Antigen Rapid Test (ART) Implementation at Construction Worksites Privileged/Confidential information may be contained in this presentation. Please do not circulate or reproduce without the permission of BCA.
Outline 1. Introduction to Antigen Rapid Test (ART) 2. Overview of ART Requirements 3. Progress of ART implementation at Pilot Worksites 4. Preparation and Implementation Details • Training of ART Supervisors • Setting up of ART Station • Drawing of ART Test Kits 5. Worker’s Supervised Self-Swab Journey at Construction Worksites 6. Uploading of ART Self Test Results 7. Workflow and Management of Ag-/Ag+/Re-tested Ag Invalid Case 8. Summary of Steps to Take 2 Privileged/Confidential information may be contained in this presentation. Please do not circulate or reproduce without the permission of BCA.
Introduction Of Antigen Rapid Test Rostered Routine Testing (RRT) Antigen Rapid Testing (ART) • A surveillance tool used in Construction, Marine and Process (CMP) sectors to An additional layer of risk identify cases early, isolate and contain mitigation measure to reduce risk the spread of COVID-19, as part of Safe of transmission from community Management Measures into and/or within CMP • RRT Regime since 18 May 2021 – revert worksites, so that workers can to RRT frequency of 7 or 14 days continue to work safely respectively for anyone entering worksites, regardless of vaccination status RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Should we implement ART at worksites now? • With the evolving COVID-19 situation, construction worksites can be better prepared • Developers and contractors are strongly encouraged to pilot ART implementation now, given that:- • Worksites will be given ART test kits to implement • ART supervisory training are being heavily subsidized RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Overview of ART requirements For Which worksites? For Who? How? • BCA has extended to all • Personnel entering construction • Broadly once every 3 days2 on main contractors of worksites and supply work top of existing RRT Regime ongoing construction premises • Workers will administer the ART projects, ready-mixed • Personnel Not residing in test kits through self-swabs companies and DfMA dormitories (i.e. Singaporeans / under supervision of trained suppliers to participate in permanent residents and personnel to ensure proper the pilot programme migrant workers residing in HDB Infection Prevention Controls, and private residential SMMs, and the correct use of properties) the test kits • Personnel must not display Acute • Test before entering site Respiratory Infection (ARI)1 symptoms before taking test 1 ARI symptoms refer to fever, cough, runny nose and loss of taste/smell 2 For workers not vaccinated: ART at Day 3, Day 7 and Day 11 of the 14-day RRT, cycle or Day 3 of the 7-day RRT cycle; For vaccinated workers: One ART within 14-day RRT or 7-day RRT cycle Day 1 refers to the following day of the RRT appointment RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Progress of ART Implementation at Pilot Worksites To date, more than 150 worksites are in the process of implementing ART, and 30 have started operation. We are in the process to onboard more worksites (The ART is on top of the existing RRT regime at worksites) Supervised Self-Swab Results out in 15 mins RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Overview of ART Implementation workflow Contractor enrols a few Personnel attend course personnel to attend ART 2 sessions - 3 hours each supervisor course (1 theory and 1 practical) Contractor plans site layout for ART and procure essentials Contractor sets up such as tables, chairs, PPE, hand worksite for ART What’s the sanitizers, trash bags, etc Worksite processes like commences ART to onboard Implementation ART? Contractor BCA verifies quantity HPB delivers submits order and place order with test kits to for ART test kits HPB worksite Contractor prepares nominal rolls for ART attendance eligible dates for ART, results reporting, etc RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Preparation & Implementation Details Training of ART Supervisors • Supervised self-swab on site – Contractor to send personnel for Supervisor training (guideline: 1 supervisor to supervise not more than 20 pax for self-swab) • Contractors to plan and consider the number of ART supervisors needed to oversee the self-swabbing process 8 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Preparation & Training of ART Supervisors Implementation Details • BCAA has rolled out training course to train ART Swab Supervisors • Companies can enrol staff for training ahead of ART implementation RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Preparation & Setting up of ART station Implementation Details A ART Self Swab Instruction Guide Available in different languages for contractors to display at swab site RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Preparation & Setting up of ART station Implementation Details