Accord Technique No 4, CLIC - G. Geschonke CERN, Geneva, Switzerland White paper CSP 09_07_2009 G.Geschonke, CERN Indico

Page created by Edna Ross
 
CONTINUE READING
Accord Technique No 4, CLIC

      G. Geschonke
 CERN, Geneva, Switzerland

     White paper CSP 09_07_2009 G.Geschonke,   1
                      CERN
The full CLIC scheme
                 326 klystrons                                                                                              326 klystrons
                 33 MW, 139 µs                                                                                              33 MW, 139 µs
                                                                           combiner rings
                       drive beam accelerator                                     Circumferences
                                                                                                               drive beam accelerator
                         2.38 GeV, 1.0 GHz                                        delay loop 72.4 m              2.38 GeV, 1.0 GHz
                                                                                       CR1 144.8 m
                                 1 km                                                  CR2 434.3 m                       1 km
                                                   delay                                              delay
                                                   loop          CR2              CR2                 loop
                                                           CR1                               CR1
                                                                                                       decelerator, 24 sectors of 876 m

                                                             BDS             BDS
   BC2                                                                     2.75 km                                                         BC2
                                                           2.75 km
    245m                                                                                                                                  245m
                                                      km             IP
 TA        e-   main linac , 12 GHz, 100 MV/m , 21.02                                                    e+ main linac                       TA
R=120m                                                                                                                                     R=120m
                                   48.3 km

      CLIC 3 TeV                                                          booster linac,
                                                                          9 GeV

                                                                     BC1
                                  e- injector                                                         e+ injector,
                                   2.4 GeV            e-      e-
                                                                            e+         e+              2.4 GeV                    Not to scale!
                                                     PDR      DR                     PDR
                                                                            DR
                                                     365m    365m                    365m
                                                                           365m

                                                White paper CSP 09_07_2009 G.Geschonke,                                                             2
                                                                 CERN
World-wide CLIC&CTF3 Collaboration
                    http://clic-meeting.web.cern.ch/clic-meeting/CTF3_Coordination_Mtg/Table_MoU.htm

                                         32 Institutes involving 21 funding agencies from 17 countries
Ankara University (Turkey)    Helsinki Institute of Physics (Finland) JINR (Russia)                       Patras University (Greece)
Argonne National Lab. (USA)   IAP (Russia)                             Karlsruhre University (Germany)    Polytech. University of Catalonia (Spain)
Athens University (Greece)    IAP NASU (Ukraine)                       KEK (Japan)                        PSI (Switzerland)
BINP (Russia)                 INFN / LNF (Italy)                       LAL / Orsay (France)               RAL (UK)
CERN                          Instituto Fisica Corpuscular (Spain)     LAPP / ESIA (France)               RRCAT / Indore (India)
CIEMAT (Spain)                IRFU / Saclay (France)                   NCP (Pakistan)                     SLAC (USA)
Cockcroft Institute (UK)      Jefferson Lab (USA) White paper CSP 09_07_2009    G.Geschonke,
                                                                       North-West. Univ. Illinois (USA)                                       3
                                                                                                          Thrace University (Greece)
Gazi Universities (Turkey)    John Adams Institute (UK)              CERN
                                                                       Oslo University (Norway)           Uppsala University (Sweden)
Tentative long-term CLIC scenario
 Shortest, Success Oriented, Technically Limited Schedule
                           Technology evaluation and Physics assessment based on LHC results
                            for a possible decision on Linear Collider with staged construction
                                    starting with the lowest energy required by Physics

                                             2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

R&D on Feasibility Issues

Conceptual Design

R&D on Performance and Cost issues

Technical design

Engineering Optimisation&Industrialisation

Construction (in stages)
Construction Detector

                                                         Conceptual            Technical         Project               First
                                                           Design               Design
                                                                                                approval ?             Beam?
                                                          Report                Report
                                                           (CDR)                (TDR)
                                                   White paper CSP 09_07_2009                                             4
                                                      G.Geschonke, CERN
CLIC critical items

                                                 SYSTEMS                                                         Critical parameters

