund                 175,000                 Personnel                            -
             Debt                                 -                 Supplies & Materials                 -
             Grants/Other                         -                 Repair & Maint.                      -
             Total                          175,000                 Capital & Other                      -
Notes:                                                              Total                                -
The necessity for a long range water master plan is recognized by Planning, Engineering, and Public Works.

                                                              27
City of Buda, Texas
                           Capital Improvement Program - Water

                                     East IH-35 12" Transmission Main Loop

Responsible Department:                  Public Works                                              CIP No.       W04

Financial Plan :
                   Prior                                Projected
                   Years        19            20           21              22             23         Future        Total
                       -             -        477,000     1,590,000             -              -             -     2,067,000

Description :
This project will largely be developer installed as new development occurs in this area. Install approximately 6,114 linear
feet of 12" water line in the Buda service area on the East side of IH-35. Supports commercial growth in I-35 business
district. Project will expand flow to service future growth and provide adequate fire flow.

                                 Insert map showing location of project or related picture

             Estimated Project Cost:                                  Project Task:                Duration (Months)
             Design/Engineering              477,000                  Planning/Design                      10
             ROW Acquisition                       -                  Right-of-way/Utilities                 2
             Construction                  1,590,000                  Construction                           6
             Other                                 -                  Total                                18
             Total                         2,067,000

             Funding Source:                                              Ongoing Operational Impact:
             Operating Fund                        -                      Personnel                                 -
             Debt                                  -                      Supplies & Materials                      -
             Grants/Other                  2,067,000                      Repair & Maint.                      2,067
             Total                         2,067,000                      Capital & Other                           -
Notes:                                                                    Total                                2,067
Private development in the area is constructing much of the line. The project amount is shown in the CIP in case a portion
is not built. The City will need to analyze this project further to determine what responsibility, if any, is on the City.

                                                               28
City of Buda, Texas
                           Capital Improvement Program - Water

                               Advanced Metering Infrastructure (AMI) System

Responsible Department:                    Public Works                                             CIP No.        W05

Financial Plan :
                   Prior                                  Projected
                   Years         19            20            21             22             23         Future         Total
                       -         250,000       250,000       250,000        250,000       250,000     1,250,000      2,500,000

Description :
The City's automated meter reading (AMR) system needs to be replaced. The current system uses outdated technology
that the vendor no longer supports and system performance has diminished. Advanced Metering Infrastructure (AMI) is
new technolgoy with more features for both the utility and customer. In 2018, the City began working with Siemens
Industries to evaluate the cities metering technology. Siemens is assisting the City with evaluation of different products,
project financing, and implementation. Initial cost estimates to replace the City's system is approximately $2.5 million which
could be financed over multiple years.

              Estimated Project Cost :                                 Project Task:                Duration (Months)
              Design/Engineering                    -                  Planning/Design                        3
              ROW Acquisition                       -                  Right-of-way/Utilities                 -
              Construction                  2,500,000                  Construction                           6
              Other                                 -                  Total                                  9
              Total                         2,500,000

              Funding Source:                                      Ongoing Operational Impact:
              Operating Fund                        -              Personnel                                   -
              Debt                                  -              Supplies & Materials                        -
              Grants/Other                  2,500,000              Repair & Maint.
              Total                         2,500,000              Capital & Other                             -
Notes:                                                             Total                                       -
Financing or other short term lending possible through a capital lease or lease to own option. Ongoing         expense is the
annual hosting costs associated with the system.

                                                                29
City of Buda, Texas
                           Capital Improvement Program - Water

                                    Old Black Colony Elevated Storage Tank

Responsible Department:                   Public Works                                              CIP No.       W06

Financial Plan :
                   Prior                                  Projected
                   Years         19             20           21             22             23         Future         Total
                       -              -        603,000            -       1,272,000             -             -     1,875,000

Description :
Construction of an elevated storage tank at the corner of Old Black Colony (OBC) and FM 1626. This tank will be located
at the entry point for HCPUA water and is necessary to keep up with demand and pressure for a growing system. This tank
is sized at 0.5 MGD but results of a water master plan may indicate that a larger tank is needed. City would need to
acquire approximately 1 acre of land for this project. The project will include the installation of approximately 450 lf of 24"
waterline to connect the tank to the Mid-Pressure Zone. Upsize approximately 464 lf of existing 12" line from Whispering
Hollow to the OBC Elevated Storage tank to a 16" line. Increase to a .5 mgd? What is actually needed?

