A review of the performance of the tunnelling for Singapore's circle line project
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
World Tunnel Congress 2008 - Underground Facilities for Better Environment and Safety - India A review of the performance of the tunnelling for Singapore’s circle line project N.H Osborne, C. Knight Hassell, L.C. Tan & R. Wong Land Transport Authority, Singapore SYNOPSIS: The Circle Line Project (CCLP) is a fully underground orbital mass rapid transit line currently under construction in Singapore, scheduled to open in 2010. It totals 33 kilometres in length and includes 29 underground stations, running under some of the busiest urban corridors within the city. The majority of the line, 28.8 kilometres, was constructed using Tunnel Boring machines (TBMs), either earth pressure balance or slurry. The project presented numerous challenges, not least in the great variability of the ground, with tunnelling carried out in all the geological strata present in Singapore, ranging from soft Marine Clays, through tropically weathered rocks, to fresh granite. Tunnelling is now substantially complete, and the merits of the differing approaches to meeting the challenges posed by the ground conditions can be reviewed. The risk management of the tunnelling process and settlement control were critical elements within the project; these are studied in detail with key successes highlighted and areas for future improvement suggested. 1. INTRODUCTION acceptable levels. One of the challenges is actually identifying that risk. Despite the fact that Singapore Singapore’s latest addition to its mass rapid is an island of 700 km2, it contains a wide range of transport (MRT) system starts in the heart of the variable and rapidly changing geology, making the urban city, under its’ famous Orchard Road, with an ground conditions difficult to predict. It has interchange station at Dhoby Ghaut allowing tropically weathered sedimentary, low grade transfer to the existing North East and the North metamorphic and igneous deposits incised by South lines (Figure 1). The line then commences its channels of very soft marine clay and fluvial orbital route to the east passing a through a further deposits. This geology, combined with the 28 stations, including 4 more interchanges, before urbanisation of the island, further highlights the reaching its final interchange station at Harbour importance of settlement control to the project. Front in the island’s south. This 33 kilometre route Tunnel settlement is a major, if not the most is split into 9 contracts, with 87% of the alignment important, concern amongst the international built by TBM. tunnelling community and this is very true in Once operational, it will be of major benefit to Singapore. Over the last ten years there have been commuters, significantly enhancing integration with numerous tunnelling projects in Singapore, with the the existing lines and appreciably reducing 20km North East Line Project (NELP) for the MRT commute time by enabling commuters to bypass and the 48km Deep Tunnel Sewerage System city centre interchanges. It brings the MRT system (DTSS) dominating the scene. These projects and to a large number of suburban hubs, resulting in a their problems have been well documented, for substantial increase in MRT connectivity. NELP by, Shirlaw et al. 2003 (1), Osborne et al. To achieve this, a large number of engineering 2002 (2) and for DTSS, Marshall et al 2007 (3). The and logistical challenges had to be overcome, with papers reinforce the fact that the ground conditions one of the greatest being controlling the settlement are very complex and controlling them particularly induced during the driving of the tunnels and taxing. On both projects, a number of localised limiting its impact upon the public. In the planning sinkholes developed and these were attributed to stages optimum consideration was given to either inappropriate face pressure, problems during minimising the tunnelling risk, by removing as launching/docking, or machine problems, however much as feasibly possible. However, on a project of common to all was the fact the ground was such a scale not all risk can be avoided, therefore problematic. the remaining risk must be identified and reduced to 1497
