WELLFIELD MANAGEMENT SYSTEM (WFMS) FOR THE SALDANHA BAY AREA
←
→
Page content transcription
If your browser does not render page correctly, please read the page content below
Annex 1 - Terms of reference Wellfield Management System (WfMS) for the Saldanha Bay area Background The Strategic Water Sector Cooperation (SSC) between Denmark and South Africa is a long-term bilateral cooperation, which amongst others are contributing to the South African water sector by demonstrating and testing different Danish groundwater mapping and assessment methodologies in South Africa in order to add long-term value to the South African work on optimizing the utilization of groundwater. Saldanha Bay Local Municipality (SBLM) is augmenting the bulk water supply from the Berg River systems with three groundwater well fields (Langebaan Road, Langebaan Road extension and Hopefield). The three wellfields are in the primary aquifer (Langebaan Road aquifer) and the last two are newly developed. The surface water (rivers and dams) in the area is also supplying other cities in Western Cape, most notably Cape Town. Adding new water sources to Saldanha Bay will therefore support water supply in the area as a whole. The Koningsvlei area is one of two additional wellfields to be developed, with a possibility of a seawater desalination plant and MAR scheme in the near future to be added into the water mix. See Appendix 1 for further details of present activities. The purpose of this project is to develop a wellfield management system (WfMS), that can secure water supply for SBLM in a sustainable way (quantity and quality of the drinking water, protection of vulnerable zones, no impact on groundwater dependent ecosystems, prepared for future water demands from competing water users, such as Cape Town, at optimal economical effectiveness etc.). Parallel to this, a regional geological model and a flow model of the area shall be made on basis of approaches of the mentioned Danish groundwater mapping. The primary purpose of the models is to give input data to the WfMS. It should be noted, that in a later stage (phase C - not part of this project), it is planned to implement and test the WfMS model. Based on the results of testing, the WfMS may be revised. It is also planned to develop the geological model and flow model into local and well field models. See section on Timeline below. The project therefore consist of two parallel phases (phase A and B), described in detail below. In both phases, there is a strong focus on capacity building: Capacity building After completion of the project, the system and the models shall be handed over to SBLM for further use and management. Therefore, capacity building forms an essential part of the project. Concretely we talk at capacitating between 5 and 10 people, expected to be managers and technicians from SBLM, West Coast District Municipality and the South African Department of Water and Sanitation (DWS). Deliverables - Successful capacity building.
- A documentation report (5-10 pages) of the capacity building process, which can be used to assist in similar processes in other South African municipalities. Note with regard to the offer, that: 1. The offer must include a proposal for the capacity building in practice. As an example, it can consist of a combination of on-the-ground and online training and knowledge exchange, and also using a combination of the different project consultants, so that e.g. consultants from outside South Africa is supported by eventual South African consultants. 2. The proposal must account for a certain flexibility for changes, identified during the project period or due to the fact that any plans during the covid-19 pandemic might have to be changed. Phase A – Development of a Wellfield Management System (WfMS) A Wellfield Management System developed in cooperation with – and to meet the needs of – SBLM. The SBLM has a wish for the system to be able to support day-to-day operations of the wellfields in connection to other water sources, which is mainly river water at the moment. The system must also be flexible and prepared for future expansions in water sources (e.g. MAR, desalination), supply infrastructure and future identifications of management needs. In addition, the system shall also be able to handle seasonal fluctuations and to provide input for long-term sustainable water management, within the framework of the All Towns Reconciliation Strategies of the area (see https://filkassen.statens-it.dk/u/sivr7Myr66WgK-vn/Saldanha%202021?l). Further needs and purposes may be identified at the beginning of the project. The system shall be based on current and known future supply demand patterns, infrastructure design constraints and mapping of existing and potential water sources and their importance in the water mix. Data from the wellfield monitoring shall feed into the system, together with day-to-day monitoring data of the surface water and other sources. Data are typically provided in an excel format. It is important to take into account that there is some freedom in the design of the system, as SBLM have no other existing systems that the new system must interact with directly. Provision need to be made to include future modules, e.g. on new wellfield, MAR and desalination. Data from the system shall feed into regional and national databases. Finally, it should be noted, that SBLM is in the process of assigning a consultant to do regular (monthly, quarterly and biannual) groundwater level and quality monitoring and reporting on the wellfields, groundwater flow mapping, delineation of protection zones and the identification of a new MAR area. This consultant is expected to be in place in May and will cooperate with this project. Deliverables - A Wellfield Management System, including license and software support for a minimum of two years. - A manual to manage the WfMS and to update it with new info, after completion of the project. - A framework for capturing future data from the geological and flow models (phase B) - A documentation report (5-10 pages) of the development process for use in similar development in other South African municipalities.