                                  Insert map showing location of project or related picture

              Estimated Project Cost:                                  Project Task:                Duration (Months)
              Design/Engineering              303,000                  Planning/Design                        6
              ROW Acquisition                 300,000                  Right-of-way/Utilities                 -
              Construction                  1,272,000                  Construction                           8
              Other                                 -                  Total                                14
              Total                         1,875,000

              Funding Source:                                         Ongoing Operational Impact:
              Operating Fund                        -                 Personnel                           -
              Debt                          1,875,000                 Supplies & Materials                -
              Grants/Other                          -                 Repair & Maint.                 5,625
              Total                         1,875,000                 Capital & Other                     -
Notes:                                                                Total                           5,625
ROW acquisition costs are unknown at this time. Debt service could be repaid utilizing impact fees. CIP project combines
the following projects identified in 2017 K. Friese study: OBC Elevated Storage Tank, Upsize Pipe from Whispering Hollow
to OBC Pump Station Site, and OBC EST to Mid-Zone Connection. Project should also be coordinated with the OBC Road
Ground Storage Tank and Pump Station project.

                                                                 30
City of Buda, Texas
                           Capital Improvement Program - Water

                                 FM 1626 12" Transmission Main Connection

Responsible Department:                   Public Works                                            CIP No.           W07

Financial Plan :
                   Prior                                 Projected
                   Years         19           20            21            22             23         Future            Total
                       -              -            -            -              -        500,000             -             500,000

Description :
Install approximately 1,475 linear feet of 12" water line along FM 1626 to connect Elm Grove Elementary School to future
Old Black Colony storage tank and pump station. The project creates redundancy and improves distribution system
operation. Timing depends on construction of Old Black Colony Pump Station and elevated tank project.

                                 Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering              116,000                 Planning/Design                        -
             ROW Acquisition                       -                 Right-of-way/Utilities                 -
             Construction                    295,000                 Construction                           -
             Other                            89,000                 Total                                  -
             Total                           500,000

             Funding Source:                                         Ongoing Operational Impact:
             Operating Fund                        -                 Personnel                                  -
             Debt                                  -                 Supplies & Materials                       -
             Grants/Other                    500,000                 Repair & Maint.                            -
             Total                           500,000                 Capital & Other                            -
Notes:                                                               Total                                      -
Funding source is Impact Fees.

                                                               31
City of Buda, Texas
                           Capital Improvement Program - Water

                                          West IH 35 Transmission Main

Responsible Department:                   Public Works                                            CIP No.         W08

Financial Plan :
                   Prior                                 Projected
                   Years         19            20           21             22            23         Future            Total
                       -              -       300,000            -              -             -              -          300,000

Description :
Hays Consolidated ISD (HCISD) is constructing a new elementary school along Old San Antonio Road and will be
installing a waterline to serve the new site. A potential CIP would be to upsize the line needed to serve the school site in
order to serve future development along the area. The size and cost of the line required to serve the school is not yet
known. The line is estimated to be 4,422 linear feet in length.

                                  Insert map showing location of project or related picture

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering                    -                 Planning/Design                        -
             ROW Acquisition                       -                 Right-of-way/Utilities                 -
             Construction                    300,000                 Construction                         12
             Other                                 -                 Total                                12
             Total                           300,000

             Funding Source:                                        Ongoing Operational Impact:
             Operating Fund                        -                Personnel                                   -
             Debt                                  -                Supplies & Materials                        -
             Grants/Other                    300,000                Repair & Maint.                       1,500
             Total                           300,000                Capital & Other                             -
Notes:                                                              Total                                 1,500
The total estimated cost of the project is $1,500,000. The City's cost could be significantly less if a   portion of the line is
installed by HCISD. City portion can be paid out of collected impact fees or possibly funds from          the Buda Economic
Development Corporation.