Figure 1. CCLP route map In addition to the ground causing settlement Marine Clay. It also contains interstitial fluvial problems, there are issues at the other end of the sands and clays and is encountered within buried tunnelling spectrum with the very strong and river channels, generally to the south and southeast abrasive conditions. Again the papers highlight that of the island. The Clay can be divided into two both tunnel advance rates and more importantly units, the Upper Marine Clay and Lower Marine machine wear are particular issues of concern. Clay. These are generally separated by peats, fluvial sands and clay, normally a few metres thick, but occasionally demonstrating a more complex 2. GROUND CONDITIONS AND interbedded relationship and over much greater TUNNELLING CHARACTERISTICS thicknesses. The formation is found at the surface Due to the diverse depositional environments and and can extend to 40m below ground. It is of low subsequent geological events the ground conditions strength, with an undrained shear strength typically in Singapore are very complex and varied, of 15 kPa close to the surface, increasing slowly presenting many challenges in tunnelling through with depth to maximum of 60 KPa. However, in the them. For CCLP all five of the geological units that more recently reclaimed areas the clay is still exist in Singapore were encountered, to varying undergoing consolidation and is significantly degrees. (Figure 2). weaker, in the order of 15KPa at an equivalent depth. From a tunnelling perspective, although of low strength, it is a good tunnelling medium that 2.1 Kallang formation can be controlled by appropriate face pressure. It is The Kallang Formation is a Holocene and late recommended that a range of 0.9-1.2 times the Pleistocene deposit which is dominated by soft overburden pressure is used, Shirlaw et al. (1). The 1498
control of settlement becomes a major issue when extremely abrasive range, Peart et al. (5) This has mixed face conditions are encountered, with resulted in large wear problems in previous projects, Kallang in the crown and rock in the invert, most notably the DTSS. balancing and controlling the earth pressure becomes very complex particularly if fluvial sand is 2.3 Jurong formation present. The Jurong Formation makes up much of western 2.2 Old alluvium and south western Singapore, consisting of late Jurassic and early Triassic sedimentary strata The Old Alluvium, predominantly to the east and comprising mainly interbedded mudtsones, northwest of Singapore, is an early Pleistocene siltstones and sandstones. It is a very variable deposit compromising alluvial clayey sands, sandy stratum with large strength ranges, from 2 MPa, or clays and occasional gravels, normally well less, to those exceeding 150MPa, and a range of cemented. It generally behaves as a weak rock, but permeability from 1*10-5 m/s to 1*10-7 m/s, with a tropically weathered zone extending typically Osborne et al (2). This variability is a consequence to 8m. It is a good medium for tunnelling, providing of its deposition and then subsequent tilting, to no stability issues for machine tunnelling, but can create thin, near vertical beds, which have be more problematic for hand works if the undergone subsequent folding and faulting. Later, weathered uncemented material is encountered, deep tropical weathering preferentially along the Knight Hassel et al (4). Its abrasiveness is bedding planes has resulted in fractured rock to frequently underestimated, with a Cerchar Arasivity considerable depth. To add further variability, some Index (CAI) in the range of 0.45 – 2.25 for intact stratum has undergone low grade metamorphism. rock. However tests done on broken down samples, Consequently stability during tunnelling is a major mirroring the action of a TBM, give much higher issue, the weaker ground, if not fully supported, has results with values up 5.0, putting it in the Figure 2. Geological map of Singapore 1499
the potential to ravel along the weathering or minor 3. TUNNELLING APPROACH fault planes, rapidly progressing to the surface. In the stronger ground, problems with progress and For previous tunnelling projects in Singapore, wear exist, with the quartzite and sandstones falling notably NELP and DTSS, the EPBM has been used in the extremely abrasive category. This is further to drive the tunnels. As the tunnelling industry is compounded by the steeply dipping beds and by the continuing to advance, and technological fact that the strata can change very rapidly from improvements are made, more options are available competent ground to very weak, with mixed face to the tunneller. As a result of a number of sink conditions not uncommon. holes that occurred during the tunnelling on NELP, due to a combination of hard and soft ground being encountered, slurry TBMs were seen as a 2.4 Fort canning boulder bed potentially better tool to overcome this problem. This is evident in the different tunnelling This is a Pleistocence colluvial deposit comprising approaches taken on CCLP, table 1. Of the strong to very strong sandstone and quartzite contracts, only one opted to use slurry TBM boulders within a very stiff clay matrix. It is derived exclusively, with two contracts using both slurry from the Jurong Formation and is limited to areas and EPBM, with the choice of slurry coinciding within and around the Central Business District in with the Bukit