A review of the performance of the tunnelling for Singapore's circle line project

Page created by David Graves
 
CONTINUE READING
A review of the performance of the tunnelling for Singapore's circle line project
World Tunnel Congress 2008 - Underground Facilities for Better Environment and Safety - India

A review of the performance of the tunnelling for Singapore’s circle line project

N.H Osborne, C. Knight Hassell, L.C. Tan & R. Wong
Land Transport Authority, Singapore

SYNOPSIS: The Circle Line Project (CCLP) is a fully underground orbital mass rapid transit line currently
under construction in Singapore, scheduled to open in 2010. It totals 33 kilometres in length and includes 29
underground stations, running under some of the busiest urban corridors within the city. The majority of the
line, 28.8 kilometres, was constructed using Tunnel Boring machines (TBMs), either earth pressure balance
or slurry. The project presented numerous challenges, not least in the great variability of the ground, with
tunnelling carried out in all the geological strata present in Singapore, ranging from soft Marine Clays,
through tropically weathered rocks, to fresh granite.
Tunnelling is now substantially complete, and the merits of the differing approaches to meeting the
challenges posed by the ground conditions can be reviewed. The risk management of the tunnelling process
and settlement control were critical elements within the project; these are studied in detail with key successes
highlighted and areas for future improvement suggested.

1.   INTRODUCTION                                            acceptable levels. One of the challenges is actually
                                                             identifying that risk. Despite the fact that Singapore
Singapore’s latest addition to its mass rapid                is an island of 700 km2, it contains a wide range of
transport (MRT) system starts in the heart of the            variable and rapidly changing geology, making the
urban city, under its’ famous Orchard Road, with an          ground conditions difficult to predict. It has
interchange station at Dhoby Ghaut allowing                  tropically weathered sedimentary, low grade
transfer to the existing North East and the North            metamorphic and igneous deposits incised by
South lines (Figure 1). The line then commences its          channels of very soft marine clay and fluvial
orbital route to the east passing a through a further        deposits. This geology, combined with the
28 stations, including 4 more interchanges, before           urbanisation of the island, further highlights the
reaching its final interchange station at Harbour            importance of settlement control to the project.
Front in the island’s south. This 33 kilometre route              Tunnel settlement is a major, if not the most
is split into 9 contracts, with 87% of the alignment         important, concern amongst the international
built by TBM.                                                tunnelling community and this is very true in
      Once operational, it will be of major benefit to       Singapore. Over the last ten years there have been
commuters, significantly enhancing integration with          numerous tunnelling projects in Singapore, with the
the existing lines and appreciably reducing                  20km North East Line Project (NELP) for the MRT
commute time by enabling commuters to bypass                 and the 48km Deep Tunnel Sewerage System
city centre interchanges. It brings the MRT system           (DTSS) dominating the scene. These projects and
to a large number of suburban hubs, resulting in a           their problems have been well documented, for
substantial increase in MRT connectivity.                    NELP by, Shirlaw et al. 2003 (1), Osborne et al.
      To achieve this, a large number of engineering         2002 (2) and for DTSS, Marshall et al 2007 (3). The
and logistical challenges had to be overcome, with           papers reinforce the fact that the ground conditions
one of the greatest being controlling the settlement         are very complex and controlling them particularly
induced during the driving of the tunnels and                taxing. On both projects, a number of localised
limiting its impact upon the public. In the planning         sinkholes developed and these were attributed to
stages optimum consideration was given to                    either inappropriate face pressure, problems during
minimising the tunnelling risk, by removing as               launching/docking, or machine problems, however
much as feasibly possible. However, on a project of          common to all was the fact the ground was
such a scale not all risk can be avoided, therefore          problematic.
the remaining risk must be identified and reduced to