                                                                32
City of Buda, Texas
                            Capital Improvement Program - Water

                     Old Black Colony Road 12" Transmission Main & Pressure Valve

Responsible Department:                   Public Works                                               CIP No.      W09

Financial Plan :
                   Prior                                 Projected
                   Years         19            20            21              22             23         Future       Total
                       -              -             -       2,592,000             -              -                  2,592,000

Description :
The project will loop the FM 1626 12" diameter transmission to the RM 967 12" diameter transmission main near the
intersection of Old Black Colony Road and Cole Springs Road. The project will also include a Pressure Reducing Valve
(PRV) to balance pressure planes. The tranmission main will convey potable water delivered from the ARWA delivery point
back thorugh the City's ditribution network along Old Black Colony Road. This project will provide operational flexibility and
additional transmission capacity to serve future growth in the Middle and Low Pressure Zones.

                                  Insert map showing location of project or related picture

             Estimated Project Cost:                                    Project Task:                Duration (Months)
             Design/Engineering               599,000                   Planning/Design                        9
             ROW Acquisition                        -                   Right-of-way/Utilities                 -
             Construction                   1,533,000                   Construction                           9
             Other                            460,000                   Total                                18
             Total                          2,592,000

             Funding Source:                                           Ongoing Operational Impact:
             Operating Fund                         -                  Personnel                              -
             Debt                           2,592,000                  Supplies & Materials                   -
             Grants/Other                           -                  Repair & Maint.                    2,592
             Total                          2,592,000                  Capital & Other                        -
Notes:                                                                 Total                              2,592
Impact fees may be used to offset a portion of the City's annual debt service requirement.

                                                                33
City of Buda, Texas
                            Capital Improvement Program - Water

                           Old Black Colony Ground Storage Tank & Pump Station

Responsible Department:                 Public Works                                             CIP No.       W10

Financial Plan :
                   Prior                               Projected
                   Years       19            20            21            22             23         Future        Total
                       -            -        304,500           -       2,030,000             -             -     2,334,500

Description :
Project includes a new 1.44 MGD pump station to serve the City's Middle Pressure Zone. The proposed 0.5 MG gorund
storage tank will receive supply from the ARWA transmission main, which must be completed before this project can be
completed.

                                Insert map showing location of project or related picture

             Estimated Project Cost:                                Project Task:                Duration (Months)
             Design/Engineering             304,500                 Planning/Design                      12
             ROW Acquisition                      -                 Right-of-way/Utilities                 -
             Construction                 1,624,000                 Construction                         12
             Other                          406,000                 Total                                24
             Total                        2,334,500

             Funding Source:                                        Ongoing Operational Impact:
             Operating Fund                       -                 Personnel                             -
             Debt                         2,334,500                 Supplies & Materials                  -
             Grants/Other                         -                 Repair & Maint.                   7,004
             Total                        2,334,500                 Capital & Other                       -
Notes:                                                              Total                             7,004

                                                             34
Wastewater Capital Improvement Program
                                                                                          FY 2019 - 2023

The City provides retail wastewater services to a portion of Buda and wholesale service to areas of Buda that are served by other water providers. The city has
previously invested in expansion of wastewater services through expansion of the wastewater treatment plant. That project was funded in the Fiscal Year 2018 budget.
Construction will be ongoing through Fiscal Year 2020.

Sources of Funding                                                                       Prior                                                                    2019-23
                                                                                         Years             19         20         21         22         23          Total

        Operating Fund                                                                     995,880          154,950    50,000           -    50,000           -     254,950
        Fund Balance                                                                             -                -   203,656     203,656         -           -     407,312
        Utility Debt                                                                    26,193,164                -         -   1,472,000   421,500   2,809,500   4,703,000
        Impact Fees                                                                              -        1,480,050         -           -         -           -   1,480,050
        Other                                                                                    -                -   490,000           -         -           -     490,000

Total                                                                                   27,189,044        1,635,000   743,656   1,675,656   471,500   2,809,500   7,335,312

Uses of Funds                                                                            Prior
                                                                                         Years             19         20         21         22         23         Future         Total