Note with regard to the offer, that: 1. Eventual programme licenses and system support fees for the first two years shall be part of the offered fixed price. 2. The aim of the project is to develop a robust system at minimum maintenance costs and maximum flexibility in use. Therefore, in the offer eventual license and support costs after the first two years and constraints on having other consultants using and developing the system after the end of the project period shall be described, as this will form part of the evaluation of the offer. Phase B – Geological model and flow model Phase B consists of two sequential and overlapping activities: A geological model and a flow model. The approximate model area is 2676 km2 and shown in figure 1 by the yellow polygon. Figure 1: The proposed modeling area (yellow polygon), with the Langebaan Rd wellfield and its extension in red, the Hopefield wellfield in purple and the proposed Koningsvlei wellfield in blue. Only shown boreholes and dug wells with relatively good monitoring data.
Figure 2: A close-up view of the wellfields. The primary purpose of the models is to provide data input to the WfMS. The geological model (when fully developed it is expected to consist of a conceptual geological model, a spatial geological digital model and a hydrostratigraphical model) and the flow model shall be developed using existing data such as borehole data, geophysical data, and existing geological and hydrological models as well as the newly gathered SkyTEM data, that will be made available by SBLM. Digitalization of relevant analogue data shall be expected as part of the project. The geological model shall be done using the software GeoScene3D. Both models shall be handed over to SBLM after the project period in a format, so other consultants can use it, eventually with use of other types of software. Nicolette Vermaak of the University of Free State has worked in the area for many years. Her work is part of her Ph.D., and she has been kind to make her thesis and other relevant data available to the project – see Appendix 2 and this link: https://filkassen.statens-it.dk/u/sivr7Myr66WgK-vn/Saldanha%202021?l If there are any questions to the material, Nicolette can be contacted at nokkie.vermaak@gmail.com and phone: +27-874478787. Deliverables - A regional 3D geological model, made with the software GeoScene3D - A regional 3D flow model - Technical reports on both models
- Written inputs to the development of a South African Groundwater Mapping and Assessment Approach (SAGMAA) - developed in a parallel project. The consultant to do this is expected to be in place in April, and first draft version of the SAGMAA is planned ultimo August. Note with regard to the offer, that: 1. Due to project period constraints, it may be necessary to simplify one or both models, calling for prioritization. In the offer shall be included a proposal for how to optimize the model development within the limited project period and still get a functional model, that can provide inputs to the WfMS, as this will form part of the evaluation of the offer. Budget The maximum cap for the assignment is 800.000 DKK inclusive of reimbursements, and per diem. Payment is in two rates, the first after completion of activity B.1 and the final after completion of the project. If preferred, additional rates can be agreed upon, in which case the rates will be based on progress documentation (short progress report and documentation of spending of time (person-hours), per diem and reimbursements). Note with regard to the offer, that: 1. It will be weighed positively that the offered price is as low as possible (see Advertisement conditions). 2. The total proposed price for the assignment should include phase A+B, including capacity building. 3. The proposed budget shall be detailed to a level, so that the background for the total price can be understood. 4. The offer must include planned person-hours for each of the proposed participants for each of the different activities/tasks. This will give insights to how the work is planned. 5. The budget for phase A should include a minimum of two years of license and support for the system.