Timah Granite. Evidently one of the Singapore. It does not pose settlement problems to driving factors in this choice was to deal with the tunnelling, but with the boulders having a diameter mixed face conditions with the ability to increase up to 7m and making up 25-30% of the strata, it the face pressure instantaneously and control the poses significant problems in terms of advance and mixed face. Choosing a slurry machine does machine wear. For CCLP this ground was only introduce an additional potential complication to the encountered on one contract and for a limited tunnelling process, that of the slurry composition length. and the plant required to produce and deliver the slurry to the tunnel face. To fully utilise the benefits 2.5 Bukit Timah granite of slurry, the plant must be set up correctly to The oldest formation in Singapore is the Bukit enable the appropriate slurry to be produced Timah Granite, an early to middle Triassic igneous effectively and efficiently. Otherwise this process strata found in central and northern areas of may introduce more problems than it actually Singapore. It comprises a number of acidic rocks, solves. predominantly granite, microgranite and granodiorite, and is frequently encountered as 4. TUNNELLING PERFORMANCE buried ridges beneath the Marine Clay and Old Alluvium. It has a very wide range of strength, from With the different approaches taken to dealing with less than 1MPa to in excess of 300 MPa, with the the varied ground conditions, a number of recurring fresh granite causing major wear as it falls into the issues with regard to the tunnelling performance extremely abrasive range. This strength range is a become evident. These can be summarised into consequence of the severe tropical weathering, three key and crucial areas. Firstly, the detrimental creating six weathering grades, from soil to fresh role of the abrasive ground conditions and the wear rock, which can occur within a very short distance to the TBMs, this not only resulted in numerous, of each other. Consequently the problem of difficult, and time consuming cutter changes, but supporting a mixed face exists, particularly in the also had an impact on the machines’ ability to intermediate weathering grades where intact rock is control settlement. Secondly, the interaction with encountered in the invert and corestones within a buildings which are known risk areas within any loose sandy or clayey matrix in the crown. This project; across CCLP these risks were identified and situation is further exacerbated by the high mitigated using a number of different solutions. The permeabilities in the intermediate weathering third area is that of settlement control itself. A grades, increasing the instability by forcing the number of localised sinkholes and slurry/foam loss ground to ‘flow’ into the TBM. to the surface occurred across the project, and it is useful to analyse these to determine their causes in attempt to prevent future occurrence. 1500
4.1 Wear Granite, Jurong and Old Alluvium are all very abrasive materials as indicated by cerchar testing. Much of the ground in Singapore is very hard and The culprit being the quartz, which resists the abrasive, consequently tunnel advance rates and chemical weathering process to remain intact and wear are both significant problems. It is evident has been altered to include overgrowths making it from the comparison of estimated and actual more angular and therefore abrasive. As the advance rates, Table 1, that frequently planned rates machine experiences wear its ability to cut the rock could not be achieved, this is predominantly due to is reduced and it advances more slowly. To further two factors. Firstly the strength of both the Jurong compound this, wear leads to more tool changes, and the Granite which can easily be under further slowing progress. For one 1.25 km drive on estimated, as although the fresh rock may only Contract 853, 5 tool changes were planned, but 10 make up a small percentage of the drive, the time required, 2 within 25m of each other, with each taken to tunnel through this rock, in excess of change lasting up to two weeks. 250MPa, is proportionally much greater. Secondly and more importantly is the wear to the TBMs. The Table 1. TBM usage and performance on CCLP Circle Line Stage 1 Circle Line Stage 2 Circle Line Stage 3 Contract 825 828 823 822 852 853 Contractor WSN JV NLC JV NLC EN JV WH/ SH/ APJV Taisei Type EPBM EPBMEPBM EPBM EPBM EPBM Slurry TBM Herrenknecht Hitachi Zosen Hitachi Mitsubishi Herrenknecht Kawasaki Zosen Kawasaki CCL Drive PRM-DBG BLV- BLV- MBT- DKT- TSG- PYL- TSG- LRC- SER- BSH- MRM- NCH MBT DKT PYL BLY MPS MPS SER BLY LRC BSH Max Drive 1695.4 (IB) 1073 180.6 539 1005.2 704 664 795 700 1200 1513 1237 length (m) 1568.4 (OB) (IB) (IB/OB) (IB/OB) (IB/OB) (IB) (OB) TBMs 2 2 4 2 2 2 2 proposed ( 2 from (No.) C828) Geology Old Kallang Kallang Kallang formation, Old Alluvium Granite Varying Alluvium, Formation Formation Old Alluvium & & Graniite & Old grades of Jurong Bukit Timah Granite Alluvium weathered & FCBB Granite TBM Outside 6580 6630 6630 6600 6630 6680 6720 dia.(mm) TBM Length / 7.4 / 47.6 8.6 / 74.6 8.6 / 65.4 8.8 / 88 7.6 / 70.4 9.9 / 64.1 9.9 / 74.1 Back-Up (m) Planned Daily 4.9 7 4 6 6 6.5 7.5 7.8 6.3 6.3 5.6 4.5 Production (m) Achieved Ave 2.8 (IB) 5.7 3.7 4.5 6.7 5.5 7.3 6.9 4.9 3.2 4.95 3.6 (OB) Daily 2.7 (OB) 5.2 2.9 5.5 6.8 5.2 6.7 9.0 4.7 3.2 5.15 3.2 (IB) Production (m) Actual/Planned 56% 77% 82.5% 83% 100% 82% 93% 100% 76% 51% 89% 75% Percentage 1501