Wastewater Projects:
WW00 Wastewater Treatment Plant Phase III Expansion & New Effluent Discharge Main       25,319,164                -         -           -         -           -             -   25,319,164
 WW01     Meadows at Buda Lift Station Expansion & New Force Main                          193,000                -         -           -         -           -             -      193,000
 WW02     Sportsplex Sewer Line Upsize                                                    450,000                 -         -           -         -           -             -     450,000
 WW03     Wastewater Master Plan                                                          150,000                 -         -           -         -           -             -     150,000
 WW04     Wastewater Manhole Rehabilitation                                               202,880                 -         -           -         -           -             -     202,880
 WW06     Garison Road Gravity Interceptor Replacement                                    874,000                 -         -           -         -           -             -     874,000
 WW07     South Loop 4 Lift Station Replacement & Gravity Interceptor Extension                  -        1,500,000         -           -         -           -             -    1,500,000
 WW08     Decommission Old Night Hawk Lift Station                                               -         135,000          -           -         -           -             -     135,000
 WW09     Northeast IH-35 12" Gravity Interceptor                                                -                -   490,000           -         -           -             -     490,000
 WW10     Northwest IH-35 15" Gravity Interceptor                                                -                -         -   1,472,000         -           -             -    1,472,000
 WW11     Bradfield/Lifschutz 12"/16"/18" Gravity Interceptor Expansion                          -                -         -           -   421,500   2,809,500             -    3,231,000
 WW12     Direct Potable Reuse (DPR) Feasibility Study                                           -                -   203,656    203,656          -           -             -     407,312
 WW13     Garlic Creek Basin Inflow & Infiltration Study                                         -                -    50,000           -         -           -             -      50,000
 WW14     Edwards Aquifer Recharge Zone Integrity Testing & Rehabilitation                       -                -         -           -    50,000           -             -      50,000

Total                                                                                   27,189,044        1,635,000   743,656   1,675,656   471,500   2,809,500             -   34,524,356

Total Uses of Funds                                                                     27,189,044        1,635,000   743,656   1,675,656   471,500   2,809,500

Cumulative Balance
Sources Over/(Under) Uses                                                                        -                -         -           -         -           -

                                                                                                     35
City of Buda, Texas
                            Capital Improvement Program - Wastewater

         Wastewater Treatment Plant Phase III Expansion & New Effluent Discharge Main

Responsible Department:                   Public Works                                            CIP No.       WW00

Financial Plan :
                   Prior                                 Projected
                   Years         19           20            21            22             23         Future        Total
               25,319,164             -            -            -              -              -             -    25,319,164

Description :
Previous budgets included funds to expand the City's current wastewater treatment plant from 1.5 mgd to 3.5 mgd. The
expansion is needed in order to provide service to the City's rapidly growing customer base. The project will more than
double the daily capacity and max out the expansion at the current location. The project also includes roughly 6,000 linear
feet of a 20" force main that will carry the treated discharge to the Plum Creek basin. The construction is pending the
approval of the TPDES permit with TCEQ. Construction is expected to take approximately 18 months. Construction is
anticipated to begin in summer 2018 and conclude in 2020. Bonds were issued in 2017 to finance the project.

             Estimated Project Cost:                                 Project Task:                Duration (Months)
             Design/Engineering                    -                 Planning/Design                      18
             ROW Acquisition                       -                 Right-of-way/Utilities                 5
             Construction                 25,319,164                 Construction                         18
             Other                                 -                 Total                                41
             Total                        25,319,164

             Funding Source:                                            Ongoing Operational Impact:
             Operating Fund                        -                    Personnel                              -
             Debt                         25,319,164                    Supplies & Materials                   -
             Grants/Other                          -                    Repair & Maint.                        -
             Total                        25,319,164                    Capital & Other                        -
Notes:                                                                  Total                                  -
The ongoing operational impact will not change initially. Additions will be the result of new wastewater flows caused by new
growth. AECOM is the lead engineer for the project design. Walker Partners Engineering will provide inspection and owner
representation throughout construction.