                                                                                                                    100 MV/m
                       Main Beam Acceleration Structures:
                                                                                                                      240 ns
                       Demonstrate nominal CLIC structures with damping features at the design
                                                                                                              < 3·10-7 BR/(pulse*m)
       Structures

                       gradient, with design pulse length and breakdown rate .
                                                                                                          RF to Beam efficiency > 30%?
                                                                                                                 136 MW, 240 ns
                       RF Power production structures:
                                                                                                              < 10-7 BR/(pulse*m)?
                       Demonstrate nominal PETS with damping features at the design power,
                                                                                                             Beam to RF efficiency >?
                       with design pulse length, breakdown rate and on/off capability
                                                                                                                 On/Off < 20 ms
       Two Beam

                       Two Beam Acceleration (TBA):                                              Two Beam Acceleration with simultaneous &
                       Demonstrate RF power production and Beam acceleration with both beams      nominal parameters as quoted above for
                       in at least one Two Beam Module equipped with all equipments                       individual components

                       Drive Beam Production                                                                  100 Amp peak current
                       - Beam generation and combination                                                12GHz bunch repetition frequency
       Drive Beam

                       - phase and energy matching                                                     0.2 degrees phase stability at 12 GHz
                       - Potential feedbacks                  Feasibility Items                              7.5 10-4 intensity stability
                       RF power generation by Drive Beam
                                                                                                            90% extraction efficiency
                       - Rf power extration
                                                                                                            Large momentum spread
                       - Beam stability
   Physics
    Beam

                       Generation and Preservation of Low Emittances                                      Emittances(nm): H= 600, V=5
                       Damping Rings, RTML and Main Linacs                                             Absolute blow-up(nm): H=160, V=15
                                                                                                        Main Linac : 1 nm vert. above 1 Hz;
   Stabili
   zation

                       Main Linac and BDS Stabilization                                             BDS: 0.15 to 1 nm above 4 Hz depending on
                                                                                                       final doublet girder implementation
                       Operation and Machine Protection
         Operation

         reliability

                       Staging of commissioning and construction                                     drive beam power of 72 MW @ 2.4 GeV
            and

                       MTBF, MTTR                                                                    main beam power of 13 MW @ 1.5 TeV
                       Machine protection with high beam power
Detector

                       Beam-Beam Background
                       Detector design and shielding compatible with breakdown generated by                   3.8 108 coherent pairs
                                                   White paper
                       beam beam effects during collisions      CSP
                                                           at high   09_07_2009 G.Geschonke, CERN
                                                                   energy                                                                       5
4.1 Participation in beam studies and
                                                     beam instrumentation for CALIFES and TBTS

                                          4.1               Work-package title              Participation in
    Work-package number                                                                     beam studies and
                                                                                            beam
                                                                                            instrumentation
                                                                                            for CALIFES and
                                                                                            TBTS

Reference                        CEA                  Wilfrid Farabolini, Roberto Corsini
institute
Time span                Start                       End
                     October 2008               September 2010
Allocated human resources         12 man.months        Allocated                                0 K€
                                                       financial
                                                       resources
                  Indicative personnel profile                           Indicative committment profile

                  Engineer         Technician         Draft man                             K    KCHF
                                                                                            €
2008              1.5                                                   2008
2009              6                                                     2009
2010              4.5                                                   2010
2011                                                                    2011
Total             12                                                    Total
                                      Milestones and Deliverables
           Date                                                  Description
October 2008                       Participation to CALIFES commissioning
September 2010                     Participation to consolidation and two-beam studies

                                            Detail description
              Provide (half of the the time) for one engineer, based at CERN, from mid 2008 to mid 2010.
The remaining time is covered by IRFU
                He will participate in beam activities (during CTF3 operation periods) and to their preparation
(during shut-down), aimed at commissioning the CALIFES probe beam linac to full specifications and at
exploitation of the probe beam in the Two-Beam Test Stand (TBTS).
               He will be involved in:
•        Reaching and quantify full beam specifications in CALIFES
•        Fully exploit installed beam diagnostics (cavity BPMs and bunch length monitoring)
•        Providing stable probe beam with good availability for two-beam studies
•        Preparing and executing beam studies involving both drive beam and probe beam (e.g. in TBTS)             On schedule as planned. Wilfrid Farabolini
                                                                                                                  is permanently at CERN. Excellent collaboration
                                                                                White paper CSP 09_07_2009 G.Geschonke, CERN                                   6
Klystron and BOC
                                           Califes