B Selection of Site 1) Fresh air ventilation is recommended for swab sites to prevent possible concentration of aerosolised substances. Not ideal to have air-conditioning at swab sites 2) Possible swab sites: a) Outdoor spaces / fields/Outdoor Tents (Preferred) For outdoor space/fields, there should be tentages and raised platforms set up to cater for wet weather b) Indoor function spaces / canteens Although less ideal, indoor function spaces/canteens, may be used. However, the doors and windows should be opened to allow as much fresh air ventilation as possible 11 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Preparation & Setting up of ART station Implementation Details C Site Layout • Contractor should plan the site layout to set up ART stations at the site. Site layout plan must be retained on site. Refer to ART playbook for more info https://go.gov.sg/bca-mom-art-playbook. • Suggest to have two (2) queues at the site to facilitate faster entry to site:- Queue for ART Queue to enter site w/o ART Personnel on site daily & visitors who are Personnel on site daily & visitors who are: non-dorm workers falling on: • Dorm workers and; • D3/D7/D11 of RRT cycle (for non-vac) • Non-dorm workers not falling on D3/D7/D11 of RRT • D7 (for vac) cycle (for non-vac) or D7 (for vac) To distinguish between Dormitory and Non-Dormitory Workers → Use FWMOMCare and SGWorkPass Apps To distinguish visitors requiring ART → • Migrant workers : Use SGWorkPass showing last RRT swab • SCPR: Use HealthHub/Manual Search showing last RRT swab 12 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Preparation & Setting up of ART station Implementation Details C Site Layout - Generic Schematic of Swab Site (example provided by MOH) Swab Supervisor/ Staff PPE Donning Swab Supervisor/ Staff PPE Doffing Individual’s Zone Zone Individual’s Entry Point Exit Point Registration • SafeEntry • Temperature Taking • Registration Central disposal and decontamination stations (To be used if unable to dispose Tables should be placed 2m apart waste at swab station). *Number of Tables in the swabbing zone is dependent on the area of the site. To ensure that SMMs are in place at all times Swab stations (should comprise minimally of a plastic table – plastic for ease of wipe down and two pedal lid bins, one for biohazard waste and one for general waste. You may also choose to provide both tables and chairs or voting booth- like set-up for each swab station. From the infection control perspective, the lesser furniture / items there are at the site, the better, as there will be lesser items to wipe down) 13 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Preparation & Setting up of ART station Implementation Details Ensure compliance to standards/measurable D Infection Prevention & Control elements of the following 7 areas: 1. Registration area 2. Sample activity and testing area 3. Holding area (waiting area for results) 4. Conveyance of Ag+ 5. PPE & Hygiene 6. Environmental Cleanliness 7. Disposal of Infectious & Waste Materials • To be discarded as biohazardous waste, to be collected by a licensed biohazardous waste disposal contractor or; • Disposed as general waste, subject to the following conditions: • Must be disposed of in closed bins (e.g. pedal bins) and; • Must be double-bagged and cable-tied before placing them at the disposal holding area and; • General waste in that area will be sent for incineration. 14 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Preparation & Drawing of ART Test kits Implementation Details • ART test kits will be provided by HPB for pilot sites • Contractor to order by registering interest to pilot ART at their worksites and order the ART kits via registration form https://go.gov.sg/bca-art-apply and provide the following: • Consent from developers to implement the ART at the specific worksite • Contractor should provide the estimated number of persons [same as figures provided to the GPEs) staying in non-dorm (HDB/Private Residential Premises (PRP)] who are entering the construction site, including ad-hoc personnel per day under the Quantity (Number of Persons) • Target commencement date to start ART operation at the worksite 15 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Worker’s Supervised Self-Swab Journey at Construction Worksites ~10-15 mins for total journey Green Zone Yellow Zone Red Zone 1 2 3 When ready, worker will proceed for Worker arrives Temperature screening and registration, verification of personal TT SafeEntry check-in done1 information Note: 1. If individual has ARI- symptoms, on-ground staff to direct worker to nearest SASH-PHPC for ART-PCR swab test (as per workflow Test Kit to be left Worker will be for ARI-patients) 6 Worker enter worksite 5 at Result table for 4 directed to the 2. If Ag+, the Ag+ workflow to if test result is Ag- 15 – 30mins to supervised self-swab kick-in analyse for results ART station 16 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Uploading of ART Self Test Results Who to