                                                               36
City of Buda, Texas
                              Capital Improvement Program - Wastewater

                        Meadows at Buda Lift Station Expansion & New Force Main

Responsible Department:                    Public Works                                            CIP No.       WW01

Financial Plan :
                   Prior                                  Projected
                   Years          19           20            21            22             23         Future        Total
                    193,000            -            -           -               -              -             -     193,000

Description :
The existing lift station (LS) within the Meadows at Buda subdivision serves the area south of Robert S Light Boulevard
and west of IH-35, as well as development along Hillside Terrace. South Buda WCID #1 will be constructing a new wet
well and a new 10" diameter force main (FM) to increase capacity. In addition to committed wastewater LUEs for the
South Buda WCID #1 service territory, the City is experiencing growth that requires wastewater pass through to the
Meadows at Buda LS. The City would be required to purchase a pro-rata share of the LS and FM improvements to
accommodate future needed pass through flow capacity. The proposed CIP includes both the FY 18 proposed interim
improvements & a pro-rata share (15% estimate) of the facility expansion.

             Estimated Project Cost:                                  Project Task:                Duration (Months)
             Design/Engineering                73,000                 Planning/Design                        -
             ROW Acquisition                        -                 Right-of-way/Utilities                 -
             Construction                     617,500                 Construction                         12
             Other                                  -                 Total                                12
             Total                            690,500

             Funding Source:                                          Ongoing Operational Impact:
             Operating Fund                   651,900                 Personnel                            -
             Debt                                   -                 Supplies & Materials       TBD
             Impact Fees                       38,600                 Repair & Maint.            TBD
             Total                            690,500                 Capital & Other                      -
Notes:                                                                Total                                -
Project will involve existing City-owned facilitates. Maximum lift station flow is limited to the ultimate capacity of the
existing 8" diameter wastewater force main serving the lift station. $193,000 budgeted in FY18 but project is not expected
to begin until FY19.

                                                                37
City of Buda, Texas
                              Capital Improvement Program - Wastewater

                                           Sportsplex Sewer Line Upsize

Responsible Department:                    Public Works                                            CIP No.       WW02

Financial Plan :
                   Prior                                  Projected
                   Years          19           20            21            22             23         Future        Total
                    450,000            -            -           -               -              -             -     450,000

Description :
A wastewater model was developed in 2012. The model identified that the existing 8" PVC line to a 12" line between
Dahlstrom Middle School and FM 1626 could surcharge under existing and future peak wet weather conditions. Adding to
the surcharging is the growth along with another school coming on line.

             Estimated Project Cost:                                  Project Task:                Duration (Months)
             Design/Engineering                67,500                 Planning/Design                      12
             ROW Acquisition                        -                 Right-of-way/Utilities                 -
             Construction                     382,500                 Construction                           -
             Other                                  -                 Total                                12
             Total                            450,000

             Funding Source:                                         Ongoing Operational Impact:
             Operating Fund                         -                Personnel                              -
             Debt                                   -                Supplies & Materials                   -
             Grants/Other                     450,000                Repair & Maint.                        -
             Total                            450,000                Capital & Other                        -
Notes:                                                               Total                                  -
This project is recommended to be paid for by impact fees and fund balance. Existing main can be left in place and
converted to a reuse line. Binkley Barfield is engineering the project. Construction is expected to begin in late FY18 and
into FY19.

                                                                38
City of Buda, Texas
                              Capital Improvement Program - Wastewater

                                              Wastewater Master Plan

Responsible Department:                    Public Works                                            CIP No.           WW03

Financial Plan :
                   Prior                                  Projected
                   Years          19           20            21            22             23         Future            Total
                    150,000            -            -            -              -              -             -         150,000

Description :
The development of a comprehensive wastewater master plan will enable the City to proactively plan for the growth and
expansion of its wastewater service area. One of the goals of the master plan will be to evaluate the drainage basins and
the ability to decommission lift stations in favor of gravity interceptors.

                                  Insert map showing location of project or related picture

             Estimated Project Cost:                                  Project Task:                Duration (Months)
             Design/Engineering               150,000                 Planning/Design                      12
             ROW Acquisition                        -                 Right-of-way/Utilities                 -
             Construction                           -                 Construction                           -
             Other                                  -                 Total                                12
             Total                            150,000

             Funding Source:                                          Ongoing Operational Impact:
             Operating Fund                   150,000                 Personnel                                  -
             Debt                                   -                 Supplies & Materials                       -
             Grants/Other                           -                 Repair & Maint.                            -
             Total                            150,000                 Capital & Other                            -
Notes:                                                                Total                                      -
Project funded in FY18 Budget.