                                                       1497
A review of the performance of the tunnelling for Singapore's circle line project
Figure 1. CCLP route map

     In addition to the ground causing settlement       Marine Clay. It also contains interstitial fluvial
problems, there are issues at the other end of the      sands and clays and is encountered within buried
tunnelling spectrum with the very strong and            river channels, generally to the south and southeast
abrasive conditions. Again the papers highlight that    of the island. The Clay can be divided into two
both tunnel advance rates and more importantly          units, the Upper Marine Clay and Lower Marine
machine wear are particular issues of concern.          Clay. These are generally separated by peats, fluvial
                                                        sands and clay, normally a few metres thick, but
                                                        occasionally demonstrating a more complex
2.   GROUND CONDITIONS AND
                                                        interbedded relationship and over much greater
     TUNNELLING CHARACTERISTICS
                                                        thicknesses. The formation is found at the surface
Due to the diverse depositional environments and        and can extend to 40m below ground. It is of low
subsequent geological events the ground conditions      strength, with an undrained shear strength typically
in Singapore are very complex and varied,               of 15 kPa close to the surface, increasing slowly
presenting many challenges in tunnelling through        with depth to maximum of 60 KPa. However, in the
them. For CCLP all five of the geological units that    more recently reclaimed areas the clay is still
exist in Singapore were encountered, to varying         undergoing consolidation and is significantly
degrees. (Figure 2).                                    weaker, in the order of 15KPa at an equivalent
                                                        depth. From a tunnelling perspective, although of
                                                        low strength, it is a good tunnelling medium that
2.1 Kallang formation                                   can be controlled by appropriate face pressure. It is
The Kallang Formation is a Holocene and late            recommended that a range of 0.9-1.2 times the
Pleistocene deposit which is dominated by soft          overburden pressure is used, Shirlaw et al. (1). The

                                                   1498
A review of the performance of the tunnelling for Singapore's circle line project
control of settlement becomes a major issue when         extremely abrasive range, Peart et al. (5) This has
mixed face conditions are encountered, with              resulted in large wear problems in previous projects,
Kallang in the crown and rock in the invert,             most notably the DTSS.
balancing and controlling the earth pressure
becomes very complex particularly if fluvial sand is
                                                         2.3 Jurong formation
present.
                                                         The Jurong Formation makes up much of western
2.2 Old alluvium                                         and south western Singapore, consisting of late
                                                         Jurassic and early Triassic sedimentary strata
The Old Alluvium, predominantly to the east and          comprising mainly interbedded mudtsones,
northwest of Singapore, is an early Pleistocene          siltstones and sandstones. It is a very variable
deposit compromising alluvial clayey sands, sandy        stratum with large strength ranges, from 2 MPa, or
clays and occasional gravels, normally well              less, to those exceeding 150MPa, and a range of
cemented. It generally behaves as a weak rock, but       permeability from 1*10-5 m/s to 1*10-7 m/s,
with a tropically weathered zone extending typically     Osborne et al (2). This variability is a consequence
to 8m. It is a good medium for tunnelling, providing     of its deposition and then subsequent tilting, to
no stability issues for machine tunnelling, but can      create thin, near vertical beds, which have
be more problematic for hand works if the                undergone subsequent folding and faulting. Later,
weathered uncemented material is encountered,            deep tropical weathering preferentially along the
Knight Hassel et al (4). Its abrasiveness is             bedding planes has resulted in fractured rock to
frequently underestimated, with a Cerchar Arasivity      considerable depth. To add further variability, some
Index (CAI) in the range of 0.45 – 2.25 for intact       stratum has undergone low grade metamorphism.
rock. However tests done on broken down samples,         Consequently stability during tunnelling is a major
mirroring the action of a TBM, give much higher          issue, the weaker ground, if not fully supported, has
results with values up 5.0, putting it in the