Table 1 (contd.) Circle Line Stage 4 Circle Line Stage 5 Contract 854 855 856 Contractor Taisei Sembawang Type Slurry Shield Mixshield EPBM EPBM TBM Kawasaki Herrenknecht Herrenknecht Herrenknecht Manufacturer CCL Drive BKB-TSN, TSN-MRM ONH-BNV-HLV- ONH-KRG-WCT PCS-PPJ, PJ-WCT BKB-BTN, BTN-FRR FRR PCS-TLB, TLB HXO HXO-HBF, HBF- EVS Max Drive 3170 5800 3000 1100 length (m) TBMS (No.) 4 2 2 3 Geology Mainly Bukit Timah Granite ONH-HLV: Predominantly Jurong formation with (GI – GVI) overlain by fill material Predominantly Jurong Formation overlaying F2, Marine Jurong Formation Clay, Estuarine and HLV-FRR: Mainly fill material Bukit Timah Granite Formation Outside dia. – 6720 6630 6630 6600 cut (mm) TBM Length / 10.1/ 110 9.6 / 95 8.7 / 74 7.9 / 70 Back-Up Length (m) Planned Daily 5 7 7 6 Production (m) Achieved Ave 3.7 4.3 3.9 7 Daily Production (m) Actual/Planned 74% 61% 55% 116% Percentage The wear problem is further compounded by to cutter discs occurs when tunnelling through other factors. Firstly the fact that to control the mixed ground. This is caused when the cutter discs ground conditions the tunnels often needed to be move from the soft soil in the face to the very hard driven with pressures in excess of 2 bar, and this granite resulting in the discs cracking or in some force accelerates the wear of the machine and its cases shattering. tools. The mixed ground also increases wear, The impact of wear on the tunnelling project particularly the combination of strong ground and should not be underestimated. In addition to the clay. The clay combines with the quartz minerals to above, tool change is a high risk operation. Entering form a grinding paste which tends to clog up the the cutterhead either in free or compressed air machine face and is difficult to remove through the contributed to several localised sinkholes on DTSS chamber. This paste rapidly abrades components of and CCLP. Therefore, the less frequent the need to the machine with the cutterhead and the discs most change tools the lower this risk. The use of susceptible, the discs can easily get clogged appropriate conditioning agents, foams and slurry preventing rotation and resulting in flats spots rheology can help to reduce this impact and avoid forming. It is not only the cutterhead that wear, but the choice of the most appropriate agent is experiences wear but all parts of machine that a difficult and complex science, particularly for the encounter the spoil. Across CCLP, significant wear slurry machines. This choice is made even of the removal pipes in slurry machines, the more difficult by the ever-changing ground bulkhead and screw was reported. Further damage conditions. 1502
4.2 Settlement control – structures house. Precondition and damage assessments of the building further highlighted its poor structural Tunnelling within the urban environment inevitably condition, consequently as an additional leads to interfacing with existing structures, either contingency, the house was propped to avoid any tunnelling under or adjacent to them. Despite efforts sudden collapse (Figure 3). During tunnelling face during the design of the alignment to minimise this pressures were maintained in the range of 0.8 -1.0 risk by avoiding existing structures not all can be times overburden. To try to reduce the settlement as avoided. The only benefit is that these risks are much as possible, maximising the potential of the obvious and known early within the project, grouting was identified an additional key measure. therefore they can be mitigated. Across CCLP a Body grouting was introduced with a bentonite mix number of different solutions were implemented to injected through the shoulder of the shield to fill the successfully tunnel past structures. overcut void and prevent the ground moving onto The alignment for the project in the early the shield skin, before the primary grouting at the planning phase is in the main designed on ridership, tailskin could take over. Although volume takes and the most direct route to link proposed stations. were relatively small it was important not to over It is however beneficial to revisit the alignment pump resulting in a temporarily