                                                                          Photo Injector
                            waveguide RF distribution

    Accelerating sections                                          RF deflector for diagnostics
                                                    7 G.Geschonke, CERN
                             White paper CSP 09_07_2009
4.2. Participation to CLIC Module

Reference              CEA (FR)              G.Riddone, Franck Peauger (ad interim)
institute
Time span               Start                   End                                                                              DB
                       Nov 2008              Dec 2011
Allocated human               6 man.months         Allocated        249 K€
resources                                          financial
                                                   resources
          Indicative personnel profile               Indicative committment profile
            Engineer Technician Draft man                       K€        KCHF
2008        1                                      2008
2009        1                         0.5          2009         49
2010        1.5                       0.5          2010         200
2011        1.5                                    2011
Total       5                         1            Total        249
                            Milestones and Deliverables
         Date                                     Description
Dec-2008                Kick-off meeting
Mar-2009                WFM design review:                                                                                               MB
Jun-2009                WFM delivery (prototype)
Sep-2009                Complete ACS final design review
Jun-2010                Complete ACS delivery
                                  Detail description
This workpackage covers the design and the procurement of accelerating structures with
wakefield monitors for the CLIC test module.
The 2-m long CLIC module will contain up to 4 PETS feeding each 2 accelerating structures.
The drive beam module will also be equipped with two quadrupoles and the main beam module
with one quadrupole, whose length varies from 0.5 to 2 m. One of the key issues to demonstrate
the CLIC feasibility is the acceleration gradient of the accelerating structures. In this context their
precise alignment has to be studied and developed. One way to release the pre-alignment
tolerances is to use the beam to obtain the information on the accelerating structure position. The
position of the beam can be achieved by using wakefield monitors, which will be directly
integrated in the accelerating structures.
The CLEX testing program foresees the test of power generation (phase 1) and two beam scheme
(phase 2) by using the two-beam test module. Already in this phase 2, as the main beam will be               Wakefield monitor studies
equipped with one to several accelerating structures, it is foreseen to integrate the first wakefield
monitor prototype to an existing testing structure.
The two-beam test module will be then followed by the CLIC test module aiming, as much as
                                                                                                             have started
possible, to reproduce the CLIC module. The main objective of the first phase will be the testing
of the accelerating structure alignment and the validation of the wakefield monitor performance.
For this phase, it is foreseen to build three complete accelerating structures with integrated
wakefield monitor.
                                                                     White paper CSP 09_07_2009 G.Geschonke, CERN                         8
Phase 2 of the two beam test stand:
- review of the WFM design will occurr on 22 July 2009 in the framework of the CLIC
module working group. A progress meeting was already held in April 2009.
The WFM procurement is expected by end of this year (about 20-25kEUR)

Phase 3 of the two beam test stand
- technical specification for the structure production: the technical specification for the
prototype qualification disks has beenn prepared and the call for tender ready to be
launched. Six-seven firms will be contacted. The contract for the prototype will be
adudicated in September 2009 (about 20 kEUR). Considering the time needed for the
prototype phase, the contract for the series (3 structures) will be adjudicated only in the
year 2010.

                             White paper CSP 09_07_2009 G.Geschonke, CERN                     9
Wakefield monitors studies
                                                                                         sigma z = 3mm , off axis beam dy=-1mm
Probes: Transverse
field Ex and Ey

                                                                                            Transverse mode at 22 GHz

                    Transverse E field in damped waveguide with beam sigz=3mm                                      Transverse E field spectrum in damped waveguide with beam
                                          and offset dy=-1mm                                                                       sigz=3mm and offset dy=-1mm

                                                                     Ex at (0;-38)
                100000                                               Ey at (38;0)                              1.E+07
                10000                                                                                          1.E+06
                 1000                                                                                          1.E+05
                                                                         20 dB                                                  25 dB
      E (V/m)

                  100
                                                                                                               1.E+04

                                                                                                    E (V/m )
                   10
                                                                                                               1.E+03
                     1
                                                                                                               1.E+02                                              Ex at (0;-38)
                   0.1                                                                                                                                             Ey at (38;0)
                                                                                                               1.E+01
                  0.01
                                                                                                               1.E+00
                         0     1        2        3            4         5            6
                                                                                                                        10      15          20            25        30             35
                                                     t (ns)
                                                                                                                                                 t (ns)