                                    Figure 2. Geological map of Singapore

                                                   1499
A review of the performance of the tunnelling for Singapore's circle line project
the potential to ravel along the weathering or minor      3.   TUNNELLING APPROACH
fault planes, rapidly progressing to the surface. In
the stronger ground, problems with progress and           For previous tunnelling projects in Singapore,
wear exist, with the quartzite and sandstones falling     notably NELP and DTSS, the EPBM has been used
in the extremely abrasive category. This is further       to drive the tunnels. As the tunnelling industry is
compounded by the steeply dipping beds and by the         continuing to advance, and technological
fact that the strata can change very rapidly from         improvements are made, more options are available
competent ground to very weak, with mixed face            to the tunneller. As a result of a number of sink
conditions not uncommon.                                  holes that occurred during the tunnelling on NELP,
                                                          due to a combination of hard and soft ground being
                                                          encountered, slurry TBMs were seen as a
2.4 Fort canning boulder bed                              potentially better tool to overcome this problem.
                                                          This is evident in the different tunnelling
This is a Pleistocence colluvial deposit comprising
                                                          approaches taken on CCLP, table 1. Of the
strong to very strong sandstone and quartzite
                                                          contracts, only one opted to use slurry TBM
boulders within a very stiff clay matrix. It is derived
                                                          exclusively, with two contracts using both slurry
from the Jurong Formation and is limited to areas
                                                          and EPBM, with the choice of slurry coinciding
within and around the Central Business District in
                                                          with the Bukit Timah Granite. Evidently one of the
Singapore. It does not pose settlement problems to
                                                          driving factors in this choice was to deal with the
tunnelling, but with the boulders having a diameter
                                                          mixed face conditions with the ability to increase
up to 7m and making up 25-30% of the strata, it
                                                          the face pressure instantaneously and control the
poses significant problems in terms of advance and
                                                          mixed face. Choosing a slurry machine does
machine wear. For CCLP this ground was only
                                                          introduce an additional potential complication to the
encountered on one contract and for a limited
                                                          tunnelling process, that of the slurry composition
length.
                                                          and the plant required to produce and deliver the
                                                          slurry to the tunnel face. To fully utilise the benefits
2.5 Bukit Timah granite
                                                          of slurry, the plant must be set up correctly to
The oldest formation in Singapore is the Bukit            enable the appropriate slurry to be produced
Timah Granite, an early to middle Triassic igneous        effectively and efficiently. Otherwise this process
strata found in central and northern areas of             may introduce more problems than it actually
Singapore. It comprises a number of acidic rocks,         solves.
predominantly      granite,    microgranite      and
granodiorite, and is frequently encountered as            4.   TUNNELLING PERFORMANCE
buried ridges beneath the Marine Clay and Old
Alluvium. It has a very wide range of strength, from      With the different approaches taken to dealing with
less than 1MPa to in excess of 300 MPa, with the          the varied ground conditions, a number of recurring
fresh granite causing major wear as it falls into the     issues with regard to the tunnelling performance
extremely abrasive range. This strength range is a        become evident. These can be summarised into
consequence of the severe tropical weathering,            three key and crucial areas. Firstly, the detrimental
creating six weathering grades, from soil to fresh        role of the abrasive ground conditions and the wear
rock, which can occur within a very short distance        to the TBMs, this not only resulted in numerous,
of each other. Consequently the problem of                difficult, and time consuming cutter changes, but
supporting a mixed face exists, particularly in the       also had an impact on the machines’ ability to
intermediate weathering grades where intact rock is       control settlement. Secondly, the interaction with
encountered in the invert and corestones within a         buildings which are known risk areas within any
loose sandy or clayey matrix in the crown. This           project; across CCLP these risks were identified and
situation is further exacerbated by the high              mitigated using a number of different solutions. The
permeabilities in the intermediate weathering             third area is that of settlement control itself. A
grades, increasing the instability by forcing the         number of localised sinkholes and slurry/foam loss
ground to ‘flow’ into the TBM.                            to the surface occurred across the project, and it is
                                                          useful to analyse these to determine their causes in
                                                          attempt to prevent future occurrence.

                                                      1500
A review of the performance of the tunnelling for Singapore's circle line project
4.1 Wear                                                            Granite, Jurong and Old Alluvium are all very
                                                                    abrasive materials as indicated by cerchar testing.
Much of the ground in Singapore is very hard and                    The culprit being the quartz, which resists the
abrasive, consequently tunnel advance rates and                     chemical weathering process to remain intact and
wear are both significant problems. It is evident                   has been altered to include overgrowths making it
from the comparison of estimated and actual                         more angular and therefore abrasive. As the
advance rates, Table 1, that frequently planned rates               machine experiences wear its ability to cut the rock
could not be achieved, this is predominantly due to                 is reduced and it advances more slowly. To further
two factors. Firstly the strength of both the Jurong                compound this, wear leads to more tool changes,
and the Granite which can easily be under                           further slowing progress. For one 1.25 km drive on
estimated, as although the fresh rock may only                      Contract 853, 5 tool changes were planned, but 10
make up a small percentage of the drive, the time                   required, 2 within 25m of each other, with each
taken to tunnel through this rock, in excess of                     change lasting up to two weeks.
250MPa, is proportionally much greater. Secondly
and more importantly is the wear to the TBMs. The

                                      Table 1. TBM usage and performance on CCLP

                     Circle Line Stage 1                Circle Line Stage 2                            Circle Line Stage 3
Contract
                     825             828              823                  822                    852                    853
Contractor         WSN JV        NLC JV              NLC                 EN JV            WH/ SH/ APJV                  Taisei

Type                EPBM         EPBMEPBM         EPBM                                        EPBM              EPBM           Slurry
TBM              Herrenknecht Hitachi Zosen
                                     Hitachi    Mitsubishi                                 Herrenknecht        Kawasaki
                                     Zosen                                                                                   Kawasaki
CCL Drive        PRM-DBG BLV- BLV- MBT- DKT- TSG- PYL- TSG-                                LRC-         SER-     BSH-         MRM-
                         NCH MBT DKT PYL BLY MPS MPS                                       SER          BLY      LRC           BSH

Max Drive        1695.4 (IB) 1073 180.6 539 1005.2 704                    664       795     700     1200         1513          1237
length (m)       1568.4 (OB) (IB) (IB/OB)                                                 (IB/OB) (IB/OB)        (IB)          (OB)