increase of the pore particularly during the design phases and examine pressure within the Marine Clay, leading to larger whether further adjustments can be made to further consolidation settlements later. As the tunnel reduce the risk. This was the case for Contract 853, advanced, primary grouting from four ports, with 2 a contract in the Bukit Timah Granite, with a known pipes per port to ensure redundancy, took over. number of mixed ground interfaces. Modifications, Here a grout mix with a gel time of 7 seconds was both horizontal and vertical were made, reducing injected at 120% of theoretical volume. The the number of residential properties to be tunnelled combination of the correctly applied face pressure under to 57 and taking the tunnel deeper, to 45m and the grouting to arrest the movement of the below ground level, within the limitations of ground on to the TBM skin proved successful. The gradient and station position, therefore reducing the maximum settlement recorded on the house was number of mixed ground interfaces, Nakano et al. less than 10mm, with immediate volume loss at 1%, 2007 (6). In addition, the tunnels were separated by reducing to 2% after six months due to the effects of up to 60m, to limit the maximum settlement by only consolidation. An identical approach was taken to having to deal with one settlement trough. These tunnelling on the adjacent Contract 828, with a measures, combined with a strict excavation spoil similar TBM and similar ground conditions, this management system, resulted in settlements in the again proved successful to limiting settlements on order of 10mm, a volume loss of 0.5% and no key structures, for more details, Osborne et al 2007 disruption to the property owners. (7). Full face Marine Clay, although originally On Contract 852, by mitigating one risk, considered one of the most challenging ground another smaller and more manageable risk was conditions in Singapore is now viewed as a introduced. For a 245m stretch of the tunnel drive, preferred ground condition for tunnelling, although the distance between the extradoses of the tunnels this does not hold true for cut and cover was reduced to between 4.0 - 2.3m, to avoid excavations. Due to its uniformity and the tunnelling beneath adjacent piled structures. The techniques available, settlement can be controlled ground was granite with varying weathering grades with appropriate tunnelling. Contract 823 presents a from grade II to V, with much of the tunnel good example, a tunnelling project entirely in the alignment through the soil/rock interface, Kallang Formation, with EPB the choice of consequently the control of ground movement was tunnelling machine. The twin bored tunnel difficult and the potential for the second tunnel to alignment was at 15m below ground and passed adversely affect the first very high. The control of within 7m of a two storey house built in 1940 on the spoil and achieving an effective plug through shallow foundations. This property was in a very these interfaces was essential to controlling the poor condition due to 60 years of consolidation ground movement. A number of measures were put settlement of the Marine Clay. The option to in place to manage this situation. The choice of demolish was not available, therefore tunnelling had machine was a Herrenknecht EPB with a double to be controlled to ensure minimal impact upon the screw conveyer configuration to control ground and 1503
water inflow during spoil removal. The addition of control the settlement as early as possible. The the second screw increased the length by 50% result was that ground movements were limited to providing a better pressure gradient along its length. 1% volume loss and the tunnel movement of the This, combined with independent rotation speeds of adjacent tunnel was less than 5mm. The largest the augers and effective use of soil conditioning, movement induced on the constructed tunnel lining enabled the formation of a solid plug and controlled was as a result of a cutter tool intervention in free the discharge of spoil through these difficult air 3 metres away from the lining, demonstrating interfaces. As an additional contingency, passive great control over this risk. support to the first tunnel was installed, combining One of the most challenging risks on the CCLP with permanent glass fibre dowels through occurred on Contract 856. Tunnelling for a length the lining into the soil pillar between the tunnels of 90m twin bore, 16m below two rows of occupied (Figure 4). 40 year old shop houses, which were in a poor Again grouting into the annulus between the condition and founded on shallow footings. The TBM shield and the ground was carried out to Figure 3. Building in poor state of repair to be tunnelled and machine Figure 4. C852 Passive support with the tunnels & fibreglass dowels through the lining 1504