     Courtesy of Franck Peauger
                                                                  White paper CSP 09_07_2009 G.Geschonke, CERN                                                                      10
Status CLEX (CLIC Experimental Area)

existing building

                            F D   F   D      F   D       F   D        F   D   F    D   F   D   F   D       F   D       DF   DF
                                                                                                                   F
                                                                                                       D
                                                                                               F
                    DFD               DFD                        FD               FD

                                                                                                                                                                     Beam from CR/TL2
                    DF D              DF D                   D F D
                                                         F
                                                     D
                                                 F

                                                                                                                   Test Beam Line TBL

       Two Beam Test Stand                                                                                                                                           Probe Beam

        All Beam lines installed, except TBL and operated with beam !
                           (ITB is not part of the base-line programme)
                                                                                                                                              11 G.Geschonke, CERN
                                                                                                                       White paper CSP 09_07_2009
Test Beam Line TBL
                                                                                 TBL
                                                                                                                                                                                       • High energy-spread beam
                1

                             6m                                                                22.4 m                                                             3.0m      3.0m
                    DUMP            F   D      F      D       F      D       F    D        F           D   F        D     F     D     F       D       F   D
                                                                                                                                                                  DF            DF
                                                                                                                                                              F

                                                                                               1.85m
                                                                                                                                                  D          P
                                                                                                                                                                         TL2’
                                                                                                                                      F                   DUM
         DUMP
                DFD                                 DFD                               FD                       FD
                                                                                                                                                                                   2
                                                                                                                                                                                       transport
                             0.75

                DFD                                                               D F D                                                                                            m
 8m

                                                   D FD                                                    LIL-ACS                  LIL-ACS               LIL-ACS
                                                                 P
                           16.5 m                         D   UM             F                                           22 m
                TBTS                                                                                                                CALIFES Probe beam injector
                                        2.5m

                                                                         D
  2.0m                                                               F
         DUMP
                       16 m
                           ITB
                            Transport path
                                                   1.4m                                                                                                                                   decelerate to 50 % beam energy
                                                                         42.5 m                                                                                                        • Drive Beam stability
                                                                                                                                                                                       • Stability of RF power extraction
                                                                                               PETS prototype
                                                                                                                                                                                         total power in 16 PETS: 2.5 GW
                                                                                                                                                                                       • Alignment procedures

5 MV/m deceleration (35 A)

165 MV output Power                                                                                                                                                                      PETS development: CIEMAT
                                                                                                                                                                                         BPM: IFIC Valencia
   2 standard cells, 16 total                                                                                           White paper CSP 09_07_2009 G.Geschonke, CERN                         and UPC Barcelona        12
4.3 12 GHz RF network for 8 PETS in TBL

Reference              CEA             Steffen Doebert, Igor Syratchev, Franck Peauger
institute                                                                                     There was a review of the CEA proposal for this
Time span             Start                       End
                  October 2008                 March 2009                                     components foreseen for June 2009. This review
Allocated human                5 man.months          Allocated            218 K€
resources                                            financial
                                                     resources                                has not happened yet.
          Indicative personnel profile                  Indicative committment profile
             Engineer Technician Draft man                         K€            KCHF
2008         1                                       2008
2009
2010
             1
             1
                                         2           2009
                                                     2010
                                                                   118
                                                                   100
                                                                                              The status is as follows:
2011                                                 2011
Total        3                           2           Total                                    Franck got drawings for high power loads (Igor
                              Milestones and Deliverables
         Date                                       Description                               style) and directional couplers (SLAC style) which
November 2008            Participation in 12 GHz component review at CERN
June 2009                Review of a proposal by CEA for the realization of the work
                         package
                                                                                              he wanted to modify if needed and discuss with
October 2009             Evaluation of prototypes
October 2009- March      Delivery of all rf components, October 4 loads and 2 directional     companies. Lately he was asked to incorporate an rf
2010                     couplers
                                    Detail description                                        pick up into the load to save the couplers and have
This work-package covers the purchase and delivery of 12 GHz rf components for 8 PETS in      only one item to make.
TBL.
Depending on high power test results, fabrication costs and fabrication delay, a list of RF   He started working on that but there is not a final
components to supply will be established.
The objective is to provide the following components needed for 8 PETS module in TBL.         result yet.
Components needed: 16 RF power loads
                      8 directional couplers
                     16 WR90 waveguide bends 90 deg (H-bend)
All components have to fulfill the high-power and vacuum specification provided by CERN.      Steffen Doebert