TBMs                  2               2              4                      2                      2               2              2
proposed                                         ( 2 from
(No.)                                             C828)
Geology              Old         Kallang         Kallang           Kallang formation, Old Alluvium             Granite Varying
                  Alluvium,     Formation       Formation           Old Alluvium & & Graniite                  & Old    grades of
                   Jurong                                         Bukit Timah Granite                          Alluvium weathered
                  & FCBB                                                                                                Granite
TBM
Outside             6580             6630            6630                 6600                    6630           6680          6720
dia.(mm)
TBM Length /      7.4 / 47.6    8.6 / 74.6      8.6 / 65.4               8.8 / 88            7.6 / 70.4        9.9 / 64.1 9.9 / 74.1
Back-Up (m)
Planned Daily        4.9        7           4    6          6      6.5     7.5      7.8     6.3          6.3      5.6            4.5
Production (m)
Achieved Ave       2.8 (IB)    5.7        3.7   4.5         6.7    5.5     7.3      6.9     4.9          3.2     4.95        3.6 (OB)
Daily              2.7 (OB)    5.2        2.9   5.5         6.8    5.2     6.7      9.0     4.7          3.2     5.15        3.2 (IB)
Production (m)
Actual/Planned       56%       77%     82.5%    83% 100% 82%              93% 100%         76%          51%      89%             75%
Percentage

                                                                1501
A review of the performance of the tunnelling for Singapore's circle line project
Table 1 (contd.)
                                                  Circle Line Stage 4                              Circle Line Stage 5
Contract
                                    854                                     855                            856
Contractor                         Taisei                                                             Sembawang

Type                           Slurry Shield                  Mixshield               EPBM               EPBM
TBM                             Kawasaki                     Herrenknecht          Herrenknecht       Herrenknecht
Manufacturer
CCL Drive                 BKB-TSN, TSN-MRM                 ONH-BNV-HLV-           ONH-KRG-WCT      PCS-PPJ, PJ-WCT
                          BKB-BTN, BTN-FRR                     FRR                                PCS-TLB, TLB HXO
                                                                                                    HXO-HBF, HBF-
                                                                                                         EVS
Max Drive                          3170                           5800                3000              1100
length (m)
TBMS (No.)                          4                              2                   2                      3
Geology            Mainly Bukit Timah Granite             ONH-HLV:            Predominantly       Jurong formation with
                   (GI – GVI) overlain by fill material   Predominantly       Jurong Formation    overlaying F2, Marine
                                                          Jurong Formation                        Clay, Estuarine and
                                                          HLV-FRR: Mainly                         fill material
                                                          Bukit Timah Granite
                                                          Formation
Outside dia. –                     6720                          6630                6630                 6600
cut (mm)
TBM Length /                     10.1/ 110                      9.6 / 95             8.7 / 74            7.9 / 70
Back-Up Length
(m)
Planned Daily                        5                             7                    7                   6
Production (m)
Achieved Ave                        3.7                           4.3                  3.9                  7
Daily Production
(m)
Actual/Planned                     74%                            61%                 55%                116%
Percentage

     The wear problem is further compounded by                  to cutter discs occurs when tunnelling through
other factors. Firstly the fact that to control the             mixed ground. This is caused when the cutter discs
ground conditions the tunnels often needed to be                move from the soft soil in the face to the very hard
driven with pressures in excess of 2 bar, and this              granite resulting in the discs cracking or in some
force accelerates the wear of the machine and its               cases shattering.
tools. The mixed ground also increases wear,                         The impact of wear on the tunnelling project
particularly the combination of strong ground and               should not be underestimated. In addition to the
clay. The clay combines with the quartz minerals to             above, tool change is a high risk operation. Entering
form a grinding paste which tends to clog up the                the cutterhead either in free or compressed air
machine face and is difficult to remove through the             contributed to several localised sinkholes on DTSS
chamber. This paste rapidly abrades components of               and CCLP. Therefore, the less frequent the need to
the machine with the cutterhead and the discs most              change tools the lower this risk. The use of
susceptible, the discs can easily get clogged                   appropriate conditioning agents, foams and slurry
preventing rotation and resulting in flats spots                rheology can help to reduce this impact and avoid
forming. It is not only the cutterhead that                     wear, but the choice of the most appropriate agent is
experiences wear but all parts of machine that                  a difficult and complex science, particularly for the
encounter the spoil. Across CCLP, significant wear              slurry machines. This choice is made even
of the removal pipes in slurry machines, the                    more difficult by the ever-changing ground
bulkhead and screw was reported. Further damage                 conditions.