ground consisted of mixed face of Kallang and increasing available options of the soil conditioning, Jurong Formations, with a high proportion of the replacing the centre double cutters with ripper tools Kallang comprising fluvial sand (Figure 5). The to reduce plugging and improvements to the first tunnel passed to the side of the shop houses and primary grouting making it more efficient. A although there were some relatively large geotechnical engineer was permanently present on settlements these were limited to the road and had the TBM during excavation, monitoring the ground minimal impact on the shop houses. The second conditions and checking excavated muck volumes. tunnel was directly under the shop houses, The shop houses themselves were monitored every consequently a much larger risk. Ground treatment 3 hours and a series of passive props were installed to the fluvial sands was considered but not regarded as an additional contingency. The whole process as a viable option as it had the potential to cause was overseen by a special task force who reviewed large settlement during the drilling. A number of and approved the tunnelling parameters that were other measures were employed to ensure that the presented in a tunnel look ahead report, prior to shop houses were not impacted. The EPBM was commencement. The tunnelling was a success; the enhanced to include a minimum face pressure settlements were controlled and although some alarm, the capability to inject bentonite directly into minor cracking occurred to the shop houses this was the face during stoppages, doubling the capacity and non structural. Shop houses – 90m Figure 5. Constantly changing ground beneath shop houses on Contract 856 1505
Not every high risk solution required specific above the complex ground conditions, can be measures to control the settlement. For Contract 825 identified as contributory causes for these events. the ground compromised of three different Although preferable to a sinkhole, discharge of formations over 500m, the Old Alluvium, the Fort conditioning agent to the surface is a problem as it Canning Boulder Bed and the Jurong Formation. is a hazard to the public, particularly the road user. Two major risks to tunnelling were identified; This happened on a number of occasions across tunnelling through two piles for an underground car more than one contract. On each occasion one of park link which could not be avoided and extended three factors was involved. With the slurry below tunnel crown level; and tunnelling 4m below machines blockages occurred as the weathered an existing live MRT tunnel. For both cases the Jurong broke down to a sticky clay, blocking the ground condition was very good and this was suction entry gate area, whilst fresh slurry was established and verified by extensive soil delivered to the excavation chamber. This resulted investigation. For the piles, within the Old in pressure spikes occurring before the operator Alluvium, the option was taken to cut the piles could react and forcing slurry to the surface, using hand excavation from the machine face and Shirlaw et al (8). Further problems were support them on specifically designed tunnel encountered when air leaked through the TBMs segments as the tunnel continued its drive. This was submerged wall into the excavation chamber achieved with no discernible settlement to the car reaching the air cushion in the plenum chamber, park link. Tunnelling under the MRT tunnel was causing air spikes and slurry discharge at the again carried out in very competent ground, Fort surface. On other occasions slurry managed to find Canning Boulder Bed. As the tunnel approached a path to the surface through either through left in, settlements were monitored both at the surface and or poorly backfiled, sheet piles, or poorly backfilled the level of the MRT to verify that settlements were site investigation boreholes. The third factor can be small. The twin tunnels passed beneath the MRT, attributed to the sensitivity of face pressure with a high level of instrumentation, and a calculations. When tunnelling through particularly maximum recorded settlement of 3mm. difficult ground there is little room for error in these calculations and it is preferable to err on the side of caution. Consequently a small variation in the input 4.3 Ground settlements parameters, be it a localised reduction in pore water The ground conditions in Singapore make the pressure or a reduction in ground level for a storm control of settlement very challenging, in particular drain, can result in the face pressure calculation the mixed face conditions which occur all too being too high and slurry or foam can force its way frequently. They are very difficult to identify with to the surface. traditional site investigation as the ground can Large settlements or