Timeline The overall duration of the project is 8 months (May-Dec 2021). In the chart, the tentative further activities (outside of this tender) is indicated – lighter blue and italics. Activity Project period (May-Dec 2021) Tentative further activities (months from initiation) - Not part of the project M J J A S O N D 1 2 3 4 5 6 7 8 9 10 11 Capacity building A.1 Development of a Phase A Wellfield Management System (WfMS) B.1 Geological Model Phase B B.2 Flow Model C.1 Rolling-out of the Phase C (not included in project) WfMS, including supple- menting monitoring net- work C.2 Testing of the WfMS in practice C.3 Alteration of WfMS based on the testing C.4 Local and wellfield models Organizational setup There will be a steering committee (SC) with representatives from Danish Environmental Protection Agency (EPA), the South African Department of Water and Sanitation (DWS) and the SBLM. Based on inputs from the offer there will be an initial meeting with the SC to decide on details in activities, including capacity building, purpose of the WfMS and models, and the timeline. A reference group (RG) of South African stakeholders (e.g. from consultants and universities) to give inputs to the projects and ensure coordination with parallel activities. It will be the responsibility of the consultant to arrange SC and RG meetings.
Qualifications of the consultants The consultant or consultants group is from a consultant company or consultant companies with a combined deep understanding and expertise from developing wellfield management systems and geological models and flow models. One company acts as main contractor, and the other consultant or consultants acts as subcontractors. The following qualifications and previous experiences should be met from the consultant or consultant group: Experience and Knowledge: o Ideally, have 15+ years of in depth relevant experience. o Knowledge of international best practice in groundwater models and water supply management systems. o Experience with setting up water supply management systems. o Experience with the Danish groundwater mapping approach and the software GeoScene3D. Qualifications and Skills: o Be fluent in English (writing and speaking) o Formal qualifications in the appropriate fields, natural resource management, civil engineering or hydrogeology. o Strong communication skills and ability to follow through and cooperate on a distance – especially during a pandemic, where physical presence of non-South Africans in South Africa may be difficult. As a service for preparing the offer, a short list of South African consultants that have worked in the Saldanha Bay area is included in Appendix 3. Note for the sake of good order, that the use of the mentioned consultants or other South African personnel in itself are not a mandatory requirement in the project, as long as the qualifications are met by one consultant or the consultant group.
Appendix 1. Background – new investigations Saldanha Bay area Saldanha Bay Municipality is at the moment augmenting the bulk water supply from the Berg River systems with three groundwater well fields (Langebaan Road, Langebaan Road extension and Hopefield). The three wellfields are in the primary aquifer (Langebaan Road aquifer) and the last two are newly developed. The Koningsvlei area is identified as one of two additional wellfields to be developed with a possibility of a seawater desalination plant in the near future. The Council for Scientific and Industrial Research (CSIR), University of Western Cape (UWC) and DWS is in the final stages of a Water Research Commission (WRC) project that investigated aquifer development and recharge. It also investigated the potential for implementation of a managed aquifer recharge (MAR) for additional water storage and the best suitable MAR method to be used. The project also focuses on the development of a management plan for Langebaan Road Aquifer system considering the implementation of MAR. A large airborne geophysics survey was conducted May-June 2020. Danish company SkyTEM did the survey. A research project (MARSA), has recently been started, which aims at developing MAR technologies that allow for a broader span of water resources to be used for MAR, including storm water, river water, saline water, and treated wastewater. This project is a collaboration between various South African and Danish partners from Universities and public and private institutions and it is coordinated by Danish Geological Survey (GEUS). It will include development of new monitoring strategies for the technologies and an assessment of the water saving achieved by implementing MAR on a larger scale in SA with focus on the West Coast District Municipality of which SBLM is a part. This research project will also focus on a field location where Berg River water will be used for MAR. The study will also determine at what concentration levels saline water can be used directly for MAR or where a pre-treatment is required as salinity varies along the river. Feasibility studies will be carried out as flow through columns to investigate the capacity of SA aquifer sediments to remove N-species, organic pollutants and potential pathogens present in the Berg river. Two postdocs will be hired, one in Denmark and one in South Africa working closely together on both the feasibility and field studies.