                                                           1502
4.2 Settlement control – structures                     house. Precondition and damage assessments of the
                                                        building further highlighted its poor structural
Tunnelling within the urban environment inevitably
                                                        condition, consequently as an additional
leads to interfacing with existing structures, either
                                                        contingency, the house was propped to avoid any
tunnelling under or adjacent to them. Despite efforts
                                                        sudden collapse (Figure 3). During tunnelling face
during the design of the alignment to minimise this
                                                        pressures were maintained in the range of 0.8 -1.0
risk by avoiding existing structures not all can be
                                                        times overburden. To try to reduce the settlement as
avoided. The only benefit is that these risks are
                                                        much as possible, maximising the potential of the
obvious and known early within the project,
                                                        grouting was identified an additional key measure.
therefore they can be mitigated. Across CCLP a
                                                        Body grouting was introduced with a bentonite mix
number of different solutions were implemented to
                                                        injected through the shoulder of the shield to fill the
successfully tunnel past structures.
                                                        overcut void and prevent the ground moving onto
      The alignment for the project in the early
                                                        the shield skin, before the primary grouting at the
planning phase is in the main designed on ridership,
                                                        tailskin could take over. Although volume takes
and the most direct route to link proposed stations.
                                                        were relatively small it was important not to over
It is however beneficial to revisit the alignment
                                                        pump resulting in a temporarily increase of the pore
particularly during the design phases and examine
                                                        pressure within the Marine Clay, leading to larger
whether further adjustments can be made to further
                                                        consolidation settlements later. As the tunnel
reduce the risk. This was the case for Contract 853,
                                                        advanced, primary grouting from four ports, with 2
a contract in the Bukit Timah Granite, with a known
                                                        pipes per port to ensure redundancy, took over.
number of mixed ground interfaces. Modifications,
                                                        Here a grout mix with a gel time of 7 seconds was
both horizontal and vertical were made, reducing
                                                        injected at 120% of theoretical volume. The
the number of residential properties to be tunnelled
                                                        combination of the correctly applied face pressure
under to 57 and taking the tunnel deeper, to 45m
                                                        and the grouting to arrest the movement of the
below ground level, within the limitations of
                                                        ground on to the TBM skin proved successful. The
gradient and station position, therefore reducing the
                                                        maximum settlement recorded on the house was
number of mixed ground interfaces, Nakano et al.
                                                        less than 10mm, with immediate volume loss at 1%,
2007 (6). In addition, the tunnels were separated by
                                                        reducing to 2% after six months due to the effects of
up to 60m, to limit the maximum settlement by only
                                                        consolidation. An identical approach was taken to
having to deal with one settlement trough. These
                                                        tunnelling on the adjacent Contract 828, with a
measures, combined with a strict excavation spoil
                                                        similar TBM and similar ground conditions, this
management system, resulted in settlements in the
                                                        again proved successful to limiting settlements on
order of 10mm, a volume loss of 0.5% and no
                                                        key structures, for more details, Osborne et al 2007
disruption to the property owners.
                                                        (7).
      Full face Marine Clay, although originally
                                                              On Contract 852, by mitigating one risk,
considered one of the most challenging ground
                                                        another smaller and more manageable risk was
conditions in Singapore is now viewed as a
                                                        introduced. For a 245m stretch of the tunnel drive,
preferred ground condition for tunnelling, although
                                                        the distance between the extradoses of the tunnels
this does not hold true for cut and cover
                                                        was reduced to between 4.0 - 2.3m, to avoid
excavations. Due to its uniformity and the
                                                        tunnelling beneath adjacent piled structures. The
techniques available, settlement can be controlled
                                                        ground was granite with varying weathering grades
with appropriate tunnelling. Contract 823 presents a
                                                        from grade II to V, with much of the tunnel
good example, a tunnelling project entirely in the
                                                        alignment through the soil/rock interface,
Kallang Formation, with EPB the choice of
                                                        consequently the control of ground movement was
tunnelling machine. The twin bored tunnel
                                                        difficult and the potential for the second tunnel to
alignment was at 15m below ground and passed
                                                        adversely affect the first very high. The control of
within 7m of a two storey house built in 1940 on
                                                        the spoil and achieving an effective plug through
shallow foundations. This property was in a very
                                                        these interfaces was essential to controlling the
poor condition due to 60 years of consolidation
                                                        ground movement. A number of measures were put
settlement of the Marine Clay. The option to
                                                        in place to manage this situation. The choice of
demolish was not available, therefore tunnelling had
                                                        machine was a Herrenknecht EPB with a double
to be controlled to ensure minimal impact upon the
                                                        screw conveyer configuration to control ground and