sinkholes also occurred change from very competent to mixed face over a across a number of the contracts, these were limited meter. Even with boreholes spaced at 25m apart, to the road or side table, and on no occasion was only 0.5% of the ground to be tunnelled through is any individual injured, nor property damaged. All sampled, therefore it is not surprising that not every these incidents occurred in the known problematic mixed ground interface is identified. Tunnelling ground conditions, either the mixed face conditions close to or under structures is an obvious and in the granite, the weathered Jurong or mixed face identifiable risk and measures can be put in place to of Jurong and Kallang Formations. It is interesting mitigate this risk. However with much of the tunnel to note that this ground risk was not always fully alignments actually avoiding structures and identified by the site investigation and its following roads the likelihood of coming across subsequent interpretation. Consequently the wrong difficult ground unexpectedly is high. Both NELP face pressure was applied. As the tunnel advances and DTSS experienced this problem with sinkholes whilst excavating the harder ground in the invert the appearing at the surface, 20 recorded for NELP, soft or loose ground in the crown is not properly Shirlaw et al.(1) and more than 5 on DTSS, controlled. This results at worst large over Marshall et al (3). CCLP experienced a similar excavation, or at best small but significant over problem with sinkholes but at the other extreme an excavation per ring. On all projects spoil excavation additional problem with slurry/foam discharge at control was being practised, but with the varying the surface. A number of common factors, over and ground conditions this is not easy. If the wrong 1506
ground is identified, the wrong bulking factor is ground treatment carried out to mitigate this risk then applied; this can result in a difference between when it was warranted. actual and theoretical volumes and any over Linked to the tool change problem is the excavation is not identified. The difference between recurring theme of machine wear. This was a Jurong and a fluvial sand can be in excess of 5m3 contributory factor in several sinkholes. As various per ring, which quickly becomes significant over components of the machine wear, the ability to several rings and can result in a large settlement. In control settlements is impacted in one of two ways. the granite, there is an even larger range in dry soil Firstly advance slows taking a longer time to volumes excavated per ring, these can vary by as excavate through a difficult ground interface and much as 17m3 or 40% per advance, across the increasing the possibility of over excavation. Also, varying weathering grades, Nakano et al (6). It is particular to EPBM, the ability to control the face therefore very important that even if the changing can be compromised when components such as the ground is not identified in the soil investigation, a screw are worn compromising the machines ability constant review of the excavated material should be to exert the required face pressure. undertaken and bulking factors revised by experienced personnel on a very regular basis. In 5. CONCLUSION the case of the slurry machines it would seem sensible to introduce various points in the system As with all the biggest engineering challenges the where the amount of material excavated can be first issue is to understand the ground and its reconciled. For example the amount of material geotechnical model, as this allows the potential excavated at the face needs to be monitored risks to be realised. The ground in Singapore is a immediately at the TBM and then as it flows particular challenge to tunnelling with the mixed through the slurry processing plant and finally if interfaces of the granite, Jurong or these grounds practical the plant should treat each TBM separately combined with the Kallang, and the frequency with so that the resulting muck from each TBM can be which they occur. The next issue is to identify identified in the respective muck pit. where these interfaces exist, so that particular There appear three other broad categories attention can be paid to dealing with them. Given which contributed to more than one sinkhole. The the variability of the ground and the site first category can be defined as man made investigation this is a very demanding task. It is obstructions. On two occasions during tunnelling suggested that more attention needs to be paid to the sheet piles, not shown on any drawings were site investigation in both the location of the encountered, once directly in the face and once at boreholes and exploring alternative options, crown level. This allowed a passage to the surface inclined boreholes, seismic studies, for example. to develop