                                                                 White paper CSP 09_07_2009 G.Geschonke, CERN                                       13
12 GHz Test-
        Test-Stand
     at CERN

                 KM Schirm BE-RF14
Schedule
ID
                                                           2009                                                                                                                2010
            1st Quarter             2nd Quarter              3rd Quarter                4th Quarter                    1st Quarter                   2nd Quarter                 3rd Quarter                    4th Quarter
     Dec       Jan      Feb   Mar     Apr       May    Jun       Jul     Aug    Sep        Oct      Nov       Dec         Jan      Feb       Mar       Apr       May       Jun      Jul      Aug        Sep        Oct
1       Klystron Supply
                                                                                                                                              G. McMonagle
2                                                                                                         Modulator
                                                                                                                                                                           Saclay,G. McMonagle
3                                            Pulse Compressor (GYCOM)
                                                                                          Karl-Martin Schirm[50%],Igor Syratchev[50%]
4                                                            Low-level RF
                                                                                                                                        J. Mourier,Luca Timeo
5                                                               RF components
                                                                                                                                                     G. Riddone; S. Doebert; K. Schirm,Saclay
6                                                                                                           Controls
                                                                                                                                                                           M. Draper;S.Doebert
7                                                                                                                         Test-Stand
                                                                                                                                                                                    G. Riddone; S. Doebert; K. Schirm
8                                                                                     Infrastructure
                                                                                                                                                        J. Monteiro; K. Schirm,G. McMonagle
9                                                                                                                                                                              System commissioning
                                                                                                                                                                                                                   ??

                                                                                                                                                                    KM Schirm BE-RF                       15
4.4.Construction of a 12 GHz Test Stand: Modulator
Reference     CEA                           G.McMonagle, Franck Peauger
institute
Time span                Start                          End

            October 2008           June 2010
Allocated human        12 man.months                  Allocated          398 K€
resources                                             financial
                                                      resources
          Indicative personnel profile                  Indicative committment profile
             Engineer Technician Draft man                         K€           KCHF
2008         1.2                                      2008
2009         3.6                                      2009         398          639.3
2010         3.6        3.6                           2010
2011                                                  2011
Total        8.4        3.6                           Total
                             Deliverables and Milestones
         Date                                        Description
January 2009            Participation in the klystron design review at SLAC
January 2009            Tender for modulator purchase
March 2009              Choice of the supplier in collaboration with CERN
May 2009-               Modulator production follow-up
April-May 2010          Delivery of the modulator to CERN, installation and high power
                                                                                                         The supplier is chosen and is Scandinova (new technology
                        tests with a SLAC klystron
                                   Detail description                                                    with solid state switchs, short delivery time of 10 months,
This work-package covers the procurement, installation and tests of a modulator for the 12 GHz Test
Stand. This modulator will be integrated in the CTF3 klystron gallery to drive an X-band klystron from   resonable price and synergy with PSI)
SLAC.
The work-package includes the following:
    Ø Call for tenders according to CERN technical specifications
    Ø Industrial follow-up of the purchase                                                               The order has been accepted by head of Irfu. The contract
    Ø Follow-up of the installation and tests at CERN
    Ø Participation in the design study of the interfaces with the Low Level RF system and the SLAC      has been signed by Scandinova without modification last
        klystron
                                                                                                         week and is under signature at CEA Saclay.

                                                                                                         The kick off meeting will be done 1st of July)at Uppsala
                                                                                                         with Scandinova and CEA Saclay.