                                                    1503
water inflow during spoil removal. The addition of           control the settlement as early as possible. The
the second screw increased the length by 50%                 result was that ground movements were limited to
providing a better pressure gradient along its length.       1% volume loss and the tunnel movement of the
This, combined with independent rotation speeds of           adjacent tunnel was less than 5mm. The largest
the augers and effective use of soil conditioning,           movement induced on the constructed tunnel lining
enabled the formation of a solid plug and controlled         was as a result of a cutter tool intervention in free
the discharge of spoil through these difficult               air 3 metres away from the lining, demonstrating
interfaces. As an additional contingency, passive            great control over this risk.
support to the first tunnel was installed, combining              One of the most challenging risks on the CCLP
with permanent glass fibre dowels through                    occurred on Contract 856. Tunnelling for a length
the lining into the soil pillar between the tunnels          of 90m twin bore, 16m below two rows of occupied
(Figure 4).                                                  40 year old shop houses, which were in a poor
     Again grouting into the annulus between the             condition and founded on shallow footings. The
TBM shield and the ground was carried out to

                        Figure 3. Building in poor state of repair to be tunnelled and machine

                Figure 4. C852 Passive support with the tunnels & fibreglass dowels through the lining

                                                       1504
ground consisted of mixed face of Kallang and              increasing available options of the soil conditioning,
Jurong Formations, with a high proportion of the           replacing the centre double cutters with ripper tools
Kallang comprising fluvial sand (Figure 5). The            to reduce plugging and improvements to the
first tunnel passed to the side of the shop houses and     primary grouting making it more efficient. A
although there were some relatively large                  geotechnical engineer was permanently present on
settlements these were limited to the road and had         the TBM during excavation, monitoring the ground
minimal impact on the shop houses. The second              conditions and checking excavated muck volumes.
tunnel was directly under the shop houses,                 The shop houses themselves were monitored every
consequently a much larger risk. Ground treatment          3 hours and a series of passive props were installed
to the fluvial sands was considered but not regarded       as an additional contingency. The whole process
as a viable option as it had the potential to cause        was overseen by a special task force who reviewed
large settlement during the drilling. A number of          and approved the tunnelling parameters that were
other measures were employed to ensure that the            presented in a tunnel look ahead report, prior to
shop houses were not impacted. The EPBM was                commencement. The tunnelling was a success; the
enhanced to include a minimum face pressure                settlements were controlled and although some
alarm, the capability to inject bentonite directly into    minor cracking occurred to the shop houses this was
the face during stoppages, doubling the capacity and       non structural.