Upload • ART Supervisor / Main contractor’s Point Of Contact (POC) When to Upload • Immediately after completion of testing for the day Where and How to Upload Swab Registration System (SRS) BCA’s FormSG HPB’s User Guide to upload ART Tests (using excel) to SRS, Daily update of ART results to BCA (not required if there is will be provided to employers no ART operation for the day) via go.gov.sg/dailyartreport RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Workflow for Ag-/Ag+/Re-tested Ag Invalid Worker arrives at worksite for ARI Symptoms ART self swab DETECTED Worker should consult a doctor for medical No ARI Symptoms treatment immediately (per usual ARI workflow) Worker undergo self swab and wait for results 2nd ART Swab test is Invalid1 Ag+ (Positive) / Ag Invalid Re-tested Ag Ag- (Negative) 1st test Invalid Worker inform Employer/Supervisor on result Ag+ Worker to be Worker proceeds isolated at site. to work and request for new test kit No ARI ARI Symptoms Symptoms Employer/Supervisor Worker to self-isolate Employer to issue Employer DETECTED PCR (C-) to submit all results to at own place of referral note and arrange arranges SRS/Sector Leads residence until PCR private transport2 to CMTG results return. SASH PHPC for conveyance3 Public Health PCR If worker is unable to confirmatory PCR test to SIF for Actions Commence (C+) self-isolate at home, • Worker to bring NRIC isolation and 1 Only workers with two Ag invalid results would be treated as Ag+. SASH PHC will help to and referral note confirmatory Workers are to be issued with the referral note for confirmatory PCR swabs. arrange for CMTG (signed by Employer) 2 To be conveyed via a private transport (e.g. car / taxi) with windows wind PCR test conveyance to SIF for verification down. 3 Case Management Task Group (CMTG) can be contacted at 6435-4060 to 18 help arrange for conveyance of the worker to a Swab Isolation Facility (SIF) RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Management of an Ag+/Re-tested Ag Invalid Worker 1) In the case that an Ag+/Re-tested Ag Invalid worker is detected, the worker should be isolated at site and his/her employer should be informed. Main Con POC/ART Supervisor/Employers should ensure that all Ag+ individuals go for a confirmatory PCR swab, and inform BCA of the Ag+ case vis go.gov.sg/dailyartreport 2) For SASH PHPCs, workers/employers must call the clinic to make an appointment and confirm that they are able to obtain a confirmatory PCR test during their visit, before heading down to the clinic. The list of SASH PHPCs can be found at http://phpc.gov.sg. 3) Main Con POC/ART Supervisor/Employer will be required to: a. Have sight over the worker’s Ag+/Re-tested Ag invalid results (but not necessary for the employer to retain the photos of worker’s test kit results and ID) b. Issue the “Notification of Positive / Invalid COVID-19 ART Result” to individuals – hardcopy or digital copy c. Inform worker of his/her legal requirement to go for a confirmatory PCR test and self-isolate until they receive his/her PCR results d. Issue him/her a PCR referral note (signed by ART provider/employer) – hardcopy or digital copy 19 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Management of an Ag+/Re-tested Ag Invalid Worker 3) The Ag+/Re-tested Ag Invalid worker should travel via private transport (car or taxi) with the windows wound down (switch off air conditioning). In addition, worker should wear a surgical mask and sit alone in the back seat (on the other side from driver). Seats should be wiped down at the end of the trip. 4) The following list of private transport service providers are available for booking. Transport cost would be borne by the worker/employer. a. Employers/workers are required to inform the hotline operator that the worker is going to a SASH PHPC for his swab test. b. For booking through mobile app, employers/workers must key “SHN” in the chat/note/comment box or check the SHN checkbox (if provided within the app). S/N Service Provider Contact Number / Mobile Application Estimated Charges ComfortDelGro Taxi (Comfort & 1 6333 1133 or via ComfortDelGro app CityCab taxis) 2 Trans-Cab 6213 0997 Booking fee (between $2.30 to $4.50) 3 SMRT 6477 5971 on top of taxi metered fare 4 Prime 6776 7553 5 Premier 6681 9462 6 GrabSHN, Go-Jek, Ryde, MVL(TADA) Via respective providers’ app Flat fare based on App 20 RESTRICTED. Do not circulate to external parties without BCA’s prior consent
Start Today To kick start the ART implementation, main contractor of the worksites can take the following steps concurrently (not necessary to be sequential): Step 1: Apply to participate in pilot ART at worksites via https://go.gov.sg/bca-art-apply Step 2: Enrol supervisors for ART training via https://go.gov.sg/bcaa-art-training Step 3: Prepare site layout plan (to be retained on site) Click here to download ART playbook https://go.gov.sg/bca-mom-art-playbook for more info 21 RESTRICTED. Do not circulate to external parties without BCA’s prior consent