                                                                          White paper CSP 09_07_2009 G.Geschonke, CERN                                               16
4.5. Construction of a 12 GHz Test Stand: Pulse compressor

Reference
institute
               CEA                            Karl Schirm, Franck Peauger
                                                                                                              ordered from Gycom
Time span            Start                       End
            October 2008               June 2010
Allocated human         12 man.months              Allocated           156 K€
resources                                          financial
                                                   resources
         Indicative personnel profile                Indicative committment profile
            Engineer Technician Draft man                        K€            KCHF
2008        1.2                                    2008
2009        3.6                        3.6         2009          56
2010        3.6                                    2010          100
2011                                               2011
Total       8.4                        3.6         Total
                             Deliverables and Milestones
        Date                                      Description
May 2009                Preliminary Design Review : decision between SLED1, SLED2 and
                        BOC
                        choice of supplier
May 2010                Delivery of the Pulse Compressor to CERN, installation and high
                        power tests with a SLAC klystron

                                         Detail description
This work-package covers the design, fabrication and installation of a 12 GHz Pulse Compressor. This
Pulse Compressor will be integrated in the CTF3 buildings at CERN. Three technical solutions are under
considerations: SLED1, SLED2 or BOC type pulse compressor
For the SLED1 option, an offer has been submitted by a Russian company. In case this solution is retained
CERN would order this product ready to use, and the contribution would be re-allocated in either 4.4. or    The pulse compressor activity at CEA is more or less in
4.6.
For the SLED2 option, the work-package includes the following:                                              standby because of the order of the GYCOM SLED1 pulse
     Ø Design study to produce a full set of fabrication drawings and related technical specifications
     Ø Commercial documentation needed for the call for tender                                              compressor by CERN. We have nevertheless started the RF
     Ø Industrial follow-up of the manufacture of the components: Delay line Ø 90 mm, 42 meters long,
        vacuum pumping ports, ion pumps, baking system                                                      design of a 12GHz BOC. We could continue if needed.
     Ø Participation in the installation of the SLED2 at CERN
For the BOC option, the work-package includes the following:                                                F.Peauger
     Ø Design study to produce a full set of fabrication drawings and related technical specifications
     Ø Commercial documentation needed in the call for tender
     Ø Industrial follow-up of the manufacture of the whole system
     Ø Participation in the installation of the BOC at CERN                                                  possibly reallocate funds later

                                                                                  White paper CSP 09_07_2009 G.Geschonke, CERN                                        17
4.6.Construction of a 12 GHz Test Stand:
                                                      RF network and components
Referenc     CEA                       Igor Syratchev, Franck Peauger
e
institute
Time               Start                 End
span       October 2008          June 2010
Allocated human       1 man.months         Allocated    50 K€
resources                                  financial
                                           resources
       Indicative personnel profile               Indicative
                                             committment profile
           Enginee Technicia Draft                    K   KCHF
           r          n          man                  €
2008                                       2008
2009       1                               2009       50

2010                                              2010
2011                                              2011
Total        1                                    Total                               For the RF network activity, we have finished the RF
                        Deliverables and Milestones
      Date                                   Description                              design of the RF valve . It will replace RF windows to
December 2008            Participation in 12 GHz component review at CERN
                                                                                      divide vacuum sectors in the RF network, in order to
February - June          High-power testing at CERN                                   change quickly the structure under test for example. The
2010
                                                                                      mechanical design is almost done by N. Chritin and we
                              Detail description
                                                                                      have to organize the fabrication.
          This work-package covers review, testing, purchase and high-power
commissioning of RF components. Several options and suppliers are under               We also plan to scale the SLAC mode launchers
evaluation. The share of activities and the commercial part will be decided after a   (rectangular to circular mode conversion). We have asked
decision about the pulse compression system 4.5. in May 2009.
                                                                                      drawings to SLAC recently in order to start the HFSS
                                                                                      calculations. F.Peauger
                                                                                      Layout and RF network under design at CERN

                                                         White paper CSP 09_07_2009 G.Geschonke, CERN                                        18
4.7. Participation à la stabilisation des éléments
                                             optiques: Instrumentation spécifique (dynamique)
Reference            CNRS/ LAPP            Claude Hauviller (CERN) and Andrea Jeremie (LAPP)
institute
Time span               Start                    End