Appendix 2 – Overview of existing data The table shows an initial overview of availability and formats of relevant data for the area. Abbreviations/description of Data bases: NGA: National Groundwater Archives. – Geosite information (borehole, dug well, spring, etc.) Hydstra: Monitoring data - groundwater levels, surface water flow, etc. WMS: Water Management System – Water quality (surface and groundwater) WARMS: Water Authorization Registration Management System – Water use registration information Data Description Available Format Boreholes/wells The position and elevation Yes Excel of existing boreholes/wells Information exists for about spreadsheet; (x, y, z coordinates). 2000 boreholes on the NGA NGA; reports Lithological information Yes Excel from the boreholes/wells. There are about 800 boreholes spreadsheet; with fairly reliable lithological NGA; reports logs, with about 120 that have stratigraphic information giving the formation The location of the well Yes Excel screen – depth and length Approximately 800 of the spreadsheet; of the screen. boreholes will have greater NGA; reports details on borehole construction; older boreholes that were recorded during hydrocensus work and private boreholes often does not have this level of information The hydraulic head Yes Excel measurements from the Water level readings (hydraulic spreadsheet; boreholes/wells. head measurements) have been NGA; Hydstra; done fairly regularly for reports approximately 200 boreholes and dug wells in the area Borehole logs, for example Yes flow logs Geophysics may be available at a number of boreholes. Digital elevation A digital terrain model Yes model (DEM) (grid) Water chemistry Results from analysis of the Yes Excel groundwater chemistry. Data is available for a number spreadsheet; of boreholes. 25 made up the WMS; reports regular official water quality monitoring the last couple of years. Geologic Digital maps that can Yes information provide information on the
geologic units in the study Need to contact Council of area. For example, a map Geoscience (CGS) showing the location of the dolerite dykes/sills. Literature on the Reports Yes* Some reports are area’s geology Articles available digitally PhD Thesis (GH Reports); others still only in hard copy. A number of reports are written in Afrikaans. Geophysical Existing geophysical Yes surveys surveys performed in the SkyTEM data from SBLM. area (e.g. resistivity Historical data form reports in measurements, seismic hard copy; raw data may not be mapping) available Rivers A shape file/tab file Yes showing the location of the rivers Hydraulic head Yes. Hydstra measurements Discharge measurements Yes Excel For some of the rivers. Number spreadsheet, of stations along Berg River; Hydstra some stations closed Will request most recent data from DWS Bellville Information on whether Yes there are rivers that dry Quite a number of non- out during the summer perennial rivers in the study period . area, where the whole river or part of the river dries up. River cross sections ? Climatic data Time distributed Yes precipitation for last 5-10 Fairly complete data set up to years, on daily basis 2012; more recent data from South African Weather Services Time distributed Potential Yes evaporation for last 5-10 Information not freely available, years, on daily basis but can be sourced. Data from Department of Agriculture in the Western Cape Groundwater An identification of which Yes WARMS data abstraction wells groundwater is base extracted from. The total amount of water Yes WARMS data extracted from the wells base
per year. Here, it would be nice to have the yearly amount of water extraction shown over a specific time period. The maximum permitted Yes WARMS data water extraction per year base (if available). Transmissivity Information on the Yes Excel transmissivity of the spreadsheet; geological units derived NGA; reports from pumping tests/aquifer tests. Maps showing zones where Need to contact CGS to the geologic units are more determine availability fractured than in other locations Information on the Yes Excel transmissivity of the spreadsheet; geological units derived NGA; reports from blow test Other hydraulic Methods for determination Yes Excel tests in fractured of water transport in spreadsheet; rocks fractures for example from NGA; reports single-hole hydraulic injection tests Potentiometric A potentiometric surface Yes Old reports surface maps map showing the level of the water table. Land use Land use Theme as basis Yes Western Cape for calculation of Farm Mapper; evaporation reports *A number of reports was provided in the Filkassen: https://filkassen.statens-it.dk/u/sivr7Myr66WgK- vn/Saldanha%202021?l.: - Geotechnical reports from the DWS regarding the exploration in the area (GH-reports: GH3224, GH3370; GH3371; GH3372; GH3373; GH3374; and GH3375) with attachments (maps, etc.) for two of them. - Report 23-11-1-17 is a WRC report in which one of the case studies is on the study area. - Rep9-Vol6-GW Langebaan Aquifer is a water resource assessment that was done for DWS in 2008. - Ph.D. thesis Nicolette Vermaak
Appendix 3 - List of some South African consultants that have worked in the Saldanha Bay area Name: Organisation: Email: Julian Conrad GEOSS jconrad@geoss.co.za Helen Seyler Delta H helen@delta-h.co.za Kornelius Riemann Umvoto Africa kornelius@umvoto.com Regan Rose Jeffers & Green Africa roser@jgafrika.com Sumaya Israel University of Western Cape sisrael@uwc.ac.za Des Visser SRK DVisser@srk.co.za