                                              Shop houses – 90m

                     Figure 5. Constantly changing ground beneath shop houses on Contract 856

                                                      1505
Not every high risk solution required specific     above the complex ground conditions, can be
measures to control the settlement. For Contract 825     identified as contributory causes for these events.
the ground compromised of three different                      Although preferable to a sinkhole, discharge of
formations over 500m, the Old Alluvium, the Fort         conditioning agent to the surface is a problem as it
Canning Boulder Bed and the Jurong Formation.            is a hazard to the public, particularly the road user.
Two major risks to tunnelling were identified;           This happened on a number of occasions across
tunnelling through two piles for an underground car      more than one contract. On each occasion one of
park link which could not be avoided and extended        three factors was involved. With the slurry
below tunnel crown level; and tunnelling 4m below        machines blockages occurred as the weathered
an existing live MRT tunnel. For both cases the          Jurong broke down to a sticky clay, blocking the
ground condition was very good and this was              suction entry gate area, whilst fresh slurry was
established and verified by extensive soil               delivered to the excavation chamber. This resulted
investigation. For the piles, within the Old             in pressure spikes occurring before the operator
Alluvium, the option was taken to cut the piles          could react and forcing slurry to the surface,
using hand excavation from the machine face and          Shirlaw et al (8). Further problems were
support them on specifically designed tunnel             encountered when air leaked through the TBMs
segments as the tunnel continued its drive. This was     submerged wall into the excavation chamber
achieved with no discernible settlement to the car       reaching the air cushion in the plenum chamber,
park link. Tunnelling under the MRT tunnel was           causing air spikes and slurry discharge at the
again carried out in very competent ground, Fort         surface. On other occasions slurry managed to find
Canning Boulder Bed. As the tunnel approached            a path to the surface through either through left in,
settlements were monitored both at the surface and       or poorly backfiled, sheet piles, or poorly backfilled
the level of the MRT to verify that settlements were     site investigation boreholes. The third factor can be
small. The twin tunnels passed beneath the MRT,          attributed to the sensitivity of face pressure
with a high level of instrumentation, and a              calculations. When tunnelling through particularly
maximum recorded settlement of 3mm.                      difficult ground there is little room for error in these
                                                         calculations and it is preferable to err on the side of
                                                         caution. Consequently a small variation in the input
4.3 Ground settlements
                                                         parameters, be it a localised reduction in pore water
The ground conditions in Singapore make the              pressure or a reduction in ground level for a storm
control of settlement very challenging, in particular    drain, can result in the face pressure calculation
the mixed face conditions which occur all too            being too high and slurry or foam can force its way
frequently. They are very difficult to identify with     to the surface.
traditional site investigation as the ground can               Large settlements or sinkholes also occurred
change from very competent to mixed face over a          across a number of the contracts, these were limited
meter. Even with boreholes spaced at 25m apart,          to the road or side table, and on no occasion was
only 0.5% of the ground to be tunnelled through is       any individual injured, nor property damaged. All
sampled, therefore it is not surprising that not every   these incidents occurred in the known problematic
mixed ground interface is identified. Tunnelling         ground conditions, either the mixed face conditions
close to or under structures is an obvious and           in the granite, the weathered Jurong or mixed face
identifiable risk and measures can be put in place to    of Jurong and Kallang Formations. It is interesting
mitigate this risk. However with much of the tunnel      to note that this ground risk was not always fully
alignments actually avoiding structures and              identified by the site investigation and its
following roads the likelihood of coming across          subsequent interpretation. Consequently the wrong
difficult ground unexpectedly is high. Both NELP         face pressure was applied. As the tunnel advances
and DTSS experienced this problem with sinkholes         whilst excavating the harder ground in the invert the
appearing at the surface, 20 recorded for NELP,          soft or loose ground in the crown is not properly
Shirlaw et al.(1) and more than 5 on DTSS,               controlled. This results at worst large over
Marshall et al (3). CCLP experienced a similar           excavation, or at best small but significant over
problem with sinkholes but at the other extreme an       excavation per ring. On all projects spoil excavation
additional problem with slurry/foam discharge at         control was being practised, but with the varying
the surface. A number of common factors, over and        ground conditions this is not easy. If the wrong

                                                     1506
ground is identified, the wrong bulking factor is        ground treatment carried out to mitigate this risk
then applied; this can result in a difference between    when it was warranted.
actual and theoretical volumes and any over                    Linked to the tool change problem is the
excavation is not identified. The difference between     recurring theme of machine wear. This was a
Jurong and a fluvial sand can be in excess of 5m3        contributory factor in several sinkholes. As various
per ring, which quickly becomes significant over         components of the machine wear, the ability to
several rings and can result in a large settlement. In   control settlements is impacted in one of two ways.
the granite, there is an even larger range in dry soil   Firstly advance slows taking a longer time to
volumes excavated per ring, these can vary by as         excavate through a difficult ground interface and
much as 17m3 or 40% per advance, across the              increasing the possibility of over excavation. Also,
varying weathering grades, Nakano et al (6). It is       particular to EPBM, the ability to control the face
therefore very important that even if the changing       can be compromised when components such as the
ground is not identified in the soil investigation, a    screw are worn compromising the machines ability
constant review of the excavated material should be      to exert the required face pressure.
undertaken and bulking factors revised by
experienced personnel on a very regular basis. In
                                                         5.   CONCLUSION
the case of the slurry machines it would seem
sensible to introduce various points in the system       As with all the biggest engineering challenges the
where the amount of material excavated can be            first issue is to understand the ground and its
reconciled. For example the amount of material           geotechnical model, as this allows the potential
excavated at the face needs to be monitored              risks to be realised. The ground in Singapore is a
immediately at the TBM and then as it flows              particular challenge to tunnelling with the mixed
through the slurry processing plant and finally if       interfaces of the granite, Jurong or these grounds
practical the plant should treat each TBM separately     combined with the Kallang, and the frequency with
so that the resulting muck from each TBM can be          which they occur. The next issue is to identify
identified in the respective muck pit.                   where these interfaces exist, so that particular
     There appear three other broad categories           attention can be paid to dealing with them. Given
which contributed to more than one sinkhole. The         the variability of the ground and the site
first category can be defined as man made                investigation this is a very demanding task. It is
obstructions. On two occasions during tunnelling         suggested that more attention needs to be paid to the
sheet piles, not shown on any drawings were              site investigation in both the location of the
encountered, once directly in the face and once at       boreholes and exploring alternative options,
crown level. This allowed a passage to the surface       inclined boreholes, seismic studies, for example.
to develop quickly, pulling ground into the              The interpretation of the site investigation should
excavation chamber during excavation, resulting in       always be carried out by an experienced geologist.
localised settlement at the ground surface. A similar          Once the risk has been identified there are
occurrence occurred on another occasion with a           many tunnelling options available to mitigating it,
poorly backfilled borehole the culprit.                  this has been demonstrated on CCLP by the
     As already identified tool changes are a high       successful tunnelling in proximity to numerous
risk operation, these contributed to the sinkholes.      structures. From the tunnelling experience on CCLP
Ideally changes should always be carried out in          there are several areas that have resulted in
good ground, but with the combined problems of           problems. In the variable ground the management of
identifying the good ground and the high rate of         the spoil is important if over excavation occurs this
wear this is not always possible. Consequently on        must be identified as early as possible to enable
one occasion during a long tool change small             reaction and to prevent the development of any
volumes of material were lost into the chamber. As       sinkhole. The importance of planning ahead and
the change lasted a period of weeks this volume          having contingencies, such as ground treatment in
accumulated sufficiently that upon tunnel restart a      place to minimise the impact of any over excavation
sinkhole developed. On the whole tool changes            is also crucial. The ground is very abrasive and
were carried out successfully; they were carefully       wear is a recurring problem. It slows progress,
planned with additional site investigation to identify   impacts the ability of the machine to function to its
the risk and on a number of occasions specific           full potential and results in the high risk operation