Allocated human
                        2008
                            36 man.months
                                                2011
                                                    Allocated            74 K€
                                                                                                   Qualification du démonstrateur pour la
resources                                           financial
                                                    resources                                      stabilisation du Linac :
         Indicative personnel profile               Indicative committment profile (a
                                                                    reviser)                       - les calculs vibratoires de l'aimant du
            Engineer Technician Draft man                         K€           KCHF
2008        0          0               0            2008          0                                démonstrateur ont ete effectues et le rapport
2009        15                                      2009          32
2010
2011
            15
            6
                                                    2010
                                                    2011
                                                                  32
                                                                  10
                                                                                                   (Milestone 1) est en cours de redaction.
Total       36                                      Total         74
                            Milestones and Deliverables
                                                                                                   - la construction d'un démonstrateur simplifié
        Date                                       Description
4/2009                 Milestone 1 : Calculs vibratoires de l’aimant du démonstrateur              (version LAPP) a commence (usinage d'un pole
                       (rapport)
12/2009                Milestone 2: Construction et qualification d’un démonstrateur               d'aimant en aluminium realise).
                       simplifié (version LAPP) et du(es) prototype(s) de contrôle servant
                       a ce démonstrateur (rapport)
3/2010                 Milestone 3 : Analyses vibratoires de l’ensemble du démonstrateur
                       (rapport)
6/2010                 Milestone 4 : Développement de la méthodologie de contrôle et               Claude Hauviller
                       application au démonstrateur (plusieurs combinaisons)
10/2010                Milestone 5 : Rebouclage des calculs vibratoires avec les mesures
                       sur le démonstrateur (rapport)
3/2011                 Milestone 6 : Evaluation des performances (Rapport)
                                  Detail description

Participer à la réalisation mécanique et à la qualification du démonstrateur pour la
stabilisation du Linac : en particulier, calculs vibratoires avec analyses initiales et bouclage
après mesures.
Développer la méthodologie de contrôle pour stabiliser des structures avec plusieurs degrés de
liberté. Appliquer ces logiciels aux différentes combinaisons de capteurs/actionneurs installées
sur le démonstrateur et en améliorer les performances. Rechercher une solution commerciale ou
développer le système d'acquisition temps réel.

                                                                   White paper CSP 09_07_2009 G.Geschonke, CERN                                     19
4.8. Participation à la stabilisation des éléments
                                                     optiques: Instrumentation spécifique (optique)

Reference           CEA/IRFU           Claude Hauviller (CERN) and Florence Ardellier-
institute                              Desages (IRFU)
Time span              Start
                       2009
                                                 End
                                                 2011
                                                                                              Etude de méthodes de mesure optique
Allocated human                12 man.months         Allocated          50 K€
resources                                            financial                                indépendantes de celle utilisée dans la boucle
                                                     resources
           Indicative personnel profile                Indicative committment profile         d'asservissement avec application au
             Engineer Technician Draft man                        K€           KCHF
2008                                                 2008                                     démonstrateur.
2009         2           2                           2009         30
2010         2           2                           2010         10
2011         2           2                           2011         10
                                                                                              La première étape consiste en la qualification d'un
Total        6           6                           Total        50
                              Milestones and Deliverables                                     banc de mesure.
          Date                                      Description
10/2009                  Résultats des mesures croisées avec interféromètre (rapport)         Le choix d'un interféromètre différentiel est
12/2009                  Intégration du système de mesure interférométrique dans le
                         démonstrateur                                                        actuellement a l'etude: consultation en liaison avec
10/2010                  Mesure des mouvements d’un point sur un pôle de l’aimant
                         (rapport)
3/2011                   Mesure sur n points correspondant aux pôles de l’aimant (rapport)
                                                                                              le CERN des fournisseurs potentiels et
                                    Detail description
Etude de méthodes de mesure optique indépendantes de celle utilisée dans la boucle            comparaison des performances de leur produit.
d’asservissement avec application au démonstrateur.
Première étape : Qualification d’un banc de mesure                                            Des equipements en pret vont etre testes et
      04/2009 à 10/2009 : Acquisition et mise en exploitation d’un interféromètre
      différentiel pour effectuer et qualifier des mesures croisées sur l’équipement
                                                                                              qualifies sur un set-up simplifie.
      (modèle), le support et le sol (mesures faites à Saclay par le SIS).
Deuxième étape : Comparaison des mesures avec les autres moyens (géophones,
accéléromètres…)
      01/2009 à 12/2009 : Ces études comparatives seront menées sur les
                                                                                              Claude Hauviller
      équipements du CERN, par le CERN et avec la participation du SIS en exploitant
      les résultats de la mesure optique.
Troisième étape : Mesures sur maquette (démonstrateur)
      01/2010 à 12/2010 : Les études à mener seront les suivantes :
          • Mesure des mouvements d’un point sur un pôle de l’aimant (10/2010)
          • Définition d’un schéma de principe du système de mesure final
          • Définition des références mécaniques, relatives et absolues
          • Mesure sur n points : 2 x 4 correspondant aux pôles sur la maquette