quickly, pulling ground into the The interpretation of the site investigation should excavation chamber during excavation, resulting in always be carried out by an experienced geologist. localised settlement at the ground surface. A similar Once the risk has been identified there are occurrence occurred on another occasion with a many tunnelling options available to mitigating it, poorly backfilled borehole the culprit. this has been demonstrated on CCLP by the As already identified tool changes are a high successful tunnelling in proximity to numerous risk operation, these contributed to the sinkholes. structures. From the tunnelling experience on CCLP Ideally changes should always be carried out in there are several areas that have resulted in good ground, but with the combined problems of problems. In the variable ground the management of identifying the good ground and the high rate of the spoil is important if over excavation occurs this wear this is not always possible. Consequently on must be identified as early as possible to enable one occasion during a long tool change small reaction and to prevent the development of any volumes of material were lost into the chamber. As sinkhole. The importance of planning ahead and the change lasted a period of weeks this volume having contingencies, such as ground treatment in accumulated sufficiently that upon tunnel restart a place to minimise the impact of any over excavation sinkhole developed. On the whole tool changes is also crucial. The ground is very abrasive and were carried out successfully; they were carefully wear is a recurring problem. It slows progress, planned with additional site investigation to identify impacts the ability of the machine to function to its the risk and on a number of occasions specific full potential and results in the high risk operation 1507
of tool change. Consequently the wear must be kept 2. Osborne N.H., Williams O.I. and Lim W.B. (2001) to a minimum and the use of effective conditioning The Jurong Formation, a Variable Ground Condition agents and slurry should be practised, even if this – its’ Tunnelling characteristics. Underground Singapore 2001. costs more initially, there should be long term benefits. 3. Marshall R.H., Flanagan R.F., Singapore’s Deep Tunnelling in Singapore is continually Tunnel Sewerage System – Experiences and evolving and lessons are being learnt from past Challenges. RETC 2007. projects. On the NELP 25% of all sinkholes 4. Knight Hassell C. K., Rosser H.B., Eng W. C., occurred during launching or docking, for CCLP Difficult ground conditions Encountered during this risk was clearly identified and through ground Construction of a Cross Passage. Underground treatment eradicated. The problematic ground Singapore 2001. conditions are known, but when encountered 5. Peart M., Poh J., Kho C. M., A revised Interpretation unexpectedly sometimes difficult to deal with. On of Old Alluvium Formation based on Ground CCLP both EPBM and slurry machines were investigations for Changi Airport Line. Underground utilised to try to control settlements generally with Singapore 2001. great success, but with occasional sinkholes. The 6. Nakano A., Sahabdeen M. M., Kulaindran A., Seah introduction of the slurry machines has resulted in a T. P., Excavation Management for Slurry TBMs new learning curve, with new problems due to the Tunnelling under Residental Houses at C853. additional level of sophistication these machines Underground Singapore 2007. bring, to utilise them to their potential they need to be operated properly by people who understand 7. Osborne N. H. Lim W. B. The Realignment of Nicoll Highway Tunnels, A risk Management Approach. them. Underground Singapore 2007. Despite the numerous challenges, tunnelling for CCLP can be regarded as a success. The key 8. Shirlaw J. N., Hulme T. W., Risk Mitigation for risks were identified and mitigated by employing a Slurry TBMs Tunnels and Tunnelling April 2008. number of different techniques. More lessons for BIOGRAPHICAL DETAILS OF THE AUTHOR the future have been learnt, leaving the tunnelling industry in Singapore in a stronger position to face Nick Osborne graduated with a degree the upcoming challenges for the new Down Town in Geology and followed it with an MRT project, which is just about to commence. MSc in Engineering Geology at Imperial College, London. He has REFERENCES worked on a number of tunnelling jobs in the UK, including the Channel 1. Shirlaw, J.N., Ong, J.C.W., Rosser, H.B., Tan, C.G., tunnel and the Jubilee Line extension. Osborne, N.H., Heslop, P.E, 2001. Local In Singapore he has worked on the Settlements and Sinkholes due to EPB Tunnelling. North east line and Circle line projects Proceedings of the Institution of Civil Engineers Vol and currently works on the new down town line. 156 Issue GE4 pp193- 211. 1508
You can also read