                                                     1507
of tool change. Consequently the wear must be kept           2.   Osborne N.H., Williams O.I. and Lim W.B. (2001)
to a minimum and the use of effective conditioning                The Jurong Formation, a Variable Ground Condition
agents and slurry should be practised, even if this               – its’ Tunnelling characteristics. Underground
                                                                  Singapore 2001.
costs more initially, there should be long term
benefits.                                                    3.   Marshall R.H., Flanagan R.F., Singapore’s Deep
      Tunnelling in Singapore is continually                      Tunnel Sewerage System – Experiences and
evolving and lessons are being learnt from past                   Challenges. RETC 2007.
projects. On the NELP 25% of all sinkholes                   4.   Knight Hassell C. K., Rosser H.B., Eng W. C.,
occurred during launching or docking, for CCLP                    Difficult ground conditions Encountered during
this risk was clearly identified and through ground               Construction of a Cross Passage. Underground
treatment eradicated. The problematic ground                      Singapore 2001.
conditions are known, but when encountered
                                                             5.   Peart M., Poh J., Kho C. M., A revised Interpretation
unexpectedly sometimes difficult to deal with. On                 of Old Alluvium Formation based on Ground
CCLP both EPBM and slurry machines were                           investigations for Changi Airport Line. Underground
utilised to try to control settlements generally with             Singapore 2001.
great success, but with occasional sinkholes. The
                                                             6.   Nakano A., Sahabdeen M. M., Kulaindran A., Seah
introduction of the slurry machines has resulted in a
                                                                  T. P., Excavation Management for Slurry TBMs
new learning curve, with new problems due to the                  Tunnelling under Residental Houses at C853.
additional level of sophistication these machines                 Underground Singapore 2007.
bring, to utilise them to their potential they need to
be operated properly by people who understand                7.   Osborne N. H. Lim W. B. The Realignment of Nicoll
                                                                  Highway Tunnels, A risk Management Approach.
them.
                                                                  Underground Singapore 2007.
      Despite the numerous challenges, tunnelling
for CCLP can be regarded as a success. The key               8.   Shirlaw J. N., Hulme T. W., Risk Mitigation for
risks were identified and mitigated by employing a                Slurry TBMs Tunnels and Tunnelling April 2008.
number of different techniques. More lessons for
                                                             BIOGRAPHICAL DETAILS OF THE AUTHOR
the future have been learnt, leaving the tunnelling
industry in Singapore in a stronger position to face                          Nick Osborne graduated with a degree
the upcoming challenges for the new Down Town                                 in Geology and followed it with an
MRT project, which is just about to commence.                                 MSc in Engineering Geology at
                                                                              Imperial College, London. He has
REFERENCES                                                                    worked on a number of tunnelling jobs
                                                                              in the UK, including the Channel
1.   Shirlaw, J.N., Ong, J.C.W., Rosser, H.B., Tan, C.G.,                     tunnel and the Jubilee Line extension.
     Osborne, N.H., Heslop, P.E, 2001.               Local                    In Singapore he has worked on the
     Settlements and Sinkholes due to EPB Tunnelling.                         North east line and Circle line projects
     Proceedings of the Institution of Civil Engineers Vol   and currently works on the new down town line.
     156 Issue GE4 pp193- 211.

                                                         1508
You can also read