                                                                 White paper CSP 09_07_2009 G.Geschonke, CERN                                        20
4.9. CLIC positron sources

Reference                          CERN                     Louis Rinolfi (CERN), Alessandro Variola (LAL)
institute
Time span                          Start                                     End
                               1 October 2008                           1 October 2010
Allocated human resources                           24 man.months               Allocated             0 K€
                                                                                financial
                                                                                resources
                      Indicative personnel profile                                Indicative committment profile

                  Engineer            Technician            Draft man                             K     KCHF
                                                                                                  €
2008                      3                     0                   0          2008
2009                      12                    0                   0          2009
2010                      9                     0                   0          2010
2011
Total                     24
                                                                               2011
                                                                               Total
                                                                                                                                The two first deliverables foreseen for May 2009 have
                                           Milestones and Deliverables

May 2009
               Date                                                    Description
                                      Optimization study and detailed characteristics of the hybrid targets and the             been produced. A draft CLIC Note has been written and
                                      corresponding geometry
May 2009                              Provides the Peak Energy Deposition Density (PEDD) for each target and the
                                      heating consequences                                                                      will be published soon.
December 2009                         Detailed beam characteristics at the end of the e+ Pre-Injector Linac (Base Line
                                      configuration)
December 2009                         Compton Scheme: Detailed laser characteristics corresponding to the proposed              Geant 4 simulations have been performed for different
                                      stacking cavity
September 2009                        Compton Scheme: Characteristics of the photons flux with the corresponding
                                      geometry                                                                                  primary beam energies, different target thickness and
November 2009                         Compton Scheme: Detailed characteristics of the e+ target(s)
March 2010                            Compton Scheme: Provides the PEDD and parameters related to thermal effects
                                                                                                                                different distances between crystal and amorphous targets.
March 2010                            Compton Scheme: Simulations optimized showing detailed beam characteristics
                                      of the e+ Pre-Injector Linac (at 200 MeV)
October 2010                          Compton Scheme : study on how to rescale the parameters for CLIC and
                                      needed R&D. : Eventual results of experimental tests at ATF for the optical
                                                                                                                                We are now in position to elaborate and define a best
                                      cavity and the laser
                                                    Detail description                                                          configuration for the CLIC e+ source based on hybrid
The CLIC Injector Complex will provide electrons and positrons.

In the Base Line design, the e+ are unpolarized and are produced by channeling
                                                                                                                                targets.
from hybrid targets (crystal+amorphous). For the production of polarized positrons,
the preferred option is based on the Compton scheme. An alternative option is the                                               It will be a trade off between the primary beam energy
undulator scheme which is studied for ILC as base line.

The design studies for the Base Line configuration will be focused on hybrid targets
                                                                                                                                (cost issue), the e+ yield (performance issue) and the
and the captured and pre-acceleration of e+. The hybrid target is a solution
proposed by LAL, in association with IPNL and BINP-Novosibirsk, where a crystal                                                 power dissipation inside the target (reliability issue).
plays the role of channeling photon source and the produced gammas are converted
subsequently in pairs e+ - e- in an amorphous target. The low energy particles,
responsible for the target heating, are extracted before the amorphous target.

The design studies for the Compton scheme will be focused on the collision scheme,
                                                                                                                                L.Rinolfi
the optical cavity, the laser system, the conversion system and the
capture/acceleration process.

LAL is already engaged in a program of high power lasers and high gain Fabry Perot
cavities. Some first results are expected for the end of 2009-2010. The experimental
test program at ATF is running for 3 years and LAL will continue it in collaboration
with KEK people. CERN will follow the results of the experiments. According to the
results, LAL will propose a parameters rescaling for CLIC.
                                                                     White paper CSP                                     09_07_2009 G.Geschonke, CERN